Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More Mobile Las Vegas Presented to Las Vegas Convention and Visitors Authority Presented by Susan Martinovich

Transcript of Tropicana Avenue To Blue Diamond Road I-15 South Design-Build Project Paving the Way to a More...

Tropicana Avenue To Blue Diamond Road

I-15 South Design-Build

Project

Paving the Way to a More Mobile Las Vegas

Presented to

Las Vegas Convention and Visitors Authority

Presented by

Susan Martinovich

Improvements to I-15 from Tropicana Ave. to South of Blue Diamond Rd., including:

Widening I-15

Addition of Collector Distributor roads

Improved ramps at interchanges Tropicana Avenue Russell Road I-215 Blue Diamond Road Silverado Ranch Blvd

What is the I-15 South Design-Build

Project?

Improvements to I-15 from Tropicana Ave. to south of Blue Diamond Rd., including:

New bridges over I-15 at Warm Springs Road

and Sunset Road

Landscaping and Aesthetics

Intelligent Transportation System Ramp Meters Variable Message Signs Cameras

What is the I-15 South Design-Build

Project?

I-15 South Design-Build Project

Blue Diamond Rd.

Silverado Ranch Blvd.

Russell Rd.

215

Tropicana Ave.

• Design-Build Lump Sum Contact

$246,500,000

• Prelim. Engr. (includes procurement)

$16,000,000• Construction Engineering

$17,000,000

• Incentives, Escalations, and Utilities

$6,000,000

Project Costs

• Notice to Proceed – September 2009

• Design substantially completed – Fall

2010

• Construction began – December 2009

• All I-15 Lanes completed and open -

March 2012

• Project Completion – Spring 2012

Schedule

• Design - 95% complete

• Construction - 48 % complete

Project Status

Budget/Cash

Flow

• Currently 300+/- working on design and construction

• Peak employment estimated at 400+/-

Employment

• Southbound I-15 auxiliary lane and 2-lane off ramp to Silverado Ranch Road - Open

• Northbound I-15 Auxiliary lane from Silverado Ranch - Open

• Sunset Bridge - Under Construction• I-15/I-215 interchange - Under Construction• C-D Roads and bridges - Under Construction• Russell Road (widening) - Under Construction

Construction to Date

Upcoming

Milestones• Sunset Bridge • Open January 13

• Warm Springs Bridge• To be demolished Feb 2011• To re-open as 6-lane bridge

Spring 2012

• I-15/ I-215 Construction• To be complete Feb 2012

• Russell Road Widening• To be complete Aug 2011