Transportation winston

86
Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc. 1 Transportation, Assignment and Transshipment Problems from Operations Research: Applications & Algorithms, 4th edition, by Wayne L. Winston

Transcript of Transportation winston

Page 1: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

1

Transportation, Assignment and Transshipment Problems

fromOperations Research: Applications & Algorithms,

4th edition, by Wayne L. Winston

Page 2: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

2

Description

A transportation problem basically deals with the problem, which aims to find the best way to fulfill the demand of n demand points using the capacities of m supply points. While trying to find the best way, generally a variable cost of shipping the product from one supply point to a demand point or a similar constraint should be taken into consideration.

Page 3: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

3

7.1 Formulating Transportation Problems

Example 1: Powerco has three electric power plants that supply the electric needs of four cities.•The associated supply of each plant and demand of each city is given in the table 1.•The cost of sending 1 million kwh of electricity from a plant to a city depends on the distance the electricity must travel.

Page 4: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

4

Transportation tableau

A transportation problem is specified by the supply, the demand, and the shipping costs. So the relevant data can be summarized in a transportation tableau. The transportation tableau implicitly expresses the supply and demand constraints and the shipping cost between each demand and supply point.

Page 5: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

5

Table 1. Shipping costs, Supply, and Demand for Powerco Example

From To

City 1 City 2 City 3 City 4 Supply (Million kwh)

Plant 1 $8 $6 $10 $9 35

Plant 2 $9 $12 $13 $7 50

Plant 3 $14 $9 $16 $5 40

Demand (Million kwh)

45 20 30 30

Transportation Tableau

Page 6: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

6

Solution

1. Decision Variable:

Since we have to determine how much electricity is sent from each plant to each city;

Xij = Amount of electricity produced at plant i and sent to city j

X14 = Amount of electricity produced at plant 1 and sent to city 4

Page 7: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

7

2. Objective function

Since we want to minimize the total cost of shipping from plants to cities;

Minimize Z = 8X11+6X12+10X13+9X14

+9X21+12X22+13X23+7X24

+14X31+9X32+16X33+5X34

Page 8: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

8

3. Supply Constraints

Since each supply point has a limited production capacity;

X11+X12+X13+X14 <= 35

X21+X22+X23+X24 <= 50

X31+X32+X33+X34 <= 40

Page 9: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

9

4. Demand Constraints

Since each supply point has a limited production capacity;

X11+X21+X31 >= 45

X12+X22+X32 >= 20

X13+X23+X33 >= 30

X14+X24+X34 >= 30

Page 10: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

10

5. Sign Constraints

Since a negative amount of electricity can not be shipped all Xij’s must be non negative;

Xij >= 0 (i= 1,2,3; j= 1,2,3,4)

Page 11: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

11

LP Formulation of Powerco’s Problem

Min Z = 8X11+6X12+10X13+9X14+9X21+12X22+13X23+7X24

+14X31+9X32+16X33+5X34

S.T.: X11+X12+X13+X14 <= 35 (Supply Constraints)

X21+X22+X23+X24 <= 50

X31+X32+X33+X34 <= 40

X11+X21+X31 >= 45 (Demand Constraints)

X12+X22+X32 >= 20

X13+X23+X33 >= 30

X14+X24+X34 >= 30

Xij >= 0 (i= 1,2,3; j= 1,2,3,4)

Page 12: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

12

General Description of a Transportation Problem

1. A set of m supply points from which a good is shipped. Supply point i can supply at most si units.

2. A set of n demand points to which the good is shipped. Demand point j must receive at least di units of the shipped good.

3. Each unit produced at supply point i and shipped to demand point j incurs a variable cost of cij.

Page 13: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

13

Xij = number of units shipped from supply point i to demand point j

),...,2,1;,...,2,1(0

),...,2,1(

),...,2,1(..

min

1

1

1 1

njmiX

njdX

misXts

Xc

ij

mi

i

jij

nj

j

iij

mi

i

nj

j

ijij

Page 14: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

14

Balanced Transportation Problem

If Total supply equals to total demand, the problem is said to be a balanced transportation problem:

nj

j

j

mi

i

i ds11

Page 15: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

15

Balancing a TP if total supply exceeds total demand

If total supply exceeds total demand, we can balance the problem by adding dummy demand point. Since shipments to the dummy demand point are not real, they are assigned a cost of zero.

Page 16: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

16

Balancing a transportation problem if total supply is less than total demand

If a transportation problem has a total supply that is strictly less than total demand the problem has no feasible solution. There is no doubt that in such a case one or more of the demand will be left unmet. Generally in such situations a penalty cost is often associated with unmet demand and as one can guess this time the total penalty cost is desired to be minimum

Page 17: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

17

7.2 Finding Basic Feasible Solution for TP

Unlike other Linear Programming problems, a balanced TP with m supply points and n demand points is easier to solve, although it has m + n equality constraints. The reason for that is, if a set of decision variables (xij’s) satisfy all but one constraint, the values for xij’s will satisfy that remaining constraint automatically.

Page 18: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

18

Methods to find the bfs for a balanced TP

There are three basic methods:

1. Northwest Corner Method

2. Minimum Cost Method

3. Vogel’s Method

Page 19: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

19

1. Northwest Corner Method

To find the bfs by the NWC method:

Begin in the upper left (northwest) corner of the transportation tableau and set x11 as large as possible (here the limitations for setting x11 to a larger number, will be the demand of demand point 1 and the supply of supply point 1. Your x11 value can not be greater than minimum of this 2 values).

Page 20: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

20

According to the explanations in the previous slide we can set x11=3 (meaning demand of demand point 1 is satisfied by supply point 1).

5

6

2

3 5 2 3

3 2

6

2

X 5 2 3

Page 21: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

21

After we check the east and south cells, we saw that we can go east (meaning supply point 1 still has capacity to fulfill some demand).

3 2 X

6

2

X 3 2 3

3 2 X

3 3

2

X X 2 3

Page 22: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

22

After applying the same procedure, we saw that we can go south this time (meaning demand point 2 needs more supply by supply point 2).

3 2 X

3 2 1

2

X X X 3

3 2 X

3 2 1 X

2

X X X 2

Page 23: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

23

Finally, we will have the following bfs, which is: x11=3, x12=2, x22=3, x23=2, x24=1, x34=2

3 2 X

3 2 1 X

2 X

X X X X

Page 24: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

24

2. Minimum Cost Method

The Northwest Corner Method dos not utilize shipping costs. It can yield an initial bfs easily but the total shipping cost may be very high. The minimum cost method uses shipping costs in order come up with a bfs that has a lower cost. To begin the minimum cost method, first we find the decision variable with the smallest shipping cost (Xij). Then assign Xij its largest possible value, which is the minimum of si and dj

Page 25: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

25

After that, as in the Northwest Corner Method we should cross out row i and column j and reduce the supply or demand of the noncrossed-out row or column by the value of Xij. Then we will choose the cell with the minimum cost of shipping from the cells that do not lie in a crossed-out row or column and we will repeat the procedure.

Page 26: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

26

An example for Minimum Cost MethodStep 1: Select the cell with minimum cost.

2 3 5 6

2 1 3 5

3 8 4 6

5

10

15

12 8 4 6

Page 27: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

27

Step 2: Cross-out column 2

2 3 5 6

2 1 3 5

8

3 8 4 6

12 X 4 6

5

2

15

Page 28: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

28

Step 3: Find the new cell with minimum shipping cost and cross-out row 2

2 3 5 6

2 1 3 5

2 8

3 8 4 6

5

X

15

10 X 4 6

Page 29: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

29

Step 4: Find the new cell with minimum shipping cost and cross-out row 1

2 3 5 6

5

2 1 3 5

2 8

3 8 4 6

X

X

15

5 X 4 6

Page 30: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

30

Step 5: Find the new cell with minimum shipping cost and cross-out column 1

2 3 5 6

5

2 1 3 5

2 8

3 8 4 6

5

X

X

10

X X 4 6

Page 31: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

31

Step 6: Find the new cell with minimum shipping cost and cross-out column 3

2 3 5 6

5

2 1 3 5

2 8

3 8 4 6

5 4

X

X

6

X X X 6

Page 32: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

32

Step 7: Finally assign 6 to last cell. The bfs is found as: X11=5, X21=2, X22=8, X31=5, X33=4 and X34=6

2 3 5 6

5

2 1 3 5

2 8

3 8 4 6

5 4 6

X

X

X

X X X X

Page 33: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

33

3. Vogel’s Method

Begin with computing each row and column a penalty. The penalty will be equal to the difference between the two smallest shipping costs in the row or column. Identify the row or column with the largest penalty. Find the first basic variable which has the smallest shipping cost in that row or column. Then assign the highest possible value to that variable, and cross-out the row or column as in the previous methods. Compute new penalties and use the same procedure.

Page 34: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

34

An example for Vogel’s MethodStep 1: Compute the penalties.

Supply Row Penalty

6 7 8

15 80 78

Demand

Column Penalty 15-6=9 80-7=73 78-8=70

7-6=1

78-15=63

15 5 5

10

15

Page 35: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

35

Step 2: Identify the largest penalty and assign the highest possible value to the variable.

Supply Row Penalty

6 7 8

5

15 80 78

Demand

Column Penalty 15-6=9 _ 78-8=70

8-6=2

78-15=63

15 X 5

5

15

Page 36: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

36

Step 3: Identify the largest penalty and assign the highest possible value to the variable.

Supply Row Penalty

6 7 8

5 5

15 80 78

Demand

Column Penalty 15-6=9 _ _

_

_

15 X X

0

15

Page 37: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

37

Step 4: Identify the largest penalty and assign the highest possible value to the variable.

Supply Row Penalty

6 7 8

0 5 5

15 80 78

Demand

Column Penalty _ _ _

_

_

15 X X

X

15

Page 38: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

38

Step 5: Finally the bfs is found as X11=0, X12=5, X13=5, and X21=15

Supply Row Penalty

6 7 8

0 5 5

15 80 78

15

Demand

Column Penalty _ _ _

_

_

X X X

X

X

Page 39: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

39

7.3 The Transportation Simplex Method

In this section we will explain how the simplex algorithm is used to solve a transportation problem.

Page 40: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

40

How to Pivot a Transportation Problem

Based on the transportation tableau, the following steps should be performed.

Step 1. Determine (by a criterion to be developed shortly, for example northwest corner method) the variable that should enter the basis.

Step 2. Find the loop (it can be shown that there is only one loop) involving the entering variable and some of the basic variables.

Step 3. Counting the cells in the loop, label them as even cells or odd cells.

Page 41: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

41

Step 4. Find the odd cells whose variable assumes the smallest value. Call this value θ. The variable corresponding to this odd cell will leave the basis. To perform the pivot, decrease the value of each odd cell by θ and increase the value of each even cell by θ. The variables that are not in the loop remain unchanged. The pivot is now complete. If θ=0, the entering variable will equal 0, and an odd variable that has a current value of 0 will leave the basis. In this case a degenerate bfs existed before and will result after the pivot. If more than one odd cell in the loop equals θ, you may arbitrarily choose one of these odd cells to leave the basis; again a degenerate bfs will result

Page 42: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

42

Illustration of pivoting procedure on the Powerco example. We want to find the bfs that would result if

X14 were entered into the basis.

Nothwest Corner bfs and loop for Powerco

35 35

10 20 20 50

10 30 40

45 20 30 30

E O E O E O

(1, 4) (3, 4) (3, 3) (2, 3) (2, 1) (1, 1)

0

12

34

5

Page 43: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

43

New bfs after X14 is pivoted into basis. Since There is no loop involving the cells (1,1), (1,4), (2,1), (2,2), (3,3) and (3, 4) the new solution is a bfs.

35-20 0+20 35

10+20 2020-20

(nonbasic)50

10+20 30-20 40

45 20 30 30

After the pivot the new bfs is X11=15, X14=20, X21=30, X22=20, X33=30 and X34=10.

Page 44: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

44

Two important points!

In the pivoting procedure:

1. Since each row has as many +20s as –20s, the new solution will satisfy each supply and demand constraint.

2. By choosing the smallest odd variable (X23) to leave the basis, we ensured that all variables will remain nonnegative.

Page 45: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

45

Pricing out nonbasic variables

To complete the transportation simplex, now we will discuss how to row 0 for any bfs. For a bfs in which the set of basic variables is BV, the coefficient of the variable Xij (call it čij) in the tableau’s row ) is given by

čij = cBV B-1aij – cij

Where cij is the objective function coefficient for Xij and aij is the column for xij in the original LP.

Page 46: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

46

Since the example is a minimization problem, the current bfs will be optimal if all the čij‘s are nonpositive; otherwise, we enter into the basis with the most positive čij.

After determining cBVB-1 we can easily determine čij. Since the first constraint has been dropped, cBVB-

1 will have m+n-1 elements.

cBVB-1= [u2 u3…um v1 v2…vn]

Where u2 u3…um are elements of cBVB-1 corresponding to the m-1 supply constraints, and v1 v2…vn are elements of cBVB-1 corresponding to the n demand constraints.

Page 47: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

47

To determine cBVB-1 we use the fact that in any tableau, each basic variable Xij must have čij=0. Thus for each of the m+n-1 variables in BV,

cBV B-1aij – cij=0

For the Northwest corner bfs of Powerco problem, BV={X11, X21, X22, X23, X33, X34}. Applying the equation above we obtain:

č11= [u2 u3 v1 v2 v3 v4] -8 = v1-8=0

0

0

0

1

0

0

Page 48: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

48

č21= [u2 u3 v1 v2 v3 v4] -9 = u2+v1-9=0

č22= [u2 u3 v1 v2 v3 v4] -12 = u2+v2-12=0

č23= [u2 u3 v1 v2 v3 v4] -13 = u2+v3-13=0

0

0

0

1

0

1

0

0

1

0

0

1

0

1

0

0

0

1

Page 49: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

49

č33= [u2 u3 v1 v2 v3 v4] -16 = u3+v3-16=0

č34= [u2 u3 v1 v2 v3 v4] -5 = u3+v4-5=0

For each basic variable Xij (except those having i=1), we see that the equation we used above reduces to ui+vj=cij. If we define u1=0, we must solve the following system of m+n equations.

0

1

0

0

1

0

0

1

0

0

1

0

Page 50: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

50

u1=0

u1+v1=8

u2+v1=9

u2+v2=12

u2+v3=13

u3+v3=16

u3+v4=5

By solving the system above we obtain:

v1=8, u2=1, v2=11,v3=12, u3=4, v4=1

Page 51: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

51

For each nonbasic variable, we now compute

čij = ui+vj – cij

We obtain:

č12 = 0+11 – 6 = 5 č13 = 0+12 – 10 = 2

č14 = 0+1 – 9 = -8 č24 = 1+1 – 7 = -5

č31 = 4+8 – 14 = -2 č32 = 4+11 – 9 = 6

Since č32 is the greatest positive čij, we would next enter X32 into the basis. Each unit that is entered into the basis will decrease Powerco’s cost by $6.

Page 52: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

52

We have determined that X32 should enter the basis. As shown in the table below the loop involving X32 and some of the basic variables is (3,2), (3,3), (2,3), (2,2). The odd cells in the loop are (2,2) and (3,3). Since the smallest value of these two is 10 the pivot is 10.

35 35

10 20 20 50

10 30 40

45 20 30 30

Page 53: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

53

The resulting bfs will be:

X11=35, X32=10, X21=10, X22=10, X23=30 and X34=30

The ui’s and vj’s for the new bfs were obtained by solving

u1=0

u2+v2=12

u3+v4=5

u1+v1=8

u2+v3=13

u2+v1=9

u3+v2=9

Page 54: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

54

In computing čij = ui+vj – cij for each nonbasic variable, we find that č12 = 5, č13 = 2 and č24 = 1 are the only positive čij‘s. Thus we next enter X12 into the basis. By applying the same steps we will finally get a solution where all čij’s are less then or equal to 0, so an optimal solution has been obtained.

The optimal solution for Powerco is X11=10, X13=25, X21=45, X23=5, X32=10 and X34=30.

As a result of this solution the objective function value becomes:

Z=6(10)+10(25)+9(45)+13(5)+9(10)+5(30)=$1020

Page 55: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

55

7.4 Sensitivity AnalysisIn this section we discuss the following three aspects of sensitivity analysis for the transportation problem:

1. Changing the objective function coefficient of a nonbasic variable.

2. Changing the objective function coefficient of a basic variable.

3. Increasing a single supply by Δ and a single demand by Δ.

Page 56: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

56

1. Changing the objective function coefficient of a nonbasic variable.

Changing the objective function coefficient of a nonbasic variable Xij will leave the right hand side of the optimal tableau unchanged. Thus the current basis will still be feasible. Since we are not changing cBVB-1, the ui’s and vj’s remain unchanged. In row 0 only the coefficient of Xij will change. Thus as long as the coefficient of Xij in the optimal row 0 is nonpositive, the current basis remains optimal.

Page 57: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

57

Let’s try to answer the following question about Powerco as an example:

For what range of values of the cost of shipping 1 million kwh of electricity from plant 1 to city 1 will the current basis remain optimal?

Suppose we change c11 from 8 to 8+ Δ.

Now č11 = u1+v1-c11=0+6-(8+ Δ)=2- Δ.

Thus the current basis remains optimal for –2- Δ<=0, or Δ>=-2, and c11>=8-2=6.

Page 58: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

58

2. Changing the objective function coefficient of a basic variable.

Since we are changing cBVB-1, the coefficient of each nonbasic variable in row 0 may change, and to determine whether the current basis remain optimal, we must find the new ui’s and vj’s and use these values to price out all nonbasic variables. The current basis remains optimal as long as all nonbasic variables price out nonpositive.

Page 59: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

59

Let’s try to answer the following question about Powerco as an example:

For what range of values of the cost of shipping 1 million kwh of electricity from plant 1 to city 3 will the current basis remain optimal?

Suppose we change c13 from 10 to 10+ Δ.

Now č13=0 changes from u1+v3=10 to u1+v3=10+ Δ.

Thus, to find the ui’s and vj’s we must solve the following equations:

u1=0 u1+v2=6 u2+v1=9 u2+v3=13

u3+v2=9 u1+v3=10+ Δ u3+v4=5

Page 60: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

60

Solving these equations, we obtain u1=0, v2=6, v3=10+ Δ, v1=6+ Δ , u2=3- Δ, u3=3, and v4=2.

We now price out each nonbasic variable. The current basis will remain optimal as long as each nonbasic variable has a nonpositive coefficient in row 0.

č11 = u1+v1-8=Δ-2<=0 for Δ<=2

č14 = u1+v4-9=-7

č22 = u2+v2-12=-3-Δ<=0 for Δ>=-3

č24 = u2+v4-7=-2-Δ<=0 for Δ>=-2

č31 = u3+v1-14=-5+Δ<=0 for Δ<=5

č33 = u3+v3-16=Δ-3<=0 for Δ<=3

Page 61: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

61

Thus, the current basis remains optimal for –2<=Δ<=2, or 8=10-2<=c13<=10+2=12

Page 62: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

62

3. Increasing Both Supply si and Demand dj by Δ.

Changing both supply and demand by the same amount will maintain the balance of the transportation problem. Since ui’s and vj’s may be thought of as the negative of each constraint’s shadow price, we know that if the current basis remains optimal,

New Z value = old Z value+Δui+Δvj

For example if we increase plant 1,s supply and city 2’s demand by 1 unit, then

New cost=1020+1(0)+1(6)=$1026

Page 63: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

63

We can also find the new values of the decision variables as follows:

1. If Xij is a basic variable in the optimal solution, increase Xij by Δ.

2. If Xij is a nonbasic variable in the optimal solution, find the loop involving Xij and some of the basic variables. Find an odd cell in the loop that is in row I. Increase the value of this odd cell by Δ and go around the loop, alternately increasing and then decreasing current basic variables in the loop by Δ.

Page 64: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

64

7.5. Assignment ProblemsExample: Machineco has four jobs to be completed. Each machine must be assigned to complete one job. The time required to setup each machine for completingeach job is shown in the table below. Machinco wants to minimize the total setup time needed to complete the four jobs.

Page 65: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

65

Setup times

(Also called the cost matrix)

Time (Hours)

Job1 Job2 Job3 Job4

Machine 1 14 5 8 7

Machine 2 2 12 6 5

Machine 3 7 8 3 9

Machine 4 2 4 6 10

Page 66: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

66

The ModelAccording to the setup table Machinco’s problem can be formulated as follows (for i,j=1,2,3,4):

10

1

1

1

1

1

1

1

1..

10629387

5612278514min

44342414

43332313

42322212

41312111

44434241

34333231

24232221

14131211

4443424134333231

2423222114131211

ijij orXX

XXXX

XXXX

XXXX

XXXX

XXXX

XXXX

XXXX

XXXXts

XXXXXXXX

XXXXXXXXZ

Page 67: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

67

For the model on the previous page note that:

Xij=1 if machine i is assigned to meet the demands of job j

Xij=0 if machine i is assigned to meet the demands of job j

In general an assignment problem is balanced transportation problem in which all supplies and demands are equal to 1.

Page 68: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

68

Although the transportation simplex appears to be very efficient, there is a certain class of transportation problems, called assignment problems, for which the transportation simplex is often very inefficient. For that reason there is an other method called The Hungarian Method. The steps of The Hungarian Method are as listed below:

Step1. Find a bfs. Find the minimum element in each row of the mxm cost matrix. Construct a new matrix by subtracting from each cost the minimum cost in its row. For this new matrix, find the minimum cost in each column. Construct a new matrix (reduced cost matrix) by subtracting from each cost the minimum cost in its column.

Page 69: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

69

Step2. Draw the minimum number of lines (horizontal and/or vertical) that are needed to cover all zeros in the reduced cost matrix. If m lines are required , an optimal solution is available among the covered zeros in the matrix. If fewer than m lines are required, proceed to step 3.

Step3. Find the smallest nonzero element (call its value k) in the reduced cost matrix that is uncovered by the lines drawn in step 2. Now subtract k from each uncovered element of the reduced cost matrix and add k to each element that is covered by two lines. Return to step2.

Page 70: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

70

7.6 Transshipment ProblemsA transportation problem allows only shipments that go directly from supply points to demand points. In many situations, shipments are allowed between supply points or between demand points. Sometimes there may also be points (called transshipment points) through which goods can be transshipped on their journey from a supply point to a demand point. Fortunately, the optimal solution to a transshipment problem can be found by solving a transportation problem.

Page 71: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

71

The following steps describe how the optimal solution to a transshipment problem can be found by solving a transportation problem.

Step1. If necessary, add a dummy demand point (with a supply of 0 and a demand equal to the problem’s excess supply) to balance the problem. Shipments to the dummy and from a point to itself will be zero. Let s= total available supply.

Step2. Construct a transportation tableau as follows: A row in the tableau will be needed for each supply point and transshipment point, and a column will be needed for each demand point and transshipment point.

Page 72: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

72

Each supply point will have a supply equal to it’s original supply, and each demand point will have a demand to its original demand. Let s= total available supply. Then each transshipment point will have a supply equal to (point’s original supply)+s and a demand equal to (point’s original demand)+s. This ensures that any transshipment point that is a net supplier will have a net outflow equal to point’s original supply and a net demander will have a net inflow equal to point’s original demand. Although we don’t know how much will be shipped through each transshipment point, we can be sure that the total amount will not exceed s.

Page 73: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

73

Transportation ProblemTransportation Problem

Powerco Power Plant: FormulationDefine Variables:

Let Xij = number of (million kwh) produced at plant i and sent to city j.

Objective Function:Min z = 8*X11 + 6*X12 + 10*X13 + 9*X14 + 9*X21 + 12*X22 + 13*X23 + 7*X24 + 14*X31 + 9*X32 + 16*X33 + 5*X34

Supply Constraints:X11 + X12 + X13 + X14 < = 35 (Plant 1) X21 + X22 + X23 + X24 < = 50 (Plant 2) X31 + X32 + X33 + X34 < = 40 (Plant 3)

Page 74: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

74

Transportation Transportation ProblemProblem

Powerco Power Plant: Formulation (Cont’d.)Demand Constraints:

X11 + X21 +X31 > = 45 (City 1) X12 + X22 +X32 > = 20 (City 2) X13 + X23 +X33 > = 30 (City 3) X14 + X24 +X34 > = 30 (City 4)

Nonnegativity Constraints:Xij > = 0 (i=1,..,3; j=1,..,4)

Balanced?Total Demand = 45 + 20 + 30 + 30 = 125Total Supply = 35 + 50 + 40 = 125

Yes, Balanced Transportation Problem! (If problem is unbalanced, add dummy supply or demand as required.)

Page 75: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

75

Transportation ProblemTransportation ProblemPowerco Power Plant: LINGO Formulation

model:! A 3 Plant, 4 Customer Transportation Problem;SETS: PLANT / P1, P2, P3/ : CAPACITY; CUSTOMER / C1, C2, C3, C4/ : DEMAND; ROUTES( PLANT, CUSTOMER) : COST, QUANTITY;ENDSETS

! The objective; [OBJ] MIN = @SUM( ROUTES: COST * QUANTITY);

Page 76: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

76

Transportation ProblemTransportation ProblemPowerco Power Plant: LINGO Formulation (Cont’d.)

! The demand constraints;@FOR( CUSTOMER( J): [DEM]@SUM( PLANT( I): QUANTITY( I, J))>= DEMAND( J));! The supply constraints;@FOR( PLANT( I): [SUP]@SUM( CUSTOMER(J): QUANTITY(I,J))<=CAPACITY( I));! Here are the parameters;DATA: CAPACITY = 35, 50, 40 ; DEMAND = 45, 20, 30, 30; COST = 8, 6, 10, 9,

9, 12, 13, 7, 14, 9, 16, 5;

ENDDATAend

Page 77: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

77

Transportation ProblemTransportation ProblemPowerco Power Plant: LINGO Solution

Optimal solution found at step: 7 Objective value: 1020.000

QUANTITY( P1, C1) 0.0000000 QUANTITY( P1, C2) 10.00000 QUANTITY( P1, C3) 25.00000 QUANTITY( P1, C4) 0.0000000 QUANTITY( P2, C1) 45.00000 QUANTITY( P2, C2) 0.0000000 QUANTITY( P2, C3) 5.000000 QUANTITY( P2, C4) 0.0000000 QUANTITY( P3, C1) 0.0000000 QUANTITY( P3, C2) 10.00000 QUANTITY( P3, C3) 0.0000000 QUANTITY( P3, C4) 30.00000

All Quantitiesare Integers!

Page 78: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

78

Transportation ProblemTransportation ProblemPowerco Power Plant: LINGO Solution (Cont’d.)

Row Slack or Surplus Dual Price OBJ 1020.000 1.000000 DEM( C1) 0.0000000 -9.000000 DEM( C2) 0.0000000 -9.000000 DEM( C3) 0.0000000 -13.00000 DEM( C4) 0.0000000 -5.000000 SUP( P1) 0.0000000 3.000000 SUP( P2) 0.0000000 0.0000000 SUP( P3) 0.0000000 0.0000000

All constraints are binding!(Typical of Balanced Transportation Problems; results in simple algorithms)

Page 79: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

79

Transportation ProblemTransportation ProblemPowerco Power Plant: Sensitivity AnalysisRow Dual Price

OBJ 1.00000 DEM( C1) -9.00000 (-v1) DEM( C2) -9.00000 (-v2) DEM( C3) -13.00000 (-v3) DEM( C4) -5.00000 (-v4) SUP( P1) 3.00000 (-u1) SUP( P2) 0.00000 (-u2) SUP( P3) 0.00000 (-u3)

Changes in total cost due to changes in demand and supply: z = v1* C1 + v2* C2 + v3* C3 + v4* C4

+ u1* P1 + u2* P2 + u3* P3e.g. C2 = 1, P1 = 1 z = 9*1 + (-3)*1 = $6

Page 80: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

80

Transportation ProblemTransportation ProblemPowerco Power Plant: Sensitivity AnalysisRow Dual Price

OBJ 1.00000 DEM( C1) -9.00000 (-v1) DEM( C2) -9.00000 (-v2) DEM( C3) -13.00000 (-v3) DEM( C4) -5.00000 (-v4) SUP( P1) 3.00000 (-u1) SUP( P2) 0.00000 (-u2) SUP( P3) 0.00000 (-u3)

Changes in total cost due to changes in demand and supply: z = v1* C1 + v2* C2 + v3* C3 + v4* C4

+ u1* P1 + u2* P2 + u3* P3e.g. C2 = 1, P1 = 1 z = 9*1 + (-3)*1 = $6

Page 81: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

81

Powerco Power Plant: Sensitivity Analysis (Cont’d.)Powerco Power Plant: Sensitivity Analysis (Cont’d.)Variable Value Reduced CostQUANTITY( P1, C1) 0.00 2.00 (c11)QUANTITY( P1, C2) 10.00 0.00 (c12) QUANTITY( P1, C3) 25.00 0.00 (c13)QUANTITY( P1, C4) 0.00 7.00 (c14)QUANTITY( P2, C1) 45.00 0.00 (c21)QUANTITY( P2, C2) 0.00 3.00 (c22)QUANTITY( P2, C3) 5.00 0.00 (c23)QUANTITY( P2, C4) 0.00 2.00 (c24)QUANTITY( P3, C1) 0.00 5.00 (c31)QUANTITY( P3, C2) 10.00 0.00 (c32)QUANTITY( P3, C3) 0.00 3.00 (c33)QUANTITY( P3, C4) 30.00 0.00 (c34)z = c11* Q11 + c12* Q12 + c13* Q13 + c14* Q14 + c21* Q21 + c22* Q22 + c23* Q23 + c24* Q24 + c31* Q31 + c32* Q32 + c33* Q33 + c34* Q34

NonbasicBasicBasicNonbasicBasicNonbasicBasicNonbasicNonbasicBasicNonbasicBasic

Page 82: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

82

Assignment ProblemsAssignment ProblemsPersonnel Assignment:

Time (hours)Job 1 Job 2 Job 3 Job 4

Person 1 14 5 8 7Person 2 2 12 6 5Person 3 7 8 3 9Person 4 2 4 6 10

Page 83: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

83

Assignment Problem FormulationAssignment Problem Formulation

Define Variables: Let Xij = 1 if ith person is assigned to jth job

Xij = 0 if ith person is not assigned to jth job

Objective Function:Min z = 14*X11 + 5*X12 + … + 10*X44

Personnel Constraints:X11 + X12 + X13 + X14 = 1X21 + X22 + X23 + X24 = 1X31 + X32 + X33 + X34 = 1X41 + X42 + X43 + X44 = 1

Demand Constraints:X11 + X21 + X31 + X41 = 1X12 + X22 + X32 + X42 = 1X13 + X23 + X33 + X43 = 1X14 + X24 + X34 + X44 = 1

Binary Constraints:Xij = 0 or Xij = 1

Page 84: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

84

Assignment Problem AlgorithmAssignment Problem Algorithm

14 5 8 72 12 6 57 8 3 92 4 6 10

Row Minimum 5 2 3 2

9 0 3 20 10 4 34 5 0 60 2 4 8

0 0 0 2Column Minimum

Subtract Row Minimum from Each Row:

Page 85: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

85

Assignment Problem AlgorithmAssignment Problem Algorithm

9 0 3 00 10 4 14 5 0 40 2 4 6

Subtract Column Minimum from Each Column:

10 0 3 00 9 3 05 5 0 40 1 3 5

Subtract Minimum uncrossed value from uncrossed values and add to twice-crossed values:

Draw lines to cross out zeros and read solution from zeros

0 0

0 0

Solution:

Page 86: Transportation winston

Copyright © 2004 Brooks/Cole, a division of Thomson Learning, Inc.

86

Hungarian MethodHungarian MethodStep 1: Find the minimum element in each row of the m x m cost matrix. Construct a new matrix by subtracting from each cost the minimum cost in its row. For this new matrix, find the minimum cost in each column. Construct a new matrix (called the reduced cost matrix) by subtracting from each cost the minimum cost in its column.

Step 2: Draw the minimum number of lines (horizontal and/or vertical) that are needed to cover all the zeros in the reduced cost matrix. If m lines are required, an optimal solution is available among the covered zeros in the matrix. If fewer than m lines are needed, proceed to Step 3.

Step 3: Find the smallest nonzero element (call its value k) in the reduced cost matrix that is uncovered by the lines drawn in Step 2. Now subtract k from each uncovered element of the reduced cost matrix and add k to each element that is covered by two lines. Return to Step 2.