Transportation Planning Committee (TPC) Meeting At 9:00 a.m., Wednesday, Sept. 5, 2012 Pima Association of Governments 177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Agenda
1. Call to Order and Introductions
2. Call to the Audience
3. In-Kind Form
4. Announcements/Comments
5. Report on Regional Council’s Meeting Schedule
• Next Regional Council meeting is scheduled for Sept. 27, 2012
DISCUSSION/ACTION ITEMS
6. Approval of Minutes of May 2, 2012, Meeting
7. Transportation Enhancements Round 19 – TETF Rankings
The Transportation Enhancement (TE) program was funded under SAFETEA-LU through a 10
percent set aside from Surface Transportation Program (STP) funds. A PAG representative will
discuss the TE process.
Discussion/Action: The Committee is asked to recommend forwarding the Transportation Enhancements Round 19 proposed rankings to Management Committee.
8. Regional Dial-a-Ride Update
Staff will provide an update on the Oro Valley Sun Shuttle Dial-a-Ride system and present recommendations regarding the expansion of the optional ADA dial-a-ride service area and the upcoming transit service procurement. Discussion/Action: Staff recommends that the Committee approve the Transit Work Group recommendations for expanding the optional ADA service area in two phases and combining the RTA Special Needs Transportation services (Handicar) and Sun Shuttle (MV Transportation) services into the upcoming transit service procurement, and subsequently pass along these recommendations to the Management Committee and RTA Board for further consideration.
9. TIP Subcommittee Report including Amendment #1 to FY 2013 – 2017 TIP
The PAG TIP Subcommittee Chair or a Subcommittee representative will be available to report
on the August 21, 2012, PAG TIP Subcommittee meeting.
Discussion/Action: This is an Information item/possible action.
10. RTA Report
• Report on RTA Board
• Jurisdictional Project Updates
• Request for increased funding for SR-86
• Small Business Enterprise (SBE) Goals
• RTA Categorical Funding Reallocation
Discussion/Action:
This is an Information and action item.
INFORMATION ITEMS
11. Road Maintenance in the PAG Region
A presentation will be provided on a paper prepared by PAG to address the current state of road
maintenance in the region, with emphasis on effective strategies for preventative maintenance
and funding availability.
Discussion/Action: The Committee is asked to review and discuss the item and its next steps.
12. MAP-21: Transportation Appropriation Bill Update
The president recently signed MAP-21, a new Transportation appropriation bill that funds
transportation through the end of fiscal year 2014. A PAG representative will discuss possible
impacts of the new bill on PAG regional funding.
Discussion/Action: This is an information item only.
13. Summary of Regional Transportation Studies
PAG provides quarterly updates to the Transportation Planning Committee on transportation-
related studies being conducted in the region. The update will include a brief summary of the
study and its goals, as well as a brief description of the project status.
Discussion/Action:
This is an information item/possible action.
14. TPC Finance Subcommittee Report
The Transportation Finance Subcommittee holds monthly meetings to develop, review and assess the financial plan needed for the Transportation Improvement Program (TIP) and the Regional Transportation Plan (RTP). Discussion/Action: This is an information item only OTHER
15. Future Agenda Items 16. Adjournment
The next regularly scheduled meeting will be on June 6, 2012 @ 9:00 a.m. or as directed by the Committee.
ACTION MAY BE TAKEN ON ANY ITEM*
Persons with a disability or language barrier may request this document in alternative formats or translations or other reasonable accommodations by contacting Nathan Barrett at (520) 792 -1093. Requests should be made as early as possible to allow time to arrange the accommodation. Si necesita ayuda con traducción, llame por favor al 792-1093 y comuníquese con Nathan Barrett.
NOTE: For items delineated as “RTA,” the Committee is acting as the RTA TPC. The PAG TPC and RTA TPC have identical memberships.
Regional Transportation Authority 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 770-9410 [tel] (520) 620-6981 [fax] RTAmobility.com [web] Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] PAGnet.org [web]
1
Transportation Planning Committee Minutes of May 2, 2012, Meeting
Committee Members Present Priscilla Cornelio, Pima County DOT, Chair Craig Civalier, Town of Oro Valley, Vice Chair Ed Stillings, FHWA Fred Stevens, TON Maria Arvayo, Pascua Yaqui Tribe Mark Pugh, San Xavier District, TON Matt Carpenter, ADOT Ryan Benavides, Town of Marana Tony Paez, City of Tucson Ursula Kramer, PDEQ
Public/Agencies
Becky Pallack, Az. Daily Star Ben Goff, Pima County Carlos Lopez, ADOT Corrina Gil, Town of Marana Curt Lueck, CLA David Perkins, KHA Doug Moseke, Stantec Joanne Hershenhorn, COT Jose Rodriguez, Town of Oro Valley Rick Ellis, Pima County Robin Raine, ADOT Steve Hogan, Parsons Brinckerhoff
Staff Carlos de Leon Cherie Campbell David Ruelas Jennifer O’Connor Jeremy Papuga Jim DeGrood John Liosatos Paul Casertano Riley Rasmussen Rob Samuelsen Rosie Soto Sheila Storm Steve Matthews
1. Call to Order and Introductions
The meeting was called to order by Ms. Cornelio at 9:00 a.m. and introductions were made.
2. Call to the Audience None.
3. In-Kind Form An in-kind form was routed among attendees.
4. Announcements/Comments Mr. Liosatos reminded the committee that historically the June and July meetings are canceled.
2
Mr. DeGrood announced that the RTA has been working with the Tucson Utility Contractors Association (TUCA) to hold a State of the RTA address, which will be held the evening of May 30 at the University Marriott. The TUCA web site has registration information.
5. Report on Regional Council’s Meeting Schedule
Mr. Liosatos reported that there were no TIP Amendments. A presentation on the Coordinated Plan was given and was approved. Updates were presented on the Social Services Block Grant Plan to adjust the budget and it was also approved. Mr. DeGrood reported that the RTA Board approved the IGA for Bus Pullouts Package #4, IGA with ADOT for SR86 Wildlife Crossings, transfer of title to the City of Tucson for seven bus pullout parcels and the reimbursement of the minimum local match requirements for projects that are successful in Transportation Enhancement Grant Cycle 19, and are eligible for RTA Categorical funds.
6. Approval of PAG and RTA TPC Minutes of April 4, 2012
ACTION: Mr. Civalier moved to approve the PAG and RTA TPC Minutes of April 4, 2012, minutes, seconded by Mr. Benavides and unanimously approved.
7. Approval of PAG’s FY 2012-2013 Overall Work Program (OWP)
Ms. Campbell presented a PowerPoint presentation regarding PAG’s FY 2013-2013 OWP Overview. Items reviewed:
� IPG Review Agenda � Key PAG Roles – Federal � Key PAG Roles – State � 2011 Certification Review Report � Work Program Organization � Changes in Format � Changes to Draft � Major Changes from Last Year � Management and Budget Goals � Cost Implications � Anticipated Revenue � Anticipated Expenses � PAG Personnel – FTEs � Anticipated Outside Services
Mr. Stillings asked if PAG is assuming something similar to the 2012 PL funding proportionments.
Ms. Campbell said yes, that she assumed 10 percent.
Mr. Goff asked what the Land Bridge is referring to.
Ms. Campbell stated that it’s also referred to as Interstate 11.
If you would like a copy of the presentation, please contact Ms. Soto at 792-1093 or [email protected].
3
8. ADOT Passenger Rail Corridor Study; Tucson to Phoenix Presentation Mr. Lopez, ADOT, and Mr. Hogan, Parsons Brinckerhoff, provided a PowerPoint presentation
regarding the ADOT Passenger Rail Corridor Study. Items reviewed:
� Stakeholder Interviews � Journey � Corridor � Passenger Rail Corridor Study Process � Alternatives Analysis � Service Type Metrics � Initial Screening: Route Location � Station Evaluation � Station Screening Results � Tucson Area Considerations � Passenger Rail Corridor Study Process
If you would like a copy of the presentation, please contact Ms. Soto at 792-1093 or [email protected].
9. Consultant Selection for Tucson Modern Streetcar Land Use and Development Implementation Plan
Mr. de Leon stated that he is looking to get a recommendation from this committee to forward to Regional Council to allow the Executive Director to negotiate with the Planning Center for the land use and development study. ACTION Mr. Paez moved to forward the Consultant Selection for the Tucson Modern Streetcar Land Use and Development Implementation Plan to the Regional Council, seconded by Mr. Civalier and unanimously approved.
If you would like a copy of the presentation, please contact Ms. Soto at 792-1093 or
10. Consultant Selection for Routes of Regional Significance Study
Mr. Liosatos stated that problems that were identified have been addressed. Jurisdictions are supportive of the next go around of the Routes of Regional Significance and are ready to move forward. An RFP was released and one response was received. A consultant selection group consisting of representatives of ADOT, Pima County, Sahuarita, Oro Valley and the RTA recommend that the proposal from Kimley-Horn, PSOMAS and Curt Lueck and Associates be accepted and direct the Executive Director to enter into a contract for the study. ACTION: Mr. Civalier moved to approve the recommendation to Regional Council, seconded by Mr. Paez and unanimously approved.
11. JARC and New Freedom Project Recommendations Mr. Papuga reported that this is a result of an application process that began in March with PAG
and the City of Tucson, as the designated recipient for FTA funds. New Freedoms projects include: 1) Rider Training Videos; 2) Purchase of Software to Optimize Paratransit Performance; 3) Purchase of software to standardize ADA fare payment throughout the region; and 4)
4
Purchase of Sun Shuttle Dial-a-ride Vehicles. JARC projects include: Purchase of Sun Shuttle Vehicles.
Ms. Cornelio questioned if the Transit Working Group has approved this. Mr. Papuga stated that it has not gone through the Working Group as the JARC and New Freedoms application process. These projects were discussed as part of the regional TIP process. Mr. Goff added that some of the elements have been through the Working Group and it was strongly supported. ACTION: Mr. Paez moved to approve the JARC and New Freedom project recommendations to Management Committee and Regional Council, seconded by Mr. Civalier and unanimously approved.
12. TIP Subcommittee Report including Amendment #8 to FY 2012-2016
Mr. Ruelas reported that the TIP Subcommittee last met on April 10 and he reviewed Amendment #8 items A-E. ACTION: Mr. Paez moved to approve TIP Amendment #8 Items A-E, seconded by Mr. Civalier and unanimously approved.
13. PAG’s FY 2013-2017 Transportation Improvement Program (TIP) Mr. Liosatos reported that Mr. Ruelas and the TIP Subcommittee had a difficult task
programming a limited amount of funds to an ever-growing amount of projects that need additional funding. The Subcommittee held quite a few meetings to derive at this program, several Open Houses were held and is currently in the public comment period.
Mr. Ruelas added that an approved project list was modeled for air quality conformity
determination and Title VI requirements. The Draft 2013 – 2017 PAG TIP is currently in the 30-day public comment period. Comment forms, 2013-2017 TIP and associated maps are available online on the PAG web site.
ACTION: Mr. Civalier moved to approve PAG’s FY 2013-2017 TIP, seconded by Mr. Benavides and unanimously approved.
14. RTA Report Mr. DeGrood reported that there are two action items: 1) Increase funding for SR77 Wildlife
Crossings. Increase the amount of funding for an approximate $3.005 million and relocate under crossing #1 to a revised location further to the south at approximately M.P. 82.06; and 2) Categorical Funding Change. This would expand the scope of the FY 09 City of Tucson HAWK Signal Project, to include the installation of a new HAWK signal at the intersection of Ocelot Road and la Cholla Blvd., adjacent to Cholla High School. Mr. DeGrood provided an RTA project update.
ACTION: Mr. Civalier moved to approve the two action items, seconded by Mr. Paez and unanimously approved.
5
14. TIP Subcommittee Report Mr. Gastelum reported that the March TIP meeting was canceled due to TIP Open Houses. There
are no TIP Amendment requests. The TIP Open Houses for the Draft 2013-2017 PAG TIP were held on March 20, 21 and 22. Thirty-two members of the public attended the Open House along with several transportation professionals representing the PAG member jurisdictions. The official 30-day comment period will commence later this month. The Draft 2013-2017 PAG TIP will be made available to the public and will be available on the PAG Web site. The next TIP meeting is Tues., April 10 at 9:00 a.m.
15. Summary of Regional Transportation Studies Mr. Barrett highlighted a few substantial updates. 1) Freight Train Work Study; 2) Pedestrian
Compatibility Study; and 3) Sahuarita Corridor Study. The Passenger Rail Study and the Arizona Sonoran Border Master Plan will be added to the monthly memos.
16. TPC Finance Subcommittee Report Mr. Goff reported that there were two consecutive months of revenue growth. We’re still short
on estimates, but not as bad as before. State budget was delivered yesterday and will be a slight bump for us. DPS sweeps are the same. Overall projection for next year looks positive. The Subcommittee is currently working on a new estimate for next fiscal year and Mr. Goff will provide an update at another TPC meeting.
17. Future Agenda Items
None. 17. Adjournment ACTION: Mr. Moghimi moved to adjourn the meeting, seconded by Mr. Civalier, and
unanimously approved. Meeting adjourned at 10:09 a.m.
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments 177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Transportation Planning Committee Wednesday, September 5, 2012
Agenda Packet Memo Transportation Enhancements Round 19 – TETF Rankings Background:
The Transportation Enhancement (TE) program was funded under SAFETEA-LU through a 10 percent set aside from Surface Transportation Program (STP) funds. The TE process is conducted through a local project application review and ranking, with final recommendation of projects to be funded from the Statewide Transportation Enhancement Review Committee (TERC). This program was developed to enhance surface transportation activities by developing projects that go above and beyond what transportation departments typically do. This program has 12 eligible categories for funding that include alternative mode enhancements, historic preservation, landscaping and other beautification activities. Discussion Points:
The region received 10 local applications and 1 state application for the final submission to ADOT for consideration. Application funding requests total approximately $8 million. The combined regional total for the projects is under the estimated state cap and will be forwarded to the TERC for consideration. The applications were reviewed and ranked by the PAG Transportation Enhancement Task Force. The Task Force consists of members who represent the different eligible categories of TE funding. The Task Force ranking recommendation is attached. ADOT’s review committee will meet in early October to develop funding recommendations that will be sent to the Arizona State Transportation Board for final determination, most likely in November or December. NOTE: During the development of the Round 19 applications a new Surface Transportation bill was passed by Congress and signed into law by the president, called MAP-21. MAP-21 changes Transportation Enhancements into Transportation Alternatives. Transportation Alternatives reduces the eligible activities from 12 to 8 and also apportions TA funding directly to PAG. Because TE projects selected this year are placed on a schedule to be
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
constructed in three years, ADOT is still waiting for guidance as to which Surface Transportation bill, SAFETEA-LU or MAP-21, they should conduct round 19 under. Even after we know which bill we are going to be working off of, several questions of how the new MAP-21 will be interpreted will need to be answered. At this point, a full range of possibilities could still take place from:
• Round 19 moving forward under SAFTEA-LU
• Round 19 moving forward under MAP-21, with PAG projects still competing statewide. Under this scenario several projects would no longer be eligible.
• Round 19 moving forward under MAP-21, with PAG project being sent back to PAG to fund out of the PAG region’s direct apportionment. This scenario means PAG would be moving from a competitive grant process to a programming process. The region would need to agree on a process to program these TA funds.
o Process would more than likely include the PAG Bicycle and Pedestrian Working Group.
o TA funds combined Transportation Enhancements and Safe Routes to School, both processes need to be combined.
o MAP-21 is only a two year bill. Who know how many extensions we are likely to see but preference may need to be given to projects that are “ready to go”.
Recommendation:
The Committee is asked to recommend forwarding the Transportation Enhancements Round 19 proposed rankings to Management Committee. Attachment: Round 19 TE rankings
Round 19 TE Rankings
Rank Project Cost Amount
Requested Description Jurisdiction
1
CDO Path Link under SR 77 to Catalina S.P. (OV CDO SUP)
$969,837 $909,842
The project will construct a 2285 foot long, 12 foot wide shared use path on top of an existing levee located on the north side of the Cañada del Oro (CDO) Wash. A ramp will be built for the path to travel under the vehicular bridge on SR 77. Upon exiting the wash on the east side of SR 77, a connection will be made to the existing path that connects to the Catalina State Park. The existing path will be widened to 12 foot to allow for two-way pedestrian and bicycle traffic.
ADOT/Oro Valley
Total $969,837 $909,842
Local 1
U of A 2nd Street Bike and Pedestrian Improvements (UA 2nd)
$846,469 $750,000
The project will construct a bicycle and pedestrian path along the Olive Road (250' long and 20' wide ) and Highland Avenue (540' long and 30' wide) alignments at their intersection with 2nd Street. Across 2nd Street at the intersections there will be high visibility pedestrian crosswalks and bicycle crossings of the new Tucson Modern Streetcar trackway that runs down the middle of 2nd Street. At Olive Road, the bicycle path will be brought through a rock wall to a shared use path in the alley. New trees at the outer edge of the paths will provide shade for users. The purpose of the project is to improve pedestrian and bicycle circulation efficiency and safety at these two locations which are intersections of the two highest volume north-south campus bicycle and pedestrian corridors with the new east-west Tucson Modern Streetcar route through campus.
City of Tucson / UA
2 Treat Ave Bicycle Boulevard (COT Treat BB)
$800,000 $749,685
Treat Bicycle Boulevard will improve an existing six-mile stretch of residential bicycle route to improve safety, comfort and convenience for bicycle travel, walking, and transit use in central Tucson. The project will involve improving six major crossings by installing bicycle/pedestrian signals and/or a refuge islands. Strategically placed traffic circles and speed humps will help to calm traffic. Treat BB passes through numerous residential and commercial areas and within a quarter mile of thirteen schools and five parks, but it provides a direct mid-town connection between three of the most popular existing bicycle routes in the city (3rd Street, Rillito and Aviation Pathways).
City of Tucson
3 Summit View Safe Routes to School Project
$702,567 $659,692 The Summit View Elementary School Safe Routes to School Project will construct a paved shared use path on East Summit
Pima County
(PC Summit) Street (classified by Pima County as a Minor Local Road) from Old Nogales Highway (Minor Local Road) to Epperson Lane (Minor Local Road) for a distance of 3,500 feet. The project includes construction of an eight-foot wide paved shared use pathway along the south side of Summit Street with associated native, drought-tolerant landscaping in front of the school. In addition, a school crosswalk with pedestrian safety lighting will be installed across Summit Street near the west end of the school property.
4
S. 12th Ave Pedestrian Safety & Beautification (COT 12th Ave)
$799,170 $748,902
This project will construct 2.4 miles of sidewalks on both sides of l2th Avenue to link intermittent stretches where none exist, and strategically place streetscape improvements, street trees and way-finding signs to attract pedestrian traffic on this busy road. The project aims to create a safe and pleasant environment for pedestrians, wheelchair users, and bus riders along 2.4 miles of busy arterial roadway between Drexel Road and 44th St. Improvements will support existing businesses, encourage new enterprise, provide better access to and from adjacent schools and neighborhoods, and improve the safety of all roadway users.
City of Tucson
5
Downtown Tucson Sidewalk Enhancements: Phase 1 (COT DT Sidewalk)
$799,400 $749,119
The project will improve conditions for pedestrians along 3,870 feet of the future Modern Streetcar route on Congress, including side streets between Congress and Broadway in Downtown Tucson. It replaces unsafe, non-ADA compliant sidewalks, adds pedestrian friendly amenities that include street furniture, information kiosks, lighting, water fountains, landscaping and trash and recycling receptacles and enhances multi-modal connections by linking transit to the complementary travel modes of walking and biking. The project will increase the viability of the Modern Streetcar providing a safe, aesthetically pleasing and unique urban oasis that will increase Streetcar ridership and creates a desirable urban core than maximizes economic development opportunity for Downtown Tucson.
City of Tucson
6
Manzanita Elem Safe Routes to School Project (PC Manzanita)
$789,203 $741,389
This Safe Routes to School Project includes the provision of 5-foot paved pedestrian paths and 6-foot bicycle lanes on Campbell Avenue from 1,070 feet south of Manzanita School to East Plaza Encantada, a distance of 2,980 feet. The project also includes traffic calming on Campbell Avenue from the south project limit to Ina Road (north of Plaza Encantada) for a total distance of 3,560 feet, plus traffic calming on Manzanita Avenue from Campbell Avenue for 870 feet to the west side of Manzanita Elementary School. The traffic calming features include neighborhood traffic circles, speed tables, a pedestrian
Pima County
refuge island, an elevated school crosswalk, and landscaped medians to help slow traffic and improve safety. Pima County has already completed a Project Assessment and 15% plans following the ADOT design process.
7 Restoration of Historic Neon Highway District (COT Neon)
$444,240 $414,203
The scope of this project is to rehabilitate and restore between 8 and 12 mid-century historic neon signs within the view shed and/or within a half mile of Tucson’s Historic Highway corridor in the City of Tucson and the City of South Tucson. The length of the project is 5.8 miles, following the historic alignment of old US Route 80, 89 and AZ 84 (Miracle Mile – Oracle Road – Drachman Street – Stone Avenue – South 6th Avenue). The restoration of these signs will have a powerful visual impact in redefining this historic significance of this disinvested highway corridor.
City of Tucson
8
High Haven Ranch Scenic Easement Project (PC High Haven)
$635,000 $594,090
The High Haven Ranch Scenic Easement Project, located in Sonoita south of Tucson and directly visible and adjacent to 1 mile of Scenic State Route Highway 83 between mileposts 41 and 42, will permanently protect 236 acres of the Ranch from development. This project will complete the second and final phase of scenic easements on the Ranch. This project will permanently protect High Haven Ranch from development, sustaining its scenic values and local agriculture, maintaining the local rural economy and expanding a critical wildlife corridor by linking to protected lands of Las Cienegas National Conservation Area and Coronado National Forest, both bordering the property.
Pima County
9
Be Safe! UA Area Bike/Ped Safety Campaign (PC Education)
$257,778 $240,255
This project is an intensive education program that covers the UA and the area within two miles of campus. The project consists of education and enforcements to improve safety for persons walking and bicycling on campus as well as in surrounding areas. It will include PSAs, UAPD and TPD safety outreach and education, safety classes and provisions including helmets and lights, and other educational outreach activities. The project will also include the installation of striping, markings and signage on the UA campus.
Pima County
10
Duval Mine Road Sidewalk and Bike Lane Improvements (Sah Duval Mine)
$734,838 $688,237
This project will provide connectivity for pedestrians and bicyclists on the north side of Duval Mine Road between La Cañada Drive and Alpha Avenue. Currently, there is a missing segment of approximately 1,350 LF of 5-foot sidewalk and 6-foot bike lane. This project will provide curb, gutter, sidewalk, hand railing, rock slope protection, necessary paving, along with markings and striping for the bike lane. Project will impact up to 0.56 acres. The project includes a bench and waste receptacle,
Sahuarita
to provide a pleasant rest area for bicyclists and pedestrians. Shade trees will be planted along the section to be improved.
Total $6,808,665 $6,335,572
1
177 N. Church Avenue, Suite 405, Tucson AZ 85701
Phone: (520) 770-9410 Fax: (520) 620-6981
RTAmobility.com
RTA Transportation Planning Committee Wednesday, September 5, 2012
Agenda Packet Memo
Regional Dial-a-ride Update
Background: In January 2012, the RTA Board approved establishing regional dial-a-ride service polices and standards; amending the intergovernmental agreement (IGA) with the Town of Oro Valley to merge the Town’s Coyote Run service into the regional dial-a-ride system, and; using the name Sun Shuttle Dial-a-Ride as the initial regional dial-a-ride brand. These actions are part of a strategy of making incremental progress in developing a seamless regional dial-a-ride system. The RTA has three contracts/agreements for the provision of public transportation transit services, which will conclude on June 30, 2012. Those contracts/agreements include RTA Special Needs Transit (Handicar), Sun Shuttle (MV Transportation) and Sun Shuttle Dial-a-Ride (Town of Oro Valley). The procurement of these service contracts/agreements offers an opportunity to make additional regional dial-a-ride progress. Discussion Points: This memo provides an update on the following interrelated regional dial-a-ride items:
• Oro Valley Sun Shuttle Dial-a-Ride Results
• Optional Americans with Disabilities Act (ADA) Service Area Expansion
• Transit Service Procurement Oro Valley Sun Shuttle Dial-a-ride Results On Feb. 13, 2012, the Town of Oro Valley began transit service as part of the improved regional Sun Shuttle Dial-a-Ride system. Under the regional Sun Shuttle Dial-a-ride IGA , the RTA funds general public trips on the Sun Shuttle Dial-a-Ride Oro Valley and all regional ADA dial-a-ride trips originating in the Sun Shuttle Dial-a-Ride Oro Valley service area. At the Town’s discretion, it funds senior trips traveling outside of the general public Sun Shuttle Dial-a-Ride Oro Valley zone. The Town of Oro Valley agreed to operate these dial-a-ride services under the newly approved regional dial-a-ride service policies and regional system brand, eliminating the Town’s Coyote Run transit service brand.
2
The merger of the Town’s transit service into the Sun Shuttle Dial-a-Ride system was expected to improve operational efficiencies and reduce costs for the Town of Oro Valley thru the elimination of duplicative ADA trips operated by Handi-car. The merging was also expected to help the Town sustain its senior transit service and be cost neutral for the RTA. The initial results of the regional dial-a-ride improvements to the Oro Valley Sun Shuttle Dial-a-Ride system are promising. As shown in Attachment A, ridership has increased significantly from an average of 680 boardings per month to approximately an average of 1,050 boardings per month. In addition, the improvements have decreased costs to both the Town of Oro Valley and the RTA. The RTA estimated net savings to date is $89,582 ($162,000 annualized) compared to assigning the ADA trips to Handi-car. Given these initial results, the Town of Oro Valley staff has expressed their support for continuing the Sun Shuttle Dial-a-Ride IGA with the RTA beyond June 2013. Optional ADA Service Area Expansion Over the last nine months, the Transit Working Group has been evaluating the potential expansion of the optional ADA service area as part of a set of initial regional dial-a-ride objectives. This evaluation identified five areas for potential optional ADA service expansion, ranked these potential areas based on estimated ADA need, estimated the annual costs for providing services to these areas, compared the costs against the 20 year allocation for Special Needs Transit in the RTA Plan, and drafted potential implementation strategies. Based on this evaluation, the Transit Working Group is recommending that expansion of the optional ADA service area be phased as follows:
• Phase 1 - Implement service expansion in the Old Town Marana/Gladden Farms Area (shown in Attachment B as Expansion Area 1) in FY2012/2013.
• Phase 2 - Implement service expansion in the Dove Mountain Area (shown in Attachment B as Expansion Area 2) and the Green Valley Area (shown in Attachment B as Expansion Area 3) with improved efficiencies resulting from the re-procurement of transit services in June 2013.
With the savings from the Oro Valley Sun Shuttle Dial-a-Ride, the RTA has budget and contract capacity with Handicar to implement Phase 1, Old Town Marana/Gladden Farms service expansion. It is anticipated that this service expansion would occur in January 2013. Transit Service Procurement Given the above, staff has begun drafting a scope of work as part of request for proposal (RFP) for transit services contract beginning on July 1, 2013. It is anticipated that the RFP would be released in October 2012 and a recommendation for award would be forwarded to the RTA Board by January 2013. The Transit Working Group identified three goals for the development of the RFP:
• Integration. The RFP should continue the process of integrating services into the seamless regional dial-a-ride system.
• Efficiency. The RFP should improve efficiency and reduce costs by combining RTA service contracts.
• Flexibility. The RFP should provide flexibility for expanding the network of providers and partnering coordinated rides with human service agencies in a brokerage program.
3
The Transit Working Group also discussed a number of major considerations regarding the scope of work and recommended the following:
• To improve efficiencies and reduce costs, there will be one provider in the ‘‘shared area’’ now served by both Sun Van, RTA Special Needs Transportation and Sun Shuttle Dial-a-Ride.
• To improve customer service, improve efficiencies and reduce costs, there will be one phone number for scheduling rides on Sun Shuttle Dial-a-Ride.
• To reduce costs and improve customer service, an electronic fare payment system will be implemented.
• To continue high quality services and efficiencies, the agreement with the Town of Oro Valley to provide Sun Shuttle Dial-a-Ride services in the Oro Valley area should continue beyond June 2013.
As a result of the above goals and recommendations, the RFP scope of work would combine the RTA Special Needs Transportation (Handicar) services and Sun Shuttle (MV Transportation) services. For the optional ADA service, the RFP would require that the service provider follow the regional dial-a-ride policies and Sun Shuttle Dial-a-Ride brand. The RFP would consolidate three customer call numbers, including Oro Valley, into one call number for scheduling all Sun Shuttle Dial-a-Ride services. The RFP would also provide an option for establishing a brokerage system, where dial-a-ride services could be purchased and sold from an expanded network of providers such as non-profit social service agencies. As a separate action, the RTA staff would work with the Town of Oro Valley to draft an IGA amendment to extend the Sun Shuttle Dial-a-Ride transit services beyond June 2013. It is anticipated that this amendment would be presented to the RTA Board for approval in January 2013. Recommendation: Staff recommends that the RTA TPC Committee approve the Transit Working Group recommendations for expanding the optional ADA service area in two phases and combining the RTA Special Needs Transportation services (Handicar) and Sun Shuttle (MV Transportation) services into the upcoming transit service procurement, and subsequently pass along these recommendations to the Management Committee and RTA Board for further consideration. Attachments: Attachment A – Oro Valley Sun Shuttle Dial-a-Ride Ridership Attachment B – Optional ADA Service Expansion Map
Attachment A
4
Attachment B Optional ADA Service Expansion Map
5
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments 177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Transportation Planning Committee
Wednesday, September 5, 2012
Agenda Packet Memo
Subject: TIP Subcommittee Report
Background: The Transportation Improvement Program (TIP), prepared by Pima Association of Governments (PAG), is a five-year schedule and budget of proposed transportation improvements within Pima County. The TIP is typically updated annually through a multi-step process in association with PAG’s member jurisdictions and other implementing agencies. The TIP addresses improvements to diverse elements of the regional transportation system including national, state and local highways, transit, aviation, ride sharing, bikeways and pedestrian facilities. The TIP also responds to various state and federal regulatory requirements for development of a transportation improvement program. Discussion Points: The PAG TIP Subcommittee Chair or a Subcommittee representative will be available to report on the August 21, 2012 PAG TIP Subcommittee meeting, including:
• TIP Amendment #1
Amendment #1 to the FY 2013-2017 TIP includes the following items: Item A: A request from the Town of Marana to transfer the project sponsor for the Ina Road Bridge from Marana to ADOT. Both jurisdictions are amenable to this transfer. No change in funding is necessary at this time. Item B: A request from the City of Tucson to combine three projects into a single project. Funding from the Liberty Ave Safe Routes to School project and the Liberty Bike Blvd Design project would be transferred to the Liberty Bike Blvd project and renamed ‘‘Liberty Bike Blvd and Safe Routes to School.’’
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Item C: This item adds two new projects which have recently received a Safe Routes to School grant from ADOT. The Old Vail Middle School SRTS Project (sponsored by Pima County) and the Robison Elementary School Healthy Street project (sponsored by the City of Tucson) both received $400,000 from this grant source. Item D: A request from Tucson Transit to amend 15 transit projects to bring funding amounts in line with what is outlined in the respective project IGAs. There are also two new transit projects that are part of this item: Sun Tran Pima County Transit Services, and South Tucson Transit Services. Finally four projects have proposed name changes to more accurately reflect the project scope: Circulator Bus Service Name Change to: Sun Shuttle Base Transit
Services Paratransit System Expansion Name Change to: Transferred Special Needs
Transit Service Area Sun Shuttle / Ajo Transit Services
Name Change to: Sun Shuttle Expanded Transit Services
Van Tran / Paratransit Expansion
Name Change to: Sun Van / Paratransit Expansion
Item E: A request from ADOT to add $700,000 of 2.6% funding to the I-10: Prince to Ruthrauff project to cover unexpected expenses. Item F: A request from the City of Tucson to increase RTA funds on four projects: Fort Lowell / Campbell Intersection, Golf Links / Kolb Rd Intersection Improvements, Grant / Craycroft Intersection, and Speedway / Arcadia HAWK. Item G: A request from ADOT to move the I-10: Cortaro Rd to Ina Frontage Road into the reserve list, since the scope of this project is included in other fully-funded projects in that same area. In addition, ADOT requests additional 2.6% funding to two existing projects: State Route 77: Tangerine to Pinal County Line, and State Route 86: Valencia to Kinney. Item H: A request from PAG to correct an earlier error that had reduced funding levels for two programmatic line items (PAG Consultant Services, and Transportation Planning Program). Funding amount for these programs are normally $100,000 each, but had mistakenly been reduced to $80,000 each. The proposed changes will have no significant effect on the air quality conformity findings or fiscal constraint analysis of the TIP.
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Recommendation: The Committee is asked for its recommendation on Amendment #1 Items A through H to the FY 2013-2017 TIP. Attachment: Amendment #1 to the FY 2013-2017 TIP.
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
A 88.03 Ina Rd. Bridge over Santa Cruz
Ina @ Santa Cruz River
Replace bridge structure
AQ STATUS : EXEMPT Active
0.00
0
1000
1000
DC
16000 0
0
0
BR
PCFCD
0
0
0
6000
0
0
C
L=342
STP 8000
0
0
C
STP
2
2
0
0
0
0
0
0
6000
0
0
C
L=342
STP 8000
0
0
C
STP
Active
0
1000
1000
DC
BR
PCFCD
PROPOSED
SB413 03DMaranaProject
sponsor to
change from
Marana to
ADOT
Page 108/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
B 17.11 Liberty Ave. Safe Routes to School
12th Ave and Canada Street
Fill gaps in sidewalk and improve ped conditions
AQ STATUS : EXEMPT Active
0.75
400
0
0
DC
400 0
0
0
SRTS 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
0
0
0
PROPOSED
TucsonRemove
Funding
83.10 Liberty Bicycle Blvd.
44th St. to Los Reales Rd.
Safe Crossing Signals, Traffic Calming, Signage
AQ STATUS : EXEMPT Active
4.85
750
48
0
DC
798 0
0
0
TEA
RTA
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
750
85
400
DC
TEA
RTA
SRTS
PROPOSED
TucsonAdd Funding
and Change
Name
111.09 Liberty Bike Blvd Design
Los Reales to Cushing St.
Design bike boulevard
AQ STATUS : ANALYZED Active
7.00
37
0
0
D
62 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
0
0
0
PROPOSED
RTA-41cdTucsonRemove
funding.
Page 208/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
C 41.12 Old Vail Middle School SRTS Project
Mary Ann Cleveland Wy from Nona Ln to Driscoll
Mountain Rd
Construct shared use path and crosswalk
AQ STATUS : EXEMPT
0.00
0
0
0
400 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
400
0
0
SRTS
PROPOSED
Pima CountyAdd new
Project
40.12 Robison Elementary School Healthy
Street
Near Robison Elementary (Treat Ave and 18th
Street)
New HAWK, filling sidewalk gaps, ADA ramps,
AQ STATUS : EXEMPT
0.00
0
0
0
400 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
400
0
0
SRTS
PROPOSED
TucsonAdd new
project
Page 308/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
D 72.03 Administrative & Maintenance Facility
near Prince & Romero Dr.
Design & build new facility
AQ STATUS : EXEMPT Active
0.00
36
0
0
CO
55000 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
29
0
0
O
RTA 29
0
0
O
RTA 29
0
0
O
RTA 29
0
0
O
RTA
Active
1013
0
0
CO
RTA
PROPOSED
RTA-46f
ALI 11.43.03Tucson
Transit
Change
funding
amounts to
match IGA
72.06 Circulator Bus Service
Develop 3 new circulator systems, expand service
AQ STATUS : EXEMPT Financial
0.00
1194
0
0
5576 1194
0
0
RTA RTA 1194
0
0
RTA 1194
0
0
RTA 0
0
0
0
0
871
0
0
O
RTA 898
0
0
O
RTA 924
0
0
O
RTA 952
0
0
O
RTA
Financial
846
0
0
O
RTA
PROPOSED
RTA-48RTAChange
funding to
match IGA,
name
change
108.06 Houghton/Broadway, Houghton Old
Vail Park-and-Rides
Design and Construct 2 park and rides
AQ STATUS : EXEMPT Active
0.00
2788
0
0
C
3260 400
0
0
O
RTA RTA 30
0
0
O
RTA 30
0
0
O
RTA 0
0
0
0
0
752
0
0
CO
RTA 52
0
0
O
RTA 52
0
0
O
RTA 52
0
0
O
RTA
Active
600
0
0
C
RTA
PROPOSED
RTA-51eTucson
Transit
Change
funding
amounts to
match IGA
Page 408/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
D 13.11 Paratransit System Expansion
Operating funds for Expanded Transit Services
AQ STATUS : EXEMPT Active
0.00
250
190
0
O
500 0
0
0
5317
RTA
0
0
0
0
0
0
0
0
0
0
0
0
0
0
O
L=3679
0
0
0
O
L=3790
0
0
0
O
L=3903
0
0
0
O
L=4020
Active
250
190
0
O
L=3572
5317
RTA
PROPOSED
RTA-47e
11.80.00RTAChange RTA
funding to
match IGA,
name
change
97.06 RTA Special Needs Transit Expansion
Expand to include new areas
AQ STATUS : EXEMPT Active
0.00
1900
0
0
O
11500 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
1957
0
0
O
RTA 2016
0
0
O
RTA 2076
0
0
O
RTA 2138
0
0
O
RTA
Active
1900
0
0
O
RTA
PROPOSED
RTA-47bRTAChange
funding
amounts to
match IGA
43.12 South Tucson Transit Services
Providing transit services in South Tucson
AQ STATUS : EXEMPT
0.00
0
0
0
2692 0
0
0
0
0
0
0
0
0
0
0
0
0
0
522
0
0
O
RTA 538
0
0
O
RTA 554
0
0
O
RTA 571
0
0
O
RTA 507
0
0
O
RTA
PROPOSED
Tucson
Transit
Add new
project
Page 508/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
D 42.10 Sun Shuttle / Ajo Transit Services
Regionwide
Operating capital and maintenance for Sun
AQ STATUS : EXEMPT Active
0.00
1657
892
128
O
13142 1707
919
0
O
RTA
5311
5316
RTA
5311
1759
946
0
O
RTA
5311
1794
0
0
O
RTA 0
0
0
0
0
1702
919
0
O
RTA
5311
1753
946
0
O
RTA
5311
1805
0
0
O
RTA 1859
0
0
O
RTA
Active
1652
892
128
O
RTA
5311
5316
PROPOSED
RTA-48eRTAChange RTA
funding to
match IGA,
name
change
95.06 Sun Tran - Express Service
Expansion
Expand existing express routes and add new
AQ STATUS : ANALYZED Active
0.00
1387
0
0
O
11058 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
1339
0
0
O
RTA 1441
0
0
O
RTA 1484
0
0
O
RTA 1528
0
0
O
RTA
Active
1358
0
0
O
RTA
PROPOSED
RTA-49aTucson
Transit
Change
funding
amounts to
match IGA
93.06 Sun Tran - Frequency and Area
Expansion
Improve frequencies along major routes, extend
AQ STATUS : ANALYZED Active
0.00
10875
0
0
O
177480 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
1085
0
0
O
RTA 1117
0
0
O
RTA 1151
0
0
O
RTA 1185
0
0
O
RTA
Active
1053
0
0
O
RTA
PROPOSED
RTA-46aRTAChange
funding
amounts to
match IGA
Page 608/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
D 70.06 Sun Tran - Weekday Evening Service
Expansion
Expand weekday evening service along major
AQ STATUS : ANALYZED Active
0.00
3031
0
0
O
37717 13800
0
0
O
RTA RTA 13666
0
0
O
RTA 13647
0
0
O
RTA 0
0
0
0
0
2006
0
0
O
RTA 2067
0
0
O
RTA 2129
0
0
O
RTA 2192
0
0
O
RTA
Active
1948
0
0
O
RTA
PROPOSED
RTA-44Tucson
Transit
Change
funding
amounts to
match IGA
94.06 Sun Tran - Weekend Service
Expansion
Expand weekend service along major routes
AQ STATUS : ANALYZED Active
0.00
1210
0
0
O
19168 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
1024
0
0
O
RTA 1055
0
0
O
RTA 1086
0
0
O
RTA 1119
0
0
O
RTA
Active
994
0
0
O
RTA
PROPOSED
RTA-45Tucson
Transit
Change
funding
amounts to
match IGA
42.12 Sun Tran Pima County Transit
Services
Various locations
Replace service formally provided by Pima County
AQ STATUS : EXEMPT
0.00
0
0
0
15284 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
O
L=2965
0
0
0
O
L=3054
0
0
0
O
L=3146
0
0
0
O
L=3240
0
0
0
O
L=2879
PROPOSED
Tucson
Transit
New Project
Page 708/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
D128.08 Transit Regional Fare System and
Rebranding
Study and capital improvements
A study and capital for a semaless regional transit
AQ STATUS : EXEMPT Active
0.00
4000
0
0
C
8232 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
3900
0
0
C
RTA
PROPOSED
RTA-46dRTAChange
funding
amounts to
match IGA
71.06 Van Tran / Paratransit Expansion
Expand ADA paratransit services regionwide
AQ STATUS : EXEMPT Active
0.00
3100
0
0
O
2500 3400
0
0
O
RTA RTA 4100
0
0
O
RTA 4600
0
0
O
RTA 0
0
0
0
0
1110
0
0
O
RTA 1144
0
0
O
RTA 1178
0
0
O
RTA 1213
0
0
O
RTA
Active
1078
0
0
O
RTA
PROPOSED
RTA-47Tucson
Transit
Change RTA
funding to
match IGA,
name
change
75.06 Volunteer Transit
Volunteer service coordinated w/Council on Aging
AQ STATUS : EXEMPT Active
0.00
245
0
0
O
4900 245
0
0
O
RTA RTA 245
0
0
O
RTA 245
0
0
O
RTA 245
0
0
O
RTA
0
0
300
0
0
O
RTA 300
0
0
O
RTA 250
0
0
O
RTA 250
0
0
O
RTA
Active
300
0
0
O
RTA
PROPOSED
RTA-47dPCOAChange
funding
amounts to
match IGA
Page 808/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
E 94.02 I-10: Prince to Ruthrauff
Prince to Ruthrauff
Widen to 8 lanes
AQ STATUS : ANALYZED Previous
1.80
0
0
0
127000 0
0
0
0
0
0
0
0
0
0
0
0
6
8
0
0
0
0
0
0
0
0
0
0
0
0
Previous
700
0
0
2.6%
PROPOSED
H6241 01DADOTAdd funding
Page 908/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
F 3.07 Ft Lowell/Campbell Intersection
Intersection improvement
AQ STATUS : ANALYZED Previous
0.00
0
0
0
4997 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
39
0
0
C
RTA
PROPOSED
RTA-36cTucsonAdd Funding
4.01 Golf Links/Kolb Rd. Intersection
Improvement
@Intersection
Reconstruct intersection
AQ STATUS : ANALYZED Active
0.00
20
0
0
C
4500 0
0
0
RTA 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
178
0
0
C
RTA
PROPOSED
RTA-36baTucsonAdd funding
1.07 Grant/Craycroft Intersection
Intersection improvement
AQ STATUS : EXEMPT Previous
0.00
0
0
0
7772 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
200
0
0
C
RTA
PROPOSED
RTA-36aTucsonAdd Funding
Page 1008/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
F 15.10 Speedway/Arcadia HAWK
@Intersection
Construct HAWK signal
AQ STATUS : EXEMPT Previous
0.00
0
0
0
150 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Active
49
0
0
C
RTA
PROPOSED
RTA-37anTucsonAdd Funding
Page 1108/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
G 10.11 I-10: Cortaro Rd to Ina Frontage
Roads
Ina to Cortaro
Reconstruct & widen frontage rds. to 40'
AQ STATUS : EXEMPT Active
1.00
5000
0
0
C
5000 0
0
0
2.6% 0
0
0
0
0
0
0
0
0
2
2
0
0
0
0
0
0
0
0
0
0
0
0
Reserve
0
0
0
PROPOSED
ADOTMoving to
reserve
11.02 SR 77: Tangerine to Pinal Co. Line
Tangerine to Pinal Co. Line
Widen to 6 lanes
AQ STATUS : ANALYZED Active
5.80
0
0
0
36500 32977
0
0
C
ASTP 0
0
0
0
0
0
0
0
0
4
6
32977
0
0
C
ASTP 0
0
0
0
0
0
0
0
0
Active
0
2000
0
C
2.6%
PROPOSED
ADOTAdd funding
2.02 SR 86: Valencia to Kinney
MP 159.5 to MP 166.1
Widen to 6 lanes
AQ STATUS : ANALYZED Active
6.60
1540
43460
0
C
57167 0
0
0
2.6%
ASTP
0
0
0
0
0
0
0
0
0
2
6
0
0
0
0
0
0
0
0
0
0
0
0
Active
3540
43460
0
C
2.6%
ASTP
PROPOSED
H713701CADOTAdd funding
Page 1208/22/2012
TIP
ID
Existing Lanes
After Lanes
STREET/PROJECT NAME
TERMINI
PROJECT DESCRIPTION
AIR QUALITY STATUS
TOTAL
PROJECT
COST
(000's) 2013 2014 2015 2016
PROPOSED FUNDING
(IN THOUSANDS OF DOLLARS)
FISCAL YEAR
2017
PAG 2013 - 2017 TIP PROJECTS
TIP STATUS
LENGTH (Mi.)
Sponsor ID
State/Fed ID
Sponsor
TIP Amendment #1 - Proposed
Amendment
action
H 85.01 PAG Consultant Services
Misc studies & consultant activities
AQ STATUS : EXEMPT Active
0.00
200
80
0
Study
2575 200
100
0
Study
STP
12.6%
STP
12.6%
200
100
0
Study
STP
12.6%
200
100
0
Study
STP
12.6%
200
100
0
Study
STP
12.6%
0
0
200
100
0
Study
STP
12.6%
200
100
0
Study
STP
12.6%
200
100
0
Study
STP
12.6%
200
100
0
Study
STP
12.6%
Active
200
100
0
Study
STP
12.6%
PROPOSED
OWP-PAGIncrease
funding
659.00 Transportation Planning Program
Operations and Contingency
AQ STATUS : EXEMPT Active
0.00
2000
80
0
Study
9408 2000
100
0
Study
STP
12.6%
STP
12.6%
2000
100
0
Study
STP
12.6%
2000
100
0
Study
STP
12.6%
2000
100
0
Study
STP
12.6%
0
0
2000
100
0
Study
STP
12.6%
2000
100
0
Study
STP
12.6%
2000
100
0
Study
STP
12.6%
2000
100
0
Study
STP
12.6%
Active
2000
100
0
Study
STP
12.6%
PROPOSED
OWP-PAGIncrease
Funding
Page 1308/22/2012
177 N. Church Avenue, Suite 405, Tucson AZ 85701
Phone: (520) 770-9410 Fax: (520) 620-6981
RTAmobility.com
Transportation Planning Committee Wednesday, September 5, 2012
Agenda Packet Memo
RTA Report
Report on the RTA Board: The RTA Board meets on Sept. 27, 2012. At that meeting the RTA Board will consider the following actions/presentations:
• Jurisdictional Project Updates
• Request for increased funding for SR-86
• Small Business Enterprise (SBE) Goals
• RTA Categorical Funding Reallocation
The RTA Board last met in Executive Session on Aug. 21, 2012. Prior to that meeting, the regular meeting was held on June 14th, at which time the following actions were taken:
• 13 Intergovernmental Agreements or amendments were approved
• The FY 2013 Budget was approved
• A HAWK signal was approved for La Cholla Blvd. at Ocelot Road
• The request to increase funding for the SR-77 Wildlife Crossing was referred back to the Wildlife Linkages Working Group
• A presentation was made on the RTA Project and Program Statutory Process by the RTA Legal Counsel
Jurisdictional Project Updates:
The RTA Jurisdictional Progress Reports are attached.
Request for increased funding for SR-86 Wildlife Crossings: The SR- 86 Wildlife Crossing Structures proposal was approved by the RTA Board in October 2011 and the IGA with ADOT was approved in April 2012. The original concept identified two under crossings, at an estimated cost of $746,280 to help restore wildlife connectivity in the Kitt Peak area, and reduce the accident rate due to wildlife collisions in the area. The project has been designed, and the current cost estimate is now $1,189,580, an increase of $433,300, an increase of over 58%. The increase is due, in part to the cost of detours that had
2
not been addressed in the original cost estimate. Other costs increases are due to increased structure costs, as quoted by the manufacturer. Recommendation / Action Item: The RTA Wildlife Linkage Committee is requesting an amendment to the current IGA to do the following:
1. Increase the amount of RTA funding from $746,280 to $899,600, with ADOT committing to fund the remaining shortfall.
2. Cancel the SR 86, Kinney to T.O. Nation Wildlife study, releasing $79,000 programmed for the study, but not pursued by ADOT.
Small Business Enterprise (SBE) Goals
The RTA Board tabled a proposed limitation on SBE goals at the Jan. 26th meeting in order to allow staff from the City to work with the RTA staff, and representatives of the contractors and subcontractors associations on process changes within the framework of the existing City SBE Ordinance that would result in SBE goals all parties could support. The RTA Board agreed to support SBE goals for short term projects that had consensus support from the involved parties. Since January, the team has modified the way SBE Goals have been set, and have established a review process that involves the RTA, Subcontractors Associations and the Tucson Utility Contractors Association. SBE Goals have been established for the following projects, by consensus: 22nd /Kino Intersection: 19% Grant Road/Oracle Intersection: 14% St Marys (Downtown Links) 18% Houghton Road, Irvington-Valencia 19% The RTA-SBE Goal Setting Procedures summary is attached. Staff anticipates recommending the continuation of the committee review of SBE Goals on future RTA projects. Request for Categorical Funding Change RTA Staff has worked with the Jurisdictions to identify funding that could be released on projects that are now completed, and to make the released funding available to be reallocated. The jurisdictions have indentified approximately $3,300,000 of Intersection Safety and Capacity (RTA #36) project funding, $900,000 of Elderly and Pedestrian Safety Improvement Funding (RTA #37), $225,000 of Signal Technology Upgrade Funding (RTA #40) and $2,700,000 of Greenway, Pathways, Bikeways and Sidewalks funding (RTA #41) that can be released from completed projects and made available for reprogramming. A call for projects has announced for the amounts above, subject to RTA Board approval.
3
RTA Project Update (Construction, billings and IGAs):
To date, a total of 484 individual projects or service upgrades have been completed, including six Roadway Element projects. Another 22 projects are under construction, including 5 Roadway Element projects (2 more are mobilizing). The RTA has expended $435.2 million on project expenses thru July 31, 2012. The RTA collected $398.9 million in excise taxes over the same period. The RTA fund balance was $148.1 million on July. 31, 2012. Attachments:
Jurisdiction Status Reports
RTA-SBE Goal Setting Procedures
Received Aug 6, 2012 MONTHLY REPORT - City of Tucson
Roadway Improvement Element
22nd St: I-10 to Tucson Blvd SR5A 19a 1, 5
J. Cuaron/F
Felix
Planning
&Design 80% 4/08 6/09
Ph II:
7/2012 12/2012 09/2013 03/2014 03/2014 2017 2015 0% 12/18 TBD
Planning on hold for I-10 to Park which includes roadway alignment selection and corridor plan. The Citizen Oversight Committee has been dissolved. Section of 22nd St between Kino Parkway and Tucson Blvd
under design.Kick-off meeting for design of 22nd St between Kino Parkway and Tucson Blvd held 6/28/12.
22nd Street/Kino Interchange 19b 1, 5
J. Cuaron/F
Felix Design 100% 1/07 6/08 7/08 10/2009 04/2010 11/2010 3/2011 2010 07/2012 0% 12/2013
The
Ashton
Co.
The Ashton Co. is the low bidder. NTP 7/9/12. Actual construction to begin 8/2012. Contractor's project schedule indicates 2 years to complete.
Broadway: Euclid to Country Club SR3A 17 5, 6 J. Burdick Planning 10% 09/10 12/2013 01/2014 08/2015 08/2016 0% TBD TBD Planning & Design phase underway. Citizens Task Force convening on a monthly (approximately) basis - next meeting scheduled for August 30, 2012.
Downtown Links, 8th Street Drainage S30N 16a 1, 6 Tom Fisher Const 100% 12/06 7/08 8/08 09/2009 09/2011 01/2011 06/2011 TBD 10/2011 100%
Borderlan
d
Downtown Links, St. Mary's Road S30N 16a 1, 6 Tom Fisher Design 100% 12/06 7/08 8/08 09/2009 09/2011 01/2011 10/2011 TBD 0% TBD
Finalizing bid package for June bid opening. Waiting for Tucson Water sign-off. Went out to bid in late June.
Downtown Links, 6th Street to Broadway S30N 16a 1, 6 Tom Fisher Design 30% 12/06 7/08 8/08 09/2009 on hold on hold on hold TBD 0% TBD
This project is divided into 4 phases: Phases III and IV design is at 30% and on hold awaiting RTA funding. The Downtown Links Urban Overlay District (DLUOD) is in progress. A formal rezoning application was
submitted to DSD by the end of March and will go to public hearing in September. RTA Value Analysis completed in Feb. and recommendations included in design proposal estimate. Recieved RTA funding for
design in late June and will re-initiate process in late July with consultant and CAC. Held a few meetings with interest groups to discuss next steps.
Grant: Oracle to Swan Land Use Planning SR2A-C 18 2, 3, 6 M. Holder Plan'g 95% 10/06 01/2013 8/09 09/2010 N/A N/A N/A N/A
Grant/Oracle Intersection Project was issued NTP for design and construction. Appears as separate RTA reporting element now. 30% design and DCR for GRIP project from Oracle to Swan was submitted for review
by City at end of July and is complete. Beginning development of Community Character and Vitality Plan, which involves development of design guidelines, and overlay zone, and amendment of 7 area and
neighborhood plans to revitalize and reuse remnant properties, and to help realize the community's future vision for land use on Grant road. We have begun a land use outreach effort to build support and identify
specific changes and language will occur through 2011. Plan and overlay zone will be brought to City of Tucson Planning Commission and then Mayor and Council for Adoption. It is anticipated that this planning
effort will reduce R/W acquisition costs over the life of the project. Scheduling for Area and Neighborhood Plan Amendment public meetings ongoing & mtgs. are anticipated to start in Nov. after study session
briefings of Planning Commission & M & C. Reviewing proposed contract mod. Mtgs. w/ affected NH mtgs. to start week of Oct. 17. Initial meetings w/NH's almost complete. Ward 3 & 6 Community Conversation
Mtgs. complete. Urban Overlay District UOD start to be approved by M&C Dec. 20, 2011. Contract Mod. No. 9 approved. Scheduling of three GRD Zoning Workshops established West - Feb. 6, Central - Feb. 8,
East - Feb. 9. Six meetings with neighborhoods with affected area & N.H. plans are scheduled between Feb. 29 and April 12, to explain proposed amendments to the ANP's necessary to accomodate the proposed
Urban Overlay District (UOD). 3-3-12 mtg. called by wards 3 & 6. Follow up mtg. scheduled 6-21-12. Contract Mod. 10 being reviewed to finalize the next draft of the UOD along with some stakeholder outreach.
Assistant CM Quigley requested a hold be placed on the contract work until he could schedule mtgs. w/the two CM's and the RTA.
Grant/Oracle Intersection SR2AR1 3 T. Weideman Construct 1% 03/2010 12/2010 03/2010 11/2010 03/2011 04/2011 12/2011 03/2010 03/2012 07/2012 1% N/A Falcone8/3/12 - Temporary signals up at iintersection. East / west bound t.raffic shifted to the north. Grant Road medians removed. Pavement removal south side underway.
Houghton and MAC Way Intersection SR1A 32a 4 M. Dillard Complete 100% Project Completed
Houghton, Irvington(inclusive) to Valencia (inclusive)SR1A,
SR1B
32b,32
c 4 M. Dillard Design 100% ADOT 10/04 4/09 9/08 8/09 4/10 3/12 11/2012 02/2012 06/2012
Bids cancelled, new bid package should be out May 2012
Houghton, Broadway(incluseive) to 22nd St.
(inclusive) SR1C 32c 2 M. Dillard Design 95% ADOT 10/12 5/09 5/09 3/10 12/11 6/12 11/12
Right of Way Acquisition in progress, Will be adding the segment from Broadway to 22nd St. (inclusive) for economy of scaled with a CMAR contract
Houghton Rd. bridge over the UPRR replacement SR1D 32e 4
PC DOT/A.
McGovern Planning 30% 06/09 12/10 6/09 12/10 2015 TBD
This project is being managed by Pima County DOT. Design at 30% stage. Environmental clearance soon to be approved. Negotiating final design and scope of work.
Houghton Rd. bridge over UPRR to I-10 SR1A 32a 4 M. Dillard Design 25% ADOT 10/04 8/11 2/12 2015 TBD 15% design complete. Performing environmental clearance work.
Val. (exclusive) to MAC Way (exclusive) SR1A 32a 4 M. Dillard Design 30% ADOT 10/04 11/06 8/08 TBD TBD Period 3 project
Escalante (exclusive) to Irvington (exclusive) SR1B 32b 4 M. Dillard Design 30% ADOT 10/04 11/06 9/08 TBD TBD Period 3 project
22nd (exclusive) to Escalante (inclusive) SR1B 32b M. Dillard Design 30% ADOT 10/04 11/06 9/08 TBD TBD Period 3 project
Tanque Verde (inclusive) to Speedway (exclusive) SR1C 32c M. Dillard Design 30% ADOT 10/04 11/06 05/2009 TBD TBD Period 3 project
Kolb Rd Extension SR8A 26 2 J. Cuaron Design 30% 5/09 9/09 2011
Phase IIB, Kolb Road Extension South is nearing 75% design, and the environmental process is underway with the draft EA expected in December 2012. Phase 1, Sabino Canyon & Tanque Verde intersection is
under construction, and expected to be completed by late summer.
Silverbell, Ina to Grant SR6A 5 1 J. Cuaron Planning 90% 05/09 6/12 1/11 07/2011 07/2014
$4M of RTA funds was approved by IGA amendment in February 2012. Project archaeologists are working with Army Corps of Engineers to develop the archeaological recovery plan. Contract awarded for the
design of Goret to Grant segment.
Speedway, Camino Seco to Houghton SR4A 28 2 F. Felix Const 75% PCDOT 12/02 10/06 9/08 6/09 6/10 7/10 11/10 09/2010 94% 06/2012 NAC Speedway, between Camino Seco and Harrison is complete. Contractor working on punch list items. Landscape establishment to begin summer 2012.
Safety Element
Golf Links/Kolb Intersect. SM05 36 F. Felix Constr 100% 12/10 04/2011 50% 09/2011
NAC
Construct
ion
Complete.
Irvington /Harrison SG11 C. Saltzman
Speedway/6th Ave. Intersection
Starr Pass/Mission Intersection SN04 36d 1 J. Donofrio Art 5% 7/07 12/07
5/08
10/09
(75%
resubmitt
al)
4/09 1/10
(90%
resubmitt
al) 4/10 n/a n/a 8/10 100% 6/11
Borderlan
d
Construction Complete. Artist contracting in process.
Intersection Improv RTA FY 09 SN09 41ax
Grant/Rosemont N001 41ax 2, 6 C. Saltzman Const 100% 8/09 01/10 04/10 4/11 100% 6/11
West
Point
Complete.
Oracle/Auto Mall N002 41ax 3 C. Saltzman Const 100% 5/09 05/2010 6/13/11 0% 8/1/11 Granite Complete.
Tanque Verde/Pima N004 41ax 2, 6 C. Saltzman Design 60% 8/09 1/11 3/11 6/11 TBD 0% TBD TBD Design underway. Will need add'l RTA funds to complete construction.
Camino Seco/Wrightstown Intersection Improvements SM04 36ab F. Felix Design 100% 07/2011 10/2011 02/2012 n/a n/a 10/2012 TBD TBD
Design is 100% complete. Utility companies clearing for construction. Construction expected this fall 2012.
ADA Bus Stop Accessibility Projects ($150k) S111 37k CW T. Fisher Const 70% 1/08
no design
needed n/a n/a 03/2010 65% TBDTDOT
Streets
Remaining funding to be used as local match for FTA grants. TDOT Streets has completed 103 ADA bus stop improvements to date. Working on select stops throughout the city where ADA improvements have been
requested. Currently working with FTA on-call JOC to continue work on bus stop improvements. Additional projects were scoped and packaged in May. Processing PO in June. Contract for 12 additional concrete
pads has been awarded. 9 of 12 completed to date. Planning the next set of improvements for citywide locations.
PELICAN - La Paloma AcademySH08-
H005 37y C. Saltzman Design 50% 12/10 2/11Environmental clearance received. In final design.
HAWK - La Cholla Blvd/Merlin St 37 ak
Project status through August 1st, 2012Start ContractorPoss'n
100%
Acq'dDate Mobil-
ized
% Contr.
Compl Date Compl
75%
Plans
90%
Plans PS&E End30% PlansStartEnd
Right-of-WayPlanning Construction
Intersection Safety and Capacity Improvements
%
Phase
ComplProject Name CIP #
Elderly & Pedestrian Improvements
Design
Project
Manager
Curr.
PhaseRTA # Wd #
HAWK - La Cholla / Ocelot 31am 1 M. Holder Design 5% 7/12 n/a n/aStantec is the designer. Due date is 1/26/2012.
HAWK - Park Ave/33rd St 37 ak
HAWK- - Speedway/10th Ave 37 al
HAWK - Stone Ave/King Rd 37 ak
HAWK - Swan/3rd StSH08-
H019 37y C. Saltzman Const 75% 1/09 3/09 8/09 5/11 7/11 TBD 0% TBD TBD
Initial construction completed, but changes are being considered due to minor operational problems.
HAWK- 22nd/Lakeshore Lane 31 am
Signal Technology
Transit Corridor Bus Pullouts
Bus Pullouts Package 4SB04 38d
1, 3,
5, 6 See below See below
5th St. / Alvernon (SB) T. Weideman R/W 100% 3/09 5/09 8/09 10/09 12/09 yes TBD 0% TBD TBD 4/12 - RTA funding approved. 6/6/12 - Tep relocated. 7/5/12 - putting JOC contract together. Qwest to relocate utility pedestal. Anticipate contractor on board September.
Bus Pullouts Package 5 SB05 38i 1,3,4 Holder
Craycroft / 29th (NB) Const 0% n/a n/a 9/09 11/09 02/10 6/10 8/10 3/12 5/12 6/12 KAZ
Mylars signed & is in R/W appraisal phase. (Tierra) Right of Entry due approx. 5-31-11. Still awaiting signatures. Quik Mart closed. Auto repair shop non responsive. Administrative Settlement to be submitted week
of Nov. 7. Condemnation Notice issued. Revised Admin. Settlement pending City approval. Received the right-of-entry to proceed with construction, however, JOC contracts are being re-bid so construction may
not start until May or June. R/W acquired. Bids due in May. N/P 6/25/12. Project is under construction.
29th / Craycroft (EB) Const 0% n/a n/a 9/09 11/09 02/10 6/10 8/10 3/12 5/12 6/12 KAZ
Mylars signed & is in R/W appraisal phase. (Tierra) Right of Entry due approx. 5-31-11. Still awaiting signatures. Diamond Shamrock still in negotiations regarding their sign. Auto repair and convienence store on
NE corner have signed. Diamond Shamrock on SW corner in verbal agreement, awaiting signatures. R/W acquired. Bids due in May. N/P 6/25/12. Project is under construction.
Environmental & Economic Vitality Element
Greenways, Pathways, Bikeways and Sidewalks
Bikeways
RTA Bicycle Lane Restriping Package 2 49B2 41am D. Swartz Const 0% 1/09 6/09 1/10 11/09 0%
Bid opening 3/1/12. Amendment sent out on 2/29/12. New bid date 3/8/12.
RTA Bike Package 3 McGovern
Plan'g and
Const
Design and construction of misc. bikeway projects. Improvements at Congress/I-10, Camino Del Cerro/Urban Loop already complete.
Liberty Ave Bike Blvd 41 by McGovern Plan'g 15%
Design underway. Kittleson awarded contract to handle design and project assessment.
University/Third St Bike Blvd 41 cc McGovern Plan'g 30%
Preliminary Planning underway. Held openhouse. Revising plan. Some minor improvements underway
Sidewalks
Fort Lowell Sidewalk Package
Pathways and Greenways
El Paso & Southwestern Greenway SP01 41af 1, 3, 6 McGovern Plan'g 90% 7/08 10/09 10/09 4/10 1/11 0% TBD TBDPhase 2, master plan being finalized. Proceeding with design of TE segment - Simpson Street to 22nd Street, as well as acquisition of key rights-of-way. Kick off meeting in April 2012 for the TE segment design.
Transit Element
Bus Frequency & Area Expansion
Bus Frequency (PLUGS) K. Riley Op'g n/a n/a n/a 6/07 n/a n/a n/a n/a Annual n/a Plugs are well used and appreciated by passengers and employees.
Sun Tran Bus Storage & Maintenance Facility- Phase
3MRC2/AR
RA 3 T. Fisher Constr 99% 8/09 12/09 02/2010 1/96 07/2010 99%
DL
Withers
Project is mostly funded with $16.022 million in FTA Stimulus grant funds. Bid openings were July 14th. Contract awarded to DL Withers began construction on September 7th. PCCP parking deck for 100 buses is
complete. Project is complete. Walk-through inspections and close-out in progress. A few minor things to fix. FTA PMOC continues to receive regular updates. Grand opening held January 26th. Currently working
on close-out process with PMOC, contractor, and design consultant. Estimated completion in mid June, except for Runway Drive improvements. Meeting with FTA PMOC in late April. A few more items to provide.
One remaining Change Order (#13). Met with FTA PMOC in late July to wrap up audit and reporting.
Seamless Fare System MRC9 Sun Tran
Work on the ePay website by HS2 continues and is slightly ahead of schedule. Sun Tran is pleased with the work product being delivered.
System Integration Testing of the complete system is scheduled for August 20 through September 7, 2012 in Chicago. Upon successful completion of all testing, remaining equipment will be delivered to Sun Tran.
Instructor Guides and Student Material are being delivered to Sun Tran to prepare for mandatory training on all the components of the system. Sun Tran’s Training Director is preparing a schedule to coordinate all
the training activities.
SRFS/Rebranding MRC8 Sun Tran
Sun Tran staff has been working with COT procurement and GFI to finalize outstanding issues and contract amendment including the ePay web site and master schedule the week of June 4. GFI recommended the
web design firm of HS2 to perform work specified in the ePay Web Application Requirements Specification document. HS2 will begin work the week of June 4, 2012.
Weekend Bus Service Expansion
Transit Weekend Extended Service
Phase III - Supportive Service
M406/M59
0/M724/M
890/M930 K. Riley Op'g n/a n/a n/a 6/08 n/a n/a 8/08 n/a Annual n/a
Ridership is high on these much needed services.
Expansion
Transit Weekday Express Service
New Enh'd Expr's - OV, GV, OV Raytheon & Rita
RanchMRB1 /
M163 K. Riley Plan'g n/a n/a n/a 6/08 n/a n/a 2/09 n/a Annual n/aRidership for the expresses is strong and the service continues to be popular .
Downtown/University high-capacity transit (streetcar)
Downtown Streetcar
MRC3 /
M158 /
M258 50 1, 6 S. Ginn
Constructi
on 22% 12/07 8/08 12/2010 02/2011 09/2011 12/2011 08/2011 22% 07/13
Old
Pueblo
Trackwor
ks
Line Segment bid package was released October 27 2011. Pre-bid Conference was 11/8/11. Bid Opening was January 17, 2012. The low bidder is Old Pueblo Trackworks. An NTP was issues March 20, 2012.
Construction began in early April 2012. A ground-breaking event occurred April , 2012. The MSF Bid Opening was March 27, 2012. NTP was givenApril 30, 2012. The City of Tucson was awarded $63 million in
TIGER funds on February 18, 2010. Grant Agreement was signed December 27, 2010. COT and RTA signed IGA for $45 in May 2010 and latest amendment in January 2012. EA Supplemental FONSI was
issued January 25, 2011. Draft Finance Plan was submitted December 2, 2010 and approved by FTA as part of Grant Agreement. Water package began in December 2010. Specialty track and TPSS have been
awarded (july 2011) with specialty track now arriving and first TPSS due to arrive in September 2012. Cushing Street Bridge project started construction in June 2011 and completed in July 2012. Next Quarterly
Report with FTA will be in September 2012. Next OIW Progress Report takes place in Oregon on 9/11/12. Construction currently on Congress Street (Church to Toole), 4th Avenue (University Blvd. to 6th Street),
University Blvd. (Bean to Park) and 2nd Street (Park to Warren Ave.). The Warren Avenue Underpass began construction in early July 2012.
Park and Ride Facilities
Broadway & Houghton MRC1 51e 2 T. Fisher Design 100% 6/07 12/08 10/09 02/2010 06/2010 11/2010 06/2011 3/09 Y 0% 06/2012 TBD
Design is 100% complete. Shared access easements with adjacent property owners approved and completed. Pima County approved sewer easements and last cut-sheet being revised for full plan set. Will go to bid
in 2012 pending intersection project readiness. Getting bid package ready.
Houghton/Old Vail (Rita Ranch) MRC4 51e 4 T. Fisher ROW 50% 6/07 3/08 4/08 9/08 10/08 2/09 N
temp
facility
100%
complete 0% 01/2011 TBD
The temporary Park & Ride (at 10000 E. Old Vail) was completed in Feb 2009 and is in operation. Facility being maintained by Streets. Old Vail Partners have delayed their development project which includes the
permanent facility. Temporary right of entry was renewed in June for one more year. No new communications with the developer since January. Contacted developer in late Feburary. No major change but
commercial development may break ground later in the year. Thelft issues at temporary facility. Reasearched other locations and developed proposal for City and RTA review.
Future Projects
Completed ProjectsRoadway Improvement Element
MAC Way Intersection SR1A 32a 4 Gutierrez Const 100% 10/04 11/06 8/08 11/08 3/09 6/09 6/09 100% 6/10 Construction complete
Safety Element
Country Club/Pima SG04 B. Hunt Complete 100% N/A 06/07 Project completed.
Nogales/Drexel SG05 B. Hunt Complete 100% N/A 06/07 Project completed.
Old Vail/Valencia SG06 B. Hunt Complete 100% N/A 06/07 Project completed
Rita/Old Vail SG07 B. Hunt Complete 100% N/A 06/07 Project completed.
Fire Station 17 Flasher SG08 Saltzman Complete 100% as-built plans completion 6/08 1 01/09 Project completed.
Sixth/Euclid SG02 B. Hunt Complete 100% N/A 03/07 Project completed.
Starr Pass/La Cholla SG01 36f 1 B. Hunt Complete 100% 11/07 100% 2/08 P.A.C.E. Project completed.
Stone/Glenn SG03 B. Hunt Complete 100% N/A 6/07 Project completed.
Wilmot/Park Place Inter. SN05 36e 6 Gutierrez Complete 100% 11/07 1/08 3/08 10/08 2/09 1/09 6/09 7/09 100% 11/09 Project completed.
Golf Links/Wilmot Intersection SN02 36b 4 Fred Felix Complete 100% 3/07 12/07 5/08 9/09 12/2009 n/a n/a 5/03 100% 09/10 SAP Project completed.
Intersection Improv RTA FY 09 SN09 41ax
St. Mary's/Silverbell N003 41ax 1 Saltzman Complete 100% 6/09 TBD 0% TBD Project completed.
Wilmot/Nicaragua N005 41ax F. Felix Constr 100% 7/09 09/09 12/09 5/10 9/10 n/a n/a 11/10 100% 12/2010 SAP
Construction start 11/8/10. TEP coordination to de-energize overhead lines and unusually cold temperatures caused some delay. Made modifications to signal design to address left turns. Substantial completion
12/21/2010. Construction accepted 03/01/2011.
Ft Lowell/Campbell Intersect. SN03 36c 3 M. Skilsky Constr 100% 5/07 9/08 4/09 12/09 4/10 5/10 100% 3/11
Falcone
Bros
Complete.
Wilmot/Nicaragua N005 41ax F. Felix Constr 100% 7/09 09/09 12/09 5/10 9/10 n/a n/a 11/10 100% 12/2010 SAP Complete.
Grant/Craycroft Intersect. SN01 36a 2, 6
F. Reyes
F. Felix
Design
Constr
100%
60% 10/07 4/085/07
(started) 1/09 100% 12/09
NAC
Construct
ion
Complete.
Elderly & Pedestrian Improvements
HAWK - Broadway/Sarnoff SH05 B. Hunt Complete 100% N/A Project completed.
HAWK - Euclid/Lester SH04 B. Hunt Complete 100% N/AProject completed.
HAWK - Santa Clara/Drexel SH03 B. Hunt Complete 100% N/A 6/07 Project completed.
HAWK - 6th St/WilsonSH08-
H006 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - 12th Ave/Calle AlvordSH08-
H007 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Alvernon & FlowerSH08-
H008 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Cmo Seco & KenyonSH08-
H009 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - C. Club/SilverSH08-
H010 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Desert Sky (Rita/Esmond Lp/Rankin)
SH08-
H001 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Drexel & Del MoralSH08-
H011 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Drexel/LibertySH08-
H012 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Escalante & PrudenceSH08-
H013 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Euclid/9thSH08-
H003 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Grande & St. Clair StreetSH08-
H015 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - OST/29th StSH08-
H016 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - OST/KenyonSH08-
H017 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Pima/SahuaraSH08-
H014 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Swan/17th StSH08-
H002 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - Wrightstown/Ftn ParkSH08-
H004 Saltzman Complete 100% as-built plans complete 6/08 100% 1/09 PACEConstruction complete. As-Built Plans complete
HAWK - So. 6th Ave/14th St SH07 37a 5 Saltzman Complete 100% 9/07 5/08 as-built plans complete 11/08 100% 3/09 PACE Construction complete. As-Built Plans complete
Church & Franklin Island Modification SY03 41at T. Weideman Complete 100% 5/09 11/09 n/a n/a 01/05/10 100% 01/15/10 K and BConstruction complete
HAWK - So. Stone/Cushing SH06 37b 5 Saltzman Complete 100% 9/07 5/08 as-built plans complete 11/08 100% 3/09 PACE Construction complete. As-Built Plans complete
Video Detection Cameras SG09 36aj P. Burton Complete 100% 03/2009 100% 02/2010 in-house
Camera systems installed and operational at all 30 specified locations .
ADA Accessibility Projects ($238k) SE01 37l CW J. Chase Complete 100% 1/08 3/09 03/2009 90% 04/2010 Varies Complete.
Sam Hughes Safe Routes to School SH14 37m Z. Canchola Complete 100% 08/2009 5/10 N/A 7/10 Complete.
HAWK - Speedway/Arcadia SH22 37an 6 D. Swartz Const 100% 2/11 4/11 4/11 7/11 12/11 Pace Complete.
HAWK - Starr Pass & Santa Cruz LaneSH08-
H018 37y 1 M. Skilsky Const 100% 10/09 1/10 4/10 100% 5/11 Borderland
Construction complete.
Signal Technology
i2 Maintenance Contract 490H 40e CW Annual 100% Annual contract - $23K per year. FY 2009 complete.
Intersection Safety and Capacity Improvements
Complete
U of A Atlas Study SC03 40c CW F. Leyva
Equip
Purch'd N/A N/A TBD
Processing payment. RHODES program is operational.
UPS/LED (30 intersections) 490E 40a CW P. Burton Complete 100% N/A N/A 1/08 01/2010 30 intersections fully operational.
Pre-emption & Transit Priority SC02 B. Hunt Complete 100% N/A 6/07 Project completed.
Transit Corridor Bus Pullouts
Bus Pullouts Package 1 SB01 38b CW J. Chase See below
Broadway and Alvernon, WB Complete 100% 7/07 3/09 5/09 12/09 n/a n/a 4/10 100% 09/10
So. AZ
Pav'g
Complete.
Country Club and Kleindale, NB & SB Complete 100% 11/07 n/a n/a 11/07 100% 2/08 in-house
Grant and Alvernon, NB Complete 100% 6/08 8/08 0% 10/08
Irvington and Campbell, WB & SB Complete 100% n/a n/a 6/08 100% 8/08
So. AZ
Pav'g
Oracle Rd. and Glenn St., NB Complete 100% 10/08 4/09 0% 6/09
So. AZ
Pav'g
Bus Pullouts Package 2SB02 38c 3, 5, 6 Saltzman See below
Ajo Way at Park Ave, EB Complete 100% 11/08 11/08 100% 3/09
NAC
Const. Construction Complete.
Oracle and Grant, NB Dropped N/A 1/07 None None 0% None None Location dropped. Replaced with Stone and Yavapai.
Oracle and Grant, SB Complete 100% 11/08 100% 10/09
West
Point
Construction Complete.
Speedway and 6th Ave., EB Complete 100% 11/08 11/08 100% 11/09
NAC
Const.
Construction Complete.
Stone and Yavapai, SB Complete 100% 11/08 11/08 100% 02/10
West
PointConstruction Complete.
Bus Pullouts Package 3SB03 38d
1, 3,
5, 6 F. Felix See below
Country Club & Broadway, NB Complete 100% Fall 2008 4/09 99% 7/09
West
Point
Complete.
Ft. Lowell & Dodge, EB Complete 100% n/a n/a
Winter
2008 100% 3/09
West
Point
Complete.
Irvington and Park, WB Complete 100% n/a n/a 11/08 100% 12/08
West
Point
Complete.
Old Nog Hwy & Los Reales, WB Dropped --- Location dropped. Casino added bus pullout themselves.
Bus Pullouts Package 4SB04 38d
1, 3,
5, 6 See below See below
6th St/Campbell (WB) J. Chase Complete 100% 12/08 1/09 4/09 5/09 07/09 09/09 08/09
24th St / C. Club (SB) (NAME CHANGE) J. Gutierrez Bid 100% 5/09 7/09 8/09 05/10 10/10 n/a n/a 01/2011 0% TBD KE&G Project complete.
6th St/Highland (WB) M. Skilsky Constr 5% 5/09 8/09 1/10 4/10 6/10 7/10
West
Point
Project complete.
6th St/Euclid (NB) F. Reyes Constr 100% 12/08 2/09 4/09 6/09 Core Project completed 12/10.
Bus Pullouts Package 5 SB05 38i 1,3,4 Holder
Congress / El Rio Health Center (WB) Const 100% n/a n/a 9/09 10/9 10/10 12/9 7/10 40400 40492 8/10 100% 10-Dec SAP
Project complete.
Flowing Wells / Roger Rd. (SB) Complete 100% n/a n/a 9/09 10/9 12/09 NA 7/10 n/a 9/10 100% 10-Oct
West
PointConstruction Complete
Environmental & Economic Vitality Element
Greenways, Pathways, Bikeways and Sidewalks
Pathways and Greenways
Arroyo Chico Wash ImprovementsRP01
(Parks) 41ao 6 Julie Parizek Constr 100% 3/07 9/07 10/07 02/08 10/2010 11/2009 11-2009 n/a n/a 12/2009 100% tbd SQPComplete.
Ironwood Hills Sidewalk SK21 41bg T. Weideman Dropped ---12/04/09 - Project cancelled due to funding.
Bikeways
RTA Bicycle Lane Restriping Package 1 49B1 41af CW D. Swartz Complete 100% 12/07 11/08
10/08
7/09 100% 01/2010Project completed Jan. 2010.
4th Ave/Fontana Bike Blvd. SP03 41bc 3, 6 T. Thivener
Constructi
on 100% 6/09 11/09 11/09 07/2010 3/10 4/11 99% 6/11
West
Point
Complete.
Transportation Enhancement Pre-Design S01F 41bb A. McGovern
Plan'g &
Design 15% 6/09 4/10All funding now exhausted.
Sidewalks Package 1 SK01 Completed Locations Listed Below
22nd St., Wilmot to Kolb F. Reyes Complete 100% 12/07 Construction completed under Road Recovery in March 2005 (N. side).
Alvernon, Broadway to 22nd F. Felix Complete 100% 3/07 Construction complete. Final payment made.
Broadway, Wilmot to Kolb J. Chase Complete 100% 6/07 Construction complete. Final payment made.
Grant, Dragoon to I-10 T. Weideman Complete 100% 6/09 n/a n/a 7/09 100% 9/09 K/B Construction complete.
Swan, 22nd to 29th J. Gutierrez Complete 100% 5/07 Construction complete. Final payment made.
Wetmore, Oracle to Stone T. Weideman Complete 100% 9/07Construction complete. Final inspection on October 3, 2007. Final payment October 15, 2007. Billed RTA.
Sidewalks Package 2 SK02 41b CW F. Reyes Location details below
22nd St., Alvernon to Swan Complete 100% 9/07 7/08 9/08 11/08 12/08 8/09 100% 12/09 SQP
Broadway, Alvernon to Swan
Craycroft, Broadway to 22nd
Mission Rd., Ajo to Irvington
Tanque Verde, Kolb to Sabino Canyon
Sidewalks Package 3 SK03 41ay CW Location details below
Craycroft, Glenn-Speedway Complete 100% 11/08 100%
So. AZ
Pav'g
Complete
Complete
n/a 4/09 05/09 2/10
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Grant/Silverbell (EB) M. Holder Complete 100% n/a
Change order approved to modify design from a pullout to a pullthrough. Contract extended to 4/14/2010. Have Authority to Acquire. In acquisition process. Mylars are signed and awaiting R/W. Will build pullout
and wait for bus shelter pad since that is the only need for R/W. Jim Stoyanoff working with Chase Bank. Est. const. start Oct. 18, 2010. Construction complete.
Construction completed 11/09
N/A 5/10 10/10 100% 11/10
West
Point
Grant, Swan-Wilmot Complete 100% 11/08 100%
West
Point
Complete
Stone, Grant-Drachman T. Weideman Complete 100% 5/09 TBD TBD 4/10 5/10 n/a n/a 06/2010 5% 08/2010
NAC
Construct
ion
Project complete October 2010.
Country Club, Broadway-22nd St T. Weideman Complete 100% n/a n/a 8/09 90% 9/09
West
Point
Project complete.
Transit Element
Bus Frequency & Area Expansion
Sun Tran Bus Storage & Maintenance Facility- Phase
2
MRC2 /
M177 /
M157 3 T. Fisher Constr 100% 09/1999 2/07 1/95 6/08 100% 11/2009
DL
Withers
Phase 2 is 100% complete.
Weekday Evening Bus Service Expansion
Transit Weekend Extended Service
Phase I - Core Service K. Heineking Op'g 12/06 Annual Evening service was added to Routes 3, 4, 6, 7, 8, 9, 11, 16 - Implemented February 2007. Service is on-going and successful.
Phase II - Essential Service K. Heineking Op'g 3/07 Annual Evening service was added to Routes 1,10, 15, 17, 19, 22 34 - Implemented May 2007. Service is on-going and successful.
Phase III - Supportive Service K. Heineking Op'g 6/07 Annual Evening service will be added to Routes 2, 21, 27, 23, 26, 29 - Implemented August 2007. Service is on-going and successful.
Weekend Bus Service Expansion
Transit Weekend Extended Service
Phase I - Core Service K. Heineking Op'g 6/07 Annual Enhanced Sat/Sun service hours will be added to Routes 3, 4, 6, 7, 8, 9, 11, 16 - Implemented August 2007. Service is on-going and extremely successful.
Phase II - Essential Service K. Heineking Op'g 9/07 Annual Enhanced Sat/Sun service hours will be added to Routes 1, 10, 15, 17, 19, 22, 34. Implemented November 2007. Service is on-going and extremely successful.
Express Service Expansion
Transit Weekday Express Service
MONTHLY REPORT - Pima CountyDesign
Received Aug 7, 2012Project Name
Roadway Improvement ElementLa Canada Drive: River to Ina
(4LCRRI)
11Rick Ellis,
PCDOT
Under
CON Feb-06 Jun-09 Nov-09
Will be
omitted Aug-10
Combined
with Stage
5 Mar-11 Jul-09 Jul-11 Sep-11 May-12 10% May-14
Select
Development
and
Construction
Inc.
Project activities are well underway with Joint Trench utility work, plus preliminary clearing, grading and drainage
activities all being initiated for the portion north and including areas in and around Orange Grove. Metro water
relocation and new installation efforts are progressing south of Orange Grove towards Roller Coaster.
Magee Road: La Canada Drive
to Oracle (4MRLCO-DOT 6)
(Stage 3)
12Paul Bennett,
PCDOT
Under
Devel. Sep-07 Sep-09 Oct-10
Will be
omitted May-11
Combined
with Stage
5 Dec-11 Mar-11 Aug-12 Jan-13 Jun-14
Final design activities are being completed in conjunction with ADOT review of right of way use permit. Right of
way efforts are nearing final completion and right of way certification letter for FHWA will be developed shortly.
Utility design activities are all occurring in parallel and relocation efforts have been initiated. Project will request
authorization to Advertise once all right of way activities are completed and in conjunction with Federal
requirements and time lines. Construction will begin pending authorization approval from ADOT/FHWA.
Magee/Cortaro Farms: Mona
Lisa to La Canada (4RTMLI)
(Stage 1)
7Paul Bennett,
PCDOT
Under
CON Sep-07 Sep-09 Sep-09 Jan-10 Apr-10
Combined
with Stage
5 Nov-10 Jan-10 Jan-11 Jan-11 Apr-11 70% Apr-13
The Ashton
Company
Construction activities are fully underway with grading, concrete curbing, drainage, and construction of
temporary roadways, plus preliminary work for final roadways all having been initiated and under construction.
Utility coordination and relocation efforts and activities are nearing final completion as well as installation of new
sewer lines and reclaimed water lines.
Magee/Cortaro Farms Corridor
Study and Thornydale to Mona
Lisa (Stage 2) (4MCFTL)
7Paul Bennett,
PCDOT
Under
CON Sep-07 Sep-09 May-10
Will be
omitted Nov-10
Combined
with Stage
5 May-11 Oct-10 Oct-11 Oct-11 Nov-11 35% Jun-13
KE&G
Construction
Project construction activities are fully underway for new bridge at the CDO wash plus the section from
Thornydale to Shannon with temporary detours and closures in effect. Once this portion is complete, work
activities will return to the section from Shannon to the CDO for final efforts. Utility relocation efforts are all fully
underway throughout the corridor, and nearing completion in key areas.
*Valencia Road: Mark to Wade
(4RTVMW)
21aPaul Bennett,
PCDOT
Under
Devel. Aug-07 Dec-11 Jan-12
Will be
omitted Jul-12
Combined
with Stage
5 Dec-12 Mar-12 Jun-13 Jun-13 Jan-14 Sep-15
The project EAMR document has been approved by the BOS and the CE is being reviewed by ADOT and
FHWA. Detailed design activities remain fully underway and utility coordination and design efforts for relocation
will be initiated shortly. Coordination efforts and activities with AZ State Lands have been initiated, and it is
anticipated that right of way will be completed in Summer 2014. Request for authorization will be submitted to
ADOT and FHWA once all right of way has been cleared and utilities have been relocated. The interim signal at
Wade will be installed later this Fall pending approval of the CE by FHWA.
La Cholla Boulevard: Tangerine
to Magee (4RTLTM)
4
Dean
Papajohn
PCDOT
Under
Devel. Apr-09 Jun-10 Jun-10
Will be
omitted Nov-10
Combined
with Stage
5 Jun-11 Jun-10 Oct-11 Jan-12 Sep-12
Project has been awarded by the Board of Supervisors to Markham Contracting. A pre-construction open house
is scheduled for August 15th to share latest information with the public. Construction activities are expected to
start before the end of the month. Utility relocation work efforts are continuing in advance of pending
construction.
Sunset Road: Silverbell to I-10
(4RTSUN)
8Rick Ellis,
PCDOT
Under
Devel. Mar-10
Coordination efforts have been underway in conjunction with the Silverbell improvement project between Grant
Road and Ina Road (currently being led by the City of Tucson) as well as the I-10 series of improvements being
led by ADOT. Next steps and specific project activities will be determined in conjunction with ADOT's I-10
phasing and implementation efforts, and coordinated with other County, Marana, Tucson and RTA efforts.
Valencia Road: Alvernon Road to
Wilmot Road (4VAKDP)
24
Damon
Ballesteros
PCDOT
Under
Devel. Jul-10 Jul-11 Aug-11
Will be
omitted Feb-12
Combined
with Stage
5 Aug-12 Feb-12 Aug-12 Dec-12 Jan-13
Detailed Design activities are nearing final completion, and right of way and utility coordination efforts are being
conducted in parallel. Coordination with UPRR, Pima Air Museum, Davis Monthan and ADOT is ongoing as it
relates to their specific areas of concern, including meetings with affected stakeholders. Public Artwork has
been shared with the public at a CAC meeting July 9th and received unanimous support. Funding agreements
and permits are being finalized in preparation for advertisement anticipated for later this Fall.
Valencia Road: Wilmot Rd to
Kolb Rd (4RTKVI)
24 &
36
Damon
Ballesteros
PCDOT
Under
Devel. Feb-08 Sep-12 Sep-12
Will be
omitted Apr-13
Combined
with Stage
5 Sep-13 Nov-12 Jul-13 Oct-13
Project design activities are underway with drainage, survey and traffic meetings and design efforts all being
held on a regular basis. Project tasks will be closely coordinated with the other Valencia project to the west, from
Alvernon to Wilmot. An NAC meeting was held July 11th to present environmental information.
Barraza/Aviation Parkway: Palo
Verde to I-10 (4RTBAR) 20 TBD Future
First Avenue: Orange Grove to
Ina (4RTFIR) 13 TBD Future
Railroad Overpass: Ruthrauff
Road (4RTRAI) 9 TBD Future
Wilmot Road: South of 1-10
(4RTWNS)
33
Bob
Roggenthen
PCDOT-
Traffic
Under
Devel.
ON_HOLD as per RTA/County Administration
*Valencia Road: Mt. Eagle to Ajo
(4RTVEA) 21b TBD Future Nov-10 N/A
*Valencia Road: Wade to Mt.
Eagle (4RTVWM) 21c TBD Future
RTA Safety Element
RT
A #
Project
Manager
Curr.
Phase
Right-of-Way
End
Start
(begin
legals) Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
PS&E
End
Construction
Mobilize
Date
%
Compl
Date
Compl Con- tractor
CON
Clear-
ance
Planning
PCDOT 1, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Pima CountyReceived Aug 7, 2012Project Name
Roadway Improvement Element
RT
A #
Project
Manager
Curr.
Phase End
Start
(begin
legals) Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
PS&E
End
Mobilize
Date
%
Compl
Date
Compl Con- tractor
CON
Clear-
ance
Ina/Oracle DESIGN for
Intersection Improvements
(4RTIRO)
36
Bob
Roggenthen
PCDOT-
Traffic
Under
Devel. Jul-08 Nov-10 Jul-10 Jan-12 Dec-12 Feb-13
Project approved by RTA in January 2008. Design engineering contract in place. This project will be
coordinated with Ina/Oracle Bus Pullouts. Significant ROW will need to be acquired. If concept is acceptable
by ADOT, this project will move forward to Public Review. Construction start date is pending due to the
purchase of a gas station in area. Appraisals are complete and proposal will be presented to GAS STATION
OWNERS. Gas Station has accepted proposal. ADOT has approved indirect left turn geometry. Have
conducted Six public meetings. Review due to soft cost. Last public meeting held Nov 30. Schedule Change
due to time delay with ADOT. Appraising residual property acquisitons as of April 1, 2011. ADOT in
review/permit writing process. May be up to 6 months for this approval.
Mona Lisa at Orange Grove
(Safety improvements are being
built as part of the Orange
Grove/ Cmo de la Tierra to La
Cholla project, 4OGCAM)
36
Dean
Papajohn
PCDOT
Under
Devel. Jul-08 Aug-12 Not req Nov-12
These RTA funds will still be used to improve the Orange Grove-Mona Lisa intersection, but the work will
become part of a new PCDOT project that will improve all of Orange Grove Road from Cmo de La Tierra to La
Cholla. Design activities are nearing final completion and utility design, coordination and relocation efforts are
underway. Project construction is estimated to start in late Fall 2012 pending substantial completion of utility
relocation efforts.
Valencia Street Lighting
(4RTVLS)
36,
37 &
41
Bob
Roggenthen
PCDOT-
Traffic
Under
CON Jan-10 >>> >>> >>> >>> >>> Dec-10
Not
Req'd >>> >>> Mar-12 30% Oct-12
Select
Construction
Federal Project, Working on Evironmental Assessment. Internal review of project. Additional funds being
requested from FHWA. Awaiting ADOT approval 4-1-11. Eligibility letter has been approved. Application for
funds in process. Funds have been approved. Project moving to Procurement. Project out for bid schedule
opening is Jan 5, 2012. Select Construction is low bidder. NTP for March 2012. Under construction.
Nogales/Old Nogales Highway
(4OTNHS)
36
Bob
Roggenthen -
PCDOT
Traffic
Under
Devel. Nov-11 May-12 Feb-2012 Feb-2012
Consultant is looking at several alternatives to determine which intersection configuration will work best for RR
and also for possible future widening of Old Vail Connection roadway. Concept designs (15%) are due by the
end of May. Problems with survey control will delay concept design preparation looking anticipate new due date
Oct 2012. GATE 2-1 held July 30... Will be rescheduled for Oct meeting for additional details.
Homer Davis Safe Routes to
Schools (4HDBPE)
37
Sal
Caccavale
PCDOT
Under
Devel. Aug-06 >>> Apr-10 Mar-11 >>> Oct-11 May-12 Apr-10 Apr-12 Apr-12 Dec-12 Jul-13
Plans have progressed to 95%. All ROW needs are now complete. Utility relocation work has started to move
forward and will continue thru October 2012. Project submittal to ADOT for construction authorizartion (95%
PS&Es) was made in July and we are now responding to questions. Construction start estimated for late 2012.
Manzanita Safe Routes to
School (4RTMES)
37
Matt Zoll,
PCDOT
Under
Devel. Dec-10 Dec-11
Design to
15% only
with
Federal
process >>> >>> >>> Dec-11
not
required Design only
Project complete and PA and 15% final delivered to ADOT 6/7/12.
Camino del Sol Pedestrian
Ramps - Miscellaneous Safety
Improvement Projects
(4RTMBS) 37
Kathryn
Skinner,
PCDOT
Under
Devel. Aug-12 Sep-12
Construction delayed until pavement preservation work is complete.
Ruthrauff Rd/UPRR Safety 39 Lou Tapley Complete >>> >>> Jan-12 >>> >>> >>> May-12
Not
Req'd >>> >>> May-12 100% May-12 KE&G Project Complete, will be moved to completed project list in August Update.
Colossal Cave Rd/UPRR Safety
Upgrade
39
Bob
Roggenthen -
PCDOT
Traffic
Under
Devel. 6/5/2012
May-1-
2012
Plans have progressed to 90%. Project broken up into 3 Phases due to funding shortages. Tremendous
amount of Railroad and Right of Way acquisition to be completed.
RTA Environment & Economic Vitality Element
Orange Grove Bike Lanes:
Oracle - Cmo de Zorrela (Bike
Package 1) (4BLOGO) 41
Kathryn
Skinner
PCDOT
Under
Devel. Mar-08 >>> >>> >>> >>> >>> Oct-12 Oct-11
100%
(Phase 2) Nov-11
Granite (Phase
2)
Construction complete on phase 2. Phase 3 added which will complete the eastbound bike lanes at Pima Wash.
Four month design schedule (July 2012 - Oct 2012). Phase 3 first submittal scheduled for early August.
Mission Rd Bike Lanes: San
Xavier - Drexel (Bike Package 1)
(4BLMPS) 41
Kathryn
Skinner
PCDOT On Hold May-09 >>> >>> >>> >>> >>>
Project is on hold until an IGA between the county and tribe covering the ownership and maintenance of the road
is finalized. IGA finalized. Meeting with District, County and RTA held to determine scope.
Valencia Rd Bike Lanes:
Cardinal - Mission (Bike
Package 2) (4BLVCM) 41
Kathryn
Skinner
PCDOT
Under
CON Dec-08 >>> >>> >>> >>> >>> Mar-11 Mar-12 95% Jul-12 SAP
Construction underway. Final Striping schedulced for early August.
Alvernon Way: Golf Links - Ajo
(Bike Package 2) (4BLAGL)41
Bob
Roggenthen
PCDOT Future Jul-09 >>> >>> Sep-12 >>> >>> TBD D E S I G N O N L Y
Country Club Bike Lanes :
Irvington - Valencia (Bike
Package 2) (4BLCCI) 41
Bob
Roggenthen
PCDOT Future Jul-09 >>> >>> >>> >>> >>> TBD D E S I G N O N L Y
F U T U R E
PCDOT 2, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Pima CountyReceived Aug 7, 2012Project Name
Roadway Improvement Element
RT
A #
Project
Manager
Curr.
Phase End
Start
(begin
legals) Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
PS&E
End
Mobilize
Date
%
Compl
Date
Compl Con- tractor
CON
Clear-
ance
Centennial Elementary & Flowing
Wells Jr. High Safe Routes to
School Enhancement
41
Jason Bahe,
PCDOT
Under
Devel. Sep-11 Sep-11 Dec-11 Mar-12
Combined
with Stage
5 Nov-12 Mar-13 Jul-13
Project design activities i.e. survey, layout and environmental assessment activities are fully underway and
overall design layout has been developed. Project design and environmental documents are being processed
through ADOT and FHWA for review and approval, prior to moving forward with the final PS&E and subsequent
request for authorization to advertise.
Oracle Sidewalks: Orange Grove
- River 41 TBD TBD
Evaluating which portion of the project can be built with the current budget. RTA has taken the lead for design
and permit acquisition
Colossal Cave Bike Lanes:
Cienega HS to Pistol Hill Rd
(Package 3)
41
Bob
Roggenthen
PCDOT TBD
Due to State Budget cuts County does not have HURF match required for this project. Project on hold until
complete funding is identified.
Rillito Riverpath & Camino de la
Tierra 41
Nancy Cole -
PC PMO Future Jul-12 TBD TBDProject startup is underway; The County will work with ADOT to secure a designer and start the
planning/scoping work for the project in July.
Camino Loma Alta Bike Lanes
41 Lou Tapley Completed
Project was completed as a part of pavement preservation work by PC Operations. Project will be moved to
Completed list in July update.
Rillito River ROW 41 TBD TBD Pending
Miscellanous Markings & Signs
41
Matt Zoll,
PCDOT
Under
Devel. Jan-11 >>> Mar-12
Developing Intergovernmental Agreement (IGA) with City of Tucson, initiating field work to review existing signs
and markings and determine locations for new signs and markings. Submitted draft IGA to City of Tucson
3/23/11 and currently working on revisions to the IGA with the City of Tucson. Continuing with IGA revisions with
COT. Awaiting hire of new COT bike/ped planner to finalize IGA.
Pantano River Park Design,
Speedway to 5th St Wash 41
Nancy Cole -
PC PMO
Under
Devel. Jan-12 >>> Nov-12 >>> >>> >>> Dec-13 N/A Dec-13 Mar-15Project has received ADOT authorization for planning/scoping stage. Geotech field work and survey are
completed. Cultural work has been previously completed.
Pantano Property Acquisitions
41
Steve
Anderson,
PCNRPR
Under
Devel. Jul-09 Oct-09
The project is 99% done. Two of the properties are in escrow are are just about done; one is about to enter.
Harrison Rd Bike Lanes, Sabino
Canyon HS (4TEHBL)
41 Jason Bahe
Under
Devel. Feb-12 Jun-12 Sep-12
Will be
omitted Nov-12
Combined
with Stage
5 Feb-13 Jul-13
Project efforts and design activities such as survey, data gathering and preliminary design layout are fully
underway and preliminary design plan set has been developed and reviewed. A public open house is scheduled
for August 14th to share results and preliminary concepts and solicit input and feedback. Once design features
have been confirmed, documentation review and approval activities will be initiated with ADOT and FHWA.
Camino de Oeste Sidewalk and
Bike Lanes
41 &
37 TBD FUTUREProject to begin in FY12-13
Wildlife LinkagesWildlife Fencing & Culvert
Crossing Study 42
Rick Ellis,
PCDOT
Opera-
tional Dec-08 >>> >>> >>> >>> >>> >>> >>> >>> >>>Culvert Study and Fencing Study: All activities have been completed and reports have been finalized and
submitted.
Transit Element
None Currently Active
P L A N N I N G O N L Y
PCDOT 3, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Pima CountyDesign
Received Aug 7, 2012
Project Name
Roadway Improvement ElementI-19 Frontage Road: Continental
to Canoa (4INFRC, DOT 37)
35
Damon
Ballesteros
PCDOT Under CON Nov-06 Aug-08 May-08 Aug-08
Over
shldr
review
Oct-08 Dec-08 Apr-09 Sep-08 Jun-09 Aug-09 Jul-09 100% Feb-11
Borderland
Const.
COMPLETE
La Cholla Boulevard: River to
Ruthrauff (4LCITR-DOT 20)
10
Dean
Papajohn
PCDOT Under CON Jul-07 Dec-08 Jan-09
Will be
omitted
Over
shldr
review
April
2009
Will be
omitted Jul-09 Jan-09 Oct-09 Jan-10 Dec-09 100% Jul-11
Eagle Rock
Construction
COMPLETE
Tanque Verde Road: Catalina
Hwy to Houghton (4TVCHH) 27Nancy Cole
CIP-PDG Under CON Feb-07 Mar-09 Apr-09
Will be
omitted Jul-09 Aug-09 Nov-09 Apr-09 Dec-09 Dec-09 Mar-10 100% Sep-11 SAP
COMPLETE
La Canada Drive: Ina to Calle
Concordia (4RTCCI) 11
Mike Bertram
HDR Inc. Under CON Jul-99 Aug-01
Will be
omitted
Will be
omitted
Will be
omitted Feb-09 Jun-09 Apr-08 Jul-09 Sep-09 Nov-09 100% Oct-11
KE&G
Construction
COMPLETE
RTA Safety Element
Laguna Elementary Safe Routes
to Schools (4LESMI)37
Sal
Caccavale
PCDOT Completed Aug-06 >>> Apr-10
Will be
omitted >>> Oct-10 Apr-11 Apr-10 Feb-11 Dec-11 100% Apr-12
Falcone
Brothers
Complete
Golder Ranch Road Bridge at the
CDO Wash (4RTGRB)39 Dave Zaleski
Under
Devel. Apr-11 Jun-11 Oct-11 100% Mar-12
The Ashton
Company
COMPLETE
Alvernon Way/Valencia
Intersection Improvements
(4RTAWV)36
Bob
Roggenthen
PCDOT-
Traffic
Under
Devel. Jan-09 Dec-10 Feb-10 Dec-10 Jul-11 100% Dec-11 Borderland
COMPLETE
Houghton and Sahuarita
Intersection Improvement
(4RTHSH)36
Bob
Roggenthen
PCDOT-
Traffic Compl. May-06 Jul-08 Jan-09 100% Jun-09 Ashton
COMPLETE
Campbell/Skyline Widening
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jul-08 Feb-09 Mar-09 Jul-09 100% Nov-09 SAP
COMPLETE
Camino Verde/Valencia
Inters.Improvements &
Signalization36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jul-08 Feb-09 Not req Oct-09 100% Dec-09
COMPLETE
Flowing Wells/Wetmore
Intersection Improvements
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jul-08 Feb-09 Not req Apr-09 100% Jun-09
COMPLETE
La Cholla/River Intersection
Improvements
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jul-08 Feb-09 Not req Dec-08 100% Mar-09 KEG
COMPLETE
Palo Verde/Michigan
Street/Coach Drive
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jul-08 Feb-09 Not req May-09 100% Jun-09 KEG
COMPLETE
Alvernon/ Los Reales
Intersection
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jan-09 Jan-10 Dec-09 100% Mar-10 SAP
COMPLETE
Continental/Camino del Sol
Intersection
36
Bob
Roggenthen
PCDOT-
Traffic Compl. Jan-09 Jan-10 Jun-09 100% Oct-09 KEG
COMPLETE
Right-of-Way
End
Con-
tractor
CON
Clear-
ance
PS&E
End
Start
(begin
legals)RT
A #
Project
Manager
Curr.
Phase Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
Mobilize
Date
%
Compl
Date
Compl
ConstructionPlanning
PCDOT 1, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Pima CountyDesign
Received Aug 7, 2012
Project Name
Right-of-Way
End
Con-
tractor
CON
Clear-
ance
PS&E
End
Start
(begin
legals)RT
A #
Project
Manager
Curr.
Phase Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
Mobilize
Date
%
Compl
Date
Compl
ConstructionPlanning
Curtis/Shannon HAWK
36
Bob
Roggenthen
PCDOT-
Traffic Under CON Jul-08 May-09 Dec-09 100% May-10 Ashton
COMPLETE
Mountain Shadows/Ventana
Signal (4RTKMV)
36
Bob
Roggenthen
PCDOT-
Traffic Comp Apr-11 May-11 May-11 Jul-11 100% Sep-11
KE&G
Construction
COMPLETE
Agua Caliente Elementary- Safe
Routes to Schools (PHASE 1)
4SRSAC
37
Kathryn
Skinner
PCDOT Compl. Apr-08 May-09 Mar-09 100% Aug-09 Granite
COMPLETE
Agua Caliente Elementary- Safe
Routes to Schools (PHASE 2)
4SRSAC
37
Kathryn
Skinner
Under
Devel. Apr-08 Pending Pending
Catalina Highway Trailhead cancelled.
Picture Rocks Safe Routes to
School (4PRDWE)37
Jason Bahe
PCDOT Under CON Apr-07 >>> >>> >>> >>> >>> Apr-10 Not Req'd >>> >>> Dec-10 100% Mar-12
SQP
Construction
COMPLETE - landscape establishment complete in March 2012
Palo Verde Corridor (3) Bus
Pullouts
38
Bob
Roggenthen
PCDOT-
Traffic Compl. Feb-09 >>> >>> >>> >>> >>> Mar-09 Not Req'd Jun-09 100% Oct-09 KEG
COMPLETE
Ina & Oracle SunTran Bus
Pullout
38
Bob
Roggenthen
PCDOT-
Traffic
Under
Devel. >>> >>> >>> >>> >>> Oct-10 Feb-09 Oct-09 May-11 100% Aug-11 Granite
COMPLETE
Regional Traffic Signal Battery
Backup (4RTBAT)
40
Tom Kelley
PCDOT-
Traffic Compl. Feb-08 >>> >>> >>> >>> >>> May-08 Not Req'd
Not
Req'd Mar-09 100% Oct-09
KEG &
Myers
COMPLETE
Sabino Canyon Road
BridgeDeck Rehabiliation
39
Dave Zaleski
PCDOT Comp. Feb-09 >>> Jul-09 >>> >>> >>> Dec-09 Not Req'd >>> >>> May-10 100% Sep-10
The Ashton
Co.
COMPLETE
Marsh Station Bridge S.
Abutment Repair (4RTMAR)39 Dave Zaleski
Under
Devel. Apr-11 May-11 Aug-11 100% Sep-11
KE&G
Construction
COMPLETE
Regional Traffic Signal Wireless
Communications System
(4RTWIR)
40
Tom Kelley
PCDOT-
Traffic Comp. Feb-08 >>> >>> >>> >>> >>> Sep-08 Not Req'd
Not
Req'd Apr-09 100% Oct-10
Smart wave
Tech
COMPLETE
Ina Road Corridor Signal Timing
(4RTICS)
40
Tom Kelley
PCDOT-
Traffic Comp. Feb-08 >>> >>> >>> >>> >>> Apr-08 Not Req'd
Not
Req'd Apr-09 100% Oct-10
Psomas &
Smart wave
Tech
COMPLETE
RTA Environment & Economic Vitality Element
PCDOT 2, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Pima CountyDesign
Received Aug 7, 2012
Project Name
Right-of-Way
End
Con-
tractor
CON
Clear-
ance
PS&E
End
Start
(begin
legals)RT
A #
Project
Manager
Curr.
Phase Project Status as of July 31, 2012Start
EAMR
& 15%
Plans Start
30%
Plans
60%
Plans
90%
Plans
Mobilize
Date
%
Compl
Date
Compl
ConstructionPlanning
Continental Sidewalks: La
Canada - PCC entrance
(Sidewalk Package 1)
(4SWCLC) 41
Kathryn
Skinner
PCDOT Compl. Mar-08 >>> >>> >>> >>> >>> Jul-08 Jul-09 100% Sep-09 KE&G
COMPLETE
Continental Bike Lanes: La
Canada - Cmo del Sol (Bike
Package 1) (4BLCCS) 41
Kathryn
Skinner
PCDOT Compl. Mar-08 >>> >>> >>> >>> >>> Jul-09 100% Sep-09 KE&G
COMPLETE
Escalante Bike Lanes: Houghton -
Old Spanish Trail (Bike Package
1) (4BLEHO) 41
Kathryn
Skinner
PCDOT Compl. Sep-08 >>> >>> >>> >>> >>> Jul-09 Sep-09 100% Nov-09 SAP
COMPLETE
Freeman Rd Bike Lanes:
Broadway - Old Spanish Trail
(Bike Package 1) (4BLFBO) 41
Kathryn
Skinner
PCDOT Compl. Sep-08 >>> >>> >>> >>> >>> Sep-09 100% Nov-09 SAP
COMPLETE
Tanque Verde Bike Lanes:
Powderhorn - Fennimore (Bike
Package 1) (4BLTVP) 41
Kathryn
Skinner
PCDOT Compl. Nov-08 >>> >>> >>> >>> >>> Oct-09 May-10 100% Sep-10 SAP
COMPLETE
Pantano River Park
41
Nancy Cole,
CIP PDG Under CON
not
required Oct-09 100% Jan-11
Norquay
Construction
COMPLETE
Bear Canyon Bike Lanes: Snyder
- Indian Bend(Bike Package 2)
(4BLBCS)
41 &
37
Kathryn
Skinner
PCDOT
Under
Devel. Dec-08 >>> >>> >>> >>> >>> Jul-10 Jan-11 100% Jul-11 Ashton
COMPLETE
Flowing Wells: River - Roger
Sidewalk Package 1)
(4SWFWR) 41
Kathryn
Skinner
PCDOT
Under
Devel. Oct-08 >>> >>> >>> >>> >>> Jul-10 Jun-11 100% Dec-11 SAP
COMPLETE
Rillito River-Country Club to
Hacienda Del Sol 41
John Spiker,
PCNRPR Under CON Dec-09 Apr-10 Dec-11 Jan-11 Jan-11 Mar-11 100% Jan-12
The Ashton
Company
COMPLETED
Abrego Bike Lanes -
Miscellaneous Safety
Improvement Projects (4RTMBS)
41
Kathryn
Skinner Completed Jan-12 100% Mar-12 SAP
COMPLETE
Wildlife Linkages
None at this time.
Transit Element
Ajo-Tucson Expansion to 5
days/week 49
Ben Goff,
PCDOT
Opera-
tional >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>>Service Started in September 2007, IGA for FY 0809 has been approved and recorded.
Ajo Dial-A-Ride48
Ben Goff,
PCDOT
Opera-
tional >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>>Service Started in October 2007. IGA for 0809 approved by the BOS and the RTA, awaiting
recording.
Green Valley/Sahuarita Circulator
48c
Ben Goff,
PCDOT Operational >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>>
Green Valley/Sahuarita Regional Connector and Circulator route has been taken over by the
RTA, May 4, 2009. The ADOT Pilot Program funds expired 1/31/09. IGA Approved in
November 2008.
Pima County Special Needs47
Ben Goff,
PCDOT
Opera-
tional >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>> >>>Service Started in September 2007, IGA for FY 0809 approved and recorded.
Design completed, Permits Completed
PCDOT 3, Printed 8/28/2012, 11:19 AM
MONTHLY REPORT - Town of MaranaProject Status as of June 2012
Project Name/Description RTA #
RTA Roadway Element - Planning / Design
Tangerine Road Corridor - I-10 to La Cañada
Blvd. 1
Scott
Leska DCR 80 Aug-10 Aug-12 Oct-11 Sep-12 Sep-13 Dec-14 Feb-15
Psomas is working. Work is progressing. Montly
TAC meetings are held at Marana. Final 30%
plans for study phase is shown to be compeleted
by September 2012. total plans for all phases will
be completed by 2022.
Camino de Mañana/Dove Mt Ext Linda Vista
Blvd. to Tangerine Road/Dove Mt. 2
Scott
Leska PSE 100 Sep-05 Jun-06 Mar-07 complete complete Complete Complete
Construction substantially complete. Warrenty
period has started.
Twin Peaks Linda Vista TI RTA 3a Twin
Peaks Blvd. to Camino De Manana 3a
Scott
Leska PSE 100 2002 2004 2004 complete complete Complete Complete
Construction substantially complete. Warrenty
period is in effect.
Twin Peaks Bridge and Roadway RTA 3b
Twin Peaks Blvd. in Continental Ranch
Neighborhood to the Linda Vista/ I-10 TI 3b
Scott
Leska PSE 100 2002 2004 2004 complete complete Complete Complete
Construction substantially complete. Warrenty
period is in effect.
Twin Peaks Roadway RTA 3b Twin Peaks
Blvd. - Tiffany Loop Drainage 3c
Scott
Leska PSE 100 2002 2004 2011 Complete Complete Complete Complete
Design completed as part of the Twin Peaks
Road TI. Kick-off Partnering meeting set for
Novermber 2011. Construction to start 11/2011
Project Status as of June 2012
Project Name/Description RTA #
RTA Roadway Element - ROW / Construction
Tangerine Road Corridor - I-10 to La Cañada
Blvd. 1
Scott
Leska DCR 0 NA NA NA NA NA
Right-of-Way and Construction has not been
determined at this time.
Camino de Mañana/Dove Mt Ext RTA -2
Linda Vista Blvd. to Tangerine Road/Dove
Mt. 2
Scott
Leska Construction 100% 100% 100% May-09 Dec-10 99%
Construction substantially complete. Warrenty
period is in affect.
Twin Peaks Linda Vista TI RTA 3a Twin
Peaks Blvd. to Camino De Manana 3a
Morris
Reyna -
Scott
Leska construction 100% complete complete May-09 Dec-10 99%
Construction substantially complete. Warrenty
period has started on most of the projectPulice
Borderland Construction
TBD
Design
Start Date End Date
Start
Date
Contractor
30%
Plans
End
60 %
Plans
End
Construction
Date
Mobilized
Date
Complete
%
Contract
Complete
PS&E End
90%
Plans
End
Project
Mgr
Current
Phase
% Phase
Compl
Planning
Project
Mgr
Current
Phase
% Phase
Compl
Right-of-Way
100%
Possession
100%
Acquired
Twin Peaks Bridge and Roadway RTA 3b
Twin Peaks Blvd. in Continental Ranch
Neighborhood to the Linda Vista/ I-10 TI 3b
Morris
Reyna -
Scott
Leska construction 100% complete complete May-09 Dec-10 99%
Construction substantially complete. Warrenty
period has started on most of the project
Twin Peaks Roadway RTA 3b Twin Peaks
Blvd. - Tiffany Loop Drainage 3c
Scott
Leska Construction 60% complete complete Aug-11 Nov-11 60%
Construction is on hold pending AT&T moving
their lines. Construction is anticipated to be
complete by August 1012.
Project Status as of June 2012
Project Name/Description RTA #
RTA Safety Element
Silverbell/Coachline RTA 36 36
Scott
Leska Construction 100 yes May-08 Aug-08 Sep-08 Oct-08 Construction is completed.
Silverbell/Ina Intersection RTA 36 36
Scott
Leska Construction 100 yes May-08 May-08 May-08 Feb-09
Construction is completed. Project under
Warrenty period and 404 Mitigation monitoring
still active.
Tangerine/Thornydale Intersection RTA 36 36
Scott
Leska Construction 100 yes May-08 Feb-09 Jun-09 Dec-09 Final construction is complete.
Silverbell/Cortaro Intersection RTA 36 36
Scott
Leska construction 99% Jan-10 Aug-10 Sep-10 May-11 Jul-11
Contractor is substantially complete. Warrenty
period in effect.
Project Status as of June 2012
Project Name/Description RTA #
RTA Environment & Economic Vitality Element
Project Name/Description RTA #
Project
Mgr
Current
Phase
% Phase
Compl Project Status as of June 2012
Transit Element
Project
Mgr
Current
Phase
Diggum Construction
Southern Arizona Paving
% Phase
Compl
Design
Design
Started
Design
Complete
Project
Bid Date
Construction
Date
Mobilized
Date
Complete Contractor
Southern Arizona Paving
Granite Construction
Construction
Date
Mobilized
Date
Complete Contractor
Pulice
SunWestern Contractors
Project
Mgr
Current
Phase
% Phase
Compl
Design
Design
Started
Design
Complete
Project
Bid Date
Marana Park and Ride RTA 51c Parking lot
for Park & Ride 51
Scott
Leska
Not in Design
Yet N/A TBD TBD TBD TBD TBD Not yet started design.
Marana Circulator Service RTA 48 48
T. Van
Hook
Not in Design
Yet N/A TBD TBD TBD TBD TBD Not yet started design.
TBD
TBD
Received July, 9 2012
MONTHLY REPORT - Town of Oro ValleyRTA # Project Current % Design Construction
Project Name/Description Design Started Design Complete Project Bid Date
Date
Mobilized Date Complete Contractor
RTA Safety Element
RTA # Project Current % Design Construction
Project Name/Description Design Started Design Complete Project Bid Date
Date
Mobilized Date Complete Contractor Project Status as of July 9, 2012
RTA Environment & Economic Vitality Element
Canada Del Oro Shared Use Path 41
Jose
Rodriguez Design Complete July 8, 2010 On going TBD TBD TBD TBD
Staff will be meeting with Home Depot
representative to negotiate right-of-way
acquisition.
Received Aug 7, 2012 MONTHLY REPORT - Town of Sahuarita
Project Name/Description RTA # Project Status as of Aug 2012
RTA Roadway Element - Planning / Design
Sahuarita Rd - I-19 to Country Club Rd 34a
Phase I - I-19 to La Villita Rd 34a Joel Harris Design 100% Dec-05 Oct-07 Dec-07 Dec-07 Apr-08 Dec-08 June, 10 2009
Design completed. Bid's Opened June 10, 2009. Construction
Contract awarded at July 13, 2009 Council meeting. Construction
NTP issued on September 8, 2009.
Phase II - La Villita Rd to Nogales Highway
PROJECT SEGMENTS 2A/2B34a Joel Harris Design 100% Dec-06 Aug-08 Jul-09 Dec-09 Feb-11 Jun-11 Apr-12
Design Completed. Construction of improvements started May 15,
2012.
Phase II - Nogales Highway to Country Club Road
PROJECT SEGMENTS 2C/2D34a Joel Harris Design 60% Dec-06 Aug-08 Jul-09 Dec-09
Feb-11
Revised 60% =
Aug 2012
Oct-12 May-13
CMAR pre-construction contract approved at Mar 14, 2011
Council meeting. Final Design contract (EEC) approved at May
15, 2012 Mayor & Council Meeting. Final Design NTP for
Segments 2C and 2D issued May 15, 2012 - approximate duration
of 12-18 months.
Project Name/Description RTA # Project Status as of Aug 2012
RTA Roadway Element - ROW / Construction
Sahuarita Rd - I-19 to Country Club Rd 34a
Phase I - I-19 to La Villita Rd 34a Joel Harris Construction 100% Jun-10 Nov-10 Sept. 8, 2009 Dec-10 100% Construction Complete. Ribbon cutting January 19, 2011.
Phase II - La Villita Rd to Nogales Highway
PROJECT SEGMENTS 2A/2B34a Joel Harris Construction 8% May-12 May-12 May-12 Sep-14 8%
Segments 2A&2B GMP#1 (Pecan Tree Removals) completed.
Segments 2A&2B GMP#2 (construction of improvements) started
May 15, 2012 with approximate duration of 26 months. (for
construction updates please see: www.ci.sahuarita.az.us
"Construction Updates" link)
Phase II - Nogales Highway to Country Club Road
PROJECT SEGMENTS 2C/2D34a Joel Harris Design 60% TBD TBD TBD TBD 0%
60% plans issued Feb 2011. CMAR pre-construction contract
approved at Mar 14, 2011 Council meeting. Final design started
May 2012. Construction to start upon completion of 2A&2B
segments.
Project Name/Description RTA # Project Status as of Aug 2012Project
Mgr Current Phase % Phase Compl
Design Construction
Design Started Design Complete Project Bid Date Date Mobilized Date Complete Contractor
Project
Mgr Current Phase % Phase Compl
Right-of-Way
100% Possession 100% Acquired
Start Date
30% Plans
End
Project
Mgr Current Phase % Phase Compl
Planning Design
Start Date End Date 60 % Plans End
90% Plans
End PS&E End
Construction
Date Mobilized Date Complete
Borderland Construction
(pending GMP#3
negotiations & ROW
Acquisitions)
Southern Arizona Paving
Borderland Construction
% Contract
Complete Contractor
RTA Safety Element
Pima Mine Road Bridge Replacement 39dRick
Robinson
Pre-Design (DCR
only)100% - Dec-10 (DCR) - - - Design Concept Report complete
Pima Mine Road /Nogales Highway IntersectionRick
RobinsonConstruction 100% Mar-11 Mar-11 Jun-11 Jan-12
Construction started June 2011 with an approximate duration of 7
months. Paving of additional turn lanes and Traffic Signal pole
installations are complete. Traffic Signal activated November 2, La Canada Drive/El Toro Road at-grade railroad
crossing (Part of La Canad Drive Phase III project)39g Joel Harris Construction 100% Jun-06 Feb-09 Mar-09 Apr-09 Mar-10
Construction completed with the Town's La Canada Drive Phase
III roadway improvement project.
Pima Mine Road / Rancho Sahuarita Blvd.
Intersection36ad
Rick
RobinsonConstruction 100% May-07 Jun-08 Jan-10 Apr-11 Traffic Signal & UPRR Signal activated week of April 11th.
Project Name/Description RTA # Project Status as of Aug 2012
RTA Environment & Economic Vitality Element
Sahuarita Rd Phase II Wildlife Crossings - Upsize
Culverts42g Joel Harris Design
60%
(with SR-Phase II,
2C&2D)
Jun-10
(with SR-Phase II,
2C&2D)
TBD
(with SR-Phase II,
2C&2D)
TBD
(with SR-Phase II,
2C&2D)
TBD
(with SR-
Phase II,
2C&2D)
TBD
(with SR-Phase
II, 2C&2D)
Sahuarita Road Phase II Segments 2C/2D Design currently
evaluating upsized culverts as part of roadway design. (Based on
recommendations from SWCA Sahuarita Road Wildlife Linkage
Assessment, completed in September 2008)
Sahuarita Rd Phase II Wildlife Crossings - Pre &
Post Construction crossing monitoring42h TBD Study 0% TBD TBD N/A N/A N/A
Sahuarita Wildlife Assessment (Pima mine Rd, Old
Nogales Hwy, Nogales Hwy)42i TBD Study 0% TBD TBD N/A N/A N/A
Southern Arizona Paving &
Construction
KE&G
Southern Arizona Paving &
Construction
TBD
TBD
EEC/Borderland
(with SR-Phase II)
Project
Mgr Current Phase % Phase Compl
Design
Design Started Design Complete Project Bid Date
Construction
Date Mobilized Date Complete Contractor
DMA Engineering
Received Aug 3, 2012 MONTHLY REPORT - RTA
Bus Pullouts Package 6 RTA 38j Holder
- Alvernon / Ft. Lowell SB
- Alvernon / Glenn SB
- Alvernon / Glenn NB
- Alvernon / Pima SB
- Alvernon / Pima NB
R/W &
Const.
100%
85 10/2009 01/2010 05/2010 N/A 03/2012 04/2012 2/9/2011 85% West Point
PSOMAS - Cont. Mod. #1 for Utility Coord. approved 4-19-2010. Cont. extended to 7-9-2010. 75% Prop. Owner ltrs. sent 5/10. Property
owner issues being discussed. Cultural Resource Clearance Waivers requested 6-23-10. Contract extended to 1-9-10 for post design
services. Environmental clearance requested 10-26-10. 100% mylars at Tucson Water for signature. Mylars signed by all. 100% utility
submittal made. R/W acquisition proposals due 12-15-10. Tierra selected for R/W acquisition. Request for construction bids to be sent 1-7-
11. West Point low bidder @ $287,175.70. Design Contract Mod. #3 extended till 9-30-11 for post design services. Re-design of Glenn
SB underway. Westpoint finished with Pima SB & Glenn NB. Will move to Ft. Lowell SB once Circle K relocates their trash enclosure
(Const. underway). WestPoint started week of Oct. 17. Re-design of Glenn SB @ 90%. Might be an issue w/TEP's 46kv pole. Alvernon/Ft.
Lowell SB complete. Shelter installed by Streets Div. crew. Waiting on mtg. w/TEP re 46kv pole relo. @ Alvernon/Glenn SB. Met w/ TEP
May 1. Looking at another option to avoid 46kv pole. Directed Psomas to submit a proposal to redesign to an abbreveated pullout
immediately north of the pole. Proposal is in for review. Proposal approved. Due date is 3-13-13.
Bus Pullouts Package 7 RTA38j Holder
- First Ave. / Ft. Lowell NB
- First Ave. / Ft. Lowell SB
- First Ave. / Prince SB
- First Ave. / Roger SB
- Ft. Lowell / First Ave. EB
R/W &
Const.
95%
60% 10/2009 01/2010 04/2010 N/A 8/10 01/2011 60% West Point
Transystems - 75% Prop. Owner ltrs. sent 4-26-2010. Cont. Mod. #1 for Utility Coord. approved 4-27-2010. Cont. extended to 7-9-2010.
Property owner issues being discussed. Cultural Resource Clearance Waivers requested 6-25-10. This is anticipated to be the second
package to start construction since only two of the five bus pullouts requires R/W. 9-1-10 Environmental Clearance requested. Contract
extended to 2-20-10 for post design services. 100% Mylars to be turned in on 11-12-10. Proposals for R/W acquisition due 10-9-10.
Request for bids week of 11-22-10. Bids due 12-7-10. RTA Board to approve 12-9-10. West Point low bidder @ $266,747. DOWL
selected for R/W Acquisition. 100% utility ltrs. sent 11-22-11. Design Cont. Mod. # 4 for signal mod. approved. Cont. Mod. #5 extend cont.
to 9-30-11 for post design services. Cont. Mod. #6 to modify R.W drawings approved. Transystems had to correct. Contractor finished
with Ft. Lowell EB. R/W acquisition modified at Ft. Lowell SB to miss revolving sign. Mario's Pizza sign relo. allowed by SIgn Code revision
& process to establish as a Historic Sign is underway. Closings at 1st Roger SB almost complete. Waiting on property owners to respond.
Bus Pullouts Package 8 RTA38j Holder
- Wilmot / Broadway SB
- St. Mary's / Silverbell EB
- 29th / Columbus EB
- 22nd / Country Club WB
R/W &
Const.
100%
100% 10/2009 11/2009 02/2010 N/A 7/10 9/11 11/2010 100% 08/2011 SAP
EPS Group - 75% Prop. Owner ltrs. Sent 5-4-2010. Cont. Mod. #1 for Utility Coord. approved 4-27-2010. Cont. extended to 7-9-2010.
Property owner issues being discussed. Cultural Resource Clearance Waivers requested 6-25-10. Environmental Clearance requested 8-3-
2010. This will be the first package to start construction since only one of the four bus pullouts requires R/W. Construction bids advertised
8-31-10. Bids due 9-29-10. Southern Arizona Paving low bidder @ $234,773. Contract extended to 1-9-10 for post design services. SAP
to start at 29th /Columbus 11-29-10 then move to Wilmot/Broadway. Tierra performing R/W acquisition for the one bus pullout that requires
R/W. SAP finished 29th/Columbus, started Wilmot/Broadway. SAP finished St. Mary's/Silverbell, started 22nd/Country Club w/Right of
Entry. Design Cont. Mod #4 extended contract to 6-30-11 for post design services. SAP finished last pullout. All const. complete & one of
1st new double shelters installed @ 22nd/ CC.
Bus Pullouts Package 9 RTA38j Holder
- Alvernon / 22nd SB
- Alvernon / 29th NB
- Alvernon / 32nd SB
R/W
Const.
98%
70% 10/2009 12/2009 06/2010 N/A 11/10 70% Westpoint
Kimley Horn - Cont. Mod. #1 for Utility Coord. approved 4-27-2010. Cont. extended to 7-9-2010. 75% Prop. Owner ltrs. sent 5/10.
Property owner issues being discussed. Cultural Resource Clearance Waivers requested 7-1-10. Contract extended to 1-9-10 for post
design services. KHA wrapping up plans to submit 100%. 100% plan submittal made. Mylars submitted and are at Tucson Water for
signature. Mylars signed & ready to be sent out for printing. 100% utility ltrs. sent 3/2/2011. DOWL selected for TW acquisition. Design
Cont. Mod. #3 extended to 10-30-11 for post design services. Minor changes @ Alvernon/ 22nd made to accomodate prop. owners. All
negotiations underway. Const. bid advertises 12-15-2011. Bids due 1-20-2012. Westpoint was low bid at $216,387.10. N/P is 3/19/2012.
Alvernon/29th St. NB complete. Alvernon/22nd St SB almost complete.
Bus Pullouts Package 10 RTA38j Holder
- Ft. Lowell / Alvernon WB
- Campbell / Adams SB
- Campbell / Prince SB
Design
R/W
Const
100%
100%
0% 10/2009 11/2009 05/2010 N/A 7/10 08/2012
EEC - Cont. Mod #1 for Water Mod. approved 3-3-2010. #2 for Campbell/Prince SB mod. Approved 4-14-2010. #3 for Utility Coord.
Approved 4-19-2010. Cont. extended to 7-9-2010. 75% Prop. Owner ltrs. sent 5/10. Property owner issues being discussed. Cultural
Resource Clearance Waivers requested 6-25-10. Contract extended to 2-20-2010 for post design services. Environmental Clearance
requested 11-9-10. 100% mylars due any day. Mylars submitted & approved. R/W acquisition bids due 2-23-2011. Tierra selected. N/P
3/7/2011 . 100% utility ltrs. sent 2-24-11. Design Cont. Mod # 6 extended to 10-30-11 for post design services. R/W offers being
prepared. Closing for Pet Assoc. & Sierra LLC to occur shortly. Working on exchange w/COT for needed R/W. Sierra LLC purchased by
Campbell/Prince LLC so R/W is being renegotiated. Administrative settlement is approved. Revised offer submitted. Awaiting closing of
Loma Catalina (formerly Roh's). Then this package will be bid. Bids are due 8-16-2012. Needs RTA Board approval. Next mtg. is Sept. 27.
Bus Pullouts Package 11 RTA38j Holder
100%
Acq'd
PS&E
End
30%
Plans
75%
PlansStart End
% Phase
Compl
Planning
Project Name
90%
Plans Poss'n Project Status as of July 31, 2012Date
Compl
Date Mobil-
ized ContractorRTA #% Contr.
Compl
Curr.
Phase
Project
Manager
Right-of-Way ConstructionDesign
Start
- Oracle / Prince NB
- Oracle / Prince SB
- Oracle / Glenn SB
- Prince / Oracle EB
Design
R/W
100%
98% 10/2009 12/2009 07/2010 N/A 9/10
EEC - Cont. Mod. #1 for Utility Coord. approved 4-27-2010. Cont. extended to 7-9-2010. 75% Prop. Owner ltrs. sent 5/10. Property
owner issues being dicsussed. Cultural Resource Clearance Waivers requested 8-2-10. Contract extended to 1-28-10 for post design
services. 100% mylars due week of 11-15-10. Environmental Clearance requested 11-24-10. Mylars submitted & approved. 100% utility
ltr. sent 3/2/2011. R/W acquisition bids due 4-14-11. Design Cont. Mod #5 extended to 10-30-11 for post design services. Westland
selected. N/P 4/22/2011. Closing for Sunpoint Gardens to occur shortly. Prop. owner at Oracle / Prince NB is balking & ltr. sent 9-2-11 to
attempt to get them back to nego. table. Property owner referred to his attorney. Negotiations ongoing. Westland transferring remaining
contract to DOWL. DOWL is pursuing closings. NE corner Oracle/Prince negotiation is moving again. Lee Family was presented with
revised Purchase Agreement. Awaiting Diocese and Lee Family to respond. Waiting on TEP to respond as to why their poles have not
been relocated from Oracle/ Prince SB & Prince/Oracle EB.
Bus Pullouts Package 12 RTA38j Holder
- Valencia / San Fernando EB
- 12th / Valencia NB
- Park / Irvington NB
- 12th / Nebraska NB
- 6th / Veterans NB
R/W
Const.
98%
68% 10/2009 12/2009 05/2010 N/A 8/10 05/2011 68% NAC
AMEC - Cont. Mod. #1 for Utility Coord. approved 4-19-2010. Cont. extended to 7-9-2010. 75% Prop. Owner ltrs. sent 5/10. Proerty
owner issues being discussed. Cultural Resource Clearance Waivers requested 7-1-10. Contract extended to 1-9-10 for post design
services. Environmental Clearance requested 11-4-10. Awaiting 100% mylars. DOWL selected for R/W acquisition. Mylars submitted &
approved. Out to bid 2-10-2011. NAC selected. 100% utility ltrs. sent 2-9-11. DOWL selected for RW acquisition. NAC to start 5-9-11
@Valencia/San Fernando EB. Design Cont. Mod. #3 extended to 10-30-11 for post design services. Valencia/San Fernando EB & 12th /
Valencia NB complete. 12th / Nebraska started const. week of Oct. 17. Prop. owner at Park / Irvington NB is balking & ltr. sent 9-2-11 to let
them know we plan to start without R/W for shelter & will fit in the best we can. Followup ltr sent Oct. 6 letting them know contractor will start
wk. of Oct. 24. Can't start without R/W for landing pad. Nego. on-going. 12th/Nebraska complete. DOWL performing interstection traffic
study @ 6th/Veterans. Traffic study complete. Nego. w/ VA ongoing. Revised easement descriptions being reviewed. Lee Family was
presented with revised Purchase Agreement. Awaiting Lee Family and VA Hospital to respond. Received the go-ahead from VA hospital.
NAC to start Aug. 13.
Bus Pullouts Package 13 RTA38j Holder
- Speedway / Wilmot EB
- Speedway / Euclid EB
- Speedway / Swan EB
- Speedway / Swan WB
- Swan / Speedway SB
Design
R/W
100%
97% 10/2009 11/2009 04/2010 N/A 8/10
Stantec - 75% Property Owner ltrs. sent 4-26-2010. Cont. mod #1 for Utility Coord. approved 4-26-2010. Cont. extended to 7-9-2010.
Cultural Resource Clearance Waivers requested 7-1-10. Contract extended to 2-11-10 for post design services. 100% mylars due week of
11-15-10. Environmental Clearance requested 11-24-10. Mylars submitted & approved. 100% utility ltrs. sent3-25-11. RW acquisition bids
due 4-29-11. Design Cont. Mod. #4 extended to 10-30-11 for post design services. DOWL selected for RW acquisition. R/W nego.
ongoing. Met w/ 4D & Pizza Hut re. 4 pking. spaces and agreed to leave them in. Stantec modified plan. Also making a minor modification
to Swan / Speedway SB take at Ambassador Diamond Jewelers. Gee Family & 828 Investors is complete. Waiting on four acquisitons at
Speedway/Swan to complete.
Bus Pullouts Package 14 RTA38j Holder
- 6th Ave. / 39th SB
- 6th Ave. / 39th NB
- 6th Ave. / 36th NB
- 6th Ave. / 29th SB
- 6th Ave. / 29th NB
- 6th Ave. / 26th NB
Design
R/W
100%
92% 10/2009 01/2010 05/2010 N/A 9/10
AECOM - Cont. Mod. #1 for Utility Coord. approved 4-19-2010. Cont. extended to 7-30-2010. 75% Prop. Owner ltrs. sent 5/10. Property
owner issues being discussed. Design consultant finalizing plans. Traffic signal & street light mods being reviewed by COT Electric Shop.
S. Tucson working on Environmental Clearance. (complete) Design Cont. Mod. #3 extended to 11-30-11 for post design services. Moving
forward W.O. electric shop review. Mylars due week of 5/16/2011. Mylars at Tucson Water for approval. Request for R/W acqusition bids
to go out 6-2-11. Westland selected for RW acquisition & appraisels ongoing (complete). Mylars @ S. Tucson for signatures.(complete).
Offers of Just Comp. signed by RTA. Offers have been made. Westland transfering remaining contract to DOWL. Torres/Chanez
acquisition complete. Others ongoing. Glass might be a condemnation. O'neill is refusing to sign. Corresponding with Glass's condemnation
attorney.
Bus Pullouts Package 15 RTA38j Holder
Oracle Rd. / Rudasill Rd. SB
Oracle Rd. / Lavery Lane SB
Oracle Rd. / C. Adobes Dr SB
Oracle Rd. / C. Adobes Rd NB
Oracle Rd. / Cresta Loma SB
Oracle Rd. / Cresta Loma NB
Oracle Rd. / Las Lomitas SB
Oracle Rd. / Las Lomitas NB
Design
R/W
25%
N/A 03/2012
KHA - RTA Board approved contract Jan 26, 2012. Awaiting approvals. N/P is March 5, 2012. Survey is complete. R/W being reviewed.
Due date 9/31/12.
Project Name/Description RTA #
RTA Roadway Element - Planning / Design
Project Name/Description RTA #
RTA Roadway Element - ROW / Construction
Project Name/Description RTA #
RTA Safety Element
Speed Alert Monitor Systems 40g
Joel
Gastelum Under
Development N/A
IGA has been recorded. In contact with
Contractor awaiting cost estimates
31st and 6th Ave. Pedestrian Crossing 36
Joel
Gastelum Complete May-10
Project Complete.Submitted final
invoice
34th St. and 6th Ave. Pedestrian Crossing 36
Joel
Gastelum Complete May-10
Project Complete.Submitted final
invoice
26th and 10th Ave Pedestrian Crossing 37ao
Joel
Gastelum
Under
Development
ADA Upgrades 37ap
Joel
Gastelum
Under
Development
4th Avenue Streetlight Project
Joel
Gastelum
Under
Development
Project Name/Description RTA #
RTA Environment & Economic Vitality Element
El Paso and Southwestern Railroad Greenway 41
Mick Jensen/
Joel
Gastelum Design
Collaborative project between City of
Tucson, City of South Tucson and
Pima County. Sage Landscaping has
been selected for the design concept
report of Greenway.
36th Street Greenway Element 41
Joel
Gastelum Complete 8-Oct May-10 Project Complete
% Phase
Compl
Right-of-Way100%
Posses-
sion
100%
Acquired
Date
Mobilized
Construction
Date
Complete
% Contract
Complete Contractor
PACE Electrical
Construction Inc.
PACE Electrical
Construction Inc.
Date
Complete Contractor
Design Construction
Design
StartedDesign
Complete
Project
Bid Date
Project Status as of Febrary 2012
MONTHLY REPORT - City of South Tucson
Project
Mgr
Current
Phase
% Phase
Compl
Planning Design
Start
Date End Date
Start
Date
60 % Plans
End
90%
Plans
PS&E
End
30%
Plans
Project Status as of February 2012
Project
Mgr
Current
Phase
Project Status as of February 2012
Project Status as of February 2012
Project
Mgr
Current
Phase
% Phase
Compl
Project
Mgr
Current
Phase
% Phase
Comply
PACE Electrical
Construction Inc.
Date
Mobilized
Design Construction
Design
Started
Design
Complete
Project
Bid Date
Date
Mobilized
Date
Complete Contractor
Borderland
MONTHLY REPORT - Tohono O'odham Nation
Project Name/Description RTA # Project Status as of April 2012
RTA Roadway Element - Planning / Design
San Xavier Path Mission Gateway-SRTS 41 Michael BendsDesign 30% 06/2009 06/2010 07/2010
Primary consultant terminated in July 2011;
new primary consultant was hired on August
30, 2011. Changed SOW to avoid
archaeological site; ADOT has distributed
consultation letters and waiting for responses.
Currently, working with BIA on ROW issues.
San Xavier Road - Little Nogales to I-19 41 Lisa Westerbeck Planning 15% 06/2010
ADOT and SXD are still negotiating language
on the Joint Project Agreement. Since the
project is not within ADOT ROW and Indian
sovereignty is at stake and an agreement has
not been made. Project design has not begun.
Project Name/Description RTA # Project Status as of March 2012
RTA Roadway Element - ROW / Construction
Project Name/Description RTA # Project Status as of March 2012
RTA Safety Element
Project Mgr
Current
Phase
% Phase
Compl
Design Construction
Construction
Date
Mobilized
Date
Complete ContractorProject Mgr
Current
Phase
% Phase
Compl
Design
Design
StartedDesign
Complete
Project
Bid Date
90%
Plans
PS&E
End
Construction
Date
Mobilized
Date
Complete
% Contract
Complete ContractorProject Mgr
Current
Phase
Design
Start
Date
End
Date
Start
Date
30%
Plans
60 %
Plans Project Mgr
Current
Phase
% Phase
Compl
Planning
% Phase
Compl
Right-of-Way100%
Posses-
sion
100%
Acquired
Project Name/Description RTA # Project Status as of March 2012
RTA Environment & Economic Vitality Element
Completed Projects
San Xavier Mission Plaza Pedestrian
Improvements
Nathan
Barrett
Post-
Construction
100% 04-2007 11-2009 10-2008 01-2009 09-2009 COMPLETE
Project
Bid Date
Date
Mobilized
Date
Complete Contractor
Sahara Development, Inc.
Project Mgr
Current
Phase
% Phase
ComplDesign
StartedDesign
Complete
RTA Project Totals
through July 31, 2012
Complete 10
Under Construction 7
In Design 13
Complete 102
Under Construction 1
In Design 8
Complete 87
Under Construction 2
In Design 12
Complete 56
Under Construction 8
In Design 30
Complete 7
Under Construction 0
In Design 4
Complete 58
Under Construction 0
In Design 0
Total Complete 310
Total Under Construction 11
Total In Design 54
Complete 79
Under Construction 3
In Design 9
Complete 7
Under Construction 0
In Design 3
Total Complete 86
Total Under Construction 3
Total In Design 12
Downtown/University high-capacity transit (Streetcar)
Complete 0
Under Construction 1
In Design 0
Park-n-Ride Transit Centers
Complete 6
Under Construction 0
In Design 1
Weekday evening
Completed 21
In Process 0
Weekday Service
Completed 23
In Process 0
Bus Frequency & Overcrowding Relief
Completed 6
In Process 0
Transit Corridor Bus Pullouts
At-grade Railroad Safety/Bridge Deficiencies
Signal Technology Upgrades to Improve Intersection Traffic Flow
Road Element
Safety Element
Intersection Safety and Capacity Improvements
Environmental and Economic Vitality Element
Greenways, Pathways Bikeways, and Sidewalks
Sub Total Safety Element
Elderly and Pedestrian Safety Improvements
Sub Total Environmental and Economic Vitality Element
Transit Element
*Includes Completed Temporary
lots
Transportation-related Critical Wildlife Linkages
RTA Project Totals
through July 31, 2012
Special Needs
Completed 3
In Process 0
Neighborhood Circulator
Completed 11
In Process 0
Express Service
Completed 7
In Process 0
Maintenance Storage Facility
Completed 1
Under Construction 0
Sub Total Transit Element
Total Complete 78
Total Under Construction 1
Total In Design 1
Grand Total
Total Initiated 586
Total In Design 80
Total Under Construction 22
Total Complete 484
*Numerous minor projects are not included i.e. ADA Accessibility Ramps
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments 177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Transportation Planning Committee Wednesday, September 5, 2012
Agenda Packet Memo Road Maintenance in the PAG Region Background:
While PAG owns no roadway infrastructure of its own, the agency coordinates a regional pavement management program. This role has included ensuring compatibility of pavement management databases and information collection techniques among PAG member agencies. This program has shown a proactive approach to coordinating regional pavement data collection among its member agencies. However, individual jurisdiction investment in pavement maintenance throughout the region has varied widely. Discussion Points: PAG has prepared a paper to address the current state of road maintenance in the region, with emphasis on effective strategies for preventative maintenance and funding availability. The paper describes current pavement management activities in the region, the general condition of public streets, and proposes recommendations for a regional approach to preventative maintenance for pavement. A presentation on the paper will be provided. Recommendation: The Committee is asked to review and discuss the item and its next steps.
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments 177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Transportation Planning Committee
Wednesday, September 5, 2012
Agenda Packet Memo
Subject: MAP-21
Background:
The Moving Ahead for Progress in the 21st Century Act (MAP-21) is the new transportation funding bill that will govern United States federal surface transportation spending for the next two years. It was passed by Congress on June 29, 2012, and signed by the president on July 6.
Discussion Points:
The bill provides for the use of $105 billion through the end of the 2014 fiscal year, and does not significantly alter total transportation funding from the previous transportation bill. It does, however, include many significant reforms and changes from the previous funding bill, SAFETEA-LU.
Some of these differences include:
• a reduction in the total number of funding programs
• reforms aimed at making the environmental review process more streamlined
• consolidation of bicycle and pedestrian transportation funding into a single program called Transportation Alternatives
• the development of a national freight policy. Specific impacts to the PAG region are still being evaluated. PAG staff will present on possible MAP-21 impacts to the region. Recommendation: This is a discussion item only.
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments
177 N. Church Ave., Transamerica Building
5th Floor Main Conference Room, Suite 501
Transportation Planning Committee
September 5, 2012
Agenda Packet Memo
SUMMARY OF REGIONAL TRANSPORTATION STUDIES
Background:
PAG provides quarterly updates to the Transportation Planning Committee on
transportation related studies being conducted in the region. The update will include a
brief summary of the study and its goals, as well as a brief description of the project status.
If you know of any current studies that are not listed here, and that may be of interest on a
regional level, please let us know and we will include the study in the next update.
Discussion and Recommendation:
This is an information item.
ADOT Statewide Bicycle and Pedestrian Plan:
Summary:
The Arizona Statewide Bicycle and Pedestrian Plan serves to provide a long-term plan for a
system of shared roadways and bicycle and pedestrian facilities for the ADOT State
Highway System. The Plan will guide ADOT in making transportation decisions, which
impact bicycling and pedestrian activities, and improve the accommodation of non-
motorized modes of transportation throughout the state. In addition, the Plan will
recommend policies, design, and maintenance guidelines for consideration by all
implementing agencies in Arizona.
Status:
TAC meeting #2 was held in early April to finalize the goals of the study and discuss needs
and deficiencies of the statewide system and programs. The consultants are currently
compiling the current conditions. The next major component of the study will be public
outreach. There will be an online survey that can be completed by anyone during the
month of May to gather input on bicycle and pedestrian issues statewide. The next
working paper will contain recommendations on activities that will help achieve the vision
and goals identified in as part of the plan update.
Freight Framework Study:
Summary:
The freight framework study is a joint effort between MAG, CAAG, and PAG. The study will
identify current trends in freight transportation in the Sun Corridor, and recommend ways
to improve freight transportation capacity and efficiency throughout the mega-region
between Phoenix and Tucson. MAG is lead agency on this project.
Status:
The Study has identified 15 freight ‘‘hot spots,’’ defined as areas with current or future
potential for heavy freight use. Of the 15 hot spots, the study team has chosen 4 for
further analysis and including transportation infrastructure, land use, commodity flows,
market analysis, and so forth. This deeper analysis will include the area around Tucson
International Airport.
ADOT Route Transfer Procedures Study
Summary:
The Arizona State Highway System includes a number of routes that do not function as
State Highways. ADOT has indicated that state highways that do not contribute to the
mission and purpose of the system create problems for ADOT and for transportation in
Arizona because they use resources that could be used to meet statewide needs, generate
administrative and liability costs, and may interfere with the vision and goals of local
jurisdictions.
The overall goal of the project is to develop a process that identifies eligible routes for
transfer from the State highway system to a local jurisdiction. The study will also develop
a process for identifying the jurisdiction responsible for specific improvements prior to
route transfer and on-going maintenance after the transfer. Finally, the study will
recommend policies that will clarify how ADOT and the State Transportation Board will
deal with key issues in route transfers.
Status:
A draft manual has been completed and has been reviewed by stake holders (including
PAG). The manual includes consideration of transfers in both directions------from state to
local jurisdiction, and from local to state jurisdiction. The manual is being presented to
each of the ADOT Engineering Districts in the state. The project is scheduled to be
complete by mid-September.
Pedestrian Compatibility Study: SR86 from MP112 to MP115 (Sells):
Summary:
This study will examine SR 86 through the Town of Sells with the goal of improving overall
pedestrian safety. The study will analyze the best location to place bridges over a
drainage channel, appropriate crossing treatments and the need and feasibility of
sidewalks or a shared-use path along the roadway.
Status:
The final draft of this study was available to the TAC members with some TAC members
expressing concerns with the final product. The consultant team is setting up a meeting to
discuss the final draft.
North-South Corridor Study (Pinal County)
Summary:
The Arizona Department of Transportation and Federal Highway Administration are
studying the area between US 60 in Apache Junction and I-10 near Eloy and Marana. The
purpose of the study is to identify and evaluate a possible route to provide a connection
between these two areas.
This study has elicited significant interest from the public and other stakeholders.
Approximately 55,000 post cards were sent out and over 400 responses have been
received.
Currently there are several alignments being considered. The goal is to narrow it down to
three or four options. There is also communication taking between the FTA and FRA and
the ADOT Intercity Rail Study.
Status:
The last team meeting for the project was held March 6, 2012. Currently, the team is
working on consensus on which route alternatives to move forward with for the EIS.
Seventeen impact criteria have been established for choosing the route alternatives.
Those with the lowest ratings based on the established criteria will be eliminated from
consideration.
The corridor will be split into 6 zones for consideration in to the EIS:
a. Zone 1: US 60 to Ocotillo Road
b. Zone 2: Ocotillo Road to Arizona Farms Road
c. Zone 3: Arizona Farms Road to SR 287
d. Zone 4: SR 287 to Martin Road
e. Zone 5: Martin Road to Florence Boulevard
f. Zone 6: Florence Boulevard to I-10
The study team plans to finalize the Alternative Selection Process at the April meeting. The
April meeting was subsequently canceled.
I-10: Junction I-19 to SR 83 and
SR 210: Golf Links Road to I-10
Summary:
Improving mobility along I-10 southeast of downtown Tucson has been a major goal of
ADOT, the City of Tucson, Pima County and PAG. This project consists of two phases; the
first phase will examine many alternatives, study each one closely, and identify those
which will be carried forward into the next phase. Phase two will advance the study to the
DCR and EA stages focusing on I-10 from I-19 to SR 83, an area expected to become more
urbanized in the future.
Status:
A meeting with project partners and DM Air Force Base was held on March 14, 2012. DM
Air Force Base presented several concerns regarding security concerns and the clearances
required for their airfield on the proposed System Alternatives in the initial report by the
consulting team. Several potential solutions were discussed with DM Air Force Base
Engineers. The project team will consider the issues brought forward by the DM Air Force
Base and work on the alignments on the System Alternatives that minimally impact
DMAFB. At the next stages of the project, the DCR, further analysis of the envelope
required by DMAFB will be provided along with more detailed maps of System
Alternatives.
Status:
The final DCR and EA report is complete and available on the ADOT website.
I-10: Tangerine Road to Ina Road corridor study
Summary:
The Arizona Department of Transportation and Federal Highway Administration are
beginning an engineering and environmental study of Interstate 10 between Tangerine
Road and Ina Road. The goal for this study is to develop a long-range plan for providing an
improved roadway for general traffic, commuters and truck traffic traveling along this
portion of the I-10 corridor. To support that goal, the study will:
• Develop and evaluate possible alternatives for widening I-10.
• Develop and evaluate possible alternatives for reconstructing the Cortaro Road
and Avra Valley Road interchanges to provide grade-separated crossings with the
Union Pacific Railroad (UPRR).
• Look at potential improvements to frontage roads in the study area.
The study will include:
• An Alternative Selection Report (ASR) to identify and assess possible alternatives,
including the consequences of not making any improvements along this corridor
(no-build alternative).
• A Design Concept Report (DCR) to document the preferred alternative.
• An Environmental Assessment (EA) to document public and agency outreach and
the potential impacts to the social, economic and natural environments.
• A Corridor Implementation Plan for recommended improvements.
Status:
A public meeting will be held on May 2, 2012 to introduce the study alternatives, present
information, and provide the opportunity for the public to ask questions and provide
input.
SR 77: Tangerine to Pinal County Line (Oro Valley)
Summary:
ADOT, the Federal Highway Administration and the Regional Transportation Authority are
working together to improve traffic flow and enhance safety along State Route 77, also
known as Oracle Road. This study is evaluating improvements, including widening the
road from two lanes to three lanes in each direction, on Oracle Road between Tangerine
Road and the Pinal County Line.
These new improvements will tie into the recently completed improvements on Oracle
Road between Calle Concordia and Tangerine Road. The current phase for this project
began in 2004, and public meetings were held on June 28, 2005, and January 27, 2009.
Input from these meetings and other contacts were used in the development of the
design concept report and environmental assessment documents.
Status:
The project has commenced Stage IV design.
The issue of constructing a noise wall was voted on by residents being affected. In January
2012, voting was closed after a reasonable attempt to gather votes from all resident
abutting the noise wall. The vote was to construct a noise barrier wall with the project
along the stretch where homes will be affected. A meeting was held April 18, 2012 to
review sound wall plans and preview renderings.
A team progress meeting was held on April 2, 2012. Cultural clearances are still under
review.
On April 10, 2012 an amendment to increase funding for the Wildlife Crossings by $3.005
was recommended for approval. This item will be covered by the TIP Subcommittee report
to the TPC.
This project is scheduled to start construction in mid calendar year 2013. The draft STIP
moved construction on this project to FY 2014. This action should only cause a month or
delay for the project.
Sahuarita Corridor Study
Summary:
The Sahuarita Corridor study will examine possible east-west corridor alignments in
Sahuarita, including El Toro Road, from Mission Road to SR 89. The study is the direct
result of a 2010 Small Area Transportation Study conducted by Kimley-Horn on behalf of
the Town of Sahuarita. .
The result of the new Study will set the stage for a future preliminary design of an east-
west corridor, and will assist in justifying funding for additional corridor planning and
engineering. Additionally, the Study will enable the Town to initiate other planning
assessments for the region, including the preservation of right of way, a critical factor to
the preferred alternative.
Status:
The project team is currently evaluating possible corridor alternatives
and developing performance measures to compare the various
alternatives.
University of Arizona Bicycle and Pedestrian Study
Summary:
In partnership with UA, Pima County, and the City of Tucson, PAG has contracted with a
consultant to produce a comprehensive study to enhance bicycle and pedestrian
circulation within the U of A campus, while creating seamless links with the surrounding
community.
The goals of the study are to reduce the risk of collision, improve existing infrastructure,
develop design standards, increase bicycle and pedestrian mode shares, increase bicycle
and pedestrian safety, and to create an implementable plan.
Status:
Tech Memo #2 was distributed to the TAC which includes preliminary recommendations
based on the public input that was provided in January. The consultant is responding to
feedback from the TAC members and is drafting a final report which will include an
implementation plan. The final draft will be available in early June and Alta Planning will
be in town June 12-14th to do presentations. There will be a public workshop on June 14th
from 6-7:30 p.m. at the UA Swede Johnson Building,
ADOT Statewide Bicycle Economic Impact Study
Summary:
According to the U.S. Department of Transportation, between 1999 and 2010 the Federal
Highway Administration invested nearly $132 million in Arizona for ‘‘stand-alone’’ bicycle-
and pedestrian-specific facilities (not including facilities constructed as part of a larger
road project such as paved shoulders or bicycle buffers at intersections). This funding has
served to improve the safety and convenience of bicycling for Arizona residents, as well as
attract non-resident bicycle tourists.
The League of American Bicyclists has ranked Arizona number 16 in the nation for
bicycling in 2011 and Arizona is one of only ten states designated by the League as a
‘‘Bicycle Friendly State.’’ They note that ‘‘Arizona plays host to many great recreational and
encouragement events. El Tour de Tucson and the Great Arizona Bicycle Adventure, a
multi-day ride that starts in Northern Arizona and terminates at the Mexico border are
must-do events for cycling enthusiasts from around the world.’’ Arizona is home to eight
of the League’s ‘‘Bicycle Friendly Communities’’ including Chandler, Flagstaff, Gilbert,
Mesa, Sedona, Scottsdale, Tempe, and Tucson & East Pima Region.
The study will divide the impact by counties; therefore, we will have a good understanding
of the impact in Pima County. This will complement an existing study the UA Eller College
has been working on.
Status:
The state has also kicked off another major effort related to bicycling. The study aims to
quantify the economic impact bicycling activity brings to Arizona. After a competitive
process, the consultant team consisting of McClure Consulting LLC, Kimley-Horn and
Associates, Inc. and Economic & Policy Resources, Inc. were selected to develop the study.
This is an objective study with a defensible methodology and approach. The study will
look at two main elements: A. The bicycle industry (manufacturing, sales, and service) as
measured by revenue and employment, and B. Bicycle tourism and visitor spending
associated with events that include organized tours, races, and charity rides. The timeline
for the study indicates it will be finished in February 2013.
Passenger Rail Study
Summary:
The Arizona Department of Transportation (ADOT) Passenger Rail Corridor Study is
continuing study of high capacity regional transportation to move passengers between
the Cities of Phoenix and Tucson. This study builds on previous work performed by ADOT
and other agencies. Because federal funds are being used to fund the work program, and
federal funds will likely be sought to help implement a preferred alternative, an
environmental document is being prepared to satisfy requirements of the National
Environmental Policy Act (NEPA).
The Federal Railroad Administration (FRA) and Federal Transit Administration (FTA) are
providing funds for this study. The agencies are designated as co-federal lead agencies for
the study process. NEPA contains certain requirements that all federal agencies must
follow. This project is designed to meet both FRA and FTA requirements to recommend a
preferred alternative for a fixed guideway project to improve the intercity connectivity and
the commuter mobility within urban areas in the same study area.
Status:
Currently, the study has completed project scoping and is now in the initial screening
process to identify the project corridor, stations and type of service
Arizona-Sonora Border Master Plan
Summary:
The Arizona Department of Transportation and Federal Highway Administration are
working collaboratively with the State of Sonora, Mexico, the Secretaria de Relaciones
Exteriores, the Secretaria de Comunicaciones y Transportes and several other local, state
and federal agencies to develop an Arizona-Sonora Border Master Plan (BMP).
The need for an integrated transportation master plan to improve the efficiency and
effectiveness of cross-border traffic prompted the need for this BMP. Arizona has a total of
six Ports of Entry (POE) along its border with Mexico. In 2010, more than 23 million people
were processed through these border crossings. At each POE, heavy congestion and
security issues affect daily pedestrian, commercial and vehicular traffic traveling across the
border.
Upon completion, the BMP will include a prioritized list of recommended Arizona-Sonora
border related infrastructure projects and document their readiness for funding and
implementation. The BMP study area extends along the entire Arizona-Sonora border,
which incorporates a wide range of international jurisdictions, including federal, tribal,
state, county and city governments on both sides of the border.
Status:
The first two working papers have been completed. Working paper #1
describes current conditions of transportation infrastructure and studies
within the study area. Working paper #2 describes the current
conditions of Arizona’s Land Ports of Entry (LPOEs).
Currently, the project team is developing criteria for ranking and
prioritizing projects within the focus area (an area between 10 and 25 on
either side of the international border).
Pima Association of Governments 177 N. Church Ave, Suite 405, Tucson, AZ 85701 (520) 792-1093 [tel] (520) 620-6981 [fax] www.pagnet.org [web]
Pima Association of Governments
177 N. Church Ave., Transamerica Building 5th Floor Main Conference Room, Suite 501
Transportation Planning Committee Wednesday, Sept. 5, 2012
Agenda Packet Memo Transportation Finance Subcommittee Background: The Transportation Finance Subcommittee holds monthly meetings to develop, review and assess the financial plan needed for the Transportation Improvement Program (TIP) and the Regional Transportation Plan (RTP). Discussion Points: The Transportation Finance Subcommittee chair or representative will report on the Sept. 5, 2012, meeting.
Recommendation:
This is an information item.