Transportation Advisory Board 12/4/2012

37
Peoria/Riverside Alternatives Analysis Briefing City of Tulsa Transportation Advisory Board December 4, 2012

Transcript of Transportation Advisory Board 12/4/2012

Page 1: Transportation Advisory Board 12/4/2012

Peoria/Riverside Alternatives Analysis BriefingCity of Tulsa Transportation Advisory Board

December 4, 2012

Page 2: Transportation Advisory Board 12/4/2012

Project Background

12/4/2012 2

Page 3: Transportation Advisory Board 12/4/2012

Tulsa Transit Ridership by Route

12/4/2012 3

47,542

48,808

80,434

86,605

89,823

113,795

126,842

130,593

130,885

134,342

161,348

166,885

171,187

190,378

260,717

315,269

458,559

306

471

118

318

117

215

203

251

111

114

100

221

210

112

101

222

105

FY12 Ridership

Page 4: Transportation Advisory Board 12/4/2012

Adopted Regional Transit System Plan (October 2011)

12/4/2012 4

Peoria/Riverside Corridor

20.2 Miles

Residents: 56,000 (1 in 7)

Jobs: 52,000 (1 in 5)

5,700 TOTAL daily trips to/from downtown (13%)

Page 5: Transportation Advisory Board 12/4/2012

Major Activity Centers

12/4/2012 5

Tulsa Tech

Blair Property Park

Cherry Street

Mabee Center/ORU Brookside

Downtown

Utica Square

St. John & Hillcrest

Page 6: Transportation Advisory Board 12/4/2012

PlaniTulsa Comprehensive Plan

12/4/2012 6

The Big “T”

Page 7: Transportation Advisory Board 12/4/2012

Trip Destinations

12/4/2012 7

Destinations for All trips on Route 105 Destinations for Work trips on Route 105

Source: INCOG Ridership Survey, Jan. 2010

Page 8: Transportation Advisory Board 12/4/2012

Ride Check Survey

12/4/2012 8

• April 24-26, 2012

(Tuesday – Thursday)

• 9 Routes surveyed

• Survey included 64% of total ridership, of which 25% was on Route 105 (Peoria)

Page 9: Transportation Advisory Board 12/4/2012

Ride Check Survey

12/4/2012 9

• Major stops at Pine, DAS, 41st

Street, 61st Street, and 81st

Street

• 4,000+ benefitting riders

• 20% flag stops (5% of riders)

Grouping On Board + Boardings

N Peoria + S Peoria 1,681

N Peoria + Downtown 2,819

S Peoria + Downtown 3,728

All Segments 4,114

Page 10: Transportation Advisory Board 12/4/2012

Public Involvement

12/4/2012 10

Page 11: Transportation Advisory Board 12/4/2012

Public Involvement

12/4/2012 11

Steering Committee Initial Meeting (June)

Initial round of public meetings July 16th & 17th

Targeted Neighborhood Outreach

Page 12: Transportation Advisory Board 12/4/2012

Public Involvement

12/4/2012 12

985 postcards sent to Businesses

72 Personal Letters to Neighborhood Leaders

Page 13: Transportation Advisory Board 12/4/2012

Public Involvement

12/4/2012 13

Big Ideas for Public Comments

• We need to ensure service for North Tulsa.

• Be conscious of where bus stops are placed.

• Better frequencies.

• Outreach to North Tulsa churches.

Page 14: Transportation Advisory Board 12/4/2012

Bus Rapid Transit

12/4/2012 15

Branded Buses Off-Board Fare Collection

Passenger InformationEnhanced Boarding Platforms

Page 15: Transportation Advisory Board 12/4/2012

Operating Characteristics for Bus Rapid Transit

Service & Amenities Options

• Less Time between buses:– 10 minutes in peak periods

– 15 minutes in off-peak

• 6am to 8pm Service Hours

• Low Floor, CNG Fueled Buses

• Traffic Signal Priority for Buses

• Passenger Shelters and Benches

• Next Bus Arrival Signs

• Pedestrian and Bicycle Amenities

• Branded Stops and Vehicles

• Stops Spaced Blocks ½-mile to 1 mile

12/4/2012 16

Page 16: Transportation Advisory Board 12/4/2012

The Spur – Ft. Worth, TX

12/4/2012 17

Page 17: Transportation Advisory Board 12/4/2012

The Spur Line – Ft. Worth, TX

12/4/2012 18

Page 18: Transportation Advisory Board 12/4/2012

12/4/2012 19

The Spur Line – Ft. Worth, TX

Page 19: Transportation Advisory Board 12/4/2012

Shelters & Passenger Information

12/4/2012 20

Page 20: Transportation Advisory Board 12/4/2012

Stop Types

12/4/2012 21

Page 21: Transportation Advisory Board 12/4/2012

Menu Exercise

12/4/2012 22

Page 22: Transportation Advisory Board 12/4/2012

Recommendations

12/4/2012 23

Geography• Preferred limits from E.

66th St N. to E. 81st St S.

Alignment & Stations• Connection to DAS via 6th

Street• Alignment Options: • Peoria Ave vs. Utica Ave. (from

E 6th ST to E 21st ST)

• Multiple station platform shelter footprints & amenity options

Page 23: Transportation Advisory Board 12/4/2012

Recommendations

• Technology & Infrastructure– Pedestrian improvements needed

surrounding stations

– Traffic signal priority, real-time arrival, automated ticket vending at select locations

• Operating Conditions– M-F: 5:30am – 8:30pm; 10 minute

peak / 15-min off-peak frequency

– Only local service on Saturday & Sunday (no BRT)

• Funding– Capital: 50/50 Federal/Local, FTA

Very Small Starts (VSS) or TIGER Grants

– Operations: Local funding

12/4/2012 24

Page 24: Transportation Advisory Board 12/4/2012

Connecting to the Existing Route System

12/4/2012 25

Page 25: Transportation Advisory Board 12/4/2012

Station Concept Examples

12/4/2012 26

•12 ft Concrete platform

•Benches and/or leaning rails

•Bicycle racks, trash cans

•Branded, BRT signage and passenger information

Page 26: Transportation Advisory Board 12/4/2012

Station Concept Examples

12/4/2012 27

• 20 ft Concrete platform

•Station canopy and structural framing support

•LED lighting beneath station canopy

•Benches and / or leaning rails, bicycle racks, trash cans

•Branded, BRT signage and passenger information

•Allowance for public art incorporated into amenities

Page 27: Transportation Advisory Board 12/4/2012

Station Concept Examples

12/4/2012 28

•35 ft Concrete platform

•Station canopy and structural framing support

•LED lighting beneath station canopy

•Benches and / or leaning rails, bicycle racks, trash cans

•Branded, BRT signage and passenger information

•Allowance for public art incorporated into amenities

Page 28: Transportation Advisory Board 12/4/2012

Station Improvement Levels

12/4/2012 29

Page 29: Transportation Advisory Board 12/4/2012

Station Example - Enhanced

12/4/2012 30

Page 30: Transportation Advisory Board 12/4/2012

Station Example - Improved

12/4/2012 31

Page 31: Transportation Advisory Board 12/4/2012

Station Example - Local

12/4/2012 32

Local Example

Page 32: Transportation Advisory Board 12/4/2012

Conceptual Station Area

12/4/2012 33

Page 33: Transportation Advisory Board 12/4/2012

Capital & Operating Cost Estimates

12/4/2012 34

Page 34: Transportation Advisory Board 12/4/2012

The Challenge

12/4/2012 35

5% of MTTA Operating Budget ($900k)

At least 3,000 benefiting riders10 min. headways during peak/15 off peak

Very Small Starts Project Proposal

Page 35: Transportation Advisory Board 12/4/2012

Capital & Operating Costs

12/4/2012 36

Preliminary Capital Cost: $20 – 25M*Potential 50%-80% share from Federal Transit Administration

Preliminary Annual Operations costs: $750,000 to $1.5 Million*

*Cost estimate subject to change as project progresses into preliminary engineering

Page 36: Transportation Advisory Board 12/4/2012

Next Steps

12/4/2012 37

November 9 – Peoria Alternatives Analysis Steering Committee #2

• December 4 – Presentation to the City of Tulsa Transportation Advisory Board

• January 7 and 8, 2013 – 2nd Round of Public Meetings (feedback on

Locally Preferred Alternative)

• February 2013 – Steering Committee Selects Locally Preferred Alternative

• March 2013 – Endorsement of LPA by MTTA Board, INCOG Transportation Policy Committee and Tulsa City Council

• Summer 2013 – Submit application for funding to Federal Transit Administration (contingent on local funding commitment)

Page 37: Transportation Advisory Board 12/4/2012

Questions & Discussion

12/4/2012 38

James Wagner, AICP

Transportation Projects Coordinator

INCOG

(918) 579-9447

[email protected]

Viplav Putta

Transportation Planning & Programs Manager

INCOG

(918) 579-9421

[email protected]