TransNet Independent Taxpayer Oversight Committee

118
TransNet Independent Taxpayer Oversight Committee Special Session: Please Note Meeting Date Wednesday, October 16, 2019 9:30 a.m. to 12 noon 401 B Street, San Diego 7th Floor Conference Room Agenda Highlights FY 2021 TransNet Triennial Performance Audit Subcommittee Selection North Coast Corridor Program Status Update Please silence all electronic devices during the meeting Mission Statement The 18 cities and county government are SANDAG serving as the forum for regional decision-making. SANDAG builds consensus; makes strategic plans; obtains and allocates resources; plans, engineers, and builds public transit; and provides information on a broad range of topics pertinent to the region’s quality of life. San Diego Association of Governments 401 B Street, Suite 800, San Diego, CA 92101-4231 (619) 699-1900 Fax (619) 699-1905 sandag.org

Transcript of TransNet Independent Taxpayer Oversight Committee

TransNet Independent

Taxpayer Oversight Committee

Special Session: Please Note Meeting Date

Wednesday, October 16, 2019 9:30 a.m. to 12 noon

401 B Street, San Diego 7th Floor Conference Room

Agenda Highlights

• FY 2021 TransNet Triennial Performance Audit Subcommittee Selection

• North Coast Corridor Program Status Update

Please silence all electronic devices during the meeting

Mission Statement The 18 cities and county government are SANDAG serving as the forum for regional

decision-making. SANDAG builds consensus; makes strategic plans; obtains and allocates

resources; plans, engineers, and builds public transit; and provides information on a broad

range of topics pertinent to the region’s quality of life.

San Diego Association of Governments ⋅ 401 B Street, Suite 800, San Diego, CA 92101-4231

(619) 699-1900 ⋅ Fax (619) 699-1905 ⋅ sandag.org

2 120718

Welcome to SANDAG. Members of the public may speak to the TransNet Independent Taxpayer Oversight Committee (ITOC) on any item at the time the Committee is considering the item. Please complete a Request to Comment form located at the Clerk desk. Members of the public may address the Committee on any issue under the agenda item entitled Public Comments/Communications/Member Comments. Public speakers are limited to three minutes or less per person. The Committee may take action on any item appearing on the agenda.

Both agenda and non-agenda comments should be sent to the Clerk of the Committee via [email protected]. Please include the meeting date, agenda item, your name, and your organization. Any comments, handouts, presentations, or other materials from the public intended for distribution at the meeting should be received by the Clerk no later than 5 p.m. two working days prior to the meeting. All public comments and materials received by the deadline become part of the official public record and will be provided to the members for their review at the meeting.

In order to keep the public informed in an efficient manner and facilitate public participation, SANDAG also provides access to all agenda and meeting materials online at sandag.org/meetings. Additionally, interested persons can sign up for email notifications at sandag.org/subscribe.

SANDAG operates its programs without regard to race, color, and national origin in compliance with Title VI of the Civil Rights Act. SANDAG has developed procedures for investigating and tracking Title VI complaints, and the procedures for filing a complaint are available to the public upon request. Questions concerning SANDAG nondiscrimination obligations or complaint procedures should be directed to the SANDAG General Counsel, John Kirk, at (619) 699-1997 or [email protected]. Any person who believes himself or herself or any specific class of persons to be subjected to discrimination prohibited by Title VI also may file a written complaint with the Federal Transit Administration.

In compliance with the Americans with Disabilities Act (ADA), SANDAG will accommodate persons who require assistance in order to participate in SANDAG meetings. If such assistance is required, please contact SANDAG at (619) 699-1900 at least 72 hours in advance of the meeting. To request this document or related reports in an alternative format, please call (619) 699-1900 or (619) 699-1904 (TTY), or fax (619) 699-1905.

SANDAG agenda materials can be made available in alternative languages. To make a request, call (619) 699-1900 at least 72 hours in advance of the meeting.

Los materiales de la agenda de SANDAG están disponibles en otros idiomas. Para hacer una solicitud, llame al (619) 699-1900 al menos 72 horas antes de la reunión.

如有需要, 我们可以把SANDAG议程材料翻译成其他語言.

请在会议前至少 72 小时打电话 (619) 699-1900 提出请求.

SANDAG offices are accessible by public transit. Phone 511 or visit 511sd.com for route information. Bicycle parking is available in the parking garage of the SANDAG offices.

3

TransNet Independent Taxpayer Oversight Committee Wednesday, October 16, 2019

Item No. Action

+1. Approval of Meeting Minutes Approve

+1A. TransNet Independent Taxpayer Oversight Committee Meeting Minutes – Wednesday, September 11, 2019

+1B. TransNet Independent Taxpayer Oversight Committee Meeting Minutes – Monday, September 16, 2019

Estimated Start Time: 9:30 a.m.

2. Public Comments/Communications/Member Comments

Members of the public shall have the opportunity to address the TransNet Independent Taxpayer Oversight Committee (ITOC) on any issue within the jurisdiction of SANDAG that is not on this agenda. Anyone desiring to speak shall reserve time by completing a Request to Comment form and giving it to the Clerk prior to speaking. Public speakers should notify the Clerk if they have a handout for distribution to ITOC members. Public speakers are limited to three minutes or less per person. ITOC members also may provide information and announcements under this agenda item.

Estimated Start Time: 9:35 a.m.

3. Executive Director's Report

Hasan Ikhrata, SANDAG

Discussion

An update on key programs, projects, and agency initiatives, including San Diego Forward: The 2021 Regional Plan and the Airport Connectivity Subcommittee will be presented.

Estimated Start Time: 9:40 a.m.

Reports

4. Actions by the Transportation Committee and Board of Directors on TransNet-Related Agenda Items Ariana zur Nieden, SANDAG

Information

An update on actions taken by the Transportation Committee and Board of Directors on agenda items that the ITOC has reviewed will be presented.

Estimated Start Time: 9:55 a.m.

+5. FY 2021 TransNet Triennial Performance Audit Subcommittee Selection Chelsea Gonzales and Ariana zur Nieden, SANDAG

Appoint

The ITOC is asked to appoint its FY 2021 TransNet Triennial Performance Audit Subcommittee.

Estimated Start Time: 10 a.m.

+6. Independent Taxpayer Oversight Committee 2020 Meeting Calendar Ariana zur Nieden, SANDAG

Approve

The ITOC is asked to approve the ITOC 2020 meeting calendar. Estimated Start Time: 10:15 a.m.

+7. Proposed FY 2020 Program Budget Amendment: GObyBIKE San Diego: Construction Outreach Program Chris Kluth, SANDAG

Discussion

The ITOC is asked to consider the proposed budget amendment for consistency with the TransNet Extension Ordinance.

Estimated Start Time: 10:20 a.m.

4

+8. TransNet Environmental Mitigation Program: FY 2020 Annual Funding Kim Smith, SANDAG

Discussion

The ITOC is asked to discuss the proposed allocation of $4 million in funding for FY 2020 for regional land management and monitoring.

Estimated Start Time: 10:35 a.m.

+9. 2018 Regional Transportation Improvement Program: Amendment No. 8 Sue Alpert, SANDAG

Discussion

The ITOC is asked to provide feedback on the proposed Amendment No. 8, focusing its review on the TransNet-funded projects.

Estimated Start Time: 10:50 a.m.

+10. Mid-Coast Corridor Transit Project Update John Haggerty, SANDAG

Information

An update on the Mid-Coast Corridor Transit project will be presented. Estimated Start Time: 11:05 a.m.

+11. North Coast Corridor Program Status Update Allan Kosup, Caltrans

Information

An update on the North Coast Corridor program will be presented. Estimated Start Time: 11:20 a.m.

12. Continued Public Comments

If the five-speaker limit for public comments was exceeded at the beginning of this agenda, other public comments will be taken at this time. Subjects of previous agenda items may not again be addressed under public comment.

13. Upcoming Meetings Information

The next ITOC meeting is scheduled for Wednesday, November 13, 2019, at 9:30 a.m. Estimated Start Time: 11:35 a.m.

10. Adjournment

+ next to an item indicates an attachment

TransNet Independent Taxpayer Oversight Committee Item: 1A October 16, 2019

September 11, 2019, TransNet Independent Taxpayer Oversight Committee Meeting Minutes

Chair Kai Ramer (Licensed Engineer) called the meeting of the TransNet Independent Taxpayer Oversight Committee (ITOC) to order at 9:30 a.m.

1. Approval of Meeting Minutes (Approve)

Action: Upon a motion by Mr. Dustin Fuller (Biology/Environmental) and a second by Mr. Stewart Halpern (Finance/Budgeting), the ITOC approved the minutes from its July 10, 2019, meeting. Yes: Chair Ramer, Vice Chair Michael L. Kenney (Licensed Civil/Traffic Engineer), Mr. Fuller, Mr. Gregg Sadowsky (Right of Way Acquisition), and Mr. Halpern. No: None. Abstain: None. Absent: Contractor/Construction and Private Sector.

2. Public Comments/Communications/Member Comments

None.

Consent

4. TransNet Senior Mini-Grant Program: Quarterly Update (Information)

This report provided an overview of progress made by TransNet Senior Mini-Grant program.

5. TransNet Major Corridor and Regional Bikeway Program Projects: Quarterly Status Report (FY 2019, 4th Quarter) (Information)

This report provided an update on TransNet Major Corridor and Regional Bikeway program projects.

6. TransNet Smart Growth Incentive Program and Active Transportation Grant Program: Quarterly Update (Information)

This report provided an update on the TransNet Smart Growth Incentive Program and Active Transportation Grant Program.

7. TransNet Environmental Mitigation Program Land Management Grant Program: Quarterly Update (Information)

This report provided an update on the TransNet Environmental Mitigation Program Land Management Grant program.

8. 2018 Regional Transportation Improvement Program: Amendment No. 7 (Information)

The ITOC reviewed the 2018 Regional Transportation Improvement Program: Amendment No. 7, focusing on TransNet-funded projects.

9. Quarterly TransNet Financial Reports for the Period Ending June 30, 2019, and Other Financial Data (Information)

This report provided an overview of the financial status of the TransNet program.

Action: Consent Items Nos. 4 through 9 were presented for information only.

Action: Approve

The TransNet Independent Taxpayer Oversight Committee is asked to approve the minutes from its September 11, 2019, meeting.

2

Reports

10. Actions by the Transportation Committee and Board of Directors on TransNet-Related Agenda Items (Information)

Ariana zur Nieden, senior TransNet program manager, presented an update on actions taken by the Transportation Committee and Board of Directors on agenda items that the ITOC reviewed: San Diego Forward: The 2021 Regional Plan; Memorandum of Agreement with the City of Imperial Beach: TransNet Debt Financing program; 2018 Regional Transportation Improvement Program: Amendment No. 5; TransNet Senior Mini-Grant program; TransNet Active Transportation Grant program; Regional Transportation Improvement Program Delegation of Authority; TransNet Major Corridors program update; and Proposed FY 2020 Program Budget Amendment: Capital Improvement Program.

Action: Information only.

3. Executive Director’s Reports (Discussion)

Hasan Ikhrata, Executive Director, presented an update on key programs, projects, and agency initiatives, including San Diego Forward: The 2021 Regional Plan and the Airport Connectivity Subcommittee.

Action: Discussion only.

12. TransNet Major Corridors Program Update (Information)

José Nuncio, TransNet department director, presented an overview of cost and anticipated revenue information for the TransNet Major Corridors program.

Action: Information only.

13. Proposed FY 2020 Program Budget Amendment: Capital Improvement Program (Information)

Mr. Nuncio presented an overview of a proposed amendment to add $593.4 million to the FY 2020 Capital Program Budget to fund more than 30 projects spread among 12 corridors and regional programs.

A variation of the proposed budget amendment was also provided to ITOC members for review as prepared by Board of Directors Chair Steve Vaus and Escondido Mayor Paul McNamara, and distributed to Board members at their September 6, 2019, meeting.

ITOC members directed staff to schedule a special meeting of the ITOC to consider whether the proposed amendments would be consistent with the TransNet Extension Ordinance. ITOC members also requested that SANDAG general counsel prepare a memorandum considering whether the proposed budget amendments are consistent with the TransNet Extension Ordinance.

Action: Information only.

11. 2018 Regional Transportation Improvement Program: Amendment No. 6 (Information)

Sue Alpert, senior TransNet financial programming analyst, provided feedback on the proposed Amendment No. 6.

Action: Information only.

14. Quarterly Finance Report and Update on Financial Markets – Through June 2019 (Information)

André Douzdjian, director of finance, presented an update on the latest developments in the financial markets, economy, sales tax revenues, and strategies being explored and implemented to minimize possible impacts to the TransNet program.

Action: Information only.

3

15. Continued Public Comments

None.

16. Upcoming Meetings

The next ITOC meeting is scheduled for Wednesday, October 16, 2019, at 9:30 a.m.

17. Adjournment

Chair Ramer adjourned the meeting at 11:45 a.m.

Meeting Start Time: 9:30 a.m. Meeting Adjourned Time: 11:45 a.m.

4

Confirmed Attendance at SANDAG TransNet Independent Taxpayer Oversight Committee Meeting

September 11, 2019

Jurisdiction Name Attended

Licensed Engineer Kai Ramer, Chair Yes

Licensed Civil/Traffic Engineer Michael Kenney, Vice Chair Yes

Contractor/Construction Brad Barnum No

Biology/Environmental Dustin Fuller Yes

Finance/Budgeting Stewart Halpern Yes

Right-of-Way Acquisition Licensed Civil/Traffic Engineer

Gregg Sadowsky Yes

Private Sector Dick Vortmann No

Advisory Members

San Diego County Auditor’s Office Tracy Drager (Alternate) Yes

SANDAG Staff Members and Titles

Hasan Ikhrata, Executive Director Yes

Laura Cote, Chief Deputy Executive Director No

Jose Nuncio, TransNet Department Director Yes

Ariana zur Nieden, Senior TransNet Program Manager Yes

TransNet Independent Taxpayer Oversight Committee Item: 1B October 16, 2019

September 16, 2019, TransNet Independent Taxpayer Oversight Committee Special Meeting Minutes

Chair Kai Ramer (Licensed Engineer) called the special meeting of the TransNet Independent Taxpayer Oversight Committee (ITOC) to order at 9:35 a.m.

1. Public Comments/Communications/Member Comments

None.

2. Proposed FY 2020 Program Budget Amendment: Capital Improvement Program (Discussion/Possible Action)

John Kirk, general counsel, and José Nuncio, TransNet department director, presented the Proposed FY 2020 Program Budget Amendment: Capital Improvement Program.

The ITOC was presented with the proposed FY 2020 Capital Program Budget Amendment (staff proposal) and an Alternative Proposal reviewed by the Board of Directors on September 6, 2019, for consistency with the TransNet Extension Ordinance. A Revised Alternative Proposal as prepared by Board Chair Steve Vaus and Escondido Mayor Paul McNamara was also distributed to ITOC members at its September 16, 2019, meeting.

Action: Upon a motion by Mr. Stewart Halpern (Finance/Budgeting), and a second by Vice Chair Michael Kenney (Licensed Civil/Traffic Engineer), the ITOC unanimously approved a motion stating that, while no outside counsel was consulted, after a very considered review by the ITOC, with the assistance of the Office of General Counsel, ITOC concluded that the Staff Proposal appears consistent with the Ordinance, both in terms of project funding and priority. The ITOC commented that, while the spirit of their motion was not to state that the Revised Alternative Proposal be considered inconsistent with the TransNet Ordinance, the Revised Alternative Proposal was not received in time for the ITOC to provide an adequate assessment. Yes: Chair Ramer, Vice Chair Kenney, Mr. Dustin Fuller (Biology/Environmental), Mr. Halpern, Mr. Greg Sadowsky (Right of Way Acquisition). No: None. Abstain: None. Absent: Contractor/Construction and Private Sector.

3. Continued Public Comments

None.

4. Upcoming Meetings

The next ITOC meeting is scheduled for Wednesday, October 16, 2019, at 9:30 a.m.

5. Adjournment

Chair Ramer adjourned the meeting at 10:26 a.m.

Action: Approve

The TransNet Independent Taxpayer Oversight Committee is asked to approve the minutes from its September 16, 2019, meeting.

Meeting Start Time: 9:35 a.m. Meeting Adjourned Time: 10:26 a.m.

2

Confirmed Attendance at SANDAG TransNet Independent Taxpayer Oversight Committee Meeting

September 16, 2019

Jurisdiction Name Attended

Licensed Engineer Kai Ramer, Chair Yes

Licensed Civil/Traffic Engineer Michael L. Kenney, Vice Chair Yes

Contractor/Construction Brad Barnum No

Biology/Environmental Dustin Fuller Yes

Finance/Budgeting Stewart Halpern Yes

Right-of-Way Acquisition Licensed Civil/Traffic Engineer

Gregg Sadowsky Yes

Private Sector Dick Vortmann No

Advisory Members

San Diego County Auditor’s Office Tracy Drager (Alternate) No

SANDAG Staff Members and Titles

Hasan Ikhrata, Executive Director Yes

Laura Cote, Chief Deputy Executive Director No

Jose Nuncio, TransNet Department Director Yes

Ariana zur Nieden, Senior TransNet Program Manager Yes

TransNet Independent Taxpayer Oversight Committee Item: 5 October 16, 2019

FY 2021 TransNet Triennial Performance Audit Subcommittee Selection

Overview

In accordance with the TransNet Extension Ordinance, one of the responsibilities of the ITOC is to conduct triennial performance audits of SANDAG and agencies involved in the implementation of TransNet-funded projects and programs to review project delivery, cost control, schedule adherence, and related activities. The review also includes consideration of changes to contracting, construction, permitting, and related processes that could improve the efficiency and effectiveness of the expenditure of TransNet revenues.

Key Considerations

Sjoberg Evashenk Consulting, Inc. has performed all four prior TransNet triennial performance audits. At its April 2019 meeting, the ITOC elected to exercise its option of conducting the fifth triennial audit with Sjoberg Evashenk Consulting, Inc. via a contract amendment of the existing agreement from the FY 2018 triennial performance audit. Retaining the firm will result in time and cost savings by expediting the procurement process as well as additional efficiencies due to the firm’s familiarity with SANDAG, the ITOC, and the various TransNet programs. At the April 2019 ITOC meeting, members discussed Sjoberg Evashenk Consulting’s reliable and effective performance to date, noting that they had no concerns and every expectation that the firm would perform well for the next performance audit.

The ITOC is asked to designate no more than three ITOC performance audit subcommittee members, including a project manager to refine the scope of work and project schedule for the FY 2021 triennial performance audit. Attachments 1 through 3 provide additional details, including the procurement schedule, scope of work from the FY 2018 triennial performance audit, and examples of other scopes of work from triennial performance audits for similar agencies.

Next Steps

The FY 2021 triennial performance audit subcommittee would be scheduled to meet on November 13, 2019, following the November ITOC meeting, to begin discussions on the draft scope of work. The draft scope of work would be presented to the ITOC for consideration at its March 11, 2020, meeting.

José Nuncio, TransNet Department Director

Key Staff Contacts: Ariana zur Nieden, (619) 699-6961, [email protected] Chelsea Gonzales, (619) 699-6930, [email protected] Karen Logan, (619) 595-5372, [email protected]

Attachments: 1. Discussion Memo 2. FY 2018 TransNet Triennial Performance Audit Scope of Work 3. Recommendations for Audit Focus Areas and Analysis

Action: Appoint

The ITOC is asked to appoint its FY 2021 TransNet Triennial Performance Audit Subcommittee.

Fiscal Impact:

TransNet triennial performance audits are conducted by the ITOC with the assistance of an independent performance auditing firm and funded through Overall Work Program Project No. 1500200. The most recent performance audit was conducted in FY 2018 at a cost of $259,998.

Schedule/Scope Impact:

The fifth performance audit, covering activities from FY 2018 through FY 2020, is scheduled to be conducted in FY 2021 and would begin in July 2020 at an estimated cost of $273,000.

Attachment 1

2

Discussion Memo

Background

In accordance with the TransNet Extension Ordinance, one of the responsibilities of the ITOC is to conduct triennial performance audits of SANDAG and agencies involved in the implementation of TransNet-funded projects and programs. Paragraph 3 of the ITOC responsibilities section of the “Statement of Understanding Regarding the Implementation of the Independent Taxpayer Oversight Committee for the TransNet Program” attached to the TransNet Extension Ordinance states as follows:

Conduct triennial performance audits of SANDAG and other agencies involved in the implementation of TransNet-funded projects and programs to review project delivery, cost control, schedule adherence and related activities. The review should include consideration of changes to contracting, construction, permitting and related processes that could improve the efficiency and effectiveness of the expenditure of TransNet revenues. These performance audits shall be conducted using the services of an independent performance auditor and should include a review of the ITOC’s performance. A draft of the ITOC’s report and recommendations regarding the performance audits shall be made available to the SANDAG Transportation Committee at least 60 days before its final adoption by the ITOC to resolve inconsistencies and technical issues related to the ITOC’s draft report and recommendations. Once this review has taken place, the ITOC shall make any final amendments it deems appropriate to its report and related recommendations, and adopt its report for presentation directly to the SANDAG Board of Directors and the public. The ITOC shall strive to be as objective and constructive as possible in the text and presentation of the performance audits. Upon completion by the ITOC, the report shall be presented to the SANDAG Board of Directors at its next regular meeting and shall be made available to the public.

With the assistance of an independent auditor, the ITOC conducted the:

• First triennial performance audit in FY 2009 (covering activities from FY 2006 through FY 2008)

• Second triennial performance audit in FY 2012 (covering activities from FY 2009 through FY 2011)

• Third triennial performance audit in FY 2015 (covering activities from FY 2012 through FY 2014)

• Fourth triennial performance audit in FY 2018 (covering activities from FY 2015 through FY 2017)

The audits focused on the implementation of the TransNet Early Action Program of projects and included a review of the performance of SANDAG, Caltrans, San Diego Metropolitan Transit System, North County Transit District, the City of San Diego, the County of San Diego, a representative sample of various local jurisdictions, and the ITOC. The second, third, and fourth audits also included a review of the implementation of recommendations from the most recently conducted audits, as well as a review of operational processes and performance for new programs implemented since conducting the first audit. The fifth performance audit, covering activities from FY 2018 through FY 2020, is scheduled to be conducted in FY 2021 and would begin in July 2020.

This report summarizes factors for ITOC consideration in appointment of the subcommittee for the FY 2021 triennial performance audit. Staff has prepared a draft procurement schedule of the upcoming audit. Attachment 2 provides a copy of the scope of work used for the FY 2018 triennial performance audit and Attachment 3 provides recommendations for potential audit focus areas and analysis.

Discussion

During the FY 2018 audit cycle, the ITOC participated in a competitive procurement to solicit an independent performance auditor. The ITOC established an evaluation subcommittee and selected a project manager

3

among its members that developed the scope of work and evaluation criteria for the solicitation. The procurement process was managed by SANDAG Contracts and Procurement staff, and the ITOC was involved in all phases of the procurement. As part of this process, the ITOC subcommittee evaluated and competitively scored each of the responsive auditing firms. Sjoberg Evashenk Consulting, Inc. scored the highest and was selected as the auditing firm for the FY 2018 triennial audit. Staff executed a new contract with Sjoberg Evashenk Consulting, Inc. to carry out the FY 2018 audit. The new contract also included language that allowed the ITOC the option of retaining the firm to conduct the fifth audit under the existing agreement. At the April 2019 ITOC meeting, the ITOC elected to exercise this option and authorize a contract amendment with Sjoberg Evashenk Consulting, Inc. to conduct the FY 2021 TransNet Triennial Performance Audit.

To begin the contract amendment process, the ITOC is asked to designate no more than three ITOC performance audit subcommittee members, including a project manager to further develop the scope of work and project schedule for the FY 2021 triennial performance audit. In order to ensure the audit begins in accordance with the provisions of the TransNet Extension Ordinance and SANDAG Board Policy No. 031, once the ITOC establishes a performance audit subcommittee and selects a project manager from its membership, SANDAG Contracts Division staff will assist the ITOC in the refinement of the scope of work and project schedule.

Procurement Schedule

Below is the draft procurement schedule for the FY 2021 TransNet Triennial Performance Audit:

Task Description Estimated Date

Establish Performance Audit Subcommittee October 16, 2019

First Subcommittee meeting to refine Scope of Work November 13, 2019 (following ITOC meeting)

Second Subcommittee meeting to review draft Scope of Work January 8, 2020 (following ITOC meeting)

Draft Scope of Work presentation to ITOC March 11, 2020

Third Subcommittee meeting to finalize Scope of Work based on ITOC input

March 11, 2020 (following ITOC meeting)

ITOC Approval of Scope of Work April 8, 2020

Task order routing/approval Mid-April to mid-May, 2020

Send task order to Sjoberg for signature Late May, 2020

Issue Notice to Proceed June 1, 2020

Begin FY 2021 Triennial Audit July 1, 2020

Scope of Work

Attachment 2 of this report includes the scope of work from the FY 2018 triennial performance audit. Since the FY 2021 triennial performance audit will be an amendment to that contract, the scope of work attached serves as the starting point for the scope of work in the fifth performance audit. The subcommittee will have the ability to make minor changes to the scope of work for the FY 2021 audit; however, significant changes will not be possible based on agency procurement practices as it would provide a competitive disadvantage

4

to those firms who responded to the original Request for Proposals (RFP) in the FY 2018 triennial performance audit. Generally, refinements or narrowing down of the existing scope of work may be allowed, so long as audit requirements per the TransNet Ordinance are maintained.

In preparation of the FY 2018 triennial performance audit scope of work and contract, staff conducted a search for similar performance audits and RFPs from other agencies. Most of the other audits and RFPs available for review focus on the triennial Transportation Development Act (TDA) performance audits required under state law. Below are links to those RFPs and/or audits for the subcommittee’s consideration while developing the scope of work for the FY 2021 performance audit:

• Orange County Transportation Authority Triennial Performance Assessments: http://www.octa.net/About-OC-Go/OC-Go-(2011-2041)/Documents-and-Reports/

• Orange County Transportation Authority FY 2016 - FY 2018 TDA Performance Audit: https://www.octa.net/pdf/IntAud-FY16-FY18-TDA-Performance-Audit-OCTA-OCTD.pdf

• San Bernardino County Transportation Authority FY 2015 - FY 2017 Triennial Performance Audit https://gosbcta.com/about-sbcta/agendas/2018/09-18-GPC-i10.pdf

• Santa Cruz County Regional Transportation Commission FY 2015 - FY 2016 and FY2017 - FY 2018 TDA Triennial Performance Audit RFP http://sccrtc.org/wp-content/uploads/2019/02/Performance-Audit-RFP-FY16-FY18.pdf

• Los Angeles County Metropolitan Transportation Authority TDA Triennial Performance Audit Scope of Services https://www.bidnet.com/bneattachments?/501126574.pdf

SCOPE OF WORK

Fourth TransNet Triennial Performance Audit (OWP 1500200, Contract #5004894)

FY 2018 TRIENNIAL PERFORMANCE AUDIT (FOURTH AUDIT)

The FY 2018 Triennial Performance Audit (fourth audit) will be conducted by the ITOC with the assistance of the independent auditor to review the three-year period between July 1, 2014, and June 30, 2017, and make recommendations for improving the efficiency and effectiveness of expenditures under the TransNet Extension Ordinance. This includes, but is not limited to, the degree to which the projects completed are achieving the goals set out in the Ordinance, financial management, project delivery, and oversight and monitoring.

The ITOC has requested that its auditor take a fresh perspective regarding the format of its fourth performance audit. This means that the ITOC will work closely with its auditor to fully leverage prior performance audit results by minimizing review of areas that have been extensively reviewed before. Instead, the fourth audit will focus on outcomes to identify what has been delivered in the implementation of the TransNet Extension Ordinance (Ordinance) and key metrics by which those outcomes should be measured. Shifting the focus of the audit from reviewing processes and organizational structures (as audited during each of the prior audits), the fourth audit will rely on and leverage prior audit results and place an emphasis on outcomes and accomplishments realized under the program.

Also new, the fourth audit will expand on discussion regarding the implementation of best practices, as well as provide comparisons between SANDAG and its peers, benchmarking SANDAG’s performance against nationally recognized resources such as the American Public Transportation Association (APTA), National Transit Database, and others. Such best practices to include, but not be limited to, data management and public access to data.

In addition, interviews of third parties that may provide additional insight into best practices, such as subject matter experts, peers from similar agencies, and members of citizen advisory groups, or others, will be conducted.

The audit will aim to provide more insight into the public’s perception of the outcomes achieved in the implementation of the Ordinance and provide recommendations as to how SANDAG and partner agencies could better inform the public about transportation options and programs. To gain insight regarding public perception, meetings to invite public input (e.g. charrettes), letters to stakeholders requesting feedback, or other means to gauge commuter perception could be used.

In addition to these new areas of analysis, a review of the changes that have occurred to the implementation of the TransNet Early Action Program (EAP), Regional Bike EAP, New Major Corridor Transit Service Operations, and other TransNet-funded programs since the third audit was conducted will be included. The fourth audit also will include a status review of the implemented recommendations made in the third audit and an evaluation of the effectiveness of those implemented recommendations. In addition, the fourth audit will provide recommendations to increase the efficiency in the approach to conducting future audits. Finally, the fourth audit will evaluate the efficiency and effectiveness of the ITOC, including adherence to its bylaws.

Attachment 2

5

The Consultant will conduct the fourth audit on behalf of the ITOC, consistent with the TransNet Extension Ordinance. The ITOC has assigned points of contact (ITOC Project Manager and SANDAG Project Manager) for all matters related to the conduct of this performance audit and will provide a point of contact for each of the agencies to be evaluated. The audit will be conducted in accordance with generally accepted governmental auditing standards. These standards require that the Consultant obtain sufficient and appropriate evidence to provide a reasonable basis for audit findings and conclusions.

A. Performance Audit Scope

The fourth audit will examine the performance of SANDAG, Caltrans, San Diego Metropolitan Transit System (MTS), North County Transit District (NCTD), and a representative sample of consultants used by these transportation agencies, reviewing material changes that have occurred since the third triennial performance audit was conducted. In addition, the fourth audit will examine the performance of the ITOC, the County of San Diego, the City of San Diego, and a representative sample of the other 17 cities of the San Diego region and key stakeholder groups. The fourth audit also will include a review of the implementation of recommendations made during the third audit.

In particular, the audit will identify outcomes under the overall program in terms of facility and service improvements for highways, rail transit services, new bus rapid transit services, local bus services, senior and disabled transportation services, local streets and roads, bicycle and pedestrian facilities, transportation-related community infrastructure to support smart growth development, and related environmental mitigation and enhancement projects and rate those outcomes against agreed-upon key metrics1 and the original goals specified by the Ordinance.2

The audit will evaluate the effectiveness of the implementation of Local Street and Road program recommendations from the third audit and the resulting performance and project delivery practices of the larger cities. The audit also will analyze the sharing of best practices across local jurisdictions relative to the Local Street and Road program, through the Cities/County Transportation Advisory Committee (CTAC) or other channels, in addition to sharing of best practices between SANDAG and Caltrans teams on the implementation of the North Coast Corridor and Mid-Coast Corridor Transit Project under the Construction Management/General Contractor (CM/GC) project delivery method.

A review will be conducted to evaluate the efficiency and effectiveness of streamlining and monitoring efforts implemented since the third audit and to assess performance outcomes of grant activities toward meeting the program goals of, but not limited to, the following grant programs:

1 The most recently adopted Regional Plan, San Diego Forward: The Regional Plan performance measures and a list of ten key questions are available here: http://www.sdforward.com/pdfs/RP_final/AppendixN-EvaluatingthePerformanceoftheTransportationNetwork.pdf 2 The TransNet Extension Ordinance Section 4. Expenditure Plan Purposes states revenues from the measure shall be used to improve transportation facilities and services countywide as set forth in the Expenditure Plan and in a manner consistent with the long-range Regional Transportation Plan and the short-range Regional Transportation Improvement Program.

6

• Environmental Mitigation Program, including an assessment of strategic planning and efforts associated with habitat acquisition and restoration activities

• Smart Growth Incentive Program

• Senior Mini-Grant Program

• Bicycle, Pedestrian, and Neighborhood Safety Program (also known as the Active Transportation Grant Program)

In addition, the review will evaluate the effectiveness of monitoring and reporting efforts implemented since the third audit to assess the Regional Bike EAP capital project delivery and management practices.

The audit also will analyze and evaluate resulting performance in all TransNet areas, including but not limited to Major Corridors; Local Street and Road; Regional Bike EAP; New Major Corridor Transit Services Operations, and other programs, to provide specific progress toward meeting program goals and what has been achieved to date.

Relying on prior audit reports, the fourth audit should include a narrative confirming the review of the following processes and consider potential changes to these processes to improve the efficiency and effectiveness of the expenditure of TransNet revenues. This process review also should focus on the benefits, risks, challenges, and opportunities of the CM/GC project delivery method.

• Project delivery

• Program and project cost control

• Program and project schedule development and adherence

• Contracting

• Organizational structure

• Construction management

• Permitting

• Project cost estimates and actuals

The Consultant will propose an audit work plan consistent with generally accepted governmental auditing standards, including interviews, representative sampling, and evaluation. The Consultant will recommend the number of interviews to be conducted, the sample size of cities and agencies to be evaluated, and other issues to ensure a representative sampling and evaluation process for the fourth audit. The Consultant will describe the proposed methodology for the performance audit and the rationale behind the Consultant’s recommendations.

7

The Consultant shall have experience in project design, construction management, and related project implementation activities. Additionally, the Consultant shall provide qualified staff with experience in the following areas:

• Critical project development activities, assessing transportation programs, and evaluating bestpractices

• Collecting data, conducting interviews, performing site visits, and assessing operations

• Objectively analyzing information and producing recommendations to improve key areas ofperformance

The Consultant shall assess the changes to the TransNet EAP, Regional Bike EAP; New Major Corridor Transit Services Operations, and TransNet-funded programs and projects utilizing on-site visitation and evaluation, and off-site analysis/audit. The Consultant shall compare TransNet program activities among TransNet recipient agencies and against other similar transportation programs and best practices, such as those programs implemented by similar transportation agencies in the Southern California and other areas.

B. Audit Objectives

The performance audit objectives listed below are an important component of the fourth audit and reflect the responsibilities of the ITOC per the TransNet Extension Ordinance:

• Review of goals consistent with TransNet Extension Ordinance Section 4. Expenditure PlanPurposes

• Identify key metrics according to which outcomes will be measured consistent with the RegionalPlan

• Identify outcomes achieved in the implementation of facilities and services under the TransNetExtension Ordinance

• Evaluate the status of implementation of the recommendations from the third triennialperformance audit and effectiveness of these prior recommendations

• Determine whether the organizational structure and operational processes continue to allow foreffective and efficient project delivery, cost control, and schedule adherence

• Identify process changes in contracting, construction, permitting, and other procedures that couldimprove the efficiency and effectiveness of the TransNet program

• Evaluate the efficiency and effectiveness of ITOC, including adherence to its bylaws

• Identify and evaluate any potential barriers to and opportunities for proposed changes

All task deliverables should be submitted to the ITOC Project Manager with a copy to the SANDAG Project Manager.

8

Task 1 – Review Existing TransNet Program Materials and Documentation

To the extent possible, the auditor will coordinate the review of existing materials and documentation for this task with the data collection task also being conducted under the TransNet Ten-Year Comprehensive Program Review. The Consultant will review existing TransNet program materials and documentation, including, but not limited to, the following:

• TransNet Extension Ordinance and Expenditure Plan

• Report and recommendations from the third triennial performance audit

• ITOC annual reports and past actions

• Technology tools used in project and program development of the EAP, including KeepSanDiegoMoving.com and the TransNet Dashboard

• Current agency organizational structure and staffing

• Current procurement and contracting practices, such as architectural and engineering services utilized by the EAP

• Current program and project performance measures, such as the number of contract change orders and the cost of contract change orders as a percentage of final contract cost. The review should include a comparison against the results from the first audit based on a review of the same or similar projects, including the percentage actually paid compared to the initial contract bid amount, which will provide a full perspective with overall payment amounts

• Current cost to local agencies when project delivery delays are experienced, including estimated delivery delay costs and savings from schedule accelerations

Task 1 – Deliverables

Memorandum summarizing items reviewed and key issues identified.

Task 2 – Develop Timeline and Meeting Schedule

The Consultant will meet with the ITOC Project Manager and other appropriate staff, and hold an organizational and scoping meeting (entrance conference) to:

• Review project and task objectives

• Review scope of services and data collection methodology

• Consult with the ITOC Project Manager, SANDAG Project Manager, and other appropriate staff on the potential need for subsequent documentation and impacts on project schedule

• Collect available data and published materials

• Establish meeting and presentation schedule

9

• Establish communication channels with other agencies

• Coordinate with local jurisdictions and agencies

Task 2 – Deliverables

• Entrance Conference

• Meeting minutes

• Meeting and presentation schedule

• Data collection methodology

• Summary Work Plan

Task 3 – Interviews and Site Visits

The Consultant will perform the following activities:

• Visit the offices of SANDAG, Caltrans, MTS, NCTD, County of San Diego, City of San Diego, and arepresentative sample of the other 17 cities in the San Diego region to observe theproject/program delivery processes employed and to interview key staff, such as: corridor projectdirectors; TransNet program staff and Project office staff; project managers; executivemanagement; and others, as appropriate. The predecessor of the incumbent of any of these staffshould be interviewed if the incumbent has been in their current position less than twelve(12) months

• Interview key transportation consultants working for the above agencies on TransNet-fundedprojects

• Interview representatives at other stakeholder agencies

• Interview ITOC members

• The review process will include perspectives from third-parties, such as subject matter experts,e.g. engineers, construction firms, among others; citizen advisory groups, such as the SocialServices Transportation Advisory Council (SSTAC) and others; peers from other similar agenciesimplementing similar transportation programs; organizations that have expressed concerns withthe TransNet program, including Circulate San Diego, BikeSD, and the Environmental HealthCoalition; and local associations, such as the San Diego County Taxpayers Association (SDCTA),including an assessment of the SDCTA report on recommendations to improve clarity andtransparency for the taxpayer, among others.

The Consultant should assume approximately 30-40 agencies/interviews. However, the Consultant should provide recommendations for the number of interviews to be conducted, the sample size of cities to be evaluated, and other issues in order to ensure a representative sampling and evaluation process for the fourth audit. The Consultant shall describe the audit plan and proposed methodology for the fourth audit and the rationale behind the Consultant recommendations. If additional

10

agencies/interviews are proposed, the Consultant shall include the proposed additional costs in its cost proposal.

The Consultant will plan, prepare, facilitate, and document all visits and interviews. The Consultant will arrange all logistics for meeting planning and preparation of all background information. Each interview and follow-up request will be documented with an interview summary that details the discussion, requests for information, and any follow-up actions needed.

Task 3 – Deliverables

• List and schedule of key staff to be interviewed and site visits to be conducted

• Documentation of site visits and interviews conducted

• Interview summaries

Task 4 – Review Operational Processes and Organizational Structures

The Consultant will identify any significant changes to operational processes and organizational structures that have taken place since the prior triennial performance audit was conducted which are material either to the efficiency or outcomes of the organization. For this task, the audit will rely on prior audit results to the extent possible while adhering to auditing standards and what is required in the TransNet Extension Ordinance.

The Consultant will review and analyze the results to provide the basis for addressing strategies and improvements to operational processes and organizational structures for the TransNet program.

Task 4 – Deliverables:

Draft summaries of each review conducted for use in developing the audit report

Task 5 – Functional Reviews and Performance Analysis

To the extent possible, the auditor will coordinate the performance analysis under this task with the performance analysis task also being conducted under the TransNet Ten-Year Comprehensive Program Review. For the TransNet EAP; Regional Bike EAP; New Major Corridor Transit Service Operations; grant programs; Local Street and Roads; and other TransNet-funded projects, the Consultant will focus its review on the changes that have taken place since the third triennial performance audit was conducted.

• Analyze the past three (3) years (covering FY 2015 to FY 2017) of financial data and scheduleadherence from the development of the TransNet EAP, Regional Bike EAP, New Major CorridorTransit Service Operations, and other TransNet-funded projects, including an assessment of thedebt structure, TransNet Plan of Finance, and TransNet Transit Operations Plan of Financedevelopment

• Review all past quarterly reports on major Congestion Relief projects presented to the ITOC asstated in ITOC Responsibilities section of the TransNet Extension Ordinance

11

• Conduct a comparison of the EAP and all TransNet project development procedures to industry norms, peer program benchmarks, and best practices

• Review implementation of recommendations from the third triennial audit to validate and determine usefulness, effectiveness, and efficiency

• Evaluate the pavement condition metric methods used by member agencies in determining and communicating progress needed, accomplished, and selection of future projects, in order to validate that TransNet funds are being spent effectively; and

• Evaluate the implementation of Rule No. 21 Accommodation of Bicyclists and Pedestrians included in SANDAG Board Policy No. 031: TransNet Ordinance and Expenditure Plan Rules.

Task 5 – Deliverables:

Draft summaries for use in developing the audit report

Task 6 – Develop Audit Findings and Recommendations into a Draft/Final Report

Although separate reports will be prepared by the auditor (Performance Audit report and Ten-Year Review report), to the extent possible, the auditor will coordinate the development of draft and final reports for this task with the report development task under the TransNet Ten-Year Comprehensive Program Review. For this task, the Consultant will perform the following activities:

• Provide a summary of outcomes achieved in the implementation of facilities and services under the TransNet Extension Ordinance

• Synthesize the above information into findings and recommendations for changes that could improve the efficiency and effectiveness of the expenditure of TransNet revenues

• Provide the ITOC with anticipated operational, financial, and other implications of the Consultant’s recommendations

• Include recommendations for additional analysis that could be included in future performance audits that were not included in this scope of work

• Produce draft and final reports in accordance with the TransNet Extension Ordinance. The draft report shall include all proposed Consultant recommendations and allow for appropriate review by the ITOC, transportation agency staff, and the SANDAG Transportation Committee prior to final approval by ITOC and presentation to the SANDAG Board of Directors and the public. The draft report is to be presented by the Consultant to the ITOC and Transportation Committee as an agenda item at a regular meeting. The ITOC presents the final results of the audit as part of its annual report presentation to the SANDAG Board.

The Consultant will provide the ITOC with recommendations that will:

• Improve the efficiency and effectiveness of the expenditure of TransNet funds through improvements in the various processes reviewed

12

• Provide optional action plans that may result in significant improvements in the delivery of theTransNet EAP and other TransNet-related programs/projects

• Improve the efficiency and effectiveness of the ITOC

The format of the TransNet Triennial Performance Audit will include:

• Table of Contents

• Executive Summary

• Introduction

• Scope and Methodology

• Audit Findings

• Conclusions and Recommendations

• Response to recommendations by ITOC

Task 6 – Deliverables

• One master electronic copy of the draft report in Microsoft Word format

• Staff meeting with the Consultant to review Draft/Final Report (exit conference)

• Presentation of the draft report at a regular ITOC and Transportation Committee meeting

Task 7 – Revise Draft Report based on Staff and Committee Review

In accordance with the TransNet Extension Ordinance, the Consultant will revise the draft report and prepare a final report for review and approval by the ITOC, Transportation Committee, transportation agency staff, and the SANDAG Board of Directors.

Task 7 – Deliverables

One master electronic copy of the final report in Microsoft Word format

Task 8 – Final Report Preparation and Printing

Following staff and committee review and approval of the TransNet Triennial Performance Audit report, the Consultant will provide an electronic copy of the final version of the TransNet Triennial Performance Audit report to be presented to the ITOC, Transportation Committee, SANDAG Board of Directors, and the public. The Consultant will provide a master copy of the report for future duplicating needs. The final report will be presented by the Consultant to the ITOC as an agenda item at a regular ITOC meeting. The final report will be presented to the SANDAG Board of Directors by the ITOC.

13

Task 8 – Deliverables

• Electronic file of the final TransNet Triennial Performance Audit report in PDF and Word format

• Final report presentation at a regular ITOC meeting

• Memorandum addressed to ITOC and SANDAG Project Manager outlining recommendations foradditional analysis on future performance audits

Task 9 – First TransNet Ten-Year Comprehensive Program Review

One of the requirements of the Ordinance is for the ITOC to provide recommendations as part of the ten-year review process. This may be completed by providing comments as part of presentation of the ten-year review either at an ITOC meeting or directly to the auditor; or could be in the form of a memo addressed by the ITOC to the Board. Should the ITOC elect to draft a memo, the ITOC may request auditor assistance.

Task 9 – Deliverables

Memorandum addressed to ITOC and SANDAG Project Manager with discussion of areas that could be considered as part of the TransNet 10-year Comprehensive Review look ahead component for Board consideration.

Task 10 - Additional Proposed Tasks (Optional Work)

ITOC may assign the Consultant additional data gathering and analysis projects via a separate Notice to Proceed if the need arises, including, but not limited to, conducting additional analyses that could be combined as part of the audit or could be more individually focused.

Assignment of this additional task is subject to availability of additional funding and whether fair and reasonable terms can be negotiated.

FY 2021 TRIENNIAL PERFORMANCE AUDIT (FIFTH AUDIT - OPTIONAL WORK)

Subject to funding availability, ITOC may assign to the Consultant the completion of the FY 2021 TransNet Triennial Performance Audit (fifth audit).The fifth audit will review the three-year period between July 1, 2017, and June 30, 2020, and make recommendations for improving the efficiency and effectiveness of expenditures under the TransNet Early Action Program (EAP), Regional Bike EAP, New Major Corridor Transit Service Operations, and other TransNet-funded programs, projects, and services. This includes, but is not limited to, financial management, project delivery, and oversight and monitoring.

The fifth audit will include a review of the changes that have occurred to the implementation of the TransNet EAP, Regional Bike EAP, New Major Corridor Transit Service Operations, and other TransNet-funded programs since the fourth audit was conducted. The fifth audit also will include a status review of the implemented recommendations made in the fourth audit and an evaluation of the effectiveness of those recommendations. In addition, the fifth audit will provide recommendations to increase the efficiency in the approach to conducting future audits. Finally, the fifth audit will evaluate the efficiency and effectiveness of the ITOC, including adherence to its bylaws.

14

This Audit would include all of the work detailed in Section I, Tasks 1 through 8, but would be tailored specifically to the time period between the fourth and fifth audits, rather than the third and fourth audits.

Deliverables

Deliverables include all of the Deliverables listed in Section I, Tasks 1 through 8, but will be tailored specifically to the time period between the fourth and fifth audits, rather than the third and fourth audits.

15

SJOBERGEVASHENK PAGE | 1 OF 3

Memo To: Dustin Fuller, Chair

TransNet Independent Taxpayer Oversight Committee Ariana zur Nieden, Senior TransNet Program Manager San Diego Association of Governments

From: Catherine Brady, Principal Sjoberg Evashenk Consulting

Date: 8/29/2018 Re: Recommendations for Audit Focus Areas and Analysis on Future TransNet Performance Audits

As contractually required, Sjoberg Evashenk Consulting is providing suggestions for potential audit focus areas and additional analysis that could be conducted in future performance audits. Given that the Scope of Work for the last four audits have been broad-sweeping looking at all TransNet areas, we recommend that the next audit(s) be more narrowly or individually focus on fewer areas to allow for greater depth and analysis in those areas of greatest risk, sensitivity, or where the Independent Taxpayer Oversight Committee (ITOC) is interested in having its performance auditor review.

This could be accomplished in the next audit cycle in two separate phases. In Phase I, the auditor should perform a thorough reconnaissance and risk assessment to narrow down focus areas to be audited at that time. Discussions with the ITOC Audit Subcommittee will help shape the areas to be audited. As part of the second phases, the auditor would conduct the actual audit fieldwork for the selected areas.

That said, the next audit will certainly need to follow-up on corrective actions taken on the most recent audit recommendations, in particular those related to financing TransNet, performance measurement, and transparency. Other potential areas for audit analysis are provided below—the list is not exhaustive, but rather provides possible areas for ITOC’s consideration. Specifically, Sjoberg Evashenk Consulting proposes the following areas for consideration:

Possible Audit Focus Areas: 1. In-depth review of project cost estimation and update processes, activities, and communications2. Evaluation of project planning, prioritization, and sequencing including criteria used, specific mechanisms

used to apply projects against the criteria, project delays or budget overruns impacts on sequencing ofprioritized projects and the TransNet Major Corridor Program overall, and how adjustments are considered and implemented.

Attachment 3

16

Page 2

3. Given projected/possible funding shortfalls, assess how the San Diego Association of Governments (SANDAG) will consider which projects may be delayed or have scope reduced and the point in time at which such decisions could be considered as well as what factors would need to be present to warrant that consideration.

4. Analysis of investments of sales tax funds and other leveraged money. In the past, limited focus was on this area, although it could be a low risk area in general.

5. Data governance looking at the policies and procedures for gathering, storing, using, reporting, and disposing of data to ensure accuracy, relevancy, controlled-access, and consistency.

6. Continued look at performance results toward meeting TransNet goals and activities taken to achieve different outcomes.

7. Reviewing transparency and communication of information by exploring options of presenting TransNet data in a more comprehensive, easier to navigate fashion and compare SANDAG activities with tools and features employed at peer transportation agencies such as Orange County Transportation Authority (OCTA) or San Francisco Transportation Authority (SFCTA). This includes understanding and managing data/information expectations of the ITOC, Board and committees, local constituents, TransNet partners, and the public.

8. Cyber-security practices for profiling threats, preventing attacks, training staff and contractors, incident management, and restoring data.

9. Comprehensive review of one or two specific Local Street and Road projects that are deemed significant, controversial, sensitive by nature, or have increased public interest such as the City of Encinitas “congestion relief” project adding a round-about. This could include a detailed file review of all related project documentation and decisions, schedules, budgets, bottlenecks, change orders, performance, progress payments, procurement, and comparing specific road, lane, or interchange activities proposed with what was actually provided and built. This could also entail, where possible if data is captured, analyze any “before” and “after” performance of the improvement in relation to overarching TransNet goals of safety or congestion relief.

10. Environmental Mitigation Program progress on new Memorandum of Understanding and reporting on performance.

11. Follow-up on progress made on the two Construction Manager/General Contractor (CMGC) projects reviewed as part of this audit cycle—North Coast Corridor and Mid-Coast and identify, in more detail than the standard follow-up on audit recommendations. Identify whether expected benefits from this delivery method have been achieved.

Periodic Audit Focus Areas: Past audits focused on certain areas that were successfully functioning or did not have significant changes in practice. Thus, we recommend that continued focus on these areas is not warranted at this time; although these areas could be incorporated into future audit Scope of Works on a more periodic or rotational basis or if identified as part of the audit risk assessment phase.

17

Page 3

These periodic focus areas would include: • Change orders and task order amendments • Project management practices over local streets and roads • Grant practices • Environmental Mitigation Program acquisition and restoration activities and expenditure • ITOC practices, other than possible comparison of member selection protocols with other entities

18

TransNet Independent Taxpayer Oversight Committee Item: 6 October 16, 2019

Independent Taxpayer Oversight Committee 2020 Meeting Calendar

Overview

The ITOC typically meets on the second Wednesday of the each month. The proposed meeting dates for 2020 are shown below.

Key Considerations

• January 8, 2020

• February 12, 2020

• March 11, 2020

• April 8, 2020

• May 6, 2020

• June 10, 2020

• July 8, 2020

• August 12, 2020

• September 9, 2020

• October 7, 2020

• November 4, 2020, or November 18, 20201

• December 9, 2020

Meeting dates in August and December 2020 are included in the list above; however, typically the ITOC cancels the meetings in both months.

Next Steps

Upon ITOC approval, staff will post ITOC meeting dates on the agency website.

1 Veterans Day is observed on November 11, 2020 (second Wednesday in November). The November ITOC meeting would be held

either the prior week on Wednesday, November 4, 2020, or the following week on Wednesday, November 18, 2020.

José Nuncio, TransNet Department Director

Key Staff Contact: Ariana zur Nieden, (619) 699-6961, [email protected]

Fiscal Impact:

Costs incurred in administering ITOC activities are paid from TransNet sales tax proceeds and audited annually. ITOC members serve without compensation except for direct expenses, such as parking or mileage for meetings related to the work of the ITOC.

Schedule/Scope Impact:

The ITOC typically meets monthly to carry out its roles and responsibilities, including conducting annual fiscal audits and triennial performance audits.

Action: Approve

The ITOC is asked to approve the ITOC 2020 meeting calendar.

TransNet Independent Taxpayer Oversight Committee Item: 7 October 16, 2019

Proposed FY 2020 Program Budget Amendment: GObyBIKE San Diego: Construction Outreach Program

Overview

The GObyBIKE San Diego: Construction Outreach Program will build awareness, enthusiasm, and support of new bike infrastructure that will be opening as part of the Regional Bike Plan Early Action Program, and will educate all mode users on how to safely navigate the project area(s) during construction and after opening. The Construction Outreach Program will focus on 18 bikeways in the City of San Diego located in the urban core, San Diego Bay, and the U.S./Mexico border region (Attachment 1). SANDAG competed for and was ultimately awarded $1.381 million of state Active Transportation Program funds in May 2019 from the California Transportation Commission. These state funds will be matched with existing local TransNet bike funds already in the FY 2020 Program Budget (Attachment 2).

Key Considerations

Benefits of the program will include improved safety during construction and after facilities open to the public for users of all travel modes, increased awareness and support for the bikeway capital projects under construction, and increased use of biking and walking for everyday trips by users of all ages and abilities. The program will increase awareness and the likelihood to try biking as a commute option within and among disadvantaged communities and regional employment centers.

The program will include messaging focused on safety, sustainability, health/wellness benefits, and how the new bikeway projects can serve the potential users’ needs. The education component will emphasize how to use new facilities, whether on foot, bike, or driving, and how to connect to desired destinations. The encouragement component will center on the reasons to travel by bike, and will be bolstered by project location-specific messaging in traditional advertising, web ads, and social media, such as “Going to a Padres game? GObyBIKE on the new Imperial Avenue Bikeway!” or “Going to Coronado beach? GObyBIKE on the Bayshore Bikeway!”

As construction activities continue, SANDAG will work with local partners, including the San Diego County Bike Coalition, the Business Improvement District Council, and other organizations, to further sustain the program beyond this initial start-up.

Fiscal Impact:

Pending approval of accepting the state funds, construction outreach activities are funded through FY 2022 for the Regional Bikeway Program.

Schedule/Scope Impact:

None.

Action: Discussion

The ITOC is asked to consider the proposed budget amendment for consistency with the TransNet Extension Ordinance.

2

Next Steps

Pending action by the Transportation Committee, the Board of Directors is scheduled to consider this item at its October 25, 2019, meeting. If approved, SANDAG will immediately put the program in motion beginning with preconstruction activities for the recently awarded Georgia – Meade and Landis Bikeways Projects starting this fall.

Coleen Clementson, Acting Director of Planning

Key Staff Contact: Chris Kluth, (619) 699-1952, [email protected] Attachments: 1. Proposed FY 2020 Program Budget Amendment for Project No. 1223093,

GObyBIKE San Diego: Construction Outreach Program 2. Proposed FY 2020 Program Budget Amendments, Various Projects (matching funds)

Project Number: Corridor Director:

RTIP Number: N/A Project Manager:

Project Name: PM Phone Number:

N/A

N/A

N/A

N/A

N/A

N/A

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $0 $0 $0 $0 $0 $100 $0 $100 $0 $100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300

Environmental Document 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Design 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Right-of-Way Support 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Right-of-Way Capital 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Construction Support 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Construction Capital 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Communications 0 0 0 0 0 467 0 600 0 600 0 0 0 0 0 0 0 0 0 0 0 0 0 1,667

Project Contingency 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total SANDAG $0 $0 $0 $0 $0 $567 $0 $700 $0 $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,967

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $0 $0 $0 $0 $0 $567 $0 $700 $0 $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,967

FUNDING PLAN ($000)

FUNDING SOURCE

State

74030003 ATP-R $0 $0 $0 $0 $0 $381 $0 $500 $0 $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,381

Local

91000100 TransNet- BPNS 0 0 0 0 0 186 0 200 0 200 0 0 0 0 0 0 0 0 0 0 0 0 0 586

$0 $0 $0 $0 $0 $567 $0 $700 $0 $700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,967

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 595-5610

Brandy Sweitzer

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

The start-up program will focus on 18 bikeways in the City of San Diego located in the urban core, San

Diego Bay, and the U.S./Mexico border region.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Construction outreach will commence in early 2020.

SITE LOCATIONPROJECT SCOPE

The GObyBIKE San Diego Construction Outreach Program builds support for new bike infrastructure and

educates all mode users on bikeway safety in the City of San Diego.

Open to Public

1223093

GObyBIKE San Diego: Construction Outreach Program

Attachment 1

3

Project Number: Corridor Director:

RTIP Number: SAN154 Project Manager:

Project Name: PM Phone Number:

Approved Proposed

Jul-16 Jul-16

Nov-16 Nov-16

Jul-20 Jul-21

Jan-21 Jan-22

Sep-21 Sep-22

Sep-22 Sep-23

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $216 $216 $25 $19 $50 $56 $95 $95 $5 $5 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $396 $396

Environmental Document 457 457 16 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 473 473

Design 374 374 50 6 220 264 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 644 644

Right-of-Way Support 15 15 35 6 0 29 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 50 50

Right-of-Way Capital 0 0 15 0 0 15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15 15

Construction Support 0 0 0 0 10 10 425 0 10 425 0 10 0 0 0 0 0 0 0 0 0 0 445 445

Construction Capital 0 0 0 0 0 0 1,700 0 0 1,700 0 0 0 0 0 0 0 0 0 0 0 0 1,700 1,700

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 15 15 35 13 0 22 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 50 50

Communications 0 0 0 0 0 0 40 10 10 10 0 0 0 0 0 0 0 0 0 0 0 0 50 20

Project Contingency 0 0 20 0 85 105 170 170 0 0 0 0 0 0 0 0 0 0 0 0 0 0 275 275

Total SANDAG $1,077 $1,077 $196 $44 $365 $517 $2,430 $275 $25 $2,140 $5 $15 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,098 $4,068

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $1,077 $1,077 $196 $44 $365 $517 $2,430 $275 $25 $2,140 $5 $15 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,098 $4,068

FUNDING PLAN ($000)

FUNDING SOURCE

Federal

75370001 TE $287 $287 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $287 $287

State

83010001 STIP-TE 37 37 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 37 37

Local

91000100 TransNet -BPNS 683 683 196 44 365 517 2,430 275 25 2,140 5 15 0 0 0 0 0 0 0 0 0 0 3,704 3,674

91080001 County of San Diego 70 70 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 70 70

$1,077 $1,077 $196 $44 $365 $517 $2,430 $275 $25 $2,140 $5 $15 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,098 $4,068

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 595-5319

Omar Atayee

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

Along Bay Boulevard south of Palomar Street in Chula Vista.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Design is 65 percent complete.

SITE LOCATIONPROJECT SCOPE

Design and construct 0.4 miles of new bikeway. A private developer will construct the remaining portion of the bikeway south of where the SANDAG project ends at Ada Avenue.

Open to Public

1129900

Bayshore Bikeway: 8B Main Street to Palomar

4

Attachment 2

Project Number: Corridor Director:

RTIP Number: SAN160 (Part of SAN228) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

N/A N/A

Jul-16 Jul-16

Jul-19 Jul-19

Dec-19 Dec-19

May-21 May-21

May-22 May-22

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $838 $838 $73 $72 $93 $94 $82 $82 $10 $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,096 $1,096

Environmental Document 2,178 2,178 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,178 2,178

Design 2,701 2,701 782 782 241 241 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3,724 3,724

Right-of-Way Support 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Right-of-Way Capital 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Construction Support 62 62 137 137 1,330 1,330 1,230 1,230 22 22 0 0 0 0 0 0 0 0 0 0 0 0 2,781 2,781

Construction Capital 0 0 0 0 6,367 6,367 6,367 6,367 215 215 0 0 0 0 0 0 0 0 0 0 0 0 12,949 12,949

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 7 7 0 0 14 14 5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 26 26

Communications 98 98 4 4 106 3 60 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 288 105

Project Contingency 0 0 0 0 261 261 412 412 10 10 0 0 0 0 0 0 0 0 0 0 0 0 683 683

Total SANDAG $5,884 $5,884 $996 $995 $8,412 $8,310 $8,156 $8,096 $277 $257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,725 $23,542

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $5,884 $5,884 $996 $995 $8,412 $8,310 $8,156 $8,096 $277 $257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,725 $23,542

FUNDING PLAN ($000)

FUNDING SOURCE

Local

91000100 TransNet -BPNS 4,061 4,061 921 920 8,412 8,310 8,156 8,096 277 257 0 0 0 0 0 0 0 0 0 0 0 0 21,827 21,644

91000101 TransNet - SGIP 5001355 141 141 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 141 141

91000101 TransNet - SGIP 5001358 432 432 75 75 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 507 507

91040000 TDA-Bike 1,250 1,250 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,250 1,250

$5,884 $5,884 $996 $995 $8,412 $8,310 $8,156 $8,096 $277 $257 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $23,725 $23,542

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 699-6980

Chris Romano

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

Fourth and Fifth Avenues between B Street and Washington Street in the City of San Diego.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Design is 100 percent complete. Construction will begin in fall 2019.

SITE LOCATIONPROJECT SCOPE

Construct 4.5 miles of new on-street bikeways.

Open to Public

1223022

Uptown Bikeways: Fourth and Fifth Avenue Bikeways

5

Project Number: Corridor Director:

RTIP Number: SAN195 (Part of SAN147) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

N/A N/A

Dec-18 Dec-18

Feb-20 Feb-20

Jul-20 Jul-20

Dec-21 Dec-21

Dec-22 Dec-22

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $409 $409 $276 $280 $200 $196 $200 $200 $200 $200 $28 $28 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,313 $1,313

Environmental Document 982 982 13 16 44 41 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,039 1,039

Design 958 958 516 646 1,026 896 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,500 2,500

Right-of-Way Support 0 0 55 99 120 76 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 175 175

Right-of-Way Capital 0 0 0 0 550 550 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 550 550

Construction Support 0 0 0 0 59 59 1,300 1,300 1,300 1,300 100 100 0 0 0 0 0 0 0 0 0 0 2,759 2,759

Construction Capital 0 0 0 0 0 0 6,797 6,797 7,000 7,000 0 0 0 0 0 0 0 0 0 0 0 0 13,797 13,797

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 77 77 0 0 50 50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 127 127

Communications 12 12 3 13 15 5 10 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 40 32

Project Contingency 0 0 0 0 75 75 800 800 1,500 1,500 0 0 0 0 0 0 0 0 0 0 0 0 2,375 2,375

Total SANDAG $2,438 $2,438 $863 $1,054 $2,139 $1,948 $9,107 $9,099 $10,000 $10,000 $128 $128 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,675 $24,667

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $2,438 $2,438 $863 $1,054 $2,139 $1,948 $9,107 $9,099 $10,000 $10,000 $128 $128 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,675 $24,667

FUNDING PLAN ($000)

FUNDING SOURCE

Federal

74030003 ATP-R $0 $0 $0 $0 $0 $0 $4,444 $4,440 $500 $500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,944 $4,940

Local

91000100 TransNet -BPNS 2,438 2,438 863 1,054 2,139 1,948 4,663 4,659 9,500 9,500 128 128 0 0 0 0 0 0 0 0 0 0 19,731 19,727

$2,438 $2,438 $863 $1,054 $2,139 $1,948 $9,107 $9,099 $10,000 $10,000 $128 $128 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $24,675 $24,667

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 699-6984

Emilio Rodriguez

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

On Harbor Drive from Park Boulevard to 32nd Street in San Diego.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Environmental document is complete. Design is 95 percent complete. Right-of-way acquisitions are ongoing.

SITE LOCATIONPROJECT SCOPE

Final design and construction of a new 2.1 mile bike path.

Open to Public

1223055

Bayshore Bikeway: Barrio Logan

6

Project Number: Corridor Director:

RTIP Number: SAN203 (Part of SAN147) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

Jan-19 Jan-19

Apr-19 Apr-19

Jan-21 Jan-21

Jul-21 Jul-21

Jan-23 Jan-23

Jan-24 Jan-24

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $117 $117 $101 $101 $45 $45 $6 $6 $25 $25 $10 $10 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $305 $305

Environmental Document 524 524 741 741 904 904 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,169 2,169

Design 0 0 0 0 970 970 88 88 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,058 1,058

Right-of-Way Support 0 0 0 0 50 50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 50 50

Right-of-Way Capital 0 0 0 0 172 172 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 172 172

Construction Support 0 0 0 0 0 0 50 50 898 898 320 320 0 0 0 0 0 0 0 0 0 0 1,268 1,268

Construction Capital 0 0 0 0 0 0 500 500 5,468 5,468 2,236 2,236 0 0 0 0 0 0 0 0 0 0 8,204 8,204

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 0 0 0 0 0 0 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 3

Communications 51 51 10 10 36 19 20 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 137 80

Project Contingency 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total SANDAG $692 $692 $852 $852 $2,177 $2,160 $667 $647 $6,411 $6,391 $2,566 $2,566 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $13,366 $13,309

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $692 $692 $852 $852 $2,177 $2,160 $667 $647 $6,411 $6,391 $2,566 $2,566 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $13,366 $13,309

FUNDING PLAN ($000)

FUNDING SOURCE

Federal

74030003 ATP-R $0 $0 $40 $40 $1,190 $1,190 $600 $600 $6,268 $6,268 $2,123 $2,123 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,221 $10,221

Local

91000100 TransNet-BPNS 692 692 812 812 987 970 67 47 143 123 443 443 1 1 0 0 0 0 0 0 0 0 3,145 3,088

$692 $692 $852 $852 $2,177 $2,160 $667 $647 $6,411 $6,391 $2,566 $2,566 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $13,366 $13,309

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 595-5354

Allison Moss

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

In San Diego, just north of San Ysidro Land Port of Entry to Ingrid Avenue and Saturn Boulevard in Imperial Beach. Along Palm Avenue, 7th Street, Elm Avenue, Thermal Avenue, and Grove Avenue from Seacoast Drive to Saturn Boulevard in Imperial Beach.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Final Environmental Document complete. Design is 30 percent complete.

SITE LOCATIONPROJECT SCOPE

Construct 8.5 miles of new bikeways.

Open to Public

1223056

Border to Bayshore Bikeway

7

Project Number: Corridor Director:

RTIP Number: SAN205 (Part of V12) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

N/A N/A

Jan-17 Jan-17

Mar-20 Mar-20

Jul-20 Jul-20

Nov-21 Nov-21

Nov-22 Nov-22

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $208 $208 $112 $108 $70 $74 $124 $124 $41 $41 $10 $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $565 $565

Environmental Document 596 $596 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 596 596

Design 717 717 461 277 20 204 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,198 1,198

Right-of-Way Support 0 0 6 0 0 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 6

Right-of-Way Capital 0 0 0 0 190 190 200 200 0 0 0 0 0 0 0 0 0 0 0 0 0 0 390 390

Construction Support 0 0 0 0 0 0 2,325 2,325 775 775 0 0 0 0 0 0 0 0 0 0 0 0 3,100 3,100

Construction Capital 0 0 0 0 0 0 9,336 9,336 3,112 3,112 0 0 0 0 0 0 0 0 0 0 0 0 12,448 12,448

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 0 0 5 0 5 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10 10

Communications 44 44 9 3 51 2 50 0 50 0 0 0 0 0 0 0 0 0 0 0 0 0 204 49

Project Contingency 0 0 5 0 70 75 326 326 64 64 0 0 0 0 0 0 0 0 0 0 0 0 465 465

Total SANDAG $1,565 $1,565 $598 $388 $406 $561 $12,361 $12,311 $4,042 $3,992 $10 $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,982 $18,827

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $1,565 $1,565 $598 $388 $406 $561 $12,361 $12,311 $4,042 $3,992 $10 $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,982 $18,827

FUNDING PLAN ($000)

FUNDING SOURCE

Local

91000100 TransNet -BPNS 1,565 1,565 598 388 406 561 12,361 12,311 4,042 3,992 10 10 0 0 0 0 0 0 0 0 0 0 18,982 18,827

$1,565 $1,565 $598 $388 $406 $561 $12,361 $12,311 $4,042 $3,992 $10 $10 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $18,982 $18,827

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 699-7319

Chris Carterette

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

Along the Pershing Drive corridor from Landis Street to C Street in the City of San Diego.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Design is 95 percent complete.

SITE LOCATIONPROJECT SCOPE

Construct three miles of new bike and pedestrian facilities between North Park and Downtown San Diego.

Open to Public

1223057

Pershing Drive Bikeway

8

Project Number: Corridor Director:

RTIP Number: SAN206 (V12) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

N/A N/A

Apr-19 Apr-19

Jul-20 Jul-20

Nov-20 Nov-20

May-22 May-22

May-23 May-23

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $197 $197 $60 $57 $50 $53 $69 $69 $26 $26 $3 $3 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $405 $405

Environmental Document 797 797 92 38 450 504 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,339 1,339

Design 3 3 1,267 1,294 406 406 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,676 1,703

Right-of-Way Support 0 0 45 0 250 295 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 295 295

Right-of-Way Capital 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Construction Support 0 0 56 84 0 0 731 731 329 329 28 28 0 0 0 0 0 0 0 0 0 0 1,144 1,172

Construction Capital 0 0 0 0 0 0 5,927 5,927 2,100 2,100 50 50 0 0 0 0 0 0 0 0 0 0 8,077 8,077

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 0 0 5 0 6 11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11 11

Communications 99 99 11 0 20 3 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 136 102

Project Contingency 0 0 40 0 135 120 180 180 50 50 0 0 0 0 0 0 0 0 0 0 0 0 405 350

Total SANDAG $1,096 $1,096 $1,576 $1,473 $1,317 $1,392 $6,913 $6,907 $2,505 $2,505 $81 $81 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,488 $13,454

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $1,096 $1,096 $1,576 $1,473 $1,317 $1,392 $6,913 $6,907 $2,505 $2,505 $81 $81 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,488 $13,454

FUNDING PLAN ($000)

FUNDING SOURCE

Federal

74030003 ATP-R $0 $0 $0 $0 $0 $0 $3,115 $3,115 $1,335 $1,335 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,450 $4,450

Local

91000100 TransNet -BPNS $1,096 $1,096 $1,576 $1,473 $1,317 $1,392 $3,798 $3,792 $1,170 $1,170 $81 $81 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $9,038 $9,004

$1,096 $1,096 $1,576 $1,473 $1,317 $1,392 $6,913 $6,907 $2,505 $2,505 $81 $81 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,488 $13,454

Linda Culp

MAJOR MILESTONES

In San Diego, on Imperial Avenue from 21st Street to 47th Street with connections to Downtown San Diego at various locations.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Design is 95 percent complete.

SITE LOCATIONPROJECT SCOPE

Design and construct 3.8 miles of urban on-street bikeways.

Open to Public

1223058

Downtown to Imperial Avenue Bikeway

FY25 FY26 FY27

(619) 699-6980

Chris Romano

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24

TOTAL:

FY20 FY21

9

Project Number: Corridor Director:

RTIP Number: SAN233 (Part of SAN227) Project Manager:

Project Name: PM Phone Number:

Approved Proposed

N/A N/A

May-16 May-16

Mar-19 Apr-19

Sep-19 Sep-19

Sep-21 Apr-22

Sep-22 Oct-23

SANDAG EXPENDITURE PLAN ($000)

TASK

Administration $125 $125 $132 $134 $123 $121 $125 $125 $45 $45 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $555 $555

Environmental Document 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Design 1,740 1,740 237 236 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,977 1,977

Right-of-Way Support 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Right-of-Way Capital 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Construction Support 0 0 143 189 2,078 2,032 1,817 1,817 105 105 0 0 0 0 0 0 0 0 0 0 0 0 4,143 4,143

Construction Capital 0 0 0 0 8,883 8,883 7,268 7,268 1,988 1,988 0 0 0 0 0 0 0 0 0 0 0 0 18,139 18,139

Vehicles 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Legal Services 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Communications 13 13 4 4 63 6 51 0 11 0 0 0 0 0 0 0 0 0 0 0 0 0 142 23

Project Contingency 0 0 0 0 35 35 35 35 11 11 0 0 0 0 0 0 0 0 0 0 0 0 81 81

Total SANDAG $1,878 $1,878 $516 $563 $11,182 $11,078 $9,296 $9,245 $2,160 $2,149 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,037 $24,918

CALTRANS EXPENDITURE PLAN ($000)

TASK

Environmental Document $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Design 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Right-of-Way Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Support 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Construction Capital 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 0

Total Caltrans $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0

Total SANDAG & Caltrans $1,878 $1,878 $516 $563 $11,182 $11,078 $9,296 $9,245 $2,160 $2,149 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,037 $24,918

FUNDING PLAN ($000)

FUNDING SOURCE

Local

91000100 TransNet-BPNS $1,878 $1,878 $516 $563 $11,182 $11,078 $9,296 $9,245 $2,160 $2,149 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,037 $24,918

$1,878 $1,878 $516 $563 $11,182 $11,078 $9,296 $9,245 $2,160 $2,149 $5 $5 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $25,037 $24,918

FY23 FY24

TOTAL:

FY20 FY21

PROJECT LIMITS

PRIOR YEARS

FY22FY19

PRIOR YEARS

PRIOR YEARS

FY22

FY19 FY20 FY21 FY22

FY19 FY20 FY21

FY23 FY24 FY25 FY26 FY27

FY23 FY24 FY25 FY26 FY27

FY25 FY26 FY27

(619) 699-7317

Danny Veeh

FY28 TOTAL

FY28 TOTAL

FY28 TOTAL

Draft Environmental Document

Final Environmental Document

Ready to Advertise

Begin Construction

Linda Culp

MAJOR MILESTONES

Within the City of San Diego communities of North Park, Normal Heights, Kensington, and City Heights along Meade Avenue from Park Boulevard to 44th Street, Georgia Street between Robinson Avenue and Howard Avenue, Howard Avenue between Georgia Street and Florida Street, and Florida Street between Howard Avenue and Meade Avenue and Landis Street, Swift Avenue, Wightman Street, and 35th Street between Alabama Street and Chamoune Avenue.

FY 20 CAPITAL BUDGET AMENDMENT IN '000'S

Close-Out

PROGRESS TO DATE

Notice of Intent to Award has been issued, construction on-track to begin in September 2019.

SITE LOCATIONPROJECT SCOPE

Design 3.5 miles and construct 6.5 miles of urban bikeways including traffic calming improvements. Includes construction of Landis bikeway.

Open to Public

1223082

North Park/Mid-City Bikeways:  Georgia-Meade Bikeway

10

TransNet Independent Taxpayer Oversight Committee Item: 8 October 16, 2019

TransNet Environmental Mitigation Program: FY 2020 Annual Funding

Overview

At its September 10, 2019, meeting, the Environmental Mitigation Program (EMP) Working Group recommended approval of the allocation of $4 million in funding for FY 2020 for regional land management and monitoring consistent with the FY 2019-2020 Work Plan, as shown in Attachment 1.

Key Considerations

The TransNet Extension Ordinance and Expenditure Plan, approved by voters in 2004, includes the EMP, which provides funding to mitigate habitat impacts from regional and local transportation projects and provides funding for regional land management and biological monitoring.

Each year, the Board of Directors allocates $4 million toward implementation of regional land management and biological monitoring pursuant to a TransNet Memorandum of Agreement (MOA) with state and federal agencies on the implementation of the EMP.

The FY 2019-2020 Work Plan is based on the objectives and priorities included in the Management Strategic Plan and outlines the overarching goals, area of emphasis, and key milestones for regional management and monitoring. The proposed funding levels for FY 2020 in Attachment 2 are consistent with the adopted TransNet MOA.

Next Steps

If approved by the Board, the FY 2019-2020 Work Plan would be implemented with the approved budget for FY 2020 and an annual status report on the EMP would be provided in early 2020.

Coleen Clementson, Acting Director of Land Use and Transportation Planning

Key Staff Contact: Kim Smith, (619) 699-6949, [email protected] Attachments: 1. TransNet EMP - Regional Management and Monitoring FY 2019-2020 Work Plan

2. Recommended FY 2020 Funding Allocation for Habitat Conservation Fund

Action: Discussion

The ITOC is asked to discuss the proposed allocation of $4 million in funding for FY 2020 for regional land management and monitoring.

Fiscal Impact:

The FY 2020 Budget includes $4 million in funding to implement the TransNet Environmental Mitigation Program FY 2019-2020 Work Plan.

Schedule/Scope Impact:

This action would allow the continuation of regional management and monitoring in FY 2020 under the provisions of the TransNet Environmental Mitigation Program.

Attachment 1

2

TransNet Environmental Mitigation Program: Regional Management and Monitoring FY 2019-2020 Work Plan

Approved by SANDAG Board of Directors, October 26, 2018

Introduction

The TransNet Extension Ordinance and Expenditure Plan, approved by the voters in November 2004, includes the Environmental Mitigation Program (EMP), which provides funding to mitigate habitat impacts from regional and local transportation projects, and provides funding for regional land management and biological monitoring. The EMP is a unique component of the TransNet Extension Ordinance in that it goes beyond traditional mitigation for transportation projects by including a funding allocation for habitat acquisition, management, and monitoring activities to help implement the regional habitat conservation plans. This funding allocation is tied to mitigation requirements and the environmental clearance approval process for projects outlined in the Regional Transportation Plan and to implement the Habitat and Open Space policy objectives developed as part of San Diego Forward: The Regional Plan.

Each year, the Board of Directors allocates $4 million to implement regional land management and biological monitoring pursuant to a TransNet Memorandum of Agreement with state and federal agencies on the implementation of the EMP. In 2013, a technical document entitled Management Strategic Plan (MSP) for Conserved Lands in Western San Diego County was developed to increase the efficient use of both the TransNet funding as well as other outside local, state, and federal funds. The MSP has several elements dealing with species management, wildlife connectivity, wildfires, and regional monitoring that will promote the purpose of the TransNet EMP. The MSP is available at: https://sdmmp.com/msp_doc.php.

The purpose of the MSP is to identify a roadmap to prioritize actions that are needed to ensure the persistence of key wildlife species, maintain ecosystem processes, and maintain healthy natural communities in an efficient and integrated manner across the region in the context of a changing ecosystem due to wildfires, habitat type conversion, and climate change.

Table 1, on page 11 of the FY 2019-2020 Work Plan, identifies the funding needs to implement these efforts in FY 2019.

FY 2019-2020 Strategic Goals and Areas of Emphasis

To guide the development of the annual allocation of regional management and monitoring funds, a set of strategic goals have been approved by the Board of Directors to implement the MSP. These strategic goals identify long-term areas of achievement that should remain relatively unchanged on an annual basis. Supporting these strategic goals are the areas of emphasis and achievement milestones, which will be updated each year to highlight particular areas of focus for the coming year and as measure of success.

Strategic Goals

1. Promote key sensitive species persistence and resiliency through management actions to prevent extirpation and extinction.

2. Promote native vegetation communities persistence and resiliency through the development and implementation of strategies to maintain and increase habitat quality.

3. Improve wildlife movement through the identification of critical linkage areas and implementation of strategies to enhance the physical and genetic connectivity of species across rural and urban landscapes.

4. Promote regional coordination through the facilitation and coordination with existing land management efforts, development of best management practices, and leverage existing funding.

3

Areas of Emphasis and FY 2019-2020 Milestones

The highest priorities for SANDAG during FY 2019-2020 are to build off prior work to continue with monitoring and management of species and their habitats, while reducing threats and increasing collaboration and use of best practices across the region.

1.0 Promote Key Sensitive Species.

1.1 Priority Rare and Endemic Plants Recovery

The MSP has identified 32 rare plant species that could either be entirely lost within San Diego County, where significant occurrences of the species could be lost, or where species specific management actions are needed to ensure persistence.

Achievement Milestones FY 2019-2020

• Continue providing regional coordination for Rare Plant Monitoring. Work with land managers and contractor to survey for 14 MSP priority rare plants in 2019 and 9 in 2020, and identify threats and management needs.

• Analyze rare plant monitoring data collected in 2014-2018. Provide recommendations for monitoring and management and develop best management practices for land managers.

• Incorporate results of rare plant monitoring, genetic studies, regional population structures, conceptual models, and best management practices to develop the MSP Seed Collection, Banking and Bulking Plan and MSP Rare Plant Management Plan for eight priority rare plant species to prioritize and guide management actions.

• Coordinate with Marine Corps Air Station Miramar on the results of their willowy monardella demographic monitoring and hydrologic studies. Develop assessments at current and historic locations and suitable habitat on Conserved Lands to address the effects of hydrologic modification on the species and the potential for expansion of occurrences. Use this information to design future surveys for this species.

1.2 Priority 1 Vertebrates Recovery

The MSP has identified 19 rare vertebrate species that could either be entirely lost within San Diego County, where significant occurrences of the species could be lost, or where species specific management is needed to ensure persistence. Another 28 species are included as priorities for vegetation-focused management. Eleven of these 47 rare vertebrate species have been prioritized for regionally supported FY 2019-2020 vertebrate recovery management.

Achievement Milestones FY 2019-2020

Amphibians

• Provide coordination for region-wide arroyo toad surveys based on the regional monitoring strategy being developed by U.S. Geological Survey (USGS). Continue supporting land managers on the implementation of priority management actions. Update surveys conducted in FY 2002-2003 in the Multiple Species Conservation Program area and in FY 2016-2017 in North County and other areas identified in MSP. Collect additional genetic material for analysis.

4

Reptiles

• Continue to monitor and enhance occurrences of previously translocated southwestern pond turtles at Sycuan Peak Ecological Reserve (Sweetwater watershed) and Rancho Jamul Ecological Reserve (Otay watershed). Identify, manage, and translocate southwestern pond turtles to additional sites in the San Dieguito and San Diego River watersheds to build the population to sustainable levels.

Birds

• Continue to support management of cactus nurseries, coastal cactus wren habitat restoration, and fire management to protect cactus wren habitat in North and South County.

• Complete the five-year coastal cactus wren study to assess population status, reproduction, dispersal, survival, food availability and habitat quality in South County in order to provide specific management recommendations to recover populations and enhance resilience during drought periods.

• Conduct surveys and collect genetic material from coastal cactus wrens in San Pasqual Valley. Analyze the collected genetic material and previously collected material from South County for nestling diet analysis and to determine if populations have recovered from reductions in genetic variability and population size.

• In 2019-2020, provide regional coordination for coastal California gnatcatcher range-wide surveys, repeating efforts carried out in 2016 and analyze the data.

• Complete the five-year study on golden eagles to monitor movement, habitat use, and population demographics. Develop and implement management recommendations.

• Repeat least Bell’s vireo surveys conducted in the Tijuana River Valley in 2017 to assess changes to vireo populations and measure how vegetation is responding to shot-hole borer damage.

• Complete the five-year study to evaluate the status of the southwestern willow flycatcher along the San Luis Rey River and survey additional watersheds with the potential to support the species. Develop and implement management recommendations.

• Continue to provide technical support to implement priority management actions for the western burrowing owl as identified in the management plan completed in 2017.

• Working with partners, participate in the statewide Tricolored Blackbird survey effort to document presence/absence, estimated numbers and habitat characteristics. Coordinate with land managers to restore suitable habitat and determine management needs.

Mammals

• Support land managers in the implementation of management recommendations from the previously completed study on Townsend’s big-eared bat and pallid bat roosts and foraging sites.

1.3 Priority 1 Invertebrates Recovery

The MSP has identified five rare invertebrate species that could be entirely lost within San Diego County. Another two species are included as priorities for vegetation focused management.

5

Achievement Milestones FY 2019-2020

• Continue Hermes copper butterfly monitoring and habitat assessments to document status and assess habitats and threats. Continue monitoring effectiveness of translocations and develop best management practices for captive rearing. Implement high priority management actions from the management plan. Work with partners to develop and implement a monitoring plan that will track long term status, habitat and threats to this species.

• Continue Harbison dun skipper host plant, adult, larval and hibernation surveys and habitat assessments. Implement high priority management actions from the management plan.

• In 2019 continue to conduct surveys for Quino checkerspot butterfly and map host plant distribution to develop a metapopulation model to guide development of a monitoring plan and identify management opportunities to increase connectivity and enhance populations. Prepare a Quino Habitat Checkerspot butterfly monitoring plan and begin regional monitoring in 2020. Develop interim Quino checkerspot management plan and implement high priority actions. Develop and include in MSP Seed Collection, Banking and Bulking Plan for Quino checkerspot forbs, and host plants and implement to restore habitat. Support U.S. Fish and Wildlife Service (USFWS) efforts to captive rear larvae and translocate to reestablish and augment wild populations.

• Provide technical support to land managers for implementation of vegetation and species monitoring and management for vernal pool invertebrate species, San Diego fairy shrimp and Riverside fairy shrimp (and western spadefoot toad where suitable conditions are present).

1.4 General Stressors and Threats Management

There are numerous existing and newly emerging threats in the San Diego region that need on-going management for the long-term persistence of native species (see Vol 2 of MSP).

Achievement Milestones FY 2019-2020

• Provide technical support for the management of tern sites at Mission Bay Park to support successful breeding of California least tern.

• Provide technical support for the eradication of feral pigs in San Diego County.

• Finalize an Invasive Animal Plan with a strategy and bio-control methods for the prioritization and management of invasive animal species in San Diego County. Complete and implement an invasive animal database and early detection rapid response system.

• In collaboration with statewide efforts, continue to provide funding for shothole borer-Fusarium complex monitoring, management, and research and education to formulate and implement management actions.

• Implement management actions based on the recommendations from the completed Argentine ant and urban runoff studies.

• Provide technical assistance to model habitat suitability for MSP species under alternative future climate change scenarios. Conduct a spatially explicit vulnerability assessment of potential climate change impacts to Conserved Lands across the MSP area. Model response of animal occurrences to climate variability.

6

2.0 Promote Native Vegetation Communities.

2.1 Vegetation Community Monitoring and Recovery

Vegetation communities serve as habitat for priority plant and animal species and as surrogates for ecosystem health. Changes in the vegetation communities due to fires, invasive species, droughts, climate change, and other factors may be causing a landscape level change to these communities.

Achievement Milestones FY 2019-2020

• Continue to develop and implement the regional vegetation monitoring strategy to determine ecological integrity of coastal sage scrub, chaparral, and riparian and oak woodlands in the San Diego region.

• Initiate the development of a grazing plan by coordinating with land managers on using grazing as a large-scale management tool to control invasive non-native grasses and forbs and restore ecological integrity and benefit MSP species in coastal sage scrub and grassland habitat.

• Implement a regional vegetation monitoring study to measure the responses of coastal sage scrub, chaparral, and grassland vegetation communities to changing environmental conditions (e.g. climate, fire). A pilot study was carried out between 2007 and 2014 by San Diego State University to implement and evaluate field based and landscape-scale remote sensing monitoring methods for coastal sage scrub, chaparral, and grassland vegetation communities, and workshops held to develop conceptual models and vegetation monitoring goals and objectives. Work proposed for in FY 2019-2020 will expand the San Diego State University work to look at the San Diego region.

• Completed adaptive management actions identified in the South County Grasslands Project to increase native grass and forb composition and bare ground components of grasslands and coastal sage scrub using layered treatments (e.g., mowing, herbicide, fire, and seeding) on four preserve areas of ≥500 acres.

2.2 Pro-active Wildfire Planning and Management

Large wildfires in 2003 and 2007, plus more recent smaller wildfires, have severely impacted populations of key species identified as critical by the MSP and their habitats. Management action to reduce threats pre- and post-fire and during suppression need to be implemented.

Achievement Milestones FY 2019-2020

• Support preparation of a Fire Ignition Reduction Plan with specific recommendations to prevent wildfire ignitions affecting Conserved Lands in the MSP area.

• Develop a regional MSP Resource Avoidance Areas Map integrated into fire agencies’ Wildland Fire Decision Support Systems and preparation of Preserve Fire Management Plans for Conserved Lands.

• Support establishment of a Wildland Fire Resource Advisor Program for locally-owned lands that integrates with federal and state programs.

7

2.3 Invasive Plant Species Management

Invasive plants pose a threat to existing native plants and increase the risk of wildfires by changing the natural ecosystem. In 2012, an Invasive Plant Strategic Plan was completed for managing invasive plant species in San Diego County.

Achievement Milestones FY 2019-2020

• Continue to work with the County of San Diego Department of Agriculture, Weights, and Measures to implement the Invasive Plant Strategic Plan.

2.4 Updated Vegetation Mapping

Vegetation mapping of the County is essential for tracking changes in vegetation cover on Conserved Lands through time. A vegetation classification system was developed, and a vegetation map was produced for western San Diego County in 2012, with further refinements in 2014.

Achievement Milestones FY 2019-2020

• Collaborate with land manager to implement an updated vegetation mapping effort to start in 2020 implementing the recommended ten-year cycle to update regional vegetation mapping

2.5 Enforcement

Non-authorized use of the preserve system continues to cause impacts to MSP species and their habitats and increase the costs of habitat maintenance and restoration.

Achievement Milestones FY 2019-2020

• Support preserve managers and land owners in enforcement of unauthorized activities on open space lands. Work with local jurisdictions to evaluate and promote opportunities to work with local law enforcement staff similar to efforts completed in FY 2017-2018 with cities of San Diego and Carlsbad.

2.6 Preserve Level Management Plan Standardization

Integration of the MSP goals and objectives into preserve level management plans will provide better coordination between regional and preserve level data collection and MSP land managers management and monitoring efforts.

Achievement Milestones FY 2019-2020

• No milestones are included in the FY 2019-2020 workplan at this time.

2.7 Land Management Implementation (e.g. grants)

The EMP Land Management Grant Program has been an important source of funding for implementing management actions to benefit MSP species and their habitats in the San Diego region.

8

Achievement Milestones FY 2019-2020

• Develop a 10th cycle of land management grants, focusing on implementation of the MSP goals, leading to a request for proposals in FY 2020.

2.8 Emergency Land Management Fund

An Emergency Land Management Fund has been established for use in large-scale emergency situations impacting MSP species and their habitats and or which known management options are available.

Achievement Milestones FY 2019-2020

• Continue to incrementally build the emergency land management to increase it to $500,000.

3.0 Improve Wildlife Movement.

3.1 Wildlife Corridor and Linkages Monitoring

Species need to move to maintain population size and genetic diversity. In a landscape fragmented by urban development and linear infrastructure, restrictions to movement could result in a risk of extinction or extirpation.

Achievement Milestones FY 2019-2020

• Work with land managers to implement management actions based on the results of studies that evaluated the genetic connectivity of horned lizards throughout the MSP.

• Continue monitoring the status and movement of mountain lions in the San Diego region to evaluate the long-term trends and responses to corridor improvements. Collaborate with Orange and Riverside counties to improve regional connectivity. Test deterrent methods to reduce livestock losses in areas of the County with high depredation pressures.

• Complete the study to determine the movement of mule deer using genetic DNA fingerprinting at prioritized areas in the North County using the same techniques as used in South County and across State Route 67 (SR 67).

• Work with partners to develop and implement a region-wide camera monitoring strategy for wildlife.

• Continue the study begun in 2014 to determine the locations and movement of American badgers in western San Diego County, assess habitat and threats, and examine ways to improve badger connectivity and reduce mortality. Prepare a specific management plan with recommendations for badger habitat management and for connectivity enhancement within the Management Strategic Planning Area.

• Continue to support and work with partners to implement the existing linkage improvement recommendations from previous studies at prioritized locations in San Diego County.

• Support local efforts to implement the State Route 94 and SR 67 Wildlife Infrastructure Plans.

9

4.0 Promote Regional Coordination.

4.1 - 4.5 San Diego Management and Monitoring Program

The San Diego Management and Monitoring Program (SDMMP.com) was established by SANDAG in 2008 to provide a regionally coordinated, scientific approach to management and biological monitoring of rare plant and animal species on Conserved Lands in San Diego County. The SDMMP is the first program of its kind to help bring cities, counties, wildlife agencies, military, consulting firms, education, and non-profit entities together to develop and implement regional land management and biological monitoring objectives across NCCP boundaries. The SDMMP is fully funded by SANDAG and is embedded with the San Diego Field Office of the USGS. There are currently five positions in the SDMMP, which include the Program Administrator, Management and Monitoring Coordinator, Senior Ecologist, Geographic Information System (GIS) Manager, and Data Manager.

Achievement Milestone FY 2019-2020

• Fund and fill the following positions as needed: SDMMP Program Administrator, Management and Monitoring Coordinator, Senior Ecologist, GIS Manager, and Data Manager.

• Implement the updated MSP and all incorporated strategic plan elements (Connectivity, Fire, Monitoring).

• Support the SDMMP and stakeholders in MSP implementation by creating and managing GIS viewers, maps and map layers, webpage content, data analysis, and databases.

• Collaborate with the military and other regional conservation planning programs to promote intra- and inter- regional habitat conservation planning in Southern California.

• Provide a quantitative and qualitative assessment on the status of regional management and monitoring efforts.

• Hold regular meetings with stakeholders to collaborate on regional management and monitoring projects.

• Provide regional science support and data analysis of regional management and monitoring data.

• Update and manage the Conserved Lands Database.

• Refine the output products of the regional database, increase availability of data sets to preserve managers, and provide pre-formatted data reports to interested stakeholders.

• Incorporate all data from regional biological assessments into the regional master occurrence database for analysis.

4.6 Conserved Lands Database Management

The SDMMP has assumed management of the Conserved Lands Database under GIS Support.

Achievement Milestone FY 2019-2020

• Continue to update the Conserved Lands Database as more lands are acquired.

10

4.7 Administrative & Science Support

Achievement Milestone FY 2019-2020

• Provide regional science, technical support and data analysis of regional management and monitoring data and reports. Work with outside entity to develop regional metrics to track health of the preserve system and present to the public.

# Strategic Goal FY 19 AllocationProposed FY 2020

Funding AllocationComments/Recommended Approach

1 Promote key sensitive species

1.1 Rare and Endemic Plant Monitoring and Recovery $325,000 $375,000

Continue to facilitate monitoring by local jurisdictions and contract a

consultant to fill the gaps in monitoring for FY 2020. Continue funding for

additional development of seed and management plans, including funding for

seed collection and banking.

1.2 Vertebrate Monitoring and Recovery $830,935 $1,215,000

Continue funding species habitat recovery.

1.3 Invertebrate Monitoring and Recovery $113,535 $80,000

Continue to work with contractors on rare butterfly monitoring and

management.

1.4 General Stressors and Threats Management $155,000 $50,000Continue to work with partners to finalize and implement the Invasive Animal

Management Plan.

Subtotal $1,424,470 $1,720,000

2 Promote native vegetation communities

2.1 Vegetation Community Monitoring and Recovery $54,764 $150,000

Continue with regional vegetation monitoring protocol development and

testing. Initiate the development of a grazing plan in coordination with land

managers.

2.2 Pro-active Wildfire Planning and Management $0 $0 No additional funding needed.

2.3 Invasive Plant Species Management $400,000 $200,000Continue to work with County of San Diego Agriculture to strategically reduce

invasive species in the region.

2.4 Updated Vegetation Mapping $0 $0 No additional funding needed. Start vegetation mapping in FY 2022.

2.5 Enforcement $0 $0No additional funding needed. Continue to work with local jurisdictions to start

multiple pilot efforts.

2.6 Preserve level management plan standardization $0 $0 No additional funding needed.

2.7 Land Management Implementation (e.g., grants) $800,000 $600,000 Start 10th cycle of the land management grants in FY 2021.

2.8 Emergency Land Management Fund $0 $0 No additional funding needed.

Subtotal $1,254,764 $950,000

3 Improve wildlife movement

3.1 Wildlife Corridor and Linkages Monitoring $95,766 $100,000Continue to work with partners and contract a consultant to implement

regional wildlife movement monitoring using motion cameras.

Subtotal $95,766 $100,000

4 Promote regional coordination

4.1 Program Administrator $210,000 $0 Continue work under a future contract in 2020.

4.2 Management & Monitoring Coordinator $160,000 $155,000 Continue to work under existing contracts for FY 2020.

4.3 Biologist $200,000 $225,000 Continue to work under existing contracts for FY 2020.

4.4 GIS Support $200,000 $292,000 Continue to work under existing contracts for FY 2020.

4.5 Database Development and Support $270,000 $278,000 Continue to work under existing contracts for FY 2020.

4.6 Conserved Lands Database Management $0 $0 No additional funding needed.

4.7 Administrative & Science Support $185,000 $280,000 Continue to work under existing contracts for FY 2020.

Subtotal $1,225,000 $1,230,000

TOTAL FUNDING STRATEGY $4,000,000 $4,000,000

TABLE 1 - Recommended Fiscal Year 2020 Funding Allocation for Habitat Conservation Fund (CIP 1200300)

Attachment 2

11

TransNet Independent Taxpayer Oversight Committee Item: 9 October 16, 2019

2018 Regional Transportation Improvement Program: Amendment No. 8

Overview

The Regional Transportation Improvement Program (RTIP) is a five-year document that reflects funding sources, project phases, and fiscal years of implementation for all transportation-related projects in the San Diego region that: (1) use federal, state, or TransNet funds; (2) increase capacity of the transportation system; or (3) are regionally significant. SANDAG develops the RTIP based on projects included in San Diego Forward: The Regional Plan, as submitted by member agencies (local jurisdictions, transit agencies, Caltrans).

The 2018 RTIP covers FY 2019 – FY 2023 and is fiscally constrained, meaning that sufficient revenue is committed or reasonably assumed to be available from local, state, and/or federal sources for each phase of the included projects. Amendments are made to the RTIP on a quarterly (or as-needed) basis to reflect funding or scope changes. Amendment No. 8 is a quarterly amendment which implements the budget amendment approved by the Board of Directors on September 27, 2019, and changes to other state and local projects as requested.

Key Considerations

The changes are summarized in Attachment 1, with explanations for the significant changes. The proposed amendments are detailed in Attachment 2. Attachment 3 contains the map from the Board approved budget action. As funding for some of these projects was provided with non-TransNet funds and/or in years outside of the RTIP, not all projects on this map are included in the amendment.

Attachment 4 summarizes the eligibility requirements for projects to use TransNet funding. Amendment No. 8 includes three new TransNet projects. These projects were reviewed by the ITOC at a special meeting on September 16, 2019, and were found consistent with the TransNet Extension Ordinance.

Although the ITOC has reviewed the FY 2020 budget amendment for consistency with the TransNet Extension Ordinance, additional TransNet-funded projects are included as part of this RTIP amendment. The ITOC is asked to review and comment on the proposed Amendment No. 8, focusing its review on the TransNet-funded projects.

Action: Discussion

The ITOC is asked to provide feedback on the proposed Amendment No. 8, focusing its review on the TransNet-funded projects.

Fiscal Impact:

Amendment No. 8 reflects an increase of $356.1 million of funds programmed for the five-year period of the 2018 Regional Transportation Improvement Program. The increase in TransNet Major Corridor funds is $54.7 million.

Schedule/Scope Impact:

Approval of Amendment No. 8 will provide funding to implement the projects in the FY 2020 budget amendment, as approved by the Board of Directors on September 27, 2019.

2

Next Steps

On October 25, 2019, the Board is scheduled to review and approve Amendment No. 8 to the 2018 RTIP.

José Nuncio, TransNet Department Director

Key Staff Contact: Sue Alpert, (619) 595-5318, [email protected] Attachments: 1. Table 1 – Summary of Changes Report

2. Table 2 – 2018 RTIP Amendment No. 8 3. Map of 2018 RTIP Major Transportation Projects included in Amendment No. 8 4. TransNet Eligibility Analysis

Project ID Lead Agency Project TitleTotal 

Programmed Before 

Total Programmed 

Revised Cost Difference 

Percent Change

Change Description

SAN260San Diego Association of 

GovernmentsCOASTER Train Sets $0 $36,800 $36,800 100%

+TransNet‐MC; +CMAQ; +SB1‐LPP Formula ‐‐ New project approved by BOD action on 9/27/2019

CAL277 Caltrans I‐15/SR 78 HOV Connectors $7,937 $32,937 $25,000 315% ↑ TransNet ‐MC; + RSTP; + SB1‐LPP Formula

CAL277A Caltrans SR 78/I‐5 HOV Connector $0 $13,000 $13,000 100% + TransNet‐MC ‐‐ New project approved by BOD action on 9/27/2019

CAL278 Caltrans SR 78 HOV/Managed Lanes $1,683 $40,681 $38,998 2317%↑ TransNet ‐MC; + RSTP; + SB1‐LPP Formula ‐‐ Carry Over from 16‐30 due to BOD action on 9/27/19

CAL78D Caltrans I‐805 South Soundwalls ‐ Unit 1 $39,244 $63,244 $24,000 61% + TransNet ‐MC AC; ↑ RSTP

V14 Various AgenciesGrouped Projects for Bicycle and pedestrian facilities ‐ Active Transportation Program (ATP)

$57,557 $71,558 $14,001 24%↑ Local Funds; ↑ ATP‐S; ↑ ATP‐R ‐‐ Four ATP projects added to grouped listing due to State and Regional ATP Grant Awards

CAL68 Caltrans SR 94/125 Southbound to Eastbound Connector $16,240 $30,240 $14,000 86% + SB1‐LPP Formula; ↑ TransNet ‐MC

SAN153San Diego Association of 

GovernmentsThe Inland Rail Trail $45,885 $56,885 $11,000 24% + SB1‐LPP Formula; + RSTP; + Local Funds‐AC

V11 Various Agencies State Route 11 $681,747 $688,477 $6,730 1%↓ Prop 1B‐TCIF; + RSTP; ↑ CBI ‐‐ Funds added by BOD ac on on 9/27/19 for Investment Grade Traffic and Revenue Study and Bond Counsel and Documents

SAN261San Diego Association of 

GovernmentsPalomar Street Rail Grade Separation $0 $5,000 $5,000 100% + TransNet ‐MC ‐‐ New project approved by BOD action on 9/27/2019

SD49 San Diego, City of Median Improvements Citywide $7,475 $10,585 $3,110 42% ↑ TransNet ‐LSI; ↑ Local Funds 

SAN114San Diego Association of 

Governments

Grouped Projects for Rehabilitation or Reconstruction of Track Structures, Track, and Trackbed in Exisiting Rights‐of‐Way: Coastal Rail Corridor

$189,795 $192,795 $3,000 2%↑ RSTP; + Local Funds‐AC ‐‐ Project LOSSAN Corrdior Improvements Study added to Grouped project listing by BOD action on 9/27/19

SD237 San Diego, City of Coastal Rail Trail $1,500 $3,500 $2,000 133%↑ TransNet‐LSI ‐‐ Addi onal funds needed to complete Preliminary Engineering

SAN73ASan Diego Association of 

GovernmentsChesterfield Drive Crossing Improvements $6,810 $7,278 $468 7% ↑ TransNet ‐MC

SD208 San Diego, City of Juan Street Reconstruction $7,133 $7,092 ($41) ‐1% Project Completed ‐ TransNet‐ LSI Carry Over reconciled to payments

Table 1 - Summary of Changes Report ($000)Amendment No. 8 LEGEND:

↑  Increase↓  Reduce↔ Revise

Attachment 1

3

Project ID Lead Agency Project TitleTotal 

Programmed Before 

Total Programmed 

Revised Cost Difference 

PercentChange

Change Description

Table 1 - Summary of Changes Report ($000)Amendment No. 8 LEGEND:

↑  Increase↓  Reduce↔ Revise

Abbreviation Fund TypeATP‐R Active Transportation Program ‐ Regional CompetitionATP‐S Active Transportation Program ‐ Statewide CompetitionCBI Corridors and Borders Infrastructure ProgramCMAQ Congestion Mitigation and Air QualityLocal Funds ‐ AC Local Funds ‐ Advanced Construction; mechanism to advance local funds to be reimbursed at a later fiscal year with federal/state fundsProp 1B ‐ TCIF Trade Corridor Improvement FundsRSTP Regional Surface Transportation ProgramSB1 ‐ LPP Formula Senate Bill 1 ‐ Local Partnership Formula ProgramTransNet  ‐ LSI Prop A Extension ‐ Local System ImprovementsTransNet  ‐ MC Prop A Extension ‐ Major Corridors

4

Table 2

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: CAL68 18-08RTIP #:

Caltrans

Interchange on SR 94 at SR 94 and SR125 Milepost begins at 1 ends at

2 - near La Mesa and Lemon Grove on SR 125 from Lemon Avenue to

SR 94 and on SR 94 from SR 125 to Bancroft Dr. - Design and

Right-Of-Way of southbound 125 to eastbound SR 94 direct connector

Project Description:

Project Title: SR 94/125 Southbound to Eastbound Connector EA NO: 14665

PPNO: 0356

RTP PG NO: A-6

SANDAG ID: 1212501

Change Reason: Add new funding source, Increase funding

Capacity Status:CI Exempt Category:Non-ExemptRT:94

Est Total Cost: $30,240 Open to Traffic: Feb 2025

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $1,835 $2,025 $3,032 $2,022 $6,014 $2,900 $8,914

SB1 - LPP Formula $3,000 $4,000 $7,000 $7,000

STIP-RIP AC $7,948 $7,948 $7,948

State Cash $26 $26 $26

TCRP $6,352 $5,000 $1,352 $6,352

TransNet Subtotal $1,835 $2,025 $3,032 $2,022 $6,014 $2,900 $8,914

Other Subtotal $21,326 $6,378 $7,948 $3,000 $4,000 $12,948 $8,378

TOTAL $30,240 $8,213 $7,948 $5,025 $7,032 $2,022 $18,962 $11,278

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-00

18/19 19/20 20/21 21/22 22/23

TransNet - MC $1,835 $25 $32 $22 $1,914 $1,914

STIP-RIP AC $7,948 $7,948 $7,948

State Cash $26 $26 $26

TCRP $6,352 $5,000 $1,352 $6,352

TransNet Subtotal $1,835 $25 $32 $22 $1,914 $1,914

Other Subtotal $7,948 $12,948 $6,378 $1,378 $14,326

$16,240 $8,213 $7,973 $32 $22 $14,862 $1,378 TOTAL

Thursday, October 3, 2019

5

Attachment 2

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: CAL78D 18-08RTIP #:

Caltrans

Palomar to SR 54 - construct soundwalls (phase 1 and 2) and design

Sweetwater River Bridge improvements. Toll Credits will be used to

match federal funds for the PE phase, Toll Credits will be used to match

federal funds for the ROW phase, Toll Credits will be used to match

federal funds for the CON phase

Project Description:

Project Title: I-805 South Soundwalls - Unit 1 EA NO: 2T260, 43018

SANDAG ID: 1280515

Change Reason: Add new funding source, Increase funding

Capacity Status:NCI Exempt Category:Other - Noise attenuationRT:805

Est Total Cost: $88,243

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $3,184 $899 $3,035 $2,190 $1,383 $1,751 $3,811 $549 $8,082 $12,442

TransNet - MC AC $14,000 $14,000 $14,000

RSTP $29,029 $2,273 $2,100 $3,400 $14,711 $2,402 $19,689 $36,802

TransNet Subtotal $3,184 $899 $3,035 $2,190 $1,383 $15,751 $3,811 $22,082 $549 $26,442

Other Subtotal $36,802 $29,029 $2,273 $2,100 $3,400 $14,711 $2,402 $19,689

TOTAL $63,244 $32,213 $3,172 $3,035 $4,290 $1,383 $19,151 $18,522 $2,951 $41,771

* $72k of SHOPP contribution programmed under CAL371; $24.927m SHOPP for construction of Sweetwater River Bridge programmed under

CAL484 in grouped listing CAL46D; Additional conversion of AC to Federal Funds will happen future years outside the current period

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-05

18/19 19/20 20/21 21/22 22/23

TransNet - MC $3,184 $1,701 $2,303 $459 $182 $113 $3,845 $249 $3,848 $7,942

RSTP $29,029 $2,273 $12,611 $2,402 $16,289 $31,302

TransNet Subtotal $3,184 $1,701 $2,303 $459 $182 $113 $3,845 $249 $3,848 $7,942

Other Subtotal $16,289 $2,273 $12,611 $29,029 $2,402 $31,302

$39,244 $32,213 $3,974 $2,303 $459 $182 $113 $16,456 $2,651 $20,137 TOTAL

Thursday, October 3, 2019

6

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: CAL277 18-08RTIP #:

Caltrans

SR-78 from Post Mile 15.49 to R16.6 and on I-15 from Post Mile R30.63

to R31.56 - preliminary engineering for northbound I-15 to westbound

SR-78 and eastbound SR-78 to southbound I-15 HOV connectors and

operational improvements

Project Description:

Project Title: I-15/SR 78 HOV Connectors EA NO: 2T240

RTP PG NO: A-19; B-32

SANDAG ID: 1207802

Change Reason: Add new funding source, Increase funding

Capacity Status:CI Exempt Category:Non-ExemptRT:15

Est Total Cost: $340,000 Open to Traffic: Oct 2027

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $816 $3 $648 $55 $15 $1,400 $2,937 $2,937

RSTP $2,100 $3,500 $6,200 $11,800 $11,800

SB1 - LPP Formula $3,000 $1,500 $6,100 $600 $11,200 $11,200

STIP-RIP AC $7,000 $7,000 $7,000

TransNet Subtotal $816 $3 $648 $55 $15 $1,400 $2,937 $2,937

Other Subtotal $30,000 $7,000 $5,100 $5,000 $12,300 $600 $30,000

TOTAL $32,937 $816 $7,003 $5,748 $5,055 $12,315 $2,000 $32,937

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-06

18/19 19/20 20/21 21/22 22/23

TransNet - MC $816 $5 $64 $44 $8 $937 $937

STIP-RIP AC $7,000 $7,000 $7,000

TransNet Subtotal $816 $5 $64 $44 $8 $937 $937

Other Subtotal $7,000 $7,000 $7,000

$7,937 $816 $7,005 $64 $44 $8 $7,937 TOTAL

Thursday, October 3, 2019

MPO ID: CAL277A RTIP #:18-08

SR 78/I-5 HOV Connector

In Oceanside and Carlsbad, Intersection of SR 78 and I-5 Milepost

begins at 0 ends at 2 - environmental studies and preliminary engineering

for high-occupancy vehicle/managed lanes direct connectors at SR 78 to

I-5

Project Title:

Project Description:

SANDAG ID: 1207803

Change Reason: New Project

Capacity Status:NCI Exempt Category:Other - Engineering studiesRT:78

Est Total Cost: $13,000

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $13,000 $13,000 $13,000

TOTAL $13,000 $13,000 $13,000

7

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

Caltrans

Thursday, October 3, 2019

MPO ID: CAL278 RTIP #:18-08

SR78 HOV/Managed Lanes

SR 78 from I-5 to I-15 Milepost begins at 0 ends at 16.54 (16.54 miles) -

environmental studies and preliminary engineering for high-occupancy

vehicle/managed lanes

Project Title:

Project Description:

EA NO: 2T241

RTP PG NO: A.2 16

SANDAG ID: 1207801,

1207804

Change Reason: Add new funding source, Increase funding

Capacity Status:NCI Exempt Category:Other - Engineering studiesRT:78

Est Total Cost: $40,681

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

$1,681 $4,100 $9,500 $15,281 $15,281

$4,000 $19,700 $19,700

TransNet - MC

RSTP

SB1 - LPP Formula

$5,200 $10,500

$5,700 $5,700 $5,700

$1,681 $15,281 $15,281

$25,400 $4,000 $25,400

TransNet Subtotal

Other Subtotal

TOTAL $40,681 $1,681 $4,000

$4,100 $9,500

$5,200 $16,200

$9,300 $25,700 $40,681

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 16-30

18/19 19/20 20/21 21/22 22/23

TransNet - MC $1,683 $1,683 $1,683

$1,683 $1,683 $1,683 TOTAL

8

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SAN73A 18-08RTIP #:

San Diego Association of Governments

On Chesterfield Drive in the City of Encinitas, between Coast Highway

101 and San Elijo Avenue, and in the North County Transit District

coastal rail corridor - complete final design and construct at-grade

crossing improvements including bike and pedestrian facilities, double

track rail, signals, and safety improvements at Chesterfield Drive

Project Description:

Project Title: Chesterfield Drive Crossing Improvements SANDAG ID: 1239817

Change Reason: Increase funding

Capacity Status:NCI Exempt Category:Safety - Railroad/highway crossing

Est Total Cost: $7,278

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $471 $15 $124 $362 $486

TransNet - MC $1,726 $2,553 $262 $13 $50 $4,504 $4,554

Fed Rail Admin (FRA-PRIIA) $2,237 $83 $2,155 $2,238

TransNet Subtotal $2,197 $2,568 $262 $13 $174 $4,866 $5,040

Other Subtotal $2,238 $2,237 $83 $2,155

TOTAL $7,278 $4,434 $2,568 $262 $13 $257 $7,021

* *$34.3 K of TNET - MC applied to OWP 33011

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-01

18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $471 $15 $124 $362 $486

TransNet - MC $1,726 $1,677 $677 $5 $50 $4,036 $4,086

Fed Rail Admin (FRA-PRIIA) $2,237 $83 $2,155 $2,238

TransNet Subtotal $2,197 $1,692 $677 $5 $174 $4,398 $4,572

Other Subtotal $2,155 $83 $2,237 $2,238

$6,810 $4,434 $1,692 $677 $5 $257 $6,553 TOTAL

Thursday, October 3, 2019

9

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SAN114 18-08RTIP #:

San Diego Association of Governments

Projects are consistent with 40 CFR Parts 93.126 and 93.127 Exempt

Tables 2 and 3 categories: rehabilitation or reconstruction of track

structures, track, and trackbed in existing right-of-way (non-capacity

increasing)- from Oceanside to San Diego along the Coastal Rail

Corridor; design track improvements

Project Description:

Project Title: Grouped Projects for Rehabilitation or Reconstruction of Track Structures,

Track, and Trackbed in Exisiting Rights-of-Way: Coastal Rail Corridor

SANDAG ID: 1239803,

1239805, 1239810, 1239813,

1239814, 1239815, 1239816,

1239821

Change Reason: Increase funding

Capacity Status:NCI Exempt Category:Mass Transit - Track rehabilitation in existing right of way

Est Total Cost: $192,795

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $39,059 $11,721 $16,006 $1,499 $450 $225 $68,960 $68,960

CMAQ $64,154 $64,154 $64,154

FTA 5307 $6,711 $6,711 $6,711

FTA 5339 $5,321 $5,321 $5,321

Fed Rail Admin (FRA-PRIIA) $7,085 $7,085 $7,085

Other Fed - ARRA - FRA $3,360 $3,360 $3,360

RSTP $25,136 $1,000 $26,136 $26,136

RSTP - Conversion $2,000 $2,000 $2,000

CAP-TRADE $4,017 $4,017 $4,017

SB1 - LPP Formula $4,750 $4,750 $4,750

Local Funds $301 $301 $301

Local Funds AC $2,000 $(2,000)$0

TransNet Subtotal $39,059 $11,721 $16,006 $1,499 $450 $225 $68,960 $68,960

Other Subtotal $123,835 $120,835 $3,000 $123,835

TOTAL $192,795 $159,894 $11,721 $19,006 $1,499 $450 $225 $192,795

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-07

18/19 19/20 20/21 21/22 22/23

TransNet - MC $39,059 $11,721 $16,006 $1,499 $450 $225 $68,960 $68,960

CMAQ $64,154 $64,154 $64,154

FTA 5307 $6,711 $6,711 $6,711

FTA 5339 $5,321 $5,321 $5,321

Fed Rail Admin (FRA-PRIIA) $7,085 $7,085 $7,085

Other Fed - ARRA - FRA $3,360 $3,360 $3,360

RSTP $25,136 $25,136 $25,136

CAP-TRADE $4,017 $4,017 $4,017

SB1 - LPP Formula $4,750 $4,750 $4,750

Local Funds $301 $301 $301

TransNet Subtotal $39,059 $11,721 $16,006 $1,499 $450 $225 $68,960 $68,960

Other Subtotal $120,835 $120,835 $120,835

$189,795 $159,894 $11,721 $16,006 $1,499 $450 $225 $189,795 TOTAL

Thursday, October 3, 2019

10

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SAN153 18-08RTIP #:

San Diego Association of Governments

On and along the North County Transit District rail corridor from North

Melrose Drive in Oceanside to North Pacific Street in San Marcos -

construct seven miles of new bike path. Construction is funded through

phase 3 (3.0 miles in Vista). Phase 4 (Oceanside) will be constructed

when funding is identified

Project Description:

Project Title: The Inland Rail Trail PPNO: 7421W

RTP PG NO: A-19

SANDAG ID: 1223023

Change Reason: Add new funding source, Increase funding

Capacity Status:NCI Exempt Category:Air Quality - Bicycle and pedestrian facilities

Est Total Cost: $66,190

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $7,393 $2,115 $1,500 $698 $742 $2,152 $2,945 $7,352 $12,449

RSTP $3,400 $3,400 $3,400

RSTP - Conversion $2,100 $2,100 $2,100

ATP - R $500 $5,103 $500 $5,103 $5,603

SB1 - LPP Formula $3,000 $2,500 $5,500 $5,500

STIP-RIP AC $16,322 $16,322 $16,322

STIP-RIP STP TE $1,414 $1,414 $1,414

STIP-RIP State Cash $2,298 $183 $2,115 $2,298

Local Funds $1,080 $1,080 $1,080

Local Funds AC $2,100 $(2,100)$0

TDA - Bicycles $6,719 $2,025 $4,694 $6,719

TransNet Subtotal $7,393 $2,115 $1,500 $698 $742 $2,152 $7,352 $2,945 $12,449

Other Subtotal $44,436 $27,833 $500 $5,103 $8,500 $2,500 $5,202 $39,234

TOTAL $56,885 $35,226 $2,615 $6,603 $698 $9,242 $2,500 $7,354 $2,945 $46,586

* $1.461M of BTA programmed under County of San Diego CNTY78

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-05

18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $7,393 $2,115 $1,500 $698 $742 $2,152 $2,945 $7,352 $12,449

ATP - R $500 $5,103 $500 $5,103 $5,603

STIP-RIP AC $16,322 $16,322 $16,322

STIP-RIP STP TE $1,414 $1,414 $1,414

STIP-RIP State Cash $2,298 $183 $2,115 $2,298

Local Funds $1,080 $1,080 $1,080

TDA - Bicycles $6,719 $2,025 $4,694 $6,719

TransNet Subtotal $7,393 $2,115 $1,500 $698 $742 $2,152 $2,945 $7,352 $12,449

Other Subtotal $28,234 $500 $5,103 $5,202 $27,833 $33,436

$45,885 $35,226 $2,615 $6,603 $698 $742 $7,354 $2,945 $35,586 TOTAL

Thursday, October 3, 2019

11

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SAN260 18-08RTIP #:

San Diego Association of Governments

In the San Diego Region along the COASTER Corridor - Two additional

train sets to provide more frequent commuter rail service, including

30-minute peak period service. Toll Credits will be used to match federal

funds for the CON phase

Project Description:

Project Title: COASTER Train Sets RTP PG NO: A-13; B-26

SANDAG ID: 1239820

Change Reason: New Project

Capacity Status:CI Exempt Category:Non-Exempt

Est Total Cost: $58,800 Open to Traffic: May 2024

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $1,500 $2,200 $8,200 $11,900 $11,900

CMAQ $12,600 $12,600 $12,600

SB1 - LPP Formula $1,500 $2,200 $8,600 $12,300 $12,300

TransNet Subtotal $1,500 $2,200 $8,200 $11,900 $11,900

Other Subtotal $24,900 $1,500 $2,200 $21,200 $24,900

TOTAL $36,800 $3,000 $4,400 $29,400 $36,800

* Board action approved an additional $22M to be programmed in FY 24 in the 2020 RTIP to be approved 09/2020

MPO ID: SAN261 18-08RTIP #:

In the City of Chula Vista at Palomar and Industrial Boulevard on the

Blue Line Trolley - final design for Rail Grade SeparationProject Description:

Project Title: Palomar Street Rail Grade Separation SANDAG ID: 1210091

RAS (M-39)

Change Reason: New Project

Capacity Status:NCI Exempt Category:Safety - Railroad/highway crossing

Est Total Cost: $5,000

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - MC $1,000 $2,000 $2,000 $5,000 $5,000

TOTAL $5,000 $1,000 $2,000 $2,000 $5,000

* Environmental phase completed under OWP 3101800

Thursday, October 3, 2019

12

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SD49 18-08RTIP #:

San Diego, City of

Morena Bl - Ashton St to Littlefield St; University Ave - Winona to

5thTraffic Circles at various locations; Crown Point Dr at La Cima Crown

Point Dr at Moorland Ave; Crown Point Dr at Lamont St; Foothill

Boulevard & Loring Street - safety improvements and/or left turn

movements (AIG00001)

Project Description:

Project Title: Median Improvements Citywide TransNet - LSI: CR

Change Reason: Increase funding

Capacity Status:NCI Exempt Category:Safety - Adding medians

Est Total Cost: $10,585

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - L (Cash) $894 $894 $894

TransNet - LSI $500 $750 $800 $1,000 $1,000 $1,000 $5,050 $5,050

TransNet - LSI Carry Over $1,523 $1,041 $2,564 $2,564

Local Funds $1,327 $750 $1,102 $975 $2,077

TransNet Subtotal $2,917 $1,791 $800 $1,000 $1,000 $1,000 $8,508 $8,508

Other Subtotal $2,077 $1,327 $750 $1,102 $975

TOTAL $10,585 $4,244 $1,791 $1,550 $1,000 $1,000 $1,000 $1,102 $9,483

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-00

18/19 19/20 20/21 21/22 22/23

TransNet - L (Cash) $894 $894 $894

TransNet - LSI $500 $750 $1,140 $100 $100 $100 $2,690 $2,690

TransNet - LSI Carry Over $1,523 $1,041 $2,564 $2,564

Local Funds $1,327 $1,102 $225 $1,327

TransNet Subtotal $2,917 $1,791 $1,140 $100 $100 $100 $6,148 $6,148

Other Subtotal $225 $1,102 $1,327 $1,327

$7,475 $4,244 $1,791 $1,140 $100 $100 $100 $1,102 $6,373 TOTAL

Thursday, October 3, 2019

13

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SD208 18-08RTIP #:

COMPLETEDSan Diego, City of

Juan St from Taylor St to Sunset Road (1 miles) - this project provides

for the replacement of the existing concrete pavement, curb, gutter and

sidewalk on Juan Street from Taylor Street to Sunset Road; Phase I

(Taylor Street to Harney Street) will provide new asphalt cement and

cement treated base pavement; Phase II (Harney Street to Sunset Road)

will provide new Portland cement concrete pavement - Project No.

S-00602 (52-729.0)

Project Description:

Project Title: Juan Street Reconstruction TransNet - LSI: CR

Change Reason: Complete project

Capacity Status:NCI Exempt Category:Safety - Pavement resurfacing and/or rehabilitation

Est Total Cost: $7,092

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - L (Cash) $2,259 $2,259 $2,259

TransNet - LSI (Cash) $90 $90 $90

TransNet - LSI Carry Over $2,043 $2,043 $2,043

Local Funds $2,700 $1,000 $1,700 $2,700

TransNet Subtotal $4,392 $4,392 $4,392

Other Subtotal $2,700 $2,700 $1,000 $1,700

TOTAL $7,092 $7,092 $1,000 $6,092

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-05

18/19 19/20 20/21 21/22 22/23

TransNet - L (Cash) $2,259 $2,259 $2,259

TransNet - LSI (Cash) $90 $90 $90

TransNet - LSI Carry Over $2,043 $41 $2,084 $2,084

Local Funds $2,700 $1,000 $1,700 $2,700

TransNet Subtotal $4,392 $41 $4,433 $4,433

Other Subtotal $1,700 $1,000 $2,700 $2,700

$7,133 $7,092 $41 $1,000 $6,133 TOTAL

Thursday, October 3, 2019

14

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: SD237 18-08RTIP #:

San Diego, City of

The proposed path will begin near the City of Del Mar at the intersection

of Carmel Valley Road and Sorrento Valley Road to the north and

continues to Union Station Downtown San Diego. The City is currently

focusing on the northerly ten miles of the trail from the Sorrento Valley

Road/Carmel Valley to the Gilman Drive/I-5 intersections. - the Coastal

Rail Trail (CRT) is a multi-jurisdictional project among the coastal cities

of Oceanside, Del Mar, Carlsbad, Encinitas, Solana Beach and San

Diego.(City CIP S00951)

Project Description:

Project Title: Coastal Rail Trail TransNet - LSI: CR

Change Reason: Increase funding

Capacity Status:NCI Exempt Category:Air Quality - Bicycle and pedestrian facilities

Est Total Cost: $24,400

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - LSI $2,000 $2,000 $2,000

TransNet - LSI Carry Over $868 $632 $1,500 $1,500

TOTAL $3,500 $868 $632 $2,000 $3,500

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-00

18/19 19/20 20/21 21/22 22/23

TransNet - LSI Carry Over $868 $632 $1,500 $1,500

$1,500 $868 $632 $1,500 TOTAL

Thursday, October 3, 2019

15

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: V11 18-08RTIP #:

Various Agencies

On new alignment from SR 125 to the U.S.-Mexico Border - Construction

of four-lane toll highway facility, CVEF and POE in three segments:

Segment 1: SR-11/905 to Enrico Fermi; Segment 2: SR-11 from Enrico

Fermi to Siempre Viva; Segment 3: POE from Siempre Viva to Mexico

Border. Toll Credits will be used to match federal funds for the ROW

phase

Project Description:

Project Title: State Route 11 EA NO: 05631

PPNO: 0999

RTP PG NO: A-6; B-5

SANDAG ID: 1201101,

1201102, 1201103, 1201105

EARMARK NO: CA393/740

Change Reason: Add new funding source, Increase funding

Capacity Status:CI Exempt Category:Non-ExemptRT:11

Est Total Cost: $688,477 Open to Traffic: Phase 1: Mar 2016 Phase 2: Sep 2021 Phase 3: Nov 2022

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - Border $1,860 $6,128 $3,315 $4,673 $7,988

TransNet - MC $2,056 $1,294 $1,493 $3,028 $1,815 $4,843

CBI $123,789 $3,350 $5,000 $34,698 $94,091 $3,350 $132,139

HPP $800 $800 $800

INFRA $49,278 $49,278 $49,278

ITS $439 $439 $439

RSTP $2,500 $2,500 $2,500

Prop 1B - TCIF $71,625 $1,760 $73,385 $73,385

SB1 - TCEP $8,710 $33,458 $8,710 $1,150 $32,308 $42,168

STIP-IIP NHS $6,882 $6,882 $6,882

STIP-IIP Prior State Cash $5,200 $5,200 $5,200

STIP-IIP State Cash $919 $919 $919

Local Funds $247,001 $114,935 $3,858 $358,078 $361,936

TransNet Subtotal $3,916 $1,294 $7,621 $6,343 $6,488 $12,831

Other Subtotal $675,646 $209,654 $61,338 $40,218 $247,001 $117,435 $64,006 $95,241 $516,399

TOTAL $688,477 $213,570 $62,632 $47,839 $247,001 $117,435 $70,349 $101,729 $516,399

* Environmental Document funded from STIP-IIP prior to CIP

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-05

18/19 19/20 20/21 21/22 22/23

TransNet - Border $1,860 $5,628 $500 $3,360 $4,628 $7,988

TransNet - MC $2,056 $2,287 $500 $2,983 $1,860 $4,843

CBI $123,789 $3,350 $29,698 $94,091 $3,350 $127,139

HPP $800 $800 $800

INFRA $49,278 $49,278 $49,278

ITS $439 $439 $439

Prop 1B - TCIF $71,625 $2,530 $74,155 $74,155

SB1 - TCEP $42,168 $8,710 $1,150 $32,308 $42,168

STIP-IIP NHS $6,882 $6,882 $6,882

STIP-IIP Prior State Cash $5,200 $5,200 $5,200

STIP-IIP State Cash $919 $919 $919

Local Funds $247,001 $114,935 $3,858 $358,078 $361,936

TransNet Subtotal $3,916 $7,915 $1,000 $6,343 $6,488 $12,831

Other Subtotal $517,169 $97,326 $247,001 $114,935 $56,506 $209,654 $95,241 $668,916

$681,747 $213,570 $105,241 $1,000 $247,001 $114,935 $62,849 $101,729 $517,169 TOTAL

Thursday, October 3, 2019

16

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

MPO ID: V14 18-08RTIP #:

Various Agencies

Projects are consistent with 40 CFR Part 93.126 Exempt Tables 2 and

Table 3 categories - Bicycle and pedestrian facilities (both motorized and

Non-motorized)

Project Description:

Project Title: Grouped Projects for Bicycle and pedestrian facilities - Active Transportation

Program (ATP)

SANDAG ID: 1223014

Change Reason: Increase funding

Capacity Status:NCI Exempt Category:Air Quality - Bicycle and pedestrian facilities

Est Total Cost: $71,558

CONRWPEPRIORTOTAL 18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $3,017 $148 $94 $26 $3,285 $3,285

TransNet - CP $1,300 $1,300 $1,300

TransNet - LSI $200 $2,900 $3,100 $3,100

TransNet - LSI (Cash) $50 $50 $50

TransNet - LSI Carry Over $48 $48 $48

ATP - R $13,698 $325 $2,886 $755 $5,185 $22,849 $22,849

ATP - S $4,024 $9,740 $2,009 $1,425 $10,816 $28,014 $28,014

Local Funds $1,937 $2,987 $5,995 $1,593 $391 $10 $12,912 $12,912

TransNet Subtotal $3,067 $396 $4,294 $26 $7,783 $7,783

Other Subtotal $63,775 $19,659 $13,052 $10,890 $3,773 $11,207 $5,195 $63,775

TOTAL $71,558 $22,726 $13,448 $15,184 $3,799 $11,207 $5,195 $71,558

PE RW CONPRIORTOTAL

PROJECT LAST AMENDED 18-07

18/19 19/20 20/21 21/22 22/23

TransNet - BPNS $3,017 $148 $94 $26 $3,285 $3,285

TransNet - CP $1,300 $1,300 $1,300

TransNet - LSI $200 $2,900 $3,100 $3,100

TransNet - LSI (Cash) $50 $50 $50

TransNet - LSI Carry Over $48 $48 $48

ATP - R $13,698 $1,080 $2,886 $17,664 $17,664

ATP - S $4,024 $9,740 $1,951 $1,182 $3,468 $20,365 $20,365

Local Funds $2,062 $3,419 $5,908 $164 $183 $10 $11,745 $11,745

TransNet Subtotal $3,067 $396 $4,294 $26 $7,783 $7,783

Other Subtotal $49,774 $14,239 $10,745 $1,346 $3,651 $10 $19,784 $49,774

$57,557 $22,851 $14,635 $15,039 $1,372 $3,651 $10 $57,557 TOTAL

Thursday, October 3, 2019

17

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

RTIP Fund Types

Federal Funding

ARRA American Recovery and Reinvestment Act (Federal Stimulus Program)

BIP/CBI Border Infrastructure Program/Corridors and Borders Infrastructure Program

CMAQ Congestion Mitigation and Air Quality

INFRA/FASTLANE Infrastructure for Rebuilding America (INFRA) Grant

FRA-ARRA Federal Railroad Administration (Federal Stimulus)

FRA-PRIIA Federal Railroad Administration Passenger Rail Investment and Improvement Act of 2008

FTA Section 5307 Federal Transit Administration Urbanized Area Formula Program

FTA Section 5339 Federal Transit Administration Bus and Bus Facilities Formula Grant Program

HPP High Priority Program under SAFETEA-LU

HSIP Highway Safety Improvement Program

ITS Intelligent Transportation System

NHS National Highway System (administered by Caltrans)

RSTP Regional Surface Transportation Program

TE Transportation Enhancement Program

CMAQ/RSTP Conversion Reimbursement of advanced federal funds which have been advanced with local funds in

earlier years

State Funding

ATP Active Transportation Program (Statewide and Regional)

SB1 - TCEP Senate Bill 1 - Trade Corridor Enhancement Program

SB1 - LPP Formula Senate Bill 1 - Local Parternship Formula Program

STIP-IIP State Transportation Improvement Program - Interregional Program

STIP-RIP State Transportation Improvement Program - Regional Improvement Program

TCIF Trade Corridor Improvement Fund (State Prop. 1B)

TIRCP Transit and Intercity Rail Capital Program

TCRP Traffic Congestion Relief Program

Local Funding

Local Funds AC Local Funds - Advanced Construction; mechanism to advance local funds to be reimbursed at

a later fiscal year with federal/state funds

TDA Transportation Development Act

TransNet-Border Prop. A Extension Local Transportation Sales Tax - Border

TransNet-BPNS Prop. A Extension Local Transportation Sales Tax - Bicycle, Pedestrian and Neighborhood

Safety Program

TransNet-CP Prop. A Local Transportation Sales Tax - Commercial Paper

TransNet-L (Cash) TransNet - L funds which agencies have received payment, but have not spent

TransNet-LSI Prop. A Extension Local Transportation Sales Tax - Local System Improvements

TransNet-LSI Carry Over TransNet - LSI funds previously programmed but not requested/paid in year of allocation

TransNet-LSI (Cash) TransNet - LSI funds which agencies have received payment, but have not spent

Thursday, October 3, 2019

18

San Diego Region (in $000s)

2018 Regional Transportation Improvement Program - TransNet OnlyAmendment No. 8

TransNet-MC Prop. A Extension Local Transportation Sales Tax - Major Corridors

TransNet-MC AC TransNet - Major Corridors - Advanced Construction; mechanism to advance TransNet funds to

be reimbursed at a later fiscal year with federal/state funds

Thursday, October 3, 2019

19

Oceanside

Poway

SanDiego

Coronado

ImperialBeach

LaMesa

Santee

El Cajon

Escondido

Vista

SanMarcos

ChulaVista

UNITED STATES

MEXICO

County of San Diego

SanDiego

Carlsbad

Encinitas

DelMar

SolanaBeach

NationalCityNationalCity

Tijuana, B.C.

Camp Pendleton

PalaReservation

Pauma and YuimaReservation

RinconReservation La Jolla

Reservation

San PasqualReservation

Santa YsabelReservation

Mesa GrandeReservation

BaronaReservation

Capitan GrandeReservation

SycuanReservation

Jamul IndianVillage

KILOMETERS

MILES0 3 6

0 4 8

5022 9/20/2019

Not Mapped

Planning

Environmental

Design

Construction

Mobility Hub

13A 13B 13C

Complete Corridor Phase Implementation

11A

9B

5B

2C

6A

3B 10B

8A8A

8A

12A

3A

2D

2D

5A

5A

5A

8B

8C

1 E1

1 A1

9C1 D1

9A

6C

7A

2B

2A

1 C11 A1

1B

1C

4A

10A

11B

6B

6A

6A

6A

1A

3C

3C

3C

2C

3D

8A

6A

9A

6A

6A

905

54

5

282

163

94

15

15

56

78

67

125

75

94

52

11

1

2-D

21-D

5

5

15

805

76

78

78

6752

8

125

5

8

905905990505

5455544454

555

2822822828282

16316316363

94949494

151515

15151515151

5656556

78787878

67676767

8888

125125125

757575

94949494

52525252

7676767676

1111111

11

2222 DD-DDD-D

222-D1111-D-DD-D

555

555

1551515151

508088005050580505

76767676

78787878

78787878

6767676752525252

888

1255125125125555

125125125

805508088005050580505

555

888

Complete Corridors: Transportation Funding Options(FY2020-FY2025)

Attachment 3

20

Attachment 4

21

Eligibility Requirements Analysis for 2018 RTIP Amendment No. 8

TransNet Eligibility The TransNet Extension Ordinance (Ordinance) and the TransNet Ordinance and Expenditure Plan Rules (SANDAG Board Policy No. 031) establish guidance and requirements for the use of TransNet. Projects must comply with these rules to be considered eligible for TransNet and that compliance must be evaluated through the Regional Transportation Improvement Program (RTIP).

Projects programmed in the RTIP must satisfy the following criteria to comply with the Ordinance. They must: (1) be consistent with The 2019 Federal Regional Transportation Plan (Regional Plan); (2) be approved by the governing body of a local agency following a public hearing; (3) be on a Regional Arterial to utilize Regional Transportation Congestion Improvement Program (RTCIP) funds; (4) at least 70% of local street and road funds are used for congestion relief; (5) accommodate bicycles and pedestrians; (6) be financially constrained; and (7) follow the Public Participation Policy. Each of these items is tested every time the RTIP is amended and each amendment must maintain the conformity of the 2018 RTIP to the Ordinance.

Project Eligibility for the 2018 RTIP All TransNet-funded projects in the 2018 RTIP meet all requirements set forth by the Ordinance and were reviewed by the ITOC on May 9, July 11, and September 12, 2018. The ITOC recommended the projects to the Regional Transportation Commission. SANDAG has made the following eligibility findings for Amendment No. 8 to the 2018 RTIP under Board Policy No. 31 rules.

Rule No. 7 – Program of Projects Approval Process and Amendments

An amendment to revise the TransNet Program of Projects (POP) must first be approved by the governing body of the local agency proposing the revision within the preceding 12 months. All projects a local agency wishes to include in its POP must be consistent with the long-range Regional Transportation Plan. A POP amendment, which includes but is not limited to adding a new project, deleting an existing project, revising the project scope, or otherwise changing the TransNet funds programmed, requires that the local agency hold a noticed public hearing with an agenda item that clearly identifies the proposed project amendments and submits a resolution using the language and deadlines prescribed by the Regional Transportation Commission as documentation of governing body approval.

1) Finding: The 2018 TransNet POP, through Amendment No. 8, is consistent with the Regional Plan (policies, programs, and projects). All projects conform to the scope, cost, and schedule included in the Regional Plan.

2) Finding: All local agencies submitting project revisions impacting TransNet funding in Amendment No. 8 have submitted a signed resolution attesting to having held a public hearing within the preceding 12 months.

22

Rule No. 18 - Use of Local Street and Road Funds for Congestion Relief

As specified in Section 2(C)(1) of the Ordinance 04-01, at least 70% of the revenues provided for local street and road purposes should be used for congestion relief purposes and no more than 30% for maintenance purposes.

3) Finding: All projects programmed in Amendment No. 8 have been designated as Congestion Relief or Maintenance consistent with guidelines set forth in Attachment 2 of Board Policy No. 31.

Rule No. 21 - Accommodation of Bicyclists and Pedestrians

Section 4(E)(3) of the Ordinance requires that all new projects or major reconstruction projects funded with TransNet shall accommodate travel by pedestrians and bicyclists except where prohibited by law or disproportionate cost.

4) Finding: All projects programmed in Amendment No. 8 have indicated that adequate provisions for bicycle and pedestrian travel have been made according to the guidelines in Board Policy No. 31.

Rule No. 23: Application of TransNet Extension Ordinance Regional Transportation Congestion Improvement Program Requirements

5) Finding: Projects in Amendment No. 8 that have RTCIP funds have been designated as Regional Arterials consistent with the Regional Plan.

Financial Constraint

The projects contained within the 2018 RTIP must be reasonable when considering available funding sources.

6) Finding: The proposed Amendment No. 8 does not exceed the current Board of Directors-approved TransNet revenue forecast amount for the current biennial and the five-year period of the RTIP.

Board Policy No. 25 – SANDAG Public Participation Policy

The SANDAG Public Participation Policy requires that a draft of all formal RTIP amendments be provided to all interested parties for a 15-day comment period. SANDAG accomplishes this by posting it in the Public Notices section of the website.

7) Finding: The draft Amendment No. 8 was posted for public review on comment on October 2, 2019, ending on October 22, 2019.

TransNet Independent Taxpayer Oversight Committee Item: 10 October 16, 2019

Mid-Coast Corridor Transit Project Update

Overview

The Mid-Coast Corridor Transit project (Mid-Coast) extends the Metropolitan Transit System Blue Line Light-Rail Trolley from Old Town to University City in San Diego. Please see Attachment 1, Mid-Coast fact sheet.

Key Considerations

Mid-Coast is currently on schedule and service is expected to begin in late-2021. Construction is about 66% complete. Highlights this quarter include advancing the new Trolley bridge over San Diego River, bridges over Rose Creek, and completing pre-cast girder installation for the Trolley bridge flyover above the Los Angeles – San Diego – San Luis Obispo Rail corridor tracks. In addition, the final pre-cast concrete girders were placed on the Genesee viaduct and placement of the concrete deck on top of the girders has begun. Work on structure or platforms at all nine stations is underway. Track installation has started in the at-grade segment between Tecolote Creek and the Balboa Station and on the aerial guideway on the UC San Diego campus.

In the last quarter, an additional property was settled, and Mid-Coast light-rail vehicles continue to be delivered ahead of schedule. The contractor continues to meet interim disadvantaged business enterprise goals for the project.

Next Steps

Work on track, signals, and power supply is scheduled to begin. Right-of-way settlements will continue to be negotiated. Public outreach remains a priority to inform the public of project status and construction impacts, particularly for traffic impacts from bridge work on Interstate 5 south of Nobel Drive.

Jim Linthicum, Director of Mobility Management and Project Implementation

Key Staff Contact: John Haggerty, (619) 699 6937, [email protected] Attachments: 1. Mid-Coast Corridor Transit Project Fact Sheet

2. Independent Taxpayer Oversight Committee Chronology of Key Actions/Summary of Significant Decisions

Action: Information

An update on the Mid-Coast Corridor Transit project will be presented.

Fiscal Impact:

The Mid-Coast Corridor Transit project is expected to be completed within its budget of $2.17 billion.

Schedule/Scope Impact:

The Mid-Coast Corridor Transit project is on schedule to complete construction in mid-2021, with revenue service beginning in late-2021.

MID-COAST CORRIDOR TRANSIT PROJECT FACT SHEET

Transportation

The Project

The Mid-Coast Trolley will extend the Trolley

Blue Line service from the Santa Fe Depot in

Downtown San Diego north to the University

City community, serving major activity

centers such as Old Town, Mission Bay, the

University of California, San Diego (UC San

Diego), and Westfield UTC.

The route begins just north of the Old Town

Transit Center, travels in existing railroad

right-of-way, and alongside Interstate 5,

to serve UC San Diego and University City.

The extension will serve nine new stations:

Tecolote Road, Clairemont Drive, Balboa

Avenue, Nobel Drive, VA Medical Center,

Pepper Canyon (serving UC San Diego

west campus), Voigt Drive (serving UC San

Diego east campus), Executive Drive, and

the terminus station at the Westfield UTC

transit center.

The Need

Freeways and arterials in the Mid-Coast

corridor are generally congested, and traffic

congestion is projected to increase as the

region grows. By 2030, population in the

corridor is forecast to increase 19 percent

and employment is expected to increase

by 12 percent. The University City area has

developed as a major employment and

high-density residential area, similar to

Downtown San Diego. University City is

San Diego’s second downtown, and UC San

Diego is a high transit use area with students

and employment. SANDAG just opened a

regional transit center at Westfield UTC, and

the Mid-Coast Trolley will directly connect to

the transit center, increasing transit ridership.

The Mid-Coast Trolley extension will provide

an effective alternative to congested freeways

and roadways for travelers, improve public

transit services, and enhance travel options

by connecting the corridor with areas served

by the existing trolley system.

Project Costs

The current project budget is $2.17 billion,

which includes financing costs.

Project Status

In fall 2014, the SANDAG Board of Directors

and the Federal Transit Administration (FTA)

gave final environmental clearance to the

project. In September 2016, through its

New Starts Program, the Federal Transit

Administration signed a Full Funding Grant

Agreement with SANDAG to provide the

nearly 50 percent federal match needed to

fund the project and allow construction to

immediately start in fall 2016. In June 2017,

SANDAG secured a loan from the federal

Transportation Infrastructure Finance and

Innovation Act (TIFIA) program, which

reduces borrowing costs and increases

flexibility that will save taxpayer dollars in

building the largest transit project in the

region’s history.

Pre-construction activities - consisting of the

relocation of underground utilities - began in

early 2016, and primary construction activities

(Continued on reverse)

401 B Street, Suite 800

San Diego, CA 92101

(619) 699-1900

Fax (619) 699-1905sandag.org

SANDAGregion

SANDAGregion

@SANDAG

Attachment 1

2

January 2019

4852

San Diego River

d

Gilm

an D

r

La Jolla PkwyVia Capri

Turquoise St

Mission Blvd

Foothill Blvd Beryl St

Grand AveGarnet Ave

Point Loma Ave

Barnett Ave

Prospe

ct St

La Jolla Blvd

Pearl St

Carroll Rd

Clairemont Mesa Blvd

Jutland Dr

Linda

Vista

Rd

Convoy St

Genesee Ave

Genesee AveUlric St

Tecolo

te Rd

Friars Rd

Washington StUniversity Ave

5th Ave6th Ave

5th Ave1st Ave

Front St

6th Ave

19th St

17th StPark Blvd

Park BlvdFlorida St

Florida St

Cabrillo Fwy

Persh

ing D

r

Rosecra

ns St

Rosecra

ns St

Catal

ina B

lvd

Nimitz Blvd

Point Loma Blvd

N Harbor DrW Laurel St

B St

F St

Market St

Suns

et Cliffs

Blvd

Sea World Dr

More

na B

lvd

Sports Arena Blvd

Ingraham St

W Mission Bay Dr

Miss

ion C

enter

Rd

La Jolla Village Dr

Governor Dr

Nautilus St

Clairemont Dr

Balboa Ave

Pacific Hwy

Mt A

cadia

Blvd

Torrey Pines Rd

Miramar RdN To

rrey P

ines R

d

BalboaAveMorena Blvd

Robinson Av

Regents Rd

Genesee Ave

Soledad Mtn Rd

Nobel Dr

Voigt Dr

Rege

nts Rd

ClairemontDrive

BalboaAvenue

NobelDrive

ExecutiveDrive

TecoloteRoad

ClairemontDrive

BalboaAvenue

NobelDrive

ExecutiveDrive

TecoloteRoad

LINDAVISTA

MISSION BEACH

LA JOLLA

LINDAVISTA

PACIFIC BEACH

MISSION VALLEY

LA JOLLA

CLAIREMONT MESACLAIREMONT MESA

OCEANBEACH

OLD TOWNSAN DIEGO

UPTOWN

UNIVERSITY CITY UNIVERSITY CITY

LINDAVISTA

PACIFIC BEACH

MISSION BEACH

MISSION VALLEY

MIDWAY/PACIFIC HWY

CORRIDOR

MIDWAY/PACIFIC HWY

CORRIDOR

OCEANBEACH

OLD TOWNSAN DIEGO

DOWNTOWNDOWNTOWN

UPTOWN

Trolley - Green Line

Trolley - Blue Line

Trolley - Future Blue Line Extension At-Grade

COASTER Line

Alignment

COASTER Station

Trolley Station

Transit Center with a FutureTrolley Station

Trolley - Future Blue LineService on Existing Tracks

Trolley - Future Blue Line Extension - AerialTrolley - Future Blue Line Extension - Undercrossing

Trolley - Orange Line

Mid-Coast CorridorTransit Project

210 Miles

Transit Center

Future Trolley StationNew Park-and-Ride Facility

San Diego BaySan Diego Bay

Pacific Ocean

Pacific Ocean

Mis

sion

Bay

Mis

sion

Bay

Santa FeDepot

Old TownTransit Center

VA MedicalCenter

VA MedicalCenter

Pepper Canyon(at UCSD West)Pepper Canyon(at UCSD West)

Voigt Drive(at UCSD East)Voigt Drive(at UCSD East)

Terminus(at Westfield UTC)Terminus(at Westfield UTC)

For More Information

» Visit: KeepSanDiegoMoving.com/MidCoast

» Call: (877) 379-0110

» Facebook: MidCoastTrolley

» Twitter: @MidCoastTrolley

started in fall 2016. Construction is now well

underway along the entire 11-mile alignment.

Service is scheduled to begin in 2021.

Funding Status

The Mid-Coast Trolley extension is fully

funded. The project is one of the highest

priorities for SANDAG in its TransNet Early

Action Program. The FFGA is providing

approximately 48 percent of the project

funding, with TransNet providing the

remaining local match. TransNet also will

provide operating funds for the Mid-Coast

Trolley extension through the year 2048.

Summary

The Mid-Coast Trolley extension will improve

access to growing employment, education,

and residential areas. A trolley extension

is particularly well-suited to the corridor

because:

» It connects with the existing regional rail

system at the Old Town Transit Center

and Downtown San Diego at Santa Fe

Depot, providing a vast improvement to

mobility within the region.

» As an extension of the existing Trolley

Blue Line, it will offer a one-seat

(no transfer) ride from the international

border and communities south of

Downtown San Diego all the way to

University City.

» It will connect residents of the corridor

with major activity centers such as

the VA Medical Center and two major

hospitals, UC San Diego, Westfield UTC,

Old Town, and Downtown San Diego.

3

Attachment 2

4

Independent Taxpayer Oversight Committee Chronology of Key Actions / Summary of Significant Discussion

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

Independent Taxpayer Oversight Committee (ITOC), July 10, 2019, Item No. 12

Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project and other projects being built concurrently in the corridor.

ITOC, April 10, 2019, Item No. 14 Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project and other projects being built concurrently in the corridor.

Transportation Committee (TC) April 5, 2019, Item No. 8 Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project and other projects being built concurrently in the corridor.

TC, January 4, 2019, Item No. 6 Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project and other projects being built concurrently in the corridor.

TC, October 5, 2018, Item No. 6, Mid-Coast Corridor Transit Project Update

Staff presented an update on the progress and status of the Mid-Coast Trolley project.

Board of Directors (BOD), July 13, 2018, Item No. 3, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The TC recommended that the BOD approve amendments to the FY 2019 Program Budget to: (1) add $400,000 in UC San Diego funds to the I-5/Voigt Drive Improvements project (Capital Improvement Program [CIP] Project No. 1200507) for design of UC San Diego betterments; and (2) add $4 million in UC San Diego funds to the I-5/Gilman Drive Bridge project (CIP Project No. 1200508) for construction of UC San Diego betterments.

TC, July 6, 2018, Item No. 10, Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project and other projects being built concurrently in the corridor.

BOD, May 25, 2018, Item No. 15, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The BOD adopted Resolution of Necessity No. 2018-19 by a two-thirds vote of all member agencies, pertaining to acquisition of property for the Mid-Coast Corridor Transit project; and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject parcel.

5

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

BOD, May 25, 2018, Item No. 6, Mid-Coast Trolley Grade Adjustment at Pepper Canyon: California Environmental Quality Act Addendum

The BOD, acting as the San Diego County Regional Transportation Commission (RTC): (1) adopted RTC Resolution No. RTC-2018-06, approving raising the grade and utility relocations within Pepper Canyon; and (2) approved the California Environmental Quality Act (CEQA) Addendum to the previously certified Final Supplemental Environmental Impact Statement and Subsequent Environmental Impact Report (State Clearing House No. 2010051001) prior to making a decision on the project, and accept the Addendum into the environmental record.

BOD, May 11, 2018, Item No. 3, Mid-Coast Trolley Nobel Drive Station

The BOD, also acting as the RTC, (1) adopted RTC Resolution No. RTC-2018-0519, approving design changes to the Mid-Coast Trolley Nobel Drive Station, including parking structure and other site modifications; (2) approved the California Environmental Quality Act (CEQA) Addendum to the previously certified Final Subsequent Environmental Impact Report (State Clearing House No. 2010051001) and accepted the Addendum into the environmental record; (3) confirmed that nothing contained in the Addendum impacts any of the findings made by the BOD in its adoption of Resolution of Necessity (Resolution No. 2018-05) to acquire specified property necessary to construct and operate the project and related public infrastructure improvements at the Nobel Drive Station; and (4) authorized the Executive Director to consider and approve future CEQA addenda for the Mid-Coast Corridor Transit project (CIP Project No. 1257001) for which none of the CEQA guidelines identified in Title 14 California Code of Regulations Section 15162 requiring the preparation of a subsequent Environmental Impact Report or Negative Declaration are met.

TC, April 6, 2018, Item No. 3, Mid-Coast Corridor Transit Project 3A. Status Update 3B. Proposed FY 2018 Program Budget Amendment: Pepper Canyon Station

Staff presented an update on the Mid-Coast Corridor Transit project. The TC recommended that the Executive Committee: (1) approve an amendment to the FY 2018 Program Budget to create a new CIP project for the construction of betterments at Pepper Canyon Station; (2) accept $3.03 million from UC San Diego to fully fund the project; and (3) authorize the Executive Director to execute an amendment to the Construction Cooperation Agreement with UC San Diego related to the betterments.

BOD, March 23, 2018, Item No. 15, Overview of Proposed 2018 TransNet Short-term Bond Issuance

The BOD adopted resolution No. RTC-2018-02, authorizing the issuance of up to $537.5 million in short-term, fixed-rate bonds to advance implementation of the Mid-Coast Corridor Transit project funding strategy.

6

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, March 16, 2018, Item No. 7, TransNet 2018 Note Issuance: Review of Draft Note Documents

The TC recommended that the BOD, acting as the RTC, adopt Resolution No. RTC-2018-02, authorizing the issuance of up to $537.5 million in fixed-rate, tax-exempt municipal short-term notes to advance implementation of the Mid-Coast Corridor Transit project; and the execution and distribution of the documents.

ITOC, March 14, 2018, Item No. 10, Overview of Proposed 2018 TransNet Short-term Bond Issuance

Staff presented the ITOC with a similar report as that presented to the BOD on March 9, 2018.

BOD, March 9, 2018, Item No. 4, Overview of Proposed 2018 TransNet Short-term Bond Issuance

Staff presented an overview of the proposed bond strategy and financing schedule for the issuance of up to $537.5 million in short-term, fixed-rate bonds to advance implementation of the Mid-Coast Corridor Transit project funding strategy.

BOD, January 26, 2018, Item No. 16, Proposed FY 2018 Program Budget Amendments: Bridge 257.2 Replacement Project

The BOD received the same report presented to the TC in January 2018, and (1) approved amendments to the FY 2018 Program Budget to create a new CIP Project No. 1146500 for the Bridge 257.2 Replacement project by transferring the associated scope and budget from the Elvira to Morena Double Track (EMDT) project (CIP Project No. 1239811) and accepting $3.387 million from North County Transit District (NCTD) to fully fund the project; (2) adopted Resolution No. 2018-12, authorizing the use of the Construction Manager/General Contractor (CM/GC) construction delivery method for the new CIP project; and (3) authorized the Executive Director to negotiate and execute a construction change order with Mid-Coast Transit Constructors for the project.

TC, January 19, 2018, Item No. 5, Proposed FY 2018 Program Budget Amendments: Bridge 257.2 Replacement Project

The TC recommended that the BOD: (1) approve amendments to the FY 2018 Program Budget to create a new CIP Project No. 1146500 for the Bridge 257.2 Replacement project by transferring the associated scope and budget from the EMDT project (CIP Project No. 1239811) and accepting $3.387 million from NCTD to fully fund the project; (2) adopt Resolution No. 2018-12, authorizing the use of the CM/GC construction delivery method for the new CIP project; and (3) authorize the Executive Director to negotiate and execute a construction change order with Mid-Coast Transit Constructors for the project.

TC, January 19, 2018, Item No. 4, Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project as well as five additional capital projects in the corridor.

7

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

BOD, September 22, 2017, Item No. 16, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The BOD adopted Resolution of Necessity No. 2018-05 by a two-thirds vote, pertaining to acquisition of property for the Mid-Coast Corridor Transit project; and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject parcels.

BOD, June 23, 2017, Item No. 9, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The BOD adopted Resolution of Necessity No. 2017-29 by a two-thirds vote, pertaining to acquisition of property for the Mid-Coast Corridor Transit project; and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject parcel.

BOD, May 26, 2017, Item No. 15, Transportation Infrastructure Finance and Innovation Act Federal Credit Assistance: Mid-Coast Corridor Transit Project

The BOD: (1) approved the Transportation Infrastructure Finance and Innovation Act (TIFIA) financing method for the Mid-Coast Corridor Transit project; (2) adopted RTC Resolution No. RTC-2017-06, authorizing the Executive Director to execute the TIFIA Loan Agreement and Direct Agreements, and the Seventh Supplemental Indenture; and (3) adopted RTC Resolution No. RTC-2017-07, authorizing the Executive Director to execute the SANDAG Direct Agreement.

ITOC, January 11, 2017, Item No. 5, Proposed FY 2017 Program Budget Amendment: Elvira to Morena Double Track Project and Construction Manager/General Contractor Construction Services Agreement Supplement 5

The ITOC received the same report regarding the FY 2017 proposed budget amendment provided to the TC and BOD in December 2016 as shown below.

BOD, December 16, 2016, Item No. 12, Proposed FY 2017 Program Budget Amendment: Elvira to Morena Double Track Project and Construction Manager/General Contractor Construction Services Agreement Supplement 5

The BOD received the same report provided to the TC at the December 2016 meeting and approved an amendment to the FY 2017 Program Budget adding $61.98 million in Transit and Intercity Rail Capital Program funding, $18.15 million in TransNet Program funding, and $3.96 million in funds from the City of San Diego to the EMDT project (CIP Project No. 1239811), increasing the project budget to $192.5 million; (2) approved the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 5 of the CM/GC Construction Services Agreement for the EMDT project in the amount of $93.6 million; and (3) authorized the Executive Director to execute Supplement 5.

BOD, December 16, 2016, Item No. 11, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The BOD adopted Resolution of Necessity No. 2017-14 by a two-thirds vote, pertaining to acquisition of property for the Mid-Coast Corridor Transit project and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject parcels.

8

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, December 9, 2016, Item No. 4, Proposed FY 2017 Program Budget Amendment: Elvira to Morena Double Track Project and Construction Manager/General Contractor Construction Services Agreement Supplement 5

The TC recommended that the BOD: (1) approve an amendment to the FY 2017 Program Budget adding $61.98 million in Transit and Intercity Rail Capital Program funding, $18.15 million in TransNet Program funding, and $3.96 million in funds from the City of San Diego to the EMDT project (CIP Project No. 1239811), increasing the project budget to $192.5 million; (2) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 5 of the CM/GC Construction Services Agreement for the EMDT project in the amount of $93.6 million; and (3) authorize the Executive Director to execute Supplement 5.

BOD, September 23, 2016, Item No. 11, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project

The BOD adopted Resolutions of Necessity Nos. 2017-01, 2017-02, and 2017-06 through 2017-10 by a two-thirds vote pertaining to acquisition of properties for the Mid-Coast Corridor Transit project and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject parcels.

ITOC, June 8, 2016, Item No. 8, Mid-Coast Corridor Transit Project Construction Manager/General Contractor Construction Contract Award

The ITOC was presented with an update of the Mid-Coast Corridor Transit project progress.

BOD, May 27, 2016, Item No. 17, Mid-Coast Corridor Transit Project: Supplement 4 To Construction Manager/General Contractor Construction Services Agreement

The same report presented at the May 20, 2016, TC meeting was presented. The BOD authorized the Executive Director to: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 4 of the CM/GC Construction Services Agreement (Supplement 4) for the Mid-Coast Corridor Transit project in the amount of $927.5 million; and (2) execute Supplement 4 for the Mid-Coast project after receiving an executed Full Funding Grant Agreement from the Federal Transit Administration (FTA).

TC, May 20, 2016, Item No. 7, Mid-Coast Corridor Transit Project: Supplement 4 To Construction Manager/General Contractor Construction Services Agreement

The TC recommended that the BOD authorize the Executive Director to: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 4 of the CM/GC Construction Services Agreement (Supplement 4) for the Mid-Coast Corridor Transit project in the amount of $927.5 million; and (2) execute Supplement 4 for the Mid-Coast Corridor Transit project after receiving an executed Full Funding Grant Agreement from the FTA.

ITOC, May 11, 2016, Item No. 8, FY 2017 TransNet Early Action Program Budget Update

Staff presented the proposed FY 2017 TransNet Early Action Program (EAP) Budget, which included an update on the Mid-Coast Corridor Transit project budget.

9

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

BOD, April 22, 2016, Item No. 11, Hearing of Necessity: Acquisition of Property Interests Located In The City Of San Diego For The Mid-Coast Corridor Transit Project And Elvira To Morena Double Track Project

The BOD: (1) received public testimony; (2) adopted Resolutions of Necessity Nos. 2016-23 through 2016-26 by a two-thirds vote pertaining to acquisition of property for the Mid-Coast Corridor Transit and EMDT projects; and (3) authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the partial interests in the subject parcels.

BOD, March 25, 2016, Item No. 18, Hearing Of Necessity: Acquisition Of Property Interests Located In The City Of San Diego For The Mid-Coast Corridor Transit Project

The BOD: (1) received public testimony; (2) adopted Resolution of Necessity No. 2016-15 by a two-thirds vote, pertaining to acquisition of property for the projects; and (3) authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the partial interests in the subject parcels.

BOD, March 25, 2016, Item No. 17, San Diego River Bridge Double Track Project: Supplement 2 To Construction Manager/ General Contractor Construction Services Agreement

The same report provided at the March 18, 2016, TC meeting was presented. The BOD authorized the Executive Director to: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 2 to the CM/GC Construction Services Agreement (Supplement 2) for the San Diego River Bridge Double Track (SDRBDT) project in the amount of $64.36 million; (2) execute Supplement 2 for the SDRBDT project; and; (3) issue a limited Notice to Proceed for up to $20 million for early procurement and work items within the existing SDRBDT project budget.

BOD, March 25, 2016, Item No. 16, Mid-Coast Corridor Transit Project and Elvira To Morena Double Track Project: Construction Manager/ General Contractor Construction Contract Amendments

The same report provided at the March 18, 2016, TC meeting was presented. The BOD authorized the Executive Director to amend the CM/GC Construction Services Agreement, Supplement 1, with Mid-Coast Transit Constructors for the construction of storm drain utility relocations and bridge work for the Mid-Coast Corridor Transit project and EMDT project in an amount not to exceed $9,240,540.

TC, March 18, 2016, Item No. 6, San Diego River Bridge Double Track Project: Construction Manager/ General Contractor Construction Services Agreement

The TC recommended the BOD authorize the Executive Director to: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 2 of the CM/GC Construction Services Agreement (Supplement 2) for the SDRBDT project in the amount of $64.36 million; (2) execute Supplement 2 for the SDRBT project; and (3) issue a limited Notice to Proceed for up to $20 million for early procurement and work items within the existing SDRBDT project budget.

10

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, March 18, 2016, Item No. 5, Mid-Coast Corridor Transit Project and The Elvira To Morena Double Track Project: Construction Manager/ General Contractor Construction Contract Amendments

The TC recommended the BOD authorize the Executive Director to amend the CM/GC Construction Services Agreement, Supplement 1, with Mid-Coast Transit Constructors for the construction of storm drain utility relocations and bridge work for the Mid-Coast Corridor Transit project and the EMDT in an amount not to exceed $9,240,540.

BOD, February 26, 2016, Item No. 22, Hearing Of Necessity: Acquisition Of Property Interests Located In The City Of San Diego For The Mid-Coast Corridor Transit Project And The Elvira To Morena Double Track Project

Staff provided a report asking the BOD to: (1) receive public testimony; (2) adopt Resolution of Necessity No. 2016-15 by a two-thirds vote, pertaining to acquisition of property for the projects; and (3) authorize staff to proceed with all condemnation filings and proceedings necessary to acquire the partial interests in the subject parcels. The BOD adopted the Resolution of Necessity No. 2016-15 and authorized condemnation filings and proceedings.

BOD, February 12, 2016, Item No. 2, Closed Session: Conference With Legal Counsel - To Consider The Initiation Of Litigation To Acquire Property Interests Via Eminent Domain For The Mid-Coast Corridor Transit Project, San Diego River Double Track Project, And Elvira To Morena Double Track Project Pursuant To Government Code Section 54956.9(D)(4)

The BOD considered the initiation of litigation to acquire property interests via eminent domain for the Mid-Coast Corridor Transit project, San Diego River Double Track project, and the EMDT project. There was no reportable action.

BOD, January 22, 2016, Item No. 12, Hearing of Necessity: Acquisition of Property Interests Located in the City of San Diego for the Mid-Coast Corridor Transit Project, San Diego River Double Track Project, And Elvira To Morena Double Track Project

Staff presented a report asking the BOD: (1) receive public testimony; (2) adopt Resolution of Necessity No. 2016-11 by a two-thirds vote pertaining to acquisition of the subject property interests for the projects; and (3) authorize staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject properties. The BOD adopted Resolution of Necessity No. 2016-11 and authorized staff to proceed with all condemnation filings and proceedings, as amended.

BOD, January 22, 2016, Item No. 11, Proposed Construction Manager/General Contractor Delivery Method: Interstate 5/Gilman Drive Bridge

Staff presented the same report presented at the January 15, 2016, TC meeting. The BOD adopted Resolution No. 2016-10 and authorized the ED to negotiate and award a Preconstruction Service Contract for this project to Mid-Coast Transit Constructors.

TC, January 15, 2016, Item No. 5, Proposed Construction Manager/General Contractor Delivery Method: Gilman Drive Bridge

The TC was asked to recommend that the BOD: (1) adopt Resolution No. 2016-10, authorizing the use of the CM/GC construction delivery method for the Interstate 5/Gilman Drive Bridge project; and (2) authorize the Executive Director to negotiate and award a Preconstruction Service Contract for this project to Mid-Coast Transit Constructors.

11

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, October 16, 2015, Item No. 10, Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project.

BOD, June 26, 2015, Item No. 11, Construction Manager/General Contractor Construction Services Contract: Mid-Coast Corridor Transit and Elvira to Morena Double Track Projects

Staff presented the same report presented at the June 19, 2015, TC meeting. The BOD approved authorizing the Executive Director to execute a CM/GC Construction Services Agreement, with Mid-Coast Transit Constructors including Supplement 1 for the construction of utility and rail relocation work for the Mid-Coast Corridor Transit project and the EMDT project.

TC, June 19, 2015, Item No. 4, Construction Manager/General Contractor Construction Services Contract: Mid-Coast Corridor Transit and Elvira to Morena Double Track Projects

The TC was asked to recommend that the BOD authorize the Executive Director to execute a CM/GC Construction Services Agreement, with Mid-Coast Transit Constructors including Supplement 1 for the construction of utility and rail relocation work for the Mid-Coast Corridor Transit project and the EMDT project.

BOD, May 22, 2015, Item No. 12, Proposed Construction Manager/General Contractor Delivery Method: Interstate 5/ Voigt Bridge and Coastal Rail Trail San Diego: Rose Creek projects

Staff presented the same report presented at the May 15, 2015, TC meeting. The BOD approved Resolution Nos. 2015-29 and 2015-30 and authorized the Executive Director to negotiate and award the Preconstruction Services Contract to Mid-Coast Transit Constructors.

TC, May 15, 2015, Item No. 6, Proposed Construction Manager/General Contractor Delivery Method: Interstate 5/ Voigt Bridge and Coastal Rail Trail San Diego: Rose Creek projects

The TC recommended that the BOD: (1) approve Resolution Nos. 2015-29 and 2015-30, authorizing the use of the CM/GC construction delivery method for the Interstate 5/Voigt Drive Bridge and Street Realignment and Coastal Rail Trail San Diego: Rose Creek projects; and (2) authorize the Executive Director to negotiate and award the Preconstruction Services Contract for these projects to Mid-Coast Transit Constructors in coordination with the Mid-Coast Corridor Transit project.

BOD, March 27, 2015, Item No. 11, Proposed Budget Amendment: Interstate 5/Gilman Drive Bridge

Staff presented the same report provided at both the March 11, 2015, ITOC, and the March 20, 2015, TC meetings. The BOD voted in favor of the recommendation, and the FY 2015 Program Budget amendment was approved.

TC, March 20, 2015, Item No. 4, Proposed Budget Amendment: Interstate 5/Gilman Drive Bridge

Staff presented the same report provided at the March 11, 2015, ITOC meeting. The TC recommended that the BOD approve an amendment to the FY 2015 Program Budget to fund the I-5/Gilman Drive Bridge project.

12

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

ITOC, March 11, 2015, Item No. 17, Proposed Budget Amendment: Interstate 5/Gilman Drive Bridge

Staff presented a proposed draft budget amendment to provide $15 million for the Interstate 5/Gilman Drive Bridge project. The proposed action was requested to coordinate the construction of the Interstate 5/Gilman Drive Bridge with Mid-Coast Light Rail Transit (LRT) and Voigt Drive Improvements to minimize the overall construction time and impacts to the University and its surrounding community. The ITOC reviewed the proposed budget amendment and expressed support.

ITOC, January 14, 2015, Item No. 11, Mid-Coast Corridor Transit Project Update

Staff presented a report on the status of the Final Supplemental Environmental Impact Statement/Subsequent Environmental Impact Report and the CM/GC construction method of the Mid-Coast Corridor Transit P project.

BOD, November 21, 2014, Item No. 11, Mid-Coast Corridor Transit Project Final Subsequent Environmental Impact Report

Staff presented a report on the Final Subsequent EIR and discussed actions necessary to complete the CEQA review process. The BOD adopted Resolution No. RTC 2015-03, certifying the Final Subsequent Environmental Impact Report for the Mid-Coast Corridor Transit project adopting Findings of Fact, a Statement of Overriding Considerations, and a Mitigation Monitoring and Reporting Program, and adopted Resolution No. RTC 2015-04, approving the Mid-Coast Corridor Transit project.

BOD, May 9, 2014, Item No. 3, Mid-Coast Corridor Transit Project Update

Staff presented a report on the general update on the Mid-Coast project, including the ongoing environmental review process, planned application for federal funding, and progress of project design. This update also discussed the recent discovery of San Diego Fairy Shrimp within the project footprint and recent community concerns related to the Interstate 5 (I-5) crossing south of Nobel Drive. The BOD discussed and provided further direction to amend the Refined Build Alternative to return the I-5 crossing south of Nobel Drive to the location designated in the Draft Supplemental Environmental Impact Statement/Subsequent Environmental Impact Report (SEIS/SEIR) document.

BOD, May 9, 2014, Item No. 2, Approval of Award to Construction Manager/ General Contractor for Mid-Coast Corridor Transit Project and LOSSAN Rail Corridor Project

Staff presented a report on the CM/GM for the Mid-Coast project including the EMDT and San Diego River Bridge Track projects. The BOD approved the selection of a CM/GC and authorized the Executive Director to negotiate and execute Pre-Construction Services contracts with Mid-Coast Transit Constructors for the Mid-Coast Corridor Transit, the EMDT, and the SDRBDT project.

BOD, February 28, 2014, Item No. 8, Mid-Coast Corridor Transit Project Construction Manager/General Contractor Procurement

Staff presented a report on the CM/GC proposals and evaluations. The BOD approved advancing all four Mid-Coast Corridor Transit project CM/GC proposers into the interview phase of the CM/GC procurement process.

13

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, February 21, 2014, Item No. 4, Mid-Coast Corridor Transit Project Construction Manager/General Contractor Procurement

Staff presented a report and asked the TC to recommend that the BOD approve advancing all four Mid-Coast Corridor Transit project CM/GC proposers, into the interview phase of the CM/GC procurement process.

BOD, November 15, 2013, Item No. 12, Mid-Coast Corridor Transit Project: Refined Build Alternative

Staff presented a report on the proposed refinements to the Build Alternative and the Final SEIS/SEIR. The BOD approved the Refined Build Alternative as the final project evaluated in the Final SEIS/SEIR.

BOD, July 26, 2013, Item No. 10, Mid-Coast Corridor Transit Project: Waiver of Certain Sections of Board Policy No. 24 and Approval of Alternative Requirements for the Mid-Coast Procurement

Staff presented a report on procurement methods as governed by Board Policy No. 024 and requested waivers to sections 1.5.6.1.2, 1.5.6.1.3, and 1.5.6.1.4. The BOD approved the waiver of sections of Board Policy No. 024 as discussed and approved the revised financial requirements for the Mid-Coast Procurement recommended.

BOD, June 28, 2013, Item No. 12, Mid-Coast Corridor Transit Project: Proposed Criteria for CM/GC Procurement and Public Hearing: Designation of LOSSAN Projects as Substantially Complex

Staff presented a report on the proposed evaluation process and criteria while also requesting the addition of two additional LOSSAN projects to the Mid-Coast Corridor. The BOD approved the CM/GC Request for Proposal evaluation criteria and contract provisions; adopted Resolution No. 2013-34 authorizing the use of the CM/GC construction delivery method for the EMDT project and San Diego River Bridge project as part of the CM/GC procurement for the Mid-Coast Corridor Transit project; opened and closed the public hearing to receive public testimony regarding the complexity of the projects and the need for a retention amount in excess of 5 percent; and adopted Resolution No. 2013-35 designating the projects as substantially complex thereby allowing retention up to 10 percent.

TC, June 21, 2013, Item No. 6, Mid-Coast Corridor Transit Project – Public Hearing for the Draft Supplemental Environmental Impact Statement/Subsequent Environmental Impact Report

The public review and comment period for the Mid-Coast Corridor Transit project draft SEIS/SEIR extended from May 17 through July 16, 2013. The BOD opened and closed the public hearing on the Draft SEIS/SEIR. Comments received at the public hearing, as well as all comments received during the review and comment period, will be addressed in the Final SEIS/SEIR for this project. This item was presented for discussion only.

14

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, June 21, 2013, Item No. 5, Mid-Coast Corridor Transit Project: Proposed Criteria for Construction Manager/General Contractor Procurement

Staff presented a report on the proposed evaluation process and criteria while also requesting the addition of two additional LOSSAN projects to the Mid-Coast Corridor. The TC recommended that the BOD (1) approve the CM/GC Request for Proposal evaluation criteria and contract provisions with substantially the same criteria and requirements shown on Attachment 1; (2) adopt Resolution No. 2013-34 (Attachment 3), authorizing the use of the CM/GC construction delivery method for the EMDT project and San Diego River Bridge project as part of the CM/GC procurement for the Mid-Coast Corridor Transit project; (3) receive public testimony regarding the complexity of the EMDT project and San Diego River Bridge project and the need for a retention amount in excess of 5 percent; and (4) adopt Resolution No. 2013-35 (Attachment 4) designating the San Diego River Bridge and EMDT project as substantially complex thereby allowing retention up to 10 percent.

TC, June 7, 2013, Item No. 7, Mid-Coast Corridor Transit Project: Construction Services Procurement

Staff presented a report regarding the BOD approval of the CM/GC construction contracting method on April 26, 2013. The TC provided comments on proposed evaluation criteria and contract requirements prior to staff completing the final documents for BOD consideration.

BOD, April 26, 2013, Item No. 7, Mid-Coast Corridor Transit Project: Proposed Construction Contracting Method and Public Hearing: Designation of Projects as Substantially Complex

Staff presented a report on three primary construction contracting methods used in the transit industry for delivery of large projects. The BOD adopted Resolution No. 2013-16 authorizing the use of the CM/GC construction delivery method for the Mid-Coast Corridor Transit project and be designated as the body to approve the award of the CM/GC contract, received public testimony and adopted Resolution No. 2013-17 designating the Mid-Coast Corridor Transit project as substantially complex.

TC, March 15, 2013, Item No. 9, Mid-Coast Corridor Transit Project: Construction Manager/ General Contractor Delivery Method Authorization and Designation of Mid-Coast Corridor Transit project as Substantially Complex

Staff presented a report on the proposal for the use of the CM/GC method. The TC recommended that the BOD: (1) adopt Resolution No. 2013-16, approving the use of the CM/GC construction delivery method for the Mid Coast Corridor Transit project; and (2) adopt Resolution No. 2013-17, approving the designation of the Mid-Coast Corridor Transit project as substantially complex. The TC also requested the BOD to be the approving body of the design bid.

ITOC, March 13, 2013, Item No. 12, Mid-Coast Corridor Transit Project Update and Construction Services Procurement

Staff presented a report with an update on the Mid-Coast project and presented an analysis and recommendations for implementing construction services on the project.

15

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, February 15, 2013, Item No. 8, Mid-Coast Corridor Transit Project Update and Construction Services Procurement Strategy

Staff presented a report on the update of the Mid-Coast project and summarized analysis and recommendations for implementing construction.

TC, November 9, 2012, Item No. 9, Mid-Coast Corridor Transit Project Status Update – Draft Supplemental Environmental Impact Statement/Subsequent Environmental Impact Report (SEIS/SEIR) Release for Public Review

Staff presented a report on the overall status of the Mid-Coast Corridor Transit project. Staff presented the item and provided details concerning the development and completion of the draft SEIS/SEIR currently under review by the FTA.

ITOC, June 13, 2012, Item No. 10, Mid-Coast Corridor Transit Project Status Update

Staff presented the same update as provided to the TC in May 2012.

TC, May 18, 2012, Item No. 9, Mid-Coast Corridor Transit Project Update

Staff presented a report on the status of the Mid-Coast Corridor Transit project including an overview of the project, status of the current phase of project development, and description of upcoming project development activities. The report included an update on San Diego Federal Delegation support, FTA coordination, environmental review, Locally Preferred Alternative refinements, as well as updates to budget and schedule.

BOD, November 18, 2011, Item No. 15, 2011 TransNet Plan of Finance Update

Staff presented the same update as provided to both the ITOC and the TC in November 2011. The BOD approved the 2011 TransNet Plan of Finance Update and authorized the Executive Director to amend the FY 2012 SANDAG Budget to incorporate changes to the capital budget for the Mid-Coast Corridor Transit project.

ITOC, November 9, 2011, Item No. 11, Mid-Coast Corridor Transit Project Update

Staff presented the same update as provided to the TC in November 2011.

TC, November 4, 2011, Item No. 6, 2011 TransNet Plan of Finance Update

Staff presented a report and the TC recommended that the BOD approve the 2011 TransNet Plan of Finance Update and authorize the Executive Director to amend the FY 2012 SANDAG Budget to incorporate changes to the capital budget for the Mid-Coast Corridor Transit project.

16

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, October 21, 2011, Item No. 9, Mid-Coast Corridor Transit Project Status Update

Staff presented a report on the status of the Mid-Coast Corridor Transit project, including proposed adjustments to both the project cost, from $1,246 million included in the FY 2012 SANDAG Budget to $1,704 million (an increase of $458 million), and delivery schedule, which now shows the start of revenue operations in 2018. These proposed project cost and schedule adjustments would be considered as part of the 2011 Plan of Finance Update scheduled to be presented to the ITOC, TC, and BOD in November 2011. Staff also reviewed the decision by the FTA to approve the project into the Preliminary Engineering phase of project development under the New Starts program.

TC, July 15, 2011, Item No. 8, Mid-Coast Corridor Transit Project Status Update

Staff presented a report on the status of the Mid-Coast Corridor Transit project and reviewed the decision by the FTA to publish a Notice of Intent in the Federal Register and conduct scoping under the National Environmental Policy Act.

TC, January 7, 2011, Item No. 10, Mid-Coast Corridor Transit Project Status Update

Staff presented a report on the status of the Mid-Coast Corridor Transit project, including an overview of the project, description of the status of the current phase of project development, and the upcoming project development activities.

BOD, July 23, 2010, Item No. 11, Mid-Coast Corridor Transit Project – Final Comparative Evaluation of Alternatives Report

Staff presented the same report provided to the ITOC and TC at their July 2010 meetings. The BOD reconfirmed the previously adopted Locally Preferred Alternative (LPA), as refined to include direct service to UC San Diego and University Towne Centre, by selecting LRT Alternative 1 (combines 1, 4, and 5), as the LPA; approved LRT Alternative 1 and the No-Build Alternative for evaluation in the Mid-Coast Corridor Transit project draft SEIS/SEIR; and approved the final Public Involvement Plan. The action also included the evaluation of a station at the Veteran’s Administration Hospital during the development of the draft environmental document.

TC, July 16, 2010, Item No. 11, Mid-Coast Corridor Transit Project – Final Comparative Evaluation of Alternatives Report

Staff presented the same report as provided to the ITOC in July 2010. The TC recommended that the BOD reconfirm the previously adopted LPA, as refined to include direct service to UC San Diego and University Towne Centre, by selecting LRT Alternative 1 (combines 1, 4, and 5), as the LPA; and that the BOD approve LRT Alternative 1 and the No-Build Alternative for evaluation in the Mid-Coast Corridor Transit project draft SEIS/SEIR; and that the BOD approve the final Public Involvement Plan.

17

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

ITOC, July 14, 2010, Item No. 7, Mid-Coast Corridor Transit Project – Final Comparative Evaluation of Alternatives Report

Staff presented a report on marketing efforts and the public information plan for the Mid-Coast Corridor Transit project, including the final responses to the scoping comments and a recommendation on an LPA to carry forward for detailed analysis in the draft SEIS/SEIR.

TC, July 2, 2010, Item No. 7, Mid-Coast Corridor Transit Project – Update on Scoping Period and Summary of Scoping Comments

Staff presented a report on the scoping period for the Mid-Coast Corridor Transit project draft SEIS/SEIR.

ITOC, May 12, 2010, Item No. 10, Mid-Coast Corridor Transit Project – Draft Comparative Evaluation of Alternatives Report and Project Scoping

Staff presented the same report as provided to the TC and BOD in April 2010.

BOD, April 23, 2010, Item No. 10, Mid-Coast Corridor Transit Project – Draft Comparative Evaluation of Alternatives Report and Project Scoping

Staff presented the same report as provided to the TC in April 2010. The BOD approved LRT Alternatives 1 (combining 1, 4, and 5), 3, and 6 to be carried forward for consideration at scoping for the Mid-Coast Corridor Transit project draft SEIS/SEIR.

TC, April 16, 2010, Item No. 9, Mid-Coast Corridor Transit Project – Draft Comparative Evaluation of Alternatives Report and Project Scoping

Staff presented and the TC recommended that the BOD approve LRT Alternatives 1 (combines LRT Alternatives 1, 4, and 5), 3, and 6 to be carried forward for consideration at scoping for the Mid-Coast Corridor Transit project draft SEIS/SEIR.

BOD, March 26, 2010, Item No. 13, Mid-Coast Corridor Transit Project – Draft Comparative Evaluation of Alternatives Report and Project Scoping

Staff presented the same report provided to the TC in March 2010.

TC, March 19, 2010, Item No. 8, Mid-Coast Corridor Transit Project – Draft Comparative Evaluation of Alternatives Report and Project Scoping

Staff presented an overview of the Draft Comparative Evaluation of Alternatives Report and its findings for the Mid-Coast Corridor Transit project.

BOD, July 24, 2009, Item No. 6, Mid-Coast Corridor Transit Project Working Group

Staff presented the same report that was presented to the TC in July 2009. The BOD approved the selected candidates to serve on the Mid-Coast Corridor Transit Project Working Group.

18

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, July 17, 2009, Item No. 8, Mid-Coast Corridor Transit Project Working Group Recommendation

Staff presented the recommended slate of participants from the selection committee for the Mid-Coast Corridor Transit Project Working Group. The TC recommended that the BOD approve the selected candidates to serve on the Mid-Coast Corridor Transit Project Working Group.

BOD, May 22, 2009, Item No. 16B, Mid-Coast Corridor Transit Project Update: Public Involvement Plan and Working Group

Staff presented the same report as presented to the TC at its May 2009 meeting. The BOD accepted the draft Mid-Coast Corridor Transit Project Public Involvement Plan (PIP) for public review and comment, approved the establishment of the Mid-Coast Corridor Transit Project Working Group and its charter, and issued the call for membership applications.

BOD, May 22, 2009, Item No. 16A, Mid-Coast Corridor Transit Project Update: Federal Transit Administration New Starts Program Overview and Status Update

Staff presented the same report as presented to the TC at its May 2009 meeting.

TC, May 15, 2009, Item No. 13B, Mid-Coast Corridor Transit Project Update: Public Involvement Plan and Working Group

Staff presented the TC with a draft PIP to support public outreach activities for the Mid-Coast Corridor Transit project. The TC recommended that the BOD accept the draft Mid-Coast Corridor Transit project PIP for public review and comment, approve the establishment of the Mid-Coast Corridor Transit Project Working Group and its charter, and issue the call for membership applications.

TC, May 15, 2009, Item No. 13A, Mid-Coast Corridor Transit Project Update: Federal Transit Administration New Starts Program Overview and Status Update

Staff presented the TC with an overview of the FTA New Starts funding that SANDAG would be applying for to match local TransNet Major Corridors capital funding for the Mid-Coast Corridor Transit project.

TC, March 20, 2009, Item No. 16, Mid-Coast Corridor Transit Project Update

Staff presented an update on continuing work and progress made on the Mid-Coast Corridor Transit project.

BOD, January 23, 2009, Item No. 15, Mid-Coast Corridor Transit Project Update

Staff presented the same update as provided to the TC in January 2009.

TC, January 16, 2009, Item No. 13, Mid-Coast Corridor Transit Project Update

Staff presented an update on the Mid-Coast Corridor Transit project, focusing on activities scheduled to be completed within the following six months, such as: alternatives development, preparation of a PIP for public scoping for the draft environmental document, BOD approval of an LPA or other alternatives, and preparation of the FTA Preliminary Engineering Application.

19

Committee/Date/Item No./Title Major Corridor Project: Mid-Coast Corridor Transit Project

TC, October 17, 2008, Item No. 11, Mid-Coast Corridor Transit Project Update

Staff presented the TC with an update on the development phase of the Mid-Coast Corridor Transit project and provided an overview of major development activities under way, including preparation of an environmental document and preliminary engineering, development of alternatives for inclusion in the draft environmental document, project funding, and a preliminary schedule.

BOD, February 23, 2007, Item No. 6, FY 2008 Federal Transportation Appropriations Proposals

Staff presented the same report as provided to the TC at the January 2007 meeting. The BOD approved the proposed list of project funding requests for the FY 2008 federal transportation appropriations cycle, including a New Starts federal funding request in the amount of $4 million for the Mid-Coast Corridor Transit project.

TC, January 19, 2007, Item No. 15, FY 2008 Federal Transportation Appropriations Proposals

The TC recommended that the BOD approve the proposed list of project funding requests for the FY 2008 federal transportation appropriations cycle, including a New Starts federal funding request in the amount of $4 million for the Mid-Coast Corridor Transit project.

TC, April 15, 2005, Item No. 9, TransNet Early Action Program: Mid-Coast Light Rail Transit Project Approach

The TC approved combining the Mid-Coast Balboa and University City LRT segments for the purposes of preparing a single SEIS and pursuing a single Full Funding Grant Agreement for the full 11-mile extension from Old Town to University City.

ITOC, May 18, 2005, Item No. 4, TransNet Early Action Program

Staff summarized the status of the EAP projects, including the Mid-Coast Corridor Transit project from Old Town to University City, as approved by the BOD earlier in the year.

BOD, January 28, 2005, Item No. 13, Draft TransNet Early Action Program

Staff presented the same report provided to the TC at the January 2005 meeting. The BOD authorized staff to proceed with the implementation of the identified EAP projects, including the Mid-Coast Corridor Transit project from Old Town to University City.

TC, January 21, 2005, Item No. 9, TransNet Early Action Program

Staff updated the TC on a selected list of high priority capital projects, including the Mid-Coast LRT extension from Old Town to University City. The TC recommended that the BOD authorize staff to proceed with the implementation of the TransNet EAP projects, including those projects that remained uncompleted from the original 1987 TransNet measure, such as the Mid-Coast Corridor Transit project from Old Town to University City.

TransNet Independent Taxpayer Oversight Committee Item: 11 October 16, 2019

North Coast Corridor Program Status Update

Overview

The North Coast Corridor (NCC) program, or Build NCC, as described in Attachment 1, is a comprehensive set of transportation, environmental, and coastal access projects to reduce congestion, improve the quality of life for residents, create a stronger local and regional economy for the future, and enhance the coastal environment.

Projects are built using the Construction Manager/General Contractor (CM/GC) delivery method, which is a best value construction procurement method. The CM/GC contractor is a joint venture of Flatiron, Skanska, and Stacy Witbeck contractors. The project budget for construction currently is $869 million and includes federal, state, and TransNet funds.

Key Considerations

The first phase of construction of Build NCC will extend through the cities of Solana Beach, Encinitas, and Carlsbad. Construction began in late 2016 and the improvements are scheduled to open to the public in late 2021. The scope of Build NCC includes the extension of the Express Lanes from Manchester Avenue to SR 78, replacement of the San Elijo Lagoon highway and rail bridges, restoration of the San Elijo Lagoon, and bicycle and pedestrian improvements.

Build NCC continues to be on schedule and within budget. Major accomplishments in the last three months include:

• Completion of concrete pours for northern San Elijo Lagoon pedestrian bridge

• Completion of pedestrian and bike enhancements on the south side of Encinitas Boulevard and Santa Fe Drive

• Completion of concrete paving for phase one of the San Elijo highway bridge (new outside bridges)

• Significant drainage, electrical work, irrigation cross-overs, asphalt base paving, and concrete pavement in the median of Interstate 5 completed

Additional detailed information can be found in Attachment 2.

Action: Information

An update on the North Coast Corridor program will be presented.

Fiscal Impact:

The project budget for construction of the North Coast Corridor program is $869 million and includes federal, state, and TransNet funds.

Schedule/Scope Impact:

The first phase of construction of the North Coast Corridor program is on schedule and within budget, and is on schedule to open to the public by late 2021.

2

Next Steps

Next steps include completing phase one (new outside bridge) of the San Elijo Highway project, continued dredging of the San Elijo Lagoon west basin and construction of lagoon pedestrian bridges, and completing the design of the Express Lanes extension from Palomar Airport Road to SR 78. In addition, staff will continue to work with California Transportation Commission staff to advance funding for the Express Lanes extension from Palomar Airport Road to SR 78. Staff will return to the Transportation Committee in three months with another Build NCC update.

Jim Linthicum, Director of Mobility Management and Project Implementation

Key Staff Contact: Allan Kosup, (619) 688-3611, [email protected] Attachments: 1. Build NCC Project Fact Sheet

2. Discussion Memo: North Coast Corridor Program Update September 2019 3. Independent Taxpayer Oversight Commiittee North Coast Corridor Chronology

Brought to you by

About the ProjectBuild NCC is the first phase of construction of the Caltrans and SANDAG North Coast Corridor (NCC) Program in the cities of Solana Beach, Encinitas, and Carlsbad. Build NCC is part of a comprehensive set of transportation, environmental, and coastal access projects to improve the quality of life for residents, create a stronger local and regional economy for the future, and enhance the coastal environment.

Highway Improvements

Caltrans and SANDAG will extend an Express Lane on Interstate 5 (I-5) - one in each direction - from Lomas Santa Fe Drive in Solana Beach to State Route 78 (SR 78) in Oceanside. Additional highway improvements include replacing and lengthening the San Elijo Lagoon highway bridge to accommodate the Express Lanes and help improve lagoon tidal flow; building several sound walls on private property; constructing a new Park & Ride/Multi-Use Facility at the I-5/Manchester Avenue interchange; and adding auxiliary lanes. The Park & Ride/Multi-Use Facility will provide parking for carpools, bike racks, electric vehicle charging stations, and recreational access to the San Elijo Lagoon and the new North Coast Bike Trail.

Rail Improvements

Improving the coastal rail line is a central component of Build NCC. The San Elijo Lagoon Double Track Project is part of a larger plan to improve the coastal rail system by adding a second track, allowing trains traveling in opposite directions to pass without slowing down or stopping, increasing efficiency and reliability. Other project features include the replacement and lengthening of the rail bridge spans over the San Elijo Lagoon. Additionally, at-grade rail crossing improvements will be made at Chesterfield Drive in Encinitas.

Lagoon/Bike/Pedestrian

Build NCC includes the restoration of the San Elijo Lagoon. The restoration project, is being made possible by the TransNet Environmental Mitigation Program (EMP), coordinated with the San Elijo Lagoon Conservancy and resource agencies. Restoration will enhance the lagoon’s wetland and upland areas, improve tidal flushing, and includes beach sand replenishment.

Improving coastal access is a critical component of the NCC Program. Build NCC will include new east-west and north-south bicycle and pedestrian trails in and around the San Elijo Lagoon.

See inside map for details.

Project Schedule and Funding

Construction Start Date 2017

Completion Date2022

Funding SourcesFederal State SANDAG ( TransNet )

ContractorFlatiron-Skanska-Stacy and Witbeck

Total Project CostApproximately $1.1 billion (Highway $871 million; Rail $80 million; Environment $130 million)

The budgeted amounts are per the Draft FY19 budget provided to the SANDAG Board of Directors.

KeepSanDiegoMoving.com/BuildNCC | #BuildNCC

As of May 2019

Attachment 1

3

Integrating Transportation and Environmental Enhancements

The San Elijo Lagoon highway bridge will be replaced and lengthened to help improve tidal flow in the lagoon. The wider bridge will accommodate an additional Express Lane in each direction. In addition, a suspended bike and pedestrian bridge will be built underneath the San Elijo Lagoon highway bridge to further increase north-south and east-west connectivity, and create more travel choices. The North Coast Bike Trail will be constructed to expand the regional bike and pedestrian network.

San Elijo Lagoon highway bridge

Preserving Community Character and Improving Coastal Access

Build NCC includes local bike/pedestrian path improvements in Encinitas and Carlsbad. The interchanges at Encinitas Boulevard and Santa Fe Drive will be upgraded with new bike and pedestrian paths. The Build NCC project team is coordinating with the City of Encinitas to install local artwork into these improvements.

To help reduce freeway noise for nearby residents, Caltrans is proposing to construct several sound walls on private property. In areas with views, transparent sound walls will be offered to residents.

Santa Fe Drive in Encinitas

San Elijo Lagoon

KeepSanDiegoMoving.com/BuildNCC | #BuildNCC4

5

Attachment 2

6

Discussion Memo: North Coast Corridor Program Update September 2019

The first phase of construction of the North Coast Corridor (NCC) program, known as Build NCC, will extend through the cities of Solana Beach, Encinitas, and Carlsbad (Attachment 1). Construction began in late 2016 and is scheduled to be opened to the public by late 2021.

Scope of Work

Highway Improvements

Caltrans will extend Express Lanes for 14 miles on I-5 from Lomas Santa Fe Drive in Solana Beach to SR 78 in Oceanside. Additional highway improvements include replacing and lengthening the San Elijo highway bridge to accommodate the Express Lanes and help improve lagoon tidal flow; constructing sound walls on private property; a new Park & Ride facility at the I-5/Manchester Avenue interchange; and including auxiliary lanes. The Park & Ride will provide parking for carpools and vanpools, secure bike parking, make available electric vehicle charging stations, and offer recreational access to the San Elijo Lagoon and the new North Coast Bike Trail.

Rail Improvements

Improving the coastal rail line is a central component of Build NCC. The San Elijo Lagoon Double Track project is part of a larger plan to improve the coastal rail system by adding a second track. The addition of the second track will allow trains traveling in opposite directions to pass without slowing down or stopping, increasing the corridor’s efficiency and reliability. Other project features include the replacement and lengthening of the rail bridge that spans over the San Elijo Lagoon. Additionally, at-grade rail crossing improvements have been made at Chesterfield Drive in Encinitas. Finally, a pedestrian undercrossing is being built on the south side of the lagoon to provide improved lagoon and coastal access.

Lagoon Restoration

Build NCC includes the restoration of the San Elijo Lagoon. The restoration project is being coordinated with the San Elijo Lagoon Conservancy and resource agencies. Restoration will enhance the lagoon’s wetland and upland areas, improve tidal flushing, and facilitate beach sand replenishment. Improving coastal access is a critical component of the NCC program. Build NCC will include new east-west and north-south bicycle and pedestrian trails in and around the San Elijo Lagoon.

Active Transportation Improvements

Build NCC includes construction of 7 miles of the North Coast Bike Trail, a planned bike trail stretching approximately 27 miles between Gilman Drive in the City of San Diego and Harbor Drive in the City of Oceanside. Build NCC also includes segments of the Coastal Rail Trail (CRT), a planned continuous bike route approximately 44 miles long between the City of Oceanside and Santa Fe Depot in Downtown San Diego. The first 1.3-mile segment of the CRT in the City of Encinitas from Chesterfield Drive to Santa Fe Drive was completed under Build NCC.

Overall Capital Project Budget and Schedule

The capital and support budgets for the projects currently in construction are $738 million and $131 million, for a total of $869 million. Actual capital expenditure through August 2019 is $ 298 million, or 40% of the capital budget.

7

Status of Work

Highway Improvements

The San Elijo Highway project, which includes the Santa Fe Drive and Encinitas Boulevard bicycle and pedestrian improvements, is 61% complete, with an anticipated open to the public in late 2021. Utilities are 90% complete. Stage one of the new outside bridge over the San Elijo Lagoon will be completed with a traffic switch in early 2020. The community improvements at Santa Fe Drive and Encinitas Boulevard are scheduled to be completed early 2020.

The eight-mile extension of the Express Lanes project from Manchester Avenue to Palomar Airport Road, which includes sound walls on private property, culvert rehab, Intelligent Transportation Systems, and bike trails, is 22% complete and is expected to be completed by the end of 2022. Drainage, electrical work, irrigation cross-overs, asphalt base paving, and concrete pavement work are ongoing at various stages in the median. The median work is expected to be completed and outside work to start in early 2020.

The design of the Express Lanes from Palomar Airport Road to SR 78 is 90% complete with construction beginning in late summer 2020, pending early allocation of state construction funds currently programmed in FY 2023.

Rail Improvements

The San Elijo Lagoon Double Track project, on the Los Angeles – San Diego – San Luis Obispo Rail Corridor, is 99% complete. Crews have been working on final punch list items this quarter.

At Chesterfield Drive the improvements to the grade crossing are complete. The City of Encinitas quiet zone is in place.

A joint ribbon cutting took place on May 9, 2019, to celebrate completion of the San Elijo Lagoon Double Track project and the CRT between Chesterfield Drive and the Swami’s undercrossing.

Lagoon Restoration

Dredging in the east and central basin is completed and the contractor has completely demobilized the 10” and the 16” dredge from the project. The remaining channel excavations in the west basin will be completed by mechanical excavation due to hard digging in the southern channel reaches. The north pedestrian bridge concrete pours are complete and stressing will begin in early September. The south pedestrian bridge stem and soffit concrete pour is complete and the deck concrete pour is scheduled for early September. Planting and irrigation is scheduled to begin in early November is the east and central basins. San Elijo Lagoon Restoration project is running under budget and is 157 working days ahead of schedule.

Coastal Rail Trail Construction

The first segment of the CRT in Encinitas is 100% completed. A joint ribbon cutting took place on May 9, 2019, to celebrate completion of the San Elijo Lagoon Double Track project and the CRT between Chesterfield Drive and the Swami’s undercrossing.

Independent Taxpayer Oversight Committee (ITOC) Attachment 3 Chronology of Key Actions /Summary of Significant Discussion

8

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

ITOC May 17, 2006 Item # 4 TransNet Major Corridor Update: I-5

Caltrans staff presented a presentation reviewing I-5 NCC project.

ITOC September 16, 2008 Item # 4 Agreement with Caltrans for Preliminary Engineering for the I-5 / SR 56 Interchange Improvement Project

Staff presented an overview of the proposed agreement that would allow Caltrans to use SANDAG on-call engineering consultants for preliminary engineering for the I-5/SR 56 Interchange Improvement project. The ITOC recommended approval to the Board of Directors.

Transportation Committee September 19, 2008 Item # 10 Agreement with Caltrans for Preliminary Engineering for the I-5 / SR 56 Interchange Improvement Project

Staff presented the same presentation from the September 2008 ITOC meeting. The Transportation Committee recommended that the Board of Directors authorize the Executive Director to sign an agreement with Caltrans for preliminary engineering for the I-5/SR 56 Interchange Improvement project.

Board of Directors September 26, 2008 Item # 14 Agreement with Caltrans for Preliminary Engineering for the I-5 / SR 56 Interchange Improvement Project

Staff presented the same presentation from the September 2008 ITOC and Transportation Committee meetings. The Board approved authorizing the Executive Director to sign an agreement with Caltrans for preliminary engineering for the I-5/SR 56 Interchange Improvement project.

ITOC July 8, 2009 Item # 9 Proposed Addition of Design Projects to the TransNet Capital Improvement Program

Staff presented an overview of a proposal to continue design work for a series of projects. With the successful competition for various federal and state transportation funds, including the federal American Recovery and Reinvestment Act and the Proposition 1B state bonds, much of the design work that was made ready for the competitions had been depleted. The ITOC recommended that the Board approve programming TransNet funds for design phase improvements on various projects, including the I-5 NCC.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

9

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Transportation Committee July 17, 2009 Item # 7 Proposed Addition of Design projects to the TransNet Capital Improvement Program

Staff presented the same report that was presented at the July 2009 ITOC meeting. The Transportation Committee recommended that the Board approve programming TransNet funds for design phase improvements on various projects, including the I-5 NCC.

Board of Directors July 24, 2009 Item # 16 Proposed Addition of Design projects to the TransNet Capital Improvement Program

Staff presented the same report that was presented at the July 2009 ITOC and Transportation Committee meetings. The Board approved programming TransNet funds for design phase improvements on various projects, including the I-5 NCC.

Transportation Committee January 15, 2010 Item # 7 2010 State Transportation Improvement Program: Revised Proposal

Staff presented an overview of the proposed programming of State Transportation Improvement Program (STIP) funds for projects in the I-5 NCC. The Transportation Committee recommended that the Board approve the proposed programming, including for projects in the I-5 corridor.

Board of Directors January 22, 2010 Item # 18 2010 State Transportation Improvement Program: Revised Proposal

Staff presented the same report presented at the January 2010 Transportation Committee meeting. The Board approved the proposed programming, including for projects in the I-5 corridor.

ITOC May 12, 2010 Item # 9 I-5 NCC Update

Caltrans staff presented an update on the I-5 NCC project, including the project development efforts under way and work to date on the project work program and upcoming release of the Draft Environmental Document.

Transportation Committee June 18, 2010 Item # 8 Interstate 5 NCC Project Update

Caltrans staff presented the same report as presented to the ITOC in May 2010.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

10

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

ITOC April 13, 2011 Item # 6 I-5/I-8 Interchange Improvements – SHOPP Funding

Caltrans staff presented proposed congestion relief and operational improvements, and the proposed funding, for the I-5/I-8 interchange. The project would be incorporated into the Capital Improvement Program of the proposed FY 2012 Program Budget and would be amended into the 2010 Regional Transportation Improvement Program, pending Board approval of the FY 2012 Program Budget and programming by Caltrans of the SHOPP funds.

Board of Directors May 27, 2011 Item # 11 Proposed FY 2012 Program Budget (Including the Overall Work Program)

The Board approved the proposed FY 2012 Program Budget (including the Overall Work Program), which included funding for the I-5/I-8 interchange project.

Joint Meeting of the Transportation and Regional Planning Committees July 15, 2011 Item # B Interstate 5 NCC Project

Caltrans staff presented an update on the I-5 NCC, including the selection of the preferred alternative by Caltrans and the Federal Highway Administration and efforts under way for the upcoming release of the Final Environmental Document.

Joint Meeting of the Transportation and Regional Planning Committees July 15, 2011 Item # C Proposed Redistribution of Funds from I-5 NCC Project in the 2050 Regional Transportation Plan

Staff presented an update on the preferred alternative selected by Caltrans and the Federal Highway Administration that included lower construction costs than the alternative in the Draft 2050 Regional Transportation Plan (2050 RTP). Staff presented proposed phasing modifications and redistribution of funding from the I-5 NCC project to certain projects in the Draft 2050 RTP. The Regional Planning and Transportation Committees recommended that staff further analyze redistribution options for these funds and provide an analysis and information for consideration by the Board of Directors.

Board of Directors July 22, 2011 Item # 11 Proposed Redistribution of Funds from I-5 NCC Project in the 2050 Regional Transportation Plan

Staff presented the same report as presented to the Regional Planning and Transportation Committees in July 2011 and addressed comments from that meeting. The Board approved the proposed phasing modifications and redistribution of funding.

ITOC Staff presented a report on the Proposition 1B Corridor Mobility Improvement

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

11

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

September 14, 2011 Item # 7 Proposition 1B Corridor Mobility Improvement Account Program Status Funding Opportunity and Budget Amendment

Account program status and described a funding opportunity for the I-5/Genesee Avenue Interchange and Widening project.

Transportation Committee October 7, 2011 Item # 4 Proposition 1B Corridor Mobility Improvement Account Program Status Funding Opportunity and Budget Amendment

Staff presented the same report as was presented at the September 2011 ITOC meeting. The Transportation Committee recommended that the Board of Directors approve funding for the I-5/Genesee Interchange and Widening project.

Board of Directors October 14, 2011 Item # 3 Proposition 1B Corridor Mobility Improvement Account Program Status Funding Opportunity and Budget Amendment

Staff presented the same report as was presented at the September 2011 ITOC and Transportation Committee meetings. The Board approved funding for the I-5/Genesee Interchange and Widening project.

Transportation Committee October 21, 2011 Item # 5 2012 State Transportation Improvement Program

The Transportation Committee recommended that the Board of Directors approve the programming of the 2012 STIP, including funding for the I-5 NCC.

Board of Directors November 18, 2011 Item # 14 2012 State Transportation Improvement Program

Staff presented the same report as was presented to the Transportation Committee at its October 2011 meeting. The Board approved the programming of the 2012 STIP, including funding for the I-5 NCC.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

12

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Joint Meeting of the Transportation and Regional Planning Committees March 1, 2013 Item # 4 NCC: Draft Public Works Plan/Transportation and Resource Enhancement Program; and Transportation Demand Management Plan

Staff presented an overview of the Public Works Plan/Transportation and Resource Enhancement Program (PWP/TREP), regulatory process, and opportunities for public participation. Staff also presented the first phase of research conducted on the NCC Transportation Demand Management (TDM).

Transportation Committee October 18, 2013 Item # 10 2014 State Transportation Improvement Program

The Transportation Committee recommended that the Board of Directors approve the programming of the 2014 STIP, including funding for the I-5 NCC.

Transportation Committee November 8, 2013 Item #5 2012 regional transportation improvement program: Amendment no. 11- administrative modification and Proposed FY 2014 program budget amendment: Los Peñasquitos Lagoon Bridge replacement project

On September 28, 2012, the Board of Directors adopted the 2012 Regional Transportation Improvement Program (RTIP). The 2012 RTIP is the multiyear program of proposed major transportation projects in the San Diego region covering the period FY 2013 to FY 2017. Amendment No. 11 is a special amendment to program federal Transportation Investment Generating Economic Recovery (TIGER) funds for the Los Peñasquitos Lagoon Bridge Replacement project. The Transportation Committee is asked to recommend that the Board of Directors: (1) approve Amendment No. 11 - Administrative Modification to the 2012 RTIP; and (2) approve the proposed amendment to the FY 2014 Program Budget for the Los Peñasquitos Lagoon Bridge Replacement project (CIP 1145000).

Board of Directors November 15, 2013 Item # 13 2014 State Transportation Improvement Program

Staff presented the same report as was presented to the Transportation Committee at its October 2013 meeting. The Board approved the programming of the 2014 STIP, including funding for the I-5 NCC.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

13

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors January 24, 2014 Item #10 Hearing of necessity: acquisition of parcels located in the city Of San Diego for the Sorrento Valley Double Track project

The Board of Directors: (1) adopted Resolution No. 2014-08 by a two-thirds vote, pertaining to acquisition of a fee interest in a portion of the property located at 11772 Sorrento Valley Road in the City of San Diego and owned by AGP Sorrento R&D Addition, LP; (2) adopted Resolution No. 2014-09 by a two-thirds vote, pertaining to acquisition of a temporary construction easement interest and permanent easement interest in portions of the property located at 11230 Sorrento Valley Road in the City of San Diego and owned by Soval, LLC; and (3) authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the partial interests in the subject parcels.

Transportation Committee February 21, 2014 Item #6 Proposed FY 2014 program budget amendment: Buena Vista Lagoon enhancement project

The Transportation Committee (1) authorized the Executive Director to enter into agreements with the National Fish and Wildlife Foundation and the Buena Vista Lagoon Foundation to accept $253,157 to pay for technical studies related to water quality and to add an elevated walkway into the environmental analysis of the project; and (2) approved an amendment to the FY 2014 Program Budget to increase the Buena Vista Lagoon Enhancement project budget (CIP 1200260) by $253,157.

Board of Directors May 9, 2014 Item #2 Approval of award to construction manager/general Contractor for mid-coast corridor transit project and LOSSAN Rail Corridor projects

The Board of Directors approved the selection of a Construction Manager/General Contractor and authorized the Executive Director to negotiate and execute Pre-Construction Services contracts with Mid-Coast Transit Constructors for the Mid-Coast Corridor Transit project, the Elvira to Morena Double Track project, and the San Diego River Bridge Double Track project.

Independent Taxpayer Oversight Committee October 08, 2014 Item #09 NCC Project Update

Mr. Kosup, Caltrans Corridor Director, presented an update on the California Coastal Commission’s recent coastal permit approval for the NCC. Mr. Kosup presented an update on the completion of the Public Works Plan and efforts under way to procure the services of a Construction Manager/General Contractor for construction of the phase 1 improvements. This item was presented for information.

Transportation Committee October 17, 2014 Item #11 NCC Project Update

Alan Kosup, Caltrans Corridor Director, presented an update on the NCC, including completion of the Public Works Plan and efforts underway to procure the services of a Construction Manager/ General Contractor for construction of the first phase of improvements.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

14

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Independent Taxpayer Oversight Committee March 11, 2015 Item #07 Proposed FY 2015 program budget amendment: Interstate 5/Gilman Drive Bridge

The Interstate 5 (I-5)/Gilman Drive Bridge project is a new bridge linking the east and west campus of UC San Diego to be constructed over I-5 at Gilman Drive. A proposed budget amendment to provide $15 million for the project was presented. This is one of several projects involving UC San Diego, and an update on negotiations toward a comprehensive agreement with the university also was presented. The ITOC was asked to review the proposed budget amendment for consistency with the TransNet Extension Ordinance. Allan Kosup, Caltrans I-5 Corridor Director, presented the item. This item was presented for discussion

Transportation Committee March 20, 2015 Item #04 Proposed FY 2015 program budget amendment: Interstate 5/Gilman Drive Bridge

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2015 Program Budget to fund the I-5/Gilman Drive Bridge project.

Board of Directors March 27, 2015 Item # 11 Proposed FY 2015 program budget amendment: Interstate 5/ Gilman Drive bridge project

The Board of Directors approved an amendment to the FY 2015 Program Budget to fund the Interstate 5/Gilman Drive Bridge

Transportation Committee May 15, 2015 Item #06 Proposed construction manager/general contractor Delivery method: Interstate 5/Voigt bridge and Coastal Rail Trail San Diego: Rose Creek projects

The Transportation Committee recommended that the Board of Directors: (1) approve Resolution Nos. 2015-29 and 2015-30, authorizing the use of the CMGC construction delivery method for the Interstate 5/ Voigt Drive Bridge and Street Realignment and Coastal Rail Trail San Diego: Rose Creek projects; and (2) authorize the Executive Director to negotiate and award the Preconstruction Services Contract for these projects to Mid Coast Transit Constructors in coordination with the Mid-Coast Corridor Transit project.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

15

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors May 22, 2015 Item # 12 Proposed construction manager/general contractor delivery Method: I-5/Voigt direct access ramp and Coastal Rail Trail San Diego: Rose Creek Projects

The Board of Directors approved Resolution Nos. 2015-29 and 2015-30, authorizing the use of the Construction Manager/General Contractor construction delivery method for the I-5/Voigt Direct Access Ramp and Coastal Rail Trail San Diego: Rose Creek projects, and authorized the Executive Director to negotiate and award the Preconstruction Services Contract for these projects to Mid-Coast Transit Constructors in coordination with the Mid-Coast program of projects.

Transportation Committee June 19, 2015 Item #04 Construction manager/general contractor construction Services contract: Mid-Coast Corridor Transit and Elvira To Morena Double Track Projects

The Transportation Committee recommended that the Board of Directors authorize the Executive Director to execute a Construction Manager/ General Contractor Construction Services Agreement, with Mid-Coast Transit Constructors including Supplement 1 for the construction of utility and rail relocation work for the Mid-Coast Corridor Transit project and the Elvira to Morena Double Track project.

Board of Directors June 26, 2015 Item # 11 Construction manager/general contractor construction Services agreement: Mid-coast corridor transit and Elvira to Morena double track projects

The Board of Directors authorized the Executive Director to execute a Construction Manager/General Contractor Construction Services Agreement with Mid-Coast Transit Constructors, including Supplement 1 for the construction of utility and rail relocation work for the Mid-Coast Corridor Transit project and the Elvira to Morena Double Track project.

Transportation Committee July 17, 2015 Item #06 Proposed FY 2016 program budget amendment: Chesterfield Drive crossing improvements

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2016 Program Budget to: (1) create a new Capital Improvement Program (CIP) project 1239817; (2) accept $2.2 million in railroad crossing grant funds from the Federal Railroad Administration; and (3) transfer project scope and matching funds from the San Elijo Lagoon Double Track (CIP 1239806) and Coastal Rail Trail Encinitas (CIP 1223017) projects

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

16

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors July 24, 2015 Item # 13 Proposed FY 2016 program budget amendment: chesterfield Drive crossing improvements

The Board of Directors approved an amendment to the FY 2016 Program Budget to create a new Capital Improvement Program (CIP) project No. 1239817, accept $2.2 million in railroad crossing grant funds from the Federal Railroad Administration, and transfer project scope and matching funds from the San Elijo Lagoon Double Track (CIP No. 1239806) and Coastal Rail Trail Encinitas (CIP No. 1223017) projects.

Transportation Committee December 11, 2015 Item #08 Proposed FY 2016 program budget amendment: LOSSAN Corridor grade crossing replacement

The Transportation Committee approved an amendment to the FY 2016 Program Budget to: (1) create a new CIP project No. 1146000: LOSSAN Corridor Grade Crossing Replacements; and (2) accept the $499,000 from NCTD for this work.

Transportation Committee January 15, 2016 Item #05 Proposed construction manager/general contractor delivery method: Gilman Drive Bridge

The Transportation Committee recommended that the Board of Directors: (1) adopt Resolution No. 2016-10, authorizing the use of the CM/GC construction delivery method for the Interstate 5/Gilman Drive Bridge project; and (2) authorize the Executive Director to negotiate and award a Preconstruction Service Contract for this project to Mid-Coast Transit Constructors.

Board of Directors January 22, 2016 Item # 11 Proposed construction manager/general contractor delivery Method: Interstate 5/Gilman Drive Bridge

The Board of Directors adopted Resolution No. 2016-10, authorizing the use of the Construction Manager/General Contractor construction delivery method for the Interstate 5/Gilman Drive Bridge project, and authorized the Executive Director to negotiate and award a reconstruction Service Contract for this project to Mid-Coast Transit Constructors.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

17

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors January 22, 2016 Item # 12 Hearing of necessity: acquisition of property interests located in The city of San Diego for the Mid-Coast Corridor transit project, San Diego River Double-track project, and Elvira to Morena Double-track project

The Board of Directors voted to adopt Resolution of Necessity No. 2016-11 by a two-thirds vote pertaining to acquisition of the subject property interests for the projects, and authorized staff to proceed with all condemnation filings and proceedings necessary to acquire the interests in the subject properties.

Board of Directors February 26, 2016 Item # 22 Hearing of necessity: acquisition of property interests located In the City of San Diego for the Mid-Coast Corridor Transit Project and the Elvira to Morena double-track project

The Board of Directors voted to delay action on Parcel C for 60-days, and to direct staff to pursue the parking structure option and provide a briefing on legal issues on a supplemental Environmental Impact Report (EIR) and the exact timeline required for a supplemental EIR.

Transportation Committee March 18, 2016 Item #05 Mid-coast corridor transit project and the Elvira to Morena Double-track project: construction manager/ general contractor construction contract Amendments

the Transportation Committee recommended that the Board of Directors authorize the Executive Director to amend the Construction Manager/General Contractor Construction Services Agreement, Supplement 1, with Mid-Coast Transit Constructors for the construction of storm drain utility relocations and bridge work for the Mid-Coast Corridor Transit project and the Elvira to Morena Double-Track project in an amount not to exceed $9,240,540.

Transportation Committee March 18, 2016 Item #06 San Diego River Bridge double-track project: Construction manager/general contractor construction Services agreement

The Transportation Committee recommended that the Board of Directors authorize the Executive Director to: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 2 of the Construction Manager/General Contractor Construction Services Agreement (Supplement 2) for the San Diego River Bridge Double-Track (SDRBDT) project in the amount of $64.36 million; (2) execute Supplement 2 for the SDRBT project; and (3) issue a limited Notice to Proceed for up to $20 million for early procurement and work items within the existing SDRBDT project budget

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

18

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors March 25, 2016 Item # 16 Mid-coast corridor transit project and Elvira to Morena Double-track project: Construction Manager/General Contractor Construction contract amendments

The Board of Directors authorized the Executive Director to amend the Construction Manager/General Contractor Construction Services Agreement, Supplement 1, with Mid-Coast Transit Constructors for the construction of storm drain utility relocations and bridge work for the Mid-Coast Corridor Transit project and Elvira to Morena Double-Track project in an amount not to exceed $9,240,540.

Board of Directors March 25, 2016 Item # 17 San Diego River Bridge Double-Track project: supplement 2 to Construction manager/general contractor construction Services agreement

The Board of Directors authorized the Executive Director to approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 2 to the Construction Manager/General Contractor Construction Services Agreement (Supplement 2) for the SDRBDT project in the amount of $64.36 million, execute Supplement 2 for the SDRBDT project, and issue a limited Notice to Proceed for up to $20 million for early procurement and work items within the existing SDRBDT project budget.

Transportation Committee May 20, 2016 Item #6 Coastal Rail Trail-Chesterfield to G Street project

The Transportation Committee directed staff to put on hold further design and environmental work for the project, pending an agreement with the City of Encinitas for development of a new alignment along the western side of Coast Highway 101, which will be reported back to the Transportation Committee within 30 days.

Board of Directors May 27, 2016 Item # 7 Rose Creek Bikeway Project: Final Mitigated Negative Declaration

The Board of Directors adopted the Final Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program for the project.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

19

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Transportation Committee June 17, 2016 Item #8 Gilman Drive Bridge project: cooperation agreement with University of California, San Diego and Caltrans; and Supplement 3 to the construction Manager/ general Contractor construction services agreement

The Transportation Committee recommended that the Board of Directors: A. (1) authorize the Executive Director to execute a Construction Cooperation Agreement with University of California, San Diego (UC San Diego) and Caltrans to fully fund the Interstate 5/Gilman Drive Bridge Project (Project); and (2) approve an amendment to the FY 2017 Program Budget to accept $4.407 million from UC San Diego to fully fund the Project (Capital Improvement Program No. 1200508); and B. (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 3 to the Construction Manager/General Contractor Construction Services Agreement for the Gilman Drive Bridge project in the amount of $15.3 million; and (2) authorize the Executive Director to execute Supplement 3.

Transportation Committee June 17, 2016 Item #9 Update on the development of an agreement with the city Of Encinitas regarding coastal rail trail implementation

As a follow up from the May 20, 2016, Transportation Committee Meeting. This item was presented for information.

Board of Directors June 24, 2016 Item # 12 Gilman Drive Bridge project: construction cooperation Agreement with university of California, San Diego and Caltrans; and supplement 3 to the Construction Manager/General Contractor Construction Services Agreement

The Transportation Committee recommended that the Board of Directors: A. (1) authorize the Executive Director to execute a Construction Cooperation Agreement with University of California, San Diego (UC San Diego) and Caltrans to fully fund the Interstate 5/Gilman Drive Bridge Project (Project); and (2) approve an amendment to the FY 2017 Program Budget to accept $4.407 million from UC San Diego to fully fund the Project (Capital Improvement Program No. 1200508). B. (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 3 to the Construction Manager/General Contractor Construction Services Agreement for the Project in the amount of $15.3 million; and (2) authorize the Executive Director to execute Supplement 3.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

20

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Transportation Committee July 15, 2016 Item #12 Update on the development of an agreement with the City of Encinitas regarding coastal rail trail Implementation

Staff presented an update on the Memorandum of Understanding(MOU) between the City of Encinitas and SANDAG to facilitate a mutually agreeable implementation of the Chesterfield to G Street segment of the Coastal Rail Trail. This item was presented for information.

Board of Directors September 23, 2016 Item # 15 Proposed FY 2017 program budget amendment: San Diego River Bridge Double Track Project

The Board of Directors approved an amendment to the FY 2017 Program Budget to add $11.466 million in TransNet funding to fully fund the San Diego River Bridge project (Capital Improvement Project No. 1239815).

Transportation Committee October 7, 2016 Item #3 2016 State Cap-And-Trade Transit and Intercity Rail Capital Program: Request For Letter of No Prejudice for The Elvira To Morena Double Track Project

The Transportation Committee approved the submittal of a Letter of No Prejudice to the California Transportation Commission for state cap-and-trade Transit and Intercity Rail Capital Program funds in the amount of $61.983 million for the implementation of the Elvira to Morena Double Track project (Capital Improvement Program Project No. 1239811).

ITOC October 12, 2016 Item #5A FY 2017 Budget Amendment: San Diego River Bridge Project

A similar presentation as the one presented to the Board on September 23, 2016, meeting, was presented to the ITOC.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

21

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

ITOC October 12, 2016 Item #05B 2016 State Cap-And-Trade Transit and Intercity Rail Capital Program: Request For Letter of No Prejudice for The Elvira To Morena Double Track Project

A similar presentation as the one presented to the Transportation Committee on October 7, 2016, was presented to the ITOC.

Transportation Committee November 4, 2016 Item #7 Proposed FY 2017 budget amendment: Interstate 5/Voigt Drive improvements

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2017 Program Budget to add $5.75 million in State Highway Operation and Protection Program funding to the Interstate 5 (I-5)/Voigt Drive Improvement project for the construction of a half-mile auxiliary lane on southbound I-5 between Genesee Avenue and La Jolla Village Drive.

Board of Directors November 18, 2016 Item # 12 Proposed FY 2017 program budget amendment: Interstate 5/Voigt Drive improvements

The Board of Directors approved an amendment to the FY 2017 Program Budget to add $5.75 million in State Highway Operation and Protection Program funding to the I-5/ Voigt Drive Improvement project for the construction of a half-mile auxiliary lane on southbound I-5 between Genesee Avenue and La Jolla Village Drive.

Transportation Committee December 9, 2016 Item #4 Proposed FY 2017 program budget amendment: Elvira to Morena double track project and construction manager/General contractor construction services agreement Supplement 5

The Transportation Committee recommended that the Board of Directors: (1) approve an amendment to the FY 2017 Program Budget adding $61.98 million in Transit and Intercity Rail Capital Program funding, $18.15 million in TransNet Program funding, and $3.96 million in funds from the City of San Diego to the Elvira to Morena Double Track (EMDT) project (Capital Improvement Program Project No. 1239811), increasing the project budget to $192.5 million; (2) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 5 of the Construction Manager/General Contractor Construction Services Agreement for the EMDT project in the amount of $93.6 million; and (3) authorize the Executive Director to execute Supplement 5.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

22

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors December 16, 2016 Item # 12 Proposed FY 2017 program budget amendment: Elvira to Morena Double Track Project and Construction Manager/general contractor construction services agreement supplement 5

The Board of Directors approved an amendment to the FY 2017 Program Budget adding $61.98 million in Transit and Intercity Rail Capital Program funding, $18.15 million in TransNet Program funding, and $3.96 million in funds from the City of San Diego to the EMDT project (Capital Improvement Program Project No. 1239811), increasing the project budget to $192.5 million; approved the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 5 of the Construction Manager/General Contractor Construction Services Agreement for the EMDT project in the amount of $93.6 million; and authorized the Executive Director to execute Supplement.

ITOC January 11, 2017 Item #05 FY 2017 Program Budget Amendment for Elvira To Morena Double Track Project And Construction Manager/General Contractor Construction Services Agreement Supplement 5

The SANDAG Board of Directors approved the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 5 of the Construction Manager/General Contractor (CM/GC) Construction Services Agreement for the EMDT project. Consent Item Nos. 3 through 5 were presented for information.

Transportation Committee January 20, 2017 Item #4 Encinitas Coastal Rail Trail segment 39c: California Environmental Quality act exemption

The Transportation Committee approved the California Environmental Quality Act exemption for Encinitas Coastal Rail Trail Segment 39C.

Board of Directors May 26, 2017 Item # 13 Proposed program budget amendments: I-5/ Gilman Drive Bridge project

The Board of Directors: (1) adopted Regional Transportation Commission (RTC) Resolution No. RTC-2017-05, adopting the Final FY 2018 Program Budget; and (2) authorized the Executive Director to execute an amendment to the adopted FY 2018 Program Budget, incorporating a 7 percent increase in assessment fees for Criminal Justice Research.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

23

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Transportation Committee June 2, 2017 Item #3 Proposed FY 2018 program budget amendment: Coastal Rail Trail: Chesterfield to Santa Fe Drive

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2018 Program Budget, adding an amount not exceed $5 million to the project (CIP No. 1223017) in order to complete the construction of the east side alignment.

Board of Directors June 9, 2017 Item #2 Proposed FY 2018 program budget amendment: Coastal Rail Trail: Chesterfield to Santa Fe Drive

The Board of Directors approved an amendment to the FY 2018 Program Budget, adding an amount not to exceed $5 million to the Coastal Rail Trail: Chesterfield to Santa Fe Drive project (Capital Improvement Program Project No. 1223017) to complete construction of the east side alignment.

ITOC June 14, 2017 Item #8 Construction Manager/General Contractor Project Delivery Method: Lessons Learned

Allan Kosup, Caltrans; and John Haggerty, Division Director of Rail, presented Construction Manager/General Contractor (CM/GC) best practices and lessons learned for implementation of the CM/GC project delivery method.

Transportation Committee June 16, 2017 Item #6 Rose Creek Bikeway project: construction manager/general contractor construction services Agreement supplement 7

the Transportation Committee recommended that the Board of Directors: (1) approve the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 7 of the Construction Manager/General Contractor Construction Services Agreement (Supplement 7) for the Rose Creek Bikeway Project (Project) in the amount of $17,001,856; and (2) authorize the Executive Director to execute Supplement 7 for construction of the Project.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

24

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors October 27, 2017 Item #7 Buena Vista Lagoon enhancement plan: availability of Final Environmental Impact Report

The Board of Directors approved Consent Item Nos. 4, 6 through 9, and 12.

ITOC January 10, 2018 Item #07 Proposed FY 2018 Program Budget Amendments: Interstate 5/Voigt Drive Improvements and Interstate 5/Genesee Avenue Auxiliary Lane projects

The ITOC reviewed a proposed FY 2018 Program Budget amendment to separate the Interstate 5 (I-5)/Genesee Avenue Auxiliary Lane component of the I-5/Voigt Drive Improvements project (Capital Improvement Program [CIP] Project No. 1200507) into its own CIP (Project No. 1200512) and add funding to fully fund the design phase of both projects. Allan Kosup, Caltrans Corridor Director, presented the item. This item was presented for discussion.

Transportation Committee January 19, 2018 Item #6 Proposed FY 2018 program budget amendments: Interstate 5/Voigt Drive improvements and Interstate 5/Genesee avenue auxiliary lane projects

The Transportation Committee recommended that the Board of Directors approve amendments to the FY 2018 Program Budget to: (1) fully fund design of the Interstate 5 (I-5)/Voigt Drive Improvements project (Capital Improvement Program [CIP] Project No. 1200507) by adding $500,000 of regional funds and $480,000 of UC San Diego funds; and (2) transfer the I-5/Genesee Avenue Auxiliary Lane project scope and associated budget from the I-5/ Voigt Drive Improvements project to a new CIP project (No. 1200512) and accept $299,000 in State Highway Operations and Protection Program funding to fully fund the design phase

Board of Directors January 26, 2018 Item #14 FY 2018 program budget amendments: Interstate 5/Voigt drive improvements and Interstate 5/Genesee avenue auxiliary lane projects

The Board of Directors approved amendments to the FY 2018 Program Budget to fully fund design of the I-5/Voigt Drive Improvements project by adding $500,000 of regional funds and $480,000 of UC San Diego funds, and transfer the I-5/Genesee Avenue Auxiliary Lane project scope and associated budget from the I-5/Voigt Drive Improvements project to a new CIP project (No. 1200512) and accept $299,000 in State Highway Operations and Protection Program funding to fully fund the design phase.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

25

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Transportation Committee February 16, 2018 Item #7 Proposed FY 2018 program budget amendment: Elvira to Morena Double Track project

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2018 Program Budget, adding $3.404 million in funds from the City of San Diego to the Elvira to Morena Double Track project (Capital Improvement Program Project No. 1239811), to fully fund two wet utility agreements.

Board of Directors March 23, 2018 Item #19 FY 2018 program budget amendment: Elvira to Morena double track project

The Transportation Committee recommended that the Board of Directors approve an amendment to the FY 2018 Program Budget, adding $3.404 million in funds from the City of San Diego to the Elvira to Morena Double Track project (Capital Improvement Program Project No. 1239811) to fully fund two wet utility agreements.

Transportation Committee June 15, 2018 Item #7 Proposed FY 2019 program budget amendment: Los Peñasquitos Lagoon bridge replacement project

The Transportation Committee recommended that the Board of Directors: (1) adopt Resolution Nos. 2018-23 through 2018-29, approving the FY 2019 Transportation Development Act and State Transit Assistance Act (STA) claims, and FY 2018 STA State of Good Repair claim; and (2) adopt the STA findings as certified by North County Transit District.

Transportation Committee July 6, 2018 Item #7 Proposed FFY 2019 program budget amendments: I-5/Voigt Drive improvements and I-5/ Gilman Drive Bridge projects

The Transportation Committee recommended that the Board of Directors approve amendments to the FY 2019 Program Budget to: (1) add $400,000 in UC San Diego funds to the I-5/Voigt Drive Improvements project (Capital Improvement Program [CIP] Project No. 1200507) for design of UC San Diego betterments; and (2) add $4 million in UC San Diego funds to the I-5/Gilman Drive Bridge project (CIP Project No. 1200508) for construction of UC San Diego betterments

Transportation Committee July 6, 2018 Item #11 NCC program: status update

Allan Kosup, Caltrans, presented an update on the NCC Program, including current and future highway, rail, and active transportation improvements, as well as lagoon restoration work. This item was presented for information.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

26

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors July 13, 2018 Item #3 Proposed FY 2019 program budget amendments: I-5/Voigt drive improvements project and I-5/Gilman Drive bridge project

The Board of Directors approved amendments to the FY 2019 Program Budget to: (1) add $400,000 in UC San Diego funds to the I-5/Voigt Drive Improvements project (Capital Improvement Program [CIP] Project No. 1200507) for design of UC San Diego betterments; and (2) add $4 million in UC San Diego funds to the I-5/Gilman Drive Bridge project (CIP Project No. 1200508) for construction of UC San Diego betterments.

Board of Directors July 27, 2018 Item #5 Proposed FY 2019 program budget amendment: Los Peñasquitos Lagoon bridge replacement project

The Board of Directors approved an amendment to the FY 2019 Program Budget, adding $979,267 in federal funds to the Los Peñasquitos Lagoon Bridge Replacement project (Capital Improvement Program Project No. 1145000) for construction capital and support.

Transportation Committee December 14, 2018 Item #9 NCC program: status update

Allan Kosup, Corridor Director, District 11, Caltrans presented an update on the NCC Program. This item was presented for information.

ITOC May 8, 2019 Item #13 NCC Program: Status Update

Allan Kosup presented an update on the NCC Program.

Transportation Committee May 17, 2019 Item #9 NCC Program: Status Update

Staff presented an update on the NCC Program.

Independent Taxpayer Oversight Committee (ITOC) Chronology of Key Actions /Summary of Significant Discussion

27

Committee / Date / Item # / Title

Major Corridor Project: Interstate 5 (I-5) North Coast Corridor

Board of Directors June 28, 2019 Item #10 Interstate 5/Voigt Drive Improvements Project

The Board of Directors 1. approved the Guaranteed Maximum Price negotiated between Mid-Coast Transit Constructors and SANDAG for Supplement 6 to the Construction Manager/General Contractor Construction Service Agreement for the Interstate 5/Voigt Drive Improvements project in the amount of $35.9 million;2. authorized the Executive Director to execute Supplement 6; 3. approved an amendment to the FY 2020 Program Budget, adding $12 million in SB 1 Local Partnership Program funding and $4.4 million in project savings from Elvira to Morena and San Diego River Bridge Double Track projects (Capital Improvement Program [CIP] Project Nos. 1239811 and 1239815) to fully fund the I-5/Voigt Drive Improvement project (CIP Project No. 1200507); and 4. approved an amendment to the FY 2020 Program Budget, accepting $14 million from UC San Diego for the UC San Diego Mid-Coast Improvements (CIP Project No. 1146700) to fund improvements along the corridor.

ITOC July 10, 2019 Item #5 Interstate 5/Voigt Drive Improvements Project

Allan Kosup, Caltrans, presented an update on Interstate 5/Voigt Drive Improvements and UC San Diego Mid-Coast Improvements projects, including recently approved amendments and construction awards

Transportation Committee September 20, 2019 Item #8 NCC Status Update

Allan Kosup, Caltrans, and SANDAG staff presented an update on the progress and status of the NCC program of projects including current and future highway, rail, active transportation and environmental work.