Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006

Transcript of Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System...

Page 1: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Transmission Studies for New Long Term Network Resources

Doug PowellManager Technical System Planning

Entergy Services, Inc. September 11, 2006

Page 2: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Two options for designating new Long-Term Network Resources

1. Incremental: Customer requests designation of new generation in addition to existing Network Resources.

2. Delisting/displacement: Customer requests designation of new generation replacing existing Network Resources.

Page 3: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Incremental Study

• New resource will be studied in addition to customer’s existing Network Resources.

• All network service studies will be performed on an incremental basis, unless service request specifies otherwise.

Page 4: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Delisting/Displacement Study

• Delisting study evaluates a new generation resource as a long-term replacement for an existing Network Resource.

• Displacement study evaluates a new generation resource as a short-term substitution for an existing Network Resource.

Page 5: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Delisting/Displacement Studies

• Performed at Customer’s election.

• Customer provides list of Network Resources to de-list/displace or Entergy Transmission can provide the delisting/displacement options for Customer.

Page 6: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Batching of Requests

• Customer can elect to have all or a portion of its requests to designate new Network Resources “batched.”

• Transmission will perform all studies in the specified “batch” and release the completed System Impact Studies (“SIS”) at one time.

• Only requests that are in consecutive order in the SIS queue can be “batched.”

Page 7: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Under the ICT

• The ICT will administer the Operating Companies’ OASIS

• The ICT will sign the SIS Agreement with customer and perform the System Impact Study

• To the extent a Facility Study is necessary and requested, Entergy transmission will conduct the study, subject to the validation of the ICT.

Page 8: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Questions??

Page 9: Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.

Timing of SIS • Transmission customer applies for transmission service

in OASIS. N/A• Entergy will forward System Impact Study Agreement

including estimated study cost and time required for completion. Within 30 Days

• Transmission customer returns executed Study Agreement to Entergy. Within 15 Days

• Entergy completes System Impact Study; Entergy approves or denies request for transmission service, or provides Facilities Study Agreement. Within 60 Days, if possible If request approved,

• Transmission Customer returns completed Service Agreement. Within 15 Days