Transmission Pricing 38
Transcript of Transmission Pricing 38
-
8/18/2019 Transmission Pricing 38
1/30
A new market clearing mechanism, based on comprehensive welfareallocation, considering participants’ optimality, ef ciency, and
extent of transmission use
Mohammadreza Baghayipour and Asghar Akbari Foroud*,†
Semnan University, Semnan, Iran
SUMMARY
This paper develops a new approach to fairly clear the market and assess the amount of each participant ’srevenue in a deregulated power system, through modifying the system nodal prices. This approach equalizes
the economic pro
t of each participant group to its fair and rational value. Transco behavior is modeled asan independent entity without direct supervision of an independent system operator, causing the possibilityof either making prot or incurring a loss for it. With this method applied, three main results for better system design and operation are produced:
(1) The rational and acceptable prot/loss values for all participant groups (producers, customers,
and Transco) are determined through fair apportionment of total system prot among them
based on their optimality and contribution of protability to the whole system.
(2) The prot/loss value for each of producers and consumers in the system is allocated according
to their proportional ef ciency and extent of transmission use.
(3) Transmission revenue assessment is performed through dening a criterion for evaluating the
transmission network optimality.
So this approach can correct wrong and unfair economic signals in the previous electricity pricingand participants’ revenue assessment methods, presenting such a fairer mechanism for it that each
participant ’s action will be oriented in maximizing the system
’s total economic ef
ciency. Copyright © 2012 John Wiley & Sons, Ltd.
key words: market clearing mechanism; social welfare allocation; revenue assessment; referencetransmission network; nodal prices
1. INTRODUCTION
In recent years, deregulation has resulted in some major changes in the economic behavior of the electricity
industry. These changes should be directed, such that the whole system act improves to attain the optimality
as well as nondiscriminatory use for all participants, namely producers, consumers, and a monopolistic
transmission company (Transco). In these systems, the private ownership manners of these entities and
their relevancy have special importance. These relations are usually controlled via an independent system operator (ISO). Here, three basic questions are posed:
(1) What are the rational revenue value and its evaluation mechanism for each participant group in
the system?
(2) How are the answered revenues between the constituents of each participant group in the system
(such as each of producers or consumers) shared, such that it is fair and nondiscriminatory from
their viewpoints?
*Correspondence to: Asghar Akbari Foroud, Semnan University, Semnan, Iran.†E-mail: [email protected]
Copyright © 2012 John Wiley & Sons, Ltd.
INTERNATIONAL TRANSACTIONS ON ELECTRICAL ENERGY SYSTEMS Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364Published online 21 June 2012 in Wiley Online Library (wileyonlinelibrary.com). DOI: 10.1002/etep.1661
-
8/18/2019 Transmission Pricing 38
2/30
(3) What is the appropriate manner and purpose of generation and transmission construction/expand-
ing, so that it reconciles all participants and improves the whole system operation to maximize its
economic ef ciency?
The answers to the rst and second questions are involved in the market clearing mechanism, and the
third broaches the generation expansion planning (GEP) and transmission expansion planning (TEP)
issues. It is clear that the answer to this question is directly affected by the answers from the previous
two queries. This is because, in the case of removing the ISO ’s force on each participant action, the
way of its revenue evaluation and recovery directly inuences its behavior. Hence, it is necessary to nd
a rational and fair mechanism for market clearing before broaching GEP and TEP issues.
The market clearing mechanism fundamentally includes two steps. The rst is to determine the
generation and consumption levels through solving the optimal power ow problem, with the purpose
of social welfare maximization (or total operational cost minimization). In fact, this step guarantees the
system economic ef ciency maximization during its operation and is completely rational. The second
step includes the determination of revenue and payment values for all participants. To this end, most of
previous papers have dened the locational marginal prices (LMPs) as the system nodal prices [1].
This way, which is usually affected by congestion, causes the total consumers’ payment to exceed total
generation revenue. As a result, the papers often have equated Transco ’s revenue with the resulted
network congestion surplus. That methodology has some drawbacks from the viewpoints of both
Transco and the other participants. However, most of the previous papers have discussed it from Transco’s point of view (summarized as follows). Moreover, the LMP-based pricing scheme will be
briey studied and criticized from the viewpoint of the other participants in Section 2.
(1) In the case that Transco’s act is optional and independent from ISO, value-based TEP is performed
with the purpose of congestion rent maximization, which consequently leads to the transmission
capacity withholding and more congestion in transmission lines, against the other participants’ inter-
ests and the system economic ef ciency [1].
(2) Alternatively, if Transco’s act is directly under ISO’s supervision, it must execute ISO’s approved
optimal transmission expansion plans. In this case, Transco earns from the network congestion rent,
exactly the same revenue as the variable part (lines capacity-dependent part) of the transmission
investment cost. However, the xed part (independent of lines capacity) of the aforementioned costs
is not recovered [1,2]. Hence, various approaches, reviewed in [3–5], have been presented to recover
the remaining xed part of the transmission costs and allocate it to the users. The postage stamp,contract pass, and megawatt-mile / megavoltampere-mile derived methods [1,3,4,6,7], transmission
capacity withholding [1,8], transmission lines’ extent-of-use evaluation-based methods [4,6,9–17],
and the evaluation of the participants’ prot/loss changes, due to the changes in the network topology
or line capacities [5,18,19] are in such group. Additionally, several papers [20–22] have used the nodal
prices or lines marginal capacity prices1 modication to equalize the congestion surplus to the total
required network revenue. Unlike the predecessors, those methods can perfectly recover both
xed and variable parts of the transmission investment costs through the modied congestion rent.
Nevertheless, all of the aforementioned methods have the principal dif culty that they recover only
the required net transmission costs as Transco’s revenue but not considering any rational prot or loss
value dependent on its optimality of act, as it is inherently incompatible with the direct supervision of
ISO. In this way, Transco will not have any incentive for ef cient transmission network constructing/
expanding (a detailed consideration of [20] and its additional drawbacks will be presented in Section 3).Rational transmission revenue assessment needs a benchmark for transmission optimality
evaluation. This benchmark should include the act of the united network, incorporating all its
lines, because evaluating the optimality of each line irrespective of the others is not so rational.
In this way, [1,23] have found the optimal transmission line capacities with the same network
topology, generations, and demands as the real one and named it the reference transmission
network (RTN). That is the network with minimum amount of total operational costs and
transmission investment costs (or long-run social welfare). Moreover, [24] denes the optimal
1Hourly operational cost reduction resulted for 1-MW increment in the capacity of each line [1].
M. BAGHAYIPOUR AND A. A. FOROUD1336
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
3/30
transmission expansion plan as RTN. Nevertheless, they all neither evaluate the current network
optimality by using the resulted RTN nor determine the rational transmission revenue, on the ba-
sis of this benchmark.
The rest of this paper is organized as follows. First, Section 2 briey reviews the LMP-based pricing
methodology and its main drawbacks. Then, Section 3 formulates the participants’ revenue and payment
assessment, on the basis of old LMPs, and Section 4 reviews the approach presented by [20]. Afterwards,
in Section 5, an ef cient approach for optimally clearing the power market and correcting the previouslymentioned weaknesses is presented. This approach denes RTN as a benchmark and introduces the total
social welfare as an ef cient criterion for evaluating the present transmission network quality as compared
with RTN. With this criterion used, the participant groups’ rational revenues, including their net costs as
well as some excess prot/loss, are determined, so that it makes correct economic signals for optimizing
their performance. Finally, the determined revenues are fairly shared among the participant individuals
through modifying the system nodal prices, based on their optimality of act, ef ciency, and extent of trans-
mission use. The proposed method is applied on IEEE RTS 30-bus system in Section 6, and the numerical
results are analyzed. Finally, Section 7 concludes the paper.
2. A VIEW OF LOCATIONAL MARGINAL PRICE-BASED PRICING SCHEME FROM THE
VIEWPOINTS OF PRODUCERS AND CONSUMERS
Here, the main drawbacks of the old LMP-based pricing methodology from the viewpoints
of producers and consumers are studied. To this end, the variations of LMPs, as well as the
participants’ costs, revenues, and prots, versus different transmission capacities are analyzed
in Figure 1(A) for a simple two-bus example, with one producer and one consumer on each
bus. In this gure, the horizontal axis contains the variations of the local generations, and two
vertical axes represent the resulted LMPs at two buses, following either of marginal cost curves.
It is supposed that the loads on the rst and second buses are equal to q1,d and q2,d , respectively
(i.e., OF and O0F lengths), and that the dashed line ZY represents per-megawatt demand worth.
Let us start following the curves from point F, which represents the value of zero for the
transmission line capacity. In this case, the local generations are equal to the local demands,
and the LMPs at the rst and second buses are denoted by points E and L, respectively. As
the line capacity increases, the operating point moves to the right, and the generation on therst bus increases, whereas the second decreases. Finally, point R represents the case with
unconstrained economic power dispatch between two buses. In this case, both of the buses have
the same LMPs, denoted by point N.
The values of producers’ and consumers’ revenues, costs, and prots in each of the aforementioned
cases are observable from the areas of the corresponding polygons in Figure 1(A). The resultant areas
are summarized in Table I. Accordingly, the main drawbacks of the LMP-based pricing mechanism
can be categorized into four principal topics.
2.1. Unfair determination of pro t/loss values for some producers and consumers
Because of the inherent characteristics of power generation units, the generation cost function is
mostly modeled as a nonlinear parabolic function. The LMP on a bus with marginal generator isthus a linear function of its generation level. Therefore, the electricity price unlike many other
commodities will increase as its generation increases, causing the generation revenue to be
usually different from the net generation cost with a generation-dependent prot, regardless of
the producers’ ef ciencies. As illustrated in Figure 1 and Table I, if two generators supply the
same local demands without any power exchange, their nodal prices will equal their marginal
costs, and the producer with less ef ciency (more slope of marginal cost curve) earns more prot.
In the case of power exchange between two buses, this drawback can slightly be solved, because
the transmission line with unlimited capacity provides the unconstrained economic dispatch
applicability, more generation, and subsequently more prot for the more ef cient producer.
However, because of the transmission investment cost, the aforementioned case is not
A NEW MARKET CLEARING MECHANISM 1337
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
4/30
economically reasonable. On the other hand, the line with the optimal capacity does not com-
pletely realize the unconstrained economic dispatch, and the less ef cient producer still may earn
the same or even more prot.
2.2. No fair and use-dependent allocation of the transmission payment among the participants
The LMP-based pricing mechanism does not guarantee fair and use-dependent allocation of the
transmission payment among the participants. For instance, if the rst producer sells a considerable
rate of electricity to the consumer on the second bus, the power price on the rst bus will increase,
and subsequently its consumers will sustain a loss, while they not only take no advantage from the
transmission line but also benet the system by reducing the line congestion. This problem can be
restated somewhat for the producers on the large demand buses, connected to a transmission line. In
this case, the line reduces the producers’ prots, and they decrease the line congestion, and so they
should not take part in transmission payment. Nevertheless, because their prot decrement is due to
their relatively less generation ef ciencies, their prots should still be less than the others’ (with more
Figure 1. (A) The variations of locational marginal prices, revenues, payments, and prots for producersand consumers in a two-bus system, when the line capacity grows and (B) the corresponding curves of
the aforementioned values versus different capacities of the line.
M. BAGHAYIPOUR AND A. A. FOROUD1338
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
5/30
T a b l e I . T h e p r o d u c e r s ’
a n d
c o n s u m e r s ’ e c o n o m i c m e a s u r e s f o r t h r e e d i f f e r e n t t r a n s m i s s i o n c a p a c i t i e s , a s
t h e a r e a s o f t h e c o r r e s p o n d i n g p o l y g o n s i n F i g u r e 1 ( A ) .
L i n e c a p a c i t y
0
T L i
U . E . D
o w
L i n e c a p a c i t y
0
T L i
U . E . D
o w
F i r s t p r o d u c e r ’ s r e v e n u e
O B
E F
O C G H
O D N R
S e c o n
d p r o d u c e r ’ s r e v e n u e
O 0
F L X
O 0
H M W
O 0
R N V
F i r s t p r o d u c e r ’ s c o s t
O A
E F
O A G H
O A N R
S e c o n
d p r o d u c e r ’ s c o s t
O 0
F L U
O 0
H M U
O 0
R N U
F i r s t p r o d u c e r ’ s p r o t
A B
E
A C G
A N D
S e c o n
d p r o d u c e r ’ s p r o t
U L X
U M W
U N
V
F i r s t c o n s u m e r ’
s r e v e n u e
O F
S Z
O F S Z
O F S Z
S e c o n
d c o n s u m e r ’
s r e v e n u e
O 0
F S Y
O 0
F S Y
O 0
F S Y
F i r s t c o n s u m e r ’
s p a y m e n t
O B
E F
O C I F
O D J F
S e c o n
d c o n s u m e r ’
s p a y m e n t
O 0
F L X
O 0
W K F = O 0
H M W + F G H + G M K I
O 0
V J F = O 0
R N V + R F J N
F i r s t c o n s u m e r ’
s p r o t
B E
S Z
Z C I S
Z D J S
S e c o n
d c o n s u m e r ’
s p r o t
S L X Y
W
K S Y
V J S Y
S y s t e m
c o n g e s t i o n s u r p l u s
0
G M K I
0
U . E . D . , U n c o n s t r a i n e d E c o n o m i c D i s p a t c h .
A NEW MARKET CLEARING MECHANISM 1339
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
6/30
ef ciency). In addition, another point that is observable from Figure 1(A) and Table I is that the system
congestion surplus is fully recovered via the second consumer, as the main transmission beneciary,
whereas the rst producer also takes advantage from the line, but it does not participate in its payment.
2.3. Improper pro le for the bulk generation pro t, as it directs the producers’ aggregate interests
against the system ef ciency
Figure 1(B) displays the variation curves of the quantities in Figure 1(A) versus different capacities of
the line. As depicted in this gure, although the economic power dispatch is perfectly compatible with
the bulk consumers’ interests, it does not satisfy the bulk producers’ desires, as their total revenue and
prot generally have descending proles as the line capacity increases. On the other hand, the line
optimum capacity is typically near its unconstraint ow [1]. Hence, although the different producers’
interests can be in diverse directions, their resultant bulk interest usually opposes the transmission
optimum capacity.
2.4. The producers seldom sustain a loss, but the other participant groups may lose in many cases
With the old LMPs used, there are several cases that the consumers incur a loss from power
purchase. For example, if in Figure 1(B), the demand worth becomes slightly fewer than the
value of dashed line ZY, it causes a loss for consumers. Moreover, the transmission payment
based on the network congestion surplus causes a loss for Transco in many cases. In contrast,
producers only may incur a loss in one rare case, depicted in Figure 2. In this gure, LMP on
the rst bus follows line FD as long as its generation remains in allowable limit. But when its
generation ef ciency is so little that its optimal generation level decreases to the minimum and
if another producer can supply the unmet load on that bus with a lower price, LMP on the
bus will follow the line DC and declines to l1, below the rst generator minimum marginal price.
In this case, the rst producer ’s prot and generation cost are equal to the areas of rectangle
OBME and trapezoid OADE, respectively. Hence, the producer incurs a loss only when the trapezoid area
exceeds the rectangle area, that is, the area of triangle CMD exceeds the area of ABC.
3. LOCATIONAL MARGINAL PRICE-BASED REVENUE AND PAYMENT ASSESSMENTFORMULATION
Like in [20], the direct current optimal power ow (DCOPF) problem is recalled here, considering
given inelastic load vector QDx and the predened unit commitment schedule, in order to nd the
optimal generation levels as well as nodal voltage angles for each hour of the system operation
lifetime, with the goal of minimizing the total generation cost, subjected to the network constraints.
Figure 2. Variation of prot and loss values for a producer ’s maximum and minimum generation levels.
M. BAGHAYIPOUR AND A. A. FOROUD1340
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
7/30
The problem is expressed as in Equations (2)–(5), using the generation cost vector formulated as in
Equation (1). The two matrices GIM and CIM are mathematically dened according to Equations
(6) and (7), with symbols gimn,g and cimn,d denoting the elements of row n–column g and row n–col-
umn d of the matrices GIM and CIM , respectively.
GC QGð Þ ¼ a QG þ b QG^ 2 (1)
minQG;dX
GC QGð Þð Þn o
(2)
Subject to
GIM QG CIM QD ¼ P dð Þ ¼ B d; lð Þ (3)
QLowGx ≤QG≤QUpGx; s L;s Uð Þ (4)
t x≤H d≤t x; g L;g Uð Þ (5)
GIM ¼ gimn;g
¼ 1: if generation unit g connects to bus n
0: otherwise
;
n ¼ 1; 2; . . . ; N Bg ¼ 1; 2; . . . ; N G
(6)
CIM ¼ cimn;d
¼ 1: if demand d connects to bus n
0: otherwise
;
n ¼ 1; 2; . . . ; N Bd ¼ 1; 2; . . . ; N D
(7)
The main results of solving the DCOPF problem in the present power system x are the vectors QGxand dx, as well as lx, that is, the vector of LMPs at the system nodes. With these vectors used, the bulk
revenue and payment assessment for various participant groups can be formulated as Equations (8)–(13).
These values are suf xed with symbol x for representing their dependence with the vectors of
transmission line capacities (Equation (5)) as well as the generation of lower and upper limits
(Equation (4)) in the present power system x. Moreover, Equation (14) formulates the transmission
network per hour investment cost, as a function of its line capacities and lengths, supposing that Transco
has constructed all the transmission lines in the power system x in the same time, and its required invest-
ment cost can hourly be amortized with zero interest rate.
LR ¼X
d QD s QD^ 2 (8)
GC x ¼ XGC QGxð Þ (9)GRx ¼ lx
T GIMQGx (10)
LC x ¼ lxT CIMQD (11)
NRx ¼ LC x GRx (12)
¼ lxT GIMQGx CIMQDð Þ ¼ lx
T P dxð Þ ¼ lxT Bdx (13)
IC x ¼ k lT t x
8760 (14)
4. A VIEW OF [20]
In [20], the previous LMPs are modied, such that the required transmission cost can perfectly be re-covered via the resulted congestion surplus. To this end, that paper rst solves the DCOPF problem,
obtaining its main consequences, and then denes some additive penalties/rewards associated with
the system generations and nodal injections. These factors are obtained, by solving a special bi-level
optimization problem that applies the minimum nodal price deviations from the precalculated LMPs,
so that the following four groups of constraints can be satised:
(1) the constraint that ensures full recovery of the required network revenue from the congestion
surplus (Equation (16));
(2) the constraint that is associated with equal sharing of transmission revenue recovery between
producers and consumers (Equation (17));
A NEW MARKET CLEARING MECHANISM 1341
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
8/30
(3) the constraint that guarantees that the optimal precalculated generation levels and voltage angles
will not change after running the optimization problem (implicit in Equations (18)–(20)); and
(4) the constraints that are associated with the inner problem satisfaction that minimizes the sum-
mation of total generation cost and the additional payments for participants’ extents of transmis-
sion use, as some functions of the aforementioned penalties/rewards (Equations (18)–(21)).
These constraints have been formulated using the Lagrange representation of the internal opti-
mization problem, and they form the main one-level optimization problem (as in Equations(15)–(21)).
minr;l;s;g
l lxk k (15)
Subject to
lT P dxð Þ ¼ NRx (16)
lTCIMQD lxTCIMQD ¼ NRx-lx
TP dxð Þ
2
(17)
ddQGGC QGÞ QGx GIM
Tl þ rg sL þ sU ¼ 0. (18)
B l þ rdð Þ þ HT
gU gLð Þ ¼ 0 (19)sT L QGx Q
LowGx
þ sT U Q
UpGx QGx
þ gT L f x t xð Þð Þ þ g
T U t x f xð Þ ¼ 0 (20)
g L;g U≥0 ; s L;s U≥0 (21)
As illustrated in [20], its approach improves some drawbacks of the old LMPs. For example, it com-
pensates the resulted prot decrement for consumers on generation buses and producers on demand
buses. Nevertheless, it cannot correct a number of them, which can be summarized in three principal
issues:
(1) It does not provide any prot/loss for Transco and consequently any incentive for its better
performance.
(2) It modies the nodal prices, on the basis of minimizing their difference with the old LMPs. In
other words, that approach assumes the old LMPs as a basis and slightly changes them to equate
the resulted network congestion income with the required transmission costs. As illustrated in
Section 2, the old LMP-based mechanism inherently has some essential drawbacks and does
not produce correct economic signals in many cases. Hence, it cannot be a good basis for nodal
prices determination.
(3) In some cases, that approach even dispossesses the old LMP-based prot apportionment mechanism
from fairness. For instance, the prot decrement for less ef cient producers on the demand buses
should not be completely compensated, as it provides some incorrect economic signals for them.
5. MARKET CLEARING STEPS, BASED ON THE PRESENT PAPER APPROACH (AFTER
SOLVING DIRECT CURRENT OPTIMAL POWER FLOW PROBLEM)
5.1. De nition and calculation of “total social welfare,” as a basis for correcting the previous defects
In order that the revenue and payment assessment process can fairly be accomplished, at rst, a bench-
mark for evaluating the whole system ef ciency affected by different participants’ behaviors is re-
quired. This benchmark, named here as “total social welfare,” is dened as the total prot of all the
participants according to Equations (22) and (23). These equations demonstrate that the mentioned
value equals the resulted net prot (or the negated net cost) of the system, considering the generation
and transmission costs as well as the obtained consumption revenue. This consequence can be inter-
preted by noting the fact that the three main participant categories indeed are some copartners in a
communal participation to produce some commodities or services, and their total prots equal the
net participation prot, that is, the net revenue minus the net cost. It is noticed that this denition
M. BAGHAYIPOUR AND A. A. FOROUD1342
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
9/30
can be extended to a more general formula, which is the difference between the net system revenue and
the net system cost. The net system revenue includes all the revenues resulted from the electricity
consumption, and the net system cost comprises all the costs required to produce and transmit the
electricity, such as generation investment and operational costs, generation emission costs, transmis-
sion investment cost, and cost of environmental impacts. From this extended denition, the economic
measure of all the advantages and disadvantages resulted from the power system operation and
planning can be considered, and the total social welfare can be obtained as the difference betweenthe equivalent economic values of the total advantages and disadvantages. The equivalent economic
evaluation of different advantages/disadvantages is usually performed by the related entities. For
example, Environmental Safety Organization assesses the emission taxes for generation companies
or the taxes of environmental impacts for both the generation and transmission companies.
SWt x ¼ Gprofit x þ Lprofit x þ Nprofit x¼ GRx GC x þ LR LC x þ NRx IC x¼ NRx GC x þ LR þ NRx IC x
(22)
¼ LR GC x IC x (23)
5.2. Bulk competence measure: the criterion for fair apportionment of total social welfare among the
participant groups and modifying Equations (16) and (17)
The resulted total social welfare in the system should be fairly apportioned among the main three bulk
participant entities, namely generation, consumption, and the monopolistic Transco. As the essence of
the bulk entities’ act in the system is completely different, this apportionment should be performed
considering their own effects on the value of total social welfare and in such a manner that their
long-term behaviors can be oriented in the total social welfare maximization. The mechanism proposed
here to attain this goal is to apportion the bulk prot shares among the three main participant groups in
proportion to a mathematical criterion named here as “bulk competence measure.” This criterion is de-
ned here as the mathematical product of two main criteria, namely bulk optimality measure and bulk
protability measure, which are introduced as follows.
5.2.1. Bulk optimality measure. Bulk optimality measure presents a criterion for evaluating the opti-mality of act for each participant group in comparison with its own best performance. To this end,
the present behavior of each group as well as its optimal case and the case of removing it from the sys-
tem should be analyzed, and the bulk optimality criterion for each participant group can be dened as
in Equation (24). In this equation, symbol BOM Co,x denotes the bulk optimality measure for the bulk
entity, suf xed by Co index in present power system x, and SWt x, SWt absence,Co, and SWt best,Co repre-
sent the resulted total social welfare supposing the present system x, the system without the entity, and
the system with its best possible behavior, respectively.
BOM Co;x ¼ SWt x SWt absence;Co
SWt best ;Co SWt absence;Co(24)
Because the participants’ behaviors can generally be evaluated from the viewpoints of either their
operation or their planning, the term for the best total social welfare in the aforementioned criterioncan be obtained in different ways, dependent on each group’s work nature. However, for the sake of
simplicity, the operation manners of the bulk entities are ignored here, and the bulk optimality measure
for both transmission and bulk generation entities are evaluated by considering their planning beha-
viors. Furthermore, as the consumers do not take part in the electrical planning processes (i.e., TEP
and GEP); their best possible manner is equated to their present manner, and so the bulk optimality
measure for them is assumed equal to 1. This assumption seems to be rational, as in essence, the con-
sumers are those who are mainly extracting the net prot or welfare from electricity consumption.
However, the discussion on how to determine the bulk optimality measure for the bulk consumption
entity in a more accurate way may still be an open problem and requires more analysis, which is out
of the scope of this paper.
A NEW MARKET CLEARING MECHANISM 1343
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
10/30
According to Equation (24), the bulk optimality measure for Transco can be obtained in this way:
(1) The total social welfare that resulted from the present transmission network (x) is denoted here
as SWt x and can be obtained by running the DCOPF problem (Equations (2)–(5) in the present
system and by using the formulation of Equation (23).
(2) The optimum case of transmission design can be attained through constructing the RTN. RTN is
dened here as the network with the same generations, demands, and topology as the present
one but with different line capacities such that the DCOPF-resulted total social welfare can be
maximized (denoted here as SWt RTN). RTN can be obtained by solving a special bi-level
optimization problem as in Equations (25) and (26). This problem can be solved by using a stochas-
tic optimization algorithm that executes the DCOPF subproblem, once for each set of the line
capacities given from the external subproblem, and that minimizes its resulted total generation cost.
SWt RTN ¼ maxt x
SWt xð Þ ¼ maxt x
LR GC x IC xð Þ (25)
Subject to
t x ≥0 (26)
as well as to
DC OPF 2 5ð Þh i
(3) The system total social welfare in the case of removing all its transmission lines is denoted here
as SWt 0. This quantity can be calculated by solving a DCOPF problem, which takes into account
variable load vector as a new decision variable in addition to the formers and consequently
considers the consumption revenue decrement due to the required load curtailment and the
generation decrement to satisfy the power balance constraint.
(4) Finally, the bulk optimality measure for Transco can be formulated in a way similar to Equation
(24), as seen in Equation (27), where symbol BOM Transco, x denotes the bulk optimality measure
for Transco in the present power system x.
BOM Transco;x ¼
SWt x SWt 0
SWt RTN SWt 0 (27)
In a similar way, the bulk optimality measure for the bulk generation entity can be obtained as
follows:
(1) The total social welfare that resulted from the present system (x) has been calculated previously
as SWt x.
(2) The optimum case of generation capacity design can be attained through constructing the refer-
ence generation capacities (RGCs). RGC is dened here as the network with the same demands,
transmission lines, and topology as the present one but with different generation capacities such
that the DCOPF-resulted total social welfare can be maximized (denoted here as SWt RGC). In
principle, RGC should be obtained by using a bi-level optimization problem similar to that of
Equations (25) and (26) and considering the generation investment costs (beside the transmissioncosts). However, for the sake of simplicity, here, it is assumed that the generation cost functions
can include both the fuel costs and the generation investment costs; thus, there is no need to con-
sider the generation total investment cost as a separate variable. Consequently, the proposed
problem for nding the RGC can be simplied to an ordinary DCOPF as in Equations (2)–(5),
with the difference that the generation upper limits are set to innity. Then, the resulted
unbounded generation levels can introduce the best possible generation capacities, and SWt RGCcan easily be calculated by applying Equation (23) on the outcomes obtained from the mentioned
DCOPF solution.
(3) Provided that the whole generation entity can be removed from the system, there will be neither
load revenues nor generation costs. Then, the total social welfare will decrease to the negated
M. BAGHAYIPOUR AND A. A. FOROUD1344
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
11/30
total transmission investment cost. On this condition, it seems rational to neglect the transmis-
sion investment costs in the total social welfare calculation, because if this case were actually
realizable, Transco, indeed, would not construct the transmission network at all. On the other
hand, according to Equation (24), considering a negative value of total social welfare in this
case results in an overestimated bulk optimality measure for the bulk generation entity. Hence,
in order to avoid such inequities, the value of total social welfare in the case of removing the
whole generation entity is assumed equal to 0. It should be noted that, because of similar rea-soning, the value of total social welfare in the case of removing the whole consumption entity
(which is required in the next section) is also equated to 0.
(4) Finally, the bulk optimality measure for the whole generation entity can be formulated as in
Equation (28), where symbol BOM Generation,x represents the bulk optimality measure for the
whole generation entity in the present power system x.
BOM Generation; x ¼ SWt x
SWt RGC(28)
5.2.2. Bulk pro tability measure. The bulk protability measure for each participant category
introduces a criterion to evaluate how much its present performance participates in attaining the pres-
ent system total social welfare, relative to the case without it. In other words, this criterion determines
the percentage increase in the total social welfare in the present system compared with the case of
removing each bulk entity, as formulated in Equation (29) with symbol BPM Co,x denoting the bulk
protability measure for the bulk entity indexed with Co in the present power system x.
BPM Co; x ¼ SWt x SWt absence;Co
SWt x(29)
Because, as described in Section 5.2.1, the value of SWt absence,Co for both the bulk generation and
consumption entities is equal to 0, according to Equation (29), the bulk protability measure for both
of them is equal to 1. This means that both the bulk generation and consumption entities have the same
protability measures. This consequence seems to be rational, as with either of them removed, the total
social welfare declines to zero.
The bulk protability measure of Transco in the present power system x, denoted here as BPM Transco,x,
can also be derived from Equation (29) as formulated in Equation (30). According to Equation (30), thisvalue for Transco is typically lower than two other bulk entities, or in other words, its act is typically of
lower importance. This outcome is also rational, because with all the transmission lines removed, the
remaining network may still be able to supply some loads (which are connected to local generations)
and thereby be protable.
BPM Transco;x ¼ SWt x SWt 0
SWt x(30)
5.2.3. Bulk competence measure. The bulk competence measure value is denoted here as BCM Co,x for
the bulk entity, indexed with Co in the present power system x, and is dened as the product of the two
aforementioned criteria (bulk optimality measure and bulk protability measure), according to
Equation (31).
BCM Co; x ¼ BOM Co; x BPM Co; x ¼ SWt x SWt absence;Co
SWt best ;Co SWt absence;Co
SWt x SWt absence;CoSWt x
(31)
In the view of the comments pointed out in the previous two sections and of Equations (27)–(31),
the bulk competence measure for each of the three bulk participant entities can be formulated as in
Equations (32)–(34). In these equations, symbols BCM Transco,x, BCM Generation,x, and BCM Consumption,xrespectively represent the bulk competence measure for Transco, entire generation entity, and entire
consumption entity in the present power system x.
BCM Transco;x ¼ SWt x SWt 0SWt RTN SWt 0
SWt x SWt 0
SWt x(32)
A NEW MARKET CLEARING MECHANISM 1345
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
12/30
BCM Generation;x ¼ SWt x
SWt RGC(33)
BCM Consumption;x ¼ 1 (34)
5.2.4. Determination of the nal bulk pro t shares for each participant group. Finally, the bulk prot
shares for the three bulk participant entities are obtained using Equations (35)–(37). Two optional
equations from these equations will be replaced later, instead of Equations (16) and (17) in the optimi-
zation problem, formulated by [20].
Nprofit x ¼ BCM Transco;x
BCM Transco;x þ BCM Generation;x þ BCM Consumption;x:SWt x (35)
Gprofit x ¼ BCM Generation;x
BCM Transco;x þ BCM Generation;x þ BCM Consumption;x:SWt x (36)
Lprofit x ¼ BCM Consumption;x
BCM Transco;x þ BCM Generation;x þ BCM Consumption;x:SWt x (37)
5.2.5. The long-term investment signals of the proposed bulk pro t apportionment scheme. The mech-
anism presented in Sections 5.2.1,5.2.2,5.2.3,5.2.4 for sharing the system ’s total social welfare among
the three bulk participant entities can produce some positive long-term investment and planning sig-
nals for both the generation and transmission entities and even for the bulk consumption entity, which
can be listed as follows:
(1) According to Equations (32) and (35), the proposed mechanism encourages the Transco (which,
as supposed here, has an active role in the system with variable prot/loss) to determine and
construct better transmission expansion plans and line capacities, which liken and close the entire
transmission network to the RTN and increase the total social welfare as much as possible.
(2) According to Equations (33) and (36), the mechanism also encourages the producers to make bet-
ter generation capacities, which are as close as possible to the RGCs. Thereby, the more ef cient
producers (with lower costs) usually have the incentive to increase their presented generation ca-
pacities, as the RGC usually introduces more capacities for more ef cient producers.
(3) As is obvious, more values of load shedding in the system with no transmission lines correspond tomore dependence between supplying the required demand and the existence of transmission
lines because of far distances between generation units and load centers. According to Equations
(32) and (35), this leads to a more decrement in SWt 0, as well as to a more prot share for
Transco. Because this consequently results in reducing the other participants’ prots, it
encourages them to decrease the farness between generation and demand centers while locating
at the design time (for example, by using the distributed generations) and leads to the system
long-term economic ef ciency increment.
5.3. Modi cation of the objective function (Equation (15)) to affect the pro t sharing mechanism
among individual producers and consumers directly by their ef ciency and extent of transmission use
In the previous sections, the way to fairly modify the constraints of Equations (16) and (17) is
explained. However, this method is ef cient to determine the bulk rational prot shares for each of
the three participant groups, and it does not modify the prot sharing mechanism for their individuals
(i.e., each producer or consumer). This means that, for example, the bulk-determined prot for the ent-
ire generation entity should be apportioned among the individual producers such that the more ef cient
producer earns more prot, although its prot should decrease, depending on its relative transmission
use, in comparison with the others. This target is attained in this section via determining a new set of
nodal power prices such that the predened entire producers and consumers’ bulk prots can be
allocated to their individuals, on the basis of their ef ciencies and extents of transmission use. In this
direction, the system nodal prices will be determined regardless of the previous LMPs but with the
purpose of causing the minimum possible differences between participants’ monetary quantities
M. BAGHAYIPOUR AND A. A. FOROUD1346
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
13/30
(revenues and payments) and their rational values, such that the network constraints as well as two
additional constraints for bulk participants’ prots can be satised. To this end, rstly, it is necessary
to dene several vectors relating to either participants’ ef ciencies or their relative extents of transmis-
sion use in the system as follows.
5.3.1. Relative extents of transmission use for producers. The aim of this section is to dene a
criterion for evaluating the producers’
relative extents of transmission use. As described in Section1, various approaches have been presented so far to attain the aforementioned goal. Those methods
mostly consider the act of each transmission line individually, and only a few of them regard the
use of the whole transmission network. For the sake of summarization, this paper avoids broaching
the aforementioned problem and simply assumes that the vector of relative extents of transmission
use for producers can be represented with symbol UGx, which, in the simplest form, is dened as in
Equation (38), with symbol uiG, representing its ith elements. In addition, in this equation, symbols
pi and gni respectively denote the ith elements of the nodal injections vector (P(dx) = Bdx) and vector
GN, that is, the vector of the numbers of generation units connected to each of the system buses
according to the denition of Equation (39). As will be seen later, the role of the recent vector in
the denominator of the fraction is to equally share the transmission use for the buses containing several
generation units among the units.
UGx ¼ uiGf g ¼ pi= P
Pj jgnið Þif pi > 0
0 if pi≤0
8<:
9=; ; i ¼ 1; 2; . . . ; N B (38)
GN ¼ gnif g ¼ GIMEg (39)
Equation (38) supposes that the relative extents of transmission use for the producers connected to
each bus are directly related to the net injected power from that bus to the system. Thereby, if the total
generation on the node equals its local demand, the relative extent of transmission use for its both
producers and consumers can be equated to 0, as they do not exchange electrical power with the
network. In the same way, positive net injected power at the bus corresponds to the transmission
use for only the producers connected to the bus and the negative value for only the consumers. How-
ever, this method does not consider the extents of use for individual transmission lines, although someparticipants may use shorter and cheaper lines, but it is the simplest way for evaluating the participants’
extent of transmission use. It should be noted that the main goal of this paper is not to determine the
aforementioned criterion, but in contrast, it attempts to modify the prot allotment mechanism with the
use of the criterion. Hence, the criterion of Equation (38) can be replaced here with any other appro-
priate equation according to the papers discussed in Section 1 or any other related paper.
5.3.2. Relative generation ef ciency vector. Generation ef ciency vector can be dened as the vec-
tor containing the ratios of the producers’ generations to their costs, according to Equation (40),
with symbol l x denoting the average electricity price in the system as dened in Equation (41).
This value presents a criterion for evaluating the worth of the generated power. It is used in Equa-
tion (40) in order to homogenize the numerator and denominator of the fraction, both in monetary
units. The costs remarked in Equation (40) may indeed include any costs or disadvantages requiredfor electricity generation or anything imposed by generation units, such as generation fuel and in-
vestment costs, emission costs, and costs of environmental impacts due to construction of power
plants, as well as equivalent transmission use costs, that is, the costs indicating the producers’
shares of transmission use. However, for the sake of simplicity, here, it is supposed that all such
costs except the equivalent transmission use cost can be included in the hourly generation cost
functions (as practically may be quite correct). Hence, in Equation (40), the denominator in the
right side only contains the vectors of hourly generation cost functions as well as the term IC xGIMUGx,indicating the vector of hourly equivalent transmission use costs for the generation units. In this term,
the extents of transmission use for the producers are indeed homogenized with their generation costs,
both as pecuniary quantities, so that both their effects can easily be compared and analyzed. To this
A NEW MARKET CLEARING MECHANISM 1347
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
14/30
end, the equivalent transmission use cost for each producer is dened here as the previously dened rel-
ative transmission use criterion multiplied by the net required transmission investment cost and is as-
sumed as the generation cost increment, superimposing to the previous generation cost. The role of
the product of two vectors GIM and UGx is also to extract the transmission use extents for individual
generation units from those calculated for the system buses. Thereby, the vector of relative generation
ef ciencies for producers considering their relative extents of transmission use can nally be formulated
as hGx=PhGxaccording to the denition of Equation (40) for hGx.
hGx ¼ lxQGx= GC QGxð Þ þ IC xGIMUGxð Þ (40)
lx ¼
Plx
N B(41)
5.3.3. Relative extents of transmission use for consumers. In the same way as with Equation (38),
Equation (42) formulates the relative extents of transmission use for consumers, with symbols uiDand dni denoting the ith elements of vectors UDx and DN, respectively. In a similar way to
Equation (39), vector DN contains the numbers of separate demands connected to each node and
can be formulated as Equation (43).
UDx ¼ uiDf g ¼ pi= P
Pj jdnið Þ if pi > 0
0 if pi≤0
8<:
9=; ; i ¼ 1; 2; . . . ; N B (42)
DN ¼ dnif g ¼ CIMEd (43)
5.3.4. Relative consumption ef ciency vector. Similar to the previously dened relative generation
ef ciency vector, the relative consumption ef ciency vector can be formulated as in Equation (44).
In this equation, vector CIM, as a multiplier, plays the role of obtaining the relative extents of
transmission use for the individual demands from those previously calculated for the system nodes.
hDx ¼ LR QDð Þ IC xCIMUDxð Þ= lxQD
(44)
5.3.5. Final modi ed optimization problem formulation. The nal modied objective function isdened here in such a manner that each producer ’s revenue and each consumer ’s payment can be matched
as close as possible with their rational values. This goal is achieved considering the fact that the products
of the power price on each bus and its connected producers ’ generation levels equal their resulted
revenues. In addition, the power price on each node multiplied by its connected consumers’ demands will
equal their obligated payments. On the other hand, each individual producer ’s rational revenue can be
dened as the summation of its generation cost and the rational prot share from the bulk-determined
prot for the entire generation entity (determined in Equation (36)) according to its relative generation
ef ciency. Similarly, the rational individual consumers’ payments can be obtained as the differences
between their load revenues (known as demand worth) and their rational prot shares from that predened
for the whole consumption entity (Equation (37)) according to their relative consumption ef ciencies.
Therefore, the modied objective function, as well as the constraints, can nally be formulated as in
Equations (45)–
(51). As is obvious, the two norm operators in Equation (45) are respectively de
ned over the sets of individual producers and consumers, even if there are two or several producers or consumers
connected to a bus. Herein, the roles of the vectors GIMT and CIMT multiplied byl is to obtain the nodal
prices that belong to the individual producers and consumers, in accordance with the aforementioned
goal. In addition, it should again be noted that the real meaning of the generation cost functions in
Equation (45) might practically include all the costs related to the electricity generation by the producers,
such as hourly generation fuel and investment costs, hourly emission costs, and hourly costs of the
environmental impacts imposed by the generation units. However, the equivalent transmission use cost
should obviously be ignored in the generation costs inclusion, because it is not actually a part of the costs
that producers are directly necessitated and only reduces their prot through separately being considered
in the generation ef ciency vector according to Equation (40).
M. BAGHAYIPOUR AND A. A. FOROUD1348
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
15/30
minr;l;s;g
GIMT l QGx GC QGxð Þ þ Gprofit xhGx=PhGx
þCIMT l QD LR QDð Þ Lprofit x
hDx=PhDx
8<:
9=; (45)
Subject to
l
T
GIMQGx GC x ¼ Gprofit x ¼
BCM Generation;x
BCM Transco;x þ BCM Generation;x þ BCM Consumption;x :SWt x (46)
LRx lTCIMQD ¼ Lprofit x ¼
BCM Consumption;x
BCM Transco;x þ BCM Generation;x þ BCM Consumption;x:SWt x (47)
ddQGGC QGÞjQGx GIM
Tl þ rg sL þ sU ¼ 0.
(48)
B l þ rdð Þ þ HT gU gLð Þ ¼ 0 (49)
sT L QGx QLowG
þ sT U Q
UpG QGx
þ gT L f x t xð Þð Þ þ g
T U t x f xð Þ ¼ 0 (50)
g L;g U≥0 ; s L;s U≥0 (51)
6. NUMERICAL ANALYSIS
The proposed algorithm (Equations (45)–(51)) has been applied on modied IEEE 30-bus system and
has been solved using MATLAB fmincon general-purpose optimization function in several different
cases. As previously mentioned, the DCOPF problem is formulated here, considering inelastic loads
(except in the case of removing all the transmission lines, which vast load shedding is required),
and so its decision variable is just the generation vector. Hence, the applied demand schedule is con-
sidered the same as those presented in the IEEE 30-bus system, listed in Table II beside the
corresponding coef cients of the consumption revenue functions appended to the mentioned test case.
However, the generation schedule has been slightly modied through inserting a new generation unit
into it, connected to bus 2, so that the effectiveness of the proposed approach in different cases can bebetter demonstrated. The default generation schedule containing the default generation cost function
coef cients and default generation capacities (i.e., the upper limits, as the lower limits are constantly
assumed equal to 0) for all the generation units in the present system is available in Table III. However,
it should be noted that the sets of generation capacities and generation cost function coef cients can
completely be changed in different cases under study, and the sets listed in Table III represent the
default generation schedule. In addition, the default transmission schedule including the two line
ending nodes, their lengths, default capacities, and required investment costs are available in Table IV.
However, the transmission topology and the line lengths are the same in all the cases under study, the
line capacities and their investment costs can also be varied in different cases, and those available in
Table IV only represent their default values. The annualized per-kilometer per-megawatt marginal
investment costs of building the transmission lines and the annualized per-megawatt investment costs
of building the power transformers and the generation units are supposed to be equal to $35/MW.km.
year, $250/MW.year, and zero, respectively. According to Equation (14), it is supposed here that therequired investment cost of a transmission line is linearly proportional to the product of its length and
capacity, whereas the corresponding cost for a transformer branch is only in linear proportion to its
capacity. In addition, for the sake of simplicity, the required investment costs of the generation units
are assumed equal to 0 (as in reality, such costs can be included in their generation cost functions).
Here, for better demonstration, the presented mechanism has been applied on such power system for
each of the several different cases described in the following remarks:
(1) To illustrate the effectiveness of the proposed approach even though two or several generation
units are simultaneously connected to one node, two cases containing two different sets of
generation cost function coef cients for both the generation units at bus 2 are applied by xing
A NEW MARKET CLEARING MECHANISM 1349
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
16/30
T a b l e I I . T h e c o e f c i e n t s o f t h e d e m a n d r e v e n u e f u n c t i o n s a n d t h e g i v e n d e
m a n d l e v e l s i n t h e s y s t e m .
D e m a n d #
B u s #
d
s
Q D
D e m a n d #
B u s #
d
s
Q D
D e m a n d #
B u s #
d
s
Q D
1
2
5 0 . 0 5
0 . 0 1 1
2 1 . 7 0
8
1 2
5 0 . 4 0
0 . 0 1 8
1 1 . 2 0
1 5
2 0
5 0 . 7 5
0 . 0 2 5
2 . 2 0
2
3
5 0 . 1 0
0 . 0 1 2
2 . 4 0
9
1 4
5 0 . 4 5
0 . 0 1 9
6 . 2 0
1 6
2 1
5 0 . 8 0
0 . 0 2 6
1 7 . 5 0
3
4
5 0 . 1 5
0 . 0 1 3
7 . 6 0
1 0
1 5
5 0 . 5 0
0 . 0 2 0
8 . 2 0
1 7
2 3
5 0 . 8 5
0 . 0 2 7
3 . 2 0
4
5
5 0 . 2 0
0 . 0 1 4
9 4 . 2 0
1 1
1 6
5 0 . 5 5
0 . 0 2 1
3 . 5 0
1 8
2 4
5 0 . 9 0
0 . 0 2 8
8 . 7 0
5
7
5 0 . 2 5
0 . 0 1 5
2 2 . 8 0
1 2
1 7
5 0 . 6 0
0 . 0 2 2
9 . 0 0
1 9
2 6
5 0 . 9 5
0 . 0 2 9
3 . 5 0
6
8
5 0 . 3 0
0 . 0 1 6
3 0 . 0 0
1 3
1 8
5 0 . 6 5
0 . 0 2 3
3 . 2 0
2 0
2 9
5 1
0 . 0 3 0
2 . 4 0
7
1 0
5 0 . 3 5
0 . 0 1 7
5 . 8 0
1 4
1 9
5 0 . 7 0
0 . 0 2 4
9 . 5 0
2 1
3 0
5 1 . 0 5
0 . 0 3 1
1 0 . 6
Σ
2 8 3 . 4
M. BAGHAYIPOUR AND A. A. FOROUD1350
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
17/30
the other producers’ coef cients in either cases to be unchanged. Hence, the applied two sets for
all producers are namely the default set of the generation cost function coef cients (listed in
Table III) and a new set available in Table V. The applied generation capacities for both the cases
are the same as the default set presented in Table III. According to the proposed algorithm, each
case may result in distinct sets of the best transmission and generation capacities (RTN and
RGC). However, because the two considered sets of the generation cost function coef cients
are completely symmetrical, the resulted RTNs in both cases are the same, which is scheduled
in Table VI. In addition, Tables VII and VIII respectively contain the resulted RGCs for the
two systems, namely the default generation cost function coef cients and the new coef cientsof Table V. In both cases, the RTN is calculated using the bi-level optimization problem of
Equations (25) and (26) and supposing the presented (default or new) generation cost function
coef cients and the default generation capacities (according to Table III), whereas the RGC is
Table III. Default generation cost function coef cients as well as default generation capacities in thesystem.
Generation unit # 1 2 3 4 5 6 7
Bus # 1 2 2 5 8 11 13a 0.038432 0.01 0.01 0.01 0.01 0.01 0.01b 20 20 10 40 40 40 40
QGxup 360.2 140 100 100 100 100 100
Table IV. Default transmission schedule including two ending nodes, lengths, default capacities, and re-quired investment costs of the transmission lines in the system. The zero lengths correspond to the trans-
former branches, of which their investment costs are only in proportion to their capacities.
From bus
Tobus
Length(km)
Capacity(MW)
Investment cost ($/h)
From bus
Tobus
Length(km)
Capacity(MW)
Investment cost ($/h)
1 2 112 114.38 51.18 15 18 62 6.41 1.591 3 156 57.21 35.66 18 19 44 3.21 0.562 4 182 28.51 20.73 19 20 26 6.31 0.663 4 59 54.81 12.92 10 20 88 8.51 2.99
2 5 322 64.06 82.42 10 17 71 4.62 1.312 6 320 40.27 51.49 10 21 71 15.90 4.514 6 149 51.86 30.87 10 22 68 7.70 2.095 7 49 18.87 3.69 21 22 35 1.62 0.236 7 45 41.67 7.49 15 23 72 5.76 1.666 8 0 12.85 0.37 22 24 73 6.09 1.786 9 0 12.02 0.34 23 24 77 2.56 0.796 10 42 10.78 1.81 24 25 37 0.09 0.019 11 0 19.72 0.56 25 26 73 3.51 1.029 10 0 31.72 0.91 25 27 54 3.59 0.774 12 28 23.87 2.67 28 27 0 16.59 0.4712 13 0 21.79 0.62 27 29 48 6.07 1.1612 14 97 8.03 3.11 27 30 110 6.95 3.0512 15 86 18.54 6.37 29 30 90 3.67 1.3212 16 60 7.90 1.89 8 28 252 1.76 1.77
14 15 64 1.83 0.47 6 28 248 14.84 14.7016 17 58 4.40 1.02 Σ 359.06
Table V. A new set of generation cost function coef cients in the system.
Generation unit # 1 2 3 4 5 6 7
a 0.038432 0.01 0.01 0.01 0.01 0.01 0.01b 20 10 20 40 40 40 40
A NEW MARKET CLEARING MECHANISM 1351
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
18/30
T a b l e V I . T h e r e f e r e n c e t r a n s m i s s i o n n e t w o r k t h a t r e s u l t e d i n t h e c a s e o f t h e d e f a u l t g e n e r a t i o n c o s t f u n c t i o n c o e f c i e n t s a n d g e n e r a t i o n c a p a c i t i e s i n t h e s y s t e m .
F r o m
b u s
T o b u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
F r o m b u s
T o
b
u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
F r o m b u s
T o b u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
1
2
7 . 5 0
3 . 3 6
4
1 2
4 2 . 5 6
4 . 7 6
2 1
2 2
4 . 1 3
0 . 5 8
1
3
5 0 . 9 0
3 1 . 7 3
1 2
1 3
2 . 0 0
0 . 0 6
1 5
2 3
5 . 8 5
1 . 6 8
2
4
6 0 . 4 8
4 3 . 9 8
1 2
1 4
9 . 3 5
3 . 6 3
2 2
2 4
7 . 2 1
2 . 1 0
3
4
4 8 . 5 0
1 1 . 4 3
1 2
1 5
1 8 . 2 0
6 . 2 5
2 3
2 4
2 . 6 5
0 . 8 2
2
5
8 5 . 3 5
1 0 9 . 8 1
1 2
1 6
7 . 8 1
1 . 8 7
2 4
2 5
4 . 8 4
0 . 7 2
2
6
7 2 . 9 6
9 3 . 2 9
1 4
1 5
3 . 1 5
0 . 8 1
2 5
2 6
5 . 5 0
1 . 6 0
4
6
5 8 . 8 3
3 5 . 0 2
1 6
1 7
4 . 3 1
1 . 0 0
2 5
2 7
8 . 3 4
1 . 8 0
5
7
1 2 . 8 5
2 . 5 2
1 5
1 8
7 . 3 0
1 . 8 1
2 8
2 7
2 1 . 3 4
0 . 6 1
6
7
3 5 . 6 5
6 . 4 1
1 8
1 9
4 . 1 0
0 . 7 2
2 7
2 9
8 . 0 6
1 . 5 5
6
8
3 1 . 6 6
0 . 9 0
1 9
2 0
9 . 4 0
0 . 9 8
2 7
3 0
8 . 9 4
3 . 9 3
6
9
3 0 . 5 0
0 . 8 7
1 0
2 0
1 1 . 6 0
4 . 0 8
2 9
3 0
5 . 6 6
2 . 0 4
6
1 0
1 8 . 3 0
3 . 0 7
1 0
1 7
8 . 6 9
2 . 4 7
8
2 8
2 . 3 4
2 . 3 5
9
1 1
2 . 0 0
0 . 0 6
1 0
2 1
1 7 . 3 7
4 . 9 3
6
2 8
2 1 . 6 8
2 1 . 4 8
9
1 0
3 0 . 5 0
0 . 8 7
1 0
2 2
9 . 3 4
2 . 5 4
Σ
4 2 0 . 4 5
M. BAGHAYIPOUR AND A. A. FOROUD1352
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
19/30
calculated supposing the presented generation cost function coef cients as well as the default
transmission capacities (according to Table IV).
(2) Furthermore, in order to further illustrate the capability of the proposed mechanism in rationally appor-
tioning the total social welfare among the main three participant entities, one additional case namely
the one containing the default generation cost function coef cients (as in Table III) with a new set
of generation capacities, listed in Table IX, is also analyzed. Then, this case is compared with the
previously analyzed case of the default generation cost function coef cients and generation capacities,
from the viewpoint of the bulk generation prot, to demonstrate the resulted positive long-term invest-
ment signals in the generation planning processes. In the recent new case, the RTN and RGC are
respectively obtained supposing the new set of generation capacities and the default transmission ca-
pacities.It is obvious that the RGC does not change from that of the previous default system, presented
in Table VII, whereas the new resulted RTN can be completely different, as scheduled in Table X.
(3) The nal analyzed case is the case with the default generation cost function coef cients and generation
capacities but with the present transmission line capacities equal to those resulted as the RTN in sim-
ilar condition. It is obvious that, in this case, the RTN is the same as the present transmission network,
whereas the RGC should again be recalculated, as displayed in Table XI. The resulted bulk Transco’s
prot can be compared with that of the similar case with default transmission line capacities, in order that its resulted positive long-term investment signals in the TEP processes can be demonstrated.
In brief, according to the aforementioned remarks, the systems under analysis here can be summa-
rized as follows:
(1) the system with the default generation cost function coef cients and generation capacities
(Table III), as well as the default transmission capacities (Table IV);
(2) the system with the new generation cost function coef cients (Table V) and the default generation
capacities (Table III), as well as the default transmission capacities (Table IV);
(3) the system with the default generation cost function coef cients (Table III) and the new generation
capacities (Table IX), as well as the default transmission capacities (Table IV); and
(4) the system with the default generation cost function coef cients and generation capacities
(Table III) but with the best possible transmission capacities (i.e., RTN in Table VI).Here, two different kinds of analysis on the numerical results obtained from the aforementioned four
systems, including the analyses on the monetary quantities for both the bulk participant entities and
their individuals, are presented as follows.
Table VII. The resulted reference generation capacities as well as current generation levels in the system with the default generation cost functions coef cients and default transmission line capacities.
Generation unit # 1 2 3 4 5 6 7
QG,RGC,xUp 169.96 0.00 40.97 11.98 19.00 19.70 21.79
QGx 169.96 0.00 40.97 11.98 19.00 19.70 21.79
Table VIII. The resulted reference generation capacities as well as current generation levels in the system with the new generation cost functions coef cients and default transmission line capacities.
Generation unit # 1 2 3 4 5 6 7
QG,RGC,xUp 169.96 40.97 0.00 11.98 19.00 19.70 21.79
QGx 169.96 40.97 0.00 11.98 19.00 19.70 21.79
Table IX. The new applied set of generation capacities in the system.
Generation unit # 1 2 3 4 5 6 7
QGxup 200 20 20 100 100 100 100
A NEW MARKET CLEARING MECHANISM 1353
Copyright © 2012 John Wiley & Sons, Ltd. Int. Trans. Electr. Energ. Syst. 2013; 23:1335–1364
DOI: 10.1002/etep
-
8/18/2019 Transmission Pricing 38
20/30
T a b l e X . T h e r e f e r e n c e t r a n s m i s s i o n n e t w o r k t h a t r e s u l t e d i n t h e s y s t e
m w i t h t h e d e f a u l t g e n e r a t i o n c o s t f u n c t i o n c o e f c i e n t s a n d n e w g e n e r a t i o n c
a p a c i t i e s ( T a b l e I X ) .
F r o m
b u s
T o b u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
F r o m b u s
T o
b
u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
F r o m b u s
T o b u s
C a p a c i t y
( M W )
I n v e s t m e n t c o s t
( $ / h )
1
2
1 3 0 . 8 8
5 8 . 5 7
4
1 2
4 0 . 8 4
4 . 5 7
2 1
2 2
3 . 9 8
0 . 5 6
1
3
7 1 . 9 8
4 4 . 8 6
1 2
1 3
1 0 . 7 3
0 . 3 1
1 5
2 3
5 . 7 6
1 . 6 6
2
4
4 0 . 1 2
2 9 . �