Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking...

68
Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference

Transcript of Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking...

Page 1: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Lines

August 20-22, 2014

Vail, CO

2014 Transmission & Distribution BenchmarkingInsights Conference

Page 2: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Agenda

◼ Introduction◼ Statistics and System Activity◼ Financial◼ Initiatives and Practices

Picture source: www.energy.gov

2

Page 3: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key benchmarking Issues in Transmission

◼ Transmission Systems are unique and designed to serve a particular geography, customer base, and other generation source and load constraints.

◼ Costs are particularly uneven over time, so really need to be evaluated on a longer time horizon.

◼ FERC capital additions do not reflect actual spending because of CWIP; Activity –based costs provide a more realistic spending level as well as the purpose of expenditures.

◼ There is no agreement on cost normalization; asset base is the best predictor, but circuit miles, structure miles, MWh transmitted, MW-miles can be used to “triangulate” your performance.

◼ Reliability is based primarily on “availability”, but also on contribution to ”End use” Customer reliability.

Regulatory◼ NERC regulations; other Regulatory bodies◼ NERC compliance audits◼ NERC performance standards (TADS)

System Challenges◼ Distributed Generation◼ Interconnections (e.g. Windmill Farms)◼ Aging infrastructure◼ New transmission corridors◼ ROW management under increasing

regulations and restrictions◼ Capacity Constraints◼ Transfer Capability Crisis (mitigated by the

recession)◼ Intelligent Grid (or more intelligent Grid)◼ Upgrading EMS systems◼ Equipment lead times

Organizational Challenges◼ Aging Workforce -- Brain Drain◼ Contractor Management◼ Cross-silo prioritization and involvement in

projects

Industry Methodology

2014:• Cyber security• Physical security• FERC politicization

3

Page 4: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Line Spending

We saw increase in spending in 2013 . . .

4

Page 5: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

5

Total Transmission Capital Additions: US Utilities

Total market size for the US for the last 7 years has grown consistently, following a drop off during the recession. Only a portion of this will be for labor costs since some portion will be for materials.

This is total US utility population – FERC Capital Additions. Capital additions represents capital spending that closed to the books and became part of the asset base in the given year.

Page 6: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2014 T&D: Capital Projects

CAPITAL PROJECT SPENDING PER ASSET NEXT 3 YEARS - TRANSMISSION

Mean Quartile

Mean 39 %

Comments

Calculation used

( CP125.1A ) / ( TF65.1 ) * 100 , ( CP125.2A ) / ( TF65.1 ) *

100 , ( CP125.3A ) / ( TF65.1 ) * 100

Page 6

Page 7: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Statisticsand

System Activity

Landsnet – National Grid, Iceland

7

Page 8: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission versus Distribution

◼ For purposes of this survey, we define distribution to be a voltage level of 45kV and below. The distinction is somewhat arbitrary, but picks a point between 69kv which is generally considered a transmission (or at least sub-transmission) level and 21kV which would generally be considered distribution.

◼ It is unrealistic to ask utilities to redefine their cost or reliability reporting on the basis of these definitions. However, a utility that has very different definitions may want to restate these statistics to better compare their performance.

Distribution Voltage Classes◼ 5kV class (>1kV, <=9kV)◼ 15kV class (>9kV, <=15kV) ◼ 25kV class (>15kV to <=26kV) ◼ 35kV class (>26kV to <=36kV) ◼ 44kV class (>36kV to <=44kV)

Transmission classes >=45kV ◼ <69kV class (>=45kV <69kV)◼ 69kV class (>=69kV <100kV) ◼ 100kV class (>=100kV <200kV) ◼ 200kV Class (>=200kV <300kV) ◼ 300kV Class (>=300 kV <400 kV) ◼ 400kV and above

8

Page 9: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Lines Demographic Profile

Min Mean Max # of BarsService Territory

Wage Rate: Transmission Journey Level Line Worker $35.30 $39.30 $42.15 9Transmission Staffing: FTEs per $100M Transmission Assets 0.00 9.84 23.72 11ROW Miles Managed per Structure Mile 0% 69% 144% 13Line work done while the line is energized: Transmission 0% 22% 100% 14

System - DemographicsTransmission Structure mile per Transmission Circuit 0.00 12.73 38.02 13Transmission Voltages on system by circuit

<69kV 0.0% 5.5% 39.6% 1569kV 0.0% 17.8% 79.4% 15100kV class 8.2% 51.9% 93.8% 15200kV Class 0.0% 13.5% 54.9% 15300kV Class 0.0% 8.4% 37.0% 15400kV and above 0.0% 2.8% 9.8% 15

Transmission structures on systemWood poles 0% 46% 97% 15Steel poles 0% 19% 84% 15Concrete poles 0% 1% 15% 15Steel lattice towers 0.% 34% 90% 15

Financial - DemographicsTransmission Line Assets per Circuit Mile $49,469 $231,977 $487,340 13

Page 10: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TYPES OF TRANSMISSION STRUCTURES ON SYSTEM

Calculation used

ST150.1 / ( ST150.1 + ST150.2 + ST150.3 + ST150.4 ) *

100 , ST150.2 / ( ST150.1 + ST150.2 + ST150.3 + ST150.4 )

* 100 , ST150.3 / ( ST150.1 + ST150.2 + ST150.3 +

ST150.4 ) * 100 , ST150.4 / ( ST150.1 + ST150.2 + ST150.3

+ ST150.4 ) * 100

ST p28

10

Page 11: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TRANSMISSION VOLTAGES ON SYSTEM BY OH CIRCUIT

Calculation used

ST120.3C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.4C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100 ,

ST120.5C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.1C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100 ,

ST120.2C / ( ST120.1C + ST120.2C + ST120.3C + ST120.4C +

ST120.5C + ST120.6C ) * 100 , ST120.6C / ( ST120.1C +

ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C ) * 100

ST p29

11

Page 12: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TRANSMISSION CIRCUIT MILES PER TRANSMISSION CIRCUIT

Calculation used

(ST120|5_Trans OH & UG Circ Mile v.13) / ( ST120.1C + ST120.2C

+ ST120.3C + ST120.4C + ST120.5C + ST120.6C )

ST p30

12

Page 13: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TRANSMISSION LINES PLANT IN SERVICE PER CIRCUIT MILE

Calculation used

TF65.1 / (ST120_Trans Circ Mile 09)

Mean $188,795

Quartile 1 $129,110

Quartile 2: $213,938

Quartile 3: $244,047

ST p39

13

Page 14: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2014 T&D: System Activity

\

NEW TRANSMISSION CIRCUIT MILES

Mean Quartile

Mean 0.84 %

Comments

Calculation used

SA55.1 / (ST120_Trans Circ Mile 09) * 100

Page 14

Page 15: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Financial – Overview of the Cost Model

Working with an adjusted FERC model

Conceptual transmission tower design by Choi Shine Architects15

Page 16: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2013YE 2012YE

Mean Q1 Q2 Q3# of Bars

Mean Q1 Q2 Q3# of Bars

O&M Cost                    

Transmission Lines O&M Expense per Circuit Mile

$15,565 $3,839 $6,288 $9,414 14 $8,992 $3,067 $6,868 $11,593 16

Transmission Line O&M per MWh transmitted $0.75 $0.32 $0.47 $0.87 14 $0.63 $0.33 $0.51 $0.67 15

Transmission Line O&M per Total Trans Assets

4.33% 2.08% 3.12% 4.03% 14 2.98% 1.98% 2.43% 4.02% 15

Investment Rate                    

Transmission Line Capital Spending less New Lines per Asset [Activity Based]

11.89% 11.54% 7.78% 2.94% 12 7.11% 8.05% 4.27% 3.24% 14

Transmission line Cost Profile

16

Median investment rate is high compared to last year

Page 17: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Substations

General Plant FERC Costs

Transmission

Capital

Trans Lines

Exclusions

Trans Substations

O&M

Trans Lines

Exclusions

Trans Substations

Distribution

Capital

Dist Lines

Exclusions

Dist Substations

O&M

Dist Lines

Exclusions

Dist Substations

A&G

FERC: The ADJUSTED FERC COST MODEL

FERC provides a general framework Certain costs must be excluded to provide fair comparisons that focus on operations Substation costs must be separated out, including certain allocations

17

Page 18: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

FERC: Specific Adjustments

◼ The following page is a schematic of how basic FERC cost data will be adjusted for this benchmarking study. A&G costs will be excluded – Utilities are asked to adjust their costs to exclude costs typically

reported as A&G (e.g. pensions and benefits) from their O&M data. General plant costs will be excluded – Utilities are asked to adjust their costs to exclude costs

typically reported as General Plant (e.g. IT/Communications infrastructure) from their T&D Capital data.

Other T&D Capital exclusions:• Transmission: Land acquisitions and extraordinary items• Distribution: Land acquisitions, street lighting and extraordinary items

Other O&M exclusions:• Transmission: Wheeling, Rents/Leases, IT costs, extraordinary items. If you charge IT

support to account 569, you should exclude it. Regional Market Expenses (Accts 575, 576).• Distribution: Streetlight Maintenance, Rents/Leases, IT costs, extraordinary items. If you

charge IT support to Distribution O&M accounts, you should exclude it.• If you normally charge R&D, such as EPRI dues, to O&M, include it, unless it is an unusually

large amount for this year Substation costs will be allocated from Transmission and Distribution accounts, and similar

adjustments made. ◼ The goal of the exclusions is to provide a fairer comparison of T&D operational performance, by

excluding certain costs that relate to demographic differences not under the control of T&D management.

18

Page 19: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

DV| % OF FERC - TRANSMISSION LINE CAPITAL

Calculation used

( TF5.6 ) / TF5.1 * 100 , TF5.2 / TF5.1 * 100 , TF5.3 / TF5.1 *

100 , TF5.4 / TF5.1 * 100 , TF5.5 / TF5.1 * 100

Mean 96 %

Quartile 1 100 %

Quartile 2: 100 %

Quartile 3: 100 %

TF p32

Very few adjustments to Capital Additions (FERC) beyond Substation allocations . . .

19

Page 20: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TRANSMISSION LINE O&M & CAPITAL PER ASSET [FERC]

Calculation used

(TF20_Trans Lines O&M FERC) / TF65.1 * 100 , (TF5_Trans

Lines Capital FERC) / TF65.1 * 100

TF p2

20

Page 21: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

DV| % OF FERC - TRANSMISSION LINE O&M EXPENSE

Comments

Calculation used

TF20.8 / TF20.1 * 100 , TF20.2 / TF20.1 * 100 , TF20.3 / TF20.1 *

100 , TF20.4 / TF20.1 * 100 , TF20.5 / TF20.1 * 100 , TF20.6 /

TF20.1

* 100 , TF20.7 / TF20.1 * 100

TF p33

Wheeling Expense and Revenue is not included. The O&M cost is a measure of operational efficiency, not economic efficiency.

21

Page 22: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

FINANCIAL COSTS ADJUSTMENTS - TRANSMISSION O&M

Comments

Calculation used

TF20.8 / TF20.1 * 100 , TF20.2 / TF20.1 * 100 , ( TF20.3 + TF20.4

+ TF20.5 + TF20.6 + TF20.7 ) / TF20.1 * 100

TF p34

22

Page 23: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Financial – Overview of the activity-based

Cost Model

Photo source: Scientific American23

Page 24: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Develop Network Strategy

Develop and Approve Asset Plans

Project/Portfolio Management

A Process Model for Managing the Network

Expand Network

Operate Network

Sustain Network

Add New Customers

Respond to Emergencies

24

Page 25: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

ACTIVITY-BASED Cost Model

While FERC has the benefit of being a uniform system of accounts, there are several important shortcomings:

•FERC capital spending lags behind actual spending; costs for large projects go into a Construction Work in Progress (CWIP) account and are not transferred until the assets are placed into service, sometimes a several year lag. •FERC capital accounts generally follow plant accounts and units of property (e.g. poles, towers, and fixtures) – not the typical reasons why utilities spend (e.g. new business)•FERC O&M accounts tend to be more activity-oriented, but do not necessarily track important categories (e.g. vegetation management)

For those reasons, a simplified Activity-Based Costing system was developed to get current year spending by activity. The following diagram depicts the Activity-Based approach

25

Page 26: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Activity-Based Cost Model

Activity-Based Costs

Transmission Lines Transmission Subs Distribution Subs Distribution Lines

Transmission Line Capital• Serve New• Expand• Sustain• Other • CIAC

T&D Substation Capital• Serve New• Expand• Sustain• Other• CIAC

Distribution Line O&M• Sustain• Other

T&D Substation O&M• Sustain the Network• Operate the Network• Other

Transmission Line O&M• Sustain the Network• Operate the Network

Distribution Line Capital• Serve New• Expand• Sustain• Other • CIAC

The activity-based cost model breaks the expenditures into capital and O&M, and then splits them into the activities shown on the process model introduced above. The following 3 pages provide more details of the individual activities for Transmission, Substations, and Distribution.

2014 Data Collection Guide

26

Page 27: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Activity Based Costs – Transmission Lines

While capital expenditures are split among several different processes from the overall process model, O&M expenses are almost entirely associated with sustaining the network.

Transmission Line Capital• Serve New: Extension to new customers

or utility substations [Industrial/Generation/Wholesale]

• Expand: Capacity Additions (Adding additional lines to existing substations, increasing capacity of existing lines)

• Sustain: Replace/Repair in kind• Sustain: system improvements

(reliability/efficiency)• Sustain: Service Restoration• Sustain: Line Relocations• Sustain: Transmission Operations Center• Sustain: Asset Retirement Costs for

Transmission Plant (FERC 359.1) • Other • CIAC

Transmission Line O&M• Inspection and Maintenance

Expense (except 569.1-4)• ROW/Vegetation Management • Service Restoration• Transmission Operations Center• Engineering/Design O&M

(including FERC 561.5-8)• Other

2014 Data Collection Guide

27

Page 28: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Line: Replacement Capital Spending

 Spending Category

2010YEQ2

2011YEQ2

2012YEQ2

2013YEQ2

Total Capital Spending 5.3% 5.3% 6.6% 9.0%

Less Serve New 0.6% 0.6% 1.0% 1.1%

Subtotal Cap Add & Sustain 4.7% 4.7% 5.6% 7.8%

Less Capacity Adds 2.0% 1.9% 3.4% 4.9%

Subtotal: Sustain 2.8% 2.8% 2.2% 2.9%

28

2013 saw a relatively high rate of total capital spending …

Page 29: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

29

TRANSMISSION LINE CAPITAL SPENDING PER ASSET [ACTIVITY-BASED] [V.14]

Calculation used

TF45.1 / TF65.1 * 100 , TF45.2 / TF65.1 * 100 , TF45.3 /

TF65.1 * 100 , TF45.1 / TF65.1 * 100 , TF45.4 / TF65.1 *

100 , TF45.5 / TF65.1

* 100 , TF45.6 / TF65.1 * 100 , TF45.1 / TF65.1 ,

TF45.7 / TF65.1 * 100

TF p11

Page 30: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

TRANSMISSION LINE CAPITAL SPENDING SUSTAIN- EX SERVE NEW, EXPAND PER ASSET [ACTIVITY-BASED] [V.14]

• #31 has very high TOC capital activity cost

• See change in title to refer to “Sustain”

Comments

Calculation used

TF45.1 / TF45.1 / 1000000 , TF45.2 / TF45.2 / 1000000 , TF45.3

/ TF65.1 * 100 , TF45.1 / TF65.1 * 100 , TF45.4 / TF65.1 * 100 ,

TF45.5 / TF65.1 * 100 , TF45.6 / TF65.1 * 100 , TF45.1 / TF65.1

, TF45.7 / TF65.1 * 100

TF p13

30

Page 31: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

OTHER ACTIVITY BASED COSTS: TRANSMISSION LINE CAPITAL SPENDING

Calculation used

TF46.1

31

ID Response22 Back Office expenses31 Capital Tools, R&D, Premise Equipment, Facilities28 N/A33 Tools and Equipment23 NA38 Environmental/Legislative/Regulatory24 Not applicable21 n/a30 Under line relocations, reimbursements exceeded costs in 201327 n/a32 Not applicable

Page 32: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2014 T&D: Transmission Financials

TRANSMISSION LINE O&M EXPENSE PER ASSETS [ACTIVITY-BASED] [V.14]

Comments

Calculation used

TF55.1 / TF65.1 * 100 , TF55.1 / TF65.1 * 100 , TF55.2 / TF65.1 *

100 , TF55.4 / TF65.1 * 100 , TF55.5 / TF65.1 * 100 , TF55.1 /

TF65.1

* 100 , TF55.6 / TF65.1 * 100

Page 32

Mean Quartile

Mean 3.04 %

Quartile 1 1.86 %

Quartile 2: 2.58 %

Quartile 3: 4.19 %

#359 has reporting anomalies

Comments

Page 33: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

OTHER ACTIVITY BASED COSTS: TRANSMISSION LINE O&M

CommentsCalculation used

TF56.1

TF p23

33

ID Response31 Management/Admin, R&D28 Planning and Operating Costs that are not directly charged to the work

programs above33 miscellaneous transmission expenses FF123 NA38 na40 Misc transmission expense net of O&M Substation included in Pension &

Benefits24 not applicable21 Transmission support30 N/A27 NERC Training359 Internal building rents32 Studies, compliance

Page 34: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

CWIP AS A % OF CAPITAL EXPENDITURES - TRANSMISSION LINE

#32 very low CWIP#28 very high CWIP

Comments

Calculation used

TF80.1 / TF5.6 * 100

TF p24

34

Page 35: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Expense/Miles Managed (TF p27)

Expense/Mile Trimmed (TF p30)

Expense/Acre Managed (TF p28)

Q2

201

2 (N

=5)

Expense/Acre Trimmed (TF 29)

10x 5x

Vegetation Management

35

Page 36: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2014 T&D: Transmission Financials

FERC VS ACTIVITY SPENDING: TRANSMISSION LINE O&M PER ASSET [V.14]

Comments

Calculation used

TF20.8 / TF65.1 * 100 , (TF55_ABC Trans Line O&M v.14) / TF65.1

* 100

Page 36

Page 37: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

2014 T&D: Transmission Financials

FERC VS ACTIVITY SPENDING: TRANSMISSION LINE CAPITAL PER ASSET [V.14]

Comments

Calculation used

TF5.6 / TF65.1 * 100 , (TF45_Trans Line Cap ABC v.14) / TF65.1

* 100

Page 37

Page 38: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission LinePractices and initiatives

Page 39: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Things I would like to know about transmission?

 The drivers of work◼ How much are companies spending?◼ On what activities?◼ What is driving spending? ◼ Role of Interconnections? ◼ Regional differences?◼ How do designs influence cost?◼ How are companies overcoming community resistance or NIMBY?◼ What is the response to the terrorist threat?◼ What does NERC/FERC require?

Organizing to do “new” and “expand” work◼ How are companies organizing to meet workload?◼ How are companies managing projects?◼ What are the challenges in contracting?◼ Where do companies get the skilled labor?◼ How are companies organizing to meeting regulatory requirements?

Organizing to do the “sustain” work◼ What are the challenges in ROW and vegetation management?◼ How are companies dealing with maintenance, especially wood pole replacement?◼ How are companies dealing with relocations?

 

 39

Related consulting studies:• Project level benchmarking• Project management best

practices• Construction Competiveness

Page 40: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Develop Network Strategy

Develop and Approve Asset Plans

Project/Portfolio Management

A Process Model for Managing the Network

Expand Network

Operate Network

Sustain Network

Add New Customers

Respond to Emergencies

40

Developing Regulatory Strategy regarding transmision operations is increasingly important

Page 41: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Line Practices/initiatives

2013 Sections◼ Asset Management -- Role of Asset Management,

replacement programs, and problematic equipment◼ Planning/Engineering/Design –Improvement

initiatives and changes to standards ◼ T-line Field Activities – Initiatives underway and

maintenance approaches◼ Work management systems – WMS Vendor and

efforts to improve usefulness◼ Contractor Productivity – Challenges, measures

and initiatives◼ Transmission Operations Center (TOC) – Changes

and challenges.◼ Right of Way –Growth inhibitors, ROW uses,

challenges and practices.◼ Transmission Automation – Technology initiatives

underway◼ NERC Standards – Impact of NERC standards on

transmission organizations, especially Critical Infrastructure Protection (CIP), Protection and Control (PRC), and Facilities Design (FAC).

◼ Maintenance – Inspections, impact of deferred maintenance, initiatives to reduce outages

2014 Sections (by process)◼ Strategy

Regulatory Strategy (including NERC compliance)

Operational Strategy (including Transmission Planning and Automation)

◼ Asset Management ◼ Capital project and program

management◼ Transmission Operations Center (TOC)◼ Sustain Activity and Respond to

Emergencies (Maintenance, including ROW)

◼ New Customers and Expand Activity (including Engineering/Design, New customers T-line Field Construction Activities

(including WMS and Contractor Productivity)

41

Page 42: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

“Under Mr. Bay, the Office of Enforcement has also focused on the reliability arena. For example, the Office of Enforcement has launched investigations, at times contemporaneous with investigations led by the North American Electric Reliability Corporation (NERC) and other regulators, into various weather-related blackouts, including the October 2011 snowstorm in the Northeast and, earlier that year, outages in the Southwest. In testimony before the Senate Committee on Energy and Natural Resources regarding the October 2011 outages, Mr. Bay stated, “there is room for improvement” in utilities’ “vegetation management and other practices to reduce transmission outages during snowstorms and similar weather events.”6 Thus, the physical security of the grid may well be another top priority if Mr. Bay is confirmed. A natural corollary to physical security of the grid is cybersecurity of the grid, which would likely be another area of focus for Mr. Bay—especially since the Obama Administration has made it an executive priority in recent years”

Page 43: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

FERC ORDER 1000

“Order 1000 is as complicated as many of the other rules FERC has finalized and published over its history, many of which foil all but specialists. But at its heart it deals with the simple issue of whether states can be forced to coordinate on transmission planning and meeting cost obligations for new electricity transmission capacity. The order, which is now at the mercy of pending and still nascent court filings, says that states can be compelled.”

43

Final Briefing on Final Rule on Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities Briefing on Order No 1000”• Order No. 888 in 1996 Requires open access to transmission facilities to address undue

discrimination and to bring more efficient, lower cost power to the Nation's electricity consumers

• Order No. 890 in 2007Requires coordinated, open and transparent regional transmission planning processes to address undue discrimination

• Order No. 1000 in 2011• Requires transmission planning at the regional level to consider and evaluate possible

transmission alternatives and produce a regional transmission plan• Requires the cost of transmission solutions chosen to meet regional transmission needs

to be allocated fairly to beneficiaries

Page 44: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

FERC ORDER 791

44

Page 45: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

FERC ORDER 745

“Demand response was dealt a blow on Friday when the U.S. Court of Appeals in Washington, D.C. vacated the Federal Energy Regulatory Commission’s Order 745 in a 2-1 decision, stating that FERC has gone too far.

FERC’s Order 745, approved in 2012, calls for grid operators to pay the full market price, known as the locational marginal price, to economic demand response resources in real-time and day-ahead markets as long as dispatching DR is cost-effective. The ruling found that FERC overstepped its jurisdiction and that the decision of payments should lie with states.

“In Order 745, however, FERC went far beyond removing barriers to demand response resources. Instead of simply 'removing barriers,' the rule draws demand response resources into the market and then dictates the compensation providers of such resources must receive,” Judge Janice Rogers Brown wrote in the majority opinion.

45

http://www.greentechmedia.com/articles/read/what-us-appeals-court-decision-on-ferc-order-745-means-for-demand-response

Page 46: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

NERC Compliance

Benchmarking Practices and Initiatives

Page 47: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors: NERC Compliance

Develop Strategy

Organize for Success

Establish Implementation Plan

Select Performance Metrics

Execute Transition Plans

Reinforce and followup

47

Page 48: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Practice Questions

NERC Compliance• Impact of CIP5 and the change from requirements

to results-based regulation• Handling and structuring audits• Separate NERC audits for Critical Infrastructure

and Reliability Standards• People fully-dedicated to the NERC compliance

organization• Process changes implemented for Critical

Infrastructure Protection [CIP]• Organization and staffing levels for Critical

Infrastructure Protection [CIP]• Process changes implemented for Protection and

Control [PRC]• Organization and staffing levels for Protection and

Control [PRC]• Process changes for Facilities Design,

Connections, and Maintenance [FAC]• Positions added for compliance with [FAC]• Future changes coming that will impact on

transmission organization

2014 Sections (by process)◼ Strategy

Operational Regulatory

◼ Asset Management ◼ Transmission Operations Center (TOC)◼ Maintenance (including ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction Activities

(including WMS and Contractor Productivity

48

Page 49: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

IMPACT OF CIP5 AND THE CHANGE FROM REQUIREMENTS-BASED TO RESULTS-BASED REGULATION

TP165.1

ID Response• 31 On November 22, 2013, FERC issued Order 791 approving CIPv5 with implementation scheduled for April

2016 for High and Medium Impact assets and April 2017 for Low Impact assets. With approval of CIPv5, FERC directed NERC to make several modifications. The modifications are still in development. Full impact of CIPv5 is yet to be determined.

• 28 The result-based regulation enabled us to improve on the management of our centralized data repositories and expectations from the various Stakeholders who produce and/or use these critical data/information.

• 33 Many more assets in scope because of the CIP5 requirements (approximately 200 additional assets)• 37 Changes for CIP5 do not have a finite date of implementation so there has been no impact as yet• 38 To date there has been minimal impact on the transition from CIP V3 to CIP V5. Although the V5 standards

have been approved, NERC is tweaking language in the standards. Over the next year, we will begin the process of identifying BES (Bulk Electric System) Cyber Systems and updating processes/procedures in preparation for the standards to go into effect on April 1, 2016.

• 40 Because the implementation date for CIP Version 5 is still far off, the impact has been relatively small so far.• 21 CIP V5 will have a substantial impact. The extent of which we are still evaluating. We have begun the

transition to V5 and are implementing the necessary controls.• 30 Uncertain at this time• 27 CIP v5 has added additional facilities, monitoring & control, and demonstration of results . We are

meeting these requirements by automating the change control process and spreading out the additional workload.• 359 1) For CIP V5, we have active projects underway in preparation for an April 2016 enforcement date. We are

further along with the existing cyber assets in that we completed our assessments and initiated projects to address the necessary changes. For new cyber assets, we are currently assessing the impacts. 2) Our existing identify, assess and correct programs will effectively address one aspect of the Reliability Assurance Initiative (RAI). As for internal controls, we expect to improve our documentation to more effectively demonstrate our existing controls; as well as do a gap assessment for any new controls.

• 32 CIP Version 5 is not in effect yet; impacts still under evaluation

49

Page 50: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

HANDLING AND STRUCTURING NERC AUDITS

TP170.1

ID Response• 31 Audit timing and scope are determined by the Reliability Entity. In 2012,

Company audits for CIP and other Reliabiity Standards were scheduled by the Reliability Entity at the same time.

• 28 1) Annual Self Certification Audit. Directed by the Utility Commission and managed by WECC. 2) 3 Years NERC Audi. On site audit review of evidence.

• 33 Audits are coordinated by our NERC Compliance Department.• 37 The company has not been audited on CIP as yet• 38 Audits are performed on a 3 year cycle. Evidence for Audit Compliance is

collected annually and stored in a document management system for easy of reference. Subject Matter Experts are prepared for testimony by performing mock interviews ahead of the audit by internal auditors and legal services.

• 40 Operations groups coordinate with the Reliability Compliance Office to write RSAWs (Reliabiiity Standard Audit Worksheets) and gather evidence.

• 21 All NERC related compliance and enforcement activities are handled by the NERC Compliance Group which resides in Regulatory Affairs.

• 30 Audits are managed by an internal compliance organization. • 27 An internal compliance program describes how we handle audits. A coordinator

facilitates all communication between the auditors and the Company. Teams of subject matter experts and standard owners prepare the material for the audit and answer questions posed by auditors during off -site or on-site interviews.

• 32 SME's are assigned and responsible for every standard. SME's work with compliance analysts to ensure standards are met. NERC RSAWs are utilized where available. All evidence is packaged up and submitted by the Compliance Department. Request for information are answered by SMEs.

50*Not certain of what the question is asking, this question is decided by the regulator so the benchmarking of such is irrelevant to some extent. It would identify inconsistencies between regions).

359 Audits are coordinated by a central group (EU Compliance) within the Transmission organization. EU Compliance establishes a project plan/schedule to prepare for the audit. The plan includes gathering evidence; building evidence packages (bookmarked pdf files); coordinating with the regional Auditor on schedule, on -site logistics and data requests; subject matter expert (SME) orientation; audit dry runs for SMEs to practice evidence presentations; and a 3rd party review of evidence.

PPL

Page 51: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

PEOPLE FULLY-DEDICATED TO THE NERC COMPLIANCE ORGANIZATION

TP180.1

ID Response• 31 10• 28 2• 33 3.5 FTEs + many Subject Matter Experts that are part time• 37 4 employees in the Transmission NERC Compliance & Standards Unit and 3 employees in NERC

Compliance & Standards (oversight)• 38 Seven plus one open position.• 40 6• 21 6 FTE's are fully dedicated within Regulatory Affairs.• 30 Compliance, 11 with 5 dedicated to CIP, not including subject matter experts• 27 Legal has 2 FTE's - 1 on CIP and 1 on Reliability; Generation has 2 FTE's, IT currently has 2.5 FTE's that

support the whole company, Engineering has 1 FTE, Operations has no dedicated FTE's but the supervisors spend much of their time as subject matter experts. There are also several areas of the company that have part -time responsibility for CIP: Engineering, Physical Security, IT, System Control& Reliability, Generation.

• 359 4 compliance group resources within the Transmission organization supporting both Legacy (FERC Order 693) and CIP (FERC Order 706) Reliability Standards. Some of the compliance staff responsibilities include: a) owns relationship with Regional Entity (Reliability First), b) provides guidance to SMEs on compliance activities as part of their business processes, c) leads self –certifications, d) coordinate audits, e) coordinate responses (comment and ballot) for new or changing standards and f) manage corrective actions. There are additional corporate services (Information Technologyand Physcial Security) resources that support our programs, which are not in this count.

• 32 3

51

ID# FTEs

Comments

31 10 NA

28 2 NA

33 3.5

Plus many Subject Matter Experts that are part time

37 7 4 employees in the Transmission NERC Compliance & Standards Unit and 3 employees in NERC Compliance & Standards (oversight)

38 7 Plus one open position

40 6 NA

21 6 Fully dedicated within Regulatory Affairs.

30 11 In Compliance group, with 5 dedicated to CIP, not including subject matter experts

27 7.5

Legal has 2 FTE's - 1 on CIP and 1 on Reliability; Generation has 2 FTE's, IT currently has 2.5 FTE's that support the whole company, Engineering has 1 FTE, Operations has no dedicated FTE's but the supervisors spend much of their time as subject matter experts. There are also several areas of the company that have part -time responsibility for CIP: Engineering, Physical Security, IT, System Control& Reliability, Generation.

359 4 4 compliance group resources within the Transmission organization supporting both Legacy (FERC Order 693) and CIP (FERC Order 706) Reliability Standards. Some of the compliance staff responsibilities include: a) owns relationship with Regional Entity (Reliability First), b) provides guidance to SMEs on compliance activities as part of their business processes, c) leads self –certifications, d) coordinate audits, e) coordinate responses (comment and ballot) for new or changing standards and f) manage corrective actions. There are additional corporate services (Information Technology and Physical Security) resources that support our programs, which are not in this count.

32 3 NA

Page 52: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

PROCESS CHANGES THAT HAVE BEEN IMPLEMENTED FOR CRITICAL INFRASTRUCTURE PROTECTION [CIP]

ID Response• 31 Current processes are aligned with current CIP version standards and may be

modified as newly approved CIP version standards become effective.• 28 New/Revised policies, procedures, etc. to meet CIP Requirements as needed.• 33 Many. For each of the 43 requirements of CIP version 3 we have implemented

some form of process change. Using a single standard, CIP-003, as an example, can illustrate the scope of process changes. For other standards even more significant changes had to be made.

• 37 The company established a CIP program that meets the requirements of CIP standards 002 through 009. Protection of Critical Cyber Asset is done through established processes involving Trans Business and IT Services. Equipment is obtained and installed for this purpose and processes to maintain the equipment are in place

• 40 Developed enterprise- wide process document to address all the requirements of the CIP Standards

• 21 Continually enhancing processes and procedures. Monitoring the development of Physical Security Standard CIP- 014.

• 30 Updated processes to improve existing CIP related transmission processes and address the dynamic nature and ever-evolving CIP compliance environment

• 27 All visitors entering a Physical Security Perimeter (PSP) must manually sign in and out and must also be escorted at all times. Company employees who do not have access to a PSP are considered visitors.

• 359 Some recent changes: 1) 24-hour revocation requirement access to NERC CIP assets in preparation for CIP V5. 2) Role-based training fin preparation for CIP V5. 3) Integrated CIP compliance approvals into our automated change management system. 4) Performed our initial assessment of NERC Critical Assets in preparation for CIP V5.

• 32 Implemented policies, programs, procedures, and processes required by CIP Standards. This includes asset and cyber asset identification, physical and cyber security, and cyber incident response, and cyber asset recovery process and procedures.

52

TP185.1

38 Successfully completed NERC audits for both CIP and the reliability standards. The next round of audits is anticipated in 2017 (normal cycle) along with recertification as a TOP that same year due to completion of a new backup control center and upgrade of the EMS system. Over the next two years, we will develop and communicate strategy to successfully complete these audits as well as the implementation of the new version 5 CIP standards. We will also develop and implement processes to mitigate security and financial risks associated with possible violations. Additionally we will create strategy for implementing the new Physical Security standard CIP- 014.

CPS

Page 53: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

PROCESS CHANGES FOR PROTECTION AND CONTROL [PRC]

TP195.1

ID Response• 31 More documentation, Evaluate new relays• 28 Existing documentation updated to include PRC Requirements.• 33 Purchased operational software to help us manage compliance + added staff.• 37 Implementation of Aspen Relay Database, Maximo Work & Asset Management system refinements, general

reliability enhancements to administrative and technical processes in PRC Compliance Programs, Annual Compliance Program reviews and institution of routine auditing of PRC -related compliance evidence (both internally and externally)

• 38 Transport Operations is considering the use of an existing automated software (CASCADE), pending license and form template estimate. There are procedural/process changes that will be implemented for battery testing, PT testing and DCB communication testing. These changes are ongoing.

• 21 Created several new processes and procedures. Continue to implement additional improvements and controls. New systems are also being utilized (Cascade and PowerBase).

• 30 Standardized documentation of transmission line settings, central storage of all e -mail for protection coordination• 27 For the protection standards we have not changed anything other than to indicate that we are in compliance with

the standards. On the maintenance side it is forcing us to be timely and do a better job of tracking our maintenance. Some of the transmission assets were not being maintained regularly and now are. Takes a lot of effort to keep all the records for the maintenance up to date and functioning.

• 359 Some recent changes include: 1) New Protection System and Maintenance Program (PSMP) to align with the most current version of PRC-005. 2) Also, changed our testing methodology from an element by element approach to a scheme -based approach, where a logical group of protection system elements are tested together. This helped improve our testing efficiency and ensure that DC control circuitry is fully tested in an end to end functional test.

• 32 None

53

Page 54: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

PROCESS CHANGES FOR FACILITIES DESIGN, CONNECTIONS, AND MAINTENANCE [FAC]

TP205.1

ID Response• 31 Affirmed commitment to buy America for all trans structure and line components.• 28 Existing documentation updated to include FAC Requirements.• 33 Compliance integrated into SME's daily work to ensure that a strong compliance

effort is maintained.• 38 Continued refinement and documentation of massive physical and cyber security

related projects. Implementation and communication of audit strategy plan, including mock audits with Legal Svcs, Internal Audit and SMEs. Annual review of reliability standard audit worksheets (RSAWs) and mock audits for subject matter experts (SMEs). Implemented a formal procedure for tracking ratings.

• 40 As a NERC registered Transmission Owner, internal documents, maintains, and publishes facility connection requirements to meet NERC Standard FAC -001. These requirements are posted on our website for public access. In 2013, we implemented no material changes to the posted process. We have developed an enterprise- wide Facility Ratings Methodology and implementation process

• 21 Several new processes and procedures. Continually enhancing the rating methodology and documentation.

• 27 Adopted the WECC SOL(System Operating Limit) Methodology by conducting Next Day Studies, attending Bi-weekly outage calls and work on Coordinated Studies with utilities.

• 30 no change in 2013• 32 None• 37 No process changes

54

The wire zone–border zone (WZ/BZ) approach . . is a site explicit way of dividing the ROW width into three distinct management zones from edge to edge: the border zone, thewire zone, and another border zone.

359 Implemented a revised Transmission Vegetation Management Program (TVMP) to use the Wire Zone/Border Zone standards. Established a special project to mitigate Facility Rating anomalies, consistent with the NERC Alert, including an as-build confirmation on ground clearance. 3) Implemented a new Facility Ratings Database / System.

PPL

Page 55: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Wire Zone/Border Zone

55

Page 56: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Impact of FUTURE CHANGES in nerc regulations

TP215.1

ID Response• 31 Increased NERC standards support activities.• 28 None from NERC/WECC compliance perspective.• 33 Besides CIP5, the new CIP-014 physical security

standard. Also, the new GMD standard will have significant impacts.

• 37 FERC Order 1000• 40 NERC's Reliability Assurance Initiative• 21 New and modified version of NERC Standards will have

an impact. Particularly CIP V5/6, PRC, TPL, MOD.• 30 Potential for new transmission line built across/through

territory that may not be owned/operated by us• 27 Continue to be engaged in any Regional Requirements

through WECC to comply with future NERC changes.• 359 New Physical Security Standard (CIP- 014); New GMD

Mitigation (TPL-007); New CIP Version 5 Implementation; Concerns over new regulations that are inconsistent, conflicting or duplicative,specifically as it relates to Cyber and Physical security; 5) Substation Connectivity - This is a project to enhance communications to our substations.

• 32 New Peak RC SOL Methodology; Establishing emergency line ratings, Real-Time Contingency Analysis software

56

38 One of the largest impacts will be implementation of the new Physical Security standard, CIP-014. This implementation will require assessments to determine what facilities are critical and how to protect them. The standard also requires engagement of 3rd parties to review the assessments and make recommendations. Reliability Standards CIP -014, PRC-005, EOP-010 (GMD), TPL- 007 (GMD), and CIP-002 (all new version 5 Standards) will result in increased capital expenditures. One of the largest impacts will be implementation of the new Physical Security standard, CIP-014. This implementation will require assessments to determine what facilities are critical and how CPS Energy will protect them. The standard also requires CPS Energy to engage 3rd parties to review the assesments and make recommendations. Reliability Standards CIP-014, PRC-005, EOP-010 (GMD), TPL -007 (GMD), and CIP-002 (all new version 5 Standards) will result in increased capital expenditures. One of the largest impacts will be implementation of the new Physical Security standard, CIP -014. This implementation will require assessments to determine what facilities are critical and how CPS Energy will protect them. The standard also requires CPS Energy to engage 3rd parties to review the assesments and make recommendations. Reliability Standards CIP -014, PRC-005, EOP-010 (GMD), TPL -007 (GMD), and CIP-002 (all new version 5 Standards) will result in increased capital expenditures.

CPS

Page 57: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors:Transmission Network Planning

Deploy automation strategy; microprocessor relays, cyber security, and digital fault recorders are most frequently addressed Assure NERC compliance; CIPS, protection and control, and FAC are noted as having most impact

Use a comprehensive scheduling and permitting process, with early engagement of stakeholders

Use a well-designed process for getting jobs from planning to delivery, with accurate estimating and effective project management

Have current, comprehensive standards covering many specifics, including use of high temperature conductors

57

Page 58: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

INITIATIVES UNDERTAKEN TO IMPROVE THE PROCESS FOR GETTING A JOB FROM PLANNING TO DELIVERY

TP25.1

ID Response• 28 Assign PM as early as possible on in the process (preliminary

study/feasibility phase). PM walks the client through and eliminate briars and enable quick response.

• 33 PM, hand off meetings between engineering and sub operations, conceptual design meetings and scoping meetings, design signoff procedures

• 23 Trans PM implemented in 2012 provides coordination of the transmission and substation planning, engineering and construction activities. Continued on a two year planning cycle.

• 37 Transmission Planning is been working with PM to improve processes of developing preliminary estimates

• 38 'We have revised our activity management project process and have• 40 Use process flowchart, in house training on design and construction• 21 'The following steps have been added, reviewed, and updated to ensure

T&S projects are completed on schedule, on budget, safely, and with the desired degree of quality:

• 30 none• 27 We conduct annual captial budget studies to determine which projects

are to be recommended for inclusion in the 5 Year Capital Budget. Transmission Planning is striving to have recommendations communicated by May 2nd.

• 359 P3 process - this is a new group that takes a conceptional design, evaluates alternatives, developes estimated costs, and turns the design into a 'real project' that can be given to PM.

• 32 Now requiring Project Portfolios and 30% design completed prior to budget approval

58

31 The company submits future projects that have been approved by leadership to the Transmission Projects Information Tracking (TPIT) list maintained by ERCOT. The TPIT list communicates future projects to ERCOT market participants, indicates whether they are included in the ERCOT planning models, and is updated three times per year. The company's Substation Engineering and Transmission Engineering groups update the expected energization dates and project costs. Transmission Planning consolidates this information and submits the updates to ERCOT. After the completion of this ERCOT list, Transmission Planning updates an internal Transmission Planning Sponsored Projects Status report. This list contains all of the projects shown in the TPIT list as well as budgeted projects that have yet to attain an approved for construction status. These two lists help Transmssion Planning communicate to the other company's groups as to the status of projects and ensures that the information Transmission Planning communicates to ERCOT market participants has been vetted through the company's management.

Centerpoint

Page 59: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

PRACTICES OR PROCESSES AROUND PERMITS AND CERTIFICATIONS THAT MAKE PLANNING MORE EFFECTIVE

TP30.1

ID Response• 31 A one stop permit request for each project utilizing Land & Right of Way personnel.

Coordination between the Trans Planning division and Regulatory Advisors who coordinate the regulatory approval process for new trans lines is facilitated by organizational structure. Both groups report to the same Director.

• 28 Early engagement and consultation with First Nation (Aboriginal), Public and government agencies is effective.

• 33 Land and environmental is brought in during the project planning stage of the project to identify issues with siting a facility. Estimates and design work are driven by environmental impacts. Designs must be stamped by a registered professional engineering with peer approvals.

• 23 We work within the State's Public Utility Commission Rules for all transmission line projects.

• 37 Apply for permits ASAP• 38 Because our Utility Coordination area have become experts in dealing with permits

and certifications from the City, they have been empowered to assist PMs in the acquisition and negotiation of these permits and certifications. In addition, we have been outsourcing the civil site design of substations which includes the acquisition of required construction permitting.

• 40 Engineers obtain permits for their jobs• 30 Maintain a list of permits and environmental issues• 27 Trans Planning studies ensure that NERC TPL, FAC and MOD standards are

thoroughly addressed to demonstrate need and that the system with the addition of proposed projects are adequate.

• 359 The P3 process includes investigation of permits and lead times, which leads to better planning of the project.

• 32 Bringing multiple departments to the table to discuss and attempt to predict timelines.

59

21 Attending Scope Meetings in the early planning stages and having the opportunity to provide early input regarding potential permitting difficulties and to propose ways to reduce the impact to make obtaining the permit easier or even possible, In addition this can avoid compensatory mitigation such as threatened and endangered species habitat replacement, and other expensive requirements by permit requirements, etc. In addition, this process/practice can reduce company risk/liability.

Westar

Page 60: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Other Practices and initiatives

Page 61: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Practice Questions

Strategy - Transmission Automation• Top 5 technologies being deployed for Transmission Automation• Other transmission automation technologies

Asset Management• Predicting condition of various critical components • Role of the Asset Management organization in your decision -making• Key responsibilities of the Transmission Asset Management organization• What keeps you up at night worrying about your system• Infrastructure replacement programs underway• Classes of equipment that are becoming problematic: Transmission• Initiatives undertaken to improve getting a job from planning to delivery• Practices around permits and certifications that make planning effective• Transmission line standard changed recently and why• Measure used to track the success of engineering/design function

Transmission Operations Center• Transmission energy control centers• Changes in energy control centers in the last few years• Major challenges facing the energy control center• Initiatives that have been successful in improving the energy control function• Response to External Forces• Changes being made to energy management system (benefits or

challenges)

2014 Sections (by process)◼ NERC standards) ◼ Strategy (including

Transmission Automation)◼ Asset Management ◼ Transmission Operations

Center (TOC)◼ Maintenance (including

ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction

Activities (including WMS and Contractor Productivity

61

Page 62: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Transmission Practice Questions (cont)

Maintenance - ROW• Technologies/tools/practices that have improved ROW

management: Chemical growth inhibitors; Herbicides; Other• Use of ROW land• Major challenges - near and long term - being faced by ROW

management• Initiatives successful in improving ROW management operations• Initiatives successful in improving ROW contract management

Field Construction• Number of reporting locations transmission line field personnel

work out of• Most important initiative underway to improve

◼ Transmission line construction◼ Transmission line maintenance practices◼ Transmission line reliability

• Important initiative underway to improve Transmission line reliability: Poles/Towers; Cable; Insulators; Other

• WMS vendor and year of implementation or last major upgrade• Challenges seen in managing a contract workforce: Transmission• Productivity measures in place for contract crews• Practices that have been successful for improving contractor

management

Transmission Maintenance• Regulatory drivers for Transmission Line inspection and

maintenance• Regular inspections performed• Inspections added in the last year

2014 Sections (by process)◼ NERC standards◼ Network Planning (including

Transmission Automation)◼ Asset Management ◼ Transmission Operations Center (TOC)◼ Maintenance (including ROW)◼ Planning/Engineering/Design ◼ T-line Field Construction Activities

(including WMS and Contractor Productivity

62

Page 63: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors:Transmission asset management

Develop and use processes to assess condition using both observational and model-based efforts

Identify risk categories including aging assets, reduced budgets, and specific equipment

Strengthen asset management role

Conduct replacement programs. Wood pole inspection and replacement are most common

Identify problematic equipment

63

Page 64: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors:Operate the Transmission system

Involve stakeholders in planning system outages

Continue to upgrade EMS

Conduct Timely and Safe Switching Operations

Monitor and Restore Operations

64

Page 65: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors:Maintain the Transmission Network

Address challenges to ROW maintenance

Conduct regular inspection programs

Improve maintenance practices; scheduling is most mentioned

65

Page 66: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Organization: Strategy on priorities and contracting strategies

Design tools including WMS and compatible units

Construct scheduling and coordination using developers and contractors

Closeout and Follow-up

Key Success Factors:Engineering/Design of sustain/capacity additions

66

Page 67: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Key Success Factors:Build Infrastructure (Field Construction)

Improve contracting; oversight, schedule planning, and routine meetings and feedback are some successful practices for improving contractor management

Improve field productivity; initiatives focus on crew size, training, and system changes

Use a Work Management System to schedule jobs. SAP and Maximo are the most used

67

Page 68: Transmission Lines August 20-22, 2014 Vail, CO 2014 Transmission & Distribution Benchmarking Insights Conference.

Thank you for your Input and Participation!

Corporate Offices

California

400 Continental Blvd. Suite 600El Segundo, CA 90245(310) 426-2790

Maryland

3 Bethesda Metro Center Suite 700Bethesda, MD 20814(301) 961-1505

New York | Texas | Washington | Wisconsin

First Quartile Consulting is a utility-focused consultancy providing a full range of consulting services including continuous process improvement, change management, benchmarking and more. You can count on a proven process that assesses and optimizes your resources, processes, leadership management and technology to align your business needs with your customer’s needs.

Visit us at www.1stquartileconsulting.com | Follow our updates on LinkedIn

About 1QC

Satellite Offices

Debi McLain Cook [email protected]

Tim. [email protected]

Dave [email protected]

Dave [email protected]

Your Presenters

Ken Buckstaff [email protected]

68