Traction Items

1. Current Issues pertaining to ALCO/EMD locos.

A. Maintenance issues of ALCO & EMD locos: (i) Zonal Railways should indicate the DLSCs set up for EMD locos viz.a.viz their proposed

action plan in the following format:-

Location of DLSC

Status of sanction

Target date Progress & remarks

Railways to indicate the number of EMD locos running on 90 day schedule. (ii) Issue of jerks in CBC trains – the position regarding introduction of tight lock couplers and soft

preload draft gear on locomotives should be provided in the following format:-

No. & type of locos targeted

No. of locos provided with tight lock couplers

No. of locos provided with soft preload draft gear

No. of locos provided with both

Status of sanction/ procurement for balance locos

Target date

RDSO, DLW and DMW may indicate the progress and railways to give a feedback on the same.

(iii) Railway should bring an analysis of the stocking and availability of must change items for POH of ALCO locos as circulated by RDSO in the following format:- No. of items to be stocked

No. of items already stocked

No. of items in which AAC has to be enhanced

%age Availability in stock

(iv) SWR should indicate the progress made in outsourcing the work of provision of various kinds of filters in EMD locos. Similarly SCR should share their preparedness for manufacture of EMD filters in-house.

B. Planning for homing of additional locos/infrastructure:

(i) Each year approx. 170-180 locos are being added to the fleet for which matching capacity in

terms of augmentation of existing sheds to home 150 locos or new sheds needs to be created. Railways have been advised to send augmentation proposals for existing sheds. Railway should confirm the status of the proposals and the likely fund requirement. Railways should bring the status of works sanctioned at DRM, GM and Board’s level for the above in the following format:- Name of shed and details of Work sanctioned in last three years under

Status of work and likely date of completion

DRM’s power GM’s Power Board level

Page 3: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

(ii) The condition of Running rooms, lobbies and training centres comes for severe criticism in

various forums. Railways should bring the status of works sanctioned at DRM, GM and Board’s level in the following format: Name of running room/lobby/training centre and details of Work sanctioned in last three years under

Status of work and likely date of completion

DRM’s power GM’s Power Board level Board has approved a plan for setting up simulators and the same was circulated in the last CMEs’ Conference. Railways should list out the proposals being sent in the M&P and WP for simulators and other works.

(iii) Board have already advised DLW, GOC, Parel and DLMW regarding the acquisition plan for

diesel locos in the next 10 years. These units should come prepared with the action plan for implementing the above.

C. Strategy for new developments: (i) DLW has turned out 1 WDP4D locos (Dual Cab) for which trials have to be planned. DLW

should indicate the plan for complete switch over to this design as already communicated by Board.

(ii) Two 4500 HP WDP4 locos having hotel load feature capable of supplying 500 KVA hotel load have been turned out by DLW. RDSO should give the status of the trials and the group may discuss their future proliferation.

(iii) Distributed Power System (DPS) trials have been successfully carried out in SCR, SWR & NR. RDSO should make a presentation on Issues relating to allotment of frequencies, CRS sanction, etc. Zonal Railways should estimate the requirement of DP in consultation with the Traffic Department so that sufficient provisioning of DPS may be made in the bulk RSP.

(iv) Railways should indicate the progress of fitment of stand alone VCD. (v) DLW and RDSO should make a presentation on the progress of the 5500 HP loco and

provision of AC and toilet facility on EMD locos.

2. Issues pertaining to DEMUs:

(i) ICF should indicate the progress of supply of RSP items against Board’s Bulk RSP. Railways should also indicate the progress of itemized RSP.

(ii) There is a need to carry out refurbishing of DEMU coaches in the 2/3 POH as most of these are running in sub-urban services and the passenger amenities items get vandalized. SR & ICF should make a presentation along with detail costing of items which should be included in the above work. RDSO should make a presentation on the LED destination boards for DEMUs.

3. Issues pertaining to Running staff : (i) Zonal Railway should ensure that technical control of running staff is exercised on the lines

mentioned in Board’s letter no.E(NG)I-2006/PM7/12 dated 2.06.2006 (Annexure-I).

Page 4: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

(ii) The progress of implementation of the subsidized meal scheme should be brought out by all the Zonal Railways in the following format:- No. of running rooms on the railway

No. of running rooms under Mechanical

No. of Mechanical running rooms provided with Subsidized meal

Action plan for balance

(iii) Vide letter No.E(MPP)/2009/3/26 dated 13.07.2009 (Annexure-II), Board had advised Zonal Railways to train all the LIs in the initial course within 6 months i.e. by January, 2010. The status of the above training should be provided as per the following format:

Name of division and training centre imparting above training

Total no. of LIs under Mechanical control

Total no. of LIs undergone Diesel initial course

Total no. of LIs undergone electric initial course

Action plan for balance

Reasons for non-compliance division-wise and action taken

(iv) SCR has carried out a review of loco Inspectors for additional activity and has got these post sanctioned. Further, they have outsourced certain activities in the lobby like data feeding, etc. so as to have the least amount of running staff on stationary duties. SCR should make a presentation on the same.

(v) Railways should bring status of the pending indents for running staff as well as action being taken for providing alternate jobs to medically de-categorized running staff.

Page 5: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

Production Unit Items 1. Review of performance of Production Units:

PU Product Actual

2009-10 Target 2010-11

Target Apr – July’10

Actual Apr – July’10

DLW Diesel Loco 258 250 84 81 CLW Electric Loco 220 230 66 68 ICF Coaches 1433 1500 470 411 RCF Coaches 1568 1600 540 540 DMW Diesel Loco

Rebuilding 112 108 37 37

Wheel 187450 190000 54117 48077 RWF Axle 65302 68000 20447 21459

Shortfalls have been observed in production of following categories of Rolling Stock:

PU Shortfall noted in

DLW EMD locomotives

RCF LHB coaches

ICF Stainless steel coaches

RWF Loco and EMU wheels and BOXN axles.

The PUs may indicate action plan to meet the annual target.

2. Increase in Diesel loco production capacity to meet Vision- 2020 goals: DLW, DMW and CR have been advised vide Board’s letter No.2010/M(PU)/1/38 dated 10.08.2010 to plan for increase in the Diesel loco production capacity. The PUs may indicate their action plan. 3. Progress of works sanctioned for raising the installed capacity:

Various works under Plan Head 42 have been sanctioned to raise the installed capacity of the PUs as indicated below:

PU Current installed capacity Envisaged installed capacity on completion of on-going works

DLW 150 locomotives 200 locomotives ICF 1000 coaches 1500 coaches RCF 1000 coaches 1500 coaches

The PUs may indicate the progress of works and the target date by which the new installed capacity will take effect.

Page 6: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

4. Inter PU assistance: The following matters pertaining to inter PU assistance will be deliberated:

• Orders for bogies by DMW on CLW. • Assistance of RCF to RBL. • Assistance of ICF to SER for Sankrail.

Page 7: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

COACHING

1. Performance review of Zonal Railways (a) Punctuality losses on C&W account : Status - Annexure – 1 (b) En-route coach detachments on ownership basis: Status - Annexure – 2 (c) Cleanliness and hygiene attention in coaches:

Mechanized cleaning of rakes, On-board House-keeping Services (OBHS), ) Clean Train Stations (CTS) ,Controlled discharge Toilet Systems (CDTS– Status: Annexure – 3 , 4, 5 and 6

(d) Setting up of Mechanized laundries for linen washing Status – Annexure- 7

2. Proliferation of LHB coaches:

LHB/ FIAT coaching stock is going to be the main stay for Indian Railways. PUs’ are already stepping up their production capabilities enabling faster proliferation of LHB coaches for AC as well as non-AC services. Current holding of LHB coaches over NR, WR, ER, ECR, SER, SR and NCR is around 700 coaches. Over 300 coaches during the year 2010-11 and 500 coaches during the year 2011-12 have been planned to be manufactured. (Annexure- 8) Zonal Railways have to gear up for maintenance of rakes in depots as well as in workshops. Performance and Maintenance cost especially of high vale items may also be kept under check. The following issues concerning maintenance and infrastructure need to be addressed for smooth migration of LHB coaches on a larger scale. a. Proposed new centers- Depots and workshops

Railway Coaching Depots Nominated workshops

CR LTT MTN

SCR SC LLGD ECoR PUI, BBS MCWS SWR SBC, MYS MYS/UBL WR ADI PL

• As more and more rakes will be inducted in services, railways may ensure setting up

of facilities and training of staff etc. to start the LHB maintenance. • CAMTECH to prepare a comprehensive document detailing all aspects of

maintenance & upkeep of LHB FIAT coaches. b. Maintenance issues of LHB coaches

• Wheel life of LHB coach is an area of concern especially due to wheel shelling

phenomena which also requires periodic check. RDSO must expedite the investigations and suggest remedial measures to control the wheel shelling. RDSO may advise current status of measures being taken to resolve this issue.

• Corrosion in bogie frames – Railways have been reporting instances of pitting corrosion on the bogie frames of LHB coaches within 3 to 4 years of service. RDSO/RCF needs to study for a change of material/suitable corrosion prevention measures.

• Roller Bearings and dampers - As against stipulated periodicity of 1.2 million Kms between successive refurbishments, Roller bearings are reported to give a

Page 8: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

much lesser service life. Likewise, as against an expected life of 6 years for the shock absorbers/dampers, the service life is much lesser. Railways may share their experiences and field performance data.

• Refurbishment of coach interiors and toilets by workshops • Facilities PU painting- in coaching depots/workshops – Review by RCF c. New manufacture of LHB coaches

• Tentative manufacturing plan for next 3 years at RCF

2010-11 – 350 coaches 2011-12 - 500 coaches 2012-13 - 500 coaches at RCF/KXH, 100 coaches at RCF/RBL

• ICF to also gear up for LHB manufacture and advise their action plan • Bogie frame manufacturing – status of outsourcing by RCF • Manufacture of power car with under slung DG set for EOG Mail/Express

trains – RCF to advise status

3. Air brake system and air suspension system on coaching stock:

The field performance indicates increase cases of brake defect leading to detention and loss of punctuality. The maintenance attention both in depots as well as in workshops need to be tightened. RDSO was advised to conduct technical audit of maintenance centers and also analyze the causes of failures in brake system.

Air brake system : ( Presentation by RDSO ): • Major defects, trend, cause-wise analysis • System improvement - maintenance practices and preventive measures RDSO may also advise status of development of electro-pneumatic brake systems

A. Air suspension system (Secondary air springs) Based on techno-economic analysis of air springs, instructions were issued for switchover to air springs in the secondary suspension of ICF design as well as FIAT design bogies, subject to the clearance of respective coach types in the oscillation trials. Air springs have been inducted in about 250stainless steel hybrid SG coaches.ICF has also planned to manufacture ICF design coaches with air suspension during the current year. While prototyping has also been carried out on LHB- FIAT coaches, regular manufacture of such coaches with air springs is yet to be taken up at RCF. Double decker coaches have being manufactured d with secondary air suspension. RDSO may advise status of following: • Operational and maintenance requirements of air springs • Safety measures – Failure indication cum brake application device

(FIBA) – status of development • Air requirements and effect on working of CDTS & auxiliary systems

4. CBC for coaching stock While the introduction of CBC in coaching stock enhances safety standard due to anti-climbing, automatic coupling features etc., recent cases of en-route train partings involving CBC is a matter of concern. RDSO should comprehensively review the design features, working instructions, special check points for coupling of CBC etc.

Page 9: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

RDSO should also study various local level design modifications carried out by Railways to ensure proper dropping of lock and obviate accidental opening of knuckles during run. RDSO may advise action on following issues: • Causes of uncoupling of knuckles and remedial measures including

design modifications etc. • Operational and maintenance issues

5. Manufacture and operation of Double-Decker coaches

The manufacturing of first rake of AC double-decker Chair Cars coaches have been taken up by RCF as per following approved layout of higher height coach (4366 mm): Layout No. CG-K9108 – with a capacity of 105 reclining type chairs. Layout No.CG-K9114 - with a high capacity of 128 non-reclining chairs. The kinetic profile of coach shell infringes with the schedule of dimensions as in MMD IB-2004. These infringements have, however been condoned by Board and following routes for operation of double-decker have been initially nominated: (i) ER/ECR : HWH-DHN (ii) WR- BCT-ADI

Before double-decker trains can be proliferated in large numbers across IR, Zonal Railways need to ensure removal of infringement to the fixed structure, if any and also to ensure the necessary clearance between the kinetic profile and fixed structure as laid down by RDSO. Double decker trains are also to be planned to be manufactured towards world class standards.

The progress/ important milestones are as under: • Manufacture & squeeze testing of prototype coach conducted successfully at

RCF. • Oscillation trials, issue of final speed certificate & obtaining CRS sanction is

underway. RDSO to advise status. • ER and ECR to confirm removal of infringement on identified roué • One rake planned for series manufacture at RCF during 2010-11. RCF may advise the

status of manufacturing

6. Performance review of upgraded materials for enhancing aesthetics, serviceability, fire worthiness and maintenance attention With a view to enhance POH periodicity, improved passenger comforts, coach aesthetics, serviceability and fire worthiness for improved safety, upgraded material have been introduced for furnishing and under gear. The field performance of some of the items has not been reported by Railways up to the mark. RDSO may advise the status of the upgraded items based on the field performance and the feed back reported by zonal railways.

7. Enhanced periodicity of POH of coaches For the enhanced periodicity between 2 successive POH, Unit exchange of overhauled bogies

has been mandated during the IOH of coaches. It is seen that Railways are generally restoring to booking the coaches to workshops for IOH rather than arranging for transportation of adequate No. of overhauled bogies between the workshops and the workshops and the depots for this purpose.

Reports indicate a significantly high cycle time for IOH of coaches on different Zonal Railways (as high as about 25 days in some cases), including the transit time from base depot to the Workshop, average time inside the workshops during IOH/POH and transit from the

Page 10: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

workshops to the base depots. The situation is least desired and Railways must exercise control over such high detentions. The position has been reported to be particularly bad for NR, ER, NFR, ECR & WCR. This situation defeats the very purpose of enhancing the availability of coaches and controlling the ineffective.

Page 11: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

ANNEXURE-3 Mechanized cleaning of Rakes Position as on 1.8.10

Tenders finalised

Rly Total No. of depots

Identified

Depots with holding >250

Other depots Total

Balance depots Depots with holding>250 Other Depots

NR 8 1 0 1 7 DLI, NDLS, HNZM, ASR,JAT, LKO. BSB,,DDN

CR 10 2 1 3 7 PA, LTT, WB,DR NGP,MZN,CSTM,KOP,BSL,SUR

SCR 9 3 1 4 5 HYB, SC, KCG, TPTY, BZA, NS NED, MTM ,COA

ER 8 2 3 5 3 TKPR,SYAE, JSDG,KOLKATTA , NCC (SDAH). ASN,MLDT & BGP

WR 8 2 3 5 3 ADI, BCT, BDTS, IND, ST VRL,PBR ,BVC,

SR 9 6 0 6 3 BBQ, TVC, NCJ, ERS, GSN* ,TPJ*,CBE,MDU ,MAQ

NCR 4 1 2 3 1 ALD JHS,GWL,CNB

ECR 10 4 4 8 2 RNCC, BJU, DBG, DNR, DHN RGD, GAYA ,SPJ,RXL, NKE

ECOR 4 3 1 4 0 PUI, VSKP, BBS SBP

NER 6 1 5 6 0 GKP LJN, MUV, CPR, KSJ, KGM

NFR 6 2 4 6 0 GHY, KIR NJP, NBQ, TSK, DBRT

NWR 8 2 6 8 0 JP, JU* LGH,SGNR, AII*, UDZ*,BME, BNW

SECR 2 1 1 2 0 BSP DUG

SER 3 3 0 3 0 SRC, HATIA, TATA

SWR 6 3 3 6 0 SBC ,YPR, MYS ASK, VSG, UBL,

WCR 3 1 2 3 0 JBP BPL, KTT

Total 104 37 36 73 32 * Attended departmentally 

 

Page 12: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

ANNEXURE-4  

 

Status of Tenders for On-Board House Keeping Services in Trains (as on 01.08.10)

Rly Total No of Trains (Pairs)

Identified No. of Trains (Pairs) for which

tender have been finalized Balance % compliance NR 100 11 89 11 SR 53 11 42 21 CR 49 19 30 39

SER 25 11 14 44 SWR 24 15 9 63

ECOR 27 17 10 63 ER 35 26 9 74

ECR 21 17 4 81 NWR 13 11 2 85 WR 34 31 3 91 NER 13 12 1 92 NCR 5 5 0 100 NFR 26 26 0 100 SCR 20 20 0 100

SECR 13 13 0 100 WCR 3 3 0 100

TOTAL 461 248 213 54

Page 13: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

 

ANNEXURE-5 CLEAN TRAIN STATIONS (CTS) 

 

Un-commissioned CTS S.NO Rly Target Date CTS Status of Tender

1 NCR June'10 ALD Tender opened.Under TC 2 NCR June'10 CNB Tender opened.Under TC

3 WCR March'08 KTE .Estimate under vetting.

Commissioned CTS (current contracts nearing completion)

S.No. Rly CTS Name of Agency Valid upto

1 NR NDLS Eureka Forbes Ltd 04.10.08 2 NER CPR Eureka Forbes Ltd 24.09.10 3 ECOR VSKP GS & Inspection Services Ltd 20.09.10 4 NFR NJP Eureka Forbes Ltd 29.11.10 4 WR ADI Eureka Forbes Ltd 25.12.10 5 NFR GHY M/s BVG India Ltd Pune 30.01.11 7 NER GKP A2Z Services Pvt Ltd Goregaon 29.01.11

Page 14: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

ANNEXURE-6  

STATUS OF CONTROLLED DISCHARGE TOILET SYSTEM (CDTS) As on 01 September 2010

RLY Total no of CDTS Units

Functioning CDTS units

Defective CDTS units

%Defective

ECR 944 81 863 91

NER 56 8 48 86

SWR 105 12 93 69

SECR 18 8 05 61

NR 1398 691 393 51

NFR 8 4 4 50

SER* 440 280 200 50

CR 205 155 57 24

ECOR 171 139 32 23

ER 685 530 155 23

SCR 460 395 65 14

SR 337 490 4 8

NCR 340 291 28 2

WR 490 480 11 2

NWR 16 14 11 0

WCR 13 9 4 0

IR 5686 3713 1973 35% approx.

Page 15: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

   

ANNEXURE-7   

MECHANISED LAUNDRIES FOR LINEN WASHING

STATUS NOS RAILWAYS

Proposal under finance vetting/under preparation

23 NR/3, ECoR/2, NCR/1, NER/2, NWR/3,SECR/2, SC/1, SR/2, SWR/5, WCR/2

Tender opened/due 8 CR/1, ECR/1, SCR/1, SER/2, WR/3 Contract Placed/Work under process

4 ER/2, SCR/1, ECR/1

Commissioned 4 CR/1, NR/2, NFR/1

Page 16: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

     

ANNEXURE-2(i)     

                                     ENROUTE COACH FAILURES OVER IR  

 Year  Total coach

Holding IRTotal No. of Coach failures  

Coach Failure Per 100 coach holding 

  A 

  B 

  C 

  D 

  E 

  F 

2005‐06  37494  99  0.26  45  16  32  4  0  2 

2006‐07  39198  78  0.20  34  17  21  3  0  3 2007‐08  40312  63  0.16  40  10  8  1  0  4 2008‐09  42488  82  0.19  53  6  13  7  2  2 2009‐10  43939  94  0.21  49  15  18  7  2  3 

                      Legend‐                         A – R.B. Failure                        B – Bogie & Suspension Gear Defects                       C – Wheel Flats/Air Brake System Defects                       D – Draw & Buffing Gear Defects                       E – Failure of Major Structural Members (Head Stock, Sole Bar Failure)                       F – Other Misc. Defects   

   

Page 17: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

 

ANNEXURE-2(ii)  ENROUTE COACH DETACHMENTS ( Ownership Basis) April – July 2010

RLY APR MAY JUN JUL Total A B C D E F

CR 2 0 1 0 3 2 0 0 0 0 1

ER 0 0 0 0 0 0 0 0 0 0 0

ECR 0 0 0 0 0 0 0 0 0 0 0

ECoR 0 0 2 0 2 1 0 0 1 0 0

NR 1 1 1 1 4 3 0 1 0 0 0

NCR 0 0 0 1 1 0 1 0 0 0 0

NER 0 0 1 0 1 1 0 0 0 0 0

NFR 0 0 0 0 0 0 0 0 0 0 0

NWR 1 1 0 0 2 0 0 1 1 0 0

SR 0 1 2 2 5 3 0 1 0 1 0

SCR 1 1 0 0 2 0 1 1 0 0 0

SER 0 0 1 0 1 0 0 1 0 0 0

SECR 0 0 0 0 0 0 0 0 0 0 0

SWR 0 0 0 0 0 0 0 0 0 0 0

WR 1 0 0 1 2 0 0 0 0 2 0

WCR 0 0 0 1 1 0 0 0 1 0 0

Total 6 4 8 6 24 10 2 5 3 3 1

Legend A-Roller Bearing Failure B-Bogie & Suspension Gear Defects C-Wheel Flats/Air Brake System defects

D-Draw & Buffing Gear defects                

E-Failure of Major Structural members of Coach Body(Head Stock,Sole Bar failure)

Page 18: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

F- Other Misc.Defects                

                               

Annexure - 1

PUNCTUALITY LOSS ON C&W A/c OVER IR 2010 -11 (April-July)

RB Failure/Hot Axle

Hanging part/Under

gear Defects

Brake System Defects,wheel

flats Passenger Complaints

Train Parting/Draw &

Buffing gear Misc. & Others Total

Indirect Indirect Indirect Indirect Indirect Indirect Indirect Rly

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Dire

ct

coac

h

wag

on

Grand Total

CR 0 0 0 2 0 0 11 2 5 2 0 0 3 0 8 6 2 3 24 4 16 44

ER 0 0 1 2 0 0 6 3 1 0 0 0 0 0 20 1 0 0 9 3 22 34

ECR 0 0 1 2 0 1 24 19 16 7 0 0 1 3 28 11 7 0 45 29 46 120

ECoR 1 1 2 0 1 0 10 6 1 0 0 0 0 0 12 20 2 3 31 10 18 59

NR 1 0 5 1 1 0 50 14 12 5 4 0 2 0 7 85 15 14 144 34 38 216

NCR 0 0 53 34 5 5 33 4 9 12 2 2 0 0 4 15 19 8 94 30 81 205

NER 0 0 0 1 0 0 2 0 0 1 0 0 0 0 0 6 1 0 10 1 0 11

NFR 0 0 0 0 0 0 3 1 4 1 0 0 1 0 1 0 0 0 5 1 5 11

NWR 0 0 0 0 0 0 7 2 1 1 0 0 0 0 6 0 0 5 8 2 12 22

SR 0 0 0 0 0 0 19 6 5 2 3 0 1 0 21 1 0 0 23 9 26 58

SCR 0 0 2 1 0 0 20 4 3 1 0 0 1 0 23 0 0 0 23 4 28 55

SER 0 0 0 0 0 1 7 1 1 0 0 0 1 0 30 7 0 5 15 1 37 53

SECR 0 0 1 0 0 0 4 0 2 0 0 0 0 0 7 1 1 2 5 1 12 18

SWR 0 0 0 0 1 0 5 2 0 1 0 0 0 0 5 2 0 0 8 3 5 16

WR 1 0 23 4 1 2 7 2 3 2 1 1 2 1 7 8 1 7 24 6 43 73

WCR 2 1 2 7 0 0 10 4 11 0 0 0 2 10 13 8 1 2 29 16 28 73

Total 5 2 90 54 9 9 218 70 74 35 10 3 14 14 192 171 49 49 497 154 417 1068

Page 19: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches
Page 20: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

19 

 

Annexure- 8

Railway-wise LHB holding, Annual Production, Maintenance Schedule and existing coaching depots/ workshops

A. Holding on the Railways (as on 1.4.10)

NR WR ER ECR SER SR NCR TOTAL302 139 161 37 22 14 14 689

B. Annual production since induction

01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09 09-10 TOTAL27 27 76 76 51 119 95 118 162 751

C. Maintenance schedules

Schedule Periodicity IOH (Shop schedule-I) 18 months/ 6 lakh kms whichever is earlier POH (Shop schedule-II) 3 years/ 12 lakh kms earned whichever is earlier POH (Shop schedule-III) 6 years/ 24 lakh kms earned whichever is earlier

D. Maintenance centers – coaching depot and workshops

Railway Coaching Depots Nominated workshops

NR NDLS JUDW WR BCT PL ER TKPR, SDAH LLH

ECR PNBE LLH SR BBQ PER*

SER SRC KGP* NCR ALD LLH*

* IOH/POH yet to be started.

Page 21: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

20 

 

Plan Head – 41

1. Status of utilisation of funds for the year 2010-11 (Upto July’ 2010) is placed at Annexure – I. The same would be reviewed during the meeting.

2. A large number of machines are pending procurement with COSs. This needs to be brought down to manageable proportions. Achievements of the Railways vis-a-vis Action Plan in this regard is placed at Annexure –II.

3. Delay in commissioning of high value machines on Railways/PUs account would be discussed during the meeting. The present position as per COFMOW’s PCDO for the month of July 2010 is enclosed as Annexure-III.

4. There are 14 cases costing ` 45.34 crore where procurement is held up for sanction of ‘excess over estimate’ on Railways/PUs account. COFMOW is unable to issue purchase orders because of delay in sanction of enhanced funds. Status as per COFMOW’s PCDO for July 2010 is placed at Annexure IV. This position would be discussed in the meeting.

Page 22: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

21 

 

Annexure‐I

PH 41 – Utilization

(Figures in Crore of Rs.)

FY Sanctions Budget Grant Expenditure %age utilisation of

BG 2004-05 295.39 160.02 177.37 110.84 2005-06 252.29 214.6 186.06 86.70 2006-07 434.39 255.50 176.91 69.24 2007-08 767.57 300.00 192.31 64.10 2008-09 967.65 445.21 325.67 73.15 2009-10 (Aprox) 656.35 408.50 394.76 96.64 2010-11 upto July'10 (aporx) 889.11 428.50 100.42 23.44

UTILISATION OF FUNDS UNDER PLANHEAD 41 DURING 2010-11 (Figures in Crore of Rs.)

S. No. RAILWAY(S)

Sanctions 2010-11

Budget Grant 2010-11

Utilisation upto July'10 (Approx)

%age utilisation of Budget Grant

1 Central Railway 23.83 19.79 5.90 29.812 Eastern Railway 90.53 32.61 2.60 7.973 East Central Railway 19.12 6.00 3.32 55.334 East Coast Railway 14.73 11.58 0.58 5.015 Northern Railway 79.59 22.83 17.14 75.086 North Central Railway 40.57 19.17 2.19 11.427 North Eastern Railway 14.03 13.65 0.79 5.798 Northeast Frontier Rly 33.43 18.76 3.47 18.509 North Western Railway 44.88 7.83 1.64 20.9510 Southern Railway 56.84 25.12 10.76 42.8311 South Central Railway 31.28 28.31 8.66 30.5912 South Eastern Railway 47.71 18.02 5.94 32.9613 Southeast Central Rly 42.04 21.25 1.81 8.5214 South Western Railway 24.75 8.96 1.63 18.1915 Western Railway 43.33 16.12 4.65 28.8516 West Central Railway 17.76 16.70 5.52 33.05

TOTAL RAILWAYS 624.42 286.7 76.60 26.7217 CLW 30.91 31.35 5.21 16.6218 DLW 67.69 25.86 6.27 24.2519 ICF 26.53 17.72 1.97 11.1220 DLMW 47.33 33.11 2.39 7.2221 RWF 61.84 12.36 4.06 32.85

Page 23: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

22 

 

22 RCF 30.39 21.40 3.92 18.32TOTAL PUs 264.69 141.80 23.82 16.80

GRAND TOTAL 889.11 428.50 100.42 23.44Previous year (2009-10) 656.35 408.50 73.66 18.03

Annexure-II

Railways - Control Chart - PH 41 ( Upto July'10 )

Action Plan 2010-11 (COFMOW) Action Plan 2010-11 (COS)

Target Actual Upto

July'10 Target Actual Upto

July'10

Rly No. Of M/cs. Cost

Proportionate Target

M/cs Received

Expenditure

No. Of M/cs. Cost

Proportion

ate Targ

et M/cs

Received Expenditure BG

Utilisation Upto

July'10 (Aprox)

%age Utilisation

of BG

CR 18 17.97 5.99 0 0.00 134 9.45 3.15 33 1.25 19.79 5.90 29.81

ER 42 27.92 9.31 7 238 18.46 6.15 41 32.61 2.60 7.97

NR 48 39.81 13.27 4 5.07 175 6.82 2.27 32 1.34 22.83 17.14 75.08

NER 18 9.36 3.12 2 1.26 85 3.13 1.04 21 0.70 13.65 0.79 5.79

NFR 21 14.61 4.87 8 8.64 68 5.42 1.81 20 1.22 18.76 3.47 18.50

SR 28 26.68 8.89 4 5.88 203 10.15 3.38 107 5.11 25.12 10.76 42.83

SCR 23 12.87 4.29 6 5.24 155 8.22 2.74 26 1.22 28.31 8.66 30.59

SER 15 4.34 1.45 0 0.00 236 14.07 4.69 17 1.02 18.02 5.94 32.96

WR 19 3.79 1.26 0 0.00 57 9.62 3.21 12 1.39 16.12 4.65 28.85

ECR 27 10.49 3.50 1 0.52 29 1.49 0.50 3 0.16 6.00 3.32 55.33 ECoR 10 6.80 2.27 2 0.04 82 4.30 1.43 8 0.54 11.58 0.58 5.01

NCR 20 17.33 5.78 4 0.50 255 10.56 3.52 128 1.45 19.17 2.19 11.42

NWR 12 5.53 1.84 0 0.00 101 3.41 1.14 10 0.42 7.83 1.64 20.95 SECR 19 6.77 2.26 3 0.84 114 6.29 2.10 46 0.26 21.25 1.81 8.52

SWR 11 6.20 2.07 1 0.56 91 2.47 0.82 35 0.85 8.96 1.63 18.19

WCR 20 11.04 3.68 0 4.04 74 2.78 0.93 13 0.73 16.70 5.52 33.05

CLW 3 0.63 0.21 0 0.00 120 22.83 7.61 29 1.64 31.35 5.21 16.62

DLW 18 35.84 11.95 1 3.46 34 7.70 2.57 9 0.00 25.86 6.27 24.25 DLMW 18 22.00 7.33 5 1.38 38 3.54 1.18 8 0.40 33.11 2.39 7.22

ICF 18 17.06 5.69 1 0.00 86 6.19 2.06 0 0.00 17.72 1.97 11.12

RCF 32 3.50 1.17 1 1.07 64 7.41 2.47 26 1.77 21.40 3.92 18.32

RWF 3 3.76 1.25 1 0.24 12 15.86 5.29 4 1.17 12.36 4.06 32.85

Total 443 304.3

0 101.43 51 38.74 2451 180.17 60.06 628 22.64 428.5

0 100.42 23.44 (Fig. in Rs. Crores)

Page 24: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

23 

 

ANNEXURE - III

SUMMARY OF MACHINES COSTING MORE THAN Rs. 25 LAKH EACH AWAITING COMMISSIONING FOR MORE THAN 6 MONTHS AFTER RECEIPT. ( Fig in ` lakh)

SR. NO. Railrays Total No. of Machines Cost

1 CENTRAL RAILWAY 6 812.06

2 EASTERN RAILWAY 5 1001.03

3 EAST CENTRAL RAILWAY 6 483.77

4 EAST COST RAILWAY 2 122.60

5 NORTHERN RAILWAY 6 1348.60

6 NORTH CENTRAL RAILWAY 2 2637.38

7 NORTH EASTERN RAILWAY 1 288.68

8 NORTH EASTFRONTIER RAILWAY 3 95.54

9 SOUTHERN RAILWAY 8 1860.49

10 SOUTH CENTRAL RAILWAY 4 1261.56

11 SOUTH EASTERN RAILWAY 2 402.16

12 SOUTH EASTCENTRAL RAILWAY 1 42.85

13 SOUTH WESTERN RAILWAY 2 71.58

14 WESTERN RAILWAY 3 577.28

15 CLW 2 291.22

16 DLW 6 1480.08

17 ICF 6 664.22

18 RWF 5 5558.31

19 DMW 6 1152.89

20 RCF 11 1514.64

TOTAL 87 21666.94

Page 25: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

24 

 

Annexure-III

MACHINES COSTING MORE THAN Rs. 25 LAKH EACH AWAITING

COMMISSIONING FOR MORE THAN 6 MONTHS AFTER RECEIPT.

(Position as on 31.07.2010)

S.No. Rly. AT No./Supplier Description of M/c Consignee Date M/c Received

Cost (fig. in ` lakh)

1 CR OP-1528/HEC VTL # PR 01.11.08 103.38

2 CR OP-1649/Amtint EOT Crane 15T BSL 29.11.08 30.44

3 CR OP-1528/HEC VTL # MTN 31.12.08 103.38

4 CR OP-1549/Hind Hyd Hydraulic Press 250T # MTN 19.11.07 72.61

5 CR OP-1619/Unique Traverser # MTN 27.08.09 107.47

6 CR G-428/Goratu CNC ATL # PR 24.12.09 394.78

7 ER OP-1498/Continental Load Box # BWN 10.12.07 42.85

8 ER OP-1651/Amtint EOT Crane 7.5T BGA 09.03.09 27.47

9 ER OP-1613/HEC Planing Machine # JMP 02.01.10 235.75

10 ER OP-1815/Premier CNC VTL # LLH 09.01.10 224.77

11 ER OP-1739/HYT Underfloor Wheel Lathe # HWH 11.01.10 470.19

12 ECR OP-1557/Global Axle Box Cleaning Box # HRK 02.03.08 91.52

13 ECR OP-1606/Global Phosphating Plant # HRK 21.03.08 131.42

14 ECR OP-1528/HEC VTL # HRK 31.03.09 109.47

15 ECR OP-1622/NESCO Coil Spring Shot Blasting M/c. HRK 31.01.10 56.43

16 ECR OP-1497/ESCORTS Road Mobile Crane HRK 23.06.09 30.93

17 ECR OP-1654/ESCORTS Road Mobile Crane HRK 23.06.10 64

18 ECoR OP-1334/Nelco Load Box # WAT 28.04.07 26.40

19 ECoR OP-1581/Saico EOT 50T @ WAT 10.08.08 96.20

20 NR OP-1528/HEC VTL # ASR 03.03.09 109.47

21 NR G-463/Global Spray Booth Bake Ovan # JUDW 17.10.09 734.52

22 NR OP-1708/HYT VTL # JUDW 09.10.09 159.13

23 NR OP-1815/Premier CNC VTL ASR 23.11.09 224.77

24 NR OP-1684/Geeta Drilling & Tapping M/c # JUDW 07.01.10 72.84

25 NR OP-1662/Hydropack Bogie Testing M/c AMV 30.01.10 47.87

26 NCR OP-1528/HEC VTL # CNB 23.06.08 103.38

27 NCR G-329/Bumar Plant for manufacture of springs # STLI 28.12.09 2534.00

28 NER OP-1446/HYT Underfloor Wheel Lathe # LJN 28.05.08 288.68

Page 26: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

25 

 

29 NFR G-395/Worldwide Spectrometer NBQS 26.11.08 26.26

30 NFR G-381/Hegenscheidt Re-Railing Equipment BPB 10.12.09 38.95

31 NFR OP-1590/Amtint EOT Crane 10T NGC 28.01.10 30.33

32 SR OP-1397/HEC Wheel Lathe Under Floor # BBQ 01.09.06 194.33

33 SR G-244/Bingham Coach Washing Plant # BBQ/Pune 17.01.07 315.86

34 SR OP-1536/HEC Travel Col. Radial Drilling M/c # TCPLLI 24.11.08 134.88

35 SR OP-1739/HYT Underfloor Wheel Lathe # JAJ 03.10.09 470.19

36 SR G-440/Baykal Shearing Machine # GOC 06.11.09 56.33

37 SR G-428/Goratu CNC ATL # GOC 28.12.09 394.78

38 SR OP-1713/Unique EOT 50T @ RPM 26.10.09 147.06

39 SR OP-1713/Unique EOT 50T @ RPM 26.10.09 147.06

40 SCR OP-1636/HYT Underfloor Wheel Lathe # AJJ 11.11.08 431.17

41 SCR G-428/Goratu CNC ATL # GTPL 28.12.09 394.78

42 SCR G-428/Goratu CNC ATL # TPTY 08.01.10 394.78

43 SCR OP-1820/Deev DG Gen set GTL 18.01.10 40.83

44 SER OP-1688/HEC VTL # KGPW 14.10.09 166.41

45 SER G-453/Geeta Horiz. Boring Machine # KGPW 29.12.09 235.75

46 SEC OP-1498/Continental Load Box # RI 11.12.07 42.85

47 SWR OP-1649/AMTINT EOT - 15 T UBL 23.01.09 42.50

48 SWR OP-1764/Krane EOT Crane 7.5T KJM 27.12.09 29.08

49 WR OP-1417/HYT Underfloor Wheel Lathe # RTM 27.08.08 342.67

50 WR OP-1629/Unique EOT- 30T PL 26.07.09 75.53

51 WR OP-1801/HYT AJTB Lathe # BVP 28.12.09 159.08

52 CLW OP-1643/Unique EOT - 50T CLW 03.02.09 145.61

53 CLW OP-1643/Unique EOT - 50T CLW 12.03.09 145.61

54 DLW G-267/HMT CNC Machining Centre # DLW 07.04.08 261.08

55 DLW G-277/TAL Travel Col. Radial Drilling M/c DLW 10.04.09 437.71

56 DLW G-432/HEC Radial Drilling M/c DLW 28.08.09 103.86

57 DLW OP-1815/Premier CNC VTL DLW 19.11.09 224.77

58 DLW G-416/Hindhydeng Power Press # @ DLW 02.06.09 258.42

59 DLW OP-1765/Premier Gear Hobber @ DLW 06.10.09 194.24

60 ICF OP-1390/Bemco Wheel Press # ICF 24.04.09 86.95

61 ICF OP-1670/Global Automatic Painting System # ICF 13.06.09 173.77

62 ICF OP-1664/METCO Traveser # ICF 25.07.09 113.31

63 ICF OP-1625/Meeka EOT Crane 5T ICF 21.11.09 28.75

Page 27: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

26 

 

64 ICF OP-1791/PMT CNC Turning Center # ICF 16.01.10 174.72

65 ICF OP-1808/Escorts Road Mobile Crane ICF 18.01.10 86.72

66 RWF OP-1698/HYT CNC VTL # RWF 24.09.09 224.44

67 RWF OP-1655/Unique EOT Crane 10 T # RWF 16.11.09 250.15

68 RWF OP-1655/Unique EOT Crane 10 T # RWF 16.11.09 250.15

69 RWF G-366/Groupodanobat Axle Machining Line # RWF 07..12.09 4354.47

70 RWF OP-1709/Premier Spl. Purpose Boring M/c # RWF 04.01.10 479.10

71 DMW OP-1505/Sunkap Double End Mill & Centre @ DMW 08.10.07 69.43

72 DMW OP-1569/EFD Induction Hardening M/c # DMW 07.07.08 197.79

73 DMW OP-1751/Avon EOT-30T DMW 02.06.09 101.22

74 DMW G-420/Precision Robotic Welding M/c # DMW 08.08.09 425.09

75 DMW OP-1515/J. Perrot CNC VTL # DMW 10.12.09 326.14

76 DMW G-440/Baykal Shearing Machine # @ DMW 03.11.09 33.22

77 RCF G-224/Trumpf CNC Laser Cutting M/c # RCF 20.05..05 253.02

78 RCF OP-1452/Global Baking Oven # RCF 18.02.07 96.64

79 RCF G-317/Hind Hydraulics Shearing Machine # RCF 28.07.08 150.19

80 RCF OP-1573/EMS Stripping Machine # RCF 29.01.09 111.15

81 RCF OP-1743/Precision CNC Plasma Profile Cutting M/c # RCF 16.04.09 201.47

82 RCF G-474/Unique Skining Tensioning Equipment RCF 21.11.09 130.86

83 RCF G-474/Unique Skining Tensioning Equipment RCF 21.11.09 130.86

84 RCF G-474/Unique Skining Tensioning Equipment RCF 21.11.09 130.86

85 RCF G-474/Unique Skining Tensioning Equipment RCF 21.11.09 130.86

86 RCF G-474/Unique Skining Tensioning Equipment RCF 21.11.09 130.86

87 RCF OP-1862/Hydropack Bogie Testing M/c RCF 25.11.09 47.87

TOTAL 21666.94

# - Tender on Turnkey

C - M/c commissioned but commissioning certificate yet to bissued.

Page 28: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

27 

 

Annexure-IV

Status of EOE Cases Under Process         

* Rs. In Lakhs            

S. No.

Tender no.

Descrip of M/c Qty. Consignee Initial

Cost Enhanced Cost

Presently with

Since Dt. of 1st submission

Status

1  G-410 Rail‐Cum‐Road‐Vehicle  1 

JBP  WCR 

500.00 

906.88       

  

2  OP-1849

Oil Fired Bogie Hearth Furnace  1 

GOC SR 

18.84 

55.48       

  

3 OP‐1849 

Normalising Furnace 

GOC SR 

21.28 

58.75       

  

Page 29: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

28 

 

ANNEXURE-V

  The following information  regarding maintenance of 140 T Diesel Breakdown Cranes on respective Railways may please be brought for discussion during the Conference:- Location of the Crane 1. Has the crane been provided with

equipment, manpower, spares and space to carry out maintenance schedules as prescribed by RDSO?

2. Ability of Divisional machinery to handle all the schedules.

3. Existence of AMC for handling higher level schedules

4. Are the spares being procured only from the OEM or their authorised dealers?

5. Is there sufficient stock of spares for the next 1-2 years? Are perishable or short shelf-life spares such as gaskets and seals being procured at the correct intervals?

6. Is the safe load indicator functioning?

7. Has a load proving test been carried out in the recent past?

8. Are the cranes fit for 100 kmph travel? If not, plan for the same?

9. Availability of spare wire ropes of the approved standard?

Page 30: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

29 

 

Planhead-42 1. Utilization of funds Railway-wise utilization of funds during 2009-10, Budget Grant 2010-11 and utilization

of funds upto July, 2010 are given in Annexure-I. It is heartening that CR, ECR, NCR, NFR, SCR, SWR, WCR & ICF have exceeded

50% of their outlays. Notable poor performers are ECoR, ER, NER, NR, NWR, SR, WR, CLW, DLW, RCF & RWF.

2. Detailed estimates pending

Railway-wise summary of detailed estimates pending is at Annexure-II. The complete list of works with pending detailed estimates is placed at Annexure-III.

3. Works more than 4 years old A Railway-wise list of works, more than 4 years old, is attached at Annexure-IV wherein

less than 50% of the cost expenditure has been met. These works need to be reviewed for speedy implementation.

4. New workshops and other major projects

The following projects have been approved in the Supplementary Demands for Grants (August, 2010):

1. DMU factory at Sankrail 2. ICF – Expansion and modernization. 3. Badnera wagon repair shop – POH of wagons. 4. Centre of excellence in wagon prototyping in Railway workshops. 1st such centre at

Kharagpur workshop. 5. Rail Axle factory in New Jalpaiguri 6. MLR workshop at Anara (Adra) for 250 coaches. 7. Wagon manufacturing factory at Guwahati 8. Wagon manufacturing factory at Haldia. 9. Erode diesel shed – Augmentation of homing capacity from 100 to 150 locos. 10. Gooty diesel shed – Augmentation of homing capacity to 150 locos. 11. Rail Wheel Factory - Replacement of Ax le forging machine.

    

Page 31: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

30 

 

Annexure-I

Fund Utilization under Planhead-42

(Rs. in crores)

Railway Actual 2009-10

Budget grant 2010-11 Utilization upto July’10 (Approx).

% Utilisation

CR 39.24 21.00 10.92 52.00% ECoR 24.08 13.52 3.23 23.89% ECR 30.96 37.64 34.38 91.34%

ECR/WP 403.05 405.39 43.01 10.61% ER 85.32 94.55 17.31 18.31%

NCR 19.24 34.19 21.00 61.44% NER 28.18 30.46 6.58 21.60% NFR 18.59 4.16 6.14 147.60% NR 43.94 37.62 13.61 36.18%

Rai Bareilly 12.01 100.00 3.26 3.26%

NWR 11.00 30.78 3.52 11.44% SCR 43.24 20.20 14.67 72.62%

SECR 13.57 11.22 5.51 49.11% SER 47.47 24.79 10.59 42.72% SR 44.08 49.48 10.88 21.98%

SWR 45.39 25.18 19.81 78.70% WCR 30.12 18.40 17.21 93.53% WR 130.26 86.59 27.63 31.91%

Sum IR 1069.74 1045.17 269.26 25.76% CLW 15.75 61.08 4.02 6.58% DLW 20.99 22.11 4.80 21.71% DMW 3.13 4.84 1.25 25.83% ICF 29.46 13.59 13.56 99.85% RCF 83.22 33.53 6.70 19.98% RWF 19.29 15.13 1.10 7.27%

Metro (Kolkata) 0.05

Sum PU 171.84 150.33 31.43 20.92% Grand Total 1241.58 1195.50 300.69 25.15%

Page 32: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

31 

 

Annexure-II Summary of Pending detailed estimates

Railway 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 Total

CR 2 2

ECoR 2 3 1 6

ECR 1 1 1 4 7

WP/ECR 2 2 4

ER 3 4 9 16

NCR 1 2 3

NER 1 2 3

NFR 2 2

NR 4 3 8 5 4 24

NWR 2 1 3

SCR 1 6 8 15

SECR 1 1 1 3

SER 7 3 10

SR 1 2 3 6

SWR 4 1 5

WCR 2 2

WR 1 5 6

CLW 1 5 6

DLW 1 1

DMW 2 2

ICF 0

RCF 1 1

RWF 2 2

Total 7 12 19 40 51 129

Page 33: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

32 

 

Annexure-III Estimate pending

(Rs. in crores)

Rly Year of

approval Pink Book No

Location Description Cost Expn. upto 3/10

Outlay 2010-11

Balance

CR 2010-11 305 Wadi Bunder Four maintenance sidings and extension of IOH shed.

23.31 0.00 0.05 23.26

CR 2010-11 306 Bhusawal Electric loco workshop - Augmentation of capacity of wheel sets manufacturing.

3.50 0.00 0.05 3.45

ECoR 2009-10 372 Vishakhapattnam

Electric Loco Shed - Augmentation of homing capacity of electric locos to 175.

12.61 0.10 0.05 12.46

ECoR 2008-09 370 Cuttack Development of freight train examination and sick line facilities for premium rakes.

2.99 1.40 0.50 1.09

ECoR 2007-08 369 Khurda Road Development of infrastructure facilities for freight train examination yard and sick line.

2.57 0.72 0.50 1.35

ECoR 2008-09 371 Mancheswar Augmentation of POH capacity of workshop to 150 coaches per month

25.74 3.15 1.63 20.95

ECoR 2010-11 374 Mancheswar Addition of two integrated washing pit lines.

15.24 0.00 0.05 15.19

ECR 2007-08 446 Dalmianagar Setting up of freight bogie and coupler manufacturing plant for high capacity higher axle load wagons (Phase-I).

97.00 46.00 1.00 50.00

ECR 2007-08 447 Mughalsarai Smart yard facilities at Down departure yard.

33.00 0.00 0.05 32.95

ECR 2009-10 457 Rajendranagar

Coaching complex - Extension of sick line.

3.06 0.00 0.05 3.01

ECR 2008-09 455 Khagaria Setting up of concrete sleeper plant.

8.24 0.05 0.10 8.09

ECR 2006-07 438 Sonpur Setting up of wagon periodic overhauling workshop.

89.20 13.87 0.50 74.83

ECR 2006-07 439 Marhoura Setting up of diesel locomotive manufacturing unit.

2052.00

23.60 15.00 2013.40

ECR 2007-08 450 Madhepura Electric loco factory. 1293.57

47.86 15.00 1230.71

ECR 2010-11 459 Mughalsarai Repair of unloable wagons. 14.00 0.00 0.05 13.95ECR 2010-11 460 Patratu Provision of covered shed and

heavy duty flooring for repair of unloable wagons.

4.84 0.00 0.02 4.82

ECR 2010-11 461 Narayanpur Anant

Provision of wagon routine overhauling depot.

9.69 0.00 0.05 9.64

ECR 2010-11 462 Barauni Setting up of new loco shed to home 100 electric locos.

49.60 0.00 0.05 49.55

Page 34: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

33 

 

ER 2009-10 530 Kanchrapara Workshop - Augmentation of capacity for POH of 40 motor & 80 trailer coaches per month.

59.65 0.00 1.00 58.65

ER 2009-10 531 Naopara Construction of repair workshop for undertaking mid-life rehabilitation of coaches (300 coaches per annum).

147.00 0.00 0.10 146.90

ER 2009-10 533 Majerhat Setting up of wagon component factory for manufacture of high capacity bogies, couplers and draft gear.

100.00 0.00 0.10 99.90

ER 2008-09 523 Malda Upgradation of freight train examination yard and sick line facilities to 'A' category.

8.80 0.00 0.05 8.75

ER 2008-09 520 Narkeldanga Car Shed

Additional pit on line No.4 & shed on line No.3 & 4 for 12 coach rakes formation.

6.00 0.37 0.05 5.58

ER 2009-10 534 Howrah Remodelling of diesel shed. 3.00 0.01 0.05 2.94ER 2010-11 536 Howrah,

Bandel Additional maintenance facilities for car shed (Phase-II) for running of 12 coach EMU trains.

10.80 0.00 0.05 10.75

ER 2010-11 541 Andal Up sick line - Extension of heavy duty cover shed with EOT crane gantry.

4.70 0.00 0.05 4.65

ER 2010-11 539 Jamalpur Diesel loco shed - Basic infrastructure for maintenance of DEMUs.

4.00 0.00 0.05 3.95

ER 2010-11 543 Sealdah Development of coaching maintenance infrastructure.

66.00 0.00 0.05 65.95

ER 2010-11 537 Barasat Extension of inspection pits and shed (line no. 3 & 4) for maintenance of 12 coach EMU rakes of carshed.

2.82 0.00 0.05 2.77

ER 2010-11 542 Tikiapara Remodelling of coaching yard (Phase-II).

44.38 0.00 0.01 44.37

ER 2010-11 538 Sonarpur Extension of shed over pit line no. 3, 4, 5 & 6 independent shunting neck and additional catwalk, stabling line, development of low land in connection with running of 12 coach at carshed.

6.00 0.00 0.05 5.95

ER 2010-11 540 Beliaghata Diesel loco shed - Upgradation to WDS6/WDM2 loco shed from WDS4B locos.

4.00 0.00 0.05 3.95

ER 2010-11 544 Kanchrapara New Rail Coach manufacturing unit.

860.16 0.00 20.00 840.16

NCR 2008-09 473 Sithouli Rail Spring Karkhana - Renewal of existing spring coiling line.

40.00 0.05 0.40 39.55

NCR 2010-11 479 Baad Upgradation of facilities for premium end to end train examination at Tank wagon

3.60 0.00 0.05 3.55

Page 35: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

34 

 

depot.

NCR 2010-11 480 Kanpur Augmentation of holding capacity from 150 to 175 electric locos.

9.65 0.00 0.05 9.60

NER 2009-10 192 Lucknow Extension of sick line covered shed in new broad gauge coaching complex.

3.58 0.00 0.40 3.18

NER 2010-11 199 Gonda Construction of routine overhauling depot.

33.91 0.00 0.05 33.86

NER 2010-11 200 Manduadih Construction of one no. washing pit as per CAMTECH design.

4.77 0.00 0.05 4.72

NFR 2009-10 173 Kishanganj Development of coaching maintenance facilities.

6.65 0.00 0.01 6.64

NFR 2009-10 178 New Guwahati

Diesel shed - Diesel electrical multiple unit maiintenance shed.

3.49 0.00 0.01 3.48

NR 2007-08 629 Ghaziabad EMU Car Shed - Extension of heavy repair shop.

4.42 2.88 0.05 1.48

NR 2007-08 631 Ferozpur, Pathankot, Jullunder Cantt.

Facilities for maintenance of RPC-IV trains.

4.46 0.05 0.05 4.36

NR 2009-10 644 Lucknow Modernisation of Alambagh workshop (Phase-I).

77.42 0.10 0.20 77.12

NR 2009-10 645 Anand Vihar 3 additional washing lines. 19.32 0.10 3.50 15.72NR 2009-10 646 Amritsar Workshop - Additional shed

with EOT cranes for manufacturing stainless steel BOXN HL wagons and air suspension bogies.

7.10 0.10 0.50 6.50

NR 2009-10 647 Jagadhri Workshop - Facilities for increasing monthly air conditioned coach periodical overhauling out-turn from 18 to 30 coaches.

3.98 0.10 3.00 0.88

NR 2009-10 648 Ghaziabad Extension of electric loco shed from 120 to 150 locos.

17.36 0.10 0.05 17.21

NR 2006-07 623 Jagadhri Workshop - Provision of paint booth.

6.77 0.00 0.11 6.67

NR 2006-07 634 Hazrat Nizamuddin

Extensive repairs and complete renovation of old washing lines (5 Nos.) at coach care centre.

30.00 2.00 2.00 26.00

NR 2006-07 626 Northern Railway

Infrastructure facilities for implementation of revised policy circular-IV for coaching stock (8 stations).

9.74 1.05 0.05 8.64

NR 2006-07 627 Rai Bareilly Setting up of new Rail Coach Factory.

1685.00

204.44 100.00 1380.56

NR 2007-08 635 Northern Railway

Trials with freight Miser ™ System for electric and diesel locomotives.

4.00 0.03 0.01 3.96

Page 36: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

35 

 

NR 2008-09 641 Alambagh Diesel shed - Augmentation of holding capacity from 100 to 175 locomotives and development of facilities for maintenance of GM locomotives.

8.69 1.54 0.40 6.75

NR 2008-09 640 Tughlakabad (Wagon Care Centre) - Augmentation of ROH capacity of BLC wagons.

4.50 2.50 0.40 1.60

NR 2008-09 638 Charbagh Workshop - Optimization of capacity of shops, improvement in infrastructure decongestion crane gantries etc.

17.09 2.09 5.10 9.89

NR 2008-09 636 Lucknow Setting up of main line electrical multiple unit car shed (10 rakes).

18.88 3.12 0.05 15.71

NR 2008-09 637 Khanalampura

Setting up of new electric loco shed for homing 100 locos.

60.80 16.02 4.00 40.79

NR 2008-09 642 Ludhiana, Amritsar

Development of mandatory facilities for terminal examination.

3.50 0.05 0.05 3.40

NR 2008-09 643 Lucknow Replacement/extension & designing old coaching shed at sick line for operating the 20 Ton EOT crane in coaching shed.

2.50 0.15 0.05 2.30

NR 2008-09 639 Lucknow Washing lines ( 600 Mtr each), (2 Nos. each) stabling lines & spurs for mini sick line at good shed area.

6.20 0.74 0.87 4.59

NR 2010-11 650 Ludhiana Upgradation of facilities for increased holding of diesel locomotives from 140 to 170 at diesel shed.

7.78 0.00 0.05 7.73

NR 2010-11 651 Charbagh Creation of facilities for IOH of 60 coaches per month in Loco shop Charbagh.

12.43 0.00 0.05 12.38

NR 2010-11 652 Ghaziabad Loco shed - Augmentation of holding capacity of electric locos from 150 to 175 AC locos.

8.00 0.00 0.05 7.95

NR 2010-11 653 Ludhiana Loco shed - Augmentation of holding capacity of electric locos from 150 to 175 AC locos.

8.00 0.00 0.05 7.95

NWR 2007-08 232 Barmer Terminal

Integrated coach care complex. 3.33 0.00 0.05 3.28

NWR 2007-08 233 Lalgarh Freight train examination facilities in Lalgarh yard.

3.20 0.00 0.01 3.19

NWR 2009-10 237 Bhagat Ki Kothi

Augmenting capacity of diesel shed for accommodating 50 EMD locos.

6.47 0.01 2.00 4.46

SCR 2009-10 443 Kacheguda Carriage & wagon depot - Conversion of stabling line into 4th pit line and provision of one stabling line.

6.60 0.00 0.10 6.50

Page 37: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

36 

 

SCR 2009-10 448 Rayanapadu Modernisation of wagon workshop.

61.71 0.00 2.00 59.71

SCR 2009-10 444 Nanded Carriage & Wagon Depot - Extension of sick line shed/ intermediate overhauling shed & service buildings.

3.50 0.00 0.10 3.40

SCR 2009-10 445 Gooty Diesel loco shed - Augmentation of berthing capacity of locomotives (3 Nos.).

3.34 0.00 0.10 3.24

SCR 2009-10 446 Kacheguda Carriage & Wagon Depot - Upgradation of pit lines (No.1 & 2).

3.68 0.00 0.50 3.18

SCR 2009-10 447 Hyderabad Coaching depot - Catwalk between line No.9 & 10 and No.11 & 12.

4.32 0.00 0.30 4.02

SCR 2007-08 431 Gooty Detachment free examination facilities for CC rake maintenance.

15.50 0.00 0.50 15.00

SCR 2010-11 450 Guntur Provision of additional pit line of 560m as per CAMTECH design.

5.71 0.00 0.05 5.66

SCR 2010-11 451 Lallaguda Construction of new shed of size 10m x 17.5m for IOH of bogies to feed the coaching depots of Secunderabad, Hyderabad, Kacheguda and Nanded.

9.74 0.00 0.05 9.69

SCR 2010-11 452 Maulali Diesel loco shed - Creation of facilities for homing 6 DEMU rakes.

5.06 0.00 0.05 5.01

SCR 2010-11 453 Guntur Provision of IOH shed at coaching depot.

4.92 0.00 0.05 4.87

SCR 2010-11 454 Tirupati Converstion of washing line to pit line at coaching depot.

3.94 0.00 0.05 3.89

SCR 2010-11 455 Kazipet Augmentation of holding capacity of Electric loco shed from 100 AC locos to 125 AC locos.

10.00 0.00 0.05 9.95

SCR 2010-11 456 Tirupati Conversion of stabling line into pit line.

3.46 0.00 0.05 3.41

SCR 2010-11 457 Gooty Diesel loco shed - New shed for WDG4 loco maintenance.

8.72 0.00 0.05 8.67

SECR 2009-10 256 Korba Upgradation of freight maintenance facilities.

4.46 0.00 0.40 4.06

SECR 2008-09 253 Raigarh New Electric loco shed with holding capacity of 100 locos.

30.00 0.00 0.50 29.50

SECR 2010-11 260 Raipur Diesel shed - Expansion of capacity to home WDG4 locos.

23.25 0.00 0.05 23.20

SER 2009-10 394 Bokaro Steel City

Extension of routine overhauling depot for maintenance of block rake with covered shed.

8.30 0.00 0.30 8.00

SER 2009-10 393 Adityapur New routine overhauling shed for air brake stock.

7.80 0.00 0.40 7.40

Page 38: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

37 

 

SER 2009-10 396 Bondamunda Electric loco shed - Extension of Chakradharpur end by 28.5 m to increase loco holding to 175.

7.29 0.00 0.30 6.99

SER 2009-10 397 Tatanagar Extension of wheel shop at centralised traction repair centre.

2.71 0.00 0.40 2.31

SER 2009-10 398 Bokaro Steel City

Upgradation of premium rake examination facilities at empty yard.

4.37 0.00 0.30 4.07

SER 2009-10 399 Bhojudih Augmentation of sick line facilities at carriage & wagon examination point.

5.59 0.00 0.30 5.29

SER 2009-10 400 Bokaro Augmentation of old sick line with EOT crane facility.

7.50 0.00 0.25 7.25

SER 2010-11 404 Tatanagar Extension of heavy lifting bay and light lifting bay and creation of maintenance facilities for homing of WAG-9 locomotives.

7.00 0.00 0.05 6.95

SER 2010-11 403 Hatia Construction of 2 nos. of integrated washing cum pit lines of 26 coach length (585 m) at coaching depot.

13.51 0.00 0.05 13.46

SER 2010-11 405 Tikiapara Extension of inspection pit and stabling pits, covered shed with lighting arrangement and modification of car shed for masintenance of 12 car rakes.

4.04 0.00 0.05 3.99

SR 2006-07 511 Alleppey Setting up of plant for manufacture of fabricated rolling stock components of coaching stock.

85.00 0.00 0.00 85.00

SR 2008-09 523 Southern Railway

Other end facilities for platform turn-around trains (50 platforms).

12.75 0.32 1.00 11.43

SR 2009-10 524 Arakkonam Electric loco shed - Augmentation of infrastructural facilities to increase holding capacity from 120 to 150 locos.

9.64 0.01 1.50 8.13

SR 2009-10 525 Perambur Modernisation of carriage & wagon workshop.

43.78 0.01 1.50 42.27

SR 2008-09 521 Tondiarpet, Irumpanam, Jolarpet

Conversion of ROH depot from vacuum to air brake stock - maintenance facilties for repair of unloadable wagons.

34.97 0.10 0.50 34.37

SR 2009-10 527 Ponmalai Diesel shed - Creation of infrastructure facilities to home and maintain WDP4/WDG4 locos.

10.00 0.01 0.50 9.49

SWR 2009-10 277 Yeshvantpur 4th pit line for 26 coach capacity with both side catwalk.

5.76 0.01 1.00 4.76

SWR 2009-10 278 Hubli Division

Other end examination facilities (7 stations).

3.41 0.00 0.50 2.91

SWR 2009-10 279 Hubli Extension of pit line No.1 & 2 to 600 m length each.

3.04 0.00 0.50 2.54

Page 39: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

38 

 

SWR 2009-10 280 Vasco da Gama

Additional pit line (Road No.7). 4.93 0.00 0.50 4.43

SWR 2010-11 282 Hubli EMD shed - Expansion of homing capacity from 150-200 locos.

18.70 0.00 0.05 18.65

WCR 2010-11 404 Bhopal CRWS - Additional infrastructure for carrying out bogie IOH.

8.80 0.00 0.05 8.75

WCR 2010-11 405 Jabalpur Construction of one 20 coach pit line and one stabling line at old loco shed.

6.52 0.00 0.05 6.47

WR 2009-10 406 Sabarmati Augmentation of diesel shed capacity for homing 100 BG EMD locos.

10.00 0.01 0.05 9.94

WR 2010-11 408 Porbandar Providing new sick line shed with 10 ton EOT crane at coaching depot.

4.51 0.00 0.05 4.46

WR 2010-11 411 Valsad Augmentation of holding capacity from 100-125 locos.

8.00 0.00 0.05 7.95

WR 2010-11 410 Vadodara Augmentation of homing capacity of Electric loco shed from 150 to 175 locos.

7.40 0.00 0.05 7.35

WR 2010-11 409 Sabarmati Setting up of mega (base) DEMU depot.

26.00 0.00 0.05 25.95

WR 2010-11 412 Dahod Augmentation of mid term rehabilitatiion capacity from 54 to 108 electric locos per annum.

28.00 0.00 0.05 27.95

CLW 2009-10 11 Dankuni Setting up of electric loco assembly and ancillary unit of Chittaranjan Locomotive Works.

65.32 1.00 50.00 14.32

CLW 2010-11 13 Chittaranjan Replacement of OH crane line at shop at (i) MAU shop No.25, 26, 17, 18 & 12 (ii) TM shop, Bay No.0 to 5 (iii) SF - total length 4000m and proposed reflooring of damaged shop floor at (i) MAU shop No.26,17,5&12.

3.30 0.00 0.05 3.25

CLW 2010-11 14 Chittaranjan Re-flooring of shop floor at Steel Foundary.

4.32 0.00 0.05 4.27

CLW 2010-11 15 Chittaranjan Thorough replacement of damaged AC sheet and wall up at SF.

3.00 0.00 0.05 2.95

CLW 2010-11 16 Chittaranjan Modernisation of CLW for augmentation of productiion capacity from 200 electric locos to 250 electric locos per annum.

45.38 0.00 0.05 45.33

CLW 2010-11 17 Chittaranjan Centre of excellence for design, development & evaluation of advanced technology systems for electrical rolling stock.

42.00 0.00 0.01 41.99

DLW 2007-08 06 Varanasi Provision of reliable power supply.

40.00 10.00 5.00 25.00

Page 40: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

39 

 

DMW 2010-11 03 Patiala Extension of loco stripping shop with two rooms in workshop area.

4.59 0.00 0.10 4.49

DMW 2010-11 04 Patiala Extension of TMS workshop area.

2.85 0.00 0.05 2.80

Metro Kolkata

2009-10 23 Naopara Rake rehabilitation facility. 69.61 0.00 0.00 69.61

RCF 2010-11 14 Kapurthala Extension of finishing shop towards shower testing area.

3.60 0.00 0.05 3.55

RWF 2009-10 06 Bangalore Extension to new scrap pre-conditioning bay (132 m x 30 m) and extension of old bay (66 m x 30 m).

8.51 0.01 0.50 8.00

RWF 2009-10 07 Bangalore Augmentation of infrastructure facility for road movement of steel scrap and wheel tyre axle items (parking lots B & C).

3.65 0.01 0.50 3.14

Page 41: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

40 

 

Annexure-IV List of works, older than 4 years and with less than 50% cost expenditure

(Rs. in crores) Rly Year of

approval Pink Book No

Location Description Cost Expn upto 3/10

Outlay 2010-11

Balance

CR 2006-07 289 Kalyan Diesel shed - Augmentation of infrastructure for holding 60 locos.

5.00 2.17 0.79 2.03

CR 2002-03 288 Parel Workshop - Facilities for in-house manufacture of composite brake blocks.

6.14 0.46 4.68 1.00

ECoR 2006-07 359 Visakhapatnam (Waltair)

Augmentation of electric loco shed to home 150 locomotives.

7.25 3.39 0.05 3.81

ECoR 2006-07 LB Paradeep Yard Infrastructural facilities for freight train maintenance.

1.77 0.83 0.00 0.95

ECoR 2006-07 360 Visakhapatnam Diesel loco shed - Augmentation of infrastructural facilities.

4.04 1.47 0.60 1.98

ECoR 2006-07 361 Bhubaneswar Augmentation of infrastructural facilities of coaching depot.

8.71 1.60 0.35 6.75

ECR 2003-04 427 Harnaut Setting up of workshop to undertake POH of upto 50 coaches.

334.00 117.02 70.39 146.58

ECR 2006-07 437 Samastipur Workshop - Facilities for repair of 'C' category unloadable wagons.

32.03 5.00 10.00 17.03

ECR 2006-07 438 Sonpur Setting up of wagon periodic overhauling workshop.

89.20 13.87 0.50 74.83

ECR 2006-07 432 Samastipur Augmentation of holding capacity of diesel shed from 50 locos to 100 locos.

7.92 1.04 5.88 1.00

ECR 2006-07 435 Patherdih Upgradation of marshalling sick line with provision of EOT crane and heavy duty flooring.

2.75 0.23 0.05 2.47

ECR 2005-06 428 Jhajha Development of additional facilities at MEMU shed (Phase-II).

3.75 0.30 0.10 3.35

ECR 2006-07 439 Marhoura Setting up of diesel locomotive manufacturing unit.

2052.00

23.60 15.00 2013.40

ECR 2001-02 426 Darbhanga Provision of integrated sick line facilities for coaches.

2.55 0.00 0.05 2.50

ECR 2006-07 431 Mughalsarai Wheel repair (RA & RD) facilities at Box'N' depot.

6.94 0.00 3.00 3.94

ER 2006-07 509 Tikiapara Remodelling of coaching yard. 24.51 11.84 0.50 12.18ER 2001-02 499 Ranaghat EMU car shed. 25.37 11.66 5.00 8.70ER 2006-07 505 Jamalpur Workshop - Extension of

Casnub Bogie shop. 5.00 2.05 0.50 2.45

Page 42: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

41 

 

ER 2005-06 LB Andal Upgradation of freight train examination yard (Up yard/CC rake base yard) to 'A' category.

1.58 0.57 0.00 1.01

ER 2006-07 508 Liluah Workshop - Facilities for overhauling of new generation coaches including upto 26 M long coaches.

20.00 7.08 2.70 10.21

ER 2005-06 LB Andal Augmentation of infrastructure facilities to upgrade Dn sick line to 'A' category.

1.53 0.52 0.00 1.01

ER 2006-07 510 Liluah Sorting yard - Development of coaching mainenance facilities phase-III.

14.01 4.43 0.50 9.08

ER 2005-06 LB Andal Upgradation of freight train examination facility at empty yard to 'A' category.

1.57 0.50 0.00 1.08

ER 2005-06 LB Andal Augmentation of infrastructure facilities to upgradate DSEY sick line to 'A' category.

1.53 0.35 0.00 1.18

ER 2006-07 LB Naihati Upgradation of maintenance facilities in Freight train examination yard to 'A' category.

2.03 0.36 0.00 1.67

ER 2006-07 506 Jamalpur Workshop - Extension of GIF & SF towards north side.

15.97 2.21 0.50 13.27

NCR 2001-02 461 Sithouli Rail Spring Karkhana - Additional infrastructure facilities for manufacture of FIAT & IR 20 bogie spring.

45.72 22.00 3.89 19.83

NCR 2005-06 LB Jhansi Provision of shed for POH of tank wagons in Timber Yard of Jhansi Wagon repair workshop.

0.37 0.16 0.00 0.21

NCR 2006-07 464 Kanpur Upgradation of Allahabad, Aligarh Jn., Agra Cantt., Kanpur Central, Gwalior & Jhansi stations, facilities including infrastructure and overhauling.

6.94 1.50 0.01 5.43

NCR 1999-00 LB Allahabad Augmentation of facilities including tamping Bank at (CPOH) workshop.

0.35 0.01 0.00 0.35

NER 2005-06 LB Gorakhpur Upgradation of freight examination point.

1.43 0.00 0.00 1.43

NR 2006-07 624 Tughlakabad Detachment free freight train examination facilities.

30.99 11.69 0.05 19.25

NR 2005-06 LB Lucknow Upgradation of freight stock examination facilities at yard.

1.40 0.44 0.00 0.97

NR 2006-07 LB Hazrat Nizamuddin

Development of mandatory facilities for terminal examination (4 stabling lines).

1.79 0.50 0.00 1.29

NR 2006-07 LB Khanalampura Extension of covered shed with provision of gantry for EOT crane.

1.15 0.30 0.00 0.85

Page 43: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

42 

 

NR 2005-06 LB Tughlakabad Upgradation of freight examination point.

2.45 0.56 0.00 1.88

NR 2006-07 LB Tughlakabad Upgradation of ROH depot. 2.29 0.50 0.00 1.79NR 2005-06 LB Delhi Development of mandatory

facilities on stabling lines for terminal examination.

1.64 0.28 0.00 1.36

NR 2006-07 627 Rai Bareilly Setting up of new Rail Coach Factory.

1685.00

204.44 100.00 1380.56

NR 2006-07 LB Lucknow High pressure jet cleaning system with ground water supply for washing lines.

1.30 0.15 0.00 1.15

NR 2006-07 626 Northern Railway Infrastructure facilities for implementation of revised policy circular-IV for coaching stock (8 stations).

9.74 1.05 0.05 8.64

NR 2006-07 634 Hazrat Nizamuddin

Extensive repairs and complete renovation of old washing lines (5 Nos.) at coach care centre.

30.00 2.00 2.00 26.00

NR 2004-05 617 Rishikesh Washing & stabling lines of 18 coach capacity.

3.45 0.10 0.05 3.29

NR 2006-07 625 New Delhi Well lighted covered shed on washing lines no.11 & 12 for maintenance of high speed trains and to facilitate all weather working at depot.

5.58 0.00 0.05 5.53

NR 2006-07 623 Jagadhri Workshop - Provision of paint booth.

6.77 0.00 0.11 6.67

SCR 2006-07 LB Gooty Upgradation of infrastructural facilities for freight train examination.

1.85 0.72 0.00 1.13

SCR 2004-05 425 Vijayawada Cat-walks on both sides of pit lines on LV5, LV6 & LV7 (2506m).

3.36 0.04 0.15 3.17

SECR 2006-07 245 Bhilai Augmentation of main line electrical multiple unit car shed from 5 to 15 rakes (Phase-I).

5.87 2.82 2.74 0.31

SER 2006-07 386 Tatanagar Augmentation of coaching maintenance facilities.

17.50 8.50 0.50 8.50

SER 1996-97 392 Bokaro Setting up of electric loco shed to home 100 locos.

43.00 18.21 2.00 22.78

SER 2006-07 395 Santragachi Extensiion of Electric Loco shed for homing 50 locomotives.

3.18 1.25 0.83 1.10

SR 2005-06 507 Royapuram Intermediate overhauling workshop/zonal base depot for track machine.

3.67 0.37 0.50 2.81

SR 2006-07 511 Alleppey Setting up of plant for manufacture of fabricated rolling stock components of coaching stock.

85.00 0.00 0.00 85.00

SWR 2006-07 265 Arsikere & Sakleshpur

Fuel pads 2.50 1.03 0.01 1.46

Page 44: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

43 

 

SWR 2006-07 LB Mysore Workshops - Augmentation of overhauling facilities to 10 broad gauge air conditioned coaches.

1.95 0.70 0.00 1.25

SWR 2006-07 264 Castlerock & Hospet

Fuel pads 2.50 0.00 0.45 2.05

WCR 2003-04 383 Bhopal Carriage Repair Workshop - Augmentation of facilities for enhancing mid-life rehabilitation outturn capacity of coaches from 300 to 500 per year.

7.57 3.45 2.44 1.69

WCR 2005-06 386 Bhopal Augmentation of capcity for mid life rehabilitation of coaches from 500 to 750 per annum.

46.50 20.32 4.24 21.94

WR 2006-07 LB Hapa Upgradation of sick line and yard facilities.

2.31 1.01 0.00 1.30

WR 2002-03 404 Mumbai Central Coaching depot - LHB coach facilities.

3.89 1.07 0.05 2.77

WR 2006-07 LB Valsad One pit line & associated sick line facilities.

1.29 0.33 0.00 0.96

CLW 2006-07 08 Chittaranjan Upgradation and centralized control of electric ovens in traction motor shop.

3.00 1.20 0.80 1.00

CLW 2006-07 10 Chittaranjan Augmentation of facilities for enhancement in production capacity of 3-phase locos to 50 locos per year.

15.52 5.00 4.52 6.00

CLW 2006-07 LB Chittaranjan Renovation of underground drain at LMS and HMS.

0.31 0.04 0.00 0.27

ICF 2006-07 14 Perambur Augmentation of capacity for manufacturing of 1500 coaches per annum.

77.92 35.85 5.38 36.69

ICF 2006-07 LB Perambur Furnishing Division - Reconstruction of laboratory building.

1.26 0.55 0.00 0.71

ICF 2006-07 LB Perambur Separate trade effluent drainage system from all machines & wash points to main collection tank.

0.86 0.31 0.00 0.56

ICF 2004-05 11 Perambur Augmentation of spring manufacturing facilities.

37.96 1.58 0.39 35.98

RWF 2002-03 02 Bangalore Mechanisation of cuttring scrap wheel and disposal.

4.89 0.01 0.35 4.53

Page 45: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

44 

 

Development Items  

SN    Action By 1  Status of WILD: 

Nine  WILD  systems  have  been  deployed  on  the  Indian  Railways  at Mahalimarup/SER,  Hospet/SWR,  Bhilai/SECR,  Arakkonam/SR, Mughalsarai/ECR  (2nos.),  Guntakal/SCR,  Asansol/ER  and Vishakhapatnam/ECoR.   Another  six  for Nagpur/SECR, Ajni/CR, Bina/WCR, Itarsi/WCR, New  Katni/WCR  and  Barwadih/ECR  have  been  ordered.    Two (Nagpur‐SECR & Barwadih‐ECR) have reached the sites.  

 WILD  systems  have  been  under  criticism  for  generation  of  false  alarms. WILD  has  very  good  potential  of  improving  vehicle  condition,  however proper understanding and development of correct practices is required. 

 ED/Research,  RDSO  has  issued  explanatory  letters  and  reports  on  the subject. Several good reports have been received from various Railways. For example, SE Railway has reported that an accident was averted  in one case when  a  cracked  wheel  (along  with  metal  elongation  in  a  portion)  was detected by WILD while passing Mahalimarup/SER.  

 Zonal railways that have WILD systems should provide feedback to RDSO on their  experiences  with  WILD.    RDSO  shall  suggest  methods  of  how  the technology  can  be  improved  further  to  reduce  cases  of  false  alarms  and dovetail the data generated by WILD into improved maintenance for rolling stock.  

 SER  SWR  SECR  SR  SCR  ER  ECR  ECoR  CR  WCR  ED/Research, RDSO 

1.1  Acoustic  Bearing  Detector:    Another  important  way  side  monitoring equipment  is  Acoustic  Bearing  Detector.    A  pilot  implementation  of  the Acoustic Bearing Monitor has been done at Bakkas (Northern Railway).  The system has been commissioned in Jan, 2010.  The system validation process is  in  hand  as  this  system  requires  correlation  of  field  data  with  the associated  examination  results.    This  is  a  complex  imported  technology requiring  critical  initial  process  as  the  standards  pertaining  to  IR  systems need to be developed.  

 ED/Testing, RDSO 

2.0  Twenty two new weighbridges are under installation/commissioning (ECR‐7, SR‐5,  SER‐4,  ER‐2,  NCR‐2,  NWR‐1,  ECoR‐1).    Eleven  Electronic  in‐motion weighbridges  are  under  procurement  (SR‐3,  WR‐3,  ER‐2,  SER‐2,  CR‐1).  Activities pertaining to Electronic in‐motion weighbridges need to be closely monitored 

All Zonal Railways 

2.1  FOIS  interface  with  EIMWBs:    To  achieve  the  objective  of  integrating weighbridge with  FOIS  through  transfer  of weighment  data  seamlessly  to FOIS,  Amendment  No.  5  has  been  issued  vide  DG(Wagon)’s  letter  No. 

All Indian Railways  

Page 46: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

45 

 

MW/CS/PE/WB dated 18/19.02.2010. All new procurements of weighbridges should be made incorporating this amendment.   

ED/Wagon, RDSO 

3.0  Environmental Friendly Toilets: Salient  points  of  the  Environment  Friendly Green  Toilet  action  plan  under implementation are summarized below: 

  

3.1  Board  has  approved  trial  of  Vacuum  Retention  Toilets on  two  Shatabdi Rakes.  NR has given clearance for disposal of waste in the sewage system. 

NR  ED/Carriage, RDSO 

3.2  RDSO  has  floated  an  open  tender  for  one  rake  of  Zero Discharge  Toilet System, developed by RDSO & IIT/Kanpur.  

ED/Carriage RDSO 

3.3  RCF has  tendered  for 200 coaches  (784 Bio‐toilets)  for Multi  technologies/ vendors extended field trials. 

RCF 

3.4  Bio‐toilets with DRDE Bio‐digester  technology –  Railway Board has signed an MOU with DRDO  for  joint development of passenger coach  toilets.   RCF has  placed  order  for  50  tanks  (Bio‐digesters)  based  on  3  types  of  design options and is floating the tender for 4th option. RCF will turn out first rake in Oct’2010.  Train  No.  1123/1124  Gwalior‐Barauni  Express  has  been nominated. AMOC  for  these  coaches has  to be  finalised before  the  rake  is put in service by NCR.  ICF  should  finalise  the  design  of  Bio‐toilets  with  DRDE’s  Bio‐digester technology  and  expedite  the  production  of  coaches  fitted with  these  Bio‐toilets with a target to turn out the rake by Dec.’2010.  Train nomination for this rake will be done shortly by Board. 

NCR  RCF  ED/Carriage, RDSO     ICF  

3.5  Trial  of  new  technologies/products  ‐  With  a  view  to  support  efforts  to develop  innovative  solutions,  a  check  list  based  scheme  for  carrying  out limited  trials with bio‐toilets has been  launched.    Interested manufacturers may submit their proposal as per the Check List, ensuring that the technology developed by  them  is  implementable, cost effective and meets  the desired objectives.    This  check  list  is  available  on  RDSO’s  website <http://www.rdso.gov.in/carriage/bio_toilets/check_list.pdf>.  Two responses have been received and are under examination by RDSO. 

ED/Carriage RDSO 

3.6  Group  for   Excellence  in Green Toilets – Considering that toilet system  is a vast  technology  domain,  covering  complex  technology,  exploration  and development  processes,  a  Group  for  excellence  in  green  toilets  has  been formed with ED/IRCAMTECH as convener. The Group is working on finalising the specification for evacuation system for different types of Toilets  

ED/ IRCAMTECH  N.Rly  ED/C, RDSO RCF 

4.0  IT Applications  for Mechanical Department   4.1  A web based application “Workshop – MCDO” has been launched with POH  All  Railways 

Page 47: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

46 

 

Outturn module  successfully,  being  developed  in  house  in  CRIS  in  January 2010.  Based  on  users  input  and  feedback,  “Workshop  ‐ MCDO  v  2.0”  has been  redesigned  and  re‐launched  with  separate  modules  for  workshops, Headquarters, Railway Board and Report Modules. The performance data of workshops can be viewed by users at Workshops, Headquarters and Railway Board. Railways  should  continue  to provide  feedback  to CRIS  to  refine  the system  further.  The  URL  of  the  “Workshop  ‐ MCDO  v2.0”  is http://10.1.5.78:8081/MCDO/ railnet. 

 CRIS 

4.2  COFMOW’s periodic positions are available on  line on COFMOW’s website. Zonal Railways and Production Units can download these positions.  All Zonal Railways/PUs may use this system and provide feedback to COFMOW & CRIS for further improvements in the system.  COFMOW in collaboration with CRIS has also commissioned a Post Contract Management Module.    This Module was  launched  for  trial on NCR,  SWR, NCR,  ICF  and DLW  in December  09.    Subsequently,  this  system  has  been made  operational  for  all  Railways  and  Production  Units.    Following information has  to be updated  against each  supply order/contract by  the consignees/railway headquarters:  a)  Date of Machine Received b)  GA Drawing received c)  GA Drawing approved d)         Site handed over e)  Foundation Started f)  Foundation completed g)  Verification Date h)  Installation and Commissioning date i)  PTC issue date j)  Remarks  Following  table gives  indication of  the extent of  system used by different railways along with number of   LOAs  issued by COFMOW  for  that  railway since then:‐  SN  Rly  LOA Issued from 1.9.09 to 

31.8.09 No. of entries made by User Raillway/PU 

1  CLW  6  15 2  CR  29  379 3  DLW  25  152 4  DMW  09  18 5  ECO  14  62 6  ECR  21  62 

 COFMOW     CRIS       All  Zonal Railways/ PUs   

Page 48: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

47 

 

7  ER  47  138 8  ICF  12  168 9  NCR  22  08 10  NER  13  47 11  NFR  15  103 12  NR  41  104 13  NWR  07  49 14  RCF  02  356 15  RWF  0  47 16  SCR  28  57 17  SEC  19  25 18  SER  32  02 19  SR  27  93 20  SWR  37  143 21  WCR  21  26 22  WR  29  86 

 All  Railways  and  Production  Units  should  continue  the  use  this  system extensively  and  provide  feed  back  to  CME/PCM,  COFMOW  and  GM/P‐II, CRIS for further improvements/modifications required in the system  

4.3  Pilot project Loco Management System (LMS) has been launched in three Diesel Sheds of Northern Railway. Northern Railway and CRIS may report progress in terms of Hardware supply and Installation, Software development & customization and identification of core team at all levels with adequate training for taking over systems. Target date of completion is June 2011.

N.RLY   CRIS 

4.4  Pilot project Freight Management Manager (FMM) has been launched in two freight depots of Northern Railway and one freight depot of North Central Railway. CRIS and Railways may report progress of Hardware supply and Installation, Software development & customization and identification of core team at all levels with adequate training for taking over systems. Target date of completion is June 2011.

NR  NCR  CRIS 

4.5  CRIS has indicated that order for Workshop Information System - II (WISE-II) project is likely to be placed by November 2010 and the work is likely to commence in December 2010. WISE –II project covers thirty four workshops of Indian Railway out of which five workshops, namely LLH, LPL, R, LGD and CB have been identified for Pilot phase and balance twenty nine workshop will be taken up in the rollout phase. Users’ requirement and proposed network inputs

ER 

WR 

SCR 

NR 

SECR 

WCR 

Page 49: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

48 

 

have all ready been circulated to all Railways workshop wise by CRIS. Detailed system requirement study will be undertaken at five pilot locations and three more workshops namely BPL, KGP and PER after the work is awarded.

SER 

SR  

CRIS 

4.6  ICMS :   This project  is scheduled to be completed by the end of December 2010.   It  is, therefore,  important that suitable timely action  is taken by the user Depots/Divisions/Zonal Head quarters.  i) The core  implementation  teams with members  from Depots, Division 

and Zones have undergone training in September 2010.  ii) The User acceptance test is planned in Sept. /October 2010. iii) The system is planned to go live at BCT by the end of October 2010 iv) The  system  is  scheduled  to  go  live  at  NDLS/LKO  by  the  end  of 

November 2010. The progress of system implementation needs to be monitored closely.  NR, WR and CRIS may report progress   

  WR  NR  CRIS 

4.7  ICF-ERP project has been launched in March 2010. ICF and CRIS may report progress of the Hardware supply and Installation, Software development & customization and identification of core teams at all levels with adequate training for taking over development systems. The target date of completion is September 2011.

ICF  CRIS   

4.8  Other production units need to upgrade/implement integrated IT systems ntegrating all business processes across departments. They may come up with the status of existing systems and the plan to upgrade the same.

All PUs other than ICF 

5.0  Crash Buffers:   Based on  the  recomendation of RSRC  for  improving crash‐worthyness of coaches, crash buffers have been  provided in coaches. 1200 nos (900  from  M/s Axtone, Poland and 300 from M/s Knorr Bremse) have been fitted by RCF, which are alloted to almost all the Railways. All Railways should monitor performance of  these Crash Buffers and  furnish  report  to RDSO for compilation.  

All Railways  ED/Carriage, RDSO  CDE/RCF 

6.0  Training :  

 

6.1  A  Committee  consisting  of  ED/IRCAMTECH  and  Professor  /IRIMEE  on Training needs of Mech. Department has been asked  to  identify  five most critical training needs of Mechanical Department, prepare a  list of training assets available and evolve an action plan  to bridge  the  identified  training gaps.  The  Committee  has  circulated  a  questionnaire  vide  letter  dated 30.9.2010 which has to be responded to by 15th October 2010.   

All Rlys/Pus 

6.2  IRIMEE  has notified two courses on Mechatronics vide letter dated 27.9.10  All Railways 

Page 50: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

49 

 

(S.No.4),  covering  new  sub‐systems  having  low  voltage  control  such  as control devices of Toilet Systems, WSP in high speed coaches and electronic sub‐systems of weighbridges.  Follow‐up modules have also been scheduled six  months  after  the  main  course.  The  plan  is  to  have  a  system  for dissemination of  knowledge  through  trained  trainers.        Zonal Railways & Workshops should ensure nomination  and sparing of suitable personnel for these courses 

6.3  Centres  of  Excellence:    Vide  Item  No.7  of  the Minutes  of  4th Workshop Management  Group  Meeting  held  on  27th  &  28th  August  2009,  it  was communicated  that Centres of Excellence are  to be developed  as per  the following details:‐ 

DMW‐    Machine maintenance (Electronics & Hydraulics) RCF –   LHB coach technologies, CDTS JMP ‐  Hydraulics GOC, DLW, BPL, KGP ‐ Welding. 

 Action taken and planned in this respect may be advised.   

E. Rly S.Rly S.E. Rly W.C. Rly  DLW DMW RCF  

  

Page 51: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

50 

 

FREIGHT 1. Performance Review of Equipment failure:

The comparative figures for 2008-09, 2009-10 and the current year for Hot axles are as below:

Year Hot Axle 2008-09 (upto Aug 2008) 228 2009-10 (upto Aug 2009) 281 2010-11 (upto Aug 2010) 278

There has been an increase in hot axle cases over Indian Railways by around 22% in

2010-11 as compared to 2008-09. WR has reported a spurt in the hot axle cases in BLC wagons, with most of these cases occurring on newly manufactured/POHed wagons.

This issue was raised during the last CMEs’ conference (March 2010) also. Railways may discuss: • Action taken on the deficiencies noticed during Quality Audits of Workshops • Submission of Bearing Failure reports to RDSO in the proper format • Further action plan in this regard

Zonal Railways may bring their analysis of the issue, action taken by them so far and

further action plan to improve performance in the area. 2. Unloadables – Railways to comply with targets specified

The arising of unloadables is increasing every year. The arising of Cat ‘C’ unloadables during the current year has been around 1000 wagons per month. The problem is proposed to be tackled as outlined in Railway Board’s letter dated July 2, 2010. Targets for ‘C’ Cat unloadables have also been given to the Open Line. Railways may indicate their plan of action to comply with the targets mentioned therein. Any issues and concerns in this regard may also be raised. Allotments have been made to the various Railways for upgraded rehabilitation of BOXN wagons to BOXNR. The compliance of the Railways which have fallen short of the targets is as follows:

Railway NCR NWR ECR SR SER SECR WR WCR Proportionate target

(upto Aug 2010) 250 167 250 167 146 167 188 205

Compliance (upto Aug 2010)

188 133 0 49 68 106 71 144

Thus, Railways need to step up efforts to comply with targets of upgraded rehabilitation given to them during the current year. Further, causes for enhanced Cat ‘C’ unloadable arising and Railway’s strategy to reduce the same may also be discussed.

Page 52: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

51 

 

3. Creating additional capacity through Higher Speed

While the sanction of the Railway Board is available for running of BOXN and BCN wagons according to RDSO’s latest Speed Certificates, the Railways are yet to take sanction of the same. Thus, while BCNM1, BCNAM1, BCNAHSM1 have been certified for running at 75 Kmph in the loaded condition at CC+6+2, and for 65, 65 and 75 Kmph at CC+8+2, Railways are still running them at 60 Kmph. Similarly, BOXNM1 and BOXNHSM1 wagons have been cleared for 75 Kmph at CC+8+2 on the MGS-GZB section of Allahabad division on NCR. BOXNHL wagons have been certified for a speed of 75 Kmph in the loaded condition, but the Railways are yet to obtain CRS sanction for the same. Railways may discuss their status and indicate the timeframe in which the requisite sanctions shall be obtained for BOXN and BCN type wagons by them.

4. Status of upgradation of wagons through provision of additional springs

A survey carried out recently indicates that modification of BOXN/BCN type of wagons to their corresponding M1 type is not yet complete. As a result, there is mixing of various types of wagons in a rake. This leads to operational inefficiencies due to differences in speed fitnesses. The approximate number of unmodified wagons as per the survey are as follows:

Type of Wagon / to be Converted

Holding as on

30.04.09

Unmodified % as on

03.07.10 as per survey

Approximiate No. of

Wagons to be modified

Modified from

03.07.10 to 31.08.10

Balance for Modification

BOXN / BOXN M-I 61394 3.3 2026 1646 380

BOXNHS / BOXNHS M-I 18511 7.78 1440 456 984

BCN/ BCN M-I 14787 2.82 417 139 278 BCNA / BCNA

M-I 28096 4.33 1217 641 576

BCNAHS / BCNAHS M-I 7347 13.22 971 192 779

Instructions have been issued to the Railways (vide Railway Board’s letter no. 2005/M(N)/204/2 Vol. II dated 29th Sept, 2010) for undertaking a month-long drive and liquidating the balance wagons for modification to M1 series by the end of October 2010. Railways may discuss the results of the drive.

Page 53: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

52 

 

5. Availability of Wagons

The detention time for wagon examination (for August 2009 and 2010) as per FOIS is as follows:

Rly CR EC ECOR ER NCR NER NFR NR Aug-

09 05:41 04:35 04:39 04:52 04:43 04:12 03:49 04:34

Aug-10 05:56 06:01 09:27 03:58 06:00 03:47 04:32 04:09

NWR SCR SER SECR SR SWR WCR WR IR avg

05:02 04:56 04:38 02:27 05:38 06:51 02:53 07:29 04:52 04:59 06:42 04:58 02:12 04:47 07:24 02:49 07:34 05:08

It may be seen from the above that the some Railways are detaining wagons for a much longer time than the others for the purpose of examination. Reasons for higher as well as lower detention may be explored. Reduction of detention time in Workshops and Open line will go a long way in increasing the availability of wagons. Zonal Railways may indicate their action plan to increase availability of wagons. Any further scope for optimizing maintenance may also be discussed.

6. Upgradation of maintenance facilities

The multi-disciplinary EDs’ Committee of Railway Board had recommended upgradation of infrastructure for maintenance of freight stock. The list of Sicklines, Examination Points and ROH Depots recommended by the Committee has been enclosed as Annexure. So far, the Works Programme proposals for enhancing freight maintenance infrastructure have been received for GIM ROH facility, BLC ROH at Moradabad and Naihati only. Railways may bring details of status of various points and the action plan for their Upgradation. Proposals for infrastructure considered essential by the Railways, other than these points may also be indicated.

7. Maintenance of New Design BOXNHL and BCNHL wagons

Two new design wagons: BOXNHL and BCNHL have been put into service. More than 8000 BOXNHL and 3000 BCNHL wagons have been manufactured till now. Presently, these wagons are based on few Zonal Railways. But, shortly these wagons will be based on all the Zonal Railways and shall be the standard Open/Covered wagon for Indian Railways in the future. These wagons have certain special features and uncommon spares for which planning needs to be done. Some of these special features are listed below:

Page 54: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

53 

 

i. Underframe and Superstructure of Stainless Steel to IRS:M44

ii. Coupler and Draft Gear procured from AAR approved sources iii. Brake Cylinder of 300 mm diameter (355 mm in existing wagons) iv. Brake rigging dimensions different from their older counterparts v. Auxiliary reservoir of 75 litres (100 litres in existing wagons)

vi. ‘K’ type CBB (‘L’ type in existing wagons) vii. Brake Slack adjuster of 750mm capacity (600mm in existing wagons)

viii. Flat Centre Pivot in the bogie (spherical in existing wagons) ix. Lock bolting (riveting in existing wagons) x. PU paint (alkyd paint in existing wagons)

Detailed information about special features of BOXNHL wagons has been circulated to all Zonal Railways by RDSO vide letter no. MW/BOXNHL dated 09/02/2009. Infrastructural Facilities required for maintenance of Stainless Steel Wagons in Yard, Sickline and ROH depots have been circulated by CAMTECH vide their letter no. IRCAMTECH.M.GWL.SS.Wagon dated 02/12/2009. Arrangements may be made for carrying out maintenance of Stainless Steel wagons in Yard/Sickline/ROH/POH by creating the required infrastructural facilities (M&P, Tools, Equipments, etc.), procurement of uncommon spares, procurement of necessary documentation from RDSO (specification, drawings, maintenance manual, etc.), training of maintenance staff, etc. In the previous CMEs’ Conference held in March 2010, two depots, MGS and NKJ were nominated for undertaking ROH of these wagons, which shall become due from October ’10 (24 months’ periodicity) onwards. Bhilai is also being nominated for the purpose. Similarly, for POH, which shall become due in 2014, two workshops, JHS and Raipur were nominated. Vide their letter no. MW/BOXNHL dated 30.07.2010, RDSO has issued detailed instructions regarding “Maintenance and Performance Monitoring of New Design BOXNHL wagons”. Railways may study the same in detail and raise any issues and concerns in this regard. Any other maintenance problems observed by the Railways may also be highlighted.

8. Siding Agreements

Instructions have been issued vide Railway Board’s letter no. 98/M(N)/951/12 dated 27-11-2002 for incorporation of clauses in the Siding Agreements for raising and collecting damage charges from siding owners for damages caused to wagons during tippling. Railways may discuss: • Status of updation of Siding Agreements • Damage charges collected • Problems, if any

Page 55: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

54 

 

  

Recommended Upgradation of Infrastructure by EDs' Committee

Exam. Yards Sick Lines ROH Depots

S.No. Rly. Stn. Code

Points to be Provided with U/L

Repair by ED Comm

RECOMMENDED BY EDs'

COMMITTEE

Present Cat.

RECOMMENDED BY EDs' COMMITTEE

Present Cat.

RECOMMENDED BY

EDs' COMMITTE

E

Present Cat.

BSL √ E

Conversion from Vacuum Brake

(VB) To Air Brake

(AB)

B

WADI Proposed

for Closure

C

VDLR √ D √ B

KYN √ C √ A

DD √ E

LONI √ D

TMBY √ D √ B

MRJ √ D √ E Proposed

for Closure

THAL √ BALHARSHA √

1 CR

TOTAL 5 8 3

DSEY √ D

PKR √ D √ F

MLDT √ F √ E

BGB √ F √ F Proposed

for Closure

D

CP √ B Proposed

for Closure

D

STN √ F √ F UDL (Dn Yd)

Asansol √ √

Berakar √

2 ER

TOTAL 1 7 6 2

Page 56: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

55 

 

UMB √ A

KJGY √ A

LDH √ D

BTI √ D

TKD For Spl. rep.-Container

Conversion from

VB To AB A

GZB √ D √ B

LKO √ B

SSB √ A √ B

MB Proposed

for Closure

C

DDL (ICD) √ E

ASR √ F √ A

JUC √ F

3 NR

TOTAL 1 8 5 2 GONDA Proposed

to Open 4 NER TOTAL 1 NTSK √ A

NGC Conv.

Vac. Bk. To AB

B 5 NFR

TOTAL 1 1 JTJ √

TNPM (ICD)

Conv. Vac. Bk. To AB

B

HOM √ F √ F

ED √ D

ERMG √ B

IPN √ E Conv.

Vac. Bk. To AB

B

TPGY √ F √ F

KNKD √ D √ C Madras Salt Cotaurs

Podanur √ √

6 SR

TOTAL 1 8 4 2

Page 57: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

56 

 

GY √ SNF (SNAG) (ICD)

√ E √ E

RDM D √ E

BPA Conv.

Vac. Bk. To AB

C

BZA E √ A

COA √ E

KKF √

7 SCR

TOTAL 1 2 4 1 BNDM Ex Yd √ D

BNDM CSL √ F

DPS √ D Proposed

for Closure

BKSC (EmpYd)

√ D

TATA √ D

BJE √ F √ E

ADRA √ √ F √ F

JSG √ F √ F

HLZ √ F

ADTP √ E Proposed to Open

8 SER

TOTAL 1 9 4 2

BRCY Conv.

Vac. Bk. To AB

B

UDN √ D √ A

KKF √ A

GIM Proposed to Open

HXP √ A Proposed to Open

RTM √ D Conv.

Vac. Bk. To AB

D

KRCA √ E Laxmibai Nagar

9 WR

TOTAL 5 2 4

Page 58: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

57 

 

PEH Proposed

for Closure

MGS (DRY) √

NRPA Proposed to Open

GHZ Proposed

for Closure

D

PTRU √ D √ F

10 ECR

TOTAL 1 1 1 1

MD Proposed to Open

MTD √ D √ E 11 NWR

TOTAL 1 1 1

BAD √ A Conv.

Vac. Bk. To AB

C

JHS C √ F Conv.

Vac. Bk. To AB

D 12 NCR

TOTAL 1 1 2

BIA √

DRZ √ F Proposed

for Closure

D

BSP √ A √ F

DGG √ D

KRBA √ F √ F

BIA (ExYd) C √ F

Conv. Vac. Bk. To AB

C

BSP (DGT Yd)

√ F

G √ F

13 SECR

TOTAL 1 4 5 2 VSKP-OEC √

VSPS-RMUY √ B

KUR √ F

CTC √ F √ F

PRDP √ F Kantabanji √

ANGUL Proposed

to Open

14 ECoR

TOTAL 1 2 4 1

Page 59: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

58 

 

HPT √

HRR √ F

UBL √ E √ F

BYPL √ F √ F

BDVT F √ F Mysore New Goods Terminal

15 SWR

TOTAL 1 2 5 NKJ New √

SKT √ D

ET √ D 16 WCR

TOTAL 1 2

IR - GRAND TOTAL 10 58 50 25

 

Page 60: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

WORKSHOP ITEM

1. Management Information System:

A workshop portal had been launched on Railnet to enable online reporting and sharing of information on workshop outturn. Now, the portal in a more detailed format has been hosted at the Railnet URL: http://10.1.5.78:8081/MCDO/. In addition to POH outturn, the progress of RSP works, POH unit cost, POH cycle time, incentive payments, staff strength, coach sick marking and local passing have also been added to the site. A meaningful analysis is possible only when complete data is fed into the portal. As already advised, Railways must feed the data regularly for proper utilization of the portal. The workshops can view each other’s performance in all the fields.

Railways must ensure reporting of workshop outturn in future through this portal by 5th of every month positively.

2. Quality Issues: An analysis of the cases of coaches getting sick marked within 100 days of POH in 2009-10 over the IR shows the following major reasons: (i) water tank/system leakage (16%) (ii) spring breakages (10.5%) (iii) brake cylinder defective (7%) (iv) wheel defects (5%) and (v) roller bearing defects (3%).

A special attention to these items needs to be given in workshops. Now, with the proliferation of 18-month POH cycle, the quality of POH would need to be stepped up. In the past, there had been cases of en route detachment of coaches due to working out of headstock, draw bar assembly and sole bar. Failures of this nature have serious safety implications. The subject was discussed in detail during CWM’s meeting held on 6.8.10 at Railway Board. CMEs must give a detailed feedback on the action taken by them in compliance of the items discussed and circulated vide the minutes of the meeting. The feedback must be given within 30 days.

Page 61: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

3. Quality of Welding Electrodes:

In the recent CWM’s meeting, it was also pointed out by some of the CWMs that workshops are experiencing difficulty in using specified class of electrodes due to heavy smoke and spatter. Workshops were advised to give a feedback to RDSO to enable them to undertake a review of approvals of welding electrodes for specific critical applications like headstock and sole bar repairs. RDSO has also circulated corrosion repair manual of coaches (C-7602, Revision II) for comments. Railways must give their feedback for consideration of RDSO.

4. IOH of bogies as a result of 18-month POH interval: Detailed instructions exist for switch over to 18-month POH schedule for coaches with supply of unit exchange IOHed bogies from workshops. However, it has been noted that many Railways are still sending complete coaches to the workshops instead of only the bogies for IOH. This is not only eating into the lifting capacity in the workshops but also the turnaround time for coaches has gone up significantly. Railways must ensure that only the bogies are sent for IOH to the workshops and duly IOHed bogies back loaded for the open line depots.

Railways are advised to consider a time bound action plan for the same and advise progress in this regard to the Board.

5. POH/IOH of LHB Coaches: As on 1.4.2010, there are about 680 LHB coaches. Going by the future projections, the likely holding of LHB coaches 5-6 years hence is likely to reach in the vicinity of 3000. As per the extant guidelines, the POH and IOH of these coaches are to be undertaken after 36 and 18 months respectively in workshops. Based on the current holding, the present requirement of POH/IOH of these coaches is 35 per month which is being undertaken at JUDW, PL and LLH workshops. With a holding 3000, the POH/IOH arisings will be to the tune of 150 per month. Hence, in addition to augmentation in the present workshops, a few other workshops will also be required to develop facilities for maintenance of LHB coaches. Following is proposed:

Augmentation of capacity in existing workshops: 1. Jagadhri – From present levels of 15 to 35 per month 2. Lilluah – From 10 to 30 per month 3. Lower Parel – From 15 to 30 per month

Page 62: Traction Items - Indian  · PDF fileTraction Items 1. Current Issues pertaining to ALCO/EMD locos. ... • Orders for bogies by DMW on CLW. ... Maintenance issues of LHB coaches

Creation of capacity in other workshops:

1. Mysore – 10 coaches per month 2. Peramur(Carr.) – 25 coaches per month 3. Lallaguda – 20 coaches per month Railways must plan for creation of facilities for the same.

6. Revision of Mechanical Code: Railway Board had constituted a Committee headed by Shri S. Dhasarathy for revision of Mechanical Code. The Committee has submitted the draft report which is being circulated as a soft copy (on a CD). A group of officers comprising CME/DLW, CWE/NR and CWE/SR has been constituted to see the practicability of implementation of various proposed provisions in the draft Mechanical Code. CMEs may kindly give their suggestions to this group.