Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables...

30
Town Hall: A History and Proposal

Transcript of Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables...

Page 1: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 2: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 3: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Town Services Building

• Build Circa 1960s

• 99 Year Lease

• Regular Flooding

• Lacks Proper Heating, Air, and Electrical Systems

• Inadequate Office, Storage, Meeting Space

• Not ADA Compliant

Page 4: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

2014 Florida Terrace Plan

Page 5: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Community Feedback

• In keeping with the values of Montreat • Cost consciousness• 3,000 to 4,000 sf occupied space• One-story• No large lobby space; community information “nook”• Share large meeting facilities with MRA and College• Conference room seating approx. 30-35 persons• Emergency Operations Center• Expansion capacity• Plan for technological advances

Page 6: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

What is most important to you about the new Town Hall?

Page 7: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

How would you describe the aesthetics or "feel" you would like in the EXTERIOR of the new Town Hall building?

Page 8: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

How would you describe the aesthetics or "feel" you would like in the INTERIOR of the new Town Hall?

Page 9: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

What is most important to you concerning the GROUNDS and LANDSCAPING around the new building?

Page 10: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

This Is The Title of the Presentation

How important are the following “options” in the construction of the new Town Hall?

Extremely Important

Extremely Unimportant

3.48

2.98

2.97

2.84

2.34

4.35

Page 11: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018
Page 12: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Timeline and DeliverablesDays Start Completion

Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018 Saturday, December 29, 2018

Review period (City) 9 Monday, December 31, 2018 Wednesday, January 9, 2019

Phase 2 Construction Documents, Costs, and Proposed Addendum 112 Thursday, January 10, 2019 Thursday, May 2, 2019

Review period (City) 13 Friday, May 3, 2019 Thursday, May 16, 2019

Issue RFQ for Lender 16 Friday, May 17, 2019 Sunday, June 2, 2019

Application to LGC 40 Monday, June 3, 2019 Saturday, July 13, 2019

Execute Construction Addendum 7 Sunday, July 14, 2019 Sunday, July 21, 2019

Phase 3 Construction 365 Monday, July 22, 2019 Tuesday, July 21, 2020

Substantial Completion Tuesday, July 21, 2020

Page 13: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Timeline and DeliverablesDays Start Completion

Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018 Saturday, December 29, 2018

Review period (City) 9 Monday, December 31, 2018 Wednesday, January 9, 2019

Phase 2 Construction Documents, Costs, and Proposed Addendum 112 Thursday, January 10, 2019 Thursday, May 2, 2019

Review period (City) 13 Friday, May 3, 2019 Thursday, May 16, 2019

Issue RFQ for Lender 16 Friday, May 17, 2019 Sunday, June 2, 2019

Application to LGC 40 Monday, June 3, 2019 Saturday, July 13, 2019

Execute Construction Addendum 7 Sunday, July 14, 2019 Sunday, July 21, 2019

Phase 3 Construction 365 Monday, July 22, 2019 Tuesday, July 21, 2020

Substantial Completion Tuesday, July 21, 2020

Page 14: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 15: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018
Page 16: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 17: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018
Page 18: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018
Page 19: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 20: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 21: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 22: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 23: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 24: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Page 25: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Preliminary Budget

➢ Construction: $1,164,869

➢ Sitework: $250,875

Opportunities for Value Engineering

Page 26: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

What is Included?

➢ Construction:

o Permit Costs

o Sitework

o Building Construction

o Stormwater Retention

o Parking and Site Ingress/Egress

o Sidewalk

o Bond

Page 27: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

What is Included?

➢ Landscaping:

o Permit Costs

o Site Plan and Landscape Design

o Native Plantings

o Flagpole

o Bond

Page 28: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

Financial Plan

• Estimated Costs Extremely Detailed and Researched

• Unencumbered Capital Fund Balance Restricted for Town Hall:

$188, 629 (13.3% of total costs)

• Proposed Loan Amount: $1,277,115

• Proposed Tax Increase: None. Monthly Debt Service Covered

by Operational Budget

Page 29: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal

In Summary

• We’ve Listened

• We’re Responding

• We’re Excited About the Future

Page 30: Town Hall: A History and Proposal · Town Hall: A History and Proposal Timeline and Deliverables Days Start Completion Phase 1 Schematic Design Phase 60 Tuesday, October 30, 2018

Town Hall: A History and Proposal