Topic 1 - Risk Project Management

download Topic 1 - Risk Project Management

of 33

Transcript of Topic 1 - Risk Project Management

  • 7/26/2019 Topic 1 - Risk Project Management

    1/33

  • 7/26/2019 Topic 1 - Risk Project Management

    2/33

    Project Management Tool

    Practical way to integrate risk into project

    planning and control and there are project

    tools that effectively support risk

    management.

    Once risks are identified as business risks,

    risk assessment and management are

    integrated into the project planningprocess.

  • 7/26/2019 Topic 1 - Risk Project Management

    3/33

    ustomer !e"uirement

    !e"uirements are customer#driven and so

    are risks

    The ! document is the project manager$s

    definition of customer re"uirements,

    developed from information gleaned from

    the customer.

    The re"uirements document addresses thecustomer$s business setting and needs and

    e%pectations for a project solution.

  • 7/26/2019 Topic 1 - Risk Project Management

    4/33

    &ork 'reakdown (tructure

    First level: The Deliverable

    ) defining the work necessary to produce the

    deliverable is to complete a work breakdown

    structure *&'(+ from the top *the deliverable+

    down tothe third or fourth level of tasks.) t represents the final product or service

    outcome of the project, performing tospecification and accepted by the sponsor,

    client, andlor user.

  • 7/26/2019 Topic 1 - Risk Project Management

    5/33

    &ork 'reakdown (tructure

    Second level: Summar Tasks -ive or si% basic chunks of high#level work that serve

    as the basic components of the project#the summary

    tasks which are integrated at the end of the project tocomplete the job.

    ) 'uilding project / architectural drawing, building supplies,

    ventilation systems, water, and electrical systems.

    ) (oftware project / hardware platform, software, interfaces,

    training program, and financing.

    ) 0ealth management system / clinic population, health

    information system, medical personnel, space, and e"uipment.

  • 7/26/2019 Topic 1 - Risk Project Management

    6/33

    &ork 'reakdown (tructure

    Third level: Subtasks 'reakdown of the summary tasks outlined above into

    two or more subtasks, which would be necessary to

    complete to produce the second level summary task.) i.e. building project, under the summary task architectural

    drawing, this might include three tasks#get ad architect, prepare

    preliminary blueprint, and check against standard blueprint

    template.

  • 7/26/2019 Topic 1 - Risk Project Management

    7/33

    &ork 'reakdown (tructure

    Fourth level: !ork Package 1etail at the real tasking level#the work package.

    ndividual tasks assigned to team members.

    The actual work assignments that will be necessary toschedule and the risks that the work will not make

    schedule, cost, and2or "uality re"uirements.

  • 7/26/2019 Topic 1 - Risk Project Management

    8/33

    !isk Matri%

    !isk matri%, the fundamental risk template thatcaptures the essential risk information in a

    project.

  • 7/26/2019 Topic 1 - Risk Project Management

    9/33

    Steps in Preparing a Risk Matri"

    (tep 3/ dentify tasks with risk.

    (tep 4/ 1escribe risk.

    (tep 5/ 1etermine impact.

    (tep 6/ 7stimate chancelprobability of risk event.

    (tep 8/ !ank risk by severity.

    (tep 9/ dentify mot causes.

    (tep :/ Prepare contingency plan.

    (tep ;/ 7stimate schedule impacts uslng M( Project software.

    (tep

  • 7/26/2019 Topic 1 - Risk Project Management

    10/33

    >etwork 1iagram

    'uild a network diagram of this summary

    task

  • 7/26/2019 Topic 1 - Risk Project Management

    11/33

    >etwork 1iagram

    Start #ith a net#ork template$

    )?lways start your network diagramming with a

    template or model of the typical network,

    and adjust it to the project you are planning.

  • 7/26/2019 Topic 1 - Risk Project Management

    12/33

    >etwork 1iagram

    Project paths 3

    # ?, , -, @, 0 A 9 B 8= B 58 B 5 B 5 A

  • 7/26/2019 Topic 1 - Risk Project Management

    13/33

    >etwork 1iagram

    Tailored net#ork diagram$

  • 7/26/2019 Topic 1 - Risk Project Management

    14/33

    >etwork 1iagram

    ndependent actvities)?n activity that doesnCt rely on others to start or to

    finish

    Predecessor actvities)?n activity that determines the start date or finish date

    of a successor activity based on a logical relationship.

    Time#based activity2duration)?ctivity that determined by the critical path of the

    project

  • 7/26/2019 Topic 1 - Risk Project Management

    15/33

    >etwork 1iagram

    ndependent actvities ) ?, '

    Predecessor actvities ) ,1,7,-,@,0

    Time#based activity2duration ) ?,,-,@,0

  • 7/26/2019 Topic 1 - Risk Project Management

    16/33

    >etwork 1iagram

    %nalsis o& earl and late starts and slack

    Project paths

    ?, , -, @, 0 A 9 B 8= B 58 B 5 B 5 A

  • 7/26/2019 Topic 1 - Risk Project Management

    17/33

    >etwork 1iagram

    %nalsis o& earl and late starts and slack

  • 7/26/2019 Topic 1 - Risk Project Management

    18/33

    @annt hart

    'ar chart representing the whole project

    graphically, based on linkages and durations

    This process, from initial re"uirement through

    the @antt chart, is the core process of projectrisk management.

    This is where risks are captured and identified,

    as part of the project planning process.

  • 7/26/2019 Topic 1 - Risk Project Management

    19/33

  • 7/26/2019 Topic 1 - Risk Project Management

    20/33

    'usiness and project risk

    Dey factors in the success or failure of any

    project are the broad business factors for

    success and failure and the process of

    selecting the project in the first place.

  • 7/26/2019 Topic 1 - Risk Project Management

    21/33

    'usiness and project risk

    S!(T analsis: risk identi&ication

    Strengths

    ) ts competencies and its core capabilities and

    identifies its current performance advantage itsdifferentiators

    !eaknesses

    ) The company looks at its weaknesses in terms of its

    inability to overcome risk and uncertainty in past

    initiatives and identifies internal improvements

    that it must make to address them.

  • 7/26/2019 Topic 1 - Risk Project Management

    22/33

    'usiness and project risk

    S!(T analsis: risk identi&ication

    (pportunities$

    ) Opportunity is the converse of riskE there is no

    risk if there is not opportunity on the other side.

    Threats$

    ) ompetition, technological change, economic

    crisis, and financial difficulty, all constitute therisk factors that the business faces and thus

    the risk factors that individual projects face

  • 7/26/2019 Topic 1 - Risk Project Management

    23/33

    'usiness and project risk

    S!(T analsis: risk identi&ication

    !eighted scoring model$

    ) Fse the weighted scoring model to select

    projects based on their relative scores against

    strategic objectives,

    ) This process is evaluating contingency plans

    to address risk inherent in various candidateproject plans, costs estimates, and cash flow

    forecasts.

  • 7/26/2019 Topic 1 - Risk Project Management

    24/33

    'usiness and project risk

    )ustomer and )lient Risk

    ) lient risk management issues

    ) Project deliverable impacts

    ) Partnering in risk management

  • 7/26/2019 Topic 1 - Risk Project Management

    25/33

    'usiness and project risk

    Project and Risk Management Processes

    ) (electing the right projects

    ) The analysis of risk in project selection involves

    three basic issues/

    -inancial risk

    (chedule risk

    Guality risk

  • 7/26/2019 Topic 1 - Risk Project Management

    26/33

    Project Manager*s Roles

    Headership

    Motivation

    Deeping risk manageable -acilitator2Manager

  • 7/26/2019 Topic 1 - Risk Project Management

    27/33

    !isk#based scheduling *P7!T+

    alculating a risk#based schedule/ P7!T

    analysis.

    To use risk assessment and analysis

    information to calculate a risk#based

    project schedule in Microsoft Project.

  • 7/26/2019 Topic 1 - Risk Project Management

    28/33

    !isk#based scheduling

    The risk#based schedule is calculated from

    your original project schedule, but uses

    your weighted estimates of three possible

    task durations *e%pected, pessimistic, andoptimistic+ to come up with a new project

    schedule.

    The new schedule is calculated forindividual tasks and rolled up to the whole

    project

  • 7/26/2019 Topic 1 - Risk Project Management

    29/33

    !isk#based scheduling

    'asis for estimates

    ) nternal accounting records

    ) Project team knowledge

    ) 7stimating manuals and databases.

    ) onstruction

    ) (oftware development

    ) Hearning curves

    ) Parametric estimating

  • 7/26/2019 Topic 1 - Risk Project Management

    30/33

    !isk#based scheduling

    Project ssues

    ) Poorly defined project scope

    ) Major omissions *overloooked+ in

    taskdactivities

    ) Optimistic time2cost estimates

  • 7/26/2019 Topic 1 - Risk Project Management

    31/33

    Management !eserve

    Project -inancial) ssues such as internal resources, commercial credit,

    e"uity issues, venture capital, government

    grantslsubsidies, and capital rationing govern theviability of the company itself and its capacity to

    finance a project up front.

    ) To share risk, many companies are going to

    earmarked venture funds for new product

    developmen so that sponsorsI funds are bounded by

    a project to avoid cross subsidy.

  • 7/26/2019 Topic 1 - Risk Project Management

    32/33

    Management !eserve

    +nsurable risk

    ) !isk that is determined to be insurable on the

    open market and which is not self funded.

    ) nsurance is a vehicle to share risk and to

    outsource risk that has a high probability and

    impact severity.

  • 7/26/2019 Topic 1 - Risk Project Management

    33/33

    Management !eserve

    +denti&ication o& project risks$

    ) nternal

    ) Technical

    ) >ontechnical

    ) 7%ternal

    ) Predictable

    ) Fnpredictable) Hegal

    ) !isk event