Toolkit: Approaches to Private Participation in Water Services Module 6 Allocating Responsibilities...
-
Upload
jared-hanken -
Category
Documents
-
view
220 -
download
2
Transcript of Toolkit: Approaches to Private Participation in Water Services Module 6 Allocating Responsibilities...
Toolkit: Approaches to Private Participation in Water Services
Module 6
Allocating Responsibilities and Risks
Introduction:
Navigating through this E-Learning Module This is one of 9 Toolkit e-learning Modules. Each Module is created in PowerPoint, and you advance through the Module by pressing the right arrow or ‘Enter’ button. Core Module: The Module takes you sequentially through four or five major issues, depending on the Module. The progress through the Module is shown by the colored area on a logo on the top right hand corner of each slide. Here is an example: Supplementary Content: The Core module covers all key issues. However, you can choose to access additional information. These supplementary slides can be accessed by passing the cursor over colored buttons. The button colors relate to issues of various levels of detail:
Navigation through the supplementary material is also by pressing the right arrow or ‘Enter’ button. At the end of each section you will return automatically to the core Module. However, there is an extra button (to pass over) on the top right hand of each supplementary page that gives you the option of a shortcut back to the core Module:
Basic Concept Detail
Expert insight
Supplementary Information / Case studies
Back to Module
E-learning design: [email protected]
Elements of the Toolkit
TOOLKITTOOLKIT
1ConsideringPrivate Participation
2Planning the Process
5Standards, Tariffs, Subsidy, Financials
4Setting Upstream Policy
3Involving Stakeholders
6Responsibilities & Risks
7Developing Institutions
8Designing Legal Instruments
9Selecting an Operator
Additional MaterialCD-ROM
Appendix BPolicy Simulation
Model
Appendix AExamples of PP Arrangements
General Outline of Toolkit
TOOLKITTOOLKIT
1ConsideringPrivate Participation
2Planning the Process
4Setting Upstream Policy
3Involving Stakeholders
6Responsibilities & Risks
7Developing Institutions
8Designing Legal Instruments
9Selecting an Operator
Additional MaterialCD-ROM
Appendix BPolicy Simulation
Model
Appendix AExamples of PP Arrangements
Module 6
5Setting Service
Standards, Tariffs, Subsidies &
Financial Arrangements
Module 6
Allocating Responsibilities and Risks
Module 6 - What will we learn?
What are the key
areas of
RESPONSIBILITY
for provision of the
water services, and
how can they be
defined?
Is it possible to use a standard model of private participation for a specific case, or is some tailored or hybrid model required?
What are the key areas of RISK associated with the responsibilities, and how can they be defined?
Management Contract for
Jordan Valley Authority,
Irrigation Water Supply, may be
the first of its kind.
What rules or mechanisms can be
established to ensure
that the allocation of
risk is maintained in a
clear and effective
manner for the private
participation arrangement?
Who is best able to
manage these risks and
responsibilities, and how best to allocate these?
Plus!
Additional Material:
Tariff Reset
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ANALYZING Responsibilities
& Risks
Module 6 Allocating Responsibilities and Risks
A big part of designing the PP Arrangement is defining and allocating the business responsibilities between the various parties.
Risk associated with these responsibilities has also to be allocated between the parties, and this is also a key part of designing the Arrangement.
A big part of designing the PP Arrangement is defining and allocating the business responsibilities between the various parties.
Risk associated with these responsibilities has also to be allocated between the parties, and this is also a key part of designing the Arrangement.
The basic process for allocating Responsibilities and Risks is:
• Identify the main areas of Responsibility involved in delivering the services and the Risks associated with each Responsibility
• Allocate each area of Responsibility and Risk to the party best able to manage it
• Design the Arrangement to achieve the best allocation of risks and responsibilities
The basic process for allocating Responsibilities and Risks is:
• Identify the main areas of Responsibility involved in delivering the services and the Risks associated with each Responsibility
• Allocate each area of Responsibility and Risk to the party best able to manage it
• Design the Arrangement to achieve the best allocation of risks and responsibilities
Module 6 Allocating Responsibilities and Risks
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ANALYZING Responsibilities
& Risks
ANALYZING Responsibilities
& Risks
Analyzing Responsibilities & Risks
In this section we ANALYZE key issues related to provision of water services, looking at two main areas:
• Key areas of RESPONSIBILITY. How can they be defined?
• Key RISKS related to these Responsibilities. How can they be defined?
In this section we ANALYZE key issues related to provision of water services, looking at two main areas:
• Key areas of RESPONSIBILITY. How can they be defined?
• Key RISKS related to these Responsibilities. How can they be defined?
Module 6 Allocating Responsibilities and Risks
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ANALYZING Responsibilities
& Risks
ANALYZING Responsibilities
& Risks
Analyzing Responsibilities & Risks
Analyzing Risks
Analyzing Responsibilities
Module 6
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
ALLOCATING Responsibilities
& Risks
Allocating Responsibilities & Risks
A key aim of private participation is to allocate risks between the Operator and the Contracting Authority.
A key aim of private participation is to allocate risks between the Operator and the Contracting Authority.
Module 6 Allocating Responsibilities & Risks
“How can we best allocate Risks and Responsibilities between the Contracting Authority and the Operator? ”
Some Guidelines:
Each Responsibility is allocated to the party best able to undertake it
Each Risk is born by the party best able to manage it, taking account of the parties’ ability to:
Predict changes in the relevant factors
Influence or control the risk factor
Control the impact of the risk on the value of the water and sanitation business
Diversify or absorb the Risk
NOTE: COST OF RISK
Bearing Risk has a cost. If Risk is allocated to the Operator, he will generally expect to be able to recover the cost. Allocating Risk to the party best able to manage it helps to reduce costs to the contracting authority and customers.
Example: One party may be better able to predict nonpaymentExample: one party may be better able to reduce nonpayment through customer management
Example: one party may be better able to reduce nonpayment through ability to offer credit termsExample: One party may be able to diversify risk
across a portfolio of projects
Allocating RisksExample (1): Demand Risk
“Example: Demand Risk affects many elements of water and sanitation companies , it can have a significant impact on the business value, and
fluctuations in demand can drastically affect investment needs.”
The extent to which Demand Risk is shared between the Contracting Authority and the Operator depends on the particular circumstances of the project including:
Availability of good information on Demand
Economic Stability
The Operator’s willingness to accept Risk
In practice the Operator will be reluctant to accept full Demand Risk, and will seek to pass it onto customers through:
Tariffs or …….
Reduced Service Levels
Allocating RisksExample (2): Currency Risk “Example: Currency Risk is made up of Exchange Rate and Convertibility Risks. Exchange rate risks comes from unpredictable variation in Exchange Rate.
Convertibility Risk comes from uncertainty as to whether the Government will restrict conversion of the local currency into foreign currency”
Currency Risk affects the business value through several mechanisms:
Operational Costs
e. g. Affects costs of imported inputs, such as energy costs
Maintenance and construction Costs
e.g. Affects price of imported parts used in new construction
Finance Costs
e.g If Loans in foreign currency but revenues from local currency, then exchange rate fluctuations will affect business profitability.
“..or, for this we example, can show graphically how Currency and Convertibility Risks affect the value of the business through several mechanisms……..”
Cash Flow
Operating & Maintenance
Currency Convertibility Risk
Total Costs
New Investment
Input Prices
Financing Risk
Exchange Rate Risk
Allocating RisksExample (2): Currency Risk
Module 6
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
Plus!
Additional Material:
Tariff Reset
DESIGNING Risk Allocation
Rules
Designing Allocation of Responsibilities & Risks
“ The next step is to design the Rules that will allocate the risks and responsibilities”
Rules for adjusting Tariffs are an important mechanism for allocating Risk between the parties, including:
Cost Pass ThroughIndexationTariff Resets
Other risk-allocating rules are also reviewed (e.g. Bonuses and compensation on termination)
Rules for adjusting Tariffs are an important mechanism for allocating Risk between the parties, including:
Cost Pass ThroughIndexationTariff Resets
Other risk-allocating rules are also reviewed (e.g. Bonuses and compensation on termination)
Module 6 Designing Allocation of Responsibilities & Risks
“ We will consider two main subjects related to Risk Allocation”
TARIFF ADJUSTMENT MECHANISMS
TARIFF ADJUSTMENT MECHANISMS
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
Module 6 Designing Allocation of Responsibilities & Risks
“ Rules for adjusting tariffs are the key mechanism for allocating risk among Customers, the Operator and the Contracting Authority……
TARIFF ADJUSTMENT MECHANISMS
TARIFF ADJUSTMENT MECHANISMS
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
Cost pass-through
Tariff Indexation Formulas
Tariff Resets
Module 6 Designing Allocation of Responsibilities & Risks
“ Rules for adjusting tariffs are the key mechanism for allocating risk among Customers, the Operator and the Contracting Authority……
TARIFF ADJUSTMENT MECHANISMS
TARIFF ADJUSTMENT MECHANISMS
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
Cost pass-through
Tariff Indexation Formulas
Tariff Resets
Tariff Resets
Tariff Indexation
Cost Pass Through
Module 6 Designing Allocation of Responsibilities & Risks
“ Rules for adjusting tariffs are the key mechanism for allocating risk among Customers, the Operator and the Contracting Authority……
TARIFF ADJUSTMENT MECHANISMS
TARIFF ADJUSTMENT MECHANISMS
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
Cost pass-through
Tariff Indexation Formulas
Tariff Resets
Tariff Resets
Tariff Indexation
Cost Pass Through
Tariff ResetsExample:Why the need for Tariff Resets?
Module 6 Designing Allocation of Responsibilities & Risks
“ In addition to Tariffs…………………………. important mechanisms covering other risks must also be must be designed”
TARIFF ADJUSTMENT MECHANISMS
TARIFF ADJUSTMENT MECHANISMS
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
Cost pass-through
Tariff Indexation Formulas
Tariff Resets
Bonuses & penalties
Government Guarantees
Termination Triggers & payments
Transition periods at commencement
Contract Duration
Module 6 Other Mechanisms for Allocating Risk
Some other key risk allocation mechanisms include:
Bonuses and penalties
Government guarantees
Termination triggers and payments
Transition periods at commencement
Contract Duration
ALLOCATION OF OTHER RISKS
ALLOCATION OF OTHER RISKS
“ Although Tariff adjustment rules are the main ways of allocating risks, other risks are allocated between Operator and the Contracting Authority by contract ”
“ Although Tariff adjustment rules are the main ways of allocating risks, other risks are allocated between Operator and the Contracting Authority by contract ”
Module 6 Other Mechanisms for Allocating Risk
Some other key risk allocation mechanisms include:
Bonuses and penalties
Government guarantees
Termination triggers and payments
Transition periods at commencement
Contract Duration
Bonuses & PenaltiesPerformance payments such as penalties and bonuses encourage efficiency gains by sharing some element of risk with the Private Operator
The Contract may lay out a list of penalties if the Operator does not perform.
The Contract may also include bonuses if the Operator exceeds certain targets
Bonuses are the main mechanisms for transferring risk in a Management Contract. A management Contract without performance bonuses only gives an Operator weak incentive to improve performance
Guarantees
The Contracting Authority or a Government entity may provide guarantees to the Operator against certain risks, such as:
Operating debt Exchange rate guarantees related to foreign debt
This guarantees downside risk, making it more attractive to the Operator.
Care must be taken not to included risks that the Operator might be able to cover by himself more effectively
Termination triggers and payments
An arrangement will usually set out a list of triggers that entitles parties to terminate early, for example: Requisition, expropriation or seizure of water systems by Government The occasion of force majeure that makes the contract unworkable If penalties exceed a certain threshold the Contracting Authority may have the
right to terminate.
Termination payments compensate the Operator for costs that would otherwise be lost under early termination (e.g. sunk investment costs by the Operator). The way that these payments are calculated and applied helps to determine the allocation of risk
Transition periods
Where information problems increase the risk a transition period can be built in at the commencement of the arrangement. This allows an initial grace period when the Operator to collect information needed to run the business on a commercial basis, without accountability for performance improvements.
Terms can be adjusted to reflect any major differences from the initial assumptions
The longer the Contract Duration the more difficult it is to predict the effect of various parameters for the life of the contract. This may make the risks and the costs become unacceptably high to the various parties.
Reset mechanisms can help reduce risks to manageable levels for long duration contracts, particularly where private investment is involved
Module 6
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities
& Risks
DESIGNING Risk Allocation
Rules
EXAMPLES Allocation - Different PP Models
EXAMPLES Allocation - Different PP Models
Different PP Models Allocating Responsibilities & Risks
In this section we look at the way that three standard PPP models deal with Risk and Responsibilities:
Management Contract Affermage/Lease Concession
Each of these models is defined by the particular allocation of Risks and Responsibilities.
These models can be tailored to meet specific situations, or hybrid versions of these models used.
In this section we look at the way that three standard PPP models deal with Risk and Responsibilities:
Management Contract Affermage/Lease Concession
Each of these models is defined by the particular allocation of Risks and Responsibilities.
These models can be tailored to meet specific situations, or hybrid versions of these models used.
Module 6 Different PP Models Allocating Responsibilities & Risks
Operator Risks:
Contract Form:
Operational Technical
Management Contract
Affermage - Lease
Concession
Service Contract (by comparison)
Regulation Financial Commercial Forex
“ Each of the three standard models of private participation is defined by the allocation of responsibilities and risks”
Risk Level:These are an indication of the level of Risk taken by the Operator for specific issues under the various PP models .
Risk Level:These are an indication of the level of Risk taken by the Operator for specific issues under the various PP models .
Module 6 Different PP Models Allocating Responsibilities & Risks
Operator Risks:
Contract Form:
Operational Technical
Management Contract
Affermage - Lease
Concession
Service Contract (by comparison)
Regulation Financial Commercial Forex
“ Each of the three standard models of private participation is defined by the allocation of responsibilities and risks”
Concession:
The Operator assumes full responsibility for service delivery, including: Management Operation Maintenance of existing assets New Investment
Concession:
The Operator assumes full responsibility for service delivery, including: Management Operation Maintenance of existing assets New Investment
Affermage – Lease
Responsibility for operating and maintaining assets plus commercial and management responsibilities, passes to the Operator
The publicly owned company continues to be accountable for new investments)
Affermage – Lease
Responsibility for operating and maintaining assets plus commercial and management responsibilities, passes to the Operator
The publicly owned company continues to be accountable for new investments)
Management Contract:
The Operator fills the Key management positions in the water company.
The publicly owned company continues to be accountable for other responsibilities (e.g. operating and maintaining assets, new investments).
Management Contract:
The Operator fills the Key management positions in the water company.
The publicly owned company continues to be accountable for other responsibilities (e.g. operating and maintaining assets, new investments).
“ …each model has a particular application to the balance between Costs and Revenues as well as Political and Regulatory Risks”
Module 6 Different PP Models Allocating Responsibilities & Risks
Political and
Regulatory Risk
Costs/Revenues
LOW HIGHOperator willing to sink capital
Operator willing to take operating and
commercial risk only
Operator will only take limited risk
Tariffs don’t cover O&M
costs
Tariffs cover O&M costs
only
Tariffs cover total costs Concession
Lease/Affermage
Lease/Affermage
Management Contract
Management Contract
“ Looking at the balance between Costs and Revenues and Political and Regulatory Risks for each model ………….”
Management Contract
The risk transferred to the Operator depends on a performance bonus.
The formula for the bonus sets how much risk is taken by the Operator.
In general, the least amount of risk is transferred to the Operator under a Management Contract.
Management Contract
The risk transferred to the Operator depends on a performance bonus.
The formula for the bonus sets how much risk is taken by the Operator.
In general, the least amount of risk is transferred to the Operator under a Management Contract.
Affermage – Lease
The risk transferred to the Operator is significant, but depends on the contract details and the way that the operator’s remuneration is determined.
Affermage: the tariff adjustment rules relating to the Operator’s tariff (or ‘affermage fee’) are the most important
Lease: the Operator gets the customer tariff minus the lease payment. Tariff adjustment related to customer tariff are the most important.
Affermage – Lease
The risk transferred to the Operator is significant, but depends on the contract details and the way that the operator’s remuneration is determined.
Affermage: the tariff adjustment rules relating to the Operator’s tariff (or ‘affermage fee’) are the most important
Lease: the Operator gets the customer tariff minus the lease payment. Tariff adjustment related to customer tariff are the most important.Concession:
The Operator takes the greatest overall risks or responsibilities of the three models
Concession:
The Operator takes the greatest overall risks or responsibilities of the three models
Module 6 Different PP Models Allocating Responsibilities & Risks
Political and
Regulatory Risk
Costs/Revenues
LOW HIGHOperator willing to sink capital
Operator willing to take operating risk only
Operator won’t take any risk
Tariffs don’t cover O&M
costs
Tariffs cover O&M costs
only
Tariffs cover total costs Concession
Lease/Affermage
Lease/Affermage
Management Contract
Management Contract
HYBRID MODELS
In addition to the three basic PP Models, it is possible to design and implement ‘hybrid structures’ that combine effective elements of different structures, balance risk, mobilize capital but protect the poor
HYBRID MODELS
In addition to the three basic PP Models, it is possible to design and implement ‘hybrid structures’ that combine effective elements of different structures, balance risk, mobilize capital but protect the poor
“ ….but it may be necessary to adapt the standard models to meet particular needs”
Module 6 Different PP Models Allocating Responsibilities & Risks
Political and
Regulatory Risk
Costs/Revenues
LOW HIGHOperator willing to sink capital
Operator willing to take operating risk only
Operator won’t take any risk
Tariffs don’t cover O&M
costs
Tariffs cover O&M costs
only
Tariffs cover total costs Concession
Lease/Affermage
Lease/Affermage
Management Contract
Management Contract
HYBRID MODELS
In addition to the three basic PP Models, it is possible to design and implement ‘hybrid structures’ that combine effective elements of different structures, balance risk, mobilize capital but protect the poor
HYBRID MODELS
In addition to the three basic PP Models, it is possible to design and implement ‘hybrid structures’ that combine effective elements of different structures, balance risk, mobilize capital but protect the poor
Examples; Risk in Hybrids
- Amman (MC)
- Cartagena Affermage/Lease
“ ….but it may be necessary to adapt the standard models to meet particular needs”
Reviewing Module 6
‘The Module has looked at a whole range of issues for analysis and allocation of responsibilities & risks in PP design………….
Including
Tariff Reset
ANALYZING Responsibilities
& Risks
ALLOCATING Responsibilities &
Risks
DESIGNING Risk Allocation Rules
EXAMPLES Allocation – Different PP Models
ANALYZING Responsibilities &
Risks
Checklist: Module 6
Define the major areas of responsibility (management, operations & maintenance, new investment)Understand what services customers want
Define specific responsibilities for each area
Identify the risks that are associated with each responsibility
Note the direct and indirect relationships between risks and responsibilities
Establish how the risks are interrelated
For each risk, identify which party ( the operator, contracting authority or customers) is best able to bear the risk , and in particular who can:
Predict the risk
Influence the risk
Control the impact of the risk
Diversify or absorb residual risk
Decide whether the risk should be fully allocated to one party or shared
Check for any constraints on the ability of the parties to bear risk (e.g. information problems; unwillingness of any of the participants to bear risk they appear best able to manage)
Based on the risk analysis, assign a party to :
Assume each responsibility
Bear each risk
‘……..and the allocation process is detailed in this Checklist”
More Information: Module 6
More information on Allocating Risks and Responsibilities:
Allocating risk generally: Asian Development Bank 2000, Beato and Vives 1996, Delmon 2001, Finnerty 1996, Kerf and others 1998, Johnson and others 2002, Levy 1996, Nevitt and Fabozzi 2000, Victorian Department of Treasury and Finance 2001a and 2001b Political and Regulatory Risk: Smith 1997a Exchange rate risk: Gray and Irwin 2003a and 2003b, Mas 1997, Matsukawa and others 2003. Debt levels and effect on risk allocation: Ehrhardt and Irwin 2004 Implementing a tariff reset: Green and Rodriguez Pardina 1999, PPIAF and World Bank Institute 2002. Estimating the cost of capital: Alexander 2000, Benninga 2000, Brealey and Myers 2001. Government guarantees: Irwin and others 1997, Irwin 2003.
Supporting Material
• The Toolkit Financial Model• Toolkit Case Study material• Toolkit Website:
http://rru.worldbank.org/Toolkits/WaterSanitation/• For comments or further details contact Cledan Mandri Perrott at
Toolkit: Module 6
End of Module
Toolkit: Module 6
Return to StartReturn to Start