Superpave The New Frontier
Toni CarrollVulcan Materials
Why Superpave?Improve Performance
◦Low Temp Cracking◦Fatigue Cracking◦Rutting
Materials◦Binder◦Aggregate ◦Mix Design & Testing
Testing & Performance Prediction
Job Format?
No more QCQA!
Most jobs are StandardSome jobs are Method
Changes to Mix SpecificationsTighter Specs
◦Air Voids ±1.5%◦Binder for HMA: -0.3%, +0.5%◦Binder for Rubber: -0.4%, +0.5%
No more VFAVMA Design Vs. Production
Changes to the Mix
Higher Binder Contents◦Compactor changes volumetrics◦Rubber binder content is now a minimum of 7.5 TWM (8.1 DWA)
Changes to the Mix
Coarser gradationsFAA required for ALL mixes, More fractured faces
Change to Fractured Face MethodCurrently a particle is considered
crushed if 25% of the face is fractured.
New procedure requires 50% of the face to be fractured. 2x more fracture!
Compaction: Kneading vs. GyratoryHVEEM Compactor uses
“kneading” motion to compact pucks◦Tamping rod presses down in
various places around the puckGyratory Compactor uses
“gyrating” motion to compact pucks◦Surface the same size as the puck
is rolled in a circular fashion around the puck
Time Saved with Gyratory
Task HVEEM GyratoryGrading Aggs 60 60
Mixing 45 45Compacting 15 20*
Cool Down for Stability
90* -
Stability Test 25 -Cleanup 20 20
TOTAL (Minutes): 255 145
TOTAL (Hours): 4.25 2.4
Technician’s Time: 2 hrs 45 min 2 hrs 5 min
*Does not require technician to be present
Cost to PurchaseCompactor: $40kAccessories: $8kConstruction Costs: $0k-$10k
TOTAL CAPITAL COST: $48,000-
$58,000
Cost to Outsource
Field Samples: $900-$1200Lab Mixed Designs: $5400-
$7500
What to Do on Your JobAvg. Caltrans job may have 20,000-30,000 tons of mix
Need Mix DesignNeed to test for VerificationNeed to test for Production Startup
Need one test for every 4,000 tons
Avg Testing for Job: 5-10 samples
Hamburg Wheel Track General Overview
Weighted steel wheel runs back and forth over HMA samples in a heated water bath
Test PurposePredicts:
◦Rutting Fatigue◦Moisture Susceptibility◦Stripping
Mix Fails Due To:◦Weak aggregate structure◦Inadequate binder stiffness◦Moisture damage
Caltrans’ Reason for HWT
No stability testRutting potentialTests for
moisture sensitivity & stripping
To be used with TSR
How will your mix fare? Stiffer asphalt binders
(higher high temperature grades) do better
Adding liquid antistrip or lime usually improves the HWT results. Improvement with lime is usually more dramatic than with liquid
Harder aggregates do better (Igneous vs. limestone)
Stone on stone mixes do better than dense mixes
Time Required for One Lab Mixed Test
Task Minutes HoursGrading Aggs 60 1.00
Mixing 45 0.75Compacting 20-210 0.33-3.5
Cutting, Prep, & RICE 45 0.75Achieving Temperature 60 1.00Testing 20,000 Passes 390 6.50
Cleanup 20 0.33
TOTAL: 640-830 10.5-14
Cost to PurchaseHWT Machine: $60kAccessories: $2kProfessional Installation:
$1.2k(Optional) Crane: $3kConstruction Costs: $5k-$30k
TOTAL CAPITAL COST: $71,000-$96,000
Cost to OutsourceOnly a few 3rd party machines
in the state
Field Samples: $900-$1700Lab Mixed Samples: $1200-
$2000
What to do on Your JobAvg. job may have 20,000-30,000
tons of mixNeed one test for Mix
Design/VerificationNeed one test for Production
StartupNeed one test for every 10,000
tons
Avg Testing for Caltrans Job: 3-5 samples
Hamburg & TSR TestingCan not hand mix samples for
mix design test resultsMust be run through the hot
plant for mix design testing (also counts as verification sample)
TSR no longer a ratio, must pass dry & wet strength minimum specifications
Freeze thaw required
Hamburg & TSR Testing Cont.
If you cannot meet the minimum HWT or TSR requirements you must test PI and treat your mix using a specified antistrip treatment
HWT Sample AmtsMix Design/VerificationProduction Startup1 per 10,000 tons or 1 per
project, whichever is greater
4 Pucks ≈ 9200 grams (Per Split)
TSR Sample AmtsMix Design/VerificationProduction Startup1 per 10,000 tons or 1 per
project, whichever is greater
6 Pucks ≈ 21,600 grams (Per Split)
Gyratory Sample AmtsMix DesignVerificationProduction Startup1 per 4,000 tons or 2 every 5
paving days, whichever is greater
3 Pucks ≈ 14,100 grams (Per Split)
Verification Sample Tonnages120 lb for each Coarse Agg80 lb for each Fine Agg10 lb for each Supplemental FineMinimum of 50 lb from each RAP
stockpile or 100 lb from the belt
Total Agg: >460lbs-630lbs (1/4 Ton!)
HMA: ≥250lbs◦Likely will need ≈650-1000lbs (1/4-1/2
Ton!)
Sample LocationsQC samples from anywhere per CT125QA TSR & Hamburg sampled from:
◦Automatic sampling device at the plant◦Automatic sampling device at the truck◦Windrow
All other QA HMA samples from:◦Automatic sampling device at the plant◦Automatic sampling device at the truck◦Windrow◦Mat behind the paver
Automatic Plant Samplers
Sample box attaches here
Automatic Plant Samplers
Automatic Truck Samplers
Automatic Truck Samplers
On Site Storage?Too much volume of samples
for retentionWork with Caltrans to
develop onsite storage with their lock for QA sample retention
No More Lost Samples!
QC Nuclear Density TestingRequired to perform QC
Nuclear Gauge Density (CT375) for all non-minor jobs
3 per 250 tons or 3 per paving day (whichever is greater)
Not used for acceptance, still using cores for acceptance
JMF ModificationsNow need new JMF if changing
binder source, LAS producer, or LAS dosage
Can do a modification instead of full mix design instead
Only test at OBCCaltrans verifies Hamburg, Air
Voids, VMA, DP, & TSR (if desired)Each modification costs $2000
Verification ChangesMust verify with plant set
within 0.2% of OBC binder content
Only two tries for free, additional tries are $3000
April 11, 2023
AMRL AccreditationCaltrans will require AMRL
accreditation to move towards national standards and hopefully reduce workload on the Caltrans IA staff.
Implementation will be with Superpave specs in July 2014
36
April 11, 2023
AMRL’s RoleAccredits any of your labs
that do testing for Caltrans Superpave mix designs
Does not need to accredit basic labs (aka. only gradations, oil content, SE, etc.)
Accredits lab & equipment, does not certify each individual technician
Proficiency Sample Program37
April 11, 2023
Caltrans’ IA RoleTechnician Proficiency TestingTechnician Certification
◦Still certify for HVEEM jobs◦Some test methods do not have equivalent AASHTO methods.
Caltrans Laboratory Accreditation Manual
Reference Sample Program
38
AMRL FeesApplication ($250 one time)Admin Fees ($725 annually)
◦$350 Base Fee ◦15 methods*$25/method ◦ Applied after 1st year
Basic Fees for 2 Scopes ($900 in assessment year)
Individual Test Fees ($2960 in assessment year)Proficiency Samples ($1480 annually)
TOTAL: ≈$4135 on a year
April 11, 2023
Out-of-SequenceNext tour: Oct 2014-June
2015Can be 1.5x normal feeGroup w/ other labs
Fee may not apply to new laboratories, contact AMRL for estimate.
40
http://www.missionsandiego.com/
http://www.sandiegohistory.org/journal/77winter/bajaimages.htm
http://www.sandiegohistory.org/journal/77winter/bajaimages.htm
http://waterandpower.org/museum/Early_Views_of_the_San_Fernando_Valley.html
http://www.cahighways.org/elcamino.html
http://www.matichcorp.com/category/1-highways.html
http://www.fmgrinding.com/gallery.html
http://gallery.moeding.net/AroundTheWorld/NorthAmerica/SouthWest/OnTheRoad/
Questions?Comments?