Tokamak Cooling Water System ORNL US ITER Project Tokamak Cooling Water System Presented to ITER...
-
Upload
braxton-willett -
Category
Documents
-
view
237 -
download
4
Transcript of Tokamak Cooling Water System ORNL US ITER Project Tokamak Cooling Water System Presented to ITER...
Tokamak Cooling Water System ORNL
US ITER Project
Tokamak Cooling Water System
Presented toITER PROJECT
1st INFORMATION FORUM
Kirby Wilcher
Cooling Water Systems Engineer
November 15, 2006
Tokamak Cooling Water System ORNL2
Tokamak Cooling Water System Team
Jan Berry
WBS Manager
Karen McElhaney
System Engineer
Kirby Wilcher
System Engineer
Robyn Rose
Project Controls
Jan Berry
WBS Manager
Tokamak Cooling Water System ORNL3
Cooling Water System
• Scope based on 2001 Design • CWS Consists of 4 Systems
– Tokamak Cooling Water System (TCWS)– Component Cooling Water System (CCWS)– Chilled Water System (CHWS)– Heat Rejection System (HRS)
Tokamak Cooling Water System ORNL4
US Scope
Physical Boundary of TCWS
Tokamak Cooling Water System ORNL5
Tokamak Cooling Water System
• TCWS Consists of 7 Sub-systems– Primary Heat Transfer System (PHTS)
Primary First Wall & Blanket (PFW/BLK) Diverter/Limiter (DIV/LIM) Vacuum Vessel (VV) Neutral Beam Injector (NB)
– Chemical and Volume Control System (CVCS)– Drain and Refilling Systems– Drying System
Tokamak Cooling Water System ORNL6
Primary Heat Transfer from In-Vessel Components Fabricated by Sub-System
• First Wall & Blanket (WBS1.2.1.1) and Neutral Beam Injector (WBS1.2.1.4):– Upper Pipe Chase– Vault
• Diverter/Limiter (WBS1.2.1.2):– Lower Pipe Chase– Upper Pipe Chase– Vault
• Vacuum Vessel (WBS1.2.1.3):– Lower Pipe Chase– Upper Pipe Chase– Roof
PHTS
Tokamak Cooling Water System ORNL7
1 GW Heat Removal Required by PHTS; Various Operating Modes
Primary Heat Transfer System (PHTS)
Operating Mode Conditions
1.2.1.1 First Wall and Blanket • Pulse: Thermal load (MW) Inlet temperature (°C)Inlet Pressure (MPa)
• Baking: Inlet temperature (°C) Inlet Pressure (MPa)
~ 690 100 (212oF)3.0 (435 psi)240 (464oF)4.4 (638 psi)
1.2.1.2 Diverter and Limiter • Pulse: Thermal load (MW) Inlet temperature (°C)Inlet Pressure (MPa)
• Baking: Inlet temperature (°C) Inlet Pressure (MPa)
202 100 (212oF)4.2 (609 psi)240 (464oF)4.4 (638 psi)
1.2.1.3 Vacuum Vessel • Pulse: Thermal load (MW) Inlet temperature (°C)Inlet Pressure (MPa)
• Baking: Inlet temperature (°C) Inlet Pressure (MPa)
• Decay heat removal: Heat load to Vacuum Vessel (MW)
10 100 (212oF)1.8 (261 psi)200 (392oF)2.4 (348 psi)
0.8 (peak)
1.2.1.4 Neutral Beam Injector • Low voltage: Thermal load (MW) Inlet temperature (°C)• High voltage: Thermal load (MW) Inlet temperature (°C)
100<80 (176oF)
1230 (86oF)
Tokamak Cooling Water System ORNL8
Chemical and Volume Control System;PFW/BLK
Tokamak Cooling Water System ORNL9
Chemical and Volume Control System;Various Operating Modes
Operational state or modePlasma Operation
StateBaking
Decontamination Mode
Volumetric Flow Rate (at inlet) 45 m3/h (198 gpm) 45 m3/h (198 gpm) 90 m3/h (396 gpm)
Feed Coolant Temp. 148°C (298oF) 240°C (464oF) 100°C (212oF)
Return Coolant Temp. 120°C (248oF) 190°C (374oF) 83°C (181oF)
Feed Coolant Pressure 1.7 MPa (247 psi) 4.3 MPa (624 psi) 1.7 MPa (247 psi)
Return Coolant Pressure 3.4 MPa (493 psi) 4.6 MPa (667 psi) 3.4 MPa (493 psi)
Tokamak Cooling Water System ORNL10
Drain and Refilling Systems;DIV/LIM
Tokamak Cooling Water System ORNL11
Drain and Refilling Systems; Various Operating Modes
System Number of drain tanks* Total internal volume (m3)
PFW/BLK PHTS 2 (1) ~ 500 (~132,000 gal)
DIV/LIM PHTS 2 (1) ~ 200 (~52,800 gal)
VV PHTS 2 ~ 120 (~31,700 gal)
NB injectors PHTS 2 (2) ~ 120 (~31,700 gal)*number of tanks in parentheses indicates those used for drainage following an in-vessel coolant leak
Tokamak Cooling Water System ORNL12
Drying System
Tokamak Cooling Water System ORNL13
Drying System; Various Operating Modes
Blow-out mode Heat-up mode Dry-out mode
Fluid Nitrogen Nitrogen Nitrogen + H2O (steam)
Fluid Inlet Temp. 40°C (104°F) 210°C (410°F) 210°C (410°F)
Fluid Outlet Temp. 40°C (104°F) 160°C (320°F) 160°C (320°F)
Fluid Inlet Pressure 4.0 MPa (580 psi) 2.1 MPa (305 psi) 0.6 MPa (87 psi)
Tokamak Cooling Water System ORNL14
New Cost Share Agreement SimplifiesInterfaces with Participant Teams
• Initial cost share agreement divided responsibility by location (inside vault/outside vault)
• New agreement divides responsibility by activity:– US no longer responsible for installation– US responsible for materials, components, and shipping
Increases US responsibility for fabrication Pre-fabrication reduces overall ITER cost
– IO responsible for engineering, on-site assembly and testing US ITER is contributing engineering
Tokamak Cooling Water System ORNL15
Seven Sub-Systems Distributed Throughout Tokamak Building
Primary Heat Transfer:• Vault• Upper Pipe Chase• Roof• Lower Pipe Chase
Support Systems:• Draining and Refilling
(WBS1.2.1.6)
• Chemical and Volume Control System (WBS1.2.1.5)
• Drying (WBS1.2.1.7)
Tokamak Cooling Water System ORNL16
Requirements Under Review
• Vendors Must Be Able to Comply with US and EU Codes & Standards– American Society of Mechanical Engineers Standards– Pressure Equipment Directive (European Union Directive)– ESPN (French Order on Nuclear Pressure Equipment)
• Nuclear vs. Non-nuclear Classification of TCWS Components to be Determined by ITER and French Regulatory Authorities
• Applicable Codes & Standards Still Under Review• Materials of Construction:
– 304L/316L Stainless Steel
Tokamak Cooling Water System ORNL17
Component Delivery by 2014
Deliverable Estimated Schedule Final DeliverySkids/Components for ITER-IO Approval Date
Stainless Steel Piping 18,450 meters Apr-07 Deliver to Fabricators
Design and Title III October 2007 March 2014
Lower Pipe Chase 10 December 2008-February 2009 June 2010
Upper Pipe Chase 30 May-July 2011 December 2013
Vault 25 May-July 2011 December 2013
Roof 10 May-July 2011 December 2013
WBS 1.2.1.5 30 October-December 2010 May 2013Chemical & Volume Control System
WBS 1.2.1.6 20 February-April 2009 June 2010Draining and Refilling System
WBS 1.2.1.7 10 November 2010-January 2011 October 2014Drying System
Estimated Number of Skids/Components 135
Tokamak Cooling Water System ORNL18
Additional Information
Additional information available at:• General Information
www.iter.org
• ITER Technical Basis
http://www.iter.org/a/index_use_5.htm
Tokamak Cooling Water System ORNL
US ITER Project
Backup Information
Detailed Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL20
Preliminary Schedule
Tokamak Cooling Water System ORNL21
Preliminary Schedule (Cont.)
Tokamak Cooling Water System ORNL22
Systems Integration Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL23
First Wall and Blanket Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL24
Divertor/Limiter Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL25
Vacuum Vessel Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL26
Neutral Beam Injector Preliminary Schedule and Milestones
Tokamak Cooling Water System ORNL27
Chemical and Volume Control System—May 2013
Tokamak Cooling Water System ORNL28
Draining and Refilling Schedule—June 2010
Tokamak Cooling Water System ORNL29
Drying System Schedule—October 2013