Today - Massachusetts Institute of...

11
1 Today: What is risk identification Example problem Tools and Methods

Transcript of Today - Massachusetts Institute of...

Page 1: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

1

Today:

What is risk identification

Example problem

Tools and Methods

Page 2: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

2

‘Risk’ - Any issue that could arise during a project or section of a project

Commercial

Technical

User Experience

Intellectual Property

Manufacture

Regulatory

Health & Safety

Etc...

Page 3: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

3

Each ‘Risk’ has a severity rating based on how easily the risk could be overcomeif it occurs.

The severity ratings are calculated by scoring risk against:

– Impact - effect of risk on project outcome

– Likelihood - probability of risk being realised

– Scale - effort required to mitigate risk (this could also be used for associatedcost)

– Uncertainty - degree of familiarity with identified risk

Page 4: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

4

The Risk profile LikelihoodIm

pact

5

1 5

1

Page 5: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

5

Scales Used For Scoring Risk (adapted to each project)1 2 3 4 5

Negligible Minor benefit lostMajor benefit lost /cost target missed /

phase repeated

Commercial viabilityof product marginalIm

pact

Project fails

Extremely unlikely Unlikely 50 / 50 likelihood Likely

Like

lihoo

d

Extremely likely

< 1 week 1 week 1-3 weeks 1 Month

Sca

le

> 1 Month

We have done itbefore

We have donesimilar before or

others have solvedthis before

Others have solvedsimilar before

Not solved beforebut it is clear how to

approach it

Unc

erta

inty Research project

needed beforeproblem can be

tackled

Page 6: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

6

When to evaluate risk

At the brainstorm phase

– Selection criteria

At the concept selection

– Critical Path

At technical review

– Areas for further analysis

Prior to manufacturing

– Assembly

– Process restrictions

Page 7: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

7

You have been given the task to Designed the next generation Auto Injector

Page 8: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

8

Methods to identify risk

Module

Part by part

Function

User Based

Page 9: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

9

What are the next steps

Make sure scores makes sense

Identify risks that need mitigation

Determine mitigation plan

– How can you best reduce the likelihood that a problem will occur

Page 10: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

10

Ways to reduce risk

Research

– Existing solutions

– Similar mechanism

– Talking with Manufacturers

Modeling

– Calculations

– FEA

Prototyping

– Quick and dirty and Cheap

Page 11: Today - Massachusetts Institute of Technologyweb.mit.edu/2.009/www/resources/mediaAndArticles/DyerIdentifyingDe… · What is risk identification Example problem Tools and Methods.

11

Prototyping

Looks like

Works like

Made like

Feels like (user studies)

Dangers

– Not representative of final system

– Works good enough team not willing to iterate

– Prototype to costly in time and money

– Not considering how it will be made later (manufacturing tolerances / cost)