CONSTITUTION HALL • 525 WEST ALLEGAN STREET • P.O. BOX 30028 • LANSING, MICHIGAN 48909-7528 www.michigan.gov/dnr • (517) 284-MDNR(6367)
STATE OF MICHIGAN
DEPARTMENT OF NATURAL RESOURCES LANSING
GRETCHEN WHITMER GOVERNOR
DANIEL EICHINGER DIRECTOR
Date:
To:
From:
July 21st, 2020
Patrick Smith - Florence County Forestry and Parks
Jeff Kakuk - West U.P. Trail Specialist
Subject: Menominee River Bridge Summary - Project No. 751/15276.JBB
Design and planning for the reconstruction of the Menominee River Bridge began moving forward in 2016. The bridge Engineering and Design contract is with OHM Advisors. In September of 2016 an Opinion of Probable Construction Cost was presented. The total construction cost estimate was, at that time, $1,304,710.00 to which an additional 18% +/- would need to be added for project administration. That would have placed the total project costs around 1.5M.
As design work continued the existing bridge railing was found to be unsafe and the options of closing or repairing were presented. The full funding had not yet been secured by either state and the repair option was determined to be the best option. That design and construction occurred in 2017 with construction project costs of $45,250 plus additional costs for design and Construction Administration.
Between June and October of 2017, the Wisconsin DNR awarded three grants to Florence County Forestry and Parks Department totaling $480,000.
As this project was preparing to release bids the team discussed the work scope and decided that based on the current funding and type of work that it made the most sense to break the project into two Phases (Phase 1 – trestle deck, Phase 2 abutment repairs).
Bids have been received for Phase 1 and the full project cost (original design, emergency railing repairs, Phase 1 construction, all administrative and oversight fees) have been determined. The costs for Phase 2 are based off an updated construction estimate.
Current cost summary for the Menominee River Bridge: Phase 1 Phase 2 Total Project Projection
$ 1,154,570 *actual $ 267,004 *estimated $ 1,421,574 ($710,787 50% cost share)
**It should be noted that this projected cost in 2020/21 is still below the estimated amount presented in 2016 prior to the emergency work.
To date the State of Wisconsin has committed $480,000 and the State of Michigan $629,000
Florence has rcvd $479,956 in grant funds to date. Seeking additional $230,831 in additional funds ($115,415.50 each from ATV and Snowmobile) for Wisconsin's share of the bridge.
#92 - Cost Increase Req from Florence Co for the Menominee River Bridge (ATV-3701 and S-5075)
State of Wisconsin Department of Natural Resources
Outdoor Motorized Recreation Trail Aids Application
PO Box 7921, Madison WI 53707-7921 dnr.wi.gov
For: (Choose all that apply) Form 8700-159 (01/14) Page 1 of4
� All-Terrain Vehicle Trail Aids D Motorized Stewardship D County Snowmobile Trail Aids (20% match required)
Notice: Completion of this form is required under s. 23.09(26) and 23.33, Wis. Stats. Failure to complete this form will result in denial of financial assistance. Personally identifiable information found on this form is not intended to be used for any other purpose. The Department may provide this information to requesters as required by Wisconsin's Open Records law [ss. 19.31 - 19.39, Wis. Stats.].
Instructions: Applications may combine more than one source of funds. They may be submitted for consideration of both traditional ATV, Snowmobile funding AND Motorized Stewardship funding. Submit two (2) copies of all forms and attachments. See page 2 for necessary attachments. Mail applications to your Community Services Specialist.
Activities Involved in Application: (Select all that apply) Leave Blank - DNR Use Only
D Maintenance D Insurance 181 Bridge Rehabilitation OAcquisition D Development OTrail Rehabilitation
Applicant Information
Project Number
Applicant/Organization Name Florence County Forestry and Parks
Check Recipient: Individual other than authorized individual to act on behalf of the applicant. Provide check recipient information below:
Authorized Individual Name, Title
Patrick Smith
Check Recipient Name: (Name to Appear on Check)
Florence County Forestry and Parks Department Address
5617 Forestry Drive City, State, ZIP Code
Florence, WI 54121 Telephone Number
(715) 528-3207
Project Title
Menominee River Bridge Repair Project Description
Address
5617 Forestry Drive City, State, ZIP Code
Florence, WI 54121 E-Mail Address
• For maintenance, include a concise statement of the type of maintenance activities and the type of grooming equipment used.• For major bridge rehabilitation, describe the proposed construction items to rehabilitate the bridge.• For trail rehabilitation, describe the repair and renovation activities necessary to improve the trail for user safety.• For development, describe development activities and structures to be constructed.• For development of intensive use areas; describe the need and expected use and method of operating and maintaining the facility.• For Motorized Stewardship describe project and source of matching funds, narrative must include the source of the matching funds.• Minimum Useful Life Agreement is required to be submitted with the signed grant agreement.
Please see attached sheets for an explanation of the project.
Estimated Cost
Maintenance Acquisition Insurance Development Bridge Rehab.
217,477.5
�-· Leave ·s1arik - DNR Use Onl
Trail Rehab. Total Estimated Cost
217,477.5
As the applicant's authorized official, I certify that, to the best of my knowledge, the information in this application is true and correct.
Typed Name of Authorized Official Official's Title
Patrick Smith Forestry and Parks Administrator
The following is the ORIGINAL grant appliation, funded in 2017-18
Florence County Forestry and Parks Department
Project: US2 Railroad Corridor, Menominee River Bridge
The Florence County Forestry and Parks Department in conjunction with the Michigan DNR proposes to replace the deck and repair the structure on a 392' bridge in the Town of Florence, Wisconsin.
The structure that is in place is an old Railroad Bridge. While the substructure of the bridge is in
relatively good shape there are areas that are in need of repair for continued long term use of the
bridge. The Michigan DNR has hired an engineering firm to design an upgrade to the current design.
We are proposing to remove the existing ties, decking and railing and replace with a steel/wood bridge
deck and railing. Other items in need of repair are the abutments, piers, and wing walls. The abutments
and piers are in need of tuck pointing, the center pier (in the River) is in need of tuck point below the
water line.
Enclosed in this application is the engineering design and cost estimate. Also enclosed are all of the
associated agreements with the Wisconsin DOT and Michigan DNR for work on the bridge and trail.
In 2014, Florence County Received a grant through the Snowmobile program to repair the railings and
decking on this bridge. In reviewing this bridge with the Michigan DNR it became apparent that the
bridge was in need of many more improvements. The grant was S-4384 for $22,740. This grant could
either be turned back to the snowmobile program or reissued to the full amount needed to complete
this project.
The US2 Railroad Grade trail is a highly used trail for snowmobiles. In 2017, this bridge will be open for
ATV use. This bridge will allow for interstate travel from Florence, WI into Iron Mountain, Michigan.
The Michigan DNR has routes through Iron Mountain to connect to other trails throughout the Upper
Peninsula.
A Michigan Engineering firm provided a design and cost estimate of $959,910.00 to remove the bridge
deck, and repair the super structure. This price includes labor, equipment, and materials. We are asking
for $45,000 from RTA, and $217,477.50 from the ATV program and $217,477.50 from the snowmobile program.
Outdoor Motorized Recreation Trail Aids Application
Form 8700-159 (01/14) Page 3 of 4
Pages 3 and 4 of this form are to be completed (including required attachments) for any new bridge development or bridge rehabilitationproject for which funds are requested. The information provided below will be used by Department staff and the appropriate advisory council to evaluate the merits of your application for funds.
(Select only one)
0 New Bridge Grant Application Supplement
0 Bridge Rehabilitation Grant Application Supplement
Official Governmental Unit Contact Patrick Smith Sponsoring Snowmobile or All-Terrain Vehicle Club Blue Ox Trail Riders Club Contact Fran Modschiedler Landowner Where Bridge is Located Wisconsin DOT and Michigan DNR
Water Body Name Menominee River
County Florence
Town No. Range No. 39 19
Telephone Number (715) 528-3207
Telephone Number (715) 674-2616Telephone Number
[g]E
ow
Section No.
11
1. If land is privately owned, how many years will the owner permit the trail to be used as a public snowmobile or all-1 20 terrain vehicle trail? (3 year minimum required) ..... ______ __. 2. What other recreational trail uses are planned for this bridge?
This is planned for Motorized recreation of Snowmobile, ATV and UTV
If there are other Recreational uses planned, how much of the bridge cost will be paid for by non-snowmobileor non-A TV users?
3. Have you contacted your local DNR water management investigator regarding a regulatory permit? @ Yes QNo
Is a permit required? @Yes QNo
Do you have an approved permit? QYes @No
New Bridge Projects Only
4. Describe the need for the bridge and alternatives considered.
Bridge Rehabilitation Projects Only
5. Briefly describe why the bridge needs to be rehabilitated.This bridge is an old Railroad bridge. There have been multiple fires on the bridge and the current decking and ties are indisrepair. The superstructure of the bridge is in need of repairs as well. Tuck pointing mortar joints and repairs of theapproaches on both sides of the bridge are also needed. We received a snowmobile grant for repairs to the decking andrailings however, the costs were much more than the grant and the grant was not used.
6. Has this bridge site ever received development or rehabilitation funds in the past? If answer is yes, give year funds were received, amount of grant award and program.
I Year: 2014 '$22,740.00 !Program: Snowmobile
QYes@No
Complete the cost estimate information on page 4 and attach additional materials if more justification is necessary.
Attachment to A TV Grant Application
The DNR will not fund any A TV projects located near or crossing a waterway or wetland, unless the required documentation listed below and the checklist on the reverse side is provided with the application. This must be completed for the following ATV grant applications:
• Bridge/Trail Rehabilitation• NewBridge• Trail Relocations (mandatory and discretionmy)• New Miles (all seasons)
The required documentation is:
¢Digitized topographic map of trail with bridge/culvert, waterway, wetland location(s), and project boundary identified (include an electronic copy if any archaeological/historical concerns are found) [Map scale should be no more than 4 sections per 8.5"x 11" map page]
IX[ Aerial photograph of trail with bridge/culvert, waterway, and wetland location(s) identified [Map scale should be no Il)9re than 4 secti
o?§ per 8.5"xl I" map page]!£l.Name of waterway(s) t!1 i'vt.aMr'<,0- ll:;\,cg ,.,...-��otograph of bridge/culvert crossing location(s) from upstream, downstream, and from both
directions across the structure.
Instructions:
The applicant is required to consult the information sources listed on the reverse side to answer the filter questions. Do not contact DNR staff for navigability or wetland detem1inations as part of completing this application. DNR staff will be reviewing all grant applications to verify that wetlands and navigability criteria are met, and to identify any permit requirements.
If you answered YES to either of the Resource Questions on the reverse side, your project may require a waterway, wetland or stormwater permit from DNR. Trail projects should be designed to avoid wetland impacts wherever possible. Alternatives that will avoid or minimize wetland impacts should be considered during the planning process, such as alternate routes or boardwalk design. If wetland impacts are unavoidable, you will be required to provide additional information during permit review about affected water resources, wetland boundaries, alternatives that were considered and why wetland impacts are unavoidable. If your project was approved by the ORV Council, the grant will NOT be written until all required permits have been applied for and approved by DNR staff.
If you answered NO to the Resource Questions on the reverse side and DNR staff confirm this inforn1ation, grants may be written as soon as an internal review is completed by staff, and all additional questions are answered.
The attachments identified above should accompany your ATV Application ( due April 15). If documentation requested below is already being requested on another form for the same project, you only need to provide it one time. If you have questions regarding these requirements, contact your regional CSS.
Please provide a separate application and attachment for each project.
Is this trail on public or private land?
Trail/Structure Conditions
�blic D Private
What is the length of the easement? ___ [in years] Expiration Date ____ _
Are there other sources of funding committed to this project already? D Yes D No
If so, what is the source? --------------------
How many miles would be affected if this project is not funded? JOi4io/ � /:'t(},..,« cvJ.. +k.:, ,'':>4. c.rr,�.·,�l l_r..,k fv,. M:t -t- � +,-.,.'-b '---T
Will this result in closure of a trail? D Yes, it will close this season D Yes, but won't be this season � No, not this season
Is this a critical section to the overall trail system? lctYes D No
Is there a reasonable alternative? D Yes � No (If YES, please explain)
How would you rate the existing trail and/or structure? (provide a separate rating for each strncture and the trail.) D In poor condition, will be condemned if not replaced this year �In stable condition but needs to be replaced soon 0 In fair condition but should be replaced
Identify the funds previously spent on this trail and over what length of time? $________ over _ _____ years/months (circle one)
Resource Questions
1. Will this project be located near or cross any intermittent or perennial waterway, based on consulting� DNR's Surface Water Data Viewer maps using the link below?}l¼Yes 0No
Check to indicate that the map below has been consulted:P<l Surface Water Data Viewer- Open Water and River and Streams maps
fhttp://dnrmaps.wisconsin.gov/imf/imf.isp?site=SurfaceWaterViewer
2. Will this project be located near or cross any wetland, based on consulting the maps linked below?0Yes �No
Check to indicate that both the maps below have been consulted:[81:surface Water Data Viewer- Wisconsin Wetland Inventory� Surface Water Data Viewer-Wetland Indicatorstittp://dnrmaps. wisconsin .gov/imf/imf.jsp?site=SurfaceWaterViewer. wetlands
3. Will this project involve land disturbance - including clearing and grubbing- of 1 acre or more ofland? (l�han 4/ 10th mile for a typical ATV trail) 0Yes� No
If Yes, check to indicate that both the maps below have been consulted for proximity to wetlands: D Surface Water Data Viewer- Wisconsin Wetland Inventory D Surface Water Data Viewer- Wetland Indicators http:/ldnrmaps. wisconsin .gov/imf/imf.jsp?site=SurfaceWaterViewer. wetlands
\ \
\I
\I
I I
I I
I I
I I
I
.. ..
I •
. ..
··;
-- .
· . 'J .. ; 0 . � : ' .
� �
� i<" -� /
. . . . - ..r-.- -
. . ..
0 0 0) V
0 0
�i�;HEAST FLORENCE �i:;H AURORASEE PAGE 38
, \
, \Florence ..c:: � 0
: County r- -- ---1 � �; , ) CFL 92 G°ct'/!� �i
nd
� 8 .g
·,, • ·, 88°
09'
(D 2014 Rockfo,/Map Pubis., Inc. SEE PAGE 2400 2000 1600
88°'08' 16
88° 07' Florence County, WI
1200
26
T.39N.-R.19E.Refer to page 50 for keyed parcels
. 400
\� 3r <'d.� ss0 os· L a ct-< 1 r "'"'
EDWARD
NEUENS
&SON SERVING THE AREA
FOR OVER 50 YEARS
SEPTIC PUMPING
& INSPECTIONS
WATER & SEWER LINES
INSTALLED
BASEMENT DIGGING
TRENCHING
SEPTIC SYSTEM
INSTALL ATION
TOPSOIL • GRAVEL
FILL DIRT
Aurora, Wisconsin
(715) 589-4409
C.
(..
C
C
C
C.
C
C.
C.
C
C
C.
r:.
�
C
t:
C:
C:
C:
C:
C
e:
e
e:
e
e:
e
e
e:
e
e
e
e
e
e:
e
-�
e'
e
C:
C:
C:
C
(C'
OPINION OF PROBABLE
CONSTRUCTION COST
ORCHARD, HILTZ & McCLIMENT, INC.
424 Hancock St, Hancock MI, 49930 Telephone: (906) 482-0535 FAX: (906) 482-6453
PROJECT: Menominee River Bridge Repairs DATE: March 24, 2017
LOCATION: Iron Mountain, MI PROJECT #: 7136-16-0020
WORK: Bridge Deck Replacement ESTIMATOR: ZAH
CHECKED BY: SEW
CURRENT ENR: SEW
1027051 _Redi-Rock Wing Wall LS 1 55,000.00$ 55,000.00$
1500001 Mobilization, Max. ____ LS 1 66,000.00$ 66,000.00$
2010001 Clearing Acre 0.5 5,000.00$ 2,500.00$
2047051 _Structure, Rem (Bridge Deck) LS 1 50,000.00$ 50,000.00$
2047051 _Structure, Rem (Timber Wall) LS 1 5,000.00$ 5,000.00$
2050010 Embankment, CIP Cyd 140 15.00$ 2,100.00$
2050016 Excavation, Earth Cyd 140 9.50$ 1,330.00$
2050030 Machine Grading Sta 1 1,000.00$ 1,000.00$
2060001 Aggregate, 6A Cyd 4 5.00$ 20.00$
2080036 Erosion Control, Silt Fence Ft 600 2.50$ 1,500.00$
3060010 Aggregate Surface Cse, 6 inch Syd 266 8.50$ 2,261.00$
7090010 Hardware, Misc. LS 1 3,000.00$ 3,000.00$
7097051 _Bridge Deck LS 1 440,000.00$ 440,000.00$
7097052 Approach Railing Ft 80 100.00$ 8,000.00$
7110003 Reflective Marker, Permanent Barrier Ea 8 8.00$ 64.00$
7120016 Patching Mortar or Conc Cft 25 450.00$ 11,250.00$
7120017 Patch, Forming Sft 4980 30.00$ 149,400.00$
8120170 Minor Traf Devices LS 1 1,500.00$ 1,500.00$
SHOW 799,925.00$
CONTINGENCY ( 20% ) SHOW 159,985.00$
TOTAL OPINION OF PROBABLE CONSTRUCTION COST = 959,910.00$
ITEM
CODEDESCRIPTION UNIT TOTAL UNIT PRICE COST