Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

28
PIPELINE QRA SEMINAR

Transcript of Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

Page 1: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

PIPELINE QRA SEMINAR

Page 2: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

2

PIPELINE RISK ASSESSMENTRISK ACCEPTANCE CRITERION

Page 3: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

3

“comparing the level of risk found during the analysis

process with risk criteria established”

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 4: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

4

• Why do you have a risk acceptance criterion?

• End-point of the risk assessment

• To be able to say whether the risk is acceptable or not

• Established by companies (internal) and/or authorities

(external)

• Base for decision-making

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 5: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

5

• Usually talking about:

- Tolerable (acceptable - green)

- Intolerable (unacceptable - red)

• And then…

- ALARP (control to ALARP/acceptable if ALARP - yellow)

• What is ALARP?

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 6: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

6

• Two conflicting objectives need to be balanced

-We have a desire to do everything physically possible to

remove all risks

- We have limited resources and that it is nearly always not

practical (nor physically possible) to remove all risk

• ALARP principle include demonstrate that the cost

involved in reducing the risk further would be grossly

disproportionate to the benefit gained

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 7: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

7

• When is a risk tolerable (acceptable)?

• What is a risk intolerable (unacceptable)?

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 8: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

8

• Everyday life – risk perception deciding the risk acceptance

criterion

Definition (Wikipedia)

“the subjective judgment that people make about the

characteristics and severity of a risk”

• 19 per 100.000 deaths from driving

• < 0.5 per 100.000 deaths from flying

• 268 per 100.000 deaths from cardiovascular diseases

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 9: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

9

• Risk perception could be depending on a number of factors:

- Social context (e.g. group pressure)

- Benefits versus losses (i.e. what could be gained versus lost)

- Risk aversion (i.e. better many small accidents than one

catastrophe)

- Control (e.g. driver versus passenger)

- Experience (i.e. unknown or know)

• Driving versus flying

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 10: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

10

• Working life – different theoretical approaches on how to

decide the risk acceptance criterion

- Comparison (e.g. statistics on accidents/fatalities and

other industries/activities)

- State-of-the-art (i.e. as safe as possible)

- Economics (i.e. price per human life)

• Different for organizations (e.g. the well being for many)

versus companies (e.g. economical aspects) versus

authorities (e.g. combinations)

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 11: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

11

• Traffic authorithy in Sweden state that 22.3 million SEK

(5.5 million GEL) is the acceptable cost for saving a life

• Safety systems (e.g. traffic barrier) is analyzed with this

approach

• How many lives could we save with this implementation

of safety system – comparison with total cost and the

acceptable cost for saving a lie (or several lives)

EXAMPLE OF RISK ACCEPTANCE CRITERION – SWEDEN TRAFFIC AUTHORITY

Page 12: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

12

• Traffic authority in Norway state that 25.0 million NOK

(5.5 million GEL) is the acceptable cost for saving a life

• Offshore industry in Norway state that up to 100.0

million NOK (up to 27.3 million GEL) is the acceptable

cost for saving a life

EXAMPLE OF RISK ACCEPTANCE CRITERION – SWEDEN TRAFFIC AUTHORITY

Page 13: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

13

• What kind of risk acceptance criterions are there?

• Quantitative and qualitative (compare with quantitative risk assessment and qualitative risk assessment)

• You can have risk acceptance criteria for everything!

-Environmental

-Human safety (e.g. discomfort, injuries and fatalities)

-Economical

-Project (e.g. delay)

-Reputation

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 14: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

14

-Environmental (e.g. allowable size of release and impact on the

environment)

-Human safety – individual risk (i.e. allowable risk for a single person)

- Human safety – group risk/societal risk (i.e. allowable risk for a defined

population)

- Human safety – consequence distance (e.g. allowable for dispersion of

gas)

-Economical (e.g. allowable potential loss from investment and cost)

-Project (e.g. allowable delay)

-Reputation (e.g. allowable attention from news, NGO’s and authorities)

INTRODUCTION TO RISK ACCEPTANCE CRITERION

Page 15: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

15

• Current risk acceptance criteria - consequence distance of

200 meters (no activities or structures)

• Difference between consequence distance of 200 meters

(fixed) and consequence distance of X meters (based on

calculations of allowable concentrations)

• Paper product versus actually practical (e.g. pipelines in

urban areas and supply of gas to industries/residences)

EXAMPLE OF RISK ACCEPTANCE CRITERION – GEORGIA PIPELINES

Page 16: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

16

• Future risk acceptance criteria – human safety based (e.g.

individual risk/societal risk)

• What could be the benefits?

- Flexibility - allow activities and structures within 200 meters

(sometimes not!)

- Actual knowledge and understand of the risk from the pipeline

EXAMPLE OF RISK ACCEPTANCE CRITERION – GEORGIA PIPELINES

Page 17: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

17

• Qualitative risk acceptance criteria

- Risk matrix

- Descriptions

• Descriptions support to the risk matrix

• Descriptions

- Human safety (e.g. minor injury or health effect or multiple

fatalities)

- Environmental (e.g. major environmental damage over an

extensive area, but recovery is possible)

- Reputation (e.g. National public, government or NGO concern)

QUALITATIVE RISK ACCEPTANCE CRITERION

Probability/frequency

HighMedium

LowLow Medium High

Consequence

Page 18: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

18

QUALITATIVE RISK ACCEPTANCE CRITERION

Probability/frequency

HighLow

Low High

Consequence

Probability/frequency

SevereSignificantModerate

MinorNegligible

Very unlikely

Unlikely Possible LikelyVery likely

Consequence Probability/frequency

HighMedium

LowLow Medium High

Consequence

Page 19: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

19

QUALITATIVE RISK ACCEPTANCE CRITERIONProbability/frequency

HighMedium

LowFatalities Injuries Discomfort

ConsequenceProbability/frequency

HighMedium

Low

Massive environmental

impact (no recovery)

Massive environmental

impact (recovery)

Small environmental impact (recovery)

Consequence

Page 20: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

20

• Quantitative risk acceptance criteria

- Numerical values (more or less)

• Human safety - individual risk

- individual risk for 1st person (e.g. operator)

- individual risk for 3rd person (e.g. public)

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 21: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

21

• Human safety – group risk/societal risk

- group risk/societal risk for 1st person and 3rd person

(including the entire population)

• Presented as FN-curve

- Frequency plotted against the number of fatalities

- Cumulative frequency of N or more fatalities

- Criteria 1 – 1 fatality with frequency 1 x 10-3 per year

- Criteria 2 – 10 fatalities with frequency 1 x 10-5 per year

- Criteria 3 – 100 fatalities with frequency 1 x 10-7 per year

• Offshore also presented as FAR (Fatal Accident Rate)

- Fatalities per 0.1 billion (108) working hours (or exposure hours)

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 22: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

22

• FN-curve

- Frequency plotted against the number of fatalities

- Cumulative frequency of N or more fatalities

- Criteria 1 – 1 fatality with frequency 1 x 10-3 per year

- Criteria 2 – 10 fatalities with frequency 1 x 10-5 per year

- Criteria 3 – 100 fatalities with frequency 1 x 10-7 per year

- Accident 1 – 100 fatalities with frequency < 1 x 10-9 per year

- Accident 2 – 10 fatalities with frequency 4 x 10-7 per year

- Accident 3 – 1 fatality with frequency 1 x 10-5 per year

- Accident 4 - …

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 23: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

23

• Who is deciding the risk acceptance criterion?

• Established by organizations (guidelines), authorities

(legal requirements) and companies (internal

requirements)

• Different theoretical approaches for organizations (e.g.

the well being for many) versus companies (e.g.

economical aspects) versus authorities (e.g.

combinations)

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 24: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

24

• Comparison of different quantitative risk acceptance criterion for individual risk:

- U.K. – 3rd party – acceptable at < 1.0 x 10-6 per year

- Netherlands – 3rd party - acceptable at < 1.0 x 10-8 per year

- Netherlands – 3rd party - unacceptable at > 1.0 x 10-6 per year (for new facilities)

- Netherlands – 3rd party - unacceptable at > 1.0 x 10-5 per year (for existing facilities)

- Venezuela – 1st party – acceptable at < 1.0 x 10-6 per year

- Venezuela – 1st party – unacceptable at > 1.0 x 10-3 per year

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 25: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

25

• Comparison of different activities and quantitative risk acceptance criterion for individual risk

(usually < 1.0 x 10-6 per year):

- dying (non-specific cause) - 1.0 x 10-2 per year

- smoking (20 cigarettes per day) – 5 x 10-3 per year

- 1.0 x 10-6 per year

- killed by lightning - 1.0 x 10-7 per year

- killed by meteorite - 1.0 x 10-11 per year

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 26: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

26

• Comparison of different quantitative risk acceptance

criterion for group risk/societal risk

- Dark blue – Flanders (region in Netherlands)

- Blue – Netherlands

- Pink – Denmark (where grey indicate ALARP)

- Red – indicative value for U.K.

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 27: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

27

• Comparison of different activities and quantitative risk acceptance criterion for group risk/societal risk

(usually FAR = 15 – fatalities per 108 working/exposure hours):

- staying at home - 3

- agriculture – 3.7

- 15

- driving a car - 57

- driving a motorcycle - 660

QUANTITATIVE RISK ACCEPTANCE CRITERION

Page 28: Title slide PIPELINE QRA SEMINAR. PIPELINE RISK ASSESSMENT RISK ACCEPTANCE CRITERION 2.

28

QUESTIONS?