“TIPS FOR PREPARING FOR YOUR OSHA PSM...
Transcript of “TIPS FOR PREPARING FOR YOUR OSHA PSM...
1 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Texas Chemical Council Environmental, Health & Safety Seminar
Moody Gardens Convention Center Galveston, Texas
“TIPS FOR PREPARING FOR YOUR
OSHA PSM INSPECTION” June 5, 2013
Mark S. Dreux, Esq. Arent Fox LLP
1717 K Street, N.W. Washington, D.C. 20036
202-857-6405 (o) 703-628-6742 (c)
E-mail: [email protected] © Mark S. Dreux 2013
2 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
OVERVIEW
♦ CONGRESSIONAL HEARINGS CRITICIZING OSHA ♦ OSHA’S RESPONSE TO CRITICISM – TWO NEP’S ♦ WEST FERTILIZER ♦ REFINING NEP ENFORCEMENT STATISTICS ♦ CHEMICAL NEP
♦ Overview ♦ Chemical NEP Enforcement Statistics
♦ LESSONS LEARNED FROM PSM CITATION PATTERNS ♦ INDUSTRY STANDARDS CITED MOST FREQUENTLY ♦ OSHA INTERPRETATION LETTER ON THRESHOLD QUANTITIES ♦ RECOMMENDATIONS
3 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CONGRESSIONAL HEARINGS ON BP DISASTER – MARCH 22, 2007
♦ Chairman Miller ♦ Is OSHA doing its job? ♦ OSHA has failed to protect workers ♦ BP is the story of the failure of OSHA ♦ OSHA’s penalty structure is ineffective
♦ Congressman Holt ♦ “OSHA is the lap dog of the industry”
4 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
KEY WITNESS AT THE CONGRESSIONAL HEARINGS
♦ Carolyn Meritt – Chairperson of CSB ♦ OSHA’s regulatory oversight was
ineffective ♦ Rigorous enforcement of PSM would have
prevented this incident ♦ OSHA has few trained inspectors.
♦ All witnesses agreed Chemical Industry and Refining Industry have similar safety issues.
5 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
OSHA’S RESPONSE TO THE CRITICISM
♦ Two National Emphasis Programs ♦ Released in June 2007 – Refining NEP ♦ Released in July 2009 – Pilot Chemical NEP ♦ Released in November 2011 – Chemical NEP
♦ Interpretation letters pulled from OSHA’s website ♦ New interpretation letters and aggressive
enforcement to expand PSM coverage ♦ More PSM trained compliance officers
6 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CRITICISM SURROUNDING THE WEST FERTILIZER
♦ Numerous New Articles ♦ OSHA does not have the resources. ♦ OSHA and state plans have 2,000 inspectors for
8 million workplaces or once every 131 years. ♦ OSHA’s penalties are too low.
♦ Congressional hearings ♦ Potential legislation ♦ Increased enforcement by OSHA
7 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
♦ Based on the 65 NEP citations:
♦ Total Citations 1,542
♦ PSM 1088 (70%) ♦ Non-PSM 454 (30%)
♦ Total Fines $9,401,472.00
8 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP CHARACTERIZATION OF THE CITATIONS
Serious 1335 87%
OTS 77 5%
Willful/Unclassified
92 8%
Repeat
38
Total 1,542 100%
9 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
♦ Most Citations 93 (88 PSM)
♦ Fewest Citations 1 (0 PSM)
♦ Highest Penalty $3,042,000
♦ Lowest Penalty $1,125
♦ Average 24 citations $144,638 penalty
10 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Mechanical Integrity 202 Process Safety Information 189 Process Hazard Analysis 188 Operating Procedures 184 Management of Change 92 Incident Investigation 71 Compliance Audits 47 Contractors 33 Training 29
REFINING NEP PSM ENFORCEMENT STATISTICS (65 NEP Citations Issued as of 3/14/11)
855 79%
11 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Emergency Planning and Response 17 Employee Participation 15 Pre-Startup Safety Review 13 Hot Work Permits 8 Trade Secrets 0 Total PSM Citations
1088
REFINING NEP PSM ENFORCEMENT STATISTICS
(65 NEP Citations Issued as of 3/14/11) (cont’d)
12 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS MECHANICAL INTEGRITY
J(1) Process equipment 0
J(2) Written procedures 37 J(3) Training 3
J(4) Inspection and testing 0
J(4)(i) Inspection and testing 29
J(4)(ii) Engineering practices 22
J(4)(iii) Frequency 23
J(4)(iv) Documentation 14
J(5) Equipment deficiencies 61
J(6)(i) Quality assurance 0
J(6)(ii) Inspections 9
J(6)(iii) Materials and spare parts 4
TOTAL 202
88
13 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ J-2 Mechanical Integrity Program ♦ No Procedures for:
♦ Pressure vessels with integrally bonded liners ♦ Corrosion under insulation inspections for pressure
vessels and piping ♦ Addressing anomalous readings pertaining to metal
thickness ♦ Determining thickness measurement frequency for
pressure vessels ♦ Determining the representative number of thickness
measurements
REFINING NEP ENFORCEMENT STATISTICS
14 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ J-4 Testing and Inspections ♦ Failure to follow own scheduled T/I
♦ Visual inspections ♦ Ultra sound ♦ Internal corrosion ♦ TML’s ♦ Vibration analysis
♦ Failure to follow RAGAGEP ♦ Testing of wrong locations ♦ Testing of wrong frequency ♦ Insufficient number of tests
♦ Failure to document the T/I results
REFINING NEP ENFORCEMENT STATISTICS
15 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ 119(J)(5) Equipment Deficiencies ♦ TML’s below recommended thickness ♦ H2S, HF & LEL detectors not working ♦ Temperature gauge broken ♦ Chains for operating valves missing ♦ Relieve valve set at 270 PSI when
MAWP was 150 PSI
REFINING NEP ENFORCEMENT STATISTICS
16 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
PROCESS SAFETY INFORMATION (PSI)
D Schedule/Prioritization 2 D(1) Information re: Hazards 0 D(2) Technological Information 17 D(3) Equipment Information 170
Total
189
17 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS PROCESS SAFETY INFORMATION (PSI)
D(3)(i) Information on Equipment 5 D(3)(i)(A) Materials of Construction 5 D(3)(i)(B) P&ID’s 38 D(3)(i)(C) Electrical Classification 7 D(3)(i)(D) Relief System Design and Design Basis 27 D(3)(i)(E) Ventilation System Design 2 D(3)(i)(F) Design Codes and Standards 9 D(3)(i)(H) Safety Systems 1 D(3)(ii) Document Equipment complies with
RAGAGEP 72
D(3)(iii) Equipment Designed on a Code no Longer in General Use
4
Total 170
18 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ P&ID’s ♦ Inaccurate info on P&ID’s
♦ Vessel or pump out of service ♦ Wrong pressure or temperature ♦ Lines mislabeled
♦ Omissions from P&ID’s ♦ Temperature indicator ♦ Sight glass ♦ By-pass line ♦ New equipment ♦ New lines
REFINING NEP ENFORCEMENT STATISTICS
19 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
♦ 119(d)(3)(i)(D) – Relief System Design and Design Basis ♦ Blowdowns/Atmospheric Discharge
♦ Lack of technical data to show safe release to atmosphere
♦ Relief Systems – ♦ Adequacy following changes especially
changes in thru-put ♦ Design basis – lack of technical support
20 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
♦ 119(d)(3)(ii) – Equipment with RAGAGEP ♦ Facility Siting – NFPA 496 and API 752 ♦ Electrical classifications—API 500 ♦ Trailers – API 753 ♦ Relief Valves and Design – ASME & API 520
♦ Adequacy and sizing of valves ♦ No PSV’s ♦ Intervening valves
21 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS PROCESS HAZARD ANALYSIS
E(1) Appropriate PHA/Prioritization 12 E(2) Methodologies 0 E(3) PHA addresses 0 E(3)(i) Hazards 15 E(3)(ii) Incidents 10 E(3)(iii) E and A Controls 15 E(3)(iv) Failure of Controls 11 E(3)(v) Facility siting 31 E(3)(vi) Human factors 23 E(3)(vii) Qualitative evaluation 2 E(4) Team of Experts 0 E(5) Findings/recommendations 53 E(6) Revalidation 15 E(7) Revalidation records 1
TOTAL 188
107
22 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ 119(e) PHA’s ♦ PHA
♦ Failure to consider all scenarios ♦ Loss of utilities or control rooms ♦ Fires and releases of HHC’s
♦ Failure to consider near misses ♦ Propane leaks ♦ Oil Spills ♦ Fires
♦ Failure to adequately consider ♦ Facility Siting ♦ Human factors
REFINING NEP ENFORCEMENT STATISTICS
23 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ Failure to address findings – ♦ Ranged 2-15 years ♦ Complexity – gravity – time (citation factors)
♦ Failure to document corrective measures
REFINING NEP ENFORCEMENT STATISTICS
24 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
OPERATING PROCEDURES
F(1) Written procedures 18 F(1)(i) Operating phases 65 F(1)(ii) Operating limits 26 F(1)(iii) Safety and health 12 F(1)(iv) Safety systems 9 F(2) Access 3 F(3) Certification 23 F(4) Safe work practices 28
TOTAL 184
130
25 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ SOP’s ♦ Lack operating limits or consequences
of deviation ♦ Missing essential step in procedure ♦ Referring to outdated equipment, step
or specific manager ♦ Error with locks or carseals on valves
for startup
REFINING NEP ENFORCEMENT STATISTICS
26 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ Safe Work Practices ♦ Procedures/practices for controlling
motorized vehicles in process areas ♦ OSHA relies electrical classification
drawings to show a “hazard”
REFINING NEP ENFORCEMENT STATISTICS
27 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS MANAGEMENT OF CHANGE
L(1) Written procedures 40 L(2) Considerations 2 L(2)(i) Technical basis 3 L(2)(ii) Impact of change 9 L(2)(iii) Operating procedures 1 L(2)(iv) Time Period 3 L(2)(v) Authorization requirements 2 L(3) Employee training 4 L(4) Update PSI 22 L(5) Revise operating procedures 6
TOTAL 92
60
32
28 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
REFINING NEP ENFORCEMENT STATISTICS
♦ MOC’s ♦ Failure to do MOC’s (adequacy)
♦ Throughput increases ♦ Changing startup pressures ♦ Rerating boilers ♦ Removing column, quench water
♦ Failure to do related updates ♦ PSI ♦ Procedures ♦ Training
29 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Summary of OSHA’s Chemical NEP
♦ Pilot Program has ended.
♦ National Program started in November 2011.
♦ Applies to chemical plants subject to PSM.
♦ Applies nationwide to all OSHA regions and state plans.
♦ State plans must implement the chemical NEP within 6 months or develop one that is “at least as effective.”
30 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Chemical NEP Programmed and Unprogrammed Inspections
♦ Programmed inspections under this NEP shall be randomly selected sites from the Region’s revised lists
♦ 3-5 programmed inspections per Area Office per year (52 Area Offices)
♦ Unprogrammed inspections: other triggers for a Chemical NEP inspection: ♦ Accident ♦ Catastrophe ♦ Complaint ♦ Referral ♦ Site-specific targeting plan
31 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Chemical NEP Dynamic Lists ♦ “CSHO’s should verify the implementation of PSM
elements to ensure that the employer’s actual program is consistent with their written program.”
♦ Three OSHA inspection protocols called “Dynamic Lists”:
♦ PSM General
♦ Ammonia Refrigeration
♦ Chemical Processing
♦ These lists will be periodically updated and are not available for public review
32 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Chemical NEP Prior PSM Citations: Abatement Requirement
♦ “During the course of the inspection, the CSHO shall review abatement for all PSM citations issued within the previous 6 years to determine whether the hazard still exists.”
♦ “If a hazard exists, the CSHO shall determine whether there has been a failure to abate in accordance with CPL 02-00-148-FOM, and issue a notice for failure to abate as appropriate.”
♦ FTA penalties can be up to $7,000 per day per violation.
33 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Chemical NEP Staffing and Duration of Inspection
♦ Usually 1-2 compliance officers
♦ Inspectors must take specialized PSM training classes
♦ 134 man hours for Chemical NEP inspection (includes preparation, opening, site work and drafting citations and reports)
♦ 25 man hours for average OSHA inspection
♦ 1000 man hours for Refining NEP inspection
34 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ CHEM NEP data from May 1, 2009 to Nov. 9, 2012 Total Inspections..........................................536 Unprogrammed.................................. 215 Programmed......................................321
♦ CHEM NEP Violations (Federal only).....2,339
Current Inspection Data for Chemical NEP
35 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ New citation data system still being implemented
♦ Current Statistical Breakdown for Top Five PSM Violations for Chem NEP.
OSHA – New Citation Data Tabulation System
1. (j) – Mechanical Integrity 2. (d) – Process Safety Information 3. (f) – Operating Procedures 4. (e) – Process Hazard Analysis 5. (l) – Management of Change
♦ Same top five PSM citations as in Refining NEP.
36 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS (Based on Sample of 98 Citations)
♦ Based on the 98 NEP citations sampled:
♦ Total Citations 1031
♦ PSM 678 (65%) ♦ Non-PSM 353 (35%)
♦ Total Fines $4,147,267.50
37 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP CHARACTERIZATION OF THE CITATIONS
Serious 856 83%
OTS 153 15%
Willful/Unclassified
7 2%
Repeat
15
Total 1031 100%
38 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS
♦ Most Citations 49 (25 PSM)
♦ Fewest Citations 1 ( 0 PSM)
♦ Highest Penalty $441,000
♦ Lowest Penalty $ 0
♦ Average 11 citations $42,300 penalty
♦ Approximately 20 Facilities with No Citations (No PSM Process)
39 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Mechanical Integrity 156 Process Safety Information 140 Operating Procedures 114 Process Hazard Analysis 106 Management of Change 44 Compliance Audits 35 Training 21 Incident Investigation 19 Employee Participation 16
CHEMICAL NEP PSM ENFORCEMENT STATISTICS (98 NEP Citations Sampled)
560 84%
40 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
Contractors 14 Emergency Planning and Response 7 Pre-Startup Safety Review 5 Hot Work Permits 1 Trade Secrets 0 Total PSM Citations
678
CHEMICAL NEP PSM ENFORCEMENT STATISTICS (98 NEP Citations Sampled)
41 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS MECHANICAL INTEGRITY
J(1) Process equipment 0
J(2) Written procedures 41 J(3) Training 5
J(4) Inspection and testing 0
J(4)(i) Inspection and testing 28
J(4)(ii) Engineering practices 11
J(4)(iii) Frequency 21
J(4)(iv) Documentation 10
J(5) Equipment deficiencies 28
J(6)(i) Quality assurance 2
J(6)(ii) Inspections 6
J(6)(iii) Materials and spare parts 4
TOTAL 156
70
42 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ J-2 Mechanical Integrity Program ♦ Summary
♦ No procedures for mechanical integrity ♦ Procedures Inadequate
♦ Inconsistent with RAGAGEP ♦ Critical Step Wrong ♦ Critical Omissions
♦ Written procedures contained no reference to applicable RAGAGEP
♦ No procedures in place for piping or valves showing signs of degradation or rust
♦ The employer’s critical equipment list did not include certain storage tanks and air compressors
♦ Procedures did not specify the necessary torque for flange bolts
CHEMICAL NEP ENFORCEMENT STATISTICS
43 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ J-4 Testing and Inspections ♦ Summary
♦ No Inspection Schedule ♦ Did Not Follow Own Inspection Schedule ♦ Schedule Inconsistent with RAGAGEP
♦ Examples ♦ Inspections were not done on storage tanks for anhydrous
ammonia, liquid chlorine, and sulfur dioxide ♦ Inspections were not done on pre-existing TML locations ♦ Employer did not conduct inspections per IIAR Bulletin 110 or its
equivalent ♦ Pressure relief valves had not been inspected every 5 years to
comply with ASHRAE-15 ♦ Inspection and NDE were not done on process equipment per
RAGAGEP such as API 570, API RP 575, and ASME/ANSI B31.3
CHEMICAL NEP ENFORCEMENT STATISTICS
44 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ 119(J)(5) Equipment Deficiencies ♦ Visual concerns – detected during walkaround
♦ Poor condition of paint/external coating was not addressed
♦ Rusted, pitted, and corroded piping were in use
♦ Valves were missing handles and could not be operated
♦ Calculated data ♦ TML’s below recommended thickness
♦ Emergency exhaust and relief discharge piping were undersized
CHEMICAL NEP ENFORCEMENT STATISTICS
45 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS
PROCESS SAFETY INFORMATION (PSI)
D Schedule/Prioritization 4 D(1) Information re: Hazards 0 D(2) Technological Information 21 D(3) Equipment Information 115
Total
140
46 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS PROCESS SAFETY INFORMATION (PSI)
D(3)(i) Information on Equipment 7 D(3)(i)(A) Materials of Construction 2 D(3)(i)(B) P&ID’s 26 D(3)(i)(C) Electrical Classification 5 D(3)(i)(D) Relief System Design and Design Basis 11 D(3)(i)(E) Ventilation System Design 6 D(3)(i)(F) Design Codes and Standards 7 D(3)(i)(G) Material and Energy Balance 1 D(3)(i)(H) Safety Systems 3 D(3)(ii) Document Equipment complies with
RAGAGEP 43
D(3)(iii) Equipment Designed on a Code no Longer in General Use
4
Total 115
47 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ P&ID’s ♦ Current P&IDs were not available ♦ Errors
♦ Two valve tags were reversed ♦ Pressure indicators were missing in the field ♦ Pipe sizes were labeled improperly ♦ Valves were in the wrong place
♦ Omissions ♦ P&ID did not include information required by RAGAGEP,
ANSI/ISA S5.1 Code ♦ Valves or equipment missing
CHEMICAL NEP ENFORCEMENT STATISTICS
48 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS
♦ 119(d)(3)(i)(D) – Relief System Design and Design Basis ♦ No worst case scenario had been developed
♦ No information for the relief system was available
♦ No documentation for design basis for the relief system for tanks and vessels
49 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS ♦ 119(d)(3)(ii) – Equipment with RAGAGEP
♦ No documentation of compliance with the HFIPI Guideline for the Bulk Storage of Anhydrous Hydrogen Fluoride
♦ No documentation of compliance with IIAR Bulletin 110 where relief valves could relieve to an unsafe location
♦ No documentation that relief valves complied with IIAR Bulletin 114
♦ No documentation of compliance with RAGAGEP where a vessel’s U-1 had not been maintained
♦ Failure to document compliance with API 520 for relief systems ♦ Technical Engineering Issues and Non-Compliance
♦ Co-location of equipment using combustion air and equipment containing refrigerant did not comply with ANSI/ASHRAE 15
♦ Location of discharge for pressure relief devices did not comply with ANSI/IIAR 2-2008
♦ Relief systems not located properly ♦ Pipes and valves not labeled properly
50 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS PROCESS HAZARD ANALYSIS
E(1) Appropriate PHA/Prioritization 10 E(2) Methodologies 1 E(3) PHA addresses 1 E(3)(i) Hazards 17 E(3)(ii) Incidents 4 E(3)(iii) E and A Controls 9 E(3)(iv) Failure of Controls 6 E(3)(v) Facility siting 11 E(3)(vi) Human factors 9 E(3)(vii) Qualitative evaluation 0 E(4) Team of Experts 1 E(5) Findings/recommendations 26 E(6) Revalidation 10 E(7) Revalidation records 1
TOTAL 106
57
51 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ 119(e) PHA’s ♦ Failure to conduct an initial PHA on a covered process ♦ Failure to consider all scenarios
♦ Loss of power ♦ Hazards associated with combustible dust ♦ Outdoor environmental factors affecting the safe operation of
process equipment ♦ Failure of pressure relief devices ♦ Specific incident that occurred at the plant (either before the
PHA was done or after) ♦ Failure to adequately consider
♦ Facility Siting ♦ Human Factors
CHEMICAL NEP ENFORCEMENT STATISTICS
52 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ 119(e) PHA’s (cont’d) ♦ Failure to address findings
♦ Employer could not verify that recommendations from a 1998 PHA were resolved
♦ Failure to establish a “system” to address recommendations ♦ Failure to document the reasons an alternative resolution was
adopted rather than that recommended by the PHA team ♦ Failure to communicate resolutions of PHA recommendations
to affected employees ♦ Complexity – gravity – time (citation factors)
♦ Failure to re-do or revalidate a PHA within 5 years
CHEMICAL NEP ENFORCEMENT STATISTICS
53 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS
OPERATING PROCEDURES
F(1) Written procedures 21 F(1)(i) Operating phases 38 F(1)(ii) Operating limits 10 F(1)(iii) Safety and health 14 F(1)(iv) Safety systems 6 F(2) Access 2 F(3) Certification 17 F(4) Safe work practices 6
TOTAL 114
89
54 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ SOP’s ♦ Operating procedures were not being implemented
by employees ♦ Factual errors
♦ Listing out of service equipment ♦ Omitting steps
♦ Regulatory errors ♦ Steps were unclear ♦ Procedures did not address which employees were
authorized to perform the various steps ♦ Procedures had not been developed for each phase of
operating the process
CHEMICAL NEP ENFORCEMENT STATISTICS
55 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ Annual Certification of Operating Procedures ♦ Certification was not done ♦ Certification was not valid because procedures
were not accurate
CHEMICAL NEP ENFORCEMENT STATISTICS
56 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP ENFORCEMENT STATISTICS
♦ Management of Change (44 Citations) ♦ Failure to do MOC
♦ Throughput changes ♦ Change in PPE for employees opening a vessel ♦ Change in TML location ♦ MOC was not completed before the equipment change
occurred ♦ Failure to evaluate
♦ Impact of the change on safety and health ♦ Failure to do related updates
♦ PSI ♦ Procedures ♦ Training
57 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
LESSONS LEARNED FROM PSM CITATION PATTERNS
♦ OSHA’s aggressive interpretations of PSM standard
♦ OSHA’s selective interpretations of RAGAGEP
♦ OSHA demands documentation for PHA, audit and incident investigation findings.
♦ Citation patterns show OSHA’s PSM priorities
58 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
OSHA’S AGGRESSIVE INTERPRETATIONS
♦ Piping and Instrumentation drawings ♦ Applying steam constitutes a change ♦ Covering mixtures of less than 10,000 lbs
of flammables under the PSM standard. ♦ Facility siting: Determining that 1 in 100
million years risk basis for a willful citation.
♦ Required to keep PHA documentation from 1994 and 1998.
59 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
OSHA’s Use of RAGAGEP
♦ API 752 ♦ Management of Hazards Associated with Location of
Process Plant Permanent Buildings ♦ API 570
♦ Piping Inspection Code: In-Service Inspection, Rating, Repair, and Alteration of Piping
♦ API 510 ♦ Pressure Vessel Inspection Code: In-Service Inspection,
Rating, Repair, and Alteration ♦ API 521
♦ Pressure-Relieving and Depressuring Systems
Most Frequently Referenced RAGAGEPs
60 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
OSHA’s Use of RAGAGEP
♦ API 574 ♦ Inspection Practices for Piping System Components
♦ API 520 ♦ Sizing, Selection, and Installation of Pressure-relieving
Devices in Refineries ♦ API 753
♦ Management of Hazards Associated with Location of Process Plant Portable Buildings
♦ ANSI/ISA S.84.01 ♦ Functional Safety: Safety Instrumented Systems for the
Process Industry Sector ♦ ASME/ANSI B31.1 and B31.3 (piping)
61 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
Electrical Safety
Respirators
Lockout/Tagout
Subpart D - Walking/Working Surfaces
Machine Guarding
62 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
♦ Electrical ♦ Working space around equipment was not kept clear ♦ Covers for electrical installations were not secured/all
unused openings were not effectively closed ♦ Improper grounding ♦ Flexible cords and cables were used as a substitute for fixed
wiring ♦ Unclassified electrical equipment was used in a classified
area ♦ Defective electrical equipment was not removed from service ♦ Proper electrical protective equipment was not provided
where necessary (FR clothing, face shields, NFPA 70E considerations for arc flash)
63 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
♦ Respirators ♦ Employer failed to determine a reasonable estimate of
employee exposure to respiratory hazards ♦ Written respiratory protection program was not in place
when respirators were necessary ♦ Medical evaluations were not provided before employees
were fit-tested or required to use respirators ♦ Fit-testing was not provided prior to initial use of the
respirator ♦ Employees did not receive training before being allowed
to use tight-fitting respirators ♦ Respirators were not cleaned and disinfected as often as
necessary to be maintained in a sanitary condition
64 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
♦ Lockout/Tagout ♦ Failure to develop, document, and utilize written lockout
procedures for specifically identified equipment ♦ Lockout/tagout devices did not meet the requirements of
1910.147(c)(5) – identify employee, tagouts must be non-reusable, etc.
♦ Periodic inspections of the lockout/tagout procedures were not completed
♦ Lockout/tagout training was deficient where each employee had his own way of locking out
♦ Lockout/tagout procedures were not implemented as required – employees failed to follow the procedures
♦ In group lockout scenarios, each employee failed to affix his own lockout device
65 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
♦ Subpart D – Walking/Working Surfaces ♦ Ladderways and platforms were not adequately guarded ♦ Wall openings over 4 feet from the level below were not
adequately guarded ♦ Open-sided floors and platforms over 4 feet from the level
below were not adequately guarded
66 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
CHEMICAL NEP MOST FREQUENTLY CITED NON-PSM CITATIONS
♦ Machine Guarding ♦ Inadequate guarding for:
♦ Drill presses ♦ Augers ♦ Conveyors ♦ Lathes ♦ Milling machines
♦ Fans ♦ Saws ♦ Grinders ♦ Shafts and shaft ends ♦ Chains and belts
67 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
♦ Question: Is the total mass of a mixture consisting of a fine, non-soluble, non-combustible solid combined with a flammable liquid considered when determining if a threshold quantity (TQ) is present in a process?
♦ Rationale: If the mixture as a whole meets the 29 CFR 1910.1200(c)(iii) definition of a flammable liquid, then the total amount of flammable liquid is 10,000 pounds, even if some components(s) of the mixture alone would not meet the required flash point.
♦ Answer: Because the mixture in question meets the definition of a liquid and has a flashpoint of less than 100°F, it is a flammable liquid. A process containing 10,000 pounds or more of the mixture would be covered under the PSM standard.
Regulatory Update: May 21, 2009 Kaster Letter PSM - Calculating TQ’s
68 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
RECOMMENDATIONS
♦ First Recommendation – Use of the Citation Data ♦ Auditing ♦ Preparing for inspections ♦ Settlements and potential repeat citations ♦ Due diligence
69 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
RECOMMENDATIONS
♦ Second Recommendation ♦ Review prior citations for PSM violations ♦ Go to osha.gov – Check OSHA’s records on
citations for PSM violations ♦ Gather documents to show abated ♦ Audit to ensure not recurring
♦ Third Recommendation ♦ Do the Unit selection analysis for the “most
hazardous process”
70 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
RECOMMENDATIONS (cont’d)
♦ Fourth Recommendation – Conduct an Audit of Selected Unit
71 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
RECOMMENDATIONS (cont’d)
♦ Traditional Safety Focus – include in Unit audit
♦ Consider whether you want to do audit under privilege. See case where we successfully defended a claim of attorney privilege for a gap analysis under Refining NEP.
Electrical LOTO PPE Guarding Respirators Walking/Working
Surfaces
72 Los Angeles / New York / San Francisco / Washington, DC / arentfox.com
RECOMMENDATIONS (cont’d)
♦ Fifth recommendation: ♦ Train a team to manage the inspection
♦ Sixth recommendation: ♦ Interview disgruntled employees