Tim.honeycutt
-
Upload
nasapmc -
Category
Technology
-
view
13.775 -
download
0
Transcript of Tim.honeycutt
![Page 1: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/1.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
Integrated Testing at KSC Integrated Testing at KSC between Constellation between Constellation
SystemsSystems
Tim HoneycuttTim Honeycutt
February 2008February 2008
[email protected]@nasa.gov
321321--867867--65676567
![Page 2: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/2.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
2
KSC Constellation Project OfficeKSC Constellation Project Office
KSC Constellation Project Office
Logistics
Command, Control, and
CommunicationsLaunch Vehicle
Crew Vehicle Ground Systems (GS)
Project
Project Control
Systems Engineering & Integration
(including IT&V)
Operations & Integration
Business Staff Office
GS Project Support Office
GS Project Integration & Requirements
GS Project Management
![Page 3: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/3.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
3
Presentation OutlinePresentation Outline
• History of Multi-Element Integration Tests (MEITs)– MEIT Concept– Previous MEITs– Major Problems Found– Benefits
• Integrated Testing at KSC for the Constellation Program– Integrated Tests
• Multi-Element Integrated Tests (MEITs)• Flight Element Integrated Tests (FEITs)• Integrated Verification Tests (IVTs)
• Summary
![Page 4: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/4.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
4
HistoryHistory
• “Ship and shoot” was the strategy for the International Space Station Program (ISSP) during the early 1990’s
– It proposed transporting flight elements directly from the factory to the launch site and begin the mission without further testing.
– Factory level testing and element interface verifications at thesubsystem-level, and interface analysis were all that was planned.
• Before the end of that decade a shift in testing strategy occurred within the ISSP
– The ISSP adopted a more integrated approach for ground validation of it’s flight hardware.
– Availability of elements at the launch site created a feasible opportunity to test multiple elements together.
– The notion of validation testing on the ground was presented andaccepted by the ISSP due to the criticality of the on-orbit functionality, including safety concerns for the crew .
![Page 5: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/5.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
5
History (cont)History (cont)
• Multi Element Integration Tests (MEITs) and Integrated Systems Tests (ISTs)
– Risk mitigation tests performed on the ground, used for validating the operation of the flight elements and their systems in an environment that is as flight-like as possible.
– These tests were used to demonstrate the interoperability and functionality of Space Station elements as integrated “in-space”assemblies on the ground before they were assembled in space for the first time.
• Space Station element-to-element interface capability was verified as well as systems end-to-end operability with hardware and software.
• Mission Sequence Testing (MST), also known as “end-to-end”integration testing, included a full-up configuration with the Mission Control Center, Tracking Data Relay Satellite System (TDRSS), and the “station” operating on the ground.
• Also verified limited on-orbit system compatibility.
![Page 6: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/6.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
6
KSC ISS MEIT/IST ExperienceKSC ISS MEIT/IST Experience
• Planned/developed and implemented the following for ISSP:
– MEIT1: • U.S. Lab, Z1, P6, SSRMS, Node1 (emulated)
– MEIT2: • S0/MT/MBS, S1, P1, P3/4, US Lab (emulated)
– MEIT3: • JEM, Node2, US Lab (emulated)
– Node2 Systems Test• Node2, US LAB & Node1 (emulated)
![Page 7: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/7.jpg)
MEIT ConfigurationsExternalPayload
24
2
UniversalDockingModule
3
Z
N
A
PS
F3
3 3
3
MBS18 18
18 18
31
31
32
3 DC-2
29
8
JEM PM18
9
9
8
DSM
3
3
ExternalPayload
24JEM ELM ES
29
JEM EF29
29
RM-1 3
RM-23
ProgressM1
3
CAM8 9
S6
17
16
16
17
14
11 S5 81111
1 1PMPMA2 48
1AFT FWD
PORT
STBD
NADIR ZENITH
NODE 1simulated
1
8
9
99
9
9
9
8
8
8
8
23
MT
31
30 30
32
21
S022 22
24
S3S4 28 22
17
16
16
17
11
1424
2424
P5811 11
25 25
P3 P42822
17
16
16
17
11
14
26
CETA 30
15 15
2222
13
15
S1
1226
CETA 30
8
CUPOLA27
27
2727
27
27
27
P6
17
16
16
17
14
11
3
SoyuzTM
PMA348
1 AFT
FWD PORT
STBD
NADIR ZENITHNODE 3
8
88
8 89
9
8
9
9 9
9
1
8
CRVadapt
CRV#11
SLP (or ULC)
25
ExternalPayload
24
ExternalPayload
24
3
SoyuzTM
89MPLM
COF
8
9
SSRMSSPDM 18
ServiceModule
5,7
5,7
43 2
2
2
4
FA
N
Z
4
4
12
18
FGB
5,7
5,7
42 1
3
4
FA
N
12
7 places
EFGF
Strela
8
9
AIRLOCK
19
20 20NTA
20 20OTA
20 20OTA
20 20NTA
9 9U.S. LAB
ZENITH
NADIR
18
8 8
27
21
JEMELM PS
8 95,7 5,7
5,7 5,7
5,75,7
5,75,7
26
SPPERAERA
18
AFT FWD
PORT
STBD
NADIR ZENITH
NODE 2
8
9
99
9
9
9
8
8
8
8
8
Z8 Z1N
A
F
11
10
P
S
12CMGs (4)
Ku-Band
27
8U.S.HAB
9 98
S0-to-Lab Struts
Primary Orbiter Docking Interface
Alternate Orbiter Docking
Interface
Alternate MPLM Berthing Location
1515
22 22
13
15
P1
12S-Band
ULC (or SLP)
25
PMA1PMA3 simulation
MEIT-2 UsesUS Lab Simulation
16 Beta Gimbal Assembly17 Solar Array Deployment18 Power/Data Grapple Fixture (PDGF)19 Orbiter ‘D’ Hatch20 NTA/OTA Attachment Mechanism21 Lab Cradle Assy / MTSAS22 Segment to Segment Attach System (SSAS)23 Mobile Transporter Drive24 Payload Attach System (PAS)25 ULC Attach System (ULCAS)26 CETA Rollers27 Window Shutter28 Solar Alpha Rotary Joint (SARJ)29 JEM Berthing Mechanism30 CETA Coupler31 Common Attach System (CAS)32 Trailing Umbilical System (TUS) (2)
11 Rocketdyne Truss Attachment (RTAS)12 Deployable Antenna13 Thermal Radiator Rotary Joint (TRRJ)14 EPS Radiator Deployment15 TCS Radiator Deployment
1 Modified APAS2 Hybrid Docking Assembly (HDA)3 Probe and Cone (P&C)4 APAS Hatch5 RSA Solar Array Deploy Mechanism6 RSA Radiator Deploy Mechanism7 RSA Array Pointing Mechanism8 Common Berthing Mechanism (CBM)9 US Common Hatch10 Manual Berthing Mechanism (MBM)
MEIT 1 Completed 2/00
MEIT 2 Completed 4/02
MEIT 3 Completed 9/03
LEGENDRemotely actuated mechanisms
EVA operated mechanismsIVA operated mechanisms
Articulating/Deployable mechanisms
Translation mechanismspassive active
![Page 8: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/8.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
8
MEIT 2 Hardware at KSCMEIT 2 Hardware at KSC
S1Truss
P3 TrussP1Truss
S0 Truss
P4 Truss
US Lab Emulator
![Page 9: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/9.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
9
Problems Found in MEITs (Top Examples)Problems Found in MEITs (Top Examples)
• P6 truss failed to power up due to Auxiliary Power Converter Unit (APCU) under voltage trip condition.
– Impact: Unable to start P6 on Orbit.
• US Lab critical activation took 36 hours during the first MEIT Power-up (computer/procedure problems), Requirement <2 hrs. During MEIT regression Mission Sequence Test, Critical Activation took 1 hr, 15 minutes.
– Impact: Loss of Lab element during on-orbit activation due to thermal loading.
• Command and Control (C&C) computers failed several times due to task overrun problems (CPU utilization problems).
– Impact: Significant operational issues (Loss of Vehicle commanding, Vehicle health visibility, visibility to crew/ground) would occur because of continued loss of C&C computers.
![Page 10: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/10.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
10
Problems Found in MEITs (Top Examples)Problems Found in MEITs (Top Examples)(continued)(continued)
• Video lines were swapped between Trailing Umbilical Systems 1, 2 (NASA) and Mobile Base System (Canadian Space Agency).
– Impact: Significant operational impact to manually route video signals. Extra Vehicular Activity (EVA) would have been required to replace two harnesses to correct the problem.
• C&C computers failed when performing synchronization to Global Positioning System (GPS) time.
– Impact: Loss of accurate GPS capability, degraded attitude control capability until development /testing and on-orbit upload of new software patch.
• Quality of Space to Ground Audio was unacceptable.
– Impact: Operation and potential safety impact to crew due to lack of understanding between Crew/Ground.
![Page 11: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/11.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
11
MEIT BenefitsMEIT Benefits
• Significant findings from MEIT have created an opportunity to correct major operational problems which would have resulted in:
– Cost/Schedule Slip• Major milestone slippage in the Program
– Critical On-orbit Operations impacts• Safety concerns for the crew• Loss of mission objectives• Loss of flight hardware
– Nominal Operations impacts• Unknown operation risks (loss of redundancy capability)
– Unplanned EVA’s
The cumulative effect of identifying & resolving integrated hardware, software and procedure problems before flight has proven to save the International Space Station Program major on-orbit issues.
![Page 12: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/12.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
12
• Testing that occurs between two or more individual ConstellationSystems to verify the interfaces between those Systems and to validate the integrated Systems' functionality and interoperability.
• Includes testing mechanical, electrical, data and fluid interfaces.
• Integrated testing applies to the in-space flight and integrated vehicle stack configurations.
– Multi-Element Integration Testing (MEIT) – Flight Element Integration Testing (FEIT) – Interface Verification Testing (IVT)
Integrated Testing at KSC Integrated Testing at KSC for the Constellation Program (CxP) for the Constellation Program (CxP)
![Page 13: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/13.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
13
Constellation ArchitectureConstellation Architecture
ConstellationArchitecture
CEV
LunarLander
Lunar SurfaceSystems
Flight CrewEquip.
EVASystems
CLV
CaLV
Future
MissionSystems
GroundSystems
CEV Elements-Launch Abort System (LAS)-Crew Module (CM)-Service Module (SM)-Spacecraft Adapter (SA)
CLV Elements-1st Stage-Upper Stage-Upper Stage Engine Architecture
System
ElementSubsystem
Future
Level 2
Level 3
Level 4Level 5
CxProgram
Project
Subsystems: examples include data, power, thermal, etc.
Crew Vehicles& Systems
Launch Vehicles& Systems
Ground & MissionSystems
Crew Exploration Vehicle – CEV/OrionLunar Lander – Lander/Altair
Crew Launch Vehicle – CLV/Ares ICargo Launch Vehicle – CaLV/Ares V
![Page 14: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/14.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
14
MultiMulti--Element Integration Test (MEIT)Element Integration Test (MEIT)
MEIT:• An integration test between two or more flight systems that will be launched
on separate launch vehicles and integrated together for the first time in space.– Interfaces between the flight systems, mission systems, and other
appropriate CxP/ISSP and external systems may be also tested as part of each MEIT.
• The primary objectives of MEIT are: – Demonstrate the interoperability, functionality, and stability of the flight
systems, elements, and sub-systems as an integrated “in-space” vehicle assembly on the ground before they are assembled in space for the first time.
– Validate critical mission sequence activities and flight procedures prior to their first-time execution in-flight.
• A secondary objective of MEIT is:– To collect functional and performance data from the integrated flight
systems to support validation of the different interface test tool sets, emulators, and simulators used by the Projects in accepting future serial numbers of those flight systems.
![Page 15: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/15.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
15
MEIT (continued)MEIT (continued)
• MEIT serves as a training ground for:– Flight crews and trainers– Mission Operations Division (MOD)/Mission Control Center (MCC)
personnel– Constellation system engineers
• MEITs are executed after all of the system-level requirements have been satisfied by the involved Project offices and those offices declare their system designs as verified for flight.
• MEITs are one time tests with a potential for a follow-on regression test.– Performed prior to first crewed missions
• Use of flight-like emulators and cables/connectors may be used when integration between the flight systems is not practical.
• Planned MEITs:– CEV to International Space Station (ISS) (using ISS emulation)– CEV to Lunar Lander/Earth Departure Stage (EDS) (using EDS
emulation)
![Page 16: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/16.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
16
MEIT 1MEIT 1
MEIT 1 Test ConfigurationMEIT 1 Test Configuration(performed in the Multi(performed in the Multi--Payload Processing Facility)Payload Processing Facility)
![Page 17: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/17.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
17
MEIT 1: CEV to ISS (Emulator)MEIT 1: CEV to ISS (Emulator)
• CEV-International Space Station (ISS) MEIT– To be performed in the year 2012, prior to first ISS flight.– Tests interoperability/functionality and all functional interfaces: data,
audio, video, RF, power.– End-to-end test with Mission Control performed via TDRSS.– Uses emulation in place of ISS flight hardware.– Mated with flight-like cables and connectors.
LID
SISS Flight EmulatorCEV
![Page 18: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/18.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
18
CEV-ISS Interfaces
– Mechanical• CxP will utilize newly developed Low Impact Docking System
(LIDS)
• LIDS is not compatible with ISS Docking System (APAS: Androgynous Peripheral Attach System)
• CxP will construct two APAS To LIDS Adapter Segments (ATLAS)
• ATLAS will be installed permanently on Peripheral Mating Adapters (PMAs) 2 and 3
• Provides power and data pass through capability
– Power• ISS will provide 120 VDC to CEV via two redundant power feeds
• CEV will convert 120 VDC ISS power to 28 VDC for internal buses
– Fluids/Gases• Only requirements are for Inter Module Ventilation (IMV) air
circulation – essentially same as for Shuttle orbiter
![Page 19: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/19.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
19
CEVCEV--ISS InterfacesISS Interfaces
– Avionics
• Audio, video, and data are distributed internally to CEV over a Gigabit Ethernet network
• CEV bus would connect to CxP provided Common Communications Adapter (CCA) which would provide conversion to legacy ISS networks.
– CCA required for MIL-STD-1553 (ISS) and Gigabit Ethernet (CEV) data conversions
– CCA installed on ISS
– CCA or prototype would be integrated into ISS emulator and tested with CEV in MEIT
• Separate CEV to ISS S-Band RF link would be implemented for rendezvous/proximity ops
![Page 20: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/20.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
20
MEIT 2MEIT 2
MEIT 2 Test Configurations (MEIT 2 Test Configurations (TCsTCs))(performed in the Space Station Processing Facility)(performed in the Space Station Processing Facility)
![Page 21: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/21.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
21
MEIT 2: Test Configuration #1MEIT 2: Test Configuration #1(TC1)(TC1)
LIDSLI
DS
EDS(Emulation)
CEV to Lunar Landerwith EDS Emulation
![Page 22: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/22.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
22
MEIT 2: Test Configuration #2MEIT 2: Test Configuration #2(TC2)(TC2)
LIDSLI
DS
CEV to Lunar Lander
![Page 23: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/23.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
23
Flight Element Integration Test (FEIT)Flight Element Integration Test (FEIT)
FEIT:– An integration test between the new or significantly modified systems
and elements being assembled into an integrated launch vehicle for the first time.
• Interfaces between the flight systems, ground systems, mission systems, and other appropriate CxP and external systems may be also tested as part of each FEIT.
• The primary objectives of the FEIT are:– Demonstrate the interoperability, functionality, and stability of the flight
systems, elements, and sub-systems as an integrated “launch vehicle” assembly prior to the first operational test flight of that particular launch vehicle configuration.
– Validate critical mission sequence activities and flight procedures prior to their first-time execution.
• A secondary objective of the FEIT is:– To collect functional and performance data from the integrated flight
systems to support validation of the different interface test tool sets, emulators, and simulators used by the Projects in accepting future serial numbers of those flight systems.
![Page 24: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/24.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
24
FEIT (continued)FEIT (continued)
• FEITs are executed after all of the system-level requirements have been satisfied by the involved Project offices and those officesdeclare their system designs as verified for flight.
• FEITs are planned and scheduled as part of the assembly and preparation of the integrated launch vehicle.
• FEITs are currently planned for every test flight (except for Ares 1-X).
• Planned FEITs:– CEV/CLV– Lunar Lander/EDS/CaLV
![Page 25: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/25.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
25
FEIT 1FEIT 1
FEIT 1 Test Configuration(performed in the Vehicle Assembly Building)
![Page 26: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/26.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
26
FEIT 1 FEIT 1 –– Ares 1 Launch Vehicle StackAres 1 Launch Vehicle Stack
• Test Configuration:– CEV/CLV Integrated Stack– Ground Systems– Missions Systems– SCaN (Space Communications
and Navigation)
CLV Upper Stage
CLV 1st Stage
CEV
![Page 27: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/27.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
27
FEIT 2FEIT 2
FEIT 2 Test Configurations (TCs)(performed in the Vehicle Assembly Building)
![Page 28: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/28.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
28
FEIT 2 FEIT 2 –– Ares V Launch Vehicle StackAres V Launch Vehicle Stack
• Test Configurations:– Lunar Lander/EDS/CaLV (TC1)
• Integrated Stack– Lunar Lander/EDS (TC2)
• On-orbit Configuration
• Both test configurations include:– Ground Systems– Missions Systems– SCaN (Space Communications
and Navigation)
EDS
TC2
EDS
Launch Vehicle
TC1
![Page 29: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/29.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
29
Interface Verification Testing (IVT)Interface Verification Testing (IVT)
• Interface Verification Testing (IVT) verifies the mechanical and/or electrical interfaces between two or more flight systems after these systems have been mated.
• IVT consists of the minimal set of activities to verify the integrity of all physical and functional interfaces between the systems involved for each specific vehicle stack configuration.
• IVTs are performed as a subset of the FEITs during the flight tests and then performed for every flight after Full Operational Capability (FOC) has been obtained with the flight and ground Systems.
• Performed in the Vehicle Assembly Building.
• MEITs/FEITs would be required if any significant design upgrades or modifications have occurred.
![Page 30: Tim.honeycutt](https://reader033.fdocuments.in/reader033/viewer/2022052901/5566a472d8b42a643c8b4991/html5/thumbnails/30.jpg)
KS
C C
onst
ella
tion
Gro
und
Ope
ratio
ns P
roje
ct O
ffice
30
SummarySummary
• Based on the previous success of MEITs for the International Space Station Program, these type of integrated tests have also been planned for the Constellation Program:– MEIT
• CEV to ISS (emulated)• CEV to Lunar Lander/EDS (emulated)• Future: Lunar Surface Systems and Mars Missions
– FEIT• CEV/CLV• Lunar Lander/EDS/CaLV
– IVT• Performed as a subset of the FEITs during the flight tests and then
performed for every flight after Full Operational Capability (FOC) has been obtained with the flight and ground Systems.
"Standing alone, components may function adequately, and failure modes may be anticipated. Yet when components are integrated into a total system and work in concert, unanticipated interactions can occur that can lead to catastrophic outcomes." (Columbia Accident Investigation Report (CAIB) Report 2003)