Timescales
-
Upload
sequoia-lopez -
Category
Documents
-
view
23 -
download
0
description
Transcript of Timescales
1
Timescales
Construction LCR
MICE Beam Monitoring counters + DAQ
My understanding
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
ISIS Shutdown
ISIS Beam tuning
MICE BEAM
External Work
MICE Detector TOF0 TOF1, Cal, Ceren, SciFi1
Start of MICE installation
Hall available for detector install
MICE work
2
Phases
LCR
Installation
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Tuning
Data
Phases
Hall installation
MICE work
3
Assumptions
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Month is 20 days
Installation is eight hours per day
Numbers are guesses :
I would like feedback on numbers which you feel are correct as well as those you think are wrong (either way).
Some of the things I include are not exactly computer or DAQ, but have an impact on them.
Conflicts are direct which means two jobs cannot be done simultaneously whatever the manpower available.
4
LCR Installation
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Tasks
• Install cabinets and racks
• Install Networking and test transfers
• Purchase DAQ computer and install
• Purchase Local storage and install
• Commission DAQ computer and storage
• Install sub-detector electronics
• Install and commission slow controls
• Transfer simulated data to tape at Atlas
• Analyse simulated data at tier1 and tier2
• Fast analysis of beam tuning data at tier1
Inputs
LCR complete. Including power and A/C.
LCR layout – rack space.
Internal cable runs. Cable runs from hall.
Installation timings. MICE DAQ system V1.0
LCR
Installation
5
LCR Installation
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Conflicts
Cables from sub-detectors require detectors to have been installed
LCR
Installation
Outputs
LCR set up. All power, racks and A/C
DAQ computer and local storage. Network connection to tier1 and 2. Data tapes written at Atlas.
Analysis and fast analysis of simulated data.
Working DAQ.
Beam Counters in position surveyed and read out.
MICE DAQ V2.0
6
Hall Installation
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Hall installation
Tasks
• Install sub-detectors (including cable runs to the LCR).
• Install beam detectors
Conflicts
Work on hall infrastructure
Outputs
Command and control communications with the LCR
Working detectors and beam monitors
Inputs
7
Tuning
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Tuning
Tasks
• Set up counters with beam
• Read out counters
• Tune beam at Initial setting (using fast grid)
other settings as possible
• Integrate detectors into the DAQ
TOF, Cerenkov, Calorimeter, Scintillating fibre tracker
• Detector pedestal (and calibration)
Conflicts
Sub-detectors integration v beam tuning
Detector installation in hall v beam tuning
Outputs
A running experiment
Inputs
LCR set up. All power, racks and A/C
DAQ computer and local storage. Network connection to tier1 and 2. Data tapes written at Atlas
Working DAQ
Beam Counters in position and surveyed
8
Data taking
Jan 07
Feb 07
Mar 07
Apr 07
May 07
Jun 07
Jul 07
Aug 07
Sep 07
Tasks
Take data
Conflicts
?
Outputs
Cooling measurement
Inputs
All detectors read-out.
Real data written to tape at Atlas
Data analysed at tier1 and tier2
Fast turn around analysis exercised
Data
9
LCR timings
Time available
120 days
5 days
• Test transfers
Infrastructure
• Fast ethernet connection to Atlas
• Install cabinets and racks
Started negotiation. Some funds will be needed
Status
• Plans for analysis at tier2s communicated to gridpp
• Archiving of data fits into the other experiment envelope
• Requirements for fast turn around analysis at tier1 communicated to gridpp
5 days
• Write to tape at Atlas 10 days
• Test transfers RAL to tier2
London – South – North – Scot
Fermilab - Sophia
5 days per tier 2
10
LCR timings
Time available
120 days
Server and Disks
Procurement
• Data storage £33,132 Clustervision quotes July ’06
• Server £11,862 Delivery time ~ x weeks
• Server installation, storage installation; system burn-in
• Mice software installation
15 days
+ 20 days
5 days
1 day
• Analyse simulated data at tier2
London – South – North - Scot
Fermilab - Sophia
2.5 days per tier 2
• Fast analysis of simulated tuning data at tier1 (dummy)
5 days
11
LCR timings
Time available
120 days
• Install and read-out sub-detector electronics
• Scintillating Fibre
• TOF
• Calorimeter
• Cerenkov
• Install and commission slow controls
• Install read-out beam counter electronics
? days
? days
? days
? days
? Days
66 + 6*? daysTotal
? DaysBeam counters need to be done 4 weeks before the rest of the detectors
Slow controls will need an earlier end date
12
Hall timings
Questions
Is there any estimate of when things will be come available?
Is there anyway of influencing the order of work and do we need to.
Time available
?
13
Tuning timings
Tasks
• Set up counters with beam
• Read out counters
• Tune beam at Initial setting (using fast grid)
• Integrate detectors into the DAQ
TOF, Cerenkov, Calorimeter, Scintillating fibre tracker
• Detector pedestal (and calibration)
Time available
20 days
5 days
10 days
5 daysContingency
14
Conclusion
My guess is there is time to do what we need.
Problem is likely to be that many detectors arrive towards the end of the period.
My worry is that I have forgotten something
I believe the Hardware/infrastructure for the DAQ is on track (see above)
I do not understand the Software/Controls infrastructure well enough to be confident everything will come together
10Tons
I’m sure I’veForgottenSomething