TIME I$ MONEY:
Key Productivity findings in Alberta Construction
Projects!
Dr. Janaka Y. Ruwanpura, PQS
Director and Assistant Professor of Project Management Specialization
Associate Chair in Design EngineeringUniversity of Calgary
![Page 2: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/2.jpg)
A Unique Research Project
• The Construction Productivity Improvement research project at the University of Calgary is the first in the Canadian construction industry to involve four competitive construction contractors with the support of three construction organizations to investigate common problems and to find solutions for improvement.
![Page 3: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/3.jpg)
Successful projects do not
happen by chance !
![Page 4: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/4.jpg)
Construction Research?
• Researchers and practitioners have added “TONS” of contributions to improve the construction project management
• Many of these problems are still bothering and yet to address.
• One such area is construction productivity
![Page 5: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/5.jpg)
This is what we thought Two Years ago!
• Identifying and analysing the most critical factors influencing construction productivity will lead to the development of more efficient and cost effective methods and strategies to improve the productivity of future construction operations in Alberta.
![Page 6: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/6.jpg)
What is missing?
• Research studies - false appearance of originality.
• Published data is out of date and of no relevance to a particular location or to a particular type of construction
• No monitoring to justify the findings• Many factors have changed over
time.• No follow-up work to find “GOOD”
solutions.
![Page 7: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/7.jpg)
Objectives• To identify the most critical factors in terms of
Human, Management and External Factors that affect productivity and to analyze the results.
• Investigate the Top Factors (Based on survey and Stakeholders requests) to determine their individual and cumulative (combined) impact on construction productivity.
• Develop methods and tools to measure and improve construction productivity
• Develop Models to Predict construction productivity.
• Develop a set of practical guidelines for productivity improvement.
• Conduct an industry seminar on the construction productivity improvement.
• Design training material to improve construction productivity.
![Page 8: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/8.jpg)
Team
Charles Lendzion/Ken Gibson, CRIC
Bill Flaig, Graham
Brian Hubert, Ledcor
Scott Thompson, Ellis Don
Bruce White, PCL
Dave Smith/John InkCCA/CCRB
Construction Productivity Research Project
University of Calgary Research Team
Dr. Janaka RuwanpuraPrincipal Investigator
Dr. George JergeasCo Investigator
Kasun HewageEldon Choy
Yangbo ZhouSushil Da Silva
Graduate Research Assistants
Adam HuangResearch Assistant
Construction Industry Steering Committee
NSERCBert van den Berg
![Page 9: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/9.jpg)
First Phase
• A Survey – A larger sample from all four companies and analyze the results
![Page 10: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/10.jpg)
Results of the Survey
![Page 11: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/11.jpg)
Survey Participants
Job Title Count Average Experience
Superintendent 17 26.24
PM 16 11.88
Estimator 4 11.50
Foreman 3 24.67
Project Coordinator 3 6.33
Construction Manager 3 26.00
Senior PM 2 32.50
Engineer 1 10.00
Manager 1 27.00
Operation Manager 1 21.00
![Page 12: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/12.jpg)
Most Important factors affecting Productivity – Survey Results
Order of Im
portance
![Page 13: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/13.jpg)
Project Managers Opinions
Inadequate Communication is most significant factor for construction productivity
![Page 14: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/14.jpg)
Superintendents Opinions
Worker Experience and Skills is most significant factor for construction productivity
![Page 15: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/15.jpg)
Phase 2 – so far
• Identified Two key areas– Human Issues: Motivation, Performance
and communication– Situations that Impact Performance and
to find ways to avoid the non-productive situations
• Developed Methods and Concepts to Monitor and Measure Productivity
• Developed a Model to Predict Productivity considering the “real” situations
![Page 16: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/16.jpg)
Progress: Monitoring and Interviews
• Contractor A: completed• Contractor B: completed• Contractor C: 95% completed• Contractor D: 40% completed.
![Page 17: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/17.jpg)
Issues Investigated
• Worker Motivation and related issues (Kasun Hewage, Ph.D. student)– Motivation– Output– Worker skills, team sprit– Communication– Measured the working time,
non-working time, and output of the workers interviewed
![Page 18: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/18.jpg)
Issues Investigated
• Interviewed Construction Management Professionals (Yangbo Zhou, M.Sc.) to identify issues related to:– Motivation– Performance– Job Satisfaction
![Page 19: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/19.jpg)
Issues Investigated
• Situations that impact Productivity and Working Time (Eldon Choy, M.Sc. and Sushil Peres Da Silva, M.Sc. student)
– Identified the situations
– Measured the working time, non-working time, and output
– Identified the links between situations
– Developed a model to predict the individual/cumulative impact of situations on productivity (Eldon)
– Working on recommendations (Sushil)
![Page 20: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/20.jpg)
Worker Motivation and Communication
![Page 21: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/21.jpg)
![Page 22: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/22.jpg)
Sample Results (1 to 7 scale)
StronglyDisagreed
1 2 3 4 5 6
Neutral
7
StronglyAgree
![Page 23: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/23.jpg)
Top 5 motives for one company
• The respect you receive from the people you work with
• The chances you have to learn new things
• The tools and equipments you have to do your work
• The supervisor’s understanding of the quality and technical details of work you do
• The opportunities to develop your skills and abilities
![Page 24: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/24.jpg)
Top 5 motives for another company
• The chances you have to learn new things
• The opportunities to develop your skills and abilities
• The job security
• The respect you receive from the people you work with
• The amount of freedom you have in your work
![Page 25: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/25.jpg)
Graphical View
![Page 26: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/26.jpg)
Working Time of the Interviewed Workers – A Sample from a Company
![Page 27: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/27.jpg)
Working Time (Direct Tool Time) – A sample
![Page 28: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/28.jpg)
Sample Comments
• About 80% percent of the interviewed workers in all construction sites mentioned lack of communication as a factor that affected their motivation to work.
• Lack of communication refers to inter-group communication and external communication with other groups and the managers.
![Page 29: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/29.jpg)
Sample Comments• Workers were not aware of company
goals and targets: they were told only about daily work targets when, in fact, they would have liked to know the overall scope of the site activities and project.
• The interviewer spent a great deal of time listening to the workers’ concerns about communication.
• When the question “What could be improved in your team?” was asked, most of the time, the workers said “lack of communication.”
• Workers blamed management, believing they themselves were not responsible for the lack of productivity that was caused mainly by poor communication.
![Page 30: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/30.jpg)
Various Situations that Impact Tool Time
• Identify the triggering situations for productivity loss
• Understand the behavior of situations and their relationships with productivity
• Examine the effectiveness of applying situation models in modeling construction operations
• Provide recommendations for productivity improvement
![Page 31: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/31.jpg)
Data Collection
• Direct site observations– Background (Date, Weather, Area)– Type of Work (False work, Forming, Columns)– States of a Worker (Working, Non-working)– Output
21 categories for non-working time for Carpentry Work; 10 categories for Columns
![Page 32: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/32.jpg)
Observation Categories of Non-Working Time for Carpenter Crew
Categories Description
Extra Breaks Representing late start and early finish. This category includes all the time which are extended non-working time before and after official breaks and lunchtime.
Idle Representing the non-working time that does not fall into any categories of this list.
Waiting Material Representing the non-working time because of materials waiting.
Move Material Representing the time in which the worker is moving materials from one location to another location, but the materials are not used.
Search Material Representing the time in which the worker is searching for or customizing materials for direct use.
Equipment Representing the time in which the worker is looking for, equipping, setting, or waiting for tools, equipment, or power supply.
Watching Representing the non-working time in which the worker is watching another worker performing work. Applies to more than one worker working together.
Precedents Representing the time in which the worker cannot perform work because the worker is waiting for slab work, columns work, rebar work, or when inspection work is being done by other crews.
Instructions Representing the non-working time in which the worker is waiting for instructions or being instructed by a foreman or supervisor.
Travel Representing the time in which the worker is traveling from a working area to another working area
![Page 33: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/33.jpg)
Observation Categories of Non-Working Time for Carpenter Crew
Check Drawings Representing the time in which the worker is reading the drawings
Interruption Representing the time period in which the worker is directed by the foreman or supervisor to perform work that is not regarded as relevant work.
Socialize Socializing or chatting time.
Inspection Representing the time in which the worker is checking the alignment or firmness of fly forms and scaffolds. No direct output is produced.
Measure Representing the time in which the worker is measuring materials or drawing alignment lines
Safety Time relating to safety meetings or safety instructions given by the safety coordinator.
Leave Representing the time in which the worker leaves the working area without a valid reason.
Irrelevant Representing the time in which the worker is working on non-value added activities. Examples are cleaning or packing irrelevant materials. The difference between this category and Interruption is that this category does not involve a foreman’s or supervisor’s directions.
Discuss Representing the time in which the workers are discussing the drawings or construction plans.
Washroom Washroom time
Warm up Representing the time in which the worker is warming up at the heaters. No work is performed.
![Page 34: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/34.jpg)
SituationsSituations False work Forming ColumnChange Area/ Traveling
Cold Weather
Crowded Area
Instructions
Interruptions
Lack of Materials
Drawing Changes
Precedent of Slab
Precedent of Columns
Precedent of Rebar
Non-availability of Concrete
Crane unavailable for Formwork
Crane unavailable for Pouring
Saturated Area
Snowing
![Page 35: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/35.jpg)
Breakdown of Work HoursExtra Breaks
8.5%
WT56.6%
Idle6.5%
Watching1.0%
Precedents1.3%
Instructions2.0%
Travel0.7%
Check Drawings0.2%
Interruption1.0%Socialize
1.2%
Inspection3.2%
Measure0.6%
Safety0.5%
Leave4.5%
Irrelevant2.4%
Discuss0.2%
Washroom0.1%
Warmup1.0%
Equipment0.7%
Search Material0.8%
Move Mat.5.9%
Wait Mat.1.0%
![Page 36: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/36.jpg)
Quantification of Situation
Crowded Area (False Work) - Magnitudes
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96
Quarter
Mag
nitu
de (%
)Maximum is 88% of the total work hours
![Page 37: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/37.jpg)
Quantification of Situation
Crowded Area (False Work) - Ra Graph
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Ra
Mag
nitu
de (%
)
In 80% likelihood, it is 24%
![Page 38: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/38.jpg)
Previous Models
• All the previous models predicted or made a relationship between a factor (or situation) and the productivity by ignoring the existence of the other situations
– Temperature vs. Productivity
– Overtime vs. Productivity
– Change Orders vs Productivity
• Is it possible? NO
![Page 39: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/39.jpg)
New Situation Based Model
• Considers the existence of situations
• You can remove a situation or situations by allowing the existence of others and check the impact of the “removal of the factor” on productivity– Remove “crowded area”– Remove “Interruptions” and
“Lack of Materials”
![Page 40: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/40.jpg)
Situations Influence Diagram
1. Change Area
4. Instructions
7. Drawing Changes
10. Saturated
Area
11. Snowing
8. Precedent
of Slab
5. Interruptions
2. Cold Weather
3. Crowded Area
6. Lack of Materials
9. Precedent of Column
![Page 41: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/41.jpg)
Conceptual Framework
Productivity =Output
Work Hours
Productivity
Amount of Working
Time
Output
Situations
1)
2)
3)4)
Productivity
![Page 42: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/42.jpg)
Conceptual Framework
1. Relationship between Situations and Working Time
Non-Working Time (NWT) = ST
2. Relationship between Situations and Output
Working Time (WT)[SM] = Output
3. Relationship between Working Time and Output
Efficiency or Production Rate
4. Relationship among SituationsStrength of Links
![Page 43: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/43.jpg)
Application of Situation-based Simulation Model
Scenarios
• All Situations (Benchmark)• Without “Change Area”• Without “Crowded Area”• Without “Instructions”• Without “Interruptions”• Without “Saturated Area”
![Page 44: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/44.jpg)
Control Variables of the Scenarios
Setting A Setting B
Number of Floors 3 5Planned Output 400 1000Daily Work Hours 8 8# of Workers 4 12
![Page 45: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/45.jpg)
Application of Situation-based Simulation Model
Setting A Setting BFalse Work % Change False Work % Change
All Situations 4.47 --- 3.88 ---Without Crowded Area 5.46 22% 5.05 30%Without Interruptions 5.69 27% 5.10 31%Without Saturated Area 5.31 19% 5.37 38%Without Change Area 3.80 -15% 3.73 -4%Without Instructions 3.62 -19% 3.57 -8%
![Page 46: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/46.jpg)
Findings from Scenarios application
• Mitigation of “Change Area” and “Instructions” do not improve productivity, because of the counter-effects (Crowded Area and Interruptions)
• Mitigation of “Crowded Area”, “Interruptions”, and “Saturated Area” can improve the productivity by about 20-25%.
![Page 47: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/47.jpg)
Development and Application of Situation-based Simulation Model
Must Eliminate: “Crowded Area” “Interuptions” “Saturated Area”
Must be Allowed: “Change Area” “Instructions”
r
![Page 48: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/48.jpg)
Development and Application of Situation-based Simulation ModelCan’t Eliminate:
“Coldness” “Snowing”
Not Significant: “Drawing Changes”
![Page 49: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/49.jpg)
Breakdown of work hours
Watching0.9%
Interruption0.2%
Measure4.1%
Instructions1.3%
Travel0.3%Check Drawings
0.2%
Extra Breaks4.6%
Idle6.9% Wait Mat.
0.4%Move Mat.
6.0%Search Material
1.4% Equipment1.3%
Washroom0.3% Discuss
1.9%
Irrelevant1.1%
Leave1.1%
Inspection0.2%
Socialize3.7%
WT64.1%
Extra BreaksIdle
Wait Mat.Move Mat.Search Material
EquipmentWatching
InstructionsTravelCheck Drawings
InterruptionSocializeInspection
MeasureLeave
IrrelevantDiscussWashroom
WT
![Page 50: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/50.jpg)
Breakdown of work hours Q1
Watching0.5%
Interruption0.0%
Measure4.4%
Instructions1.6%
Travel0.3%
Check Drawings0.1%
Extra Breaks6.7%
Idle6.2%
Wait Mat.0.4%
Move Mat.5.1%
Search Material1.2%
Equipment1.6%
Washroom0.2%
Discuss2.5%
Irrelevant1.0%
Leave0.4%
Inspection0.3%
Socialize3.3%
WT64.1%
Extra Breaks
Idle
Wait Mat.
Move Mat.
Search Material
Equipment
Watching
Instructions
Travel
Check Drawings
Interruption
Socialize
Inspection
Measure
Leave
Irrelevant
Discuss
Washroom
WT
![Page 51: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/51.jpg)
Breakdown of work hours Q2
Socialize3.4%
Inspection0.2%
Leave1.2%Irrelevant
0.8%
Discuss2.0%Washroom
0.4%
Equipment1.0%
Search Material1.3%
Move Mat.5.1%
Wait Mat.0.3%
Idle6.6%Extra Breaks
4.7%
Check Drawings0.2%
Travel0.3%
Instructions1.1%
Measure3.9%
Interruption0.0%
Watching0.8%
WT66.7%
Extra Breaks
Idle
Wait Mat.
Move Mat.
Search Material
Equipment
Watching
Instructions
Travel
Check Drawings
Interruption
Socialize
Inspection
Measure
Leave
Irrelevant
Discuss
Washroom
WT
![Page 52: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/52.jpg)
Breakdown of work hours Q3
Watching1.2%
Interruption0.5%
Measure4.3%
Instructions1.3%
Travel0.3%
Check Drawings0.0%
Extra Breaks2.7%
Idle7.9% Wait Mat.
0.6%
Move Mat.7.6%
Search Material1.7%
Equipment1.3%
Washroom0.2% Discuss
1.6%
Irrelevant1.1%
Leave1.7%
Inspection0.1%
Socialize4.0%
WT61.9%
Extra Breaks
Idle
Wait Mat.
Move Mat.
Search Material
Equipment
Watching
Instructions
Travel
Check Drawings
Interruption
Socialize
Inspection
Measure
Leave
Irrelevant
Discuss
Washroom
WT
![Page 53: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/53.jpg)
Breakdown of work hours Q4
Socialize4.8%
Inspection0.5%
Leave0.4%
Irrelevant3.3%
Discuss1.1%
Washroom0.1%
Equipment1.6%
Search Material0.7%
Move Mat.5.5%
Wait Mat.1.1%
Idle5.4%
Extra Breaks7.0%
Check Drawings0.9%
Travel1.0%
Instructions1.0%
Measure3.6%
Interruption0.0%
Watching0.5%
WT61.5%
Extra Breaks
Idle
Wait Mat.
Move Mat.
Search Material
Equipment
Watching
Instructions
Travel
Check Drawings
Interruption
Socialize
Inspection
Measure
Leave
Irrelevant
Discuss
Washroom
WT
![Page 54: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/54.jpg)
Breakdown of work hours
Rework7.0%
Socialize3.7%
Inspection0.2%
Leave1.1%Irrelevant
1.1%
Discuss1.9%
Washroom0.3%
Equipment1.3%
Search Material1.4%
Move Mat.6.0%
Wait Mat.0.4%
Idle6.9%Extra Breaks
4.6%
Check Drawings0.2%
Travel0.3%
Instructions1.3%
Measure4.1%
Interruption0.2%
Watching0.9%
WT57.2%
Extra BreaksIdleWait Mat.Move Mat.Search MaterialEquipmentWatchingInstructionsTravelCheck DrawingsInterruptionSocializeInspectionMeasureLeaveIrrelevantDiscussWashroomReworkWT
![Page 55: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/55.jpg)
Breakdown of output per QuarterForming
Break down of Output/Hr - Forming
Q126%
Q227%
Q325%
Q422%
Q1
Q2
Q3
Q4
![Page 56: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/56.jpg)
Productivity (False Work)
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
0.00 20.00 40.00 60.00 80.00 100.00
Confidence Interval
Pro
du
ctiv
ity
(m2/
hr)
![Page 57: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/57.jpg)
What Else?
• Similar Data collected for– Rebar Work on Slabs– Column Work
![Page 58: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/58.jpg)
Recommendations: We are working on them now
• Common sense solutions• Minor modifications to on going site
operations• Out of the box
![Page 59: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/59.jpg)
Sample Comments & Recommendations It was noted that 3.8% of the time, carpenters
were required to move to the lower level and manually move material up to their work area.
This also resulted in an increase in the category of “Idle time” and “Watching”.
This could be rectified by ensuring that the formwork and false work were moved up to the new level in advance.
Another option is to have sufficient quantity of formwork and false work material on site so that quantities of these materials do not result in the worker’s time being underutilized.
![Page 60: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/60.jpg)
Sample Comments & Recommendations
When formwork and false work were available around their work area, it was not collected and stacked as per size as a result 2.6% of the carpenters time were used in measuring and searching for the right size of formwork/false work to use.
In the future, if the team removing the formwork and false work could stack the materials as per size, better productivity will be obtained from the carpenters.
![Page 61: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/61.jpg)
Sample Comments & Recommendations It was also observed that the survey team
which provided the levels for the formwork and false work did not keep ahead of the carpenters.
This happened 30% of the time. On one occasion, the formwork which was built had to be removed and the false work readjusted and on the second instance, the slope given by the surveyor was erroneous. These resulted in rework.
One recommendation would be for the survey team to start a few hours earlier in the day so that their work does not delay the progress on site and vice versa the workers do not hamper their work.
![Page 62: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/62.jpg)
Developing a Model
• Develop an analytical model for redistributing time saved based on the recommendations.
• This model will offer two scenarios for the increase in the output as a result.
– An optimistic and a pessimistic
![Page 63: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/63.jpg)
On-site Testing of a few Recommendations
• Subject to acceptance by the general contractor a few of the recommendation will be tested to verify the increase in tool time
![Page 64: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/64.jpg)
Motivation, Performance and Job Satisfaction of Construction Management Professionals
![Page 65: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/65.jpg)
Top 10 Motivation Factors: Importance (7 point scale)
Motivation factor Importance
Safety on construction site 6.19
The team spirit of the people you work with 6.18
Opportunities to learn new knowledge and skills 6.09
Seeing good results from your work 6
Opportunities to develop your skills and abilities 5.96
The resources you have to do your work 5.89
Opportunities for challenging work 5.82
Opportunities to do the work that best utilizes your talents and abilities 5.7
Opportunities to do something that makes you feel good about yourself as a construction management person
5.7
Freedom and openness to talk directly to senior management 5.7
How important each motivation factor is in motivating them doing their jobs
![Page 66: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/66.jpg)
Top 10 Motivation Factors: Satisfaction (7 point scale)
Motivation factor Satisfaction
Safety on construction site 5.98
Seeing good results from your work 5.89
Opportunities for challenging work 5.88
The amount of freedom you have in your work 5.82
Freedom and openness to talk directly to senior management 5.77
The team spirit of the people you work with 5.74
Opportunities to learn new knowledge and skills 5.72
Receiving respect from the people you work with 5.72
Opportunities to do something that makes you feel good about yourself as a construction management person
5.68
Opportunities to develop your skills and abilities 5.65
How satisfied they are of receiving each motivation factor while doing their jobs
![Page 67: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/67.jpg)
What Else?
• Separate analysis based on– Age– Experience– Educational Background
![Page 68: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/68.jpg)
Analysis• Analyzing the relationship between the
importance degree and satisfaction degree of each motivation factor, the researcher identified the motivation factor, which considerable CMPs perceive that it is important in motivating them doing their jobs, but they do not satisfy, and then the researcher conducted in-depth interviews to investigate the problems that lie behind the motivation factor.
![Page 69: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/69.jpg)
Two motivation factors were identified as having potential problems
• Senior manager's positive feedback after successfully accomplishing the task
• Bonus the CMP’s received
![Page 70: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/70.jpg)
Senior manager's positive feedback after successfully accomplishing your task • Field engineers
– “There were several times that my former supervisors made the work very dissatisfying so that I quitted my jobs. All I received was criticism, and when praise was due, I didn’t receive anything.”
– “I am working very hard without any good words from my boss, but when something goes wrong, even it is not my fault, he always yells at me. Yelling and blaming has no effect other than de-motivating us.”
– “ I don’t really care about money. If my boss would just say thank you, if he or she would just acknowledge that I exist. The only time I hear anything is when I screw up. I never hear when I do a good job.”
![Page 71: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/71.jpg)
Five Strategies of Recommendations
• Invite employees’ involvement in setting up performance or productivity evaluation criteria;
• Adopt clear and fair performance or productivity evaluation criteria, which are widely understood and accepted by employees;
• Set up a committee to evaluate employees’ performance or productivity according to the criteria;
• Allocate bonuses, which have a clear and strong correlation with employees’ performance or productivity.
• Monitor the outcome at regular intervals to see if allocating bonuses have achieved the desired effect.
![Page 72: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/72.jpg)
Future
• There are several other recommendations to share with individual companies
![Page 73: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/73.jpg)
Conclusions• The Project provided many benefits
– Identified key issues
– Quantified impacts
– Will develop recommendations
• Excellent support from the collaborating companies
• Will issue “specific” reports to the collaborating companies
• Will issue a “generalized” report after analyzing the results of the 4 companies (by Dec. 2005)
![Page 74: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/74.jpg)
Future• Win-Win situation for the companies and
the University• Planning to extend the “productivity”
research to study and analyze more issues in the next 2-5 years
• Will create a “Productivity” task force so that specific needs could be identified for future “research.”
• Will maintain QUALITY of research that will be beneficial to industry.
• Will develop an integrated PM framework for the benefit of the construction contractors.
![Page 75: TIME I$ MONEY: Key Productivity findings in Alberta Construction Projects! Dr. Janaka Y. Ruwanpura, PQS Director and Assistant Professor of Project Management.](https://reader035.fdocuments.in/reader035/viewer/2022062518/56649e395503460f94b2b3c2/html5/thumbnails/75.jpg)
Publications – 2005 • Canadian Journal of Civil Engineering
Special Issue in Construction (Aug. 05)– Situation Based Model and Case Study– Motivation, Performance, Satisfaction of
CMP.
• American Society of Civil Engineers – Construction Research Congress (San Diego, Apr. 05)– Situation Based Model
• Canadian Society for Civil Engineering – Annual Conference (Toronto, June 05)– Motivation, and Communication of
Workers