Time Cost Tradeoff

download Time Cost Tradeoff

of 8

Transcript of Time Cost Tradeoff

  • 8/20/2019 Time Cost Tradeoff

    1/18

     

    Construction Management 164 Dr. Emad Elbeltagi

    CHAPTER 8

    PROJECT TIME-COST TRADE-OFF

    In the previous chapters, duration of activities discussed as either fixed or random

    numbers with known characteristics. However, activity durations can often vary

    depending upon the type and amount of resources that are applied. Assigning more

    workers to a particular activity will normally result in a shorter duration. Greater speed

    may result in higher costs and lower quality, however. In this section, we shall consider

    the impacts of time and cost trade-offs in activities.

    Reducing both construction projects’ cost and time is critical in today’s market-driven

    economy. This relationship between construction projects’ time and cost is called time-

    cost trade-off decisions, which has been investigated extensively in the construction

    management literature. Time-cost trade-off decisions are complex and require selection

    of appropriate construction method for each project task. Time-cost trade-off, in fact, is

    an important management tool fo overcoming one of the critical path method limitations

    of being unable to bring the project schedule to a specified duration.

    8.1  Time-Cost Trade-Off

    The objective of the time-cost trade-off analysis is to reduce the original project duration,

    determined form the critical path analysis, to meet a specific deadline, with the least cost.

    In addition to that it might be necessary to finish the project in a specific time to:

    -  Finish the project in a predefined deadline date.

    -  Recover early delays.

    -  Avoid liquidated damages.

    -  Free key resources early for other projects.

  • 8/20/2019 Time Cost Tradeoff

    2/18

     

    Construction Management 165 Dr. Emad Elbeltagi

    -  Avoid adverse weather conditions that might affect productivity.

    -  Receive an early completion-bonus.

    -  Improve project cash flow

    Reducing project duration can be done by adjusting overlaps between activities or by

    reducing activities’ duration. What is the reason for an increase in direct cost as the

    activity duration is reduced? A simple case arises in the use of overtime work. By

    scheduling weekend or evening work, the completion time for an activity as measured in

    calendar days will be reduced. However, extra wages must be paid for such overtime

    work, so the cost will increase. Also, overtime work is more prone to accidents and

    quality problems that must be corrected, so costs may increase. The activity duration can

     be reduced by one of the following actions:

    -  Applying multiple-shifts work.

    -  Working extended hours (over time).

    -  Offering incentive payments to increase the productivity.

    -  Working on week ends and holidays.

    -  Using additional resources.

    -  Using materials with faster installation methods.

    -  Using alternate construction methods or sequence.

    8.2  Activity Time-Cost Relationship

    In general, there is a trade-off between the time and the direct cost to complete an

    activity; the less expensive the resources, the larger duration they take to complete an

    activity. Shortening the duration on an activity will normally increase its direct cost

    which comprises: the cost of labor, equipment, and material. It should never be assumed

    that the quantity of resources deployed and the task duration are inversely related. Thus

    one should never automatically assume that the work that can be done by one man in 16

    weeks can actually be done by 16 men in one week.

  • 8/20/2019 Time Cost Tradeoff

    3/18

     

    Construction Management 166 Dr. Emad Elbeltagi

    A simple representation of the possible relationship between the duration of an activity

    and its direct costs appears in Figure 8.1. Considering only this activity in isolation and

    without reference to the project completion deadline, a manager would choose a duration

    which implies minimum direct cost, called the normal duration. At the other extreme, a

    manager might choose to complete the activity in the minimum possible time, called

    crashed duration, but at a maximum cost.

    Figure 8.1: Illustration of linear time/cost trade-off for an activity

    The linear relationship shown in the Figure 8.1 between these two points implies that anyintermediate duration could also be chosen. It is possible that some intermediate point

    may represent the ideal or optimal trade-off between time and cost for this activity. The

    slope of the line connecting the normal point (lower point) and the crash point (upper

     point) is called the cost slope of the activity. The slope of this line can be calculated

    mathematically by knowing the coordinates of the normal and crash points.

    Cost slope = crash cost – normal cost / normal duration – crash duration

    As shown in Figures 8.1, 8.2, and 8.3, the least direct cost required to complete an

    activity is called the normal cost (minimum cost), and the corresponding duration is

    called the normal duration. The shortest possible duration required for completing the

    activity is called the crash duration, and the corresponding cost is called the crash cost.

     Normally, a planner start his/her estimation and scheduling process by assuming the least

    costly option

     Normal duration&

     Normal cost

    Crash duration

    &

    Crash cost

    Time

    Cost

  • 8/20/2019 Time Cost Tradeoff

    4/18

     

    Construction Management 167 Dr. Emad Elbeltagi

    Figure 8.2: Illustration of non-linear time/cost trade-off for an activity

    Figure 8.3: Illustration of discrete time/cost trade-off for an activity

     Example 8.1

    A subcontractor has the task of erecting 8400 square meter of metal scaffolds. The

    contractor can use several crews with various costs. It is expected that the production will

    vary with the crew size as given below:

    Crash duration

    &

    Crash cost

    Time

    Cost

     Normal duration&

     Normal cost

     Normal duration&

     Normal cost

    Crash duration&

    Crash cost

    Time

    Cost

  • 8/20/2019 Time Cost Tradeoff

    5/18

     

    Construction Management 168 Dr. Emad Elbeltagi

    Estimated daily production

    (square meter)

    Crew

    size(men)

    Crew formation

    166

    204

    230

    5

    6

    7

    1 scaffold set, 2 labors, 2 carpenter, 1 foreman

    2 scaffold set, 3 labors, 2 carpenter, 1 foreman

    2 scaffold set, 3 labors, 3 carpenter, 1 foreman

    Consider the following rates: Labor LE96/day; carpenter LE128/day; foreman LE144/day

    and scaffolding LE60/day. Determine the direct cost of this activity considering different

    crews formation.

    Solution

    The duration for installing the metal scaffold can be determined by dividing the total

    quantity by the estimated daily production. The cost can be determined by summing up

    the daily cost of each crew and then multiply it by the duration of using that crew. The

    calculations are shown in the following table.

    Crew size Duration (days) Cost (LE)

    5

    6

    7

    50.6 (use 51)

    41.2 (use 42)

    36.5 (use 37)

    51 x (1x60 + 2x96 + 2x128 + 1x144) = 33252

    42 x (2x60 + 3x96 + 2x128 + 1x144) = 33936

    37 x (2x60 + 3x96 + 3x128 + 1x144) = 34632

    This example illustrates the options which the planner develops as he/she establishes the

    normal duration for an activity by choosing the least cost alternative. The time-cost

    relationship for this example is shown in Figure 8.4. The cost slop for this activity can be

    calculates as follow:

    Cost slope 1 (between points 1 and 2) = (33936 – 33252) / (51 – 42) = 76.22 LE/day

    Cost slope 2 (between points 2 and 3) = (34632 – 33936) / (42 – 37) = 139.2 LE/day

  • 8/20/2019 Time Cost Tradeoff

    6/18

  • 8/20/2019 Time Cost Tradeoff

    7/18

     

    Construction Management 170 Dr. Emad Elbeltagi

    Figure 8.5: Project time-cost relationship

    The project total time-cost relationship can be determined by adding up the direct cost

    and indirect cost values together as shown in Figure 8.5. The optimum project duration

    can be determined as the project duration that results in the least project total cost.

    8.4  Shortening Project Duration

    The minimum time to complete a project is called the project-crash time. This minimum

    completion time can be found by applying critical path scheduling with all activity

    durations set to their minimum values. This minimum completion time for the project can

    then be used to determine the project-crash cost. Since there are some activities not on the

    critical path that can be assigned longer duration without delaying the project, it is

    advantageous to change the all-crash schedule and thereby reduce costs.

    Heuristic approaches are used to solve the time/cost tradeoff problem such as the cost-

    lope method used in this chapter. In particular, a simple approach is to first apply critical

     path scheduling with all activity durations assumed to be at minimum cost. Next, the

     planner can examine activities on the critical path and reduce the scheduled duration of

    activities which have the lowest resulting increase in costs. In essence, the planner

    develops a list of activities on the critical path ranked with their cost slopes. The heuristic

    solution proceeds by shortening activities in the order of their lowest cost slopes. As the

    Project duration

    Project cost

  • 8/20/2019 Time Cost Tradeoff

    8/18

     

    Construction Management 171 Dr. Emad Elbeltagi

    duration of activities on the shortest path are shortened, the project duration is also

    reduced. Eventually, another path becomes critical, and a new list of activities on the

    critical path must be prepared. Using this way, good but not necessarily optimal

    schedules can be identified.

    The procedure for shortening project duration can be summarized in the following steps:

    1. Draw the project network.

    2.  Perform CPM calculations and identify the critical path, use normal durations and

    costs for all activities.

    3. Compute the cost slope for each activity from the following equation:

    cost slope = crash cost – normal cost / normal duration – crash duration

    4. Start by shortening the activity duration on the critical path which has the least cost

    slope and not been shortened to its crash duration.

    5. Reduce the duration of the critical activities with least cost slope until its crash

    duration is reached or until the critical path changes.

    6. When multiple critical paths are involved, the activity(ies) to shorten is determined

     by comparing the cost slope of the activity which lies on all critical paths (if any),

    with the sum of cost slope for a group of activities, each one of them lies on one of

    the critical paths.

    7. Having shortened a critical path, you should adjust activities timings, and floats.

    8. The cost increase due to activity shortening is calculated as the cost slope

    multiplied by the time of time units shortened.

    9. Continue until no further shortening is possible, and then the crash point is reached.

    10. The results may be represented graphically by plotting project completion time

    against cumulative cost increase. This is the project direct-cost / time relationship.

    By adding the project indirect cost to this curve to obtain the project time / cost

    curve. This curve gives the optimum duration and the corresponding minimum

    cost.

  • 8/20/2019 Time Cost Tradeoff

    9/18

     

    Construction Management 172 Dr. Emad Elbeltagi

     Example 8.2

    Assume the following project data given in Table 8.1. It is required to crash the project

    duration from its original duration to a final duration of 110 days. Assume daily indirect

    cost of LE 100.

    Table 8.1: Data for Example 8.2

     Normal CrashActivity Preceded by

    Duration (day) Cost (LE) Duration (day) Cost (LE)

    A

    BC

    D

    E

    F

    -

    -B

    C

    D, F

    B

    120

    2040

    30

    50

    60

    12000

    180016000

    1400

    3600

    13500

    100

    1530

    20

    40

    45

    14000

    280022000

    2000

    4800

    18000

    Solution

    The cost slope of each activity is calculated. Both the crashability and the cost slope are

    shown beneath each activity in the precedence diagram. The critical path is B-C-D-E and

    the project duration in 140 days. Project total normal direct cost = sum of normal direct

    costs of all activities = LE 48300.

    1.  The activity on the critical path with the lowest cost slope is of activity “D”, this

    activity can be crashed by 10 days. Then adjust timing of the activities.

    C (40)

    20 60

    20 60

    End (0)

    140 140

    140 140

    E (50)

    90 140

    90 140

    A (120)

    20 140

    0 120

    Start (0)

    0 0

    0 0

    B (20)

    0 20

    0 20

    D (30)

    60 90

    60 90

    F (60)

    30 90

    20 80

    20@100

    10@600

    5@200

    10@60

    15@300

    10@120

  • 8/20/2019 Time Cost Tradeoff

    10/18

     

    Construction Management 173 Dr. Emad Elbeltagi

    A new critical path will be formed, B-F-E.

     New Project duration is 130 days.

    The project direct cost is increased by 10 x 60 = LE 600.

    Project direct cost = 48300 + 600 = LE 48900

    2.  At this step activity “E” will be crashed, as this activity lies on both critical paths.

    Activity “E” will be shortened by 10 days.

    Accordingly, all activities will b turn to critical activities.

     New Project duration is 120 days.

    The project direct cost is increased by 10 x 120 = LE 1200.

    Project direct cost = 48900 + 1200 = LE 50100

    C (40)

    20 60

    20 60

    End (0)

    130 130

    130 130

    E (50)

    80 130

    80 130

    A (120)

    10 130

    0 120

    Start (0)

    0 0

    0 0

    B (20)

    0 20

    0 20

    D (20)

    60 80

    60 80

    F (60)

    20 80

    20 80

    20@100

    10@600

    5@200 15@300

    10@120

    C (40)

    20 60

    20 60

    End (0)

    120 120

    120 120

    E (40)

    80 120

    80 120

    A (120)

    0 120

    0 120

    Start (0)

    0 0

    0 0

    B (20)

    0 20

    0 20

    D (20)

    60 80

    60 80

    F (60)20 80

    20 80

    20@100

    10@600

    5@200 15@300

  • 8/20/2019 Time Cost Tradeoff

    11/18

     

    Construction Management 174 Dr. Emad Elbeltagi

    3.  In this step, it is difficult to decrease one activity’s duration and achieve decreasing in

    the project duration. So, either to crash an activity on all critical paths (if any),

    otherwise, choose several activities on different critical paths. As shown, activities

    “A” and “B” can be crashed together which have the least cost slope (100 + 200).

    Then, crash activities “A” and “B” by 5 days.

     New Project duration is 115 days.

    The project direct cost is increased by 5 x (100 + 200) = LE 1500.Project direct cost = 50100 + 1500 = LE 51600

    4.  In this final step, it is required to decrease the duration of an activity from each path.

    The duration of activity ”A” will be crashed to 110 days, “C” to 35 days, and “F” to

    55 days. Thus, achieving decreasing project duration to 110 days. Also, increase in

    the project direct cost by 5 x (100 + 600 + 300) = LE 5000

    C (40)

    15 55

    15 55

    End (0)

    115 115

    115 115

    E (40)

    75 115

    75 115

    A (115)

    0 115

    0 115

    Start (0)

    0 0

    0 0

    B (15)

    0 15

    0 15

    D (20)

    55 75

    55 75

    F (60)

    15 75

    15 75

    15@100

    10@600

      15@300

    C (35)

    15 50

    15 50

    End (0)

    110 110

    110 110

    E (40)

    70 110

    70 110

    A (110)

    0 110

    0 110

    Start (0)

    0 0

    0 0

    B (15)

    0 15

    0 15

    D (20)

    50 70

    50 70

    F (55)

    15 70

    15 70

    10@100

    5@600

    10@300

  • 8/20/2019 Time Cost Tradeoff

    12/18

     

    Construction Management 175 Dr. Emad Elbeltagi

    0

    10000

    20000

    30000

    40000

    50000

    60000

    70000

    80000

    100 110 120 130 140 150

    Project duration (days)

       C  o  s   t   (   L   E   )

     

    Duration (days) Direct cost (LE) Indirect cost (LE) Total cost (LE)

    140

    130

    120

    115

    110

    48300

    48900

    50100

    51600

    56600

    14000

    13000

    12000

    11500

    11000

    62300

    61900

    62100

    63100

    67600

     Example 8.3

    The durations and direct costs for each activity in the network of a small construction

    contract under both normal and crash conditions are given in the following table.

    Establish the least cost for expediting the contract. Determine the optimum duration of

    the contract assuming the indirect cost is LE 125/day.

    Solution

    The cost slope of each activity is calculated. Both the crashability and the cost slope are

    shown beneath each activity in the precedence diagram. The critical path is A-C-G-I and

    the contract duration in 59 days.

  • 8/20/2019 Time Cost Tradeoff

    13/18

     

    Construction Management 176 Dr. Emad Elbeltagi

    Table 8.2: Data for Example 8.3

     Normal Crash

    Activity Preceded by Duration (day) Cost (LE) Duration (day) Cost (LE)

    A

    B

    C

    D

    E

    F

    G

    H

    I

    -

    A

    A

    B

    B

    C

    E, C

    F

    D, G, H

    12

    8

    15

    23

    5

    5

    20

    13

    12

    7000

    5000

    4000

    5000

    1000

    3000

    6000

    2500

    3000

    10

    6

    12

    23

    4

    4

    15

    11

    10

    7200

    5300

    4600

    5000

    1050

    3300

    6300

    2580

    3150

    Solution

    The cost slope of each activity is calculated. Both the crashability and the cost slope are

    shown beneath each activity in the precedence diagram. The critical path is A-C-G-I and

    the contract duration in 59 days.

    1.  The activity on the critical path with the lowest cost slope is “G”, this activity can

     be crashed by 5 days, but if it is crashed by more than 2 days another critical path

    will be generated. Therefore, activity “G” will be crashed by 2 days only. Then

    adjust timing of the activities.

    D (23)

    24 47

    20 43

    I (12)

    47 59

    47 59

    H (13)

    34 47

    32 45

    F (5)

    29 34

    27 32

    B (8)

    14 22

    12 20

    A (12)

    0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)

    22 27

    20 25

    G (20)

    27 47

    27 47

    2@40

    2@100 1@502@150

    3@200

    5@60

    1@300

    2@75

  • 8/20/2019 Time Cost Tradeoff

    14/18

     

    Construction Management 177 Dr. Emad Elbeltagi

    A new critical path will be formed, A-C-F-H-I. New contract duration is 57 days and the cost increase is 2 x 60 = LE 120.

    2.  At this step the activities that can be crashed are listed below:

    Either “A” at cost LE 100/day

    Or “C” at cost LE 200/day

    Or “I” at cost LE 75/day

    Or “F & G” at cost LE 360/day

    Or “H & G” at cost LE 100/ day

    Activity “I” is chosen because it has the least cost slope, and it can be crashed by 2

    days. Because it is last activity in the network, it has no effect on other activities.

     New contract duration is 55 days and the cost increase is 2 x 75 = LE 150.

    Cumulative cost increase = 120 + 150 = LE 270

    D (23)

    22 45

    20 43

    I (12)

    45 57

    45 57

    H (13)

    32 45

    32 45

    F (5)

    27 32

    27 32

    B (8)

    14 22

    12 20

    A (12)

    0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)

    22 27

    20 25

    G (18)

    27 45

    27 45

    2@40

    2@100 1@502@150

    3@200

    3@60

    1@300

    2@75

    D (23)

    22 45

    20 43

    I (10)

    45 55

    45 55

    H (13)

    32 45

    32 45

    F (5)

    27 32

    27 32

    B (8)14 22

    12 20

    A (12)0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)22 27

    20 25

    G (18)27 45

    27 45

    2@40

    2@100 1@502@150

    3@200

    3@60

    1@300

  • 8/20/2019 Time Cost Tradeoff

    15/18

     

    Construction Management 178 Dr. Emad Elbeltagi

    3.   Now, we could select “A” or both “H & G”, because they have the same cost

    slope. Activity “A” is chosen to be crashed. This will change the timings for all

    activities, but no new critical path will be formed.

     New contract duration is 53 days and the cost increase is 2 x 100 = LE 200.

    Accordingly, cumulative cost increase = 270 + 200 = LE 470

    4.   Now, activities “H & G” can be crashed by 2 days each. “A” new critical path A-

    B-D-I will be formed.

     New contract duration is 51 day and the cost increase is 2 x 100 = LE 200.

    Accordingly, cumulative cost increase = 470 + 200 = LE 670

    D (23)

    20 43

    18 41

    I (10)

    43 53

    43 53

    H (13)

    30 43

    30 43

    F (5)

    25 30

    25 30

    B (8)

    12 20

    10 18

    A (10)

    0 10

    0 10

    C (15)

    10 25

    10 25

    E (5)

    20 25

    18 23

    G (18)

    25 43

    25 43

    2@40

    1@502@150

    3@200

    3@60

    1@300

    D (23)

    18 41

    18 41

    I (10)

    41 51

    41 51

    H (11)

    30 41

    30 41

    F (5)

    25 30

    25 30

    B (8)

    10 18

    10 18

    A (10)

    0 10

    0 10

    C (15)

    10 25

    10 25

    E (5)

    20 25

    18 23

    G (16)

    25 41

    25 41

    1@502@150

    3@200

    1@60

    1@300

  • 8/20/2019 Time Cost Tradeoff

    16/18

     

    Construction Management 179 Dr. Emad Elbeltagi

    5.  At this stage, the network has three critical paths. The activities that can be

    crashed are listed below:

    Either C & B at cost LE 350/day or F, G & B at cost LE 510/day

    Activities C & B are chosen because they have the least cost slope.

     New contract duration is 49 days and the cost increase is 2 x 350 = LE 700.

    Cumulative cost increase = 670 + 700 = LE 1370

     Now, there is no further shortening is possible.

    The contract duration and the corresponding cost are given in the table below.

    Duration Direct cost X 1000 LE Indirect cost x 1000 LE Total cost x 1000 LE

    59 36.50 7.375 43.875

    57 36.62 7.125 43.745

    55 36.77 6.875 43.645

    53 36.97 6.625 43.595

    51 37.17 6.375 43.545

    49 37.87 6.125 43.995

    D (23)

    16 39

    16 39

    I (10)

    39 49

    39 49

    H (11)

    28 39

    28 39

    F (5)

    23 28

    23 28

    B (6)

    10 16

    10 16

    A (10)

    0 10

    0 10

    C (13)

    10 3

    10 23

    E (5)

    18 23

    16 21

    G (16)

    23 39

    23 39

    1@50

    1@200

    1@60

    1@300

    0

    10

    20

    30

    40

    50

    48 50 52 54 56 58 60

    Time (days)

       L   E   x

       1   0   0   0

    Direct cost

    Total cost

    Indirect cost

  • 8/20/2019 Time Cost Tradeoff

    17/18

     

    Construction Management 180 Dr. Emad Elbeltagi

    8.5  Exercises

    1.  The following table gives the activities involved in a pipeline contract. The

    duration and cost data are also given. The indirect cost for the contract is

    LE120/day. Calculate the minimum cost of the work corresponding to contract

    duration of 102 days.

     Normal Crashability Cost

    SlopeAct. Description Predes.

    Time Cost (days) (LE)

    A Preparation --- 10 200 - -

    B Move on to site A 20 200 - -

    C Obtain pipes A 40 1800 - -

    D Obtain valves A 28 500 8 10

    E Locate pipeline B 8 150 - -

    F Cut specials C 10 100 4 40

    G Excavate trench E 30 3000 20 180

    H Prepare valve chambers C, G 20 2800 12 50

    I Layout joint pipes C, G 24 1000 10 65

    J Fit valves D, F, H 10 200 4 80

    K Concrete anchors I 8 520 1 80L Backfill J, K 6 420 1 60

    M Finish valve chambers J, K 6 200 3 40

     N Test pipeline J, K 6 150 2 70

    O Clean up site L, N 4 300 - -

    P Leave site M, O 2 180 - -

    2.  Cost and schedule data for a small project are given below. Assume an indirect

    cost of LE 200/day. Develop the time-cost curve for the project and determine theminimum contract duration

  • 8/20/2019 Time Cost Tradeoff

    18/18

     

    Construction Management 181 Dr. Emad Elbeltagi

    Cost (LE) Duration (days)Activity Preceded by

    Crash Normal Crash Normal

    A

    B

    C

    D

    E

    F

    G

    H

    I

    -

    A

    B

    B

    B

    C

    F

    E

    D, G, H

    3900

    6500

    7200

    4900

    2200

    1700

    7200

    10000

    4700

    3600

    5500

    6350

    4700

    2050

    1200

    7200

    9450

    4500

    6

    3

    7

    18

    9

    6

    5

    10

    6

    7

    5

    9

    19

    10

    8

    5

    11

    7

    3.  Draw the precedence diagram for the following data.

    Duration (days)

    Activity Followed by

     Normal Minimum

    Cost slope

    LE / day

    A

    BC

    D

    E

    F

    G

    H

    I

    J

    K

    L

    M

     N

    B, E, F

    KH, D

    I, N

    G, M

    L

    C

    I, N

    -

    E, F

    G

    M

    C

    -

    7

    98

    11

    9

    8

    7

    6

    12

    10

    14

    18

    9

    12

    5

    57

    4

    6

    7

    5

    2

    9

    8

    10

    16

    8

    9

    200

    450400

    100

    400

    500

    200

    200

    200

    600

    350

    700

    550

    200

    It is required to compress the schedule to a 65-day. How much more would the

     project cost?