    5/29/12 TIMBERLAND POWERSYSTEMS

    PREPAID POWER DISTRIBUTION

    SYSTEM IN RAJASTHAN

    Rakshit KumarS. VenkateswaranRushikesh Malaviya

    TIMBERLAND POWERSYSTEMS

    TIMBERLAND POWER SYSTEMS PVT.

    LTD.

  • 7/31/2019 Timberland Power Distribution_MCOM

    2/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contents

    1. INTRODUCTION

    2. STATEMENT OF NEED

    3. PROJECT DESCRIPTION

    3.1 TIMBERLAND PREPAID PDS

    4. PROJECT MANAGEMENT

    4.1 PROJECT SCHEDULE OF JHUNJHUNU

    5. BUDGET & QUALIFICATIONS

    6. CONCLUSIONS

    5/29/12 TIMBERLANDPOWER SYSTEMS

    22

  • 7/31/2019 Timberland Power Distribution_MCOM

    3/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    1. INTRODUCTIONElectrical distribution systems have seen

    enormous changes since the early days of power

    generation.

    At present the demand & supply gap is

    increasing exponentially.

    Depleting natural resources and increasing

    population pose greatest challenge.

    -

    5/29/12 TIMBERLANDPOWER SYSTEMS

    33

  • 7/31/2019 Timberland Power Distribution_MCOM

    4/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd

    Timberland Power Distribution Systems Pvt.Ltd. has developed - prepaid power

    distribution system.

    A win-win situation for both: power

    generating companies & consumers.

    This system is approved by Government of

    India.

    5/29/12 TIMBERLANDPOWER SYSTEMS

    44

  • 7/31/2019 Timberland Power Distribution_MCOM

    5/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd This system employs cutting edge software

    system

    System alarms for any theft of electricity in thegrid

    It has low cost of implementation

    Prepaid meter and IT infrastructure to be setup

    Customers purchases rupee amount of electrical

    units

    5/29/12 TIMBERLANDPOWER SYSTEMS

    55

  • 7/31/2019 Timberland Power Distribution_MCOM

    6/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    ContdSystem will be implemented in state of Rajasthan:

    one district at a time (Jhunjhunu district has 6towns, 250 villages)

    Approximately 7000lacs units per annum

    There is a huge loss of25-30% due to theft ofelectricity

    Contractual agreement with Government ofRajasthan for 15% of profit

    This project will be a prototype model for

    5/29/12 TIMBERLANDPOWER SYSTEMS

    66

  • 7/31/2019 Timberland Power Distribution_MCOM

    7/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd

    5/29/12 TIMBERLANDPOWER SYSTEMS

    77

    Graphicalrepresentation ofRevenue model

  • 7/31/2019 Timberland Power Distribution_MCOM

    8/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    2. STATEMENT OF NEED At present 25-30% is lost due to line-tapping in

    Rajasthan

    10% of electricity shortage

    5-8% of unpaid bills

    Transmission Loss 15%

    Overhead expenses

    Collection & verification employees

    5/29/12

    88

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    9/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    istribution of electricity usag

    5/29/12

    99

    TIMBERLANDPOWER SYSTEMS

    Contd

    Current PowerDistribution

  • 7/31/2019 Timberland Power Distribution_MCOM

    10/27

    5/29/12 TIMBERLAND POWERSYSTEMS

    3. Project description

    POWER DISTRIBUTION OVERVIEW

    5/29/12

    1010

    TIMBERLAND POWERSYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    11/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    3.1 Timberland Prepaid PDS

    Proposed plan to the government in the month ofSeptember, 2010

    Obtained approval for the same from government

    Our work include:

    Installation of prepaid meters

    Sale of prepaid packages to customers

    Following up and maintenance of the installedsystems with Electricity Board

    Handing over the collected revenue to Electricity

    5/29/12

    1111

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    12/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    4. Project managementThree Level Structure for a

    District

    5/29/12

    1212

    TIMBERLANDPOWER SYSTEMS

    For central hub station

    -Station manager-Manager-Senior Engineer-Junior Engineer-PRO (Public RelationsOfficer)-Legal Advisor IT-Support staff-Electrician-Help boys-Collection agent

    Centralhub

    stationin

    Jhunjhunu

    district

    Sub-hub

    station

    Sub-hub

    station

    Sub-hub

    station

    Sub-hub

    station

    Sub-hub

    station

    Sub-hub

    station

    2nd LevelTowns

    1st LevelDistrict

    50 village-hub stations, each station will cater to 5 villages intotal 250 villages

    (ratio of 1:5)3rd LevelVillages

    For Sub-hub station

    (total 6 stations)-Station manager-Junior Engineer-IT support staff-Electrician-Help boys-Collection agent

    For Village hub station

    (50 centers for 250villages)-Collection agent-Security personnel

  • 7/31/2019 Timberland Power Distribution_MCOM

    13/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd(reporting structure)

    5/29/12

    1313

    TIMBERLANDPOWER SYSTEMS

    CEO

    CFO StationManager( District)

    LegalAdviser

    Junior

    Engineers

    Senior

    Engineers

    Manager(Central

    Hub)

    Security

    Personn

    Electricians

    Help

    Boys

    ITStaff

    PRO

    Junior

    Engineers

    SeniorEngineers

    Manager(Sub Hub)

    Security

    Personn

    Electricians

    Help

    Boys

    ITStaff

    Collection

    Agent

  • 7/31/2019 Timberland Power Distribution_MCOM

    14/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd

    Processors and software packages for stations willbe sourced from IBM India

    Prepaid Meters will be purchased from EngineeringWing ofBangladesh University of Engineering andTechnology (BUET)

    Computers in the respective Electricity Board officeswill be used

    Remaining computers will be purchased from local

    vendors

    5/29/12

    1414

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    15/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    4.1 project schedule for jhunjhunuPhase 1 (Dec 1, 2010 to Dec 11, 2010)

    Installation in Central Hub Station (Jhunjhunu)

    Phase 2 (Dec 12, 2010 to Dec 25, 2010)

    Installation in two sub-hub stations (Chirawa & Khetri)

    Phase 3 (Dec 26, 2010 to Jan 09, 2011)

    Installation in two sub-hub stations (Buhana & NawalGarh)

    Phase 4 (Jan 10, 2011 to Jan 23, 2011)

    Installation in sub-hub stations (Udaipurwati & Pilani)

    Phase 5 (Jan 24, 2011 to Feb 06, 2011)

    Installation in 25 village-hub stations.

    Phase 6 (Feb 07, 2011 to Feb 21, 2011)

    Installation & implementation in next 25 village-hub

    5/29/12

    1515

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    16/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    5. Budget & qualifications Budget include costs to be incurred in Jhunjhunu

    District

    IT Infrastructure

    Installation Charge

    Operating expenses General operating expenses

    5/29/12

    1616

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    17/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd (IT Infrastructure cost)

    5/29/12

    1717

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    18/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd (installation charge)

    5/29/12

    1818

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    19/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd (General expenses)

    5/29/12

    1919

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    20/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd (operating expenses)

    5/29/12

    2020

    TIMBERLANDPOWER SYSTEMS

  • 7/31/2019 Timberland Power Distribution_MCOM

    21/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd (operating expenses)

    5/29/12

    2121

    TIMBERLANDPOWER SYSTEMS

    5/29/12TIMBERLAND 5/29/12TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    22/27

    5/29/12 TIMBERLANDPOWER SYSTEMSContd (REVENUE MODEL,

    ESTIMATED)

    5/29/12

    2222

    TIMBERLANDPOWER SYSTEMS

    S.No. Description Lac Unit**

    (based on 2009-2010figures)

    Rate perunit in Rs

    Total in Rsx 1,00,000

    1Total ElectricityConsumptions in Units

    7177.68

    2 Household Use 991.37 4.5 4461.165

    3 Commercial and Tempuse

    1576.97

    5.25

    8279.0925

    4 Industrial Use 1627.04 5.75 9355.48

    5 Public Lighting Use 920.53 5 4602.65

    6 Irrigation Use 880.15 3.75 3300.5625

    7 Public WaterDistribution Use

    1091.49

    4

    4365.96

    8 Other use 90.13 3 270.39

    TOTAL 34635.3

    **data source: Central Electricity Regulatory CommissionTotal Revenue generated : 346 crore Rs.

    Profit for Government (30%) : 103.9 crores Rs.

    Income for Timberland Power Systems (15%): 15.5 crores Rs.

    5/29/12 TIMBERLAND 5/29/12 TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    23/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    QualificationS Timberland power Distribution System Pvt. Ltd. Is

    incorporated in April, 2010

    Owners:

    Mr. Mohan Lal Ahluwalia

    Mr. Shyam Prasad Members of the board and advisory committee of

    the company

    Experience: Around 20 years of experience in NHPC(National Hydro Power Corporation) .

    A core team of 15 employees who have an averageexperience of8-10 years in electricity generationprojects.

    5/29/12

    2323

    TIMBERLANDPOWER SYSTEMS

    5/29/12 TIMBERLAND 5/29/12 TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    24/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd

    Details of CEO and CFO for companies operationsin State of Rajasthan:

    Chief Executive Officer (CEO):Mr. Arun Kumar

    Professional record:

    B.Tech. -May-1986 (IIT Chennai)

    M.B.A. -June-1988 (IIM Ahmedabad)

    Bharat Heavy Electric Machine: General Manager June-1988 toDec-1997.

    Larsen & Tubro: Vice President Jan-1998 to Aug-2010

    Chief Financial Officer (CFO):Mr. Ram Sharma

    Professional Record

    M.Com.-May 1986 (M.S. University, Vadodara)

    5/29/12

    2424

    TIMBERLANDPOWER SYSTEMS

    5/29/12 TIMBERLAND 5/29/12 TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    25/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    6. conclusions

    Prepaid distribution systems benefits forPower distribution companies

    Better forecasting of revenues

    Greater cost controls

    Reduced resource needs for collection &verification

    Reduced power related consumer incidences &unnecessary overheads

    Prepaid distribution system benefits forconsumers

    Better management of finances

    Greater visibility into costs and energy use

    Greater predictability

    5/29/12

    2525

    TIMBERLANDPOWER SYSTEMS

    5/29/12 TIMBERLAND 5/29/12 TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    26/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Contd

    Support from the Government of India and

    Rajasthan.

    Company is going to setup this system in theState of Rajasthan district wise (Planned for next3 years)

    Company is looking for Rs. 10.6 crores for capital

    investment

    We welcome you to visit our pilot project atRewari.

    5/29/12

    2626

    TIMBERLANDPOWER SYSTEMS

    5/29/12 TIMBERLAND 5/29/12 TIMBERLAND

  • 7/31/2019 Timberland Power Distribution_MCOM

    27/27

    5/29/12 TIMBERLANDPOWER SYSTEMS

    Thank You

    Companys offices address:

    Timberland Power Distribution Systems Pvt. Ltd.

    Plot # 52,

    Malviya Nagar, Near Ahinsa Circle

    Jaipur (Rajasthan)

    India 302005

    5/29/12

    2727

    TIMBERLANDPOWER SYSTEMS