Timber Sale Appraisal Hindsight Sale FG-341-2020-W00231-01 · 2020-02-05 · District: Forest Grove...
Transcript of Timber Sale Appraisal Hindsight Sale FG-341-2020-W00231-01 · 2020-02-05 · District: Forest Grove...
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Cost Summary
Conifer Hardwood TotalGross TimberSale Value $1,413,636.13 $2,617.70 $1,416,253.83
Project Work: ($103,400.00)
Advertised Value: $1,312,853.83
12/18/19 1
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Timber Description
Location: Portions of Sections 16 and 17, T3N, R5W, W.M., Washington County, Oregon
Stand Stocking: 20%
Specie Name AvgDBH Amortization (%) Recovery (%)
Douglas - Fir 23 0 98
Western Hemlock / Fir 18 0 98
Alder (Red) 13 0 95
Volume by Grade 2S 3S & 4S 6"-11" Camprun Total
Douglas - Fir 2,405 491 0 2,896
Western Hemlock / Fir 267 106 0 373
Alder (Red) 0 0 10 10
Total 2,672 597 10 3,279
12/18/19 2
Comments: Pond Values Used: Local Pond Values, August 2019.
Western redcedar and Other Cedars Stumpage Price = Pond Value minus Logging Cost: $869.76/MBF = $1,086.00/MBF - $216.24/MBF
Bigleaf maple and Other Hardwood Stumpage Price = Pond Value minus Logging Cost: $135.77/MBF = $390/MBF - $254.23/MBF
BRANDING AND PAINTING COST ALLOWANCE = $2.00/MBF
FUEL COST ALLOWANCE = $3.00/Gallon
HAULING COST ALLOWANCEHauling costs equivalent to $950 daily truck cost.
Other Costs (with Profit & Risk to be added): None
Other Costs (No Profit & Risk added):Machine Time to Block/Waterbar Roads,and Skid Trails:20 hours x $150/hour = $3,000Machine Time to Pile Landing Slash:10 hours x $150/hour = $1,500Equipment Cleaning: 3 pieces x $1,000/Piece = $3,000Slash Treatment: 41 acres x $200/acre = $8,200TOTAL Other Costs (No Profit & Risk added) = $15,700
ROAD MAINTENANCEMove-in: $4,000General Road Maintenance: 2.9 miles x $1,200/mile = $3,480TOTAL Road Maintenance: $7,480/3,279 MBF = $2.28/MBF
12/18/19 3
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Logging ConditionsCombination#: 1 Douglas - Fir 20.00%
Western Hemlock / Fir 20.00%Alder (Red) 20.00%
Logging System: Cable: Medium Tower >40 - <70 Process: Stroke Delimber
yarding distance: Medium (800 ft) downhill yarding: Notree size: Mature / Regen Cut (900 Bft/tree), 3-5 logs/MBF
loads / day: 12 bd. ft / load: 4000
cost / mbf: $125.00
machines: Log Loader (A)Stroke Delimber (A)Tower Yarder (Medium)
Combination#: 2 Douglas - Fir 80.00%Western Hemlock / Fir 80.00%Alder (Red) 80.00%
Logging System: Shovel Process: Feller Buncher
yarding distance: Medium (800 ft) downhill yarding: Notree size: Mature / Regen Cut (900 Bft/tree), 3-5 logs/MBF
loads / day: 13 bd. ft / load: 3793
cost / mbf: $71.75
machines: Feller Buncher w/ Delimber
12/18/19 4
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Logging CostsOperating Seasons: 1.00 Profit Risk: 12%
Project Costs: $103,400.00 Other Costs (P/R): $0.00
Slash Disposal: $0.00 Other Costs: $15,700.00
Miles of Road
DirtRock
(Contractor)Rock
(State) Paved
0.0 0.0 0.0 0.0
Road Maintenance:
Hauling Costs
Species $ / MBF Trips/Day MBF / Load
Douglas - Fir $0.00 2.0 4.8
Western Hemlock / Fir $0.00 2.0 4.6
Grand Fir $0.00 2.0 4.8
Alder (Red) $0.00 2.0 3.7
$2.28
12/18/19 5
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Logging Costs Breakdown
Logging RoadMaint
FireProtect Hauling Other
P/R applProfit &
RiskSlash
Disposal Brand & Paint Other Total
Douglas - Fir
$82.40 $2.33 $1.34 $100.94 $0.00 $22.44 $0.00 $2.00 $4.79 $216.24
Western Hemlock / Fir
$82.40 $2.33 $1.34 $105.33 $0.00 $22.97 $0.00 $2.00 $4.79 $221.16
Alder (Red)
$82.40 $2.39 $1.34 $134.80 $0.00 $26.51 $0.00 $2.00 $4.79 $254.23
Specie Amortization Pond Value Stumpage Amortized
Douglas - Fir $0.00 $663.25 $447.01 $0.00
Western Hemlock / Fir $0.00 $540.45 $319.29 $0.00
Alder (Red) $0.00 $516.00 $261.77 $0.00
12/18/19 6
District: Forest Grove Date: December 18, 2019
Timber Sale AppraisalHindsight
Sale FG-341-2020-W00231-01
Summary
Specie MBF Value Total
Douglas - Fir 0 $0.00 $0.00
Western Hemlock / Fir 0 $0.00 $0.00
Alder (Red) 0 $0.00 $0.00
Specie MBF Value Total
Douglas - Fir 2,896 $447.01 $1,294,540.96
Western Hemlock / Fir 373 $319.29 $119,095.17
Alder (Red) 10 $261.77 $2,617.70
Amortized
Unamortized
Gross Timber Sale Value
Recovery: $1,416,253.83
Prepared By: Adrian Torres Phone: 503-359-2191
12/18/19 7
Timber Sale:
Sale Number:
Project Point Description Cost
A Install Gate $994.00
C Install Gate $1,064.00
D Block Road $550.40
E Block Road $550.40
F Install Gate $1,269.20
Total Rock =
40 cy Boulders
Move-in & Within Area Move= $149.54
$4,577.54
Project Point Cost
B $95,594.09
Total Rock =
120 cy 1½" - 0
8 cy Boulders
Move-in = $3,228.37
$98,822.46
$103,400.00TOTAL CREDITS =
PROJECT COST SUMMARY SHEET
Hindsight
FG-341-2020-W00231-01
PROJECT NO. 1: CONSTRUCT AND INSTALL 3 GATES, BLOCK ROAD
TOTAL PROJECT COST =
PROJECT NO. 2: INSTALL TEMPORARY BRIDGE
TOTAL PROJECT COST =
Timber Sale:
Install gate at Point A
Construction of posts 1 ea @ $500.00 per ea = $500.00
Gate 1 ea @ $220.00 per ea = $220.00
Post and gate install 1 ea @ $274.00 per ea = $274.00
Install gate at Point C
Construction of posts 1 ea @ $500.00 per ea = $500.00
Gate 1 ea @ $290.00 per ea = $290.00
Post and gate install 1 ea @ $274.00 per ea = $274.00
Install gate at Point F
Construction of posts 1 ea @ $500.00 per ea = $500.00
Gate 1 ea @ $220.00 per ea = $220.00
Post and gate install 1 ea @ $274.00 per ea = $274.00
$3,052.00
ROCK
Subgrade rock
Road Blocking Boulders $13.41 $19.39 $1.60 32 $1,100.80
Gate Reinforcement Boulders $13.41 $19.39 $1.60 8 $275.20
Subtotal = 40 $1,376.00
Totals All Rock = 40
Boulders = 40
$1,376.00
$4,428.00TOTAL PROJECT COST =
PROJECT NO. 1 GATE INSTALLATION
Sale Number:
SUMMARY OF CONSTRUCTION COST
Hindsight FG-341-2020-W00231-01
Rock SizeBase Cost
$/cy
Haul Cost
$/cy
Placement/
Processing
Cost $/cy
Total EA Rock Cost
TOTAL ROCK COSTS =
TOTAL GATE COSTS =
Timber Sale:
14' x 40' Bridge 1 ea @ $85,750.00 per ea = $85,750.00
Delivery 1 ea @ $4,950.00 per ea = $4,950.00
Sill Preparation 2.00 hr @ $175.00 per sta = $350.00
Sill 2 ea @ $150.00 per ea = $300.00
Removal of existing bump rails 2.00 hr @ $40.00 per sta = $80.00
Bridge Installation 2.00 hr @ $350.00 per sta = $700.00
$92,130.00
ROCK
Rock
Sill, Abutment and Surfacing rock 1½" - 0 $13.41 $11.62 $1.22 120 $3,150.00
Boulders 36" $13.41 $17.42 $1.60 8 $259.09
Subtotal = 128 $3,409.09
Totals All Rock = 128
1½" - 0 = 120
Boulders = 8
$3,409.09
EROSION CONTROL
Grass seed & fertilizer 0.05 ac @ $500.00 per ac = $25.00
Straw mulch (acre) 0.05 ac @ $600.00 per ac = $30.00
$55.00
$95,594.09
Total CY
Placement/
Processing
Cost $/cy
Haul Cost
$/cy
Base
Cost $/cy
TOTAL ROCK COSTS =
TOTAL EROSION CONTROL COSTS =
TOTAL PROJECT COST =
SUMMARY OF CONSTRUCTION COST
BRIDGE
Hindsight Sale Number: FG-341-2020-W00231-01
PROJECT NO. 2
TOTAL CONSTRUCTION COSTS =
Rock
SizeRock Cost
Timber Sale: Hindsight Sale Number:
PROJECT No. 1 & 2 MOVE-IN, WITHIN AREA MOVE, & CLEANING COSTS
Equipment Total
Grader $655.57
Roller & Compactor $418.51
2 Excavators- With Equipment Cleaning $2,303.83
$3,377.91
SUMMARY OF CONSTRUCTION COST
FG-341-2020-W00231-01
TOTAL MOVE-IN COSTS =
1 1/2" - 0: 120 cy (truck measure)
Riprap: 48 cy (truck measure)
Total truck yardage: 168 cy
Load dump truck $1.60 / cy x 168 cy = $268.80
Subtotal: $268.80
Move in Excavator $1,884.31
Move in Dump Truck $100.24
Subtotal: $1,984.55
$2,253.35
$13.41/cy
STOCKPILE COST SUMMARY
Timber Sale: Hindsight
Sale Number: FG-341-2020-W00231-01
Stockpile Name: Wildcat Mountian
TOTAL PRODUCTION COST =
ROCK DEVELOPMENT COST =
Timber Sale:
Sale Number:
Project Point Description Cost
A Install Gate $994.00
C Install Gate $1,064.00
D Block Road $550.40
E Block Road $550.40
F Install Gate $1,269.20
Total Rock =
40 cy Boulders
Move-in & Within Area Move= $149.54
$4,577.54
Project Point Cost
B $95,594.09
Total Rock =
120 cy 1½" - 0
8 cy Boulders
Move-in = $3,228.37
$98,822.46
$103,400.00
PROJECT COST SUMMARY SHEET
Hindsight
FG-341-2020-W00231-01
PROJECT NO. 1: CONSTRUCT AND INSTALL 3 GATES, BLOCK ROAD
TOTAL PROJECT COST =
PROJECT NO. 2: INSTALL TEMPORARY BRIDGE
TOTAL PROJECT COST =
TOTAL CREDITS =
Hindsight
Page 1 of 1
TIMBER SALE SUMMARY
Hindsight Contract No. FG-341-2020-W00231-01
1. Location: Portions of Sections 16 and 17, T3N, R5W, W.M., Washington County, Oregon.
2. Type of Sale: This Timber Sale is 104 net acres of Modified Clearcut. The timber will be sold on a recovery basis at a sealed bid auction.
3. Revenue Distribution: 100% BOF; 100% Washington County.
4. Sale Acreage: Acres are net of stream buffers and road prisms. Acreage was
determined using ESRI ArcMap GIS software.
5. Cruise: The Timber Sale was cruised by ODF Cruisers in September of 2019. For more information, see Cruise Report.
6. Timber Description: The Timber Sale Area consists of a thinned 80-year old Douglas-fir stand with minor amounts of western hemlock, grand fir, western red cedar, red alder and big leaf maple. The stand has an average of 163 ft2 of basal area (all species), an average Douglas-fir DBH of 23 inches, and an estimated average net Douglas-fir volume of approximately 27.8 MBF per acre.
7. Topography and Logging Method: Slopes within the Timber Sale Area ranges from 2% to 80% and variable in northern aspect. The Timber Sale is 80% ground-based yarding. The maximum cable corridor length is approximately 700 feet and the average length is 400 feet. The average horizontal skid trail length is approximately 450 feet and the maximum is approximately 600 feet.
8. Access: All access to the Timber Sale Area is on surfaced all-weather roads. From
Forest Grove, travel north on Highway 47 through Banks then merge onto Highway 26 westbound and continue for approximately 11.5 miles to Timber Road. Turn left and proceed south on Timber Road 0.7 miles to Lousignont Road. Turn right and continue approximately 0.6 miles to the South Lousignont Road. Turn left and continue on South Lousignont Road for approximately 300 feet to the northeast portion of the timber sale.
9. Projects:
Project No. 1: Construct and Install 3 Gates, Block Road $4,577.54 Project No. 2: Road Improvement $98,822.46
Total Credit for all Projects $103,400.00
SPECIES 2 SAW 3 SAW 4 SAW CR TOTAL
Cruise Volume 2,454 404 97 0 2,955
Hidden D&B (2%) (49) (8) (2) (0) (59)
NET TOTAL 2,405 396 95 0 2,896
% of Total 83 14 3 0
Cruise Volume 187 87 15 0 289
Hidden D&B (2%) (4) (2) (0) (0) (6)
NET TOTAL 183 85 15 0 283
% of Total 65 30 5 0
Cruise Volume 86 6 0 0 92
Hidden D&B (2%) (2) (0) (0) (0) (2)
NET TOTAL 84 6 0 0 90
% of Total 93 7 0 0
Cruise Volume 0 0 0 11 11
Hidden D&B (5%) (0) (0) (0) (1) (1)
NET TOTAL 0 0 0 10 10
% of Total 0 0 0 100
2 SAW 3 SAW 4 SAW CR TOTAL
2,405 396 95 0 2,896
183 85 15 0 283
84 6 0 0 90
0 0 0 10 10
2,672 487 110 10 3,279Total
Douglas-fir
Western
hemlock
Douglas-fir
Red alder
SPECIES
SALE TOTAL
Grand fir
Western hemlock
Grand fir
Red alder
AREA 1: MC (104 ACRES)
Volume Summary
(Shown in MBF)
Hindsight
FG-341-2020-W00231-01
September 2019
!!
!
!!
!!! ! !
! !!
!!
!! ! !
!! !
! !!
!!!!!!
!!
!!
!!
!
!!
!!
!!
!!
!!
!
!!
!!!
!!
!!
!!
!
!!!
!!
!!
!!!
!!!!!!!!!!!!!
!!
!!
!!
!
!!
!!
! !
!
!!
!
!!
!
!
! !!!
!!
! ! !!
!!
!!
!!
!!
""""
""
""
""
""
""
M organ Creek
Sout h
Lo
usignont Rd.
PRIVATE
STATE
STAT
EPR
IV ATE
Lousignont Rd.
Morgan Cre ek R d.
A
E
2G F
3
1
C
B
D4
1200
1200
800
1200
1000
9
16
8
17
20
17 16
21
LOGGING PLANFOR TIMBER SALE CONTRACT # FG-341-2020-W00231-01
HINDSIGHTPORTIONS OF SECTIONS 16 & 17, T3N, R5W, W.M.,
WASHINGTON COUNTY, OREGON
Forest Grove District GISSeptember, 2019
This product is for informational use and may not besuitable for legal, engineering, or surveying purposes.
1 inch = 1,000 feet1:12,000
0 1,000 2,000500Feet
¹APPROXIMATE NET ACRES
TRACTOR CABLETOTAL 2183
Legend! ! ! Timber Sale Boundary
ODF Ownership BoundarySurfaced RoadsUnsurfaced RoadsType-F StreamType-N StreamStream BufferCable Yarding AreaTractor Yarding Area
!! Cable Landing"" Tractor Landing
Reforested AreaSection Lines40 Foot Contour Band200 Foot Contour Band