TIF and Beyond: City Economic Development
Projects
Patricia Martin, Ahlers & Cooney, P. C.R. Mark Cory, Ahlers & Cooney, P. C.
CAVEATThis Guide is intended for general informational purposes only. Answers to legal questions about Iowa urban renewal law can vary greatly depending upon the specific facts in a given situation. Please consult an attorney.
2
Housing Incentive OptionsUrban Revitalization
Urban Renewal
Pros Cons
Tax increment is created Administration; Limited options for non-LMI housing
3
Pros Cons
County Assessor takes over administration
No tax increment is created (meaning all financial benefits go to the owner)
Easy to amend term/schedulesAttractive schedules if you can meet requirements
Burdensome to start one
Attractive schedules if:• Area is designated as blight and you
want to include single family residential• If housing is for LMI individuals/families• If building is multi-residential (3 or more
housing units and up to 75% of sq. ft. is residential)
4
• How attractive? Up to 100% for up to 10 years–Can be a smaller percentage and
smaller number of years.
5
CITY ONLY INCENTIVE AGREEMENTS
When are these useful?• Only one parcel is involved
• Mid-level projects• Or retail
How does a city get this authority? » Iowa Code section 15A.1»Must be tied to the creation or retention
of jobs 6
7
Pros Cons
NO UR Plan, no amendmentsNo UR reporting
No tax increment is created
No county or school effect because city is only accessing its own taxes
Less complex agreement
Rebates are smaller because city has access to only its taxes to rebate
Consider whether 384.24A(4) is applicable. (loan agreement procedure)
7
CITY ONLY INCENTIVE AGREEMENTS
1. Developer (Business) completes a project with an assessed value of at least X dollars. What is X? X depends on your city. It may be $500,000 for a small city and $1.0 M for a larger city or some different minimum.2. Developer (Business) either agrees to retain X jobs and/or create Y new jobs. 3. Developer (Business) enters into a short development agreement and Developer annually certifies that:
• Developer (Business) is still operating the business• Developer (Business) has paid all property taxes for this parcel (and all other commercial parcels) and • Developer (Business) has retained X employees and/or hired Y employees.
4. If so, Developer (Business) receives a % of city-only taxes or all the city taxes except the City’s debt service levy for X years.
8
LEAGUE’S “SNAPSHOT OF TAX
INCREMENT FINANCE” SAYS:
1,530 TIF Districts out of 2,528 total TIF Districts had a base year after 1995 (61%)
and
75% of those had a statutory end date
WHAT DOES THIS MEAN?
9
END OF LIFE DISCUSSION
STARTING FOR ECONOMIC DEVELOPMENT PLANS/AMENDMENTS ADOPTED
AFTER 1/1/95, THERE IS A 20 YEAR LIMITATION ON THE
COLLECTION OF TIF“If an urban renewal plan for an urban renewal area is based upon a finding that the area is
10
an economic development area and that
no part contains slum or blighted conditions,
then the division of revenue provided in section 403.19 and stated in the plan shall be limited to twenty years from the calendar year following the calendar year in which the municipality first certifies to the county auditor the amount of any loans, advances, indebtedness, or bonds which qualify for payment from the division of revenue provided in section 403.19.” Iowa Code Section 403.17(10).”
11
EXAMPLE
Question: What if the City adopted an ED plan on 1/2/95, and adopted a TIF ordinance on that entire Plan Area on 1/2/95 and the City then certified debt by 12/1/95, when is the sunset?
Answer: The last fiscal year to collect tax increment on the area within that TIF Ordinance (the entire URA) is FY 15-16. Given that we are currently in FY 14-15, that is our next fiscal year. In fact, under that scenario, if your last fiscal year to collect TIF is FY 15-16, you would have to certify by 12/1/14 to get the FY 15-16 increment.
12
First of all: The statutory limit is on the collection of tax increment within a TIF ordinance of an economic development urban renewal area.
• It is not a limit on the duration of a Plan. • It is not a limit of how long an area can be covered by a
Plan.• It is not applicable to mixed Economic Development/
Blight areas
15
OPTION: Take out the undeveloped land from the urban renewal area and create a new UR area using some or all of the undeveloped land and perhaps additional undeveloped land.
16
What have you lost?
The land you cut out gets a new stepped-up base (January 1 of the year before debt is first certified) but you may not lose much because undeveloped land will likely still have a relatively low base value.
17
When should you do this?
a) Right now
OR
b) Wait until a prospect that wants to build shows up so you don't waste your money on creating an URA that is not yet needed or contains the wrong parcels.
18
If Original Area is all developed, you don’t need to do anything.
Remember, even if you do nothing, while the ability to collect Increment expires on the Original Area.... you can still use Increment from the Amendment No. 1 Area on UR projects in the Original Area.
What if you guessed right?
How to Put Projects on the Board
19
20
Sometimes, rebate agreements do not achieve the desired results.
1. City needs to build infrastructure
2. Project requires cash “up front”
(needs, not developer wants)
3. Other unique circumstances
Which play should you run?
21
Joint efforts of City, UR counsel and bond counsel
22
384.24(3)(q)
Essential Purpose:
“aiding in the planning, undertaking, and carrying out of urban renewal projects under the authority of chapter 403… .”
23
384.24(3)(q)
1. G.O. Debt Service Levy Available
2. Requires Valid UR Purpose under Statute and UR Plan
3. Subject to 10/20 Notice and Reverse Referendum
4. May or May not Certify for TIF Reimbursement
24
403.12
1. Requires Valid UR Purpose under Statute and UR Plan
2. GO Debt Service Levy Available
3. 10/20 Reverse Referendum
4. Public Sale
5. May or May not Certify
25
384.24 (not “q” purpose)
Many times, an urban renewal project undertaking constitutes an essential purpose on its own, such as a street, water, sanitary sewer, storm sewer, sidewalk, etc.
26
384.28 allows the council to “elect” which procedures to follow “when a project or activity may be reasonably construed to be included in more than one classification” under the definitions of essential and general corporate purposes.
27
Election ConsiderationsUR Purpose
• Clear intent to treat as UR project
• Easy proof of council approval
• Less chance of dispute over reimbursement eligibility
Standard ECP Purpose
• 4/20 notice – no reverse referendum
28
403.9 Urban Renewal Revenue
1. Requires valid UR purpose under statute and plan
2. 4/20 hearing
3. No reverse referendum, but no debt service levy
4. Payable only from TIF or other project income
29
Option Plays
1. Start 403.12/384.24(3)(q) and 403.9 at same time
2. Conduct two or more ECP and or GCP purpose hearings in addition to 403.12/384.24(3)(q)
3. 403.9 and multiple G.O. Hearings
30