Installation documentation f or PAPI units PU3L Thorn Airfield Lighting Page 1 / 43 PU3L Version 6.0 (27 October 2010) Doc 2111.E INSTALLATION DOCUMENTATION for PU3L  DOC 2111.E www.ThornAirfieldLighting.com Thorn Airfield Li ghting France 156 boulevard Haussmann 75379 Paris Cedex 08 FRANCE Tel : +33 (0) 1 49 53 62 62 Fax : +33 (0) 1 49 53 62 89 [email protected]  Thorn Airfield Lighting Pty Ltd 7-9 Newcastle Road Bayswater Victoria 3153  AUSTRALIA Tel : +61 (0) 3 97 20 32 33 Fax : +61 (0) 3 97 20 82 33 [email protected] Thorn Airfield Lighting UK Ltd 11 Town Quay Wharf, Abbey Road, Barking, Essex, IG117BZ UNITED KINGDOM Tel : +44 (0) 208 594 2747 Fax : +44 (0) 208 594 2848 [email protected]  

description

THORN PAPI Lights Installation Manual

Transcript of THORN PAPI Lights Installation Manual

Page 1: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 1/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 1 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

INSTALLATION DOCUMENTATION

for PU3L  

DOC 2111.E

www.ThornAirfieldLighting.com 

Thorn Airfield Lighting France156 boulevard Haussmann75379 Paris Cedex 08FRANCE Tel : +33 (0) 1 49 53 62 62

Fax : +33 (0) 1 49 53 62 [email protected]  

Thorn Airfield Lighting Pty Ltd7-9 Newcastle RoadBayswater Victoria 3153AUSTRALIA Tel : +61 (0) 3 97 20 32 33

Fax : +61 (0) 3 97 20 82 [email protected]

Thorn Airfield Lighting UK Ltd11 Town Quay Wharf, Abbey Road,Barking, Essex, IG117BZUNITED KINGDOM Tel : +44 (0) 208 594 2747

Fax : +44 (0) 208 594 [email protected]  

Page 2: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 2/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 2 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

RECORD of CHANGE Documentation 2111.E

Revision Designation Editor Checked Date

1 First issue J MD J anuary 2000

2 Second issue J MD J uly 2000

3 Modifications (text and drawings) J MD September 2000

4 New Logo and addresses J MD SD December 2003

5New section on the use of theclinometer

FR September 2008

6 Correction on page 6 FR

Page 3: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 3/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 3 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

TABLE OF CONTENTS

1  INTRODUCTION........................................................... ................................................................ ............. 4 

1.1  USE RESTRICTION NOTICE AND WARRANTY .......................................................... ................................... 4 

1.1.1  Use of the Document................................................... ................................................................. ... 4 

1.1.2  Warranty........................................................ .................................................................... ............. 4 

1.2  SAFETY INSTRUCTIONS ......................................................... ................................................................ ... 5 

2  REFERENCE DOCUMENTS........................................................................... .......................................... 5 

3  GENERAL STATEMENTS ABOUT PAPI SYSTEM INSTALLATION.......... .................................... 6 

4  TOOLS AND ACCESSORIES REQUIRED .................................................................. ........................... 7 4.1  STANDARD TOOLS ...................................................... ............................................................... .............. 7 

4.2  SPECIAL TOOLS .......................................................... ............................................................... .............. 7 

5  INSTALLATION.................................................................................................... ...................................... 8 

5.1  CIVIL WORKS ............................................................. ............................................................... .............. 8 

5.1.1  PU3L unit possible height ................................................................. ............................................. 8  

5.1.2  Concrete plinth standard dimensions ....................................................... ...................................... 9 

5.1.3   Electrical circuits............................................................................... ........................................... 11 

5.2  I NSTALLING THE LEGS ON THE CONCRETE PLINTH............................................................ ...................... 13 

5.3  MOUNTING THE PU3L BOX ONTO THE LEGS ......................................................... ................................. 14 

5.4  ELECTRICAL CONNECTIONS ............................................................. ...................................................... 16 

5.4.1 

Connection of the secondary cables on the PU3L...................................................................... .. 16  

5.4.2  Fixing and connecting the lamps ...................................................................... ............................ 18  

5.5  ADJUSTMENT OF ELEVATION A NGLE.......................................................... ........................................... 19 

5.5.1  Use of the clinometer ................................................................... ................................................. 19 

5.5.2  Calibration procedure ................................................................. ................................................. 20 

6  INSTALLATIONS OF OPTIONAL DEVICES...................................................................... ................ 21 

6.1  I NSTALLATION OF THE TILT SWITCH ........................................................... ........................................... 21 

6.1.1   Mounting and adjustment ............................................................... .............................................. 21 

6.1.2  Cabling of the tilt switch system ............................................................... .................................... 23 

6.1.2.1  PU3L internal cabling..................... ...................... ....................... ...................... ....................... .............. 23 

6.1.2.2  PU3L external cabling.................... ...................... ....................... ...................... ....................... .............. 24 

6.1.3  Commissioning of the tilt switch system ................................................................ ....................... 29 

6.1.3.1 

 Test in normal status..................... ...................... ...................... ...................... ...................... ................. 29 

6.1.3.2   Test in normal status..................... ...................... ...................... ...................... ...................... ................. 30 

6.1.3.3  Problem occurred during commission ...................... ...................... ....................... ...................... ........ 31 

6.2  I NSTALLATION OF HEATING RESISTOR ........................................................ ........................................... 33 

6.2.1   Mounting of heating resistors and terminal plates ................................................................ ....... 33 

6.2.1.1  Mounting of heating resistors...................... ....................... ...................... ....................... ...................... 33 

6.2.1.2  Mounting the terminal plates.................... ...................... ....................... ...................... ....................... ... 34 

6.2.2  Cabling of the heating resistors.................................... ................................................................ 35 

6.2.2.1  PU3L internal cabling..................... ...................... ....................... ...................... ....................... .............. 35 

6.2.2.2  PU3L external cabling.................... ...................... ....................... ...................... ....................... .............. 36 

7  DIMENSIONS OF THE PU3L ................................................................ ................................................. 41 

Page 4: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 4/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 4 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

1 Introduction

 The documentation lists the different steps to follow in order to install thePU3L PAPI unit.

 You will find in this document two main paragraphs:

"General Information and Requirements": This chapter gives general description and use of the fittingcovered by this document.

"Installation of the fitting": This chapter describes how to maintain the fitting covered by thisdocument.

1.1 Use restriction not ice and warranty

1.1.1 Use of the Document

 This Installation documentation is the property of 

THORN Airfield Light ing 156 bd. Haussmann

75379 Paris Cedex 08France

 This documentation or any parts of this documentation may not be reproduced, stored in a retrieval

system or transmitted in any form or by any means (mechanical, photocopying, recording,electronic,…) without THORN's prior consent.

1.1.2 Warranty

THORN Airfield Lighting guarantees that the performance of the inset lights described in thisdocument, when sold by THORN Airfield Lighting or its licensed representatives, meets therequirements of ICAO Annex 14 volume 1 and FAA specification AC 150/5345-28.

Any defect in design, material or workmanship, which may occur during proper and normal use over

a period covered by the warranty stipulate in the contract, will be replaced by THORN Airfield Lightingfree of charge, ex works.

Operational failure resulting from lamp burnt out, improper installation, damage due to runwaymaintenance equipment … is not considered a result of proper use and is beyond the scope of thewarranty.

 The above constitutes the limits of THORN Airfield Lighting 's liabilities concerning the equipmentcovered by this document.

Page 5: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 5/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 5 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

1.2 Safety instructions

WARNING: Prior to the commencement of work all electrical services MUST be isolated from the

supply and connected to earth. Full details of the work involved must be given to the AuthorisePerson responsible for the electrical engineering services at the airport with regard to the duration of the work, etc.. It is recommended that prior to starting any cutting work the nature and location of services such as cable ducts, etc... should be identified. It is a prerequisite of this type of installationthat the work should be carried out by trained and experienced personnel.

2 Reference documents

 This paper refers to following documents:

• THORN Commercial Documentation General Brochure Doc 1001.E,

• THORN PU3L Commercial Documentation Doc 1111.E,

• Last Edition of ICAO Annex 14 Edition of J uly 1995,

• Last Edition of FAA Advisory Circular AC 150/5345-28.

Page 6: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 6/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 6 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

3 General statements about PAPI System Installation

 The first step of PAPI System installation is the calculation required to accurately locate thepositionning of the units relative to the runway threshold and the runway edge. The distance from thethreshold will be determine by the largest aircraft to use the runway, the height of the aircraft wheelsover the threshold, possible obstacles in approach zone, accordance with ILS System…For more details concerning this calculation please se the Paragraph 8.4 of the Part 4 of ICAOAerodrome Design Manual

Once the above distance has been calculated the PAPI position are given as follows :

Fig 1 : LOCATION OF PAPI RELATIVE TO RUNWAY EDGE

 The PU3L is mounted on three legs, each comprising a tripod stand, frangible coupling and analuminium tube, the length of which has to be determined at the time of installation. The final length of the tubes will depend upon the individual heights of the PAPI units, these heights being dependentupon local ground conditions etc.. On the centre of each PAPI body is a datum point which can beused to ensure that all of the units are the same level. Please note that the PAPI units should be

mounted as low as possible.

 The tube supplied are 60 mm diameter and 400 mm long. Please note that92 mm of tube is placedinside the frangible coupling and this must be allowed for in calculating the required length.

Page 7: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 7/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 7 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

4 Tools and accessories required

4.1 Standard Tools

• Two open end wrench of 22 mm.

• One 22 mm box spanner / socket.

• Two open end wrench of 17 mm.

• One 8 mm box spanner / socket.

• One small flat screwdriver

• One brush or cloth

• One spirit level

4.2 Special Tools

• One set of adjustment tools (supplied in a little case).

Note : Standard surveyors equipment shall be also required to determine the location of the foundation blocks etc..

• One multimeter (for Tilt Switch Installation).

Page 8: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 8/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 8 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5 Installation

5.1 Civil Works

5.1.1 PU3L unit possible height

In order to help you to fix the topographic heights of the top of the concrete plinth dedicated tosupport the four PU3L Unit of the PAPI. Please take into account the following data (See Fig 2) :

1) The Threaded Rods of the three Legs permit an maximum vertical adjustmentof 55 mm.

2)  The Maximum possible distance between the top of Concrete Block andthe Bottom of the PU3L Box is 570 mm (on the Front Legs).

3)  The Minimum possible distance between the top of Concrete Block and

the Bottom of the PU3L Box is 300 mm (on the Rear Legs).

Fig 2 : MAXIMUM AND MINIMUM HEIGHT OF PU3L

Page 9: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 9/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 9 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.1.2 Concrete plinth standard dimensions

Once the location of the foundations for the PAPI units have been determined, each of the units willneed to have a concrete plinth constructed as per the dimensions given in Fig.3.

Note : These dimensions are minimum requirements suitable for compacted and stabilisedground and may need to be increased due to local conditions. Ideally, the concrete plinths shouldbe level with the ground, however, the requirements for chamfered edges should be bourn inmind.

 Three sets of three sealing rods with M10 threads (one per tripod base) may be fixed into theconcrete whilst wet, alternatively, the use of rawl bolts is recommended.

We would also recommend that a conduit elbow tube be placed in the concrete plinth for thesecondary AGL cables.

Page 10: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 10/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 10 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

Fig 3 : STANDARD SIZES OF THE CONCRETE PLINTH

Page 11: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 11/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 11 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.1.3 Electrical circui ts

Manholes and conduits dedicated to receive respectively Isolating Transformers and Power supplyCables (Primary and Secondary) must also be supplied and installed into the ground to shelter theequipment used to power supplied the PAPI System.

Manholes and conduits characteristics are function of local needs (type of soil, type of climate, etc…).Nevertheless we can give as an example the great following statements (See Fig 4 and Fig 5) : Useone Manhole (A) for 2 PU3L Units (=>2 Manholes for one PAPI System), Minimise the length of theconduit (B) dedicated to lead the secondary cables (= minimise the distance between the Manhole(A) and the concrete block (C) which support the PU3L Unit), Use one conduits (D) network for eachindependent Primary circuits used for Power supplied the PAPI System (the use of only one or twoindependent circuits is possible).

Fig 4 : MANHOLE AND CONDUITS (I)

Page 12: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 12/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 12 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

Fig 5 : MANHOLE AND CONDUITS (II)

Page 13: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 13/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 13 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.2 Installing the legs on the concrete plinth

FOR EACH LEG

 A) Mount the Tripod Stand (B) on theSealing Rods (A).

B) Fix the Tripod Stand (B). Using an openspanner n° 10, screw and lock three M10nuts (C) on the three Sealing Rods (A).

C) Use a 55 mm open ended spanner to fixthe Frangible Coupler (D) to the TripodStand (B).

D) Mount The Tube of the Leg (E) in theFrangible Coupling (D). The Tube Must bepreviously cut to obtain the requestedheight (See paragraph 3.).Please note that the maximum amount of 

adjustment with the threaded Rods (H) is55 mm.

- Minimum distance between the plinthand the Base of the PU3L= 260 mm (on the rear Leg)

- Maximum distance between the plinthand the base of the PU3L Box

= 570 mm (on the Front Legs)

E) Use a spirit level (J) and a open ended,10 mm spanner to set the tube (E) “Vertically” in the Frangible Coupling (D),adjusting the six fixing screws (F) to suit.

F) Then tightening the six Locknuts (G)

G) Place the lower locknut (I) on the Threaded Rod (H).

H) Screw the threaded Rod (H) into

position in the Tube (E).Note : A minimum of 25 mm is requiredto be inserted.

I) When the Rod is correctly positionedtighten the lower Locknut (I).

Page 14: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 14/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 14 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.3 Mounting the PU3L box onto the legs

FOR EACH LEG

 A) Screw the Upper Locknut (B) on the Threaded Rod of the Leg (A) about 20 mmbelow its final Position.

B) Screw the Fixing Nut (C) on the Threaded Rod (A) about its final fixingposition (height h above the ConcretePlinth.

C) Place the Lower Fixing Washer (D) onthe Threaded Rod (A). 

D) Place the first part of lower Knee J oint(E) on the Threaded Rod (A). 

E) Place the Second part of lower Knee J oint (F) on the Threaded Rod (A). 

REMOVE THE PU3L COVER

 A) Opening the Three catches (A). * the catches are of the locking type anda stab (B) needs to be press before thecatch will open.

Note : The locking Part of thecatches is use to secure the closing.If you forget to push on it you willnever be able to open the Catches.Don’t force on the Catches you candamage it.

B) Lock the three catches in the uprightposition 

C) Remove the PU3L Cover

Page 15: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 15/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 15 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

INSTALL THE PU3L BASE PLATE

ON THE THREE LEGS

 A) Having remove the Cover (A) of thePU3L.

B) Place the Base Plate (B) on the ThreeLegs (C).

FOR EACH LEG

 A) Place the upper Knee J oint (F) on the Threaded Rod (A). 

B) Mount the top part of the Knee J oint (E) on the Threaded Rod (A). 

C) Mount the Upper Fixing Washer (D) onthe Threaded Rod (A). 

D) Screw the PU3L Fixing Nut (C) on the Threaded Rod of the Leg (A). Do nottighten it at this stage.

E) Screw the PU3L Locknut (B) on the Threaded Rod (A) about 10 mm over thefixing Nut (C).

Page 16: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 16/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 16 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.4 Electrical connections

5.4.1 Connection of the secondary cables on the PU3L

Note : On the four legs of PU3L the connection of Secondary cables must be done usingCompression Packers marked (1), (2) and (3) in the drawing (the Compression Packer (4) is notused). For PU3L equipped with two lamps only Compression Packer marked (2) and (3) are used.

Page 17: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 17/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 17 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

FOR EACH CABLE

 A) Unscrew and Remove the Lower Nut(C) of the Compression Packer (A).

B) Remove the Plug (D) from the LowerNut (C) of the Compression Packer (A).

Note : all the unused cable entries musthave the blanking plug left in situ inorder to maintain IP rating of the unit.

C) Pass the Secondary Cable (F) - Through the Compression PackerLower Nuts (C),- Then through the CompressionPacker Gasket (E),- And through the Compression PackerBody (B).

D) Pull the Secondary Cable about 15 cminto the box

E) Strip back the outer sheath of the cableby approx. 20 mm.

F) bare the cables cores for a distance of about 10 mm.

G) Connect the two cable cores to thePU3L dedicated Terminal (Twoconnections par secondary cable).

H) Pull back the Cable to leave theminimum amount inside the unit.

I) Reassemble the Compression Packer

Body (B) and tighten to suit.

Page 18: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 18/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 18 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.4.2 Fixing and connecting the lamps

FOR EACH LAMP

 A) Open the lamp retaining spring (A).

B) Install the Lamp (C) in Lamp Holder (B).Note : Ensure that the indentations inthe Lamp Holder line up with those inthe Pk30d Lamp (See (D)).

C) Close the lamp retaining Spring (A).

D) Connect the Two Lamp Leads to theappropriate terminals (F) inside the PU3L.

Page 19: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 19/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 19 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.5 Adjustment of Elevation Angle

At this stage the PU3L PAPI Units has been :

- Installed on their Concrete plinths.- Equipped of secondary Cables (two or three).- Equipped with Lamps (two or three).

 The final stage of the installation process is to set the elevation angles of the Units.

Note : The angle of approach on the typical airf ield is normally 3 degrees,however , this has to be verified with the client and the local Aviation Authori ty. The standard angular displacement between each uni t is 20

minutes of arc.For a 3 degree approach this would give the unit closest to the runway asetting of 3°30’, the next 3°10’, the next 2°50’ and the last one 2°30’.

5.5.1 Use of the clinometer 

Degreeson this line

Minutes onthis line

 The 0 of the line of the spirit level is in regard of the first division after the 3°. As one division on thebody line is 15 minutes, the clinometer is adjusted to 3° and 15minutes. If you want to adjust to 3°and 20 minutes, you have to add 5 minute. The line for the minute is fixed on the spirit level, so youneed to adjust the division n°5 in regards with the next division on the body line Then you get 3°+15

‘+5’=3° 20‘. Secure the position by the brake under the spirit level.

Page 20: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 20/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 20 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

5.5.2 Calibration procedure

SETTING UP THE TWO SPECIAL ALIGNMENT TOOLS

 A) Position the Spirit Level over the FrontLegs of the PU3L on the dedicatedreference point (A).

B) Set and Lock the required ElevationAngle on the Clinometer by moving thespirit level on the body of the tool. Adjustthe 0 on the spirit level line with the divisionyou need on the line of the body.

C) Position the Clinometer near the rear

Leg on the dedicated reference point (B).

 ADJUSTEMENT OF PU3L

 A) If Necessary, Using The lower FixingNuts (A), adjust the height ‘h ’ of the PU3LBase Plate. Do not tighten it at this stage.

B) Adjust the front legs fixing nuts (A),whilst observing the spirit level, to set thefront of the unit horizontal and level. Do nottighten it at this stage.

C) Adjust the rear leg fixing nuts (B), whilstobserving clinometer, to set the requiredangle of the unit. Do not tighten it at thisstage.

D) Tighten the Upper Fixing Nuts (C) of thethree Legs. After ensuring that the anglesetting have not changed.

* Correct the adjustment if necessary.

E) Tighten the locknuts (D) (Upper andLower) of the three legs to fix in place.

F) Remove the Spirit Level and theClinometer and store them in the Alignment Tools Case.

G) Replace the PU3L Cover and Close the Three Catches.

Page 21: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 21/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 21 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

Now the PAPI Unit PU3L is operational. When the 4 Units of aPAPI System are all operational the System itself is operational

and then could be put in service and use.

Page 22: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 22/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 22 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6 Installations of opt ional devices

As all the PU3L Units are delivered without lamps and any optional devices (Tilt Switch and HeatingResistors), you must install yourself the corresponding devices in the PU3L unit if you want toimplement the corresponding optional function.

6.1 Installation of the tilt switch

 The Tilt Switch system is composed of four Tilt Switch devices (One “Master Tilt Switch” Unit andthree “Slave Tilt Switch” Units mounted in the corresponding PU3L (one became the Master and thethree other became Slaves) linked together by Cables. The installation of aTilt Switch System can bemade in three main operations :

1) Mechanical Mount ing and Adjustment of the Devices

in the PU3L Units

2) Wiring of the System

3) Commissioning of the Whole System.

6.1.1 Mounting and adjustment

 The first operation to do is to mount and adjust the four Tilt switch Devices in the corresponding fourPU3L.

MOUNTING

FOUR EACH PU3L UNITS

 A) Remove the Cover of the PU3L (seeParagraph 5.3.).

B) Using the Two Fixing Holes (D) locatedon the PU3L Base Plate ( A) and the twoFixing Screw (C) located on the Tilt Switch

Devices (B), fix and lock the Tilt SwitchDevice on the PU3L Base Plate.

Note :a) One of the three PU3L Units mustbe equipped with The “Master” TiltSwitch Device and the three otherwith “Slave” Tilt Switch devices. You can recognise the “Master” Tilt

Switch Devices because it is the onlyone equipped with Power Supplyand Control Module (=Big Modulelocated under the Tilt Switch Device.

Page 23: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 23/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 23 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

b) Following the design of the AFLcircuits and what is more convenient

for you (see Paragraph 6.1.2.2.2.). You can install “Master” Tilt Switchdevice in the first or in the last(starting from the runway edge)PU3L Unit of the PAPI System.

MASTER SLAVE

 ADJUSTMENT

FOUR EACH PU3L UNITS

 A) Put the Spirit Level use in Paragraph5.5 on the Plate of the Tilt Switch Devicewhich support the two Mercury Contact in( A).

B) Using the Adjustment screw (B) andlooking at the Spirit Level set Horizontallythe Plate of the Tilt Switch Device whichsupport the two Mercury Contact.

C) Verify that the Mercury Contact areClosed.

* For “Master” PU3L Unit, using anOhmmeter Verify that Connection 13 of the Tilt Switch Device Main Terminaland Connection 1 of the Mercury

Contact Terminal are short circuited.

* For “Slave” PU3L Units, using anOhmmeter Verify that Connection 3 and13 of the Tilt Switch Device Main Terminal are short circuited. 

D) If necessary put back in place the PU3LCover.

Page 24: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 24/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 24 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2 Cabling of the til t swi tch system

After Mounting and adjustment of the four Tilt Switch Devices in the four PU3L Unit, the nextoperation is to make the electrical cabling over the system. This cabling operations are divided in twoseparate steps : Cabling internal to PU3L Units and Cabling External to PU3L Units.

6.1.2.1 PU3L internal cabling

 This operation Permit to connect the Contacts of the relay dedicated to short circuit the lamps (whenat least one of the PU3L Unit is miss-adjusted) to the two poles of each lamps.All the Tilt Switch Devices are delivered equipped with one set of three two pole cable each onededicated to be connected to one lamp.

PU3L INTERNAL CABLING

FOUR EACH PU3L UNITS

 A) If necessary Remove the Cover of thePU3L (see Paragraph 5.3.).

B) Depending of the number of lamps of your PU3L Connect 2 or 3 cables (B)of the Tilt Switch Device to the dedicatedConnections of the PU3L Main Terminal( A).

Note : the Connection corresponding tothe lamps are marked on the PU3Lbase Plate casting.

* L1 for Lamp 1* L2 for Lamp 2* L3 for Lamp 3

C) If necessary put Back in place the PU3LCover.

Page 25: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 25/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 25 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2.2 PU3L external cabling

6.1.2.2.1 Passing a cable through a compression packer  

Concerning connection of cables coming from out of the PU3L Units the first step is always to passthe corresponding cables through the Compression Packers.

FOR EACH CABLE TO CONNECT

 A) Unscrew and Remove the Lower Nut(C) of the Compression Packer (A).

B) Remove the Plug (D) from the LowerNut (C) of the Compression Packer (A).

Note : all the unused cable entries musthave the blanking plug left in situ inorder to maintain IP rating of the unit.

C) Pass the corresponding Cable (F) - Through the Compression PackerLower Nuts (C),- Then through the CompressionPacker Gasket (E),- And through the Compression PackerBody (B).

D) Pull the corresponding Cable about 20cm into the box

E) Strip back the outer sheath of the cableby approx. 20 mm.

F) Bare the cables cores for a distance of about 10 mm.

G) Connect the cable cores to the tiltSwitch Device dedicated terminal (seeParagraph 6.2.2.2.2.2.).

H) Pull back the Cable to leave theminimum amount inside the unit.

I) Reassemble the Compression PackerBody (B) and tighten to suit.

Page 26: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 26/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 26 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2.2.2 Connections on tilt switch device main terminal 

 The wiring overview drawing below shows the different electrical connections necessary on a PAPIsystem with Tilt Switch option equipped of PU3L Units.

WIRING OVERVIEW

1. Isolating Transformer for the lamps 5. Heating Resistors Supply 230 Vac (Option)2. Isolating Transformer for the Supply 6. Alarm Feed Back Cable (Option)

of the ”Master” Tilt Switch devices 7. Cable for - Mercury contacts Loop

3. Primary Cable - Relays Supply (+12 Vdc)

4. Secondary Cable - Heating Resistors Supply (Option)

Page 27: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 27/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 27 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2.2.2.1 Compression packers correspondence

Find here after the correspondence between Functions (Master Tilt Switch Device Supply 6.6 A,Alarm Feed Back Signal, Heating Resistor Supply, Mercury contacts Loop, Relays Supply) andCompression Packers.

MASTER PU3L UNIT 

1. Master Tilt Switch Device Supply (2.8 to 6.6 A)

2. Alarm Feed Back Signal (Dry Contact)

3. Heating Resistor Supply (Option) = 230 Vac

4. Control “Out” = Mercury Contacts Loop

+ Relays Supply (+12 Vdc)

+ Heating Resistors Supply 230 Vac (Option)

SLAVE PU3L UNIT 

1. Not Used

2. Not Used

3. Control “In” = Mercury Contacts Loop

+ Relays Supply (+12 Vdc)

+ Heating Resistors Supply 230 Vac (Option)

4. Control “Out” = Mercury Contacts Loop

+ Relay Supply (+12 Vdc)

+ Heating Resistors Supply 230 Vac (Option)

Page 28: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 28/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 28 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2.2.2.2 Main terminal connections correspondence

Find here after the correspondence between Functions (Master Tilt Switch Device Supply 6.6 A,Alarm Feed Back Signal, Heating Resistor Supply, Mercury contacts Loop) and Connection on the TiltSwitch Device Main Terminal.

MASTER PU3L UNIT 

1 and 2 Master Tilt Switch Device Supply (2.8 to 6.6 A), Input3 and 4 Alarm Feed Back Signal, Internal Dry Contact (Option)

5 and 6 Heating Resistors Supply “In” (Option) 230 V, Input

11 and 12 Relays Supply (+12 Vdc), Output

13 and 14 Mercury Contacts Loop, Output

15 and 16 Heating Resistors Supply ”Out” (Option) 230 V, Output

SLAVE PU3L UNIT 

1 and 2 Relays Supply (+12 Vdc), Input

3 and 4 Mercury Contacts Loop, Input

5 and 6 Heating Resistors Supply “In” (Option) 230 V, Input

11 and 12 Relays Supply (+12 Vdc), Output13 and 14 Mercury Contacts Loop, Output

15 and 16 Heating Resistors Supply ”Out” (Option) 230 V, Output

Page 29: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 29/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 29 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.2.2.2.3 Connections between PU3L units

Find here after the wiring you have to make on and between the Main Terminals of the Tilt SwitchDevice of PU3L for the commissioning of the Tilt Switch function on the PAPI System.

Connection BetweenMaster PU3L Unit and the First Slave PU3L Unit

MASTER TERMINAL FIRST SLAVE TERMINAL

1. Master Tilt Switch Device Supply 3. Heating Resistors Supply (Option)

2. Alarm Feed Back Signal (Option) A . Optional Wires 

Connection Between

First Slave PU3L Unit and the Second Slave PU3L Unit

FIRST SLAVE TERMINAL SECOND SLAVE TERMINAL

A . Optional Wires only for Heating Resistors supply 

Page 30: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 30/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 30 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

Connection Between

Second Slave PU3L Unit and the Last Slave PU3L Unit

SECOND SLAVE TERMINAL LAST SLAVE TERMINAL

1. Jumper (Absolutely necessary to Close the Mercury Contacts Loop)A . Optional Wires only for Heating Resistors supply 

6.1.3 Commissioning of the tilt switch system

After Mounting and Adjustment of the all Tilt Switch Devices in the PU3L Unit and after wiring of the

whole System, you have to Commission the Tilt Switch System. During this commissioning you haveto test either the “Normal Status” or the “Default Status”.

6.1.3.1 Test in normal status

1) Power On the PAPI System (Supply the Corresponding AFL loop(s) with in Current with TRMSValue From 2.8 to 6.6 Amps.2) Control that all the PU3L Units of the PAPI System is light on and operational.3) Remove the Cover of the PU3L Master Unit, and Control the Following things.

 A) Control the status of the three LEDs of the Tilt Switch Device (See Drawing here after).* The Red LED (1) showing that the Power Supply Module supply 12 Vdc

is light on.* The Green LED (2) Showing that the Mercury Contacts Loop is Closedis Light on.

* The Red LED (3) Showing that the Mercury Contacts Loop is open is Light off .4) With an Ohmmeter, verify that the Dry Contact of the ”Alarm” Feed Back information is open(meaning PAPI System in Serviceable). Make the measurement between the connections 3 and 4 of the Master Tilt Switch Device Main Terminal.

Page 31: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 31/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 31 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.1.3.2 Test in normal status

1) Now Push Down the Plate Supporting the Mercury Contacts In ( A)(see Drawing here after). 

2) Wait 5 seconds.3) Verify that all the PU3L Unit Light off. 4) Control the Following things.

 A) Control the status of the three LEDs of the Tilt Switch Device.* The Red LED (1) showing that the Power Supply Module supply 12 Vdc

is light on.* The Green LED (2) Showing that the Mercury Contacts Loop is Closed

is Light off .* The Red LED (3) Showing that the Mercury Contacts Loop is open is Light on.

5) With an Ohmmeter, verify that the Dry Contact of the ”Alarm” Feed Back information is Close(meaning PAPI System is “Out Off Service” on miss-alignment). Make the measurement betweenthe connections 3 and 4 of the Master Tilt Switch Device Main Terminal.6) Stop to push Down the Plate Supporting the Mercury Level. 7) Wait 5 seconds.8) Control that now all the PU3L Units of the PAPI System is light on and operational.

Page 32: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 32/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 32 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

9) Repeat Three time the test (from 1) to 7)) creating the default separately on the three “Salve”PU3L Unit 

 A) Remove the cover and create the Default describe in 1) on the corresponding Slave PU3LUnit.B) Control the status of the three LEDs of the Master PU3L like in 4) A).C) Put Back in place the Cover of the corresponding PU3L Unit.D) Test the next Slave PU3L Unit.

When Default Status have been tested on the four PU3L Units with successyour Tilt Switch System is consider as operational.

6.1.3.3 Problem occurred during commission

6.1.3.3.1 The PAPI system is light off when it is power on 

1) Verify the PAPI AFL Loop(s) are Powered On with a TRMS value of at least 2.8 Amps.

2) Remove the covers of all the PU3L

3) Control the status of the three LEDs of the Master Tilt Switch Device.

 A) The Red LED (1) showing that the Power Supply Module supply 12 Vdcmust be light “On”.

* LED light Off means that the Control and Supply Module doesn’t supply the 12 Vdc to allthe relays and by default all the lamps are short Circuited.

- Verify that the Master Tilt Switch Module is Supplied (2.8 to 6.6 amps). If it is the casechange the Master Tilt Switch Module and restart the commissioning.

B) The Green LED (2) Showing that the Mercury Contacts Loop is Closed must be Light “On”.* LED light Off means that the Mercury Contacts Loop is Open somewhere. Find where the

loop is open, correct the problem and restart the commissioning.- To find where the Loop is open do as follow :

a) Power Off the PAPI System.b) Open the loop on the PU3L Master Unit. Disconnect the wire Connected to the

connections 13 and 14 of the Master Tilt Switch Device Main Terminal.

Page 33: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 33/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 33 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

c) With an Ohmmeter tested the Mercury Contacts Loop. Verify that the loop is closed(Make Measurement on the wires disconnected in c).

. If the loop is Closed the Problem came from the Master Tilt Switch Device. Test

again that the “Master” Mercury Contacts are Closed.If it is not the case Adjust it again and restart the commissioning .Otherwise Change the Master Tilt Switch Device.

d) If the loop is Open, find where the loop is Open. To do this operate as follow :1) Go to the First Slave PU3L and measure the Mercury Contacts Loop on the TiltSwitch Device Main Terminal. Make measurement between the connections 2 and3 of the Main Terminal.

If the loop is closed. The problem is located on the Wiring between ActualPU3L and the Previous one (here between the Master and the First Slave).Find and Correct it, then restart the * commissioning.If the loop is Open. Test the Mercury Contacts of the Actual PU3L (here theFirst Slave PU3L). Make measurement between the connections 3 and 13 of the Main Terminal. If the Mercury Contacts are Open the problem is located on

Mercury Contacts Plate. Find and Correct it ( make again the adjustment), thenrestart the * commissioning.

2) If the Problem is not located on the First Slave do the same operations than in1) on the Second Slave PU3L.3) If the Problem is not located on the second Slave do the same operations thanin1) on the Last Slave PU3L.

* Before restarting the commissioning don’t forget to reconnect the correspondingwires on the connections 2 and 3 of the Main Terminal of the Master Tilt SwitchDevice and put back in place the covers of the four PU3L.

6.1.3.3.2 Some PU3L of the PAPI system remain light of f  

1) Remove the covers of all the PU3L.

2) With a Voltmeter Verify the distribution on the System of the 12 Vdc dedicated to open the “ShortCircuit Relay”.

 A) On the first “Light Off” Slaves PU3L (starting from the Master)* Verify the Input 12 Vdc. Make measurement between the connections 1 and 2 of the TiltSwitch Device Main Terminal.

- If the 12 Vdc is not present. The problem is located on the Wiring between ActualPU3L and the Previous one. Find and Correct it, then restart the commissioning.

* Otherwise verify the output 12 Vdc. Make measurement between the connections 11 and12 of the Tilt Switch Device Main Terminal.

- If the 12 Vdc is not present. The problem is located inside the PU3L. Find and Correct

it, then restart the commissioning.3) Put Back in place the Covers on all the PU3L.

Page 34: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 34/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 34 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2 Installation of heating resistor For use in cold or wet areas the PU3L unit could be equipped as an option with one special HeatingResistor. This Heating Resistor must be supplied in 230 Vac (this option need a dedicated supplywiring). The installation of Heating Resistors on a PAPI System is made in two main operations :

1) Mechanical Mounting in the PU3L Units

2) Wiring

6.2.1 Mounting of heating resistors and terminal plates

 The first operation to do is to mount one Heating Resistor and one Terminal Plate in the four PU3L of the PAPI System.

6.2.1.1 Mounting of heating resistors

MOUNTING OF

HEATING RESISTOR

FOUR EACH PU3L UNITS

 A) Remove the Cover of the PU3L (seeParagraph 5.3.).

B) Using the Two set of fixing screw (D)and nut (E), fix the Heating Resistor (B)and its two Radiators (C) on theSeparating Screen ( A) of the PU3L.

C) If necessary put back in place the PU3L

cover.

Page 35: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 35/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 35 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.1.2 Mounting the terminal plates

 The connections of the Heating Resistors with external wiring are done using Terminals Mounted onPlates that you have also to mount in the PU3L Units.

Note : If your PU3L is also equipped with the Optional Tilt switch System. The connection of theHeating Resistors are done on the Main Terminal of the Tilt Switch Devices. In this case seeprevious chapter for the mechanical installation of the Tilt Switch Devices.

If your PU3L is not equipped with the Optional Tilt switch System. You have to install special TerminalPlates in all the PU3L.

MOUNTING OF

TERMINAL PLATES

FOUR EACH PU3L UNITS

 A) Remove, if necessary, the Cover of thePU3L (see Paragraph 5.3.).

B) Using the Two Fixing Holes (D) locatedon the PU3L Base Plate ( A) and the twoFixing Screw (C) located on the TerminalPlate (B), fix and lock the Terminal Plateon the PU3L Base Plate.

Page 36: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 36/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 36 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2 Cabling of the heating resistors

 The second operation to do is to make the electrical cabling over the PAPI system This cablingoperations are divided in two separate steps : Cabling internal to PU3L Units and Cabling External toPU3L Units.

6.2.2.1 PU3L internal cabling

 This operation permit to connect the two poles of the heating Resistor to the Main Terminal of the Terminal Plate or of the Tilt Switch Device.

PU3L INTERNAL CABLING

FOUR EACH PU3L UNITS

 A) If necessary Remove the Cover of thePU3L (see Paragraph 5.3.).

B) Pass the Resistor two Wires under theReflector Holder ( A), under the TerminalPlate (or Tilt Switch Device) (B). Thenconnect them to the Connections 15 and16 of the main Terminal.

C) If necessary put Back in place the PU3LCover.

Page 37: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 37/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 37 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2.2 PU3L external cabling

6.2.2.2.1 Passing a Cable Through a Compression Packer  

Concerning connection of cables coming from out of the PU3L Units the first step is always to passthe corresponding cables through the Compression Packers.

FOR EACH CABLE TO CONNECT

 A) Unscrew and Remove the Lower Nut(C) of the Compression Packer (A).

B) Remove the Plug (D) from the LowerNut (C) of the Compression Packer (A).Note : all the unused cable entries musthave the blanking plug left in situ inorder to maintain IP rating of the unit.

C) Pass the Cable (F) - Through the Compression PackerLower Nuts (C),- Then through the CompressionPacker Gasket (E),- And through the Compression PackerBody (B).

D) Pull the Cable about 20 cm into the box

E) Strip back the outer sheath of the cableby approx. 20 mm.

F) Bare the cables two cores for a distanceof about 10 mm.

G) Connect the cable two cores to the Terminal Plate dedicated terminal (seenext Paragraph).

H) Pull back the Cable to leave theminimum amount inside the unit.

I) Reassemble the Compression PackerBody (B) and tighten to suit.

Page 38: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 38/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 38 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2.2.2 Connections on main terminal 

 The wiring overview drawing below shows the different electrical connections necessary on PAPIsystem without Tilt Switch using PU3L Units equipped with Heating Resistors (=Distribution of 230Vac Power Supply). For System Equipped of Tilt Switch see previous Chapter.

WIRING OVERVIEW

1. Isolating Transformer for the lamps 4. Heating Resistors Supply 230 Vac

2. Primary Cable 5. Cables for Heating Resistors Supply3. Secondary Cable

Page 39: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 39/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 39 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2.2.2.1 Compression packers correspondence

Find here after the correspondence between Functions (Heating Resistors Supply Input and HeatingResistors Supply Output ) and Compression Packers.

1. Not Use

2. Not Use3. Heating Resistors Supply “In” = 230 Vac

4. Heating Resistors Supply “Out” = 230 Vac

Page 40: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 40/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 40 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2.2.2.2 Main terminal connections correspondence

Find here after the correspondence between Functions (Heating Resistors Supply Input and HeatingResistors Supply Output ) and Connection on Terminal of the Terminal Plate.

1 and 2 Not Use

3 and 4 Not Use

5 and 6 Heating Resistors Supply “In” 230 V, Input

11 and 12 Not Use

13 and 14 Not Use

15 and 16 Heating Resistors Supply ”Out” 230 V, Output

Page 41: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 41/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 41 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

6.2.2.2.2.3 Connections between PU3L units

Find here after the wiring you have to make on and between the Main Terminals of the Main TerminalPlate for Installation of Heating Resistors on the PAPI System.

Connection BetweenPU3L Unit n° 1 and the PU3L Unit n°2

PU3L n°1 TERMINAL PU3L n°2 TERMINAL

1. Heating Resistors Supply

Connection BetweenPU3L Unit n° 2 and the PU3L Unit n°3

PU3L n°2 TERMINAL PU3L n°3 TERMINAL

Connection BetweenPU3L Unit n° 3 and the PU3L Unit n°4

PU3L n°3 TERMINAL PU3L n°4 TERMINAL

Page 42: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 42/43

Installation documentation for PAPI units PU3L 

©Thorn Airfield Lighting Page 42 / 43 PU3L

Version 6.0 (27 October 2010) Doc 2111.E

7 Dimensions of the PU3L

Page 43: THORN PAPI Lights Installation Manual

7/16/2019 THORN PAPI Lights Installation Manual

http://slidepdf.com/reader/full/thorn-papi-lights-installation-manual 43/43

Installation documentation for PAPI units PU3L 

COMMENTS

Last page left blank for user comments.