Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug...

38

Transcript of Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug...

Page 1: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

 

Page 2: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-1

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

National Solidarity Program – Third Party Monitoring Monthly Summary – March 2015 1. Inspections International Relief & Development (IRD) engineers conducted Third Party Monitoring (TPM) inspections of 60 National Solidarity Program (NSP) projects in March, consisting of 55 construction projects, and financial monitoring of five Provincial Management Units (PMU). This month’s financial monitoring took place in the provinces of Farah, Faryab, Ghor, Hilmand, and Paktika. Construction inspections were conducted in the provinces of Badghis, Baghlan, Bamyan, Hirat, Jawzjan, Kabul, Kandahar, Kapisa, Khost, Kunar, Kunduz, Laghman, Logar, Nangarhar, Nimroz, Parwan, Sar-e-Pul, and Takhar. NSP construction projects inspected in March fell within six sectors: education, irrigation, power, rural development, transportation, and water supply and sanitation. Construction was complete at 18 of the sites inspected this month and ongoing at 35; another two projects were graded for design only because their proposal was approved but physical work had not yet commenced. Among inspected projects currently under construction, progress varied from 40-98%. (Figures 1 through 3) 

Figure 1: NSP TPM project inspections, March 2015

Page 3: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-2

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

 

Province

Inspections by Sector

PMU

Financial Monitoring

Total Education

Irrigation

Power

Rural

Development

Transportation

Water Supply & Sanitation

Badghis 2 1 3 Baghlan 1 1 Bamyan 1 2 1 4 Farah 1 1 Faryab 1 1 Ghor 1 1

Hilmand 1 1 Hirat 1 3 4

Jawzjan 1 2 3 Kabul 1 1 2

Kandahar 2 1 3 Kapisa 1 1 1 3 Khost 1 1 Kunar 2 1 2 5

Kunduz 2 1 2 5 Laghman 2 1 1 1 5

Logar 2 1 1 4 Nangarhar 3 1 2 6

Nimroz 1 1 Paktika 1 1 Parwan 2 2

Sar-e-Pul 2 2 Takhar 1 1 Total 5 8 2 16 14 9 5 60

IRD’s Year IV work plan dictates that 800 site visits will be conducted throughouth the year. Among these, 732 will be subprojects of CDCs that have received or are going to receive a second block grant under NSP III, and the remaining 68 will be financial monitoring of PMUs (each PMU will be inspected twice). Of the 60 inspections conducted in March, 55 were NSP IIIB subprojects, and five were PMUs that were all inspected for the first time.

0

1

2

3

4

5

6

3

1

4

1 1 1 1

4

3

2

3 3

1

5 5 5

4

6

1 1

2 2

1

Inspections by Province

Figure 3: NSP TPM inspections by province and sector, March 2015

Figure 2: NSP TPM inspections by province, March 2015

Page 4: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-3

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

2. Findings 2.1 Construction Monitoring IRD grades all construction projects in three categories - material quality, workmanship quality, and design quality – using a scale of 1 to 5 (1-very poor, 2-poor, 3-average, 4-good, 5-very good). Completed projects are additionally graded in a fourth category - maintenance quality - using the same 5-point scale. The grading system is further defined in Annex A. Excluding maintenance, which was only assessed on the 18 completed projects, the average overall grade of the 55 construction sites inspected in March was 3.54 exclusive of two sites where construction activities had not begun. Broken down by category, the average grade for materials was 3.54, workmanship 3.48, and design 3.62. The 18 completed projects, which were additionally graded for maintenance, had an average score of 3.01 in this fourth category. Thirty-five of the 37 incomplete projects had a written operations and maintenance (O&M) plan. Of those CDCs without a formal O&M plan, none of them had a functional maintenance mechanism in place. Four projects inspected in March achieved grades higher than 4.00, two were rated 4.00, 44 were above average overall (higher than 3.00 but less than 4.00), one was average (3.00), and four were below average (<3.00). Four projects were graded above 4.00 in quality of materials, seven were graded 4.00, 35 were above average, three average, and two were too early to evaluate. With regards to workmanship, three projects achieved above 4.00, four were graded 4.00, 38 projects were graded above average, four average, four below average, and two at too early a stage to evaluate. For design quality, one was graded above 4.00, 15 were rated 4.00, 30 were above average, seven average, and two below average. Of the 18 completed construction projects that received a maintenance grade, one was graded 4.00, five above average, eight average, and four were below average. This month, no projects were found to have completely failed due to a lack of maintenance or other deficiencies. A complete list of project grades is provided in Annex B. Of the six projects graded 4.00 or above in March, three were school buildings, one canal, and one protection wall; one of these six, the protection wall, was graded for design only as construciton had not yet begun. The 44 projects graded above average included one canal, 14 community centers, five culverts, four water wells, one footbridge, one micro hydro power plant, four pathways, seven protection/retaining walls, one school boundary wall, two tertiary roads, three water supply netowrks, one irrigation water reservoir, and one hand pump installation (graded for design only). A community center received the only grade of 3.00, and the four projects receiving below average grades were a community center, a retaining wall, a shallow well project, and an irrigation water reservoir. Representatives from the Ministry of Rural Rehabilitation and Development (MRRD) accompanied IRD on 87 % of site visits this month, compared to 81% in February, 85% in January, 93% in December, 100% in November and 86% in the same month of last year (March 2014). A number of key findings were noted by IRD this month. Of the 55 project sites inspected in March, construction of 50 did not commence on the planned start date; the difference between planned and actual start dates varied from 30 to 882 days. Of the 18 completed sites inspected in March, none were completed on the planned completion date, delays in construction completion varied from 24 to 676 days.

Page 5: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-4

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

2.2 Fiduciary Monitoring All five PMU’s inspected for financial regularities in March (Farah, Faryab, Ghor, Hilmand, and Paktika) were able to provide all requisite documentation, photographs of which have been included in the inspection reports.

3. Observations 3.1 Notable Successes The highest graded project inspected in March, a secondary school building (IRD-NS-71472) in Kabul Province, received grades of 4.30 for both materials and workmanship and 4.50 for design resulting in an overall rating of 4.37. Facilitated by SDO, this school building consists of five classrooms, and two administrative rooms, built with a total budget of 3,300,000 AFN (including 10% community contribution). Construction began in May 2014 and was 80% complete in March, including all structural work, installation of wood ceiling beams and carpentry work. Interior/exterior painting, installation of bulbs, and window glass remains to be done. (Photos 1 and 2) The second highest graded project inspected in March, a primary school building (IRD-NS-73269) in Nangarhar Province, received a grade of 4.20 for materials, 2.30 for workmanship, and 4.00 for design, giving it an overall grade of 4.17. Facilitated by BRAC, the one story building consists of six classrooms and three administration rooms. With a total budget of 3,333,333 AFN (including 10% community contribution), construction began in December 2013 and was completed in October 2014. Per site inspection, construction was completed according to design and specifications, and a boundary wall, which was not specified in the approved scope of work was also constructed by the community using their own funds. The building was being used as a multi-purpose facility; in addition to serving as a

Photo 1: A well-constructed secondary school building, 80% complete. Kabul Province (IRD-NS-71472)

Photo 2: School facilities observed to be constructed with high quality materials, workmanship and design. Kabul Province (IRD-NS-71472)

Photo 3: The second highest graded project inspected in March, a school building that is also used for community functions. Nangarhar Province (IRD-NS-73269)

Page 6: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-5

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

school it is used for community gatherings and as a conference center for Community Development Council (CDC) meetings. An O&M plan was developed which stated each benefitting family would pay 22 AFN per year to maintain the project, but ultimately the facility was turned over to the Ministry of Education (MoE) and a Memorandum of Understanding (MoU) signed by NSP and MoE assigned the responsibility of O&M to MoE. (Photos 3 and 4) The third highest rated project inspected this month was a canal and protection wall (IRD-NS-84753) in Laghman Province which was given a grade of 4.00 in all categories (material quality, workmanship quality, and design). Facilitated by MADERA, construction of a 401 meter protection wall, and 259 meters of stone masonry canal was being built with a budget of 2,498,246 AFN (including 10% community contribution), and was 93% complete in March. As stated above, the designed length of the canal was 259 meters, which was to be built in two sections: one measuring 215 meters long and 60 centimeters wide, and the other 44 meters long with a width of 80 centimeters. On inspection it was noted that, without PMU approval, the canal had been constructed a total of 272 meters in length, but narrower than designed with a width of 50 centimeters. An O&M plan was available; which stated that a specified local resident (selected by the CDC) was to serve as a maintenance person tasked with complete maintenance of the project, and each household in the community is to supply one pound of wheat per month to be sold, the profits of which provide the salary for the maintenance worker. (Photos 5 and 6) 3.2 Notable Deficiencies The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat. Receiving a grade of 2.10 for both materials and workmanship, and 3.00 for design it had an overall grade of 2.57. The scope of work includes two shallow wells, each 13 meters deep and 1 meter in diameter, installation of hand pumps and required accessories. The budget of 144,444 AFN includes a 10% community contribution. Upon site inspection, both wells were installed and

Photo 4: A class in-session at the second highest graded project inspected in March. Nangarhar Province (IRD-NS-73269)

Photo 5: Skillful stone masonry was observed at this canal project. Laghman Province (IRD-NS-84753)

Photo 6: A well-built canal, 93% complete, constructed of high quality materials. Laghman Province (IRD-NS-84753)

Page 7: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-6

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

operational, but observed to be constructed with poor quality materials and workmanship, which did not meet design and specifications. Indus hand pumps which were specified in the BoQ were replaced with inferior quality Kabul pumps. Aprons, top rings, and top covers were also observed to be of substandard quality. An initial well was dug to a depth of 16 meters but failed to find water. The resulting shaft was not backfilled or covered, creating a potential risk of someone falling down the shaft, particularly children. (Photos 7 and 8) The second lowest graded project inspected in March was a retaining wall, culvert and road graveling (IRD-NS-71014) project in Parwan Province, facilitated by UN Habitat. Receiving a grade of 2.89 for materials, 2.71 for workmanship, and 3.04 for design, its overall average was 2.88. Construction of 16 slab culverts, 13 pipe culverts (12 inch diameter steel), 626 meters of retaining wall in several sections, and 748 meters of road graveling with two layers each of 10 centimeter thickness was the scope of work. In March 60% of construction activities were complete, including 10 slab culverts (minor work remaining), 250 meters of road graveling (the first 10 centimeter layer), and 510 meters of retaining wall. Typical culvert design was used but they were constructed with poor quality materials and workmanship. (Photos 9 and 10)

Photo 7: Poorly constructed water wells, built with substandard materials. Bamyan Province (IRD-NS-81239)

Photo 8: These poorly constructed water wells exhibited substandard workmanship. Bamyan Province (IRD-NS-81239)

Photo 9: Culverts built with low quality materials. Parwan Province (IRD-NS-71014)

Photo 10: Poorly constructed culverts. Parwan Province (IRD-NS-71014)

Page 8: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-7

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Figure 4: Average grades of facilitating partners, March 2015

Figure 5: Gender composition of CDCs

3.3 Facilitating Partners In March, six projects achieved overall grades of 4.00 or above, ranging from 4.00 to 4.37. The facilitators of these projects were MADERA, SDO, BRAC and UN Habitat. The lowest graded project, which received a grade of 2.57, was implemented by UN Habitat. The average grade of all projects implemented by each FP is outlined in the adjacent table. (Figure 4)

4. Social Safeguards, Environment and Safety, and Gender 4.1 Social Safeguards Land was required for 34 out of the 55 NSP construction projects inspected this month, which amounted to 11.75 jeribs. Land was donated by private individuals for 20 of these projects, and land transaction documents were available for 18 out of the 20 sites. FPs had a safeguard focal point at 53 sites, and safeguard training had been provided to 47 communities. Of the 55 sites, 47 were providing a monthly report to the NSP PMU office. Social safeguards were documented at only 13 of the 55 projects inspected this month. The Environmental and Social Mitigation Plan (ESMP) was available at 34 of the 55 sites. A Community Participatory Monitoring (CPM) committee was established at 42 out of the 55 CDCs. (Figure 6) Six grievances were reported at two sites visited in March, per FP and CDC information all had been resolved, but none were recorded. Most of the disclosed grievances were regarding construction materials and workmanship. 4.2 Environment and Safety Four life safety issues were observed in March. Of the 37 projects under construction, first aid kits and/or personal protective equipment was not available at any project site. No safety training was provided and

no safety signs were observed by IRD monitors. See Annex C for more details. Of the 55 sites inspected this month no construction camps (on-site housing for laborers) had been established. There were no indications of fuel waste, or other potential risks of water contamination observed at any sites this reporting period. 4.3 Gender Forty-eight CDCs included female members on the council (87%), with an average of 7.92 women for every 9.63 men in a combined-gender CDCs. (Figure 5)

Facilitating Partner Number of Projects

Average Grade

BRAC 4 4.02

RI 1 3.80

ACTED 1 3.80

MADERA 10 3.75

Action Aid 3 3.71

CONCERN 1 3.70

SDO 2 3.65

ZOA 2 3.65

IRC 5 3.54

GRSP 5 3.51

NPO/RRAA 3 3.33

UN-Habitat 18 3.32

Grand Total 55 3.54

Mixed Gender

CDCs, 48

No Female Sub CDC, 4

Female Sub CDC, 3

Non Mixed Gender CDCs, 7

Gender Composition of Community Development Councils

Page 9: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-8

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Figure 6: Community Participatory Monitoring established at CDCs

Forty-four CDCs included females in office positions, of which 42 CDCs had two females as deputy head of CDC and secretary, and the remaining two CDCs had one female as deputy head of the CDC.

A record of CDC meetings held in the previous three months was available at 38 projects, which averaged four meetings during that timeframe; one reported 10, and six others recorded six meetings during this three-month period. Forty-five projects documented female participation in the project identification process, which is close to the normal percentage of female participation when compared to previous findings.

FPs reported that female social mobilizers were working on 50 of the 55 construction projects inspected. These social mobilizers made a total of 167 visits to 48 project sites during the previous three months. Male social mobilizers made 225 visits to 51 sites during the previous three months.

5. Feedback Quality and design deviations, as well as maintenance related issues observed in March are provided in Annexes C, D and E. The deviations listed in Annex E do not include those observed prior to January 2015, which have been provided in previous monthly summaries and continue to be provided directly to the Ministry on a regular basis. The detailed deviation log, along with photos, was shared with NSP in early March. IRD attended the last technical coordination meeting with MRRD/NSP and FPs on February 25, 2015 at the NSP MRRD office, and the minutes were shared in the February monthly summary report. March’s meeting is not yet scheduled as of the writing of this report.

6. Recommendations and Future Plans The following recommendations are based on findings from this month’s NSP TPM inspections, many of which build upon previously reported deficiencies.   NSP should consider including a protective concrete layer atop the water membrane (IZOGAM) during the

design of roof construction. Throughout the year IRD found the majority of community centers and school buildings to have flat roofs which did not have a protective layer on the top of IZOGAM in their design. Placing IZOGAM without a protective layer can cause damage of the water membrane due to cold weather and direct sunlight. One such example encountered this month was a community center in Badghis Province (IRD-NS-69898).

Inadequate mortar is often observed in stone masonry work. Specifications state that 25-35% of the total volume of stone masonry should be mortar, but this minimum is frequently not met, as was the case at a retaining wall construction project inspected this month in Kapisa Province (IRD-NS-71847).

0

10

20

30

40

50

No Yes

13

42

Community Participatory Monitoring (CPM) Established at CDC Level

Page 10: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-9

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Of the 55 projects inspected in March, 50 were either behind schedule or not completed by the planned completion date. The main reasons for construction delays cited by FPs and CDCs include delay of payments to the CDC, revision of the sub-project design and/or scope of work, agricultural work, and cold weather. NSP should try to ensure that construction activities adhere to the work schedule.

7. Targets and Deliverables The Year IV terms of reference require 800 inspection reports to be submitted including 732 construction project inspections and 68 provincial fiduciary inspections (two in each province). As of the end of March, IRD has completed 33 initial fiduciary inspections, and 358 construction inspections. A scheduled inspection of the Daikundi PMU in March had to be cancelled due to unavailability of flights; it has since been rescheduled for inspection in April.

8. Point of Contact The points of contact for this report are Abdul Saboor Patyal ([email protected]) and Mark "Paddy" Smith ([email protected]).

Project Highlight

Shakardara District, Kabul Province IRD-NS-71472

Kokcheen Village School

                                          Kokcheen Village has a sizable population of 550 families, but up until five years ago the village lacked any permanent educational facilities. Secondary education was available to older children in community center conference rooms rented with tuition fees, but no primary level education was available for children under the age of 10 in the community.

In recent years in an attempt to expand the education opportunities to younger children, community elders arranged rental of a private home in the village to be used as a school building. The Ministry of Education formally recognized it as a primary school and children attended classes up to third grade. This temporary arrangement was an improvement, but the house was inadequate to serve as school facilities long-term, especially in light of an increasing student poulation.

In 2013, the National Solidarity Program (NSP) offered Kokcheen Village funding for a development project of their choosing and a permanent primary school building was declared their number one priority. Land for the school was donated free of charge by the nephew of the first president of Afghanistan, Sardar Mohammad Daud Khan.

The school construction is presently 65% complete, but is already functional with classes held daily open to attendance by both boys and girls in separate shifts. When complete, the school will have a total of five classrooms.

Mr. Rahman tells IRD that the people of Kokcheen are very pleased that they have been granted the school facilities, enabling them to provide every child of this community access to basic education.

Three decades of conflict had a profound impact on Afghanistan’s education system and infrastructure with many villages lacking dedicated school buildings in the aftermath. Kokcheen Village, in the Shakardara District of Kabul Province is one such place. Mr. Fazil Rahman, the head of the Kokcheen Community Development Council (CDC) recently spoke with a visiting International Relief & Development (IRD) engineer about recent advancements in the education infrastructure in his community, made feasible by the donations of both international and domestic donors.

Page 11: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-10

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex A - Construction Quality Grading System

Workmanship: 5. Very good: The workmanship meets all the NSP specifications. The project is sustainable over the entire design life and there is 100% functionality. 4. Good: The workmanship meets most NSP specifications with minor deviations in workmanship quality that has no impact on the sustainability and the project has at least 90% functionality. 3. Average: The workmanship quality meets the major specifications, but deviations have caused reduced sustainability (no longer the design life) and decreased functionality between 70% and 90%. 2. Poor: The workmanship quality deviates significantly from the specifications. There is marked impact on the sustainability of the project and significant decrease in the functionality to between 40% and 70%. 1. Very Poor: The project barely follows any specifications. The sustainability of the project is zero as there ski already n need for serous reworking; functionality is below 40%.

Materials: 5. Very good: The materials meet all the NSP specifications. The project is sustainable over the entire design life and there is 100% functionality. 4. Good: The materials quality meets most NSP specifications with minor deviations in workmanship quality that has no impact on the sustainability and the project has at least 90% functionality. 3. Average: The materials quality meets the major specifications, but deviations have caused reduced sustainability (no longer the design life) and decreased functionality between 70% and 90%. 2. Poor: The materials quality deviates significantly from the specifications. There is marked impact on the sustainability of the project and significant decrease in the functionality to between 40% and 70%. 1. Very Poor: The project barely follows any specifications. The sustainability of the project is zero as there is already a need for serious reworking; functionality is below 40%.

Design: 5. Very Good: The design was created with full consideration of the site requirements. The design is fully appropriate and allows for 100% of intended functionality and design life. 4. Good: The design was created with consideration of most of the site requirements, however small considerations could have reduced wear and tear and lowered maintenance requirements. Intended functionality is between 90% and 100% and design life was not impacted. 3. Average: The design considered only the major site requirements. Some of the design was inappropriate for the site and caused the project to have between 70% and 90% of intended functionality and a shorter design life. 2. Poor: The design barely considered any site requirements. Much of the design is inappropriate and severely lowers functionality to between 40% and 70%. Sustainability is negatively impacted and the project will require far more maintenance than otherwise would be necessary. 1. Very poor: The design does not consider any of the site requirements. The design is inappropriate so as to make the project unsustainable and non-functional (below 40%). Portions of the design may have not been feasibly implemented. If the project is currently working, it required serious deviations from the design in order to do so.

Page 12: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-11

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Maintenance: 5. Very Good: Maintenance is being conducted, and repairs are being made, sufficient to keep functionality of the project at 100% for the design life. 4. Good: Maintenance and repairs are being conducted sufficient to keep functionality of the project between 90% and 100% for the design life. 3. Average: Maintenance and repairs are being conducted sufficient to keep functionality of the project between 70% and 90% for the design life. 2. Poor: Maintenance and repair are barely being conducted, with resultant reduction in functionality of the project to between 40% and 70%. Sustainability is negatively impacted and the project will require far more maintenance than otherwise would be necessary. 1. Very poor: Maintenance is not being conducted or is not considered, and functionality of the project is less than 40% because of lack of attention to this activity.

Page 13: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-12

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex B Summary of Grades by Project

IRD Project ID

MRRD Subproject ID

Facilitating Partner

Project Title Province Material Grade

Workmanship Grade

Design Grade

Maintenance Grade

Overall Grade (Excluding Maintenance Grade)

IRD-NS-47107

20-2002-0176-2-a

UN-Habitat Water Supply Network Construction

Hirat 3.30 3.30 3.50 3.80 3.37

IRD-NS-76259

14-1406-0098-2-a

GRSP Community Center Construction

Kunduz 3.50 3.30 3.00 2.80 3.27

IRD-NS-75208

10-1012-0018-2-a

MADERA Protection Wall and Canal Construction

Kunar 3.68 3.62 3.70 3.47 3.67

IRD-NS-36012

14-1406-0087-2-b

GRSP Shallow Well Boring

Kunduz 3.36 3.26 4.00 2.56 3.54

IRD-NS-35521

14-1405-0034-2-b

GRSP Shallow Well Boring

Kunduz 3.45 3.37 3.95 3.00 3.59

IRD-NS-77686

24-2402-0038-2-a

UN-Habitat Community Center Construction

Kandahar 3.50 3.50 3.80

3.60

IRD-NS-76894

24-2402-0014-2-a

UN-Habitat Community Center Construction

Kandahar 3.00 3.00 3.00

3.00

IRD-NS-77722

20-2010-0057-2-a

UN-Habitat Water Supply Network Construction

Hirat 3.30 3.20 3.00

3.17

IRD-NS-84753

09-0902-0143-2-a

MADERA Canal Construction and Protection wall Construction

Laghman 4.00 4.00 4.00

4.00

IRD-NS-71472

01-0107-0021-2-a

SDO Secondary School Building Construction

Kabul 4.30 4.30 4.50

4.37

IRD-NS-73658

10-1012-0036-2-a

MADERA Pathway Construction and Retaining wall Construction

Kunar

3.80 3.73 4.00

3.84

IRD-NS-81239

28-2801-0073-2-a

UN-Habitat Shallow Well Digging

Bamyan 2.10 2.10 3.50 3.00 2.57

IRD-NS-71847

02-0202-0088-2-a

UN-Habitat Culvert, Retaining wall, & Road Gravilling Construction

Kapisa

2.94 2.78 3.38

3.03

IRD-NS-74965

09-0902-0091-2-b

MADERA Power line supply Laghman

4.00

IRD-NS-73479

09-0902-0009-2-a

MADERA Shallow Well Boring

Laghman 4.00 3.60 4.00 3.10 3.87

IRD-NS-69912

19-1901-0058-2-a

NPO-RRAA Footbridge Badghis 3.50 3.60 3.90 3.00 3.67

IRD-NS-79845

10-1012-0051-2-a

MADERA Micro-Hydro Power Plants Construction

Kunar 3.80 3.80 4.00

3.87

IRD-NS-78989

28-2801-0055-2-c

UN-Habitat Culvert Construction

Bamyan 3.55 3.50 4.00

3.68

IRD-NS-78606

28-2801-0053-2-a

UN-Habitat Community Center Construction

Bamyan 3.30 3.20 3.50

3.33

IRD-NS-72097

03-0301-0049-2-a

UN-Habitat Retaining Wall, Culvert & Road Graveling

Parwan 3.24 3.15 3.43

3.28

IRD-NS-69898

19-1901-0038-2-a

NPO-RRAA Community Center Construction

Badghis 3.20 3.20 3.80

3.40

IRD-NS-80967

24-2404-0064-2-a

UN-Habitat Culvert and Retaining Wall Construction

Kandahar 3.30 3.00 3.77

3.36

IRD-NS-71014

03-0301-0016-2-a

UN-Habitat Retaining Wall, Culvert Construction & Road Graveling

Parwan

2.89 2.71 3.04

2.88

IRD-NS-72955

08-0818-0006-2-a

UN-Habitat School Boundary Wall Construction

Nangarhar 3.60 3.50 3.50

3.53

IRD-NS-78984

28-2801-0028-2-a

UN-Habitat Tertiary Road Basic Access

Bamyan 3.10 3.10 3.00

3.07

IRD-NS-79654

08-0818-0015-2-a

UN-Habitat Retaining Wall Construction and pipe Culvert

Nangarhar 3.73 3.57 3.00

3.43

IRD-NS-71455

01-0105-0061-2-b

SDO Water Divider Construction

Kabul 3.00 3.00 2.80

2.93

Page 14: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-13

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

IRD-NS-69866

19-1901-0011-2-a

NPO/RRAA Community Center Construction

Badghis 3.00 3.00 2.80 3.00 2.93

IRD-NS-79741

09-0902-0084-2-a

MADERA Canal and Protection Wall Construction

Laghman 3.68 3.40 4.00

3.69

IRD-NS-70700

05-0505-0100-2-a

IRC Protection Wall Construction

Logar 3.30 3.30 3.50

3.37

IRD-NS-70400

17-1706-0014-2-b

Action Aid Culvert Construction

Jawzjan 4.00 4.00 3.30 3.00 3.77

IRD-NS-73004

08-0821-0058-2-a

BRAC Pathway Construction and side Ditch

Nangarhar 3.83 3.77 3.93

3.84

IRD-NS-71939

02-0202-0034-2-b

UN-Habitat Deep Well Boring Kapisa 3.60 3.40 3.35 1.00 3.45

IRD-NS-74088

13-1301-0047-2-a

ACTED Community Center construction

Baghlan 3.80 3.90 3.70 3.00 3.80

IRD-NS-71940

02-0202-0035-2-a

UN-Habitat Community Center Construction

Kapisa 3.40 3.70 3.50

3.53

IRD-NS-72538

05-0505-0069-2-a

IRC Pathway Construction

Logar 3.40 3.43 3.50

3.44

IRD-NS-73269

08-0802-0005-2-a

BRAC Primary School Building Construction

Nangarhar 4.20 4.30 4.00 4.00 4.17

IRD-NS-75229

17-1702-0008-2-a

Action Aid Tertiary Road Graveling and Culvert Construction

Jawzjan

4.00 4.00 3.97 2.70 3.99

IRD-NS-84460

14-1405-0005-2-b

GRSP Community Center Construction

Kunduz 3.35 3.50 3.55

3.47

IRD-NS-72521

05-0505-0011-2-a

IRC Water Reservoir & Canal Construction

Logar 3.70 3.50 4.00

3.73

IRD-NS-70692

05-0505-0098-2-b

IRC Community Center construction

Logar 3.20 3.30 3.00

3.17

IRD-NS-80517

17-1702-0003-2-a

Action Aid Community Center Construction

Jawzjan 3.50 3.40 3.20

3.37

IRD-NS-79209

31-3101-0169-2-a

ZOA Community Center Construction

Sar-e-Pul 3.70 3.80 3.50 3.00 3.67

IRD-NS-73014

08-0821-0093-2-a

BRAC Primary School Building Construction

Nangarhar 4.20 4.10 4.00

4.10

IRD-NS-76069

20-2002-0145-2-a

UN Habitat Primary School Buiding Construction

Hirat 4.30 3.90 4.00

4.07

IRD-NS-74968

09-0902-0096-2-b

MADERA Community Center Construction

Laghman 3.80 3.80 3.00

3.53

IRD-NS-77970

22-2202-0053-2-b

RI Hand Pump Installation

Nimroz

3.80

IRD-NS-78463

32-3206-0043-2-b

IRC Protection Wall Construction

Khost 4.00 3.90 4.00 3.30 3.97

IRD-NS-81327

31-3101-0155-2-c

ZOA Community Center Construction

Sar-e-Pul 3.60 3.80 3.50 3.63

IRD-NS-36058

14-1406-0099-2-a

GRSP Culvert and Retaining Wall

Kunduz 3.60 3.53 3.97 3.50 3.70

IRD-NS-74669

08-0802-0104-2-a

BRAC Community Center Construction

Nangarhar 4.00 4.00 3.90 3.00 3.97

IRD-NS-76760

20-2002-0129-2-a

UN-Habitat Water Supply Network Construction

Hirat 3.40 3.30 3.80 3.50

IRD-NS-73648

10-1012-0004-2-b

MADERA Retaining Wall Construction

Kunar 4.00 3.70 4.00 3.90

IRD-NS-30077

12-1206-0005-2-a

CONCERN Community Center Construction

Takhar 3.80 3.80 3.50 3.70

IRD-NS-73174

10-1012-0043-2-b

MADERA Protection Wall Construction

Kunar 2.75 2.65 4.00 3.80 3.13

Average 3.54 3.48 3.62 3.01 3.54

Page 15: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-14

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex C Social Safeguards, Environment and Safety, and Gender

Issue Description IRD Project ID

MRRD Sub-project ID

Project Title Province District

Social Safeguards

ESMP was not available at 21 sites, including the 7 sites

reported by FP where ESMP not required.

IRD-NS-47107, IRD-NS-76259, IRD-NS-36012, IRD-NS-35521, IRD-NS-77686, IRD-NS-84753, IRD-NS-71472, IRD-NS-74965, IRD-NS-73479, IRD-NS-80967, IRD-NS-71455, IRD-NS-79741, IRD-NS-70700, IRD-NS-70400, IRD-NS-71940, IRD-NS-72521, IRD-NS-79209, IRD-NS-74968, IRD-NS-77970, IRD-NS-81327, IRD-NS-36058

20-2002-0176-2-a, 14-1406-0098-2-a, 14-1406-0087-2-b, 14-1405-0034-2-b, 24-2402-0038-2-a, 09-0902-0143-2-a, 01-0107-0021-2-a, 09-0902-0091-2-b, 09-0902-0009-2-a, 24-2404-0064-2-a, 01-0105-0061-2-b, 09-0902-0084-2-a, 05-0505-0100-2-a, 17-1706-0014-2-b, 02-0202-0035-2-a, 05-0505-0011-2-a, 31-3101-0169-2-a, 09-0902-0096-2-b, 22-2202-0053-2-b, 31-3101-0155-2-c, 14-1406-0099-2-a

Water Supply Network Construction, Community Center Construction, Shallow Well Boring, Shallow Well Boring, Community Center Construction, Canal and Protection wall Construction, Secondary School Building Construction, Power line supply, Shallow Well Boring, Culvert and Retaining Wall Construction, Water Divider Construction, Canal and Protection Wall Construction, Protection Wall Construction, Culvert and community center, Water Reservoir & Canal Construction, Community Center Construction, Community Center Construction, Hand Pump Installation, Community Center Construction, Culvert and Retaining Wall

Hirat, Kunduz, Kunduz, Kunduz, Kandahar, Laghman, Kabul, Laghman, Laghman, Kandahar, Kabul, Laghman, Logar, Jawzjan, Kapisa, Logar, Sar-e-Pul, Laghman, Nimroz, Sar-e-Pul, Kunduz

Hirat, Khan Abad, Khan Abad, Ali Abad, Daman, Qarghayi, Shakardara, Qarghayi, Qarghayi, Arghandab, Qarabagh, Qarghayi, Mohammad Agha, Khanaqa, Hisa Duwum-e- Kohestan, Mohammad Agha, Sar-e-Pul, Qarghayi, Kang, Sar-e-Pul, Dasht-e-Archi

Land transaction document was not

available.

IRD-NS-79654

IRD-NS-77970

08-0818-0015-2-a

22-2202-0053-2-b

Retaining Wall Construction and pipe Culvert

Hand Pump Installation

Nangarhar

Nimroz

Kama

Kang

Community participatory monitoring (CPM) committee was

not established.

IRD-NS-47107, IRD-NS-75208, IRD-NS-73658, IRD-NS-79845, IRD-NS-71014, IRD-NS-72955, IRD-NS-79654, IRD-NS-73004, IRD-NS-73269, IRD-NS-73014, IRD-NS-76069, IRD-NS-77970, IRD-NS-76760

20-2002-0176-2-a, 10-1012-0018-2-a, 10-1012-0036-2-a, 10-1012-0051-2-a, 03-0301-0016-2-a, 08-0818-0006-2-a, 08-0818-0015-2-a, 08-0821-0058-2-a, 08-0802-0005-2-a, 08-0821-0093-2-a, 20-2002-0145-2-a, 22-2202-0053-2-b, 20-2002-0129-2-a

Water Supply Network Construction, Protection Wall and Canal Construction, Pathway and Retaining wall Construction, Micro-Hydro Power Plants Construction, Retaining Wall, Culvert & Road Graveling, School Boundary Wall Construction, Retaining Wall and pipe Culvert, Pathway Construction and side Ditch, Primary School Building Construction, Primary School Building Construction, Primary School Building Construction, Hand Pump Installation, Water Supply Network Construction

Hirat, Kunar, Kunar, Kunar, Parwan, Nangarhar NangarharNangarharNangarhar Nangarhar Hirat, Nimroz, Hirat

Hirat, Narang, Narang, Narang, Chaharikar, Kama, Kama, Behsud, Surkh Rod, Surkh Rod, Injil, Kang, Injil

Six grievances were reported at two sites visited in March, per

FP and CDC information all had been resolved, but none of them was

recorded. Most of the mentioned grievances

IRD-NS-69898

IRD-NS-73648

19-1901-0038-2-a

10-1012-0004-2-b

Community Center Construction

Retaining Wall Construction

Badghis

Kunar

Qala-e-Naw

Narang

Page 16: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-15

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

were about construction material

and workmanship.

Record of CDC meetings was not

available at 17 CDCs.

IRD-NS-77686, IRD-NS-76894, IRD-NS-84753, IRD-NS-71472, IRD-NS-81239, IRD-NS-71847, IRD-NS-78989, IRD-NS-72097, IRD-NS-80967, IRD-NS-71014, IRD-NS-70700, IRD-NS-71939, IRD-NS-71940, IRD-NS-72538, IRD-NS-72521, IRD-NS-70692, IRD-NS-76069

24-2402-0038-2-a, 24-2402-0014-2-a, 09-0902-0143-2-a, 01-0107-0021-2-a, 28-2801-0073-2-a, 02-0202-0088-2-a, 28-2801-0055-2-c, 03-0301-0049-2-a, 24-2404-0064-2-a, 03-0301-0016-2-a, 05-0505-0100-2-a, 02-0202-0034-2-b, 02-0202-0035-2-a, 05-0505-0069-2-a, 05-0505-0011-2-a, 05-0505-0098-2-b, 20-2002-0145-2-a

Community Center Construction, Community Center Construction, Canal and Protection wall Construction, Secondary School Building Construction, Shallow Well Digging, Culvert, Retaining wall, & Road Gravelling, Culvert Construction, Retaining Wall, Culvert & Road Graveling, Culvert and Retaining Wall Construction, Retaining Wall, Culvert & Road Graveling, Protection Wall Construction, Deep Well Boring, Community Center Construction, Pathway Construction, Water Reservoir & Canal Construction, Community Center construction, Primary School Building Construction

Kandahar, Kandahar, Laghman, Kabul, Bamyan, Kapisa, Bamyan, Parwan, Kandahar, Parwan, Logar, Kapisa, Kapisa, Logar, Logar, Logar, Hirat

Daman, Daman, Qarghayi, Shakardara, Bamyan, Hesa Awal, Bamyan, Sayd Khel, Arghandab, Chaharikar, Mohamad Agha, Hesa Awal, Hisa Duwum, Mohamad Agha, Mohamad Agha, Mohamad Agha, Injil

Of the seven none mixed CDCs with a

separate female subcommittee, record of female meeting was

not available at six CDCs.

IRD-NS-77686, IRD-NS-76894, IRD-NS-71472, IRD-NS-80967, IRD-NS-71455, IRD-NS-70400

24-2402-0038-2-a, 24-2402-0014-2-a, 01-0107-0021-2-a, 24-2404-0064-2-a, 01-0105-0061-2-b, 17-1706-0014-2-b

Community Center Construction, Community Center Construction, Secondary School Building Construction, Culvert and Retaining Wall Construction, Water Divider Construction, Culvert Construction

Kandahar, Kandahar, Kabul, Kandahar, Kabul, Jawzjan

Daman, Daman, Shakardara, Arghandab, Qarabagh, Khanaqa

FP male social mobilizers had no visit from three CDCs during last three months.

IRD-NS-77686 IRD-NS-80967 IRD-NS-73174

24-2402-0038-2-a 24-2404-0064-2-a 10-1012-0043-2-b

Community Center Construction, Culvert and Retaining Wall Construction, Protection Wall Construction

Kandahar, Kandahar, Kunar

Daman, Arghandab, Narang

Safeguard focal point was not available for the two sites.

IRD-NS-72538, IRD-NS-70692

05-0505-0069-2-a, 05-0505-0098-2-b

Pathway Construction, Community Center construction

Logar, Logar

Mohamad Agha, Mohamad Agha

FP did not provide safeguard training.

IRD-NS-75208, IRD-NS-84753, IRD-NS-73658, IRD-NS-69912, IRD-NS-69898, IRD-NS-69866

10-1012-0018-2-a, 09-0902-0143-2-a, 10-1012-0036-2-a, 19-1901-0058-2-a, 19-1901-0038-2-a, 19-1901-0011-2-a

Protection Wall and Canal Construction, Canal and Protection wall Construction, Pathway and Retaining wall Construction, Footbridge, Community Center Construction, Community Center Construction

Kunar, Laghman, Kunar, Badghis, Badghis, Badghis

Narang, Qarghayi, Narang, Qala-e-Naw, Qala-e-Naw, Qala-e-Naw

Focal point safeguard report was not provided.

IRD-NS-69912, IRD-NS-69898, IRD-NS-69866, IRD-NS-70700, IRD-NS-72521, IRD-NS-77970

19-1901-0058-2-a, 19-1901-0038-2-a, 19-1901-0011-2-a, 05-0505-0100-2-a, 05-0505-0011-2-a, 22-2202-0053-2-b

Footbridge, Community Center Construction, Community Center Construction, Protection Wall Construction, Water Reservoir & Canal Construction, Hand Pump Installation

Badghis, Badghis, Badghis, Logar, Logar, Nimroz

Qala-e-Naw, Qala-e-Naw, Qala-e-Naw, Mohamad Agha, Mohamad Agha, Kang

Environment and Safety

Life safety issue was observed at four sites.

IRD-NS-76259, IRD-NS-71472, IRD-NS-81239,

14-1406-0098-2-a, 01-0107-0021-2-a, 28-2801-0073-2-a,

Community Center Construction, Secondary School Building Construction, Shallow Well Digging, Footbridge, Tertiary

Kunduz, Kabul, Bamyan,

Khan Abad, Shakardara, Bamyan,

Page 17: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-16

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

IRD-NS-69912 19-1901-0058-2-a Road Basic Access Badghis Qala-e-Naw

EMP checklist was not available.

IRD-NS-80967, IRD-NS-79741, IRD-NS-72538, IRD-NS-74968, IRD-NS-78463

24-2404-0064-2-a, 09-0902-0084-2-a, 05-0505-0069-2-a, 09-0902-0096-2-b, 32-3206-0043-2-b

Culvert and Retaining Wall Construction, Canal and Protection Wall Construction, Pathway Construction, Community Center Construction, Protection Wall Construction

Kandahar, Laghman, Logar, Laghman, Khost

Arghandab, Qarghayi, Mohamad Agha, Qarghayi, Mando Zayi

100 trees for a protection wall project, and 3 trees for another project’s road widening were cut, but new trees were not planted.

IRD-NS-71847, IRD-NS-72097

02-0202-0088-2-a, 03-0301-0049-2-a

Culvert, Retaining wall, & Road Gravelling

Retaining Wall, Culvert & Road Graveling

Kapisa, Parwan

Hesa Awal Sayd Khel

EHS management or First Aid Training was

not provided to the workers at 31 out of 55

sites.

IRD-NS 77686, IRD-NS-76894, IRD-NS-77722, IRD-NS-84753, IRD-NS-73658, IRD-NS-71847, IRD-NS-74965, IRD-NS-79845, IRD-NS-72097, IRD-NS-69898, IRD-NS-80967, IRD-NS-71014, IRD-NS-72955, IRD-NS-79654, IRD-NS-79741, IRD-NS-70700, IRD-NS-73004, IRD-NS-71940, IRD-NS-72538, IRD-NS-84460, IRD-NS-72521, IRD-NS-70692, IRD-NS-80517, IRD-NS-73014, IRD-NS-76069, IRD-NS-74968, IRD-NS-77970, IRD-NS-81327, IRD-NS-76760, IRD-NS-73648, IRD-NS-30077

24-2402-0038-2-a, 24-2402-0014-2-a, 20-2010-0057-2-a, 09-0902-0143-2-a, 10-1012-0036-2-a, 02-0202-0088-2-a, 09-0902-0091-2-b, 10-1012-0051-2-a, 03-0301-0049-2-a, 19-1901-0038-2-a, 24-2404-0064-2-a, 03-0301-0016-2-a, 08-0818-0006-2-a, 08-0818-0015-2-a, 09-0902-0084-2-a, 05-0505-0100-2-a, 08-0821-0058-2-a, 02-0202-0035-2-a, 05-0505-0069-2-a, 14-1405-0005-2-b, 05-0505-0011-2-a, 05-0505-0098-2-b, 17-1702-0003-2-a, 08-0821-0093-2-a, 20-2002-0145-2-a, 09-0902-0096-2-b, 22-2202-0053-2-b, 31-3101-0155-2-c, 20-2002-0129-2-a, 10-1012-0004-2-b, 12-1206-0005-2-a

Kandahar, Hirat,

Laghman, Kunar, Kapisa, Parwan, Badghis,

Nangarhar, Logar, Kunduz, Jawzjan, Nimroz,,

Sar-e-Pul, Takhar

Daman, Zinda Jan, Qarghayi, Narang,

Hesa Awal, Sayd Khel,

Qala-e-Naw, Arghandab Chaharikar,

Kama, Mohamad Agha,

Behsud, Hisa Duwum, Khan Abad,

Khwaja Du Koh, Surkh Rod,

Injil, Kang,

Sar-e-Pul, Farkhar

Gender

Women have not signed on CDP plan,

and have not participated during project selection.

IRD-NS-77686, IRD-NS-76894, IRD-NS-71472, IRD-NS-71847, IRD-NS-80967, IRD-NS-70400, IRD-NS-71939, IRD-NS-71940, IRD-NS-78463, IRD-NS-30077

24-2402-0038-2-a, 24-2402-0014-2-a, 01-0107-0021-2-a, 02-0202-0088-2-a, 24-2404-0064-2-a, 17-1706-0014-2-b, 02-0202-0034-2-b, 02-0202-0035-2-a, 32-3206-0043-2-b, 12-1206-0005-2-a

Community Center Construction, Community Center Construction, Secondary School Building Construction, Culvert, Retaining wall, & Road Gravelling, Culvert and Retaining Wall Construction, Culvert Construction, Deep Well Boring, Community Center Construction, Protection Wall Construction, Community Center Construction

Kandahar, Kandahar,

Kabul, Kapisa,

Kandahar, Jawzjan, Kapisa, Kapisa, Khost, Takhar

Daman, Daman,

Shakardara, Hesa Awal, Arghandab, Khanaqa,

Hesa Awal, Hisa Duwum, Mando Zayi,

Farkhar

Page 18: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-17

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Four non-mixed CDCs did not had separate

female sub-committee.

IRD-NS-77686, IRD-NS-76894, IRD-NS-80967, IRD-NS-70400

24-2402-0038-2-a, 24-2402-0014-2-a, 24-2404-0064-2-a, 17-1706-0014-2-b

Community Center Construction, Community Center Construction, Culvert and Retaining Wall Construction, Culvert Construction

Kandahar, Kandahar, Kandahar, Jawzjan

Daman, Daman, Arghandab, Khanaqa

At 11 out of the 55 CDCs visited this, none

of the female was in office position.

IRD-NS-77686, IRD-NS-76894, IRD-NS-71472, IRD-NS-71847, IRD-NS-80967, IRD-NS-71455, IRD-NS-70400, IRD-NS-71939, IRD-NS-71940, IRD-NS-78463, IRD-NS-30077

24-2402-0038-2-a, 24-2402-0014-2-a, 01-0107-0021-2-a, 02-0202-0088-2-a, 24-2404-0064-2-a, 01-0105-0061-2-b, 17-1706-0014-2-b, 02-0202-0034-2-b, 02-0202-0035-2-a, 32-3206-0043-2-b, 12-1206-0005-2-a

Community Center Construction, Community Center Construction, Secondary School Building Construction, Culvert, Retaining wall, & Road Gravelling, Culvert and Retaining Wall Construction, Water Divider Construction, Culvert Construction, Deep Well Boring, Community Center Construction, Protection Wall Construction, Community Center Construction

Kandahar, Kandahar, Kabul, Kapisa, Kandahar, Kabul, Jawzjan, Kapisa, Kapisa, Khost, Takhar

Daman, Daman, Shakardara, Hesa Awal Arghandab, Qarabagh, Khanaqa, Hesa Awal, Hisa Duwum, Mando Zayi, Farkhar

FP did not had female social mobilizers in the districts and provinces

outlined to the right.

Kandahar,

Kunar

Daman, Arghandab,

Narang,

FP had no female staff at provincial level.

Kunar

 

Page 19: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-18

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex D Projects with Maintenance Deficiencies

IRD Project ID

MRRD Sub-project ID

Project Sector

Project Title Facilitating Partner

ProvinceProject status

O&M issue

Hirat IRD-NS-47107 20-2002-

0176-2-a Water and Sanitation

Water Supply Network Construction

UN-Habitat

Complete Based on operation and maintenance, community is going to collect 137 AFN per family in each month, but per site community installed meters boxes and they are going to pay 7 AFN/cum water consumption, and 3000 AFN/month has being paid for operator.

Kunduz IRD-NS-76259 14-1406-0098-2-a

Rural Development

Community Center Construction

GRSP Complete A proper operation and maintenance plan (maintenance mechanism) was not available in the document. A signed document indicates that CDC is responsible for project future maintenance to do it through donation box.

Kunar IRD-NS-75208 10-1012-0018-2-a

Irrigation Protection Wall Construction

MADERA Complete Project was completed, and it was partially operational. Maintenance plan was available, per plan each family should pay 20 AFN per month to maintain the project. Base on IRD's experience of visiting similar projects in the pats, the plan is not realistic, and community would not pay for maintenance of the projects with low sense of ownership.

Kandahar IRD-NS-77686 24-2402-0038-2-a

Rural Development

Community Center Construction

UN-Habitat

Ongoing Operation and maintenance plan was available at job site, per plan each family to pay 100 AFN per month for project maintenance, but per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic.

Kandahar IRD-NS-76894 24-2402-0014-2-a

Rural Development

Community Center Construction

UN-Habitat

Ongoing Operation and maintenance plan was available at job site, per plan each family to pay 8.6 AFN per month for project maintenance, but per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic.

Kapisa IRD-NS-71847 02-0202-0088-2-a

Transport Retaining Wall Construction

UN-Habitat

Ongoing Operation and maintenance plan was available in the document. Based on plan, CDC will collect 90 AFN/month through donation box. Per CDC information, they established donation box, but they are collecting 30 AFN/month form each family for public project maintenance after completion.

Laghman IRD-NS-74965 09-0902-0091-2-b

Power Protection Wall Construction

MADERA Ongoing Project was not completed, and it was not operational. A typical maintenance plan was available, which each family should give 1-lb wheat in each month to maintain the project. But per CDC information, that project has been changed to power line project and the beneficiaries will pay the consumption bill to the DABS, and DABS will maintain the project after completion.

Laghman IRD-NS-73479 09-0902-0009-2-a

Water and Sanitation

Shallow Well Boring

MADERA Completed Project was completed, and it was operational. Maintenance plan was available; per plan each family should pay 19 AFN for maintenance, but this amount was not yet collected. However, no maintenance related defects were observed during inspection.

Page 20: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-19

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Badghis IRD-NS-69912 19-1901-0058-2-a

Transport Culvert Construction

NPO-RRAA

Completed Operation and maintenance plan was not available, but based on CDC, they are going to collect wheat for maintenance, but the amount was not mentioned. The project was under construction.

Parwan IRD-NS-72097 03-0301-0049-2-a

Transport Retaining Wall Construction

UN-Habitat

Ongoing Operation and maintenance plan was available in the document. Based on plan, CDC will collect 6 AFN/month through donation box. Per CDC information, they didn't established donation box yet, but they will establish after completion.

Badghis IRD-NS-69898 19-1901-0038-2-a

Rural Development

Community Center Construction

NPO-RRAA

Ongoing Operation and maintenance plan was not available. The project was under construction.

Kandahar IRD-NS-80967 24-2404-0064-2-a

Transport Culvert Construction

UN-Habitat

Ongoing Operation and maintenance plan was available at job site, per plan each family to pay 110 AFN per month for project maintenance, but per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic.

Nangarhar IRD-NS-72955 08-0818-0006-2-a

Education School Boundary Wall Construction

UN-Habitat

Ongoing Project was not yet completed, but it was operational. Maintenance plan was available, per plan each family should pay 25 AFN per year to maintain the project. But, this was not a realistic maintenance plan, because project will be handed over to ministry of education.(MoE) after completion, and will be responsible for the maintenance.

Nangarhar IRD-NS-79654 08-0818-0015-2-a

Transport Retaining Wall Construction

UN-Habitat

Ongoing Project was not yet completed, but it was operational. Maintenance plan was available, per plan each family should pay 25 AFN per year to maintain the project. But, this was not a realistic maintenance plan

Kabul IRD-NS-71455 01-0105-0061-2-b

Irrigation Canal Construction

SDO Ongoing Operation and maintenance plan was not available at job site.

Badghis IRD-NS-69866 19-1901-0011-2-a

Rural Development

Community Center Construction

NPO/RRAA

Completed Operation and maintenance plan was not available, but it was mentioned in proposal that community is going to collect wheat, but the amount was not clear.

Logar IRD-NS-70700 05-0505-0100-2-a

Irrigation Protection Wall Construction

IRC Ongoing An agreement letter signed by CDC members which indicates that they are responsible for project future maintenance, but the mechanism was not specified.

Jawzjan IRD-NS-70400 17-1706-0014-2-b

Transport Culvert Construction

Action Aid Completed Operation and maintenance plan was available at job site, per plan each family to pay 11 AFN per month for project maintenance, but per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic.

Nangarhar IRD-NS-73004 08-0821-0058-2-a

Transport Pathway Construction

BRAC Ongoing Project was not yet completed, but it was operational. Maintenance plan was available, per plan each family should pay 25 AFN per year to maintain the project. But, this was not a realistic maintenance plan.

Kapisa IRD-NS-71939 02-0202-0034-2-b

Water and Sanitation

Deep Well Boring

UN-Habitat

Completed Operation and maintenance plan was available in the document. Based on plan, CDC had to collect 96.8 AFN/month from each family for operation and maintenance, but they couldn't follow the plan because community can't support the fuel cost for

Page 21: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-20

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Baghlan IRD-NS-74088 13-1301-0047-2-a

Rural Development

Community Center Construction

ACTED Completed Based on operation and maintenance plan, community is going to collect 10 AFN per month from each family, but it was not implemented yet.

Kapisa IRD-NS-71940 02-0202-0035-2-a

Rural Development

Community Center Construction

UN-Habitat

Ongoing Operation and maintenance plan was available in the document. Based on plan, CDC will collect 116 AFN/month through donation box. Per CDC information, they didn't established donation box yet, but they will establish after completion.

Logar IRD-NS-72538 05-0505-0069-2-a

Transport Pathway Construction

IRC Ongoing An agreement letter signed by CDC members which indicates that they are responsible for project future maintenance, but the mechanism was not specified.

Nangarhar IRD-NS-73269 08-0802-0005-2-a

Education Primary School Building Construction

BRAC Completed Project was completed, and it was operational. Maintenance plan was available, per plan each family should pay 22 AFN per year to maintain the project. But, this was not a realistic maintenance plan, because project was handed over to ministry of education (MoE) after completion, and they are responsible for the maintenance.

Jawzjan IRD-NS-75229 17-1702-0008-2-a

Transport Tertiary Road Graveling

Action Aid Completed Operation and maintenance plan was available at job site, per plan each family to pay 120 AFN per month for project maintenance, but per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic.

Logar IRD-NS-72521 05-0505-0011-2-a

Irrigation Water Reservoir Construction

IRC Ongoing An agreement letter signed by CDC members which indicates that they are responsible for project future maintenance, but the mechanism was not specified.

Nangarhar IRD-NS-73014 08-0821-0093-2-a

Education Community Center Construction

BRAC Ongoing Project was not completed, and it was not operational. Maintenance plan was available, per plan each family should pay 25 AFN per year to maintain the project. But, this was not a realistic maintenance plan, because project will be handed over to ministry of education (MoE), and after completion, the MoE will be responsible for the maintenance.

Hirat IRD-NS-76069 20-2002-0145-2-a

Education Primary School Building Construction

UN Habitat

Ongoing Project was not completed, and it was not operational. Maintenance plan was available, per plan each family should provide 5 Kg wheat annually, but, this was not a realistic maintenance plan, because project will be handed over to ministry of education (MoE), and after completion, the MoE will be responsible for the maintenance.

Nimroz IRD-NS-77970 22-2202-0053-2-b

Water and Sanitation

Hand Pump Installation

RI Ongoing The project design and proposal was approved by PMU, but operation and maintenance plan was not available.

Khost IRD-NS-78463 32-3206-0043-2-b

Irrigation Protection Wall Construction

IRC Completed Project was completed, and it was operational. Maintenance plan was available; per plan each family should pay 50 AFN in each month for maintenance. Per site observation and IRD's previous experience of visiting similar projects, the plan is not realistic. Per CDC information, they established donation box, and collected 5000 AFN so far, will maintain the project through that donation box.

Page 22: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-21

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Hirat IRD-NS-76760 20-2002-0129-2-a

Water and Sanitation

Water Supply Network Construction

UN-Habitat

Ongoing Operation and maintenance plan was not available, but based on community whenever they install the meters, so community should pay based per water consumption.

Kunar IRD-NS-73174 10-1012-0043-2-b

Irrigation Protection Wall Construction

MADERA No Project was completed, but 20m long wall of first section and constructed part of third section were ruined by flood water, and CDC has owned to construct the ruined part of the protection wall. Per site inspection, constructed part was operational, and maintenance plan was available. Per plan each family should pay 20 AFN annually to maintain the project, but this plan was not a realistic maintenance plan and mentioned amount was not yet collected.

Page 23: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-22

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex EDeficiencies Recommended for Action

Issue Type Issue

Description Project tittle Province

IRD subproject

Number

NSP/ MRRD

subproject ID

Facilitating Partner

Date observed by IRD and

reported to WB

Date corrective action by

NSP/ MRRD

IRD Recommendations

NSP/FPs Feedback

Quality/Design

The following deviations observed: 1) Oversize round stones and gravel observed along the road surface, by passage of the time and movement of the vehicles the oversize round stones and gravel will be displaced from the road alignment. 2) Both sides cross slope was considered in design but wasn't applied. 3) Concrete cap was placed with 5 cm thickness, while 10 cm thick cap was required per NSP standard design/specification. 4) Culvert No 3 downstream headwall was destroyed by traffic incident. 5) Culvert No 4 upstream and No 5 downstream headwalls were partially damaged. 6) Culvert No 7 downstream wingwalls were missing. 7) Per site condition drain was needed which was not considered in design drawing. 8) Culvert No 13 between edge slabs gap was observed due to improper slab placement.

Retaining Wall, Culvert & Tertiary Road

Parwan IRD-NS-71013

03-0301-0012-2-a

UN-Habitat

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

The following deviation observed: 1) 47 m long concrete cap was placed with 5 cm thickness while per standard NSP specification, theckness of cap should be 10 cm. 2) Culvert abutment wall pointing was missed. 3) Headwalls were specified in design of slab culvert, but were missed.

Pathway Construction

Parwan IRD-NS-72028

03-0301-0064-2-a

UN-Habitat

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

The following deviations observed: 1) Gate controllers weren’t installed, instead of gate controllers chain were installed, which affect function of the gate. 2) Protection wall

Intake, Protection Wall, and Canal Construction

Ghor IRD-NS-78533

27-2709-0025-2-a

Afghan Aid

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Page 24: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-23

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

concrete cap at location No 1, 2, 3, 4 & 5 were placed with 5-8 cm thickness, while 10 cm was specified in NSP standard design/specification, and segregation was observed in different points of capping. 3) Protection wall expansion joints were not specified in design drawing, while it was required after 10m per NSP standard specification/design.

Quality/Design

The following deviations observed: 1) Protection wall at location No 1, canal and supper passage concrete cap was placed with 2-6 cm thickness, while 10 cm was specified in design drawing. Cap was observed with poor workmanship. 2) Expansion joint was not specified in design of protection wall, while it was required after 10 m per NSP standard specification/design. 3) Protection wall concrete cap was missing at location No 2, while 10 cm thick cap was required and specified in design drawing. 4) Pointing of 15m canal was missing, and may cause of canal side wall damage. 5) Intake weir apron concrete was damaged due to poor quality. 6) Supper passage slab re-bars were not properly bent and should have to be cut. 7) Aqueduct wingwalls concrete cap was missing.

Protection Wall, Intake, Canal, Supper Passage, and Aqueduct Construction

Ghor IRD-NS-60333

27-2709-0013-2-a

Afghan Aid

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Design The following deviation observed: 1) Expansion joints were not specified in design drawing while it was required after 10 m c/c per NSP standard design/specification.

Protection Wall Construction

Kunduz IRD-NS-76227

14-1405-0006-2-b

GRSP 10-Feb-2015 NSP to assure implantation of the specification in design drawing.

Quality/Design

The following deviations observed:

1) Typical road design has been used, which do not conform to site

condition. 1) Stone masonry

open channel concrete cap was placed with 7 cm thickness while 10 cm thick was required

per NSP standard design/specification. 2) Location-3 stone

masonry channel with top cover space was

observed between two

Pathway, Protection Wall, and Tertiary Road Graveling

Kabul IRD-NS-71555

01-0108-0015-2-a

SDO 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Page 25: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-24

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

slabs placement which was not placed

properly.

Quality/Design

The following deviations observed: 1) Culvert design was not matching with site condition. 2) Concrete cap of protection wall No 1 & 2 was placed with 7 cm thickness while 10 cm was specified in design drawing. 3) Protection wall No 2 expansion joint and weep holes were not constructed while it was specified in design drawing. 4) Culvert No 1 stone masonry set chair was constructed for slab placement while reinforced concrete set chair was specified in design drawing. 5) Section-I road thickness observed with 11 cm while 15 cm was required per NSP standard specification. 6) Section-I road side ditch concrete cap was placed with 7 cm thickness while 10 cm thick was required per NSP standard design/specification.

Tertiary Road Graveling, Protection Wall, and culverts Construction

Kabul IRD-NS-71623

01-0108-0005-2-a

SDO 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

The following deviations observed: 1) Culvert No 1 abutment walls pointing and wingwalls were missing. 2) Protection wall location No 1 and 2 concrete cap was placed with 2 cm Design thickness while 10 cm was required per NSP standard design/specification, and expansion joints were missing.

Culvert, Pathway, and Protection Wall Construction

Kabul IRD-NS-71625

01-0108-0006-2-a

SDO 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Design Water reservoir No 1 and 2 ventilation pipe was missing while it was specified in design drawing.

Water Supply Reservoir Construction

Jawzjan IRD-NS-80520

17-1702-0017-2-b

Action Aid

10-Feb-2015 NSP to assure implantation of the design/specification.

Quality/Design

The below deviations observed; 1) concrete cap of 10 cm thickness had been specified in design, but it was placed with 8 cm thick 2) Backfilling was missed at some points 3) Expansion joints were not filled by expandable material even it was not constructed at one portion.

Protection Wall Construction

Laghman IRD-NS-70673

09-0902-0040-2-C

MADERA

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality 1) Boring well has been changed to boundary wall, but the revised scope and PMU approval was not available.

Community Center Construction

Kabul IRD-NS-83455

01-0108-0067-2-a

SDO 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specificati

Page 26: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-25

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

2) Brick masonry of the boundary wall was not textured properly at some points.

on.

Quality/Design

The below deviations observed; 1) Pipe was leaked at two points. 2) Control valve of network was missed at one point.

Water Supply Network Construction

Ghor IRD-NS-81113

27-2702-0021-2-a

Afghan Aid

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

The below deviations observed at third network. 1) Valve control box of (1x1x1) m dimensions was specified in design, but constructed with dimension of (1x1x0.8) m. 2) Side wall of 50 cm width had been specified in design, but it was constructed of 35 cm. 3) Reinforced concrete slab and ring of third reservoir was placed in cold weather without any measures.

Water Supply Network Construction

Ghor IRD-NS-77372

27-2702-0024-2-a

Afghan Aid

10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

Following deviations were observed: 1) Design thickness of concrete cap was 10cm, but placed with (5-8) cm thick. 2) Compaction was considered in BoQ, but was not done.

Tertiary Road Basic Access and Retaining wall Construction

Khost IRD-NS-78390

32-3203-0022-2-a

IRC 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Quality/Design

Following deviations and findings were observed during project inspection: 1) Design width of road was 4m, but was 3.5m in some parts. 2) Design size of expansion joint was 3cm, but constructed 10cm, which did not conform to NSP specification.

Tertiary Road Graveling, Retaining wall and Causeway Construction

Khost IRD-NS-79225

32-3203-0018-2-a

IRC 10-Feb-2015 To remove the defects, and NSP to assure implantation of the design/specification.

Design Expansion joints were needed to be considered along the protection wall, but it was neither considered in design nor constructed.

Protection Wall Construction

Daikundi IRD-NS-70238

34-3409-0033-2-b

Oxfam 10-Feb-2015 NSP to assure implantation of the specification in design drawing.

Quality Expansion joints were constructed, but it was not filled by expandable material and the width was not uniform along the height.

Pipe Scheme Construction

Daikundi IRD-NS-70250

34-3409-0013-2-a

Oxfam 10-Feb-2015 To remove the defects.

Quality/Design

Ventilation and overflow pipes were missing at job site.

Water Supply Reservoir Construction

Kabul IRD-NS-83487

01-0108-0063-2-b

SDO 10-Feb-2015 NSP to assure implantation of the design/specification.

Quality Cross slope was not applied in most points along the road which can be caused of road damage during rain.

Tertiary Road Basic Access

Daikundi IRD-NS-70272

34-3409-0006-2-a

Oxfam 10-Feb-2015 NSP to assure implantation of the design/specification.

Quality The cross slope was not applied at some points. Road surface was damaged at some points due to lack of

Tertiary Road Basic Access

Daikundi IRD-NS-78794

34-3409-0004-2-c

Oxfam 10-Feb-2015 NSP to assure implantation of the design/specification.

Page 27: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-26

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

cross slope.

Quality/Design

Wooden planks were specified in design of latrine roof, but were missing at some latrines, and instead tree branches were used.

Shallow Well Boring and Latrine Construction

Daikundi IRD-NS-78793

34-3409-0004-2-a

Oxfam 10-Feb-2015 NSP to assure implantation of the design/specification.

Quality Downspout was not installed for latrine # 11, which caused damage of side wall.

Latrine Construction

Daikundi IRD-NS-70237

34-3409-0032-2-b

Oxfam 10-Feb-2015 NSP to assure implantation of the design/specification.

Quality 1) Expansion joints were constructed after each 15 m c/c, but it

was not filled by expandable material.

Gabion Wall and Retaining Wall Construction

Kapisa

IRD-NS-71842

02-0202-0063-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and filled the joints by expandable material.

Quality/Design

The following deviation observed:

1) Section C-C, B-B, and A-A concrete cap was placed with 5 cm thickness while 10 cm thick was required per

NSP standard design/specification. 2) Section C-C, B-B, and A-A expansion

joints and weep holes were not specified in design drawing nor constructed, while

expansion joints were required after 10 m c/c

per NSP standard design/specification.

3) Section B-B retaining wall was

settled due to weak material of foundation and lack of expansion

joints.

Retaining wall, Culvert construction, and Road Graveling

Parwan IRD-NS-72027

03-0301-0055-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

The following deviation observed: 1) Section A-A and B-B concrete cap was placed with 5 cm thickness while 10 cm thick was required per NSP standard design/specification. 2) Section A-A and B-B expansion joints and weep holes were not specified in design drawing nor constructed, while expansion joints were required after 10 m c/c per NSP standard design/specification.

Retaining Wall, Pathway, and Culvert Construction

Parwan IRD-NS-72026

03-0301-0050-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality The following deviations observed: 1) Apron soak pit of shallow well No 1, 3, 4, 5, and 6 were missing, while it was specified in design. 2) Apron run-off channel of shallow well No 5 was missed, while it was specified in design.

Shallow Well Boring

Kunduz IRD-NS-75560

14-1406-0112-2-b

GRSP 10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Design Expansion joints were missing along the retaining wall.

Retaining wall & Side Ditch

Kandahar IRD-NS-80959

24-2404-0013-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the

Page 28: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-27

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Construction design/specification

Quality 1. The precast slabs were not placed properly, observed with below average workmanship. 2. Side ditch side wall segregation was observed on concrete surface.

Side Ditch Construction

Kandahar IRD-NS-77750

24-2404-0043-2-b

UN-Habitat

10-Mar-2015 To remove the defects.

Design The expansion joints and weep holes were missing at job site.

Protection Wall Construction

Kandahar IRD-NS-78330

24-2402-0008-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Design The weep holes were missing at job site.

Protection Wall Construction

Kandahar IRD-NS-80945

24-2402-0016-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

1- Concrete cap was placed with 5 cm thickness while 10 cm thick was required per NSP standard design/specification. 2- Weep holes were missing at job site.

Protection Wall Construction

Kandahar IRD-NS-77689

24-2402-0047-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Design Per design drawing of protection wall, expansion joints to be constructed in each 30 m c/c, while it was required after each 10 m c/c per NSP standard design/specification, and it was missing along the wall in different segment.

Protection Wall and Water Divider Construction

Kandahar IRD-NS-77691

24-2402-0052-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

Honeycombing was observed on concrete surface. 100 m canal was constructed with 0.2 m canal side walls while design dimension was 0.3 m.

Canal and Water divider Construction

Panjsher IRD-NS-78526

33-3301-0003-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

The below deviation has been observed; 1) Longitudinal slope was not specified in design. 2) Bottom face of slab oversize gravel was observed.

Canal Construction

Hirat IRD-NS-46803

20-2002-0076-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

the below deviations has been observed; 1) Concrete cap of 5 cm thickness had been specified in design, but it was placed (2-4) cm while it was required with 10 cm per NSP standard design/specification. 2) Cracks were observed at some points of concrete cap.

Canal Construction

Panjsher IRD-NS-79479

33-3301-0033-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

2) Concrete cap was placed of (2-4) cm while 10 cm thick was required per NSP standard design/specification. 3) At some points canal bed concrete was not placed.

Canal Construction

Panjsher IRD-NS-79475

33-3301-0012-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Page 29: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-28

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Design 1: Weep holes had been specified in design, but not constructed on site.

Retaining Wall Construction

Hirat IRD-NS-46883

20-2002-0102-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

1: Expansion joints were constructed after each (20-25) m, while it was required after each 10 m c/c per NSP standard design/specification 2: Expansion joints had not been constructed in 2nd portion.

Retaining Wall Construction

Hirat IRD-NS-76329

20-2010-0015-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

1) Stone masonry retaining wall of 70 cm height had been specified in design at one point, but per site requirement it was constructed of more than 2 m height without any ring beam, potential risk may the wall collapse and cause deaths or injuries . 2) Honeycombing was observed at some points of pathway.

Pathway Construction

Panjsher IRD-NS-81434

33-3301-0020-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

1: Segregation was observe at concrete beam might be due to poor shuttering. 2: Design was not matching with site because both culverts of (5x3x2) m dimensions had been specified in design, but it was constructed of (4.3x4.3x3) m.

Culvert Construction

Hirat IRD-NS-46823

20-2002-0084-2-b

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification

Quality/Design

1) Segregation and crack were observed at some points in concrete canal. 2) Concrete cap of 5 cm thickness had been specified in design, while 10 cm thick was required per NSP manual, and it was placed with 2 cm, and cracks were observed at some points as well. 3) Per site condition backfilling required, but neither specified in design nor done on site.

Canal Construction

Panjsher IRD-NS-68182

33-3301-0030-2-a

UN-Habitat

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality 1: Honeycomb was observed at parapet wall's concrete might be lack of vibration.

Community Center Construction

Kabul IRD-NS-70549

01-0105-0049-2-b

SDO 10-Mar-2015 To remove the defects.

Quality 1: Steel of ring beam was not covered at one point. 2: Parapet wall concrete's steel was not covered properly and honeycombing was observed at one point.

Community Center Construction

Kabul IRD-NS-71446

01-0105-0003-2-a

SDO 10-Mar-2015 To remove the defects.

Quality 1) Plumbing of bathrooms were missed.

Community Center Construction

Hirat IRD-NS-77347

20-2002-0083-2-b

UN-Habitat

10-Mar-2015 To remove the defects.

Quality 1) Ring beam steel bar was not covered at some point, and

Community Center Construction

Panjsher IRD-NS-78540

33-3301-0015-2-a

UN-Habitat

10-Mar-2015 To remove the defects.

Page 30: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-29

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

honeycomb was observed.

Quality/Design

Two dug wells were specified in design, and excavation of well was still on-going, but CDC has already constructed apron and placed RCC rings.

Shallow Well Boring

Kunar IRD-NS-79844

10-1012-0047-2-b

MADERA

10-Mar-2015 NSP to assure to sequence of construction activities.

Quality Expansion joint was placed at each 10m distance, but was not filled by expandable materials. 2) Designed thickness of concrete cap was 10cm, but constructed 7-8cm.

Protection Wall Construction

Khost IRD-NS-78444

32-3206-0004-2-a

IRC 10-Mar-2015 To remove the defects.

Quality/Design

1) Apron shapes were not conformed to design. 2) Run-off channels and soak pits were specified in design, but were not constructed.

Shallow Well Hand Dug

Kunar IRD-NS-73688

10-1016-0030-2-b

MADERA

10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

Shutters of two doors were not painted. Installation of bulbs/lights were specified in BOQ, but were missed at job site.

Community Center Construction

Paktya IRD-NS-17335

07-0722-0015-2-a

CARE 10-Mar-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality 1) Site cleaning process was left in most of culverts. 2) Form-work of some culverts weren’t done properly. During placing of concrete, bottom surface of slab was not leveled due to poor workmanship of form-work. Segregation and honeycombing were observed in some culverts.

Tertiary Road Graveling and Culverts Construction

Paktya IRD-NS-74556

07-0705-0116-2-a

CARE 10-Mar-2015 To remove the defects.

Quality Apron was specified in design for third culvert, but was missed at job site.

Culvert Construction

Khost IRD-NS-81409

32-3206-0048-2-b

IRC 10-Mar-2015 To remove the defects.

Quality Designed thickness of concrete cap was 10cm, but constructed 7cm at some points.

Protection Wall Construction

Paktya IRD-NS-17366

07-0722-0026-2-b

CARE 10-Mar-2015 To remove the defects.

Quality/Design

The following deviation observed: 1) Ventilation pipe hole was constructed on the top of cover slab, but pipe installation was missing while it was required. 2) Overflow pipe was not specified in design drawing while it was required.

Deep Well Boring

Kapisa IRD-NS-71939

02-0202-0034-2-b

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality The following deviations observed: 1) Apron soak pit of

shallow well No 1, 2, 4, and 5 were missing,

while it was specified in design.

2) Shallow well No 4 Pamir hand pump was

installed, but it was damaged, and stored in one of CDC members

house. water pump was installed, except

Shallow Well Boring

Kunduz IRD-NS-35521

14-1405-0034-2-b

GRSP 10-Apr-2015 To remove the defects.

Page 31: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-30

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

few families, the intended beneficiaries

may not benefit. 3) Shallow well No 5

Pamir hand pump riser rod was damaged and

need to repair. 4) Dry latrine Windows

fly screen was specified in BOQ, but it

was missing. 5) Dry latrine squat

hole cover and ventilation pipe fly screen were not

available, while it was specified in BOQ.

Quality The following deviations observed: 1) Shallow well No 1, 5, 6, and 8 soak pit was specified in design of apron but was missing. 2) Shallow well No 3 and 6 Pamir hand pump was damaged, and needed to be repaired. 3) Shallow well No 4 apron run-off channel was constructed, but it was not matching with design drawing. 4) Shallow well No 8 and 9 hand pump riser rod was damaged and need to repair.

Shallow Well Boring

Kunduz IRD-NS-36012

14-1406-0087-2-b

GRSP 10-Apr-2015 To remove the defects.

Quality/Design

The following deviation observed: 1) Inadequate mortar was used between stones which was not conformed with specification (30%-35%). 2) Concrete cap was placed with 5 cm thickness according to design drawing, but 10 cm thick was required per NSP standard design/specification. 3) Expansion joints were specified after 15 m c/c in design drawing, but it was not constructed, while it was required after 10 m c/c per NSP standard design/specification. 4) Weep holes weren’t specified in design drawing nor constructed, while it was required per NSP standard design/specification. 5) Side ditch side walls concrete cap was placed with 5 cm thickness according to design drawing, but 10 cm thick was required per NSP standard design/specification. 6) Culvert No 3 stone masonry set chairs were constructed for

Culvert, Retaining wall, & Road Graveling Construction

Kapisa IRD-NS-71847

02-0202-0088-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Page 32: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-31

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

slabs placement with poor quality while reinforced concrete set chairs were specified in design drawing. 7) Culvert No 4, 5, and 6 set chairs were constructed for slabs placement with poor quality while it was not matching with design drawing. 8) Culvert headwalls were missing while it was specified in design drawing.

Quality/Design

The following deviation observed: 1) Retaining wall concrete cap was placed with 5 cm thickness, but 10 cm thick was required per NSP standard design/specification. 2) Expansion joints and weep holes were not constructed, while joints were required after 10 m c/c per NSP standard design/specification. 3) Section-I and II along the road surface over size gravel observed which was not conform to specification. 10 cm first layer material was placed, while 10 cm second layer was remaining. 4) Culvert No 5 headwalls were specified in design drawing, but it was missing. 5) Side ditch concrete cap was placed with 5 cm thickness, but 10 cm thick was required per NSP standard design/specification.

Retaining Wall, Culvert & Road Graveling

Parwan IRD-NS-72097

03-0301-0049-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Design Length of first and second sections of protection wall was

189m and 214m respectively, but

expansion joints were neither specified in

design nor constructed.

Protection Wall and Canal Construction

Kunar IRD-NS-75208

10-1012-0018-2-a

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification.

Design Length of each segment of retaining

wall was 43m and 29m, but expansion joints

were neither designed nor constructed.

Pathway Construction and Retaining wall Construction

Kunar IRD-NS-73658

10-1012-0036-2-a

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification.

Quality. At one point of

protection wall, small stones were used at

bottom and big stones on the top.

Pathway Construction and Retaining wall Construction

Kunar IRD-NS-73659

10-1012-0036-2-a

MADERA

10-Apr-2015 NSP to assure implantation of the specification.

Page 33: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-32

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Design Expansion joints were constructed, but were

not filled by expandable materials to prevent from water losses.

Canal Construction and Protection wall Construction

Laghman IRD-NS-84753

09-0902-0143-2-a

MADERA

10-Apr-2015 To remove the defects.

Quality/Design

1) 16-inch diameter drilling machine was

considered for drilling, but each well was drilled by 12-inch diameter boring

machine. 2) Rectangular shape

apron with size of (2.8x1.8) m was

specified in design, but constructed trapezoidal shape apron at job site, which did not conform

to NSP design. 3) Ruf-off channel was constructed for well #1, but did not conform to

NSP design. 4) 4-inch diameter

PVC pipe was installed instead to construct

Run-off channel of well #2.

5) Soak pits were specified in design, but was missed for 1st well and was not required

for second per site condition.

Shallow Well Boring

Laghman IRD-NS-73479

09-0902-0009-2-a

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

1) Design length, diameter and thickness of penstock was 5.6m,

40cm and 5mm respectively, but

installed with 4.6m length, 40cm diameter and 4mm thickness.

2) Power house steel I-beams were not anti-

corrosion painted.

Micro-Hydro Power Plants Construction

Kunar IRD-NS-79845

10-1012-0051-2-a

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

1) Design top width of first section of retaining

wall was 0.6m, but constructed 0.5m.

2) Design thickness of concrete cap was

10cm, but constructed 5cm with poor

workmanship. Concrete segregation was

observed. 3) Expansion joints were specified in

design at each 20m distance, and

constructed but were not filled by expandable

materials. 4) Weep holes were required, but neither

designed not constructed, but

observed more than 10cm at some points.

Retaining Wall Construction and pipe Culvert

Nangarhar IRD-NS-79654

08-0818-0015-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality 1) Gaps observed

between the stones of stone masonry

protection wall first

Canal and Protection Wall

Laghman IRD-NS-79741

09-0902-0084-2-a

MADERA

10-Apr-2015 To remove the defects.

Page 34: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-33

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

segment, indicates adequate amount of mortar was not used during stone masonry

work. 2) Backfilling was specified, but was

missed at first segment of protection wall. 3) Concrete cap

second segment of canal was constructed

from the mixture of sand and cement only, and most of parts were being damaged due to poor material quality. 4) Backfilling of first

segment of canal was missed.

5) Adequate amount of longitudinal slope was not considered during

second segment of canal construction and

water could not flow smoothly.

6) Pointing was missed at some point of second segment of

canal.

Construction

Quality 1) Cracks were observed in the bottom steps of stairs, also the height of rise was vary from 15-18cm, which

standard height of rise was 15cm in design.

2) Per Ministry of Education specification,

classrooms' doors should be open to

corridor side, but were installed which is being

opened to inside of classrooms, which did not conform to MoE

specification. 3) Re-bars of columns at the top of roof were

not bonded. 4) Earthing ground

system was specified, but was missed during building construction. 5) Double-rod neons

were specified in design, but ordinary bulbs were installed

which did not conform to MoE specification. 6) Shutter of some

windows were not fixed properly and some

gaps were observed between shutters and frames of windows, which may result of

dusting inside classes. 7) Wooden windows were specified, but

metal windows were installed.

Primary School Buiding Construction

Herat IRD-NS-76069

20-2002-0145-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the specification and to remove the defects.

Design 1) 8 doors, 7 with size of (1x2.5) m and one

size of (2x2.5) m were specified in design, but

5 doors of size of

Community Center Construction

Laghman IRD-NS-74968

09-0902-0096-2-b

MADERA

10-Apr-2015 NSP to assure implantation of the design.

Page 35: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-34

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

(1x2.5) were installed, and designed size

width of bathrooms' doors was 1m, but reduced to 0.8m.

2) Design size of each bathroom was (2.4x2.8) m, but both bathrooms

were constructed of (1.2x2) m size each.

Quality 1) Pointing of second segment of protection wall was done by hand without using of some

specific tools of pointing.

2) Backfilling was not done entirely per

specification, and some parts of back side was

remained from backfilling.

Protection Wall Construction

Khost IRD-NS-78463

32-3206-0043-2-b

IRC 10-Apr-2015 To remove the defects.

Quality/Design

Expansion joint was specified at each 10cm

distance, but were missed at job site.

Retaining Wall Construction

Kunar IRD-NS-73648

10-1012-0004-2-b

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification.

Quality/design

1) Per IRD field observation, because

of missing of backfilling at first section, 20m wall was ruined by

flood. 2) Expansion joint was specified at each 10m

distance, but was missed at job site. 3) Backfilling of

second segment was specified and required per site condition, but was missed at job site.

Protection Wall Construction

Kunar IRD-NS-73174

10-1012-0043-2-b

MADERA

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality 1) A portion of re-bars safety ring for reservoir ladder was damaged.

2) A manhole for water reading meter was

supposed to be constructed from kilned

brick masonry, but it was constructed from bricks with mud mortar and observed with poor

material quality and workmanship.

Water Supply Network Construction

Hirat IRD-NS-47107

20-2002-0176-2-a

UN-Habitat

10-Apr-2015 To remove the defects.

Quality/Design

1) Apron of well # 1 observed with

inadequate concrete thickness, with poor material quality and

workmanship, segregation was

observed.

2) Apron soak pit and run-off channel of well # 1 do not match with

design. 3) Indus hand pump

was specified in design, but Kabul pump was installed on well #

1. 4) Top cover slab of

Shallow Well Digging

Bamyan IRD-NS-81239

28-2801-0073-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Page 36: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-35

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

well # 1 was observed with poor material

quality and workmanship, steel were exposed and

crack was observed. 5) Due to poor quality

of material & workmanship, the

apron concrete of well # 2 has been damaged.

6) Apron run-off channel of well # 2 was

with poor material quality and

workmanship, cracks were observed and don not match with design.

7) Hand pump was fixed close to cover slab manhole, might

damage during pumping, and cover was bigger than top

ring. 8) 52 reinforced

concrete rings had been specified in

design for both wells, but cast-in- place

unreinforced concrete was placed.

9) Well # 1 was dug in a private compound.

Quality 1: Wingwalls concrete cap of both culverts

with 10 cm thickness had been specified in

design, but it was placed of (3-5) cm, and

segregation was observed as well.

Culvert Construction

Bamyan IRD-NS-78989

28-2801-0055-2-c

UN-Habitat

10-Apr-2015 To remove the defects.

Quality/Design

1) Wooden planks of 5 cm thickness had been specified in design for

the deck, but those were placed of 3 cm.

2) Space was observed between planks.

Footbridge Badghis IRD-NS-69912

19-1901-0058-2-a

NPO-RRAA

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality 1) Brick masonry texture was not done

properly at some points.

2) Segregation was observed at some

points of columns might be due to lack of

vibration. 3) Grid beam steel was

not covered and segregation was

observed as well might be due to lack of

vibration. 4) Interior plaster was completed, but cracks were observed at two

points.

Community Center Construction

Bamyan IRD-NS-78606

28-2801-0053-2-a

UN-Habitat

10-Apr-2015 To remove the defects.

Quality 1: Locks of windows and doors were with

poor quality. 2: Painting of the

partition wall of store was with poor material

Community Center Construction

Badghis IRD-NS-69866

19-1901-0011-2-a

NPO/RRAA

10-Apr-2015 To remove the defects.

Page 37: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-36

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

quality and workmanship.

3: Doors and windows were painted two coats,

prime coat was not applied, and the quality was poor, while three

coats were specified in proposal.

Quality 1) A beam observed with deflection in the

center, might be due to shuttering during

placing concrete, but no crack observed. 2) Slope was not

properly applied on roof, and rain water

was standing on water membrane (IZOGAM), and may damage the

IZOGAM. 3) Water membrane

(Izogam) was disported from slab concrete at

some points.

Community Center Construction

Badghis IRD-NS-69898

19-1901-0038-2-a

NPO-RRAA

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

1) Cross-slope was not applied at some points. 2) Based on community

request and PMU approval they ignore the side ditch, but it

was required per site condition.

3) 700 m long tertiary road basic access had

been specified in design, but actually it

was 400 m long on the site which was a

survey/design mistake.

Tertiary Road Basic Access

Bamyan IRD-NS-78984

28-2801-0028-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Quality/Design

Concrete Segregation was observed on

culvert #1, 2, and 3 slab and steel bars were not covered properly in culvert

headwalls. Right side abutment wall of culvert

# 6 was constructed shorter than other side,

and headwall and precast slabs were supported on round

stones. Typical culvert design was used, and was not matching with site condition, and the

culverts were constructed per site

condition.

Retaining Wall Construction

Parwan IRD-NS-71014

03-0301-0016-2-a

UN-Habitat

10-Apr-2015 NSP to assure implantation of the design/specification and to remove the defects.

Page 38: Third Party Monitoring - BRAC NSP TPM...The lowest graded project inspected in March was a hand dug shallow well project (IRD-NS-81239) in Bamyan Province facilitated by UN Habitat.

         

NSP-37

 

International Relief & Development Afghanistan Reconstruction Trust Fund Monitoring Program

Annex F Projects without a construction quality certificate

IRD Project

ID MRRD

Sub-project ID Project Sector Project Title

Facilitating Partner

Project Status

IRD-NS-76894 24-2402-0014-2-a Rural Development

Community Center Construction

UN-Habitat Ongoing, 55% progress

IRD-NS-77686 24-2402-0038-2-a Rural Development

Community Center Construction

UN-Habitat Ongoing, 60% progress

IRD-NS-80517 17-1702-0003-2-a Rural Development

Community Center Construction

Action Aid Ongoing, 98% progress

IRD-NS-74968 09-0902-0096-2-b Rural Development

Community Center Construction

MADERA Ongoing, 90% progress

IRD-NS-78606 28-2801-0053-2-a Rural Development

Community Center Construction

UN-Habitat Ongoing, 70% progress

IRD-NS-69898 19-1901-0038-2-a Rural Development

Community Center Construction

NPO-RRAA Ongoing, 90% progress

IRD-NS-71940 02-0202-0035-2-a Rural Development

Community Center Construction

UN-Habitat Ongoing, 95% progress

IRD-NS-70692 05-0505-0098-2-b Rural Development

Community Center Construction

IRC Ongoing, 92% progress

IRD-NS-30077 12-1206-0005-2-a Rural Development

Community Center Construction

CONCERN Ongoing, 65% progress