Theta Earth Dam
-
Upload
drebighead -
Category
Documents
-
view
259 -
download
5
description
Transcript of Theta Earth Dam
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
ATHI WATER SERVICES BOARD
THETA WEIR IN GATUNDU SOUTH DISTRICT
GATUNDU SOUTH WATER AND
SANITATION COMPANY
DESIGN REPORT AND DRAWINGS
Consultant: Client:
Eng. Peter Njurumba Chief Executive Officer, P.O. Box 212 00206, Athi Water Services Board, KISERIAN Africa Re Centre, Hospital Road, September, 2010 NAIROBI
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
1 EXECUTIVE SUMMARY
In mid eighties and early nineties, parts of Kiganjo, Kiamwangi and Ngenda used to be supplied
with water by Thiririka Water Project which was constructed by the Director Labour Section of
the then Ministry of Water Development. Other water supply schemes that were constructed by
the Ministry within the vicinity of this area were Ndarugu, Karimenu and Juja. The projects
served the communities for a while, but as populations exploded with time and water demand
parameters rose, the water demand outstripped the supply thereby necessitating water rationing
wihin the supply areas. This situation called for quick intervention measures which included
tapping water from the pipeline destined for Nairobi. Some of the major centers served by
pipeline were Gatundu Town and Ichaweri and the communities along the corridors of the
pipeline. At the same time, the water demand in the city kept on increasing against decreasing
water supply parameters caused mainly by fluctuating water levels in the river courses caused
primarily by prolonged dry spells and climate change. This called for quick disconnection of the
areas that were being served by the pipeline which in return aggravated the water supply
situation.
Against the above background and in order to meet the water demand, Gatundu South Water and
Sanitation Company which is the local Water Service Provider (WSP) appointed by the Athi
Water Services Board conceived the idea increasing storage to cater for the rural population and
thus achieve its objective. This policy was to be achieved by way of constructing Theta Dam that
would regulate the flows of the river and thus enhance water supply to the demand areas. In this
connection, the Client has procured a consultancy service which is aimed at carrying out the
necessary studies in terms of feasibility study, preliminary and final designs and preparation of
tender documents. The client was supposed to carry out an environmental impact assessments of
the project with a view to determining its technical, economic and environmental viability.
Athi Water Services Board through its Water Service Provider namely Gatundu South Water and
Sanitation Co. Ltd commissioned a Consultant to carry out the design of Theta Dam in Gatundu
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
South District which is one of the areas within the jurisdiction of the board. The other areas
under the mandate of the board are Nairobi, Thika, Gatundu North, Lari, and Limuru.
As a first step towards the design f the project, the consultant visited the site together with
officers from Gatundu South Water and Sanitation Office and identified a suitable dam site
within the Kikuyu Escarpment Forest just about 11 km from Mundoro Town Center.
Engineering considerations have shown that the dam is 17m high and it can command a storage
capacity of about 1,170,000m3.
Water Resources Assessment
The reservoir is located in an area that receives about 1015mm and 1270mm annually, with a
mean value of 1180mm per annum. From the flow duration curve, the 50% flow is about
0.23m3/sec which translates to 19,872m
3/day. From the envelop curve, the flow for the same
return period is equal to Kikuyu Escarpment Forest. The Q(80) and Q(95) flows are 17,194 m3/day
and 6,739 m3/day respectively. The raw water looks very palatable and clear and therefore
requires very little treatment. During the initial stages, chlorination may be the only form of
treatment required while a conventional water treatment plant for a capacity of 8,000m3 per day
may be constructed in future.
Geotechnical and Geological Study
Theta Dam is located in the thicket of the Kikuyu Escarpment Forest where there are good soils
for the construction of an earthfill dam. However, in view of the height of the dam which is 15m,
the dam enters into the category of large dam according to the classification of dams by the
World Commission on Dams. In this regard, the design work has to be stringent especially in the
area of eradication of seepage under the foundation and embankment wall. In order to minimize
seepage through the foundation, pressure grouting with cement and bentonite is essential while
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
seepage through the embankment wall will be controlled through good workmanship in terms of
quality control during construction.
Estimated Project Costs
The estimated cost of the project is Ksh. which covers the construction of the
river diversion system, embankment wall with the filters and riprap material, open channel
spillway together with the energy dissipater, intake tower and the draw off system.
Conclusion
The study shows that the construction of the proposed dam is technically and economically
feasible since it will alleviate the water scarcity situation in the supply areas and hence enhance
water and sanitation services as well as social economic development and, therefore, improve the
living standards of the local communities.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
TABLE OF CONTENTS
Design of Theta Weir .......................................................................................................... 2 1. Background Information .............................................. Error! Bookmark not defined.
2. Location ......................................................................................................................... 7 3. Sediment Loads ............................................................ Error! Bookmark not defined. 4. Engineering Design and Construction of Theta Weir .. Error! Bookmark not defined. 5. Scope of works ............................................................. Error! Bookmark not defined.
5.1 STAGE I ................................................................ Error! Bookmark not defined.
5.1.1 Desk Study ................................................... Error! Bookmark not defined. 5.2 STAGE II ............................................................... Error! Bookmark not defined.
5.2.1 Field trip to the Selected Site. ...................... Error! Bookmark not defined.
5.2.2 STAGE III .......................................................... Error! Bookmark not defined. 6. Considerations made during the Studies ............ Error! Bookmark not defined.
i. Geology of the area .................................................... Error! Bookmark not defined.
ii. Topography ............................................................ Error! Bookmark not defined. iii. Reservoir area ........................................................ Error! Bookmark not defined. iv. Location of weir with respect to the Consumers ... Error! Bookmark not defined.
7. Results of the Studies ........................................... Error! Bookmark not defined. 8. Site Visits ............................................................. Error! Bookmark not defined.
9. Selected Site ......................................................... Error! Bookmark not defined.
10. Design of the Weir ............................................... Error! Bookmark not defined.
11. Diversion of Flows ............................................... Error! Bookmark not defined. 12. Design of the Weir ............................................... Error! Bookmark not defined.
13. Background Information ...................................... Error! Bookmark not defined. 14. Location ................................................................ Error! Bookmark not defined. 15. Catchment area ..................................................... Error! Bookmark not defined.
16. Geology ................................................................ Error! Bookmark not defined.
17. Foundation ............................................................ Error! Bookmark not defined. 18. Reservoir Characteristics ..................................... Error! Bookmark not defined. 19. Reservoir characteristics ...................................... Error! Bookmark not defined. 20. Flood Estimation .................................................................................................. 19
21. Proposed Weir ...................................................... Error! Bookmark not defined. 22. Design of the weir ................................................ Error! Bookmark not defined. 23. Spillway ................................................................ Error! Bookmark not defined.
24. Determination of the Base Width of the Dam ...... Error! Bookmark not defined. 25.0 Stability Analysis .............................................. Error! Bookmark not defined. 26. Coordinates of the O-Gee Concrete Spillway ...... Error! Bookmark not defined. 26.1 Hydraulic Jump ................................................ Error! Bookmark not defined. 27. Invert Radius ........................................................ Error! Bookmark not defined.
28. Stability calculations ............................................ Error! Bookmark not defined. 29. River Diversion .................................................... Error! Bookmark not defined. 30. Priced Bill of Quantities ....................................... Error! Bookmark not defined.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
31. Estimated Construction cost ................................. Error! Bookmark not defined.
DESIGN OF THETA DAM
CHAPTER 1.0: INTRODUCTION
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
1.1 GENERAL BACKGROUND
Athi Water Services Board is one of the Eight Water Service Boards established under the Water
Act 2002 and it re[orts to the Ministry of Water and Irrigation. Its principal mandate is efficient
and economical provision of water to the consumers through the Water Service Providers. In the
case of this project, the Water Service Provider is Gatundu South Water and Sanitation Company
Limited with its headquarters in Gatundu Town which is also the headquarters of Gatundu South
District.
1.2 PROJECT BACKGROUND
Gatundu South areas of Mundoro, Kiganjo, Kiamwangi, Ngenda and Gathage have been
experiencing water shortages for quite some especially after the yields of the sole sources of
water started diminishing due to prolonged dry spells while at the same time, the population
went on soaring thereby increasing the water demand. In its pursuit to efficiently provide water
and sanitation services to the communities, Athi Water Services Board, therefore, proposes to
construct on river Theta a regulating reservoir which would regulate the river flows and thus
make water available in sufficient quantities. In cognizance of this fact, the Board procured
consultancy services to design the dam and thus realize its objective.
1.3 SCOPE OF STUDY
In April, 2010, Athi Water Services Board through its Water Service Provider namely Gatundu
South Water and Sanitation Company Limited commissioned the design of a weir on Theta
River. Following the completion of the design, it was established that the storage capacity of the
created reservoir is rather small about 30,000m3 and it would not help achieve the intended
objective of providing water to the consumers in sufficient quantities.
Against the above background and in an effort to increase the storage capacity of the reservoir,
the Board decided to construct a 15m high earth dam across the same axis. However, in both
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
cases the Consultant was guided by the Terms of Reference that were drawn for the project and
these included but not limited to the following:
i. Exploration of Theta River within 2 km upstream and downstream with a view
to establishing the best dam site that can have maximum impacts in terms water supply to
the needy areas.
ii. Carry out flood routing through the reservoir so as to indicate the efficiency of
the reservoir.
iii. Taking into account the findings in (i) and (ii), identify the best alternative that
can meet the objective of the assignment.
iv. Collection, compilation and analysis of data for use in the design of the dam.
v. Carrying out topographical survey within the dam reservoir and spillway areas
to enable preliminary and final design of the dam.
vi. Design the dam identified under item (iii) above including the intake tower.
vii. Environmental Impact Assessment studies within the project area.
viii. Preparation of Tender Documents which shall contain Invitation to Tender,
Instructions to Tenderers, Bills of Quantities, Drawings, Specifications, Conditions of
Contract, Schedules, Pre-qualification Documents, etc. for the dam.
1. 4 PREVIOUS STUDIES
The project area had not been subjected to many studies except the hydrological assessment
study which was done in 2009, and a report of which is attached as an Appendix.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
CHAPTER 2.0: PROJECT AREA
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
2.1 PROJECT BACKGROUND AND LOCATION
The proposed Theta Earth Dam is located in Gatundu South District in Kikuyu Escarpment
Forest after the Kenya Wildlife Services Offices near Mundoro Town. The dam is on coordinates
S 00.92506o and E 036.71755 o on elevation 2265masl. It can be accessed from Nairobi
through the main road to Mundoro via Gathage, Ngenda, Kiamwangi and Kiganjo Towns
through a distance of approximately 80km. The dam is about 11km from Mundoro Market
Centre via an earth road which passes through the Kenya Forest Offices on the edge of the forest.
This roads farther ahead joins the flyover near Gwa Kanyua where the road to Njabini Market
Centre branches.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Figure 1: Proposed dam site on Theta River
Figure 1.2 Location of Theta District
2.2 CATCHMENT AREA
The catchment area for Theta Dam is 1.6km2 within the Kikuyu Escarpment Forest on 1:50,000
scale topographic map.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
The area rises from 2220 masl to a maximum of 2360 masl through a length of about 1.6km from
the farthest point to the dam site. The area has been well conserved with a good indigenous
forest cover which reduces the amount of erosion and subsequent generation of sediments. This
goes along way in increasing the economic lifespan of the dam.
The average slope along the catchment area is 2.5%.
2.3 RAINFALL
Theta Dam catchment has a bimodal type of rainfall. The long rains are received in the months
of April/March while the short rains occur between the months of October/November.
A meteorological station in Kieni Forest Station has been used to generate the flood flows which
are used for the design of the spillway of the dam.
2.4 GEOLOGY
The geology of this area comprises of basement systems which are mainly grits, sandstones,
shales and limestones that have been metamorphosed by heat and pressure or by impregnation by
pervading fluids. Other types are derived from lavas and volcanic fragmental rocks. The variety
of rocks is extensive and includes mica and mica hornblende gneisses and schists, pyrexinite,
granulites quartzites and marbles. There is also a considerable development of migmatites.
Detailed investigation or review of the geology of the dam site has not been done for this study
since the design is focusing rehabilitation works i.e. rising the existing embankment with the
existing foundation.
SOILS
The predominant soils are black clays (grumosolic soils) which consist of black cotton and
include the calcareous and non-calcareous variants. The adjacent area has rock outcrops that
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
have been subjected to geological and accelerated erosion to an extent that they have lost their
original characteristics.
SOIL SAMPLING AND TESTING
Field investigations around the dam site were carried out in June, 2008 and involved geophysical
sounding, trial pitting and soil sampling.
GEOPHYSICAL EXPLORATION
A core trench was excavated along the dam and spillway axis. Similarly, trial holes were dug in
the borrow areas to determine the suitability of the soil materials for use as construction
materials. The materials looked fairly homogeneous and consequently, only two samples were
submitted to the laboratory for tests to establish the following parameters:
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Particle size distribution
Permeability
Atterberg limits
Linear shrinkage
Triaxial Test
Compaction test OMC (%) and MDD (g/cm3)
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
The laboratory test results on the soil samples are shown in the table below:
Testing Summary Sheet (Theta Borrow Area)
Soil Classification Red Soils, Soil Type Silt of high plasticity
Conclusion: the test results indicate that the samples are suitable for the construction of the dam.
These material are available in sufficient quantities and this mean necessitate the construction of
a homogeneous dam with the necessary filters.
Soil tests Trial Pit 1 Trial Pit 2
Particle size:
Gravel %
Sand %
Silt %
Clay %
Permeability Test:
Hydraulic Conductivity, k,
(cm/sec)
Atterberg limits:
Liquid Limit (LL) - %
Plastic Index (PI) - %
Plasticity Index (PI) - %
Linear Shrinkage (LS) - %
Shear Strength Test:
Cohesion C (Kg/cm2)
Friction Angle ( o)
Compaction Test:
OMC - %
MDD g/cm3
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
HYDROLOGY AND ESTIMATION OF FLOOD FLOW
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
2.7 HYDROLOGY
Within the proposed location of the weir, there are no river gauging stations. However, a
hydrological analysis was done by Kibson Consult and the obtained flows along the river with
respect to the position of the proposed weir are presented in the table below:
Table of Flood Flows for various return periods
Return Period Flood flow m3/sec
50 year return period 0.23
80 year return period 0.09
95 year return period 0.04
2.8 ESTIMATION OF FLOOD FLOWS
The flood flow from the catchment area is a function of the size of the catchment area, its slope
and degree of catchment conservation which is represented through a run off factor, the values of
which are presented below:
Generalized values of run off factor1
Catchment soil type Run off factors (Kr)
Rocky and impermeable 0.80 to 1.00
Slightly permeable, bare 0.60 to 0.80
Slightly permeable, partly cultivated or covered with vegetation 0.40 to 0.60
Cultivated, absorbent soil 0.30 to 0.40
1Ministry of Water Development. Guidelines for design, construction and rehabilitation of small dams and pans in
Kenya. Kenya Belgium Water Development Programme, June 1992, Nairobi.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Sandy bare soil 0.20 to 0.30
Heavy forest 0.10 to 0.20
The Theta catchment can be classified as well conserved with good forest cover and a run off
factor of 0.1 can be assumed. The catchment area is given as 1.6 km2.
The Mean Annual Precipitation (MAP) for Theta Dam is 1280mm per annum.
Based on a safe yield of 1,200 mm per annum, the catchment area of 1.6 km2 and the run off
factor of 0.1, the expected annual inflow into the reservoir will be 192,000m3. However, the fact
that Theta river is perennial gives an assurance that there will always be an inflow into the dam
equal to a Q(50) of 0.23m3/sec or 19,872m
3/day obtained as per the hydrological analysis.
The evaporation rates for Theta area are neglected due to the fact that the dam is in a fairly thick
forest where no significant winds are experienced.
Considering the above, replenishment of the reservoir is quite feasible and the Water Service
Provider will therefore realize huge water sales that will ensure the sustainability of the project.
RICHARDS METHOD
In estimating the expected flood flow for the purpose of designing the spillway, Richards
method and the rational formula were used.
The method is based on an empirical formula to calculate the time of concentration (Tc) of the
catchment. Richards method takes account of the rainfall pattern and intensity and the
catchment characteristics determining its run-off, size, shape and slope as well as soil and
vegetation type (the latter two collated into a run-off factor Kr).
Time of concentration Tc:
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
afSRKLCTT rcc .../.1/
23
Where: Tc = time of concentration in hours
L = the longest path of the catchment in km (14km)
C = a coefficient function of (Kr.R)
Kr = run off factor (table 3.3)
R = rainfall coefficient; FttR ./1
F = total rainfall in mm for the selected storm duration t
t = selected storm duration (12 hours)
s = slope of the catchment (4%)
a = the area of the catchment in km2
f(a) = ratio of the average rainfall intensity (i) to the maximum rainfall intensity (I) over the
catchment area
Once the time of concentration Tc has been derived, the rainfall intensities are calculated as
follows:
)1/( cTRI (mm/hr)
and
)(. afIi (mm/hr)
Finally the rational formula is used to calculate the expected maximum flood flow
6.3/.. aiKQ rp (m3/s)
The rainfall intensities for return periods of 5, 10, 25, 50 and 100 years were obtained from the
Rainfall Frequency Atlas of Kenya. The rainfall intensity for 1000 years return period was
developed using Gumbels Type 1 External Distribution Values.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
The following table shows flood flows for different return periods
Return period Flood (m3/sec)
5 8.5
20 11.3
50 16.6
100 17.0
500 19.5
1000 21.8
Figure 6.1 PMF for Theta Dam
The flood flow return periods for each dam classification are given in the table 6.2 below.
Recommended return periods for the design of spillways
10 25 50 100 500 1000
5
10
15
20
25
Return Period - Years [Log scale]
Flood Discharge
m3/s
Theta Dam Probable Maximum Flood
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Class of Dam Minimum return period for spillway design
A (Low Risk) 1 in 50
B (Medium Risk) 1 in 100
C (High Risk) 1 in 500
However, in order to ensure maximum safety of the dam and also to take care of the
uncertainties that might have arisen due to limited hydrological data that is available for the
catchment area, a return period of 1 in 1,000 years is adopted.
GENERALIZED TROPICAL FLOOD MODEL
This model combines the merits of the East African Flood Model with the experience gained in
catchment modeling in West Africa and it is applicable in all areas of the tropics where locally
validated alternatives are not existing as is the prevailing situation in the area under study. It
involves determination of model coefficients where three components are established.
These are:
i. Hydrograph base time
ii. Contributing area coefficient
iii. Peak flow factor
After computations, the flood flows for various return periods are shown in the table below:
Return Period Flood flow in m3/sec
5 10.8
20 14.1
50 16.2
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
100 17.7
500 21.3
1000 22.8
The flood flow for a 1,000 year return period is 22.8m3/sec but for design purposes, the flood
flow has been rounded to 25m3/sec.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DAM EMBANKMENT DESIGN
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DESIGN OF DAM AND ANCILLARY WORKS
SELECTION OF DAM TYPE
Dams are classified according to the materials used for construction. Usually, they are made of
earth, rock, concrete and masonry. A combination of dams using earth materials at the abutments
and concrete in the middle to form the spillway section is another form of a dam called
composite structure, but it requires workmanship of a high standard because of the interface
between the soil material and concrete.
The choice of the material depends firstly upon the geology of the proposed dam site and
secondly upon the costs of the various alternatives. Concrete and masonry dams require a hard
rock foundation, but earth dams can be constructed on either rock foundations or on firm clays
and other sound strata not as hard as rock. Whatever the type of the dam used, the foundation
material below the dam must be either watertight, or capable of being made watertight by such
means as grouting. The dam, foundation and abutments must also be stable under all static and
dynamic loading conditions.
EARTH AND ROCK FILL EMBANKMENT DAMS
Classification of dams into either earthfill or rockfill category is determined by the construction
materials.
EARTH DAMS
Earth dams are composed of suitable material from borrow areas or required excavation and
compacted in layers by mechanical means and can either be homogeneous or zoned. Compaction
is done by means of tamping rollers, sheep foot rollers, heavy pneumatic rollers, vibratory
rollers, tractors or earth hauling equipment.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
ROCKFILL DAMS
Rock fill dams are composed largely of fragmented rock with an impervious core. The rock fill
layers are compacted in layers of approximately 250 mm thick by rubber-tyred rollers or steel
wheel vibratory rollers. Free- draining, well-compacted rock fill can be placed with steep slopes
if the dam is on rock foundation. In both cases, a core trench should be constructed for purposes
of minimizing seepage losses under the foundation.
Based on the topography of the dam site and the preliminary geophysical and geological study
results, it is recommended to construct an earth dam with a central impervious clay core since
this is the most economical and technically suitable type of dam considering the availability of
materials within the vicinity of the dam site.
DESIGN CRITERIA
The design of a structure should ensure a safe and economical section which in the case of an
earth dam is realized through optimization of the slopes.
The foundation, abutments and the embankment should be stable for all conditions of
construction and operations.
Other factors to be considered are as follows:
i. Seepage through the embankment, foundation and abutment should not result in
excess forces.
ii. Use of non dispersive to reduce piping
iii. The gross freeboard dam must be sufficient to prevent overtopping and to allow
for settlement of embankment and foundation.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
iv. The spillway and outlet works should be adequately sized to prevent
overtopping the dam crest.
v. The side and longitudinal slopes of the spillway must be stable.
vi. Embankment slopes should be stable under all conditions
The construction materials for the embankment wall will be excavated from the borrow areas
within the reservoir area and this will increase the storage capacity of the reservoir and overly
increase the suitability coefficient of the site.
THE PLATE BELOW SHOWS THE GORGE ACROSS WHICH THE DAM WILL BE CONSTRUCTED
SIZING THE DAM
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
The estimated storage capacity of the reservoir is based on the topographic survey map done in
July, 2010 by Geosite Systems of Nairobi, using scale of 1:10,000.
SLOPES
The United States Bureau of Reclamation (USBR) as well as the Design Manual for Water
Supply Systems in Kenya 1986 Edition both recommend upstream and downstream slopes of
1:3.0 and 1:2.5 respectively during the preliminary design stages. However, these slopes have
already been optimized during the through slope stability analysis and they are stable.
CREST WIDTH, LENGTH AND DAM HEIGHT
According to the Ministry of Water Irrigation Design Manual, the minimum crest width of an
earth dam should be 5.0m especially to allow for access road and manipulation of machinery and
equipment during construction. The US Bureau of Reclamation recommends a minimum crest
width of 3m. The crest should also be sloped to promote drainage and minimize surface
infiltrations. It should also be cambered so that the design freeboard is maintained after post
construction settlement takes place.
The proposed Theta Dam is a homogeneous earthfill embankment wall with a crest width and
length of 10 m and 60 m respectively. According to the contour survey, the crest of the dam is on
2251 masl while the bed is on 2234 masl thereby giving a 17m high embankment wall.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
SPILLWAY DESIGN
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DAM FREE BOARD
Spillways are provided to facilitate release of surplus water or floodwater that cannot be
contained in the available storage space. The importance of safe spillway cannot be over-
emphasized; many failures of dams have been caused by spillways of insufficient capacity.
Reservoir spillways are therefore major hydraulic structures during dam construction and later in
the operation and regulation of the dam. Spillways are designed to discharge the largest possible
flood during the design life of the dam for a selected return period.
Guidelines for spillway design floods in Kenya are presented in three design manuals produced
by the Ministry of Water and Irrigation (MoWI).
i. Guidelines for the Design, Construction and Rehabilitation of Small Dams and
Pans are used for dams of heights not more than 10m.
ii. Practice Manual for Water Supply Services in Kenya
iii. Water Resources Management Authority (WRMA) Guidelines
The first two manuals are applicable for small dams. For larger dams, Water Resources
Management Authority (WRMA), has published guidelines which are based on the perceived
risks associated with dam failure. The table below shows the categorisation of dams based on
storage depth, storage volumes and runoff catchments.
The minimum required freeboard (above F.W.L) of the dam was evaluated from wind set up,
significant wave height and wave run up. The value of wind set up is a function of the fetch of
the reservoir and the velocity of wind in the direction of predominant winds. In the case of Theta
dam, the fetch of the reservoir is is approximately 450m considering the left arm of the reservoir.
The spillway for this dam will be located on the right hand side of the dam. This location of the
spillway will avoid construction of a bridge on piers for purposes of moving to the right hand
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
side of the reservoir. This arrangement will also reduce the construction cost of the bridge and
the necessary piers.
Categorization of dams based on storage depth, storage and runoff catchments
Class of
dam
Maximum Depth
of Water at NWL
(m)
Storage (m3) Catchment Area
(km2)
Minimum Return
Period for
spillway design
A (low
risk)
0 4.99 1,000,000 >1000 1 in 100 Years
Design of Small Dams by the United States Bureau of Reclamation (USBR), 1987, recommends
use of probable maximum flood (PMF) for spillway inflow design. PMF hydrograph represents
the maximum runoff condition resulting from the most severe combination of hydrologic and
meteorological conditions considered reasonably possible for the drainage basin under study.
The PMF is used by design and construction organizations as a basis for design in those cases
where the failure of the dam from overtopping would cause loss of life or widespread
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
destruction. In estimating PMF, use is made of Maximum Probable Precipitation which requires
isolation of rainfall storm in the catchment of interest.
This information on particular storm and criteria for developing PMF and PMP is not developed
currently. In view of this, the consultant has used the 1 in 1,000 year frequency flood (25m3/s)
for spillway design.
SELECTION AND SIZING OF THE SPILLWAY
Preliminary hydraulic sizing of the spilling is undertaken based on the peak flow analysis. An
inflow flood of 25m3/s (1:1,000 year return period) is used to size the spillway.
The critical depth is determined using the following equation:
hc = 3q2/g
Where,
hc is critical water depth on top of the spillway sill. The critical depth is two
third the approach depth (ha): hc = 2/3ha.
ha =3/2*3q2/g,
Specific discharge (q) = 25/15 = 1.67 m2/s
Critical depth hc = 3q2/g
A table for selecting the best width of the spillway front through the critical depth equation is
presented below:
Q B q q^2 q^2/g (q^2/g)^0.33 ha
25 5 5 25 2.54842 1.361662353 2.042494
25 10 2.5 6.25 0.637105 0.861766551 1.29265
25 15 1.666667 2.777778 0.283158 0.659431065 0.989147
25 20 1.25 1.5625 0.159276 0.545393347 0.81809
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
25 25 1 1 0.101937 0.470705451 0.706058
From the above table, an open channel spillway with a front width of 15m is selected. The
critical depth and the depth of water in the reservoir are as follows:
Description Depth of water (m)
hc 0.659
ha 0.989
The open channel spillway is selected since it fulfills the fundamental requirements of low cost,
less demand for workmanship and availability of local labour. Secondly, the excavated materials
will be used as random fill depending on their suitability.
WIND SET UP
Wind set up (the tilting of the reservoir surface caused by the movement of the surface water
towards the leeward shore under the action of wind) was estimated from the following formula:
Zs = (Vw .F)/ (63,200d) metres
With: Zs = rise above the still water level
Vw = speed of the wind in (km/hr)
Vw = The speed of the wind is assumed to be 54km/hr (15m/s)
F = fetch of the reservoir (0.45 km)
d = average depth of the reservoir along the fetch (10.0 m)
Hence:
Zs = ((54^2) x0.45)/ (63,200x10.0) =0.0021m
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Significant wave height: The average height in metres (Zw) of the highest one third of the waves
was estimated as follows:
Zw =0.005Vw (^1.06) F (^0.47) (m)
Hence: Zw =0.005 x 54(^1.06) x4.0 (^0.47) =0.197m
Wave run up: the height to which a wave will run up a slope depends on the surface. The ratio
[wave run up / significant wave height Zr/Zw] depends on the ratio of wave height to wave
length
The wave period tw can be expressed as follows:
tw =0.32Vw 0.44 F0.28 (m)
Hence: tw =0.32 x 54 0.44 x 0.45 0.28 =1.48
The wave length may be computed from:
= 1.56tw2 =1.56x2.19 = 3.42 m
Ratio Zw/ =0.197/3.42 = 0.057
For embankments lined with riprap and an upstream slope of 1/3, the ratio Zr/Zw should not
exceed 0.7
Zr=0.7x 0.057 =0.04m
Depth of Water above the Spillway Sill
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Required Dam freeboard: the required dam freeboard was then obtained as the sum of wind set
up, significant wave height and wave run up.
Required dam free board (above F.W.L.) = 0.0021+0.197+0.04+0.987 =1.23m
Allowing a safe board of 0.6m, then a gross freeboard 1.83m which is rounded to 2.0m and
which is considered to be adequate for the dam.
DESIGN OF THE INFLOW AND OUTFLOW SECTIONS OF THE SPILLWAY
INFLOW SECTION
With a 2.0m gross freeboard, the normal water line will be on level 2249 since the crest is on
level 2251m. The inflow section is 22m long and it will have an invert slope of 1% towards the
reservoir. The level at the entrance point to the spillway is, therefore, 2248.78m. About 10m of
the inflow section before the spillway sill will be rip-rapped or stone pitched to prevent any
erosion since this is the area where transition of flows will take place just before the sill. The
spillway width tapers from 15m at the entrance point to 5m at the exit point.
OUTFLOW SECTIONS OF THE SPILLWAY
The outflow section of the spillway is 70m long. The longitudinal profile of the spillway has
been selected in such a manner as to reduce the volume of earthworks and hence the construction
cost. The depth of water above the spillway sill is 2249m where the depth of water will be equal
to the critical depth (0.659m) and the exit point is on level 2234m. The two levels at the entrance
and exit points of the spillway through the length of 70m give a slope of 0.214m.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
NORMAL DEPTH OF WATER AT THE TERMINAL POINT OF THE SPILLWAY
The width of the spillway channel at the terminal point is 5m. The normal depth of water at the
terminal point of the spillway is calculated using the uniform flow equation. And the calculations
are presented in the table below.
214.0
014.0
1
arg
,
6/1
hechannelalslopeoftlongitudini
ofconcreteoefficientroughnesscn
Rn
C
P
AR
adiusHydraulicrR
meterwettedperiP
ficientChezyscoefC
AreaA
eDischQ
RiACQ
Using the equation and the data, the depth of water is calculated using trial and error method.
h B A P R R^(1/6) C (Ri)^0.5 Q
0.25 5 1.25 5.5 0.22727273 0.78119218 55.7994414 0.22053654 15.3822694
0.28 5 1.4 5.56 0.25179856 0.79464936 56.7606689 0.2321312 18.4462907
0.3 5 1.5 5.6 0.26785714 0.80287981 57.3485581 0.23941894 20.5954964
0.32 5 1.6 5.64 0.28368794 0.8106004 57.9000285 0.24639241 22.8258041
0.33 5 1.65 5.66 0.29151943 0.81428778 58.1634131 0.24977021 23.9703553
0.338 5 1.69 5.676 0.29774489 0.81716054 58.3686099 0.25242307 24.8997565
0.339 5 1.695 5.678 0.29852061 0.81751498 58.3939271 0.25275168 25.0167812
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
0.34 5 1.7 5.68 0.29929577 0.8178684 58.4191717 0.25307962 25.1339934
0.35 5 1.75 5.7 0.30701754 0.82134799 58.6677136 0.25632353 26.3163525
0.38 5 1.9 5.76 0.32986111 0.83123123 59.3736595 0.26568831 29.9722857
0.4 5 2 5.8 0.34482759 0.83740137 59.8143836 0.27164886 32.4970183
From the above calculations, the normal depth of water as a function of height h is equal to
0.339m which is rounded to 0.34m.
FLOW PROFILES
As seen from the calculations the depth of water will be 0.659m above the spillway sill. Due to
the tapering nature of the spillway, this depth will reduce to 0.168m within the first 10m length
of the spillway. Thereafter, the depth of water will keep on increasing and it will attain a level of
0.339m(0.34m) at the terminal point of the spillway.
DEPTH OF THE RETAINING WALL
The purpose of the retaining wall is to confine the flood flows within the spillway channel. The
height of the wall at the sill is 2m which then reduces to 0.85m within the first length of 7m. The
other heights of the retaining wall are established using Mannings equation and they are
established at 10m intervals and presented in the following table.
0m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.05 15 0.75 15.1 0.04966887 0.60622976 43.302126 0.10309772 3.34826272
0.12 15 1.8 15.24 0.11811024 0.70040677 50.0290547 0.15898299 14.3167835
0.15 15 2.25 15.3 0.14705882 0.72647515 51.8910823 0.17739952 20.712269
0.168 15 2.52 15.336 0.16431925 0.74004012 52.8600084 0.18752152 24.9792201
0.17 15 2.55 15.34 0.16623207 0.74146928 52.9620912 0.18860982 25.4723845
0.18 15 2.7 15.36 0.17578125 0.74840542 53.45753 0.19395151 27.9940551
0.19 15 2.85 15.38 0.18530559 0.7550175 53.9298213 0.19913663 30.6072979
h=0.168
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
10m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.05 13.6 0.68 13.7 0.04963504 0.6061609 43.297207 0.10306259 3.03437921
0.12 13.6 1.632 13.84 0.11791908 0.70021767 50.0155476 0.15885428 12.9665399
0.15 13.6 2.04 13.9 0.14676259 0.726231 51.8736427 0.17722075 18.7538952
0.16 13.6 2.176 13.92 0.15632184 0.73391046 52.4221756 0.18290127 20.8636672
0.179 13.6 2.4344 13.958 0.17440894 0.74742825 53.3877323 0.19319294 25.1087257
0.18 13.6 2.448 13.96 0.17535817 0.74810484 53.4360599 0.19371796 25.3405318
0.19 13.6 2.584 13.98 0.18483548 0.75469786 53.9069897 0.19888387 27.7036598
h=0.179m
20m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.05 12.2 0.61 12.3 0.0495935 0.6060763 43.2911643 0.10301946 2.72049761
0.1 12.2 1.22 12.4 0.0983871 0.67939569 48.5282637 0.14510286 8.59073937
0.11 12.2 1.342 12.42 0.10805153 0.69009086 49.2922042 0.15206258 10.0589605
0.14 12.2 1.708 12.48 0.13685897 0.71782199 51.272999 0.17113685 14.9871866
0.16 12.2 1.952 12.52 0.15591054 0.73358821 52.3991579 0.18266049 18.6830919
0.191 12.2 2.3302 12.582 0.18520108 0.7549465 53.9247498 0.19908046 25.0155457
0.2 12.2 2.44 12.6 0.19365079 0.76058212 54.3272946 0.20357129 26.9851249
h=0.191
30m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.05 10.8 0.54 10.9 0.04954128 0.60596989 43.2835633 0.10296521 2.40661869
0.1 10.8 1.08 11 0.09818182 0.67915919 48.5113705 0.1449514 7.59433448
0.15 10.8 1.62 11.1 0.14594595 0.72555579 51.8254136 0.176727 14.8374988
0.206 10.8 2.2248 11.212 0.19843025 0.76367968 54.5485485 0.20606813 25.0083481
0.25 10.8 2.7 11.3 0.23893805 0.78769876 56.2641973 0.2261255 34.3514789
0.3 10.8 3.24 11.4 0.28421053 0.81081507 57.9153625 0.24661925 46.2770595
h=0.206
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
40m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.1 9.2 0.92 9.4 0.09787234 0.67880185 48.4858465 0.14472277 6.45564563
0.15 9.2 1.38 9.5 0.14526316 0.72498884 51.7849168 0.17631312 12.5998971
0.2 9.2 1.84 9.6 0.19166667 0.75927748 54.2341054 0.20252572 20.2101941
0.25 9.2 2.3 9.7 0.2371134 0.78669281 56.1923437 0.22526044 29.1131984
0.228 9.2 2.0976 9.656 0.21723281 0.77529229 55.378021 0.21561035 25.0454997
0.12 9.2 1.104 9.44 0.11694915 0.69925425 49.946732 0.15819962 8.72331544
h=0.228
50m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.1 7.7 0.77 7.9 0.09746835 0.67833397 48.4524266 0.14442378 5.38821555
0.15 7.7 1.155 8 0.144375 0.72424802 51.7320014 0.17577329 10.5025353
0.2 7.7 1.54 8.1 0.19012346 0.75825495 54.1610675 0.20170875 16.8241323
0.255 7.7 1.9635 8.21 0.23915956 0.78782045 56.272889 0.22623029 24.9965964
0.228 7.7 1.7556 8.156 0.21525257 0.77410967 55.2935476 0.21462537 20.8344045
0.12 7.7 0.924 7.94 0.1163728 0.6986786 49.9056141 0.15780931 7.27702717
h=0.255m
60m
h B A P R R^(1/6) C (Ri)^0.5 Q
0.1 6.5 0.65 6.7 0.09701493 0.6778069 48.4147787 0.14408745 4.53437539
0.15 6.5 0.975 6.8 0.14338235 0.72341554 51.6725386 0.17516799 8.82509018
0.2 6.5 1.3 6.9 0.1884058 0.75710866 54.07919 0.20079552 14.1165167
0.255 6.5 1.6575 7.01 0.23644793 0.78632433 56.1660232 0.22494412 20.9412142
0.285 6.5 1.8525 7.07 0.26202263 0.79990254 57.1358961 0.23679705 25.0636056
0.3 6.5 1.95 7.1 0.27464789 0.80620224 57.5858746 0.24243483 27.2236026
h=0.285
70m
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
h B A P R R^(1/6) C (Ri)^0.5 Q
0.1 5 0.5 5.2 0.09615385 0.6768003 48.3428785 0.14344659 3.46731045
0.15 5 0.75 5.3 0.14150943 0.72183166 51.5594041 0.17402017 6.72928212
0.2 5 1 5.4 0.18518519 0.75493569 53.9239782 0.19907192 10.7347499
0.25 5 1.25 5.5 0.22727273 0.7811536 55.7966857 0.22053654 15.3815097
0.339 5 1.695 5.678 0.29852061 0.81748204 58.391574 0.25275168 25.0157731
0.35 5 1.75 5.7 0.30701754 0.82131566 58.6654044 0.25632353 26.3153167
h=0.339
The flow profile is shown in the following graph.
L m
0 0.168
10 0.179
20 0.191
30 0.206
40 0.228
50 0.255
60 0.285
70 0.339
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
RESERVOIR CHARACTERISTICS
From a topographic survey which was done in July, 2010 and the selected dam height of 17m,
the area volume height relationship curve of the reservoir was computed and the amount of
storage up to the normal water of the reservoir considering a gross freeboard of 2m is
1,170,000m3 while the submerged are is 117,000m
2.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
VOLUME CURVE
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
AREA CURVE
EMBANKMENT VOLUMES
The embankment volume for Theta Dam is estimated using the topographic survey and it is
equal to 20,482m3.
SUITABILITY COEFFICIENT OF THE SITE
The suitability coefficient (SC) of the site is the ration of the volume of fill material to the
volume of the water stored in the reservoir.
In the case of Theta Dam, this ratio is calculated using as follows:
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
57
20482
000,170,1
SC
SC
fillvolume
storageSC
This ratio represents a very good site whereby the unit cost of water will be very low.
SEDIMENT LOADS
The sedimentation yield of catchments in Kenya is estimated to range between 500 1500
m3/km
2/year depending on the rates of erosion. For this particular catchment and based on the
above figures, the sediment yield is assumed to be 500m3/km
2/year.
DEAD STORAGE
The Dead Storage of the reservoir is dependent of the size of the catchment area and the degree
of environmental degradation/conservation. The amounts of sediment loads determine the
economic lifespan of the dam.
This dam is in a thick forest with very little sediment loads. In this regard, a sediment load of
500m3/km
2/year is assumed for the entire catchment area of 1.6km
2. The annual sediment yield
is 800m3. Assuming a trap efficiency of 6% the total sediment trapped is 28.8m
3. Assuming a
specific gravity of sediment is 1.85t/m3, then the annual volume of sediments is 54m
3.
Considering a lifespan of 200 years, then the volume of the required dead storage is 10,800 m3.
However, due to uncertainties in the estimation of the degree of environmental degradation, and
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
a desire to increase the volume of sediment loading, a final dead storage volume of 100,000 m3 is
adopted for this dam. This gives the dead water level to be on 2238.8m.
It is necessary to note that most of the sediments will be deposited in the upper reaches of the
reservoir thereby reducing its fetch. This has a positive attribute in the sense that the reservoir
waters will be very clear which reduces the cost of treatment.
Figure 1.3 Trap Efficiency of Reservoirs2
CENTRAL CLAY CORE
The dam will have a central clay core which will be excavated to a depth of 3m to encounter a
good foundation. The core trench will then be cleaned and be filled up with impervious clay
.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
material which will be properly compacted at the optimum moisture content until the maximum
densities will be achieved.
UPSTREAM SLOPE PROTECTION
The dam will have a protection of the upstream slope comprising of graded rip rap material on a
protective granular material or geotextile polyfelt material preferably T600. The embankment toe
of the dam will have rock toe drain to protect the slope from both wild and domestic animals
.
DOWNSTREAM SLOPE PROTECTION
The downstream slope will be protected by grassing on a 25mm thick red soil. Both the slope
and the berm will be grassed down to the rock toe drain which will protect the slope from
destruction by both wild and domestic animals.
FILTERS
The dam will have horizontal filter drains that will connect the rock toe with the impervious clay
core. The filters will lower the phreatic line within the limits of the downstream slope of the
embankment wall and thus maintain most of the materials in a dry condition. This will increase
the stability of the downstream slope. The filters will be 4 in number and they will be
constructed using graded sand and ballast all surrounded in geotextile polyfelt material.
DAM STABILITY
The usual failure of an earth embankment dam consists in the sliding of a large mass of soil
along a curved surface. There are various methods of checking the stability of a fill. In all these,
a failure arc is assumed and the forces acting on the sliding mass are worked out. These forces
are resisted by the shear force developed along the sliding surface. The Factor of Safety (F.O.S.)
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
is the ratio of the shear force to the forces causing sliding. Several failures arcs are assumed and
the respective F.O.S. is calculated. The minimum F.O.S. is then taken as the Factor of Safety.
The slope stability analysis is done based on the adopted slopes and the soil properties (section
5) using the Bishop Microcomputer Tool and the results are presented in appendix II and
drawing no. DRG. THETA.. The F.O.S on the upstream slope is
.. while the downstream slope is both of which are above the
acceptable F.O.S levels of 1.2.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
RIVER DIVERSION WORKS
AND DRAW OFF SYSTEM
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
RIVER DIVERSION WORKS AND DRAW OFF SYSTEM
During the construction phase, the flows along the river course will be diverted so as to create a
good working environment. This will be done by way of constructing an upstream coffer dam
and a river diversion channel in form of a box culvert. The draw off pipe will be fixed inside the
box culvert as well as the scour pipe in case it may become necessary to drain the reservoir after
impoundment takes place. During the construction and impoundment phases of the reservoir,
compensation flow equivalent to 85% of the base flow will be released for sustenance of the
ecosystem downstream of the dam. Similarly, compensation flows will be released through the
same pipe even after impoundment and especially when the dam is not spilling. This is made
possible by the fact that the storage capacity of the dam is huge enough.
The river diversion works should be capable of evacuating a peak flood flow 1 in 20 year return
period, the magnitude of which is 14.1m3/sec. In this case, a 8.5m high coffer dam will be
constructed to facilitate release of the diversion flow. The freeboard below the crest of the coffer
dam is 2m which means that a water depth of 5m is considered for purposes of the design of this
component. The coffer dam will ultimately be incorporated into the main embankment wall of
the dam.
The diversion flow is assumed to be 6m3/sec and the size of the pipe is determined as follows:
0.1.........arg
2
tcoefficienedischC
Where
gHCAQ
A = Cross sectional Area
Assuming a freeboard of 2m, the depth of water H, therefore, is equal to 6.5m
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
224.1
5.681.92
14
2
214
14
mA
xxA
gHC
QA
gHCA
Q
SIZE OF THE DIVERSION PIPE
From the above analysis, the flows will be diverted through a box culvert measuring 1.24m high
and 1.0m wide.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
ENERGY DISSIPATION
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
ENERGY DISSIPATION
The flood flows as they are discharged back to the river bed will cause a hydraulic jump where
excessive energy will be generated. This energy will scour the river bed as well as the bed of the
spillway. It is, therefore, necessary to dissipate the excessive kinetic energy within the limits of
the hydraulic jump and just before the terminal point where the spillway joins the river channel.
This will be accomplished by constructing a flip bucket just near the terminal point of the
spillway whereby the water jet will be deflected to the atmosphere where the water will lose
substantial amount of energy before it falls on the river course.
The profile of the spillway is such that it tapers from 15m wide at the sill to 5m at the terminal
point.
In order to achieve the maximum length to where the water jet will fall from the edge of the flip
bucket, different angles of inclination to the horizontal are assumed and the optimum angle of
inclination to the horizontal is selected.
DETERMINATION OF THE VELOCITY OF FLOW AT THE TERMINAL POINT
From the calculations, the normal depth of water as a function of height h is equal to 0.339m
which is rounded to 0.34m. The velocity of water at the terminal point is expressed using the
following equations:
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
sec/7.14
7.1
25
7.1
34.05
2
mV
V
A
QV
mA
xA
BhA
AVQ
FLIP BUCKET EQUATION
The equation for the flip bucket is as follows:
)2
{2 2
22
V
gySinSinCos
g
VL
If the angle of inclination is equal to 00, then the equation is as presented below:
Where:
L - Horizontal distance from the heel to the centre of the erosion zone
v - Velocity of water at the terminal point of the spillway = 14.7m/sec.
- Angle of inclination to the horizontal
y - Difference in elevation between the heel and the erosion depth. In this case, y
is assumed to be 2.0m
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
Angle of inclination () Length L (m)
100 6.87
150 8.06
200 9.20
250 10.21
300 11.03
350 11.62
400 11.92
450 11.94
500 11.63
550 11.01
From the above table, it is evident that the farthest length of possible point of erosion L from the
edge of the flip bucket is achieved when the angle of inclination is 450 when the length is
approximately 11.94m. A corresponding graph for the calculations is presented below.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DETERMINATION OF THE HEIGHT OF THE WALL WITHIN THE HYDRAULIC JUMP SECTION
The height of the wall within the limits of the flip bucket is calculated on the basis of the normal
depth of water which is equal to 0.34m and the congruent depth.
INITIAL DEPTH AT THE TERMINAL POINT OF THE SPILLWAY
The initial depth according to the calculations is 0.34m
THEORETICAL CONGRUENT DEPTH
The congruent depth is determined on the basis of the initial or critical depth of water which is
equal to 1.37m and it also guides on the height of the wall within the limits of the flip bucket.
However, the depth of water at the terminal point of the spillway channel is below the critical
depth and hence supercritical. The initial depth as established earlier is 1.37m
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
mightofallwithaheConsideraw
mh
xh
h
x
xxxh
gh
qhh
4
87.3
77.22685.0
}122.25
2201{685.0
}137.181.9
551.181{
2
37.1
}18
1{2
2
2
2
32
3
1
2
12
= non uniform distribution of velocity 1.1
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
GEOLOGICAL INVESTIGATIONS
AND SEISMICITY
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
GEOLOGICAL INVESTIGATIONS
INTRODUCTION
Some initial investigations were carried out in two stages to determine the feasibility of the dam
site. The first stage desk comprised of the study of topographical and geological maps of the
area. The second stage involved a walk over survey of the selected dam site including the
proposed dam foundation axis and sites of other structures such as spillway and diversion and
outlet works and the area that will be submerged by the reservoir upon its impoundment after the
completion of the dam.
The two stages allowed an assessment of topographical features, suitability of the dam and other
structures foundation in terms of strength, durability, water tightness etc, and how these
conditions are likely to influence the subsequent dam design.
GEOLOGY OF THE AREA
The project area is within the tertiary volcanics of middle and upper tertiary age which are
widespread in Central Kenya. Hey are mainly of alkaline type including basalts phonolites,
nephlenites, trachytes and alkali rhyolites and their pyroclastic equivalents.
.
FAULTS
The probable fault marked in the geological map of Kenya is to the west of the proposed dam
site and it cuts along the Great Rift Valley from Ethiopia to the north to Tanzania to the south.
SEISMIC POTENTIAL
The seismic map of possible intensities in Kenya from Professor L. S. Loupekines report on
Earthquakes in Kenya zones the project site as Zone VI in a scale of V to IX on increasing
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
intensities. The site is, therefore, in an area of minimal seismic potential. However, appropriate
design seismic parameters will be adopted in the stability calculations.
In accordance with the Code of Practice relating to earthquake design and seismic zoning map of
Kenya the proposed dam site located in Zone VI. This zone (Zone VI) is characterized as having
intensity of Damage is slight; a few instances of fallen plaster or damaged chimneys.
Table 5.1: Earthquake parameters for some dam projects in Kenya
Dam Project Design Basis
Earthquake DBE
Maximum
Credible Earthquake
MCE
Comments
Turkwel amax. = 0.20g
Return period
410 years
amax. = 0.45g
M = 7.5 Occurring at
20km. from dam site.
Dam completed in
1988 1991
Chemususu amax. = 0.22g
Return period
400years
a max. = 0.50g
M = 7.5
Return period 2540
years
Dam located at the
intersection of Rift
Valley and Kavirondo
Rift
Final design in 1989
Kiambere a max. = 0.12g a max. = 0.25g Dam completed in
1988
Thika a max. = 0.13g a max. = 0.40g Dam completed in
1988
Source: SOGREAH Consultants-Feasibility Study of Rehabilitation of Sasumua Dam
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DAM CONSTRUCTION MATERIALS
The most economical dam is one that will utilize the materials found within reasonable distance
from the construction site so as to reduce haulage costs. The following materials were identified
during this initial reconnaissance of the project site:
EARTH FILL MATERIALS
The proposed dam site is located in a thick forest with fairly rich red clay soils of high plasticity.
A core trench dug across the dam axis reveals a gradual change of the soil to lighter colour sandy
murram soils at a depth of about 1.5 meter and presence of a high water table in the upstream
reaches of the reservoir area.
Samples of these soils were tested in the laboratory and the results are attached in Appendix 5. In
summary sample 1, 2 and 3 representing the darkish top soils classify as inorganic clays, silty
clays or sandy clays of high plasticity (CL). They have optimum moisture content of 24% and a
maximum dry density of 1800 kg/m3. Samples number four gives similar results while sample
number five classify as inorganic clays or silts of high plasticity (MH or OH). The light coloured
soil found at a depth of 1 meter in the drainage trench classifies as well graded sand with little or
no fines.
ROCK MATERIALS
The requirements for rock materials for the riprap and toe drain is that the material has to be
hard, durable and able to withstand disintegration from mechanical or chemical weathering and
or from quarrying, loading, haulage and placing operations.
Within the dam site, there are no potential quarries except where such rock materials can be
obtained from excavations during construction. In this regard, the possible quarries from rock
materials can be obtained are in Kiamwangi, Magomano and Ndarugu but the haulage costs are a
bit excessive due to the long distances.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
DAM FOUNDATION
The following materials cover the dam axis defining the centre line of the dam foundation:
Mostly weathered rocks, rock debris and murram on the steeper upper slopes.
Deposits of silt clay and or sandy clays to gravelly silt/sandy clays on the lower gentler slopes.
SANDY GRAVELS ON THE RIVER CHANNEL
From the geology of the area, the above horizons overlie solid rock at relatively shallow depths.
The above top materials will be excavated to rock over the impervious core, filter, drainage
layers areas, and a key or cutoff trench constructed with materials similar to that used for the
impervious core. This will reduce leakage and associated instability on the upper pervious
foundation layers.
In addition, a grout curtain will be constructed into the rock to seal off any joints, cracks,
fissures, and shear zones, which may act as seepage paths. The grout curtain should extend to a
depth equal to the head of water at any particular section.
FILTER MATERIALS
There are no sources of clean sand within the project site. In this regard, the sand for the
construction works as well as filters will be sources from Masinga, Machakos or Kiserian in
Kajiado North District.
FIELD INVESTIGATIONS
RESERVOIR AREA
Thorough investigations to locate potential seepage paths such as sandy / gravel layers,
weathered rock zones, lateritic soil zones, faults and fractured bedrock zones will be carried out
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
over the reservoir area during construction. This will be by way of geophysical methods,
geological studies, and limited borings.
Thus:
Electrical resistivity sounding and / or seismic refraction to map the stratification with depth and
electrical resistivity profiling to investigate the lateral variations. A desk study of the areas
geological maps and reports will help identify boundaries of the stratification, including soil
overburden, weathered horizons, fractured bedrock etc.
A few selected borings will be sunk within the reservoir area and identified stratification used to
correlate resistivity sounding and profiling. Samples of the various strata will be taken for
physical properties tests to proof suitability for use as dam material and for strength tests for
slope stability analysis. Borings must be an obsolete minimum and any to be properly resealed to
ensure it does not connect with underlying permeable layers and act as future leakage paths.
DAM AREA
This will be investigated by sinking borings as below:
Along the dam axis at every 100 150 meters intervals and extending beyond the expected dam
height by not less than 50 meters on each bank (to capture the spillway location as well)
A next set of borings at intervals of 200 meters about 50 meters on either side of the dam axis to
map out the lateral extent of stratification.
A set of borings along the spillway axis, intake tunnel, emergency spillway axis at every 50
meter spacing and at locations of intake tower, power house and treatment works.
Disturbed samples for physical properties determination and undisturbed samples for bearing
capacity and settlements tests will be recovered at appropriate strata. Depth to bedrock and
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
character of rock are important. In general, borings will be to a depth at least equal to the height
of the dam.
SUMMARY OF GEOLOGICAL INVESTIGATIONS
Based on the findings of the initial reconnaissance, the following conclusions can be made:
That the location of the dam axis is geologically suitable and that a safe economical dam
foundation can be achieved.
That substantial quantities of materials that can be obtained from borrow areas within the
reservoir area have low compacted dry densities (1800 kg/m3) which makes them suitable for
dam construction works. The required quantities are estimated to be about 15,000 m3 which is
obtainable from the nearby borrow areas.
That rocks on hills defining the dam axis and on locations of spillway, diversion and other
structures where excavations will be done appear suitable for use as rock fill and rip rap. The
deficits will be bridged by rock materials from Kiamwangi, Magomano and Ndarugu quarries.
That an earth fill dam with an impervious central clay core may be the most economical and
technically suitable considering the materials available at the site.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
SEISMICITY
According to the seismic zoning map of Kenya (seismic zoning map of Kenya by L. S.
Loupekine, 1973), Theta dam is located in seismic zone V (appendix 2). This demonstrates that
the area is not prone to earthquakes and hence no specific seismic loading design for structural
members is necessary. For this reason no incorporation for seismic loading has been
incorporated or checked for in the dam embankment design.
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
INSTRUMENTATION
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
INSTRUMENTATION
Appropriate instrumentation enables monitoring of the behaviour of the dam during the
operation phase. This will give an advance indication of the potential effects of any initial
deficiencies or deterioration during operations. Instruments will be required to monitor the
following design and operation parameters.
i. Pore water pressure in the fill
ii. Total pressure in embankment core
iii. Settlement and distortion
iv. Seepage flow
v. Reservoir water level
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
AUXILIARY WORKS
-
Athi Water Services Board
Gatundu South Water and Sanitation Company
Design of Theta Weir
Eng. P. Njurumba
September, 2010
CAMBER
The dam will have a 30cm camber above the design crest level. The camber will take care of any
differential settlement which might arise as a result of the consolidation of the embankment
material. Above the camber will be a thin layer of murram to provide motorability along the
crest.
PARKING BAY
A parking bay will be constructed on the left hand side of the dam to accommodate vehicles for
the people who may wish to visit the dam site either for social or recreational purposes.
FENCING
Fencing of the dam is not of absolute necessity since the dam is in the forest with no noticeable
encroachment. However, this may be done to keep off the wild animals and thus maintain water
of a better quality.
If fencing will be done, then cedar posts will be used with 10 strands of barbed wire G16. This
will be shown in the general specification drawings.
RAMP
Theta dam is located in a forest where there are some animals and even the local people graze
their domestic animals in the forest. In cognizance of the fact that the animals would water from
the dam, it is proposed that ramps be constructed on both sides of the reservoir to facilitate
watering the animals and thus prevent damage to the embankment slopes as the animals look for
water.