Theta Earth Dam

69
Athi Water Services Board Gatundu South Water and Sanitation Company Design of Theta Weir Eng. P. Njurumba September, 2010 ATHI WATER SERVICES BOARD THETA WEIR IN GATUNDU SOUTH DISTRICT GATUNDU SOUTH WATER AND SANITATION COMPANY DESIGN REPORT AND DRAWINGS Consultant: Client: Eng. Peter Njurumba Chief Executive Officer, P.O. Box 212 00206, Athi Water Services Board, KISERIAN Africa Re Centre, Hospital Road, September, 2010 NAIROBI

description

Dam Design

Transcript of Theta Earth Dam

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    ATHI WATER SERVICES BOARD

    THETA WEIR IN GATUNDU SOUTH DISTRICT

    GATUNDU SOUTH WATER AND

    SANITATION COMPANY

    DESIGN REPORT AND DRAWINGS

    Consultant: Client:

    Eng. Peter Njurumba Chief Executive Officer, P.O. Box 212 00206, Athi Water Services Board, KISERIAN Africa Re Centre, Hospital Road, September, 2010 NAIROBI

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    1 EXECUTIVE SUMMARY

    In mid eighties and early nineties, parts of Kiganjo, Kiamwangi and Ngenda used to be supplied

    with water by Thiririka Water Project which was constructed by the Director Labour Section of

    the then Ministry of Water Development. Other water supply schemes that were constructed by

    the Ministry within the vicinity of this area were Ndarugu, Karimenu and Juja. The projects

    served the communities for a while, but as populations exploded with time and water demand

    parameters rose, the water demand outstripped the supply thereby necessitating water rationing

    wihin the supply areas. This situation called for quick intervention measures which included

    tapping water from the pipeline destined for Nairobi. Some of the major centers served by

    pipeline were Gatundu Town and Ichaweri and the communities along the corridors of the

    pipeline. At the same time, the water demand in the city kept on increasing against decreasing

    water supply parameters caused mainly by fluctuating water levels in the river courses caused

    primarily by prolonged dry spells and climate change. This called for quick disconnection of the

    areas that were being served by the pipeline which in return aggravated the water supply

    situation.

    Against the above background and in order to meet the water demand, Gatundu South Water and

    Sanitation Company which is the local Water Service Provider (WSP) appointed by the Athi

    Water Services Board conceived the idea increasing storage to cater for the rural population and

    thus achieve its objective. This policy was to be achieved by way of constructing Theta Dam that

    would regulate the flows of the river and thus enhance water supply to the demand areas. In this

    connection, the Client has procured a consultancy service which is aimed at carrying out the

    necessary studies in terms of feasibility study, preliminary and final designs and preparation of

    tender documents. The client was supposed to carry out an environmental impact assessments of

    the project with a view to determining its technical, economic and environmental viability.

    Athi Water Services Board through its Water Service Provider namely Gatundu South Water and

    Sanitation Co. Ltd commissioned a Consultant to carry out the design of Theta Dam in Gatundu

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    South District which is one of the areas within the jurisdiction of the board. The other areas

    under the mandate of the board are Nairobi, Thika, Gatundu North, Lari, and Limuru.

    As a first step towards the design f the project, the consultant visited the site together with

    officers from Gatundu South Water and Sanitation Office and identified a suitable dam site

    within the Kikuyu Escarpment Forest just about 11 km from Mundoro Town Center.

    Engineering considerations have shown that the dam is 17m high and it can command a storage

    capacity of about 1,170,000m3.

    Water Resources Assessment

    The reservoir is located in an area that receives about 1015mm and 1270mm annually, with a

    mean value of 1180mm per annum. From the flow duration curve, the 50% flow is about

    0.23m3/sec which translates to 19,872m

    3/day. From the envelop curve, the flow for the same

    return period is equal to Kikuyu Escarpment Forest. The Q(80) and Q(95) flows are 17,194 m3/day

    and 6,739 m3/day respectively. The raw water looks very palatable and clear and therefore

    requires very little treatment. During the initial stages, chlorination may be the only form of

    treatment required while a conventional water treatment plant for a capacity of 8,000m3 per day

    may be constructed in future.

    Geotechnical and Geological Study

    Theta Dam is located in the thicket of the Kikuyu Escarpment Forest where there are good soils

    for the construction of an earthfill dam. However, in view of the height of the dam which is 15m,

    the dam enters into the category of large dam according to the classification of dams by the

    World Commission on Dams. In this regard, the design work has to be stringent especially in the

    area of eradication of seepage under the foundation and embankment wall. In order to minimize

    seepage through the foundation, pressure grouting with cement and bentonite is essential while

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    seepage through the embankment wall will be controlled through good workmanship in terms of

    quality control during construction.

    Estimated Project Costs

    The estimated cost of the project is Ksh. which covers the construction of the

    river diversion system, embankment wall with the filters and riprap material, open channel

    spillway together with the energy dissipater, intake tower and the draw off system.

    Conclusion

    The study shows that the construction of the proposed dam is technically and economically

    feasible since it will alleviate the water scarcity situation in the supply areas and hence enhance

    water and sanitation services as well as social economic development and, therefore, improve the

    living standards of the local communities.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    TABLE OF CONTENTS

    Design of Theta Weir .......................................................................................................... 2 1. Background Information .............................................. Error! Bookmark not defined.

    2. Location ......................................................................................................................... 7 3. Sediment Loads ............................................................ Error! Bookmark not defined. 4. Engineering Design and Construction of Theta Weir .. Error! Bookmark not defined. 5. Scope of works ............................................................. Error! Bookmark not defined.

    5.1 STAGE I ................................................................ Error! Bookmark not defined.

    5.1.1 Desk Study ................................................... Error! Bookmark not defined. 5.2 STAGE II ............................................................... Error! Bookmark not defined.

    5.2.1 Field trip to the Selected Site. ...................... Error! Bookmark not defined.

    5.2.2 STAGE III .......................................................... Error! Bookmark not defined. 6. Considerations made during the Studies ............ Error! Bookmark not defined.

    i. Geology of the area .................................................... Error! Bookmark not defined.

    ii. Topography ............................................................ Error! Bookmark not defined. iii. Reservoir area ........................................................ Error! Bookmark not defined. iv. Location of weir with respect to the Consumers ... Error! Bookmark not defined.

    7. Results of the Studies ........................................... Error! Bookmark not defined. 8. Site Visits ............................................................. Error! Bookmark not defined.

    9. Selected Site ......................................................... Error! Bookmark not defined.

    10. Design of the Weir ............................................... Error! Bookmark not defined.

    11. Diversion of Flows ............................................... Error! Bookmark not defined. 12. Design of the Weir ............................................... Error! Bookmark not defined.

    13. Background Information ...................................... Error! Bookmark not defined. 14. Location ................................................................ Error! Bookmark not defined. 15. Catchment area ..................................................... Error! Bookmark not defined.

    16. Geology ................................................................ Error! Bookmark not defined.

    17. Foundation ............................................................ Error! Bookmark not defined. 18. Reservoir Characteristics ..................................... Error! Bookmark not defined. 19. Reservoir characteristics ...................................... Error! Bookmark not defined. 20. Flood Estimation .................................................................................................. 19

    21. Proposed Weir ...................................................... Error! Bookmark not defined. 22. Design of the weir ................................................ Error! Bookmark not defined. 23. Spillway ................................................................ Error! Bookmark not defined.

    24. Determination of the Base Width of the Dam ...... Error! Bookmark not defined. 25.0 Stability Analysis .............................................. Error! Bookmark not defined. 26. Coordinates of the O-Gee Concrete Spillway ...... Error! Bookmark not defined. 26.1 Hydraulic Jump ................................................ Error! Bookmark not defined. 27. Invert Radius ........................................................ Error! Bookmark not defined.

    28. Stability calculations ............................................ Error! Bookmark not defined. 29. River Diversion .................................................... Error! Bookmark not defined. 30. Priced Bill of Quantities ....................................... Error! Bookmark not defined.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    31. Estimated Construction cost ................................. Error! Bookmark not defined.

    DESIGN OF THETA DAM

    CHAPTER 1.0: INTRODUCTION

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    1.1 GENERAL BACKGROUND

    Athi Water Services Board is one of the Eight Water Service Boards established under the Water

    Act 2002 and it re[orts to the Ministry of Water and Irrigation. Its principal mandate is efficient

    and economical provision of water to the consumers through the Water Service Providers. In the

    case of this project, the Water Service Provider is Gatundu South Water and Sanitation Company

    Limited with its headquarters in Gatundu Town which is also the headquarters of Gatundu South

    District.

    1.2 PROJECT BACKGROUND

    Gatundu South areas of Mundoro, Kiganjo, Kiamwangi, Ngenda and Gathage have been

    experiencing water shortages for quite some especially after the yields of the sole sources of

    water started diminishing due to prolonged dry spells while at the same time, the population

    went on soaring thereby increasing the water demand. In its pursuit to efficiently provide water

    and sanitation services to the communities, Athi Water Services Board, therefore, proposes to

    construct on river Theta a regulating reservoir which would regulate the river flows and thus

    make water available in sufficient quantities. In cognizance of this fact, the Board procured

    consultancy services to design the dam and thus realize its objective.

    1.3 SCOPE OF STUDY

    In April, 2010, Athi Water Services Board through its Water Service Provider namely Gatundu

    South Water and Sanitation Company Limited commissioned the design of a weir on Theta

    River. Following the completion of the design, it was established that the storage capacity of the

    created reservoir is rather small about 30,000m3 and it would not help achieve the intended

    objective of providing water to the consumers in sufficient quantities.

    Against the above background and in an effort to increase the storage capacity of the reservoir,

    the Board decided to construct a 15m high earth dam across the same axis. However, in both

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    cases the Consultant was guided by the Terms of Reference that were drawn for the project and

    these included but not limited to the following:

    i. Exploration of Theta River within 2 km upstream and downstream with a view

    to establishing the best dam site that can have maximum impacts in terms water supply to

    the needy areas.

    ii. Carry out flood routing through the reservoir so as to indicate the efficiency of

    the reservoir.

    iii. Taking into account the findings in (i) and (ii), identify the best alternative that

    can meet the objective of the assignment.

    iv. Collection, compilation and analysis of data for use in the design of the dam.

    v. Carrying out topographical survey within the dam reservoir and spillway areas

    to enable preliminary and final design of the dam.

    vi. Design the dam identified under item (iii) above including the intake tower.

    vii. Environmental Impact Assessment studies within the project area.

    viii. Preparation of Tender Documents which shall contain Invitation to Tender,

    Instructions to Tenderers, Bills of Quantities, Drawings, Specifications, Conditions of

    Contract, Schedules, Pre-qualification Documents, etc. for the dam.

    1. 4 PREVIOUS STUDIES

    The project area had not been subjected to many studies except the hydrological assessment

    study which was done in 2009, and a report of which is attached as an Appendix.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    CHAPTER 2.0: PROJECT AREA

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    2.1 PROJECT BACKGROUND AND LOCATION

    The proposed Theta Earth Dam is located in Gatundu South District in Kikuyu Escarpment

    Forest after the Kenya Wildlife Services Offices near Mundoro Town. The dam is on coordinates

    S 00.92506o and E 036.71755 o on elevation 2265masl. It can be accessed from Nairobi

    through the main road to Mundoro via Gathage, Ngenda, Kiamwangi and Kiganjo Towns

    through a distance of approximately 80km. The dam is about 11km from Mundoro Market

    Centre via an earth road which passes through the Kenya Forest Offices on the edge of the forest.

    This roads farther ahead joins the flyover near Gwa Kanyua where the road to Njabini Market

    Centre branches.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Figure 1: Proposed dam site on Theta River

    Figure 1.2 Location of Theta District

    2.2 CATCHMENT AREA

    The catchment area for Theta Dam is 1.6km2 within the Kikuyu Escarpment Forest on 1:50,000

    scale topographic map.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    The area rises from 2220 masl to a maximum of 2360 masl through a length of about 1.6km from

    the farthest point to the dam site. The area has been well conserved with a good indigenous

    forest cover which reduces the amount of erosion and subsequent generation of sediments. This

    goes along way in increasing the economic lifespan of the dam.

    The average slope along the catchment area is 2.5%.

    2.3 RAINFALL

    Theta Dam catchment has a bimodal type of rainfall. The long rains are received in the months

    of April/March while the short rains occur between the months of October/November.

    A meteorological station in Kieni Forest Station has been used to generate the flood flows which

    are used for the design of the spillway of the dam.

    2.4 GEOLOGY

    The geology of this area comprises of basement systems which are mainly grits, sandstones,

    shales and limestones that have been metamorphosed by heat and pressure or by impregnation by

    pervading fluids. Other types are derived from lavas and volcanic fragmental rocks. The variety

    of rocks is extensive and includes mica and mica hornblende gneisses and schists, pyrexinite,

    granulites quartzites and marbles. There is also a considerable development of migmatites.

    Detailed investigation or review of the geology of the dam site has not been done for this study

    since the design is focusing rehabilitation works i.e. rising the existing embankment with the

    existing foundation.

    SOILS

    The predominant soils are black clays (grumosolic soils) which consist of black cotton and

    include the calcareous and non-calcareous variants. The adjacent area has rock outcrops that

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    have been subjected to geological and accelerated erosion to an extent that they have lost their

    original characteristics.

    SOIL SAMPLING AND TESTING

    Field investigations around the dam site were carried out in June, 2008 and involved geophysical

    sounding, trial pitting and soil sampling.

    GEOPHYSICAL EXPLORATION

    A core trench was excavated along the dam and spillway axis. Similarly, trial holes were dug in

    the borrow areas to determine the suitability of the soil materials for use as construction

    materials. The materials looked fairly homogeneous and consequently, only two samples were

    submitted to the laboratory for tests to establish the following parameters:

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Particle size distribution

    Permeability

    Atterberg limits

    Linear shrinkage

    Triaxial Test

    Compaction test OMC (%) and MDD (g/cm3)

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    The laboratory test results on the soil samples are shown in the table below:

    Testing Summary Sheet (Theta Borrow Area)

    Soil Classification Red Soils, Soil Type Silt of high plasticity

    Conclusion: the test results indicate that the samples are suitable for the construction of the dam.

    These material are available in sufficient quantities and this mean necessitate the construction of

    a homogeneous dam with the necessary filters.

    Soil tests Trial Pit 1 Trial Pit 2

    Particle size:

    Gravel %

    Sand %

    Silt %

    Clay %

    Permeability Test:

    Hydraulic Conductivity, k,

    (cm/sec)

    Atterberg limits:

    Liquid Limit (LL) - %

    Plastic Index (PI) - %

    Plasticity Index (PI) - %

    Linear Shrinkage (LS) - %

    Shear Strength Test:

    Cohesion C (Kg/cm2)

    Friction Angle ( o)

    Compaction Test:

    OMC - %

    MDD g/cm3

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    HYDROLOGY AND ESTIMATION OF FLOOD FLOW

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    2.7 HYDROLOGY

    Within the proposed location of the weir, there are no river gauging stations. However, a

    hydrological analysis was done by Kibson Consult and the obtained flows along the river with

    respect to the position of the proposed weir are presented in the table below:

    Table of Flood Flows for various return periods

    Return Period Flood flow m3/sec

    50 year return period 0.23

    80 year return period 0.09

    95 year return period 0.04

    2.8 ESTIMATION OF FLOOD FLOWS

    The flood flow from the catchment area is a function of the size of the catchment area, its slope

    and degree of catchment conservation which is represented through a run off factor, the values of

    which are presented below:

    Generalized values of run off factor1

    Catchment soil type Run off factors (Kr)

    Rocky and impermeable 0.80 to 1.00

    Slightly permeable, bare 0.60 to 0.80

    Slightly permeable, partly cultivated or covered with vegetation 0.40 to 0.60

    Cultivated, absorbent soil 0.30 to 0.40

    1Ministry of Water Development. Guidelines for design, construction and rehabilitation of small dams and pans in

    Kenya. Kenya Belgium Water Development Programme, June 1992, Nairobi.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Sandy bare soil 0.20 to 0.30

    Heavy forest 0.10 to 0.20

    The Theta catchment can be classified as well conserved with good forest cover and a run off

    factor of 0.1 can be assumed. The catchment area is given as 1.6 km2.

    The Mean Annual Precipitation (MAP) for Theta Dam is 1280mm per annum.

    Based on a safe yield of 1,200 mm per annum, the catchment area of 1.6 km2 and the run off

    factor of 0.1, the expected annual inflow into the reservoir will be 192,000m3. However, the fact

    that Theta river is perennial gives an assurance that there will always be an inflow into the dam

    equal to a Q(50) of 0.23m3/sec or 19,872m

    3/day obtained as per the hydrological analysis.

    The evaporation rates for Theta area are neglected due to the fact that the dam is in a fairly thick

    forest where no significant winds are experienced.

    Considering the above, replenishment of the reservoir is quite feasible and the Water Service

    Provider will therefore realize huge water sales that will ensure the sustainability of the project.

    RICHARDS METHOD

    In estimating the expected flood flow for the purpose of designing the spillway, Richards

    method and the rational formula were used.

    The method is based on an empirical formula to calculate the time of concentration (Tc) of the

    catchment. Richards method takes account of the rainfall pattern and intensity and the

    catchment characteristics determining its run-off, size, shape and slope as well as soil and

    vegetation type (the latter two collated into a run-off factor Kr).

    Time of concentration Tc:

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    afSRKLCTT rcc .../.1/

    23

    Where: Tc = time of concentration in hours

    L = the longest path of the catchment in km (14km)

    C = a coefficient function of (Kr.R)

    Kr = run off factor (table 3.3)

    R = rainfall coefficient; FttR ./1

    F = total rainfall in mm for the selected storm duration t

    t = selected storm duration (12 hours)

    s = slope of the catchment (4%)

    a = the area of the catchment in km2

    f(a) = ratio of the average rainfall intensity (i) to the maximum rainfall intensity (I) over the

    catchment area

    Once the time of concentration Tc has been derived, the rainfall intensities are calculated as

    follows:

    )1/( cTRI (mm/hr)

    and

    )(. afIi (mm/hr)

    Finally the rational formula is used to calculate the expected maximum flood flow

    6.3/.. aiKQ rp (m3/s)

    The rainfall intensities for return periods of 5, 10, 25, 50 and 100 years were obtained from the

    Rainfall Frequency Atlas of Kenya. The rainfall intensity for 1000 years return period was

    developed using Gumbels Type 1 External Distribution Values.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    The following table shows flood flows for different return periods

    Return period Flood (m3/sec)

    5 8.5

    20 11.3

    50 16.6

    100 17.0

    500 19.5

    1000 21.8

    Figure 6.1 PMF for Theta Dam

    The flood flow return periods for each dam classification are given in the table 6.2 below.

    Recommended return periods for the design of spillways

    10 25 50 100 500 1000

    5

    10

    15

    20

    25

    Return Period - Years [Log scale]

    Flood Discharge

    m3/s

    Theta Dam Probable Maximum Flood

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Class of Dam Minimum return period for spillway design

    A (Low Risk) 1 in 50

    B (Medium Risk) 1 in 100

    C (High Risk) 1 in 500

    However, in order to ensure maximum safety of the dam and also to take care of the

    uncertainties that might have arisen due to limited hydrological data that is available for the

    catchment area, a return period of 1 in 1,000 years is adopted.

    GENERALIZED TROPICAL FLOOD MODEL

    This model combines the merits of the East African Flood Model with the experience gained in

    catchment modeling in West Africa and it is applicable in all areas of the tropics where locally

    validated alternatives are not existing as is the prevailing situation in the area under study. It

    involves determination of model coefficients where three components are established.

    These are:

    i. Hydrograph base time

    ii. Contributing area coefficient

    iii. Peak flow factor

    After computations, the flood flows for various return periods are shown in the table below:

    Return Period Flood flow in m3/sec

    5 10.8

    20 14.1

    50 16.2

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    100 17.7

    500 21.3

    1000 22.8

    The flood flow for a 1,000 year return period is 22.8m3/sec but for design purposes, the flood

    flow has been rounded to 25m3/sec.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DAM EMBANKMENT DESIGN

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DESIGN OF DAM AND ANCILLARY WORKS

    SELECTION OF DAM TYPE

    Dams are classified according to the materials used for construction. Usually, they are made of

    earth, rock, concrete and masonry. A combination of dams using earth materials at the abutments

    and concrete in the middle to form the spillway section is another form of a dam called

    composite structure, but it requires workmanship of a high standard because of the interface

    between the soil material and concrete.

    The choice of the material depends firstly upon the geology of the proposed dam site and

    secondly upon the costs of the various alternatives. Concrete and masonry dams require a hard

    rock foundation, but earth dams can be constructed on either rock foundations or on firm clays

    and other sound strata not as hard as rock. Whatever the type of the dam used, the foundation

    material below the dam must be either watertight, or capable of being made watertight by such

    means as grouting. The dam, foundation and abutments must also be stable under all static and

    dynamic loading conditions.

    EARTH AND ROCK FILL EMBANKMENT DAMS

    Classification of dams into either earthfill or rockfill category is determined by the construction

    materials.

    EARTH DAMS

    Earth dams are composed of suitable material from borrow areas or required excavation and

    compacted in layers by mechanical means and can either be homogeneous or zoned. Compaction

    is done by means of tamping rollers, sheep foot rollers, heavy pneumatic rollers, vibratory

    rollers, tractors or earth hauling equipment.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    ROCKFILL DAMS

    Rock fill dams are composed largely of fragmented rock with an impervious core. The rock fill

    layers are compacted in layers of approximately 250 mm thick by rubber-tyred rollers or steel

    wheel vibratory rollers. Free- draining, well-compacted rock fill can be placed with steep slopes

    if the dam is on rock foundation. In both cases, a core trench should be constructed for purposes

    of minimizing seepage losses under the foundation.

    Based on the topography of the dam site and the preliminary geophysical and geological study

    results, it is recommended to construct an earth dam with a central impervious clay core since

    this is the most economical and technically suitable type of dam considering the availability of

    materials within the vicinity of the dam site.

    DESIGN CRITERIA

    The design of a structure should ensure a safe and economical section which in the case of an

    earth dam is realized through optimization of the slopes.

    The foundation, abutments and the embankment should be stable for all conditions of

    construction and operations.

    Other factors to be considered are as follows:

    i. Seepage through the embankment, foundation and abutment should not result in

    excess forces.

    ii. Use of non dispersive to reduce piping

    iii. The gross freeboard dam must be sufficient to prevent overtopping and to allow

    for settlement of embankment and foundation.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    iv. The spillway and outlet works should be adequately sized to prevent

    overtopping the dam crest.

    v. The side and longitudinal slopes of the spillway must be stable.

    vi. Embankment slopes should be stable under all conditions

    The construction materials for the embankment wall will be excavated from the borrow areas

    within the reservoir area and this will increase the storage capacity of the reservoir and overly

    increase the suitability coefficient of the site.

    THE PLATE BELOW SHOWS THE GORGE ACROSS WHICH THE DAM WILL BE CONSTRUCTED

    SIZING THE DAM

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    The estimated storage capacity of the reservoir is based on the topographic survey map done in

    July, 2010 by Geosite Systems of Nairobi, using scale of 1:10,000.

    SLOPES

    The United States Bureau of Reclamation (USBR) as well as the Design Manual for Water

    Supply Systems in Kenya 1986 Edition both recommend upstream and downstream slopes of

    1:3.0 and 1:2.5 respectively during the preliminary design stages. However, these slopes have

    already been optimized during the through slope stability analysis and they are stable.

    CREST WIDTH, LENGTH AND DAM HEIGHT

    According to the Ministry of Water Irrigation Design Manual, the minimum crest width of an

    earth dam should be 5.0m especially to allow for access road and manipulation of machinery and

    equipment during construction. The US Bureau of Reclamation recommends a minimum crest

    width of 3m. The crest should also be sloped to promote drainage and minimize surface

    infiltrations. It should also be cambered so that the design freeboard is maintained after post

    construction settlement takes place.

    The proposed Theta Dam is a homogeneous earthfill embankment wall with a crest width and

    length of 10 m and 60 m respectively. According to the contour survey, the crest of the dam is on

    2251 masl while the bed is on 2234 masl thereby giving a 17m high embankment wall.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    SPILLWAY DESIGN

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DAM FREE BOARD

    Spillways are provided to facilitate release of surplus water or floodwater that cannot be

    contained in the available storage space. The importance of safe spillway cannot be over-

    emphasized; many failures of dams have been caused by spillways of insufficient capacity.

    Reservoir spillways are therefore major hydraulic structures during dam construction and later in

    the operation and regulation of the dam. Spillways are designed to discharge the largest possible

    flood during the design life of the dam for a selected return period.

    Guidelines for spillway design floods in Kenya are presented in three design manuals produced

    by the Ministry of Water and Irrigation (MoWI).

    i. Guidelines for the Design, Construction and Rehabilitation of Small Dams and

    Pans are used for dams of heights not more than 10m.

    ii. Practice Manual for Water Supply Services in Kenya

    iii. Water Resources Management Authority (WRMA) Guidelines

    The first two manuals are applicable for small dams. For larger dams, Water Resources

    Management Authority (WRMA), has published guidelines which are based on the perceived

    risks associated with dam failure. The table below shows the categorisation of dams based on

    storage depth, storage volumes and runoff catchments.

    The minimum required freeboard (above F.W.L) of the dam was evaluated from wind set up,

    significant wave height and wave run up. The value of wind set up is a function of the fetch of

    the reservoir and the velocity of wind in the direction of predominant winds. In the case of Theta

    dam, the fetch of the reservoir is is approximately 450m considering the left arm of the reservoir.

    The spillway for this dam will be located on the right hand side of the dam. This location of the

    spillway will avoid construction of a bridge on piers for purposes of moving to the right hand

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    side of the reservoir. This arrangement will also reduce the construction cost of the bridge and

    the necessary piers.

    Categorization of dams based on storage depth, storage and runoff catchments

    Class of

    dam

    Maximum Depth

    of Water at NWL

    (m)

    Storage (m3) Catchment Area

    (km2)

    Minimum Return

    Period for

    spillway design

    A (low

    risk)

    0 4.99 1,000,000 >1000 1 in 100 Years

    Design of Small Dams by the United States Bureau of Reclamation (USBR), 1987, recommends

    use of probable maximum flood (PMF) for spillway inflow design. PMF hydrograph represents

    the maximum runoff condition resulting from the most severe combination of hydrologic and

    meteorological conditions considered reasonably possible for the drainage basin under study.

    The PMF is used by design and construction organizations as a basis for design in those cases

    where the failure of the dam from overtopping would cause loss of life or widespread

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    destruction. In estimating PMF, use is made of Maximum Probable Precipitation which requires

    isolation of rainfall storm in the catchment of interest.

    This information on particular storm and criteria for developing PMF and PMP is not developed

    currently. In view of this, the consultant has used the 1 in 1,000 year frequency flood (25m3/s)

    for spillway design.

    SELECTION AND SIZING OF THE SPILLWAY

    Preliminary hydraulic sizing of the spilling is undertaken based on the peak flow analysis. An

    inflow flood of 25m3/s (1:1,000 year return period) is used to size the spillway.

    The critical depth is determined using the following equation:

    hc = 3q2/g

    Where,

    hc is critical water depth on top of the spillway sill. The critical depth is two

    third the approach depth (ha): hc = 2/3ha.

    ha =3/2*3q2/g,

    Specific discharge (q) = 25/15 = 1.67 m2/s

    Critical depth hc = 3q2/g

    A table for selecting the best width of the spillway front through the critical depth equation is

    presented below:

    Q B q q^2 q^2/g (q^2/g)^0.33 ha

    25 5 5 25 2.54842 1.361662353 2.042494

    25 10 2.5 6.25 0.637105 0.861766551 1.29265

    25 15 1.666667 2.777778 0.283158 0.659431065 0.989147

    25 20 1.25 1.5625 0.159276 0.545393347 0.81809

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    25 25 1 1 0.101937 0.470705451 0.706058

    From the above table, an open channel spillway with a front width of 15m is selected. The

    critical depth and the depth of water in the reservoir are as follows:

    Description Depth of water (m)

    hc 0.659

    ha 0.989

    The open channel spillway is selected since it fulfills the fundamental requirements of low cost,

    less demand for workmanship and availability of local labour. Secondly, the excavated materials

    will be used as random fill depending on their suitability.

    WIND SET UP

    Wind set up (the tilting of the reservoir surface caused by the movement of the surface water

    towards the leeward shore under the action of wind) was estimated from the following formula:

    Zs = (Vw .F)/ (63,200d) metres

    With: Zs = rise above the still water level

    Vw = speed of the wind in (km/hr)

    Vw = The speed of the wind is assumed to be 54km/hr (15m/s)

    F = fetch of the reservoir (0.45 km)

    d = average depth of the reservoir along the fetch (10.0 m)

    Hence:

    Zs = ((54^2) x0.45)/ (63,200x10.0) =0.0021m

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Significant wave height: The average height in metres (Zw) of the highest one third of the waves

    was estimated as follows:

    Zw =0.005Vw (^1.06) F (^0.47) (m)

    Hence: Zw =0.005 x 54(^1.06) x4.0 (^0.47) =0.197m

    Wave run up: the height to which a wave will run up a slope depends on the surface. The ratio

    [wave run up / significant wave height Zr/Zw] depends on the ratio of wave height to wave

    length

    The wave period tw can be expressed as follows:

    tw =0.32Vw 0.44 F0.28 (m)

    Hence: tw =0.32 x 54 0.44 x 0.45 0.28 =1.48

    The wave length may be computed from:

    = 1.56tw2 =1.56x2.19 = 3.42 m

    Ratio Zw/ =0.197/3.42 = 0.057

    For embankments lined with riprap and an upstream slope of 1/3, the ratio Zr/Zw should not

    exceed 0.7

    Zr=0.7x 0.057 =0.04m

    Depth of Water above the Spillway Sill

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Required Dam freeboard: the required dam freeboard was then obtained as the sum of wind set

    up, significant wave height and wave run up.

    Required dam free board (above F.W.L.) = 0.0021+0.197+0.04+0.987 =1.23m

    Allowing a safe board of 0.6m, then a gross freeboard 1.83m which is rounded to 2.0m and

    which is considered to be adequate for the dam.

    DESIGN OF THE INFLOW AND OUTFLOW SECTIONS OF THE SPILLWAY

    INFLOW SECTION

    With a 2.0m gross freeboard, the normal water line will be on level 2249 since the crest is on

    level 2251m. The inflow section is 22m long and it will have an invert slope of 1% towards the

    reservoir. The level at the entrance point to the spillway is, therefore, 2248.78m. About 10m of

    the inflow section before the spillway sill will be rip-rapped or stone pitched to prevent any

    erosion since this is the area where transition of flows will take place just before the sill. The

    spillway width tapers from 15m at the entrance point to 5m at the exit point.

    OUTFLOW SECTIONS OF THE SPILLWAY

    The outflow section of the spillway is 70m long. The longitudinal profile of the spillway has

    been selected in such a manner as to reduce the volume of earthworks and hence the construction

    cost. The depth of water above the spillway sill is 2249m where the depth of water will be equal

    to the critical depth (0.659m) and the exit point is on level 2234m. The two levels at the entrance

    and exit points of the spillway through the length of 70m give a slope of 0.214m.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    NORMAL DEPTH OF WATER AT THE TERMINAL POINT OF THE SPILLWAY

    The width of the spillway channel at the terminal point is 5m. The normal depth of water at the

    terminal point of the spillway is calculated using the uniform flow equation. And the calculations

    are presented in the table below.

    214.0

    014.0

    1

    arg

    ,

    6/1

    hechannelalslopeoftlongitudini

    ofconcreteoefficientroughnesscn

    Rn

    C

    P

    AR

    adiusHydraulicrR

    meterwettedperiP

    ficientChezyscoefC

    AreaA

    eDischQ

    RiACQ

    Using the equation and the data, the depth of water is calculated using trial and error method.

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.25 5 1.25 5.5 0.22727273 0.78119218 55.7994414 0.22053654 15.3822694

    0.28 5 1.4 5.56 0.25179856 0.79464936 56.7606689 0.2321312 18.4462907

    0.3 5 1.5 5.6 0.26785714 0.80287981 57.3485581 0.23941894 20.5954964

    0.32 5 1.6 5.64 0.28368794 0.8106004 57.9000285 0.24639241 22.8258041

    0.33 5 1.65 5.66 0.29151943 0.81428778 58.1634131 0.24977021 23.9703553

    0.338 5 1.69 5.676 0.29774489 0.81716054 58.3686099 0.25242307 24.8997565

    0.339 5 1.695 5.678 0.29852061 0.81751498 58.3939271 0.25275168 25.0167812

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    0.34 5 1.7 5.68 0.29929577 0.8178684 58.4191717 0.25307962 25.1339934

    0.35 5 1.75 5.7 0.30701754 0.82134799 58.6677136 0.25632353 26.3163525

    0.38 5 1.9 5.76 0.32986111 0.83123123 59.3736595 0.26568831 29.9722857

    0.4 5 2 5.8 0.34482759 0.83740137 59.8143836 0.27164886 32.4970183

    From the above calculations, the normal depth of water as a function of height h is equal to

    0.339m which is rounded to 0.34m.

    FLOW PROFILES

    As seen from the calculations the depth of water will be 0.659m above the spillway sill. Due to

    the tapering nature of the spillway, this depth will reduce to 0.168m within the first 10m length

    of the spillway. Thereafter, the depth of water will keep on increasing and it will attain a level of

    0.339m(0.34m) at the terminal point of the spillway.

    DEPTH OF THE RETAINING WALL

    The purpose of the retaining wall is to confine the flood flows within the spillway channel. The

    height of the wall at the sill is 2m which then reduces to 0.85m within the first length of 7m. The

    other heights of the retaining wall are established using Mannings equation and they are

    established at 10m intervals and presented in the following table.

    0m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.05 15 0.75 15.1 0.04966887 0.60622976 43.302126 0.10309772 3.34826272

    0.12 15 1.8 15.24 0.11811024 0.70040677 50.0290547 0.15898299 14.3167835

    0.15 15 2.25 15.3 0.14705882 0.72647515 51.8910823 0.17739952 20.712269

    0.168 15 2.52 15.336 0.16431925 0.74004012 52.8600084 0.18752152 24.9792201

    0.17 15 2.55 15.34 0.16623207 0.74146928 52.9620912 0.18860982 25.4723845

    0.18 15 2.7 15.36 0.17578125 0.74840542 53.45753 0.19395151 27.9940551

    0.19 15 2.85 15.38 0.18530559 0.7550175 53.9298213 0.19913663 30.6072979

    h=0.168

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    10m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.05 13.6 0.68 13.7 0.04963504 0.6061609 43.297207 0.10306259 3.03437921

    0.12 13.6 1.632 13.84 0.11791908 0.70021767 50.0155476 0.15885428 12.9665399

    0.15 13.6 2.04 13.9 0.14676259 0.726231 51.8736427 0.17722075 18.7538952

    0.16 13.6 2.176 13.92 0.15632184 0.73391046 52.4221756 0.18290127 20.8636672

    0.179 13.6 2.4344 13.958 0.17440894 0.74742825 53.3877323 0.19319294 25.1087257

    0.18 13.6 2.448 13.96 0.17535817 0.74810484 53.4360599 0.19371796 25.3405318

    0.19 13.6 2.584 13.98 0.18483548 0.75469786 53.9069897 0.19888387 27.7036598

    h=0.179m

    20m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.05 12.2 0.61 12.3 0.0495935 0.6060763 43.2911643 0.10301946 2.72049761

    0.1 12.2 1.22 12.4 0.0983871 0.67939569 48.5282637 0.14510286 8.59073937

    0.11 12.2 1.342 12.42 0.10805153 0.69009086 49.2922042 0.15206258 10.0589605

    0.14 12.2 1.708 12.48 0.13685897 0.71782199 51.272999 0.17113685 14.9871866

    0.16 12.2 1.952 12.52 0.15591054 0.73358821 52.3991579 0.18266049 18.6830919

    0.191 12.2 2.3302 12.582 0.18520108 0.7549465 53.9247498 0.19908046 25.0155457

    0.2 12.2 2.44 12.6 0.19365079 0.76058212 54.3272946 0.20357129 26.9851249

    h=0.191

    30m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.05 10.8 0.54 10.9 0.04954128 0.60596989 43.2835633 0.10296521 2.40661869

    0.1 10.8 1.08 11 0.09818182 0.67915919 48.5113705 0.1449514 7.59433448

    0.15 10.8 1.62 11.1 0.14594595 0.72555579 51.8254136 0.176727 14.8374988

    0.206 10.8 2.2248 11.212 0.19843025 0.76367968 54.5485485 0.20606813 25.0083481

    0.25 10.8 2.7 11.3 0.23893805 0.78769876 56.2641973 0.2261255 34.3514789

    0.3 10.8 3.24 11.4 0.28421053 0.81081507 57.9153625 0.24661925 46.2770595

    h=0.206

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    40m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.1 9.2 0.92 9.4 0.09787234 0.67880185 48.4858465 0.14472277 6.45564563

    0.15 9.2 1.38 9.5 0.14526316 0.72498884 51.7849168 0.17631312 12.5998971

    0.2 9.2 1.84 9.6 0.19166667 0.75927748 54.2341054 0.20252572 20.2101941

    0.25 9.2 2.3 9.7 0.2371134 0.78669281 56.1923437 0.22526044 29.1131984

    0.228 9.2 2.0976 9.656 0.21723281 0.77529229 55.378021 0.21561035 25.0454997

    0.12 9.2 1.104 9.44 0.11694915 0.69925425 49.946732 0.15819962 8.72331544

    h=0.228

    50m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.1 7.7 0.77 7.9 0.09746835 0.67833397 48.4524266 0.14442378 5.38821555

    0.15 7.7 1.155 8 0.144375 0.72424802 51.7320014 0.17577329 10.5025353

    0.2 7.7 1.54 8.1 0.19012346 0.75825495 54.1610675 0.20170875 16.8241323

    0.255 7.7 1.9635 8.21 0.23915956 0.78782045 56.272889 0.22623029 24.9965964

    0.228 7.7 1.7556 8.156 0.21525257 0.77410967 55.2935476 0.21462537 20.8344045

    0.12 7.7 0.924 7.94 0.1163728 0.6986786 49.9056141 0.15780931 7.27702717

    h=0.255m

    60m

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.1 6.5 0.65 6.7 0.09701493 0.6778069 48.4147787 0.14408745 4.53437539

    0.15 6.5 0.975 6.8 0.14338235 0.72341554 51.6725386 0.17516799 8.82509018

    0.2 6.5 1.3 6.9 0.1884058 0.75710866 54.07919 0.20079552 14.1165167

    0.255 6.5 1.6575 7.01 0.23644793 0.78632433 56.1660232 0.22494412 20.9412142

    0.285 6.5 1.8525 7.07 0.26202263 0.79990254 57.1358961 0.23679705 25.0636056

    0.3 6.5 1.95 7.1 0.27464789 0.80620224 57.5858746 0.24243483 27.2236026

    h=0.285

    70m

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    h B A P R R^(1/6) C (Ri)^0.5 Q

    0.1 5 0.5 5.2 0.09615385 0.6768003 48.3428785 0.14344659 3.46731045

    0.15 5 0.75 5.3 0.14150943 0.72183166 51.5594041 0.17402017 6.72928212

    0.2 5 1 5.4 0.18518519 0.75493569 53.9239782 0.19907192 10.7347499

    0.25 5 1.25 5.5 0.22727273 0.7811536 55.7966857 0.22053654 15.3815097

    0.339 5 1.695 5.678 0.29852061 0.81748204 58.391574 0.25275168 25.0157731

    0.35 5 1.75 5.7 0.30701754 0.82131566 58.6654044 0.25632353 26.3153167

    h=0.339

    The flow profile is shown in the following graph.

    L m

    0 0.168

    10 0.179

    20 0.191

    30 0.206

    40 0.228

    50 0.255

    60 0.285

    70 0.339

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    RESERVOIR CHARACTERISTICS

    From a topographic survey which was done in July, 2010 and the selected dam height of 17m,

    the area volume height relationship curve of the reservoir was computed and the amount of

    storage up to the normal water of the reservoir considering a gross freeboard of 2m is

    1,170,000m3 while the submerged are is 117,000m

    2.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    VOLUME CURVE

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    AREA CURVE

    EMBANKMENT VOLUMES

    The embankment volume for Theta Dam is estimated using the topographic survey and it is

    equal to 20,482m3.

    SUITABILITY COEFFICIENT OF THE SITE

    The suitability coefficient (SC) of the site is the ration of the volume of fill material to the

    volume of the water stored in the reservoir.

    In the case of Theta Dam, this ratio is calculated using as follows:

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    57

    20482

    000,170,1

    SC

    SC

    fillvolume

    storageSC

    This ratio represents a very good site whereby the unit cost of water will be very low.

    SEDIMENT LOADS

    The sedimentation yield of catchments in Kenya is estimated to range between 500 1500

    m3/km

    2/year depending on the rates of erosion. For this particular catchment and based on the

    above figures, the sediment yield is assumed to be 500m3/km

    2/year.

    DEAD STORAGE

    The Dead Storage of the reservoir is dependent of the size of the catchment area and the degree

    of environmental degradation/conservation. The amounts of sediment loads determine the

    economic lifespan of the dam.

    This dam is in a thick forest with very little sediment loads. In this regard, a sediment load of

    500m3/km

    2/year is assumed for the entire catchment area of 1.6km

    2. The annual sediment yield

    is 800m3. Assuming a trap efficiency of 6% the total sediment trapped is 28.8m

    3. Assuming a

    specific gravity of sediment is 1.85t/m3, then the annual volume of sediments is 54m

    3.

    Considering a lifespan of 200 years, then the volume of the required dead storage is 10,800 m3.

    However, due to uncertainties in the estimation of the degree of environmental degradation, and

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    a desire to increase the volume of sediment loading, a final dead storage volume of 100,000 m3 is

    adopted for this dam. This gives the dead water level to be on 2238.8m.

    It is necessary to note that most of the sediments will be deposited in the upper reaches of the

    reservoir thereby reducing its fetch. This has a positive attribute in the sense that the reservoir

    waters will be very clear which reduces the cost of treatment.

    Figure 1.3 Trap Efficiency of Reservoirs2

    CENTRAL CLAY CORE

    The dam will have a central clay core which will be excavated to a depth of 3m to encounter a

    good foundation. The core trench will then be cleaned and be filled up with impervious clay

    .

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    material which will be properly compacted at the optimum moisture content until the maximum

    densities will be achieved.

    UPSTREAM SLOPE PROTECTION

    The dam will have a protection of the upstream slope comprising of graded rip rap material on a

    protective granular material or geotextile polyfelt material preferably T600. The embankment toe

    of the dam will have rock toe drain to protect the slope from both wild and domestic animals

    .

    DOWNSTREAM SLOPE PROTECTION

    The downstream slope will be protected by grassing on a 25mm thick red soil. Both the slope

    and the berm will be grassed down to the rock toe drain which will protect the slope from

    destruction by both wild and domestic animals.

    FILTERS

    The dam will have horizontal filter drains that will connect the rock toe with the impervious clay

    core. The filters will lower the phreatic line within the limits of the downstream slope of the

    embankment wall and thus maintain most of the materials in a dry condition. This will increase

    the stability of the downstream slope. The filters will be 4 in number and they will be

    constructed using graded sand and ballast all surrounded in geotextile polyfelt material.

    DAM STABILITY

    The usual failure of an earth embankment dam consists in the sliding of a large mass of soil

    along a curved surface. There are various methods of checking the stability of a fill. In all these,

    a failure arc is assumed and the forces acting on the sliding mass are worked out. These forces

    are resisted by the shear force developed along the sliding surface. The Factor of Safety (F.O.S.)

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    is the ratio of the shear force to the forces causing sliding. Several failures arcs are assumed and

    the respective F.O.S. is calculated. The minimum F.O.S. is then taken as the Factor of Safety.

    The slope stability analysis is done based on the adopted slopes and the soil properties (section

    5) using the Bishop Microcomputer Tool and the results are presented in appendix II and

    drawing no. DRG. THETA.. The F.O.S on the upstream slope is

    .. while the downstream slope is both of which are above the

    acceptable F.O.S levels of 1.2.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    RIVER DIVERSION WORKS

    AND DRAW OFF SYSTEM

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    RIVER DIVERSION WORKS AND DRAW OFF SYSTEM

    During the construction phase, the flows along the river course will be diverted so as to create a

    good working environment. This will be done by way of constructing an upstream coffer dam

    and a river diversion channel in form of a box culvert. The draw off pipe will be fixed inside the

    box culvert as well as the scour pipe in case it may become necessary to drain the reservoir after

    impoundment takes place. During the construction and impoundment phases of the reservoir,

    compensation flow equivalent to 85% of the base flow will be released for sustenance of the

    ecosystem downstream of the dam. Similarly, compensation flows will be released through the

    same pipe even after impoundment and especially when the dam is not spilling. This is made

    possible by the fact that the storage capacity of the dam is huge enough.

    The river diversion works should be capable of evacuating a peak flood flow 1 in 20 year return

    period, the magnitude of which is 14.1m3/sec. In this case, a 8.5m high coffer dam will be

    constructed to facilitate release of the diversion flow. The freeboard below the crest of the coffer

    dam is 2m which means that a water depth of 5m is considered for purposes of the design of this

    component. The coffer dam will ultimately be incorporated into the main embankment wall of

    the dam.

    The diversion flow is assumed to be 6m3/sec and the size of the pipe is determined as follows:

    0.1.........arg

    2

    tcoefficienedischC

    Where

    gHCAQ

    A = Cross sectional Area

    Assuming a freeboard of 2m, the depth of water H, therefore, is equal to 6.5m

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    224.1

    5.681.92

    14

    2

    214

    14

    mA

    xxA

    gHC

    QA

    gHCA

    Q

    SIZE OF THE DIVERSION PIPE

    From the above analysis, the flows will be diverted through a box culvert measuring 1.24m high

    and 1.0m wide.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    ENERGY DISSIPATION

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    ENERGY DISSIPATION

    The flood flows as they are discharged back to the river bed will cause a hydraulic jump where

    excessive energy will be generated. This energy will scour the river bed as well as the bed of the

    spillway. It is, therefore, necessary to dissipate the excessive kinetic energy within the limits of

    the hydraulic jump and just before the terminal point where the spillway joins the river channel.

    This will be accomplished by constructing a flip bucket just near the terminal point of the

    spillway whereby the water jet will be deflected to the atmosphere where the water will lose

    substantial amount of energy before it falls on the river course.

    The profile of the spillway is such that it tapers from 15m wide at the sill to 5m at the terminal

    point.

    In order to achieve the maximum length to where the water jet will fall from the edge of the flip

    bucket, different angles of inclination to the horizontal are assumed and the optimum angle of

    inclination to the horizontal is selected.

    DETERMINATION OF THE VELOCITY OF FLOW AT THE TERMINAL POINT

    From the calculations, the normal depth of water as a function of height h is equal to 0.339m

    which is rounded to 0.34m. The velocity of water at the terminal point is expressed using the

    following equations:

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    sec/7.14

    7.1

    25

    7.1

    34.05

    2

    mV

    V

    A

    QV

    mA

    xA

    BhA

    AVQ

    FLIP BUCKET EQUATION

    The equation for the flip bucket is as follows:

    )2

    {2 2

    22

    V

    gySinSinCos

    g

    VL

    If the angle of inclination is equal to 00, then the equation is as presented below:

    Where:

    L - Horizontal distance from the heel to the centre of the erosion zone

    v - Velocity of water at the terminal point of the spillway = 14.7m/sec.

    - Angle of inclination to the horizontal

    y - Difference in elevation between the heel and the erosion depth. In this case, y

    is assumed to be 2.0m

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    Angle of inclination () Length L (m)

    100 6.87

    150 8.06

    200 9.20

    250 10.21

    300 11.03

    350 11.62

    400 11.92

    450 11.94

    500 11.63

    550 11.01

    From the above table, it is evident that the farthest length of possible point of erosion L from the

    edge of the flip bucket is achieved when the angle of inclination is 450 when the length is

    approximately 11.94m. A corresponding graph for the calculations is presented below.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DETERMINATION OF THE HEIGHT OF THE WALL WITHIN THE HYDRAULIC JUMP SECTION

    The height of the wall within the limits of the flip bucket is calculated on the basis of the normal

    depth of water which is equal to 0.34m and the congruent depth.

    INITIAL DEPTH AT THE TERMINAL POINT OF THE SPILLWAY

    The initial depth according to the calculations is 0.34m

    THEORETICAL CONGRUENT DEPTH

    The congruent depth is determined on the basis of the initial or critical depth of water which is

    equal to 1.37m and it also guides on the height of the wall within the limits of the flip bucket.

    However, the depth of water at the terminal point of the spillway channel is below the critical

    depth and hence supercritical. The initial depth as established earlier is 1.37m

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    mightofallwithaheConsideraw

    mh

    xh

    h

    x

    xxxh

    gh

    qhh

    4

    87.3

    77.22685.0

    }122.25

    2201{685.0

    }137.181.9

    551.181{

    2

    37.1

    }18

    1{2

    2

    2

    2

    32

    3

    1

    2

    12

    = non uniform distribution of velocity 1.1

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    GEOLOGICAL INVESTIGATIONS

    AND SEISMICITY

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    GEOLOGICAL INVESTIGATIONS

    INTRODUCTION

    Some initial investigations were carried out in two stages to determine the feasibility of the dam

    site. The first stage desk comprised of the study of topographical and geological maps of the

    area. The second stage involved a walk over survey of the selected dam site including the

    proposed dam foundation axis and sites of other structures such as spillway and diversion and

    outlet works and the area that will be submerged by the reservoir upon its impoundment after the

    completion of the dam.

    The two stages allowed an assessment of topographical features, suitability of the dam and other

    structures foundation in terms of strength, durability, water tightness etc, and how these

    conditions are likely to influence the subsequent dam design.

    GEOLOGY OF THE AREA

    The project area is within the tertiary volcanics of middle and upper tertiary age which are

    widespread in Central Kenya. Hey are mainly of alkaline type including basalts phonolites,

    nephlenites, trachytes and alkali rhyolites and their pyroclastic equivalents.

    .

    FAULTS

    The probable fault marked in the geological map of Kenya is to the west of the proposed dam

    site and it cuts along the Great Rift Valley from Ethiopia to the north to Tanzania to the south.

    SEISMIC POTENTIAL

    The seismic map of possible intensities in Kenya from Professor L. S. Loupekines report on

    Earthquakes in Kenya zones the project site as Zone VI in a scale of V to IX on increasing

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    intensities. The site is, therefore, in an area of minimal seismic potential. However, appropriate

    design seismic parameters will be adopted in the stability calculations.

    In accordance with the Code of Practice relating to earthquake design and seismic zoning map of

    Kenya the proposed dam site located in Zone VI. This zone (Zone VI) is characterized as having

    intensity of Damage is slight; a few instances of fallen plaster or damaged chimneys.

    Table 5.1: Earthquake parameters for some dam projects in Kenya

    Dam Project Design Basis

    Earthquake DBE

    Maximum

    Credible Earthquake

    MCE

    Comments

    Turkwel amax. = 0.20g

    Return period

    410 years

    amax. = 0.45g

    M = 7.5 Occurring at

    20km. from dam site.

    Dam completed in

    1988 1991

    Chemususu amax. = 0.22g

    Return period

    400years

    a max. = 0.50g

    M = 7.5

    Return period 2540

    years

    Dam located at the

    intersection of Rift

    Valley and Kavirondo

    Rift

    Final design in 1989

    Kiambere a max. = 0.12g a max. = 0.25g Dam completed in

    1988

    Thika a max. = 0.13g a max. = 0.40g Dam completed in

    1988

    Source: SOGREAH Consultants-Feasibility Study of Rehabilitation of Sasumua Dam

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DAM CONSTRUCTION MATERIALS

    The most economical dam is one that will utilize the materials found within reasonable distance

    from the construction site so as to reduce haulage costs. The following materials were identified

    during this initial reconnaissance of the project site:

    EARTH FILL MATERIALS

    The proposed dam site is located in a thick forest with fairly rich red clay soils of high plasticity.

    A core trench dug across the dam axis reveals a gradual change of the soil to lighter colour sandy

    murram soils at a depth of about 1.5 meter and presence of a high water table in the upstream

    reaches of the reservoir area.

    Samples of these soils were tested in the laboratory and the results are attached in Appendix 5. In

    summary sample 1, 2 and 3 representing the darkish top soils classify as inorganic clays, silty

    clays or sandy clays of high plasticity (CL). They have optimum moisture content of 24% and a

    maximum dry density of 1800 kg/m3. Samples number four gives similar results while sample

    number five classify as inorganic clays or silts of high plasticity (MH or OH). The light coloured

    soil found at a depth of 1 meter in the drainage trench classifies as well graded sand with little or

    no fines.

    ROCK MATERIALS

    The requirements for rock materials for the riprap and toe drain is that the material has to be

    hard, durable and able to withstand disintegration from mechanical or chemical weathering and

    or from quarrying, loading, haulage and placing operations.

    Within the dam site, there are no potential quarries except where such rock materials can be

    obtained from excavations during construction. In this regard, the possible quarries from rock

    materials can be obtained are in Kiamwangi, Magomano and Ndarugu but the haulage costs are a

    bit excessive due to the long distances.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    DAM FOUNDATION

    The following materials cover the dam axis defining the centre line of the dam foundation:

    Mostly weathered rocks, rock debris and murram on the steeper upper slopes.

    Deposits of silt clay and or sandy clays to gravelly silt/sandy clays on the lower gentler slopes.

    SANDY GRAVELS ON THE RIVER CHANNEL

    From the geology of the area, the above horizons overlie solid rock at relatively shallow depths.

    The above top materials will be excavated to rock over the impervious core, filter, drainage

    layers areas, and a key or cutoff trench constructed with materials similar to that used for the

    impervious core. This will reduce leakage and associated instability on the upper pervious

    foundation layers.

    In addition, a grout curtain will be constructed into the rock to seal off any joints, cracks,

    fissures, and shear zones, which may act as seepage paths. The grout curtain should extend to a

    depth equal to the head of water at any particular section.

    FILTER MATERIALS

    There are no sources of clean sand within the project site. In this regard, the sand for the

    construction works as well as filters will be sources from Masinga, Machakos or Kiserian in

    Kajiado North District.

    FIELD INVESTIGATIONS

    RESERVOIR AREA

    Thorough investigations to locate potential seepage paths such as sandy / gravel layers,

    weathered rock zones, lateritic soil zones, faults and fractured bedrock zones will be carried out

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    over the reservoir area during construction. This will be by way of geophysical methods,

    geological studies, and limited borings.

    Thus:

    Electrical resistivity sounding and / or seismic refraction to map the stratification with depth and

    electrical resistivity profiling to investigate the lateral variations. A desk study of the areas

    geological maps and reports will help identify boundaries of the stratification, including soil

    overburden, weathered horizons, fractured bedrock etc.

    A few selected borings will be sunk within the reservoir area and identified stratification used to

    correlate resistivity sounding and profiling. Samples of the various strata will be taken for

    physical properties tests to proof suitability for use as dam material and for strength tests for

    slope stability analysis. Borings must be an obsolete minimum and any to be properly resealed to

    ensure it does not connect with underlying permeable layers and act as future leakage paths.

    DAM AREA

    This will be investigated by sinking borings as below:

    Along the dam axis at every 100 150 meters intervals and extending beyond the expected dam

    height by not less than 50 meters on each bank (to capture the spillway location as well)

    A next set of borings at intervals of 200 meters about 50 meters on either side of the dam axis to

    map out the lateral extent of stratification.

    A set of borings along the spillway axis, intake tunnel, emergency spillway axis at every 50

    meter spacing and at locations of intake tower, power house and treatment works.

    Disturbed samples for physical properties determination and undisturbed samples for bearing

    capacity and settlements tests will be recovered at appropriate strata. Depth to bedrock and

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    character of rock are important. In general, borings will be to a depth at least equal to the height

    of the dam.

    SUMMARY OF GEOLOGICAL INVESTIGATIONS

    Based on the findings of the initial reconnaissance, the following conclusions can be made:

    That the location of the dam axis is geologically suitable and that a safe economical dam

    foundation can be achieved.

    That substantial quantities of materials that can be obtained from borrow areas within the

    reservoir area have low compacted dry densities (1800 kg/m3) which makes them suitable for

    dam construction works. The required quantities are estimated to be about 15,000 m3 which is

    obtainable from the nearby borrow areas.

    That rocks on hills defining the dam axis and on locations of spillway, diversion and other

    structures where excavations will be done appear suitable for use as rock fill and rip rap. The

    deficits will be bridged by rock materials from Kiamwangi, Magomano and Ndarugu quarries.

    That an earth fill dam with an impervious central clay core may be the most economical and

    technically suitable considering the materials available at the site.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    SEISMICITY

    According to the seismic zoning map of Kenya (seismic zoning map of Kenya by L. S.

    Loupekine, 1973), Theta dam is located in seismic zone V (appendix 2). This demonstrates that

    the area is not prone to earthquakes and hence no specific seismic loading design for structural

    members is necessary. For this reason no incorporation for seismic loading has been

    incorporated or checked for in the dam embankment design.

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    INSTRUMENTATION

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    INSTRUMENTATION

    Appropriate instrumentation enables monitoring of the behaviour of the dam during the

    operation phase. This will give an advance indication of the potential effects of any initial

    deficiencies or deterioration during operations. Instruments will be required to monitor the

    following design and operation parameters.

    i. Pore water pressure in the fill

    ii. Total pressure in embankment core

    iii. Settlement and distortion

    iv. Seepage flow

    v. Reservoir water level

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    AUXILIARY WORKS

  • Athi Water Services Board

    Gatundu South Water and Sanitation Company

    Design of Theta Weir

    Eng. P. Njurumba

    September, 2010

    CAMBER

    The dam will have a 30cm camber above the design crest level. The camber will take care of any

    differential settlement which might arise as a result of the consolidation of the embankment

    material. Above the camber will be a thin layer of murram to provide motorability along the

    crest.

    PARKING BAY

    A parking bay will be constructed on the left hand side of the dam to accommodate vehicles for

    the people who may wish to visit the dam site either for social or recreational purposes.

    FENCING

    Fencing of the dam is not of absolute necessity since the dam is in the forest with no noticeable

    encroachment. However, this may be done to keep off the wild animals and thus maintain water

    of a better quality.

    If fencing will be done, then cedar posts will be used with 10 strands of barbed wire G16. This

    will be shown in the general specification drawings.

    RAMP

    Theta dam is located in a forest where there are some animals and even the local people graze

    their domestic animals in the forest. In cognizance of the fact that the animals would water from

    the dam, it is proposed that ramps be constructed on both sides of the reservoir to facilitate

    watering the animals and thus prevent damage to the embankment slopes as the animals look for

    water.