THEMIS Instrument PDR GSE-1 UCB, October 15-16, 2003
IDPU Ground Support EquipmentPreliminary Design Review
F. HarveyUniversity of California - Berkeley
THEMIS Instrument PDR GSE-2 UCB, October 15-16, 2003
Overview
GSE• Requirements• GSE Components• IDPU GSE• Traveling GSE• Calibration GSEs• “Gold Box” ETU board debug• GSE Interface Board• Defect Tracking• Schedule• Issues
THEMIS Instrument PDR GSE-3 UCB, October 15-16, 2003
Requirements
Evolving Roles• ETU Board debug: digital test signals, instrument TLM…• Instrument calibration: analog stimulus, fixtures…• Flight Board test• IDPU GSE: STOL/ITOS/Hashii
Requirements• Robust for travel• No data loss or corruption introduced by GSE• Able to create semi-realistic input conditions for tests• Flight grade electronic and mechanical interfaces.• Safety checks (like FSW) for HV and deployment.• Longevity
THEMIS Instrument PDR GSE-4 UCB, October 15-16, 2003
GSE Components
Commercial• GPIB-compatible power supplies• GPIB-compatible waveform generator• Firewire-compatible 333kSps ADC• 19” 6U VME subrack• Rugged traveling case• Altera Stratix / Nios computer• GSE computer
Locally designed and built components• GSE Interface Board, software and FPGA• Power supply connection to backplane• Motor, SMA, and load simulators.• Cabling
THEMIS Instrument PDR GSE-5 UCB, October 15-16, 2003
IDPU GSE
Properties• Spacecraft-like interface to IDPU, telemetry & power• User interface is modeled on Hashii/ITOS/STOL.• Provides digital test patterns for ESA & SST• Provides analog waveforms for instrument(s)
THEMIS Instrument PDR GSE-6 UCB, October 15-16, 2003
Traveling GSE
Properties• Robust enclosure• Supports full IDPU GSE abilities, board regression testing.• Does not easily support calibrations outside SSL.
THEMIS Instrument PDR GSE-7 UCB, October 15-16, 2003
Calibration GSEs
Properties• Major parts
– EFI “Boom Box”. 2 varieties, 2 copies each, 4 Meters long– Vacuum chamber and pumps– Ion gun– Manipulator– Manipulator controller
• References– Jim Lewis’ PDR PowerPoint talks on ESA & SST– J Bonnell’s paper “Themis EFI GSE Workstation Functional
Requirements”, 9/30/2003
THEMIS Instrument PDR GSE-8 UCB, October 15-16, 2003
“Gold Box” ETU board debug
Properties• Can supply digital “test patterns” for missing parts: FGE,
SST, ESA• Usually sends DUT’s telemetry to PC, not S/C telemetry.• Small VME backplane. Shares boards with larger GSEs.
THEMIS Instrument PDR GSE-9 UCB, October 15-16, 2003
GSE Interface Board
Overview• Altera Stratix Board, mounted as daughter board• 6U parent has simple non-FPGA circuits borrowed from
DCB design.• FPGA has CDI transmit / receive, test pattern generation,
TLM receive, UART, Spin Sync logic, S/C time circuit.• Tristate logic and 100 ohm resistors allow test patterns
when certain boards are missing.
THEMIS Instrument PDR GSE-10 UCB, October 15-16, 2003
Defect Tracking
NASA-compliant Defect Tracking• Themis PFR (Problem Failure Report)• Template file supplied with GSE software• Email front end. • Tracks suspected problems with Themis, FSW, GSE,
interface boards, ITOS, MOC…• Prioritized• Cognizant Engineer is always assigned to an entry (until it’s
resolved)• Mission Assurance Holds Original & Tracks to Closure
THEMIS Instrument PDR GSE-11 UCB, October 15-16, 2003
Schedule
GSE-related target dates• DFB breadboard 10/27/03 (no UCB GSE planned)• EFI boom calibration 11/03• PCB ETU 12/08• DCB ETU 12/15• ETC ETU 12/15• BEB (actel) ETU 1/2/04• FGE ETU 1/20/04 (no UCB GSE planned)• LVPS 1/23/04• IDPU ETU 4/13/04
THEMIS Instrument PDR GSE-12 UCB, October 15-16, 2003
Schedule
I&T Flow
IDPU F1 Assembly 1 wkIDPU F1 Functionals 1 wkIDPU F1 PROM Installation/Test 2 daysIDPU F1 Functionals 1 wkIDPU F1 Limited EMC 1 dayIDPU F1 Coat/Stake 3 daysIDPU F1 CPT 2 daysIDPU F1 Test Review 1 dayIDPU F1 Vibration 1 dayIDPU F1 Thermal Vacuum 5 days
THEMIS Instrument PDR GSE-13 UCB, October 15-16, 2003
Issues
Shared Facilities• Configuration control• Upstairs Vacuum chamber• Downstairs Vacuum chamber
Tight resources for building GSEs• Layout personnel• Technicians• FPGA engineers• GSE programmers