1
Yves Brachet President Europe, Middle East and African Region
The Westinghouse AP1000® Plant: Passive, Proven Technology to Meet European Energy Demands
AP1000 is a trademark or registered trademark of Westinghouse Electric Company LLC, its affiliates and/or its subsidiaries in the United States of America and may be registered in other countries throughout the world. All rights reserved. Unauthorised use is strictly prohibited. Other names may be trademarks of their respective owners.
2
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• Offices, support centers and manufacturing units:
• Belgium: Brussels* and Nivelles • Bulgaria: Sofia • Czech Republic: Prague and Temelín • France: Orsay, Marseille, Metz and Lyon • Germany: Mannheim • Spain: Madrid, Vandellós, Hospitalet
del Infante and Asco • Sweden: Västeras and Täby • Switzerland Baden • Ukraine: Kiev and Kharkov • United Kingdom: Chorley and Springfields • South Africa: Cape Town and
Johannesburg
Westinghouse in Europe Today Serving our Customers Across the Region
* Westinghouse EMEA Headquarters
3
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• 1962 First Pressurized Water Reactor (PWR) in Europe commissioned
under Westinghouse license (Belgian Reactor 3 or BR3) • 60% of Europe’s nuclear power plants are based on Westinghouse
technology • 54 out of the 58 French reactors are based on Westinghouse licensed
technology • 25 commercial reactors designed and supplied by Westinghouse across
Europe • 4,000 highly-skilled and trained people across Europe, plus an
additional 1,500 contractors • Two nuclear fuel facilities (Springfields & Västeras) in Europe • 65 PWRs (including VVERs), Advanced Gas-cooled Reactors (AGR)
and Boiling Water Reactors (BWR) are currently fuelled by Westinghouse in Europe
Westinghouse in Europe Today Sits at the Heart of Europe’s Nuclear Industry
4
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Westinghouse AP1000 PWR Westinghouse Focus on Commercial Nuclear Technology
Our newest design – the AP1000 pressurized water reactor (PWR) – features innovative passive safety systems and
proven technologies based on Westinghouse’s 50+ years of experience
Nearly 50 percent of the nuclear power plants in operation worldwide are based on Westinghouse technology
5
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
● Passive Safety-Related Systems – Use “passive” processes only, no active pumps,
diesels, …. – One-time alignment of valves – No support systems required after actuation – Greatly reduced dependency on operator
actions ● Active Defense in Depth-Related Systems
– Reliably support normal operation – Redundant equipment powered by onsite
diesels – Minimize challenges to passive safety systems – Not necessary to mitigate design basis
accidents ● Severe accident scenario effects are mitigated
by in-vessel retention of the melted fuel
Westinghouse AP1000 PWR Major Safety Advancements
6
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Westinghouse AP1000 PWR Plant Value Drivers
Passive Safety, through Proven
Technology
Delivery Certainty, through Experience
Regulatory Certainty
Reviewed by multiple countries; first and only Generation III+ reactor to
receive design certification from the U.S. NRC
Passive safety replaces dependence on mechanical and electrical systems – harnesses natural forces like gravity,
convection and condensation to achieve safe shutdown
Provides a plant that is easier and less expensive to build, operate and
maintain
6
7
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• EUR confirms the AP1000 plant can be successfully deployed in Europe (May 2007)
• AP1000 plant amended design approved by NRC (December 2011)
• UK regulators grant Interim Design approval (December 2011)
• China licensing activities on-track, with Final Safety Analysis Report (FSAR) submitted to customer (2012)
• Combined construction and operating licenses (COL) approved for Vogtle 3&4 site (February 2012) and V.C. Summer 2&3 site (March 2012)
• Canada (CNSC) Phase 2 Pre-License (2013)
Westinghouse AP1000 PWR Regulatory Certainty
8
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
V.C. SUMMER
VOGTLE
HAIYANG
SANMEN
• Eight AP1000 units under construction worldwide - Four units in China - Four units in the United States
Photos © Georgia Power Company; South Carolina Electric & Gas Company; Sanmen Nuclear Power Company Ltd.; Shandong Nuclear Power Company Ltd. All rights reserved.
Westinghouse AP1000 PWR Global Project Delivery
9
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Haiyang 1&2 Shandong Province
Sanmen 1&2 Zhejiang Province
Westinghouse AP1000 PWR China Projects
10
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• Major equipment delivered and installed at Sanmen Unit 1 and Haiyang Unit 1 includes: – Reactor Vessel – Steam Generators – Reactor Vessel Internals – Polar Crane – Integrated Head Package
● Shield Building Conical Roof set at Sanmen Unit 1 and Haiyang Unit 1
● Passive Containment Cooling Water Tank set at Sanmen Unit 1 and Haiyang Unit 1
● Digital I&C turnover to Startup staff in progress ● Sanmen operator candidates have completed
simulator training; Haiyang operator candidates started simulator training in July 2013
● Technology transfer well advanced
Photo © Sanmen Nuclear Power Company, Ltd. All rights reserved.
Haiyang Site – May 2014
Photo © Shandong Nuclear Power Company, Ltd. All rights reserved.
Sanmen Site – May 2014
Westinghouse AP1000 PWR Progress of China Projects: Summary
11
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
2009 to 2014
Sanmen Site Progress: Time Lapse View
12
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
V.C. Summer 2&3 Jenkinsville, South Carolina Vogtle 3&4
Waynesboro, Georgia
Westinghouse AP1000 PWR U.S. Projects
13
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• Nuclear Island basemat concrete pours completed for V.C. Summer Units 2&3; Vogtle Units 3&4
• Containment Vessel Bottom Head (CVBH) set in nuclear island for Vogtle Units 3&4; V.C. Summer Units 2&3
• First CV Ring set for V.C. Summer Unit 2; fabrication of additional rings continues at both sites
• Component and module fabrication proceeding; CA20 module (Auxiliary Building) set at Vogtle Unit 3 and V.C. Summer Unit 2
• Reactor Vessels delivered for initial units at each site; additional equipment and component deliveries continue to proceed
Vogtle Unit 3 Nuclear Island – May 2014
V.C. Summer Unit 2 Nuclear Island – June 2014
Photo © Georgia Power Company. All rights reserved.
Photo © South Carolina Electric & Gas Company. All rights reserved.
Westinghouse AP1000 PWR Progress of U.S. Projects: Summary
14
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• Strong reference plant design established
• Licensed in the country of origin
• Commitment to sustainable localization
• Multiple plants built and operating
• Experiences captured and applied for optimized delivery of future plants
Westinghouse AP1000 PWR Requirements for a Successful New-Build Program
Photo © Sanmen Nuclear Power Company, Ltd. All rights reserved.
Sanmen Site – May 2014
15
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
AP1000 Plant Optimization Continuum
SCHEDULE
COST
CERTAINTY
Current Projects
2nd of a Kind
Nth of a Kind
Achieving reduced schedule and cost, increased certainty through: - Lessons Learned - Optimization Concepts - Best Practices - Technical Advances
Westinghouse AP1000 PWR Continuous Improvement in Project and Product Delivery
16
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Sanmen 1
Haiyang 1
Sanmen 2
Haiyang 2
V.C. Summer 2
Vogtle 3
V.C. Summer 3
Vogtle 4
Xudapu 1&2
Lufeng 1&2
Haiyang 3&4
Sanmen 3&4
FNC 2009
FNC 2009
FNC 2009
FNC 2010
FNC 2013
FNC 2013
FNC 2013
FNC 2013
FNC 2014
FNC 2014
FNC 2014
FNC 2015
Westinghouse AP1000 PWR New Build – Forward Program
17
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Moorside 1, 2 & 3 West Cumbria, United Kingdom
18
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
• Toshiba and GDF SUEZ complete NuGeneration Ltd (NuGen) deal (30 June).
• NuGen plans to build three AP1000 reactors in West Cumbria (Moorside Project) - largest, single proposed nuclear power plant construction project in Europe:
Westinghouse AP1000 PWR Westinghouse New Build in the U.K.
- Delivering 3.4 GW of safe power at a competitive strike price, due to our modular design, fewer components and smaller footprint, enabling a shorter construction schedule.
- First AP1000 reactor targeted for operation in 2024 (each reactor will take approx. four years to build), due to our modular design, existing progress in Generic Design Assessment (GDA) and progress on site evaluation.
19
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Westinghouse AP1000 PWR Westinghouse New Build in the U.K.
- Providing nearly seven percent of U.K.’s projected electricity requirements; delivery enough low-carbon electricity to power six million homes.
- Creating between 14,000 and 21,000 U.K. jobs (4,000 to 6,000 at peak construction) and reinvigorating the U.K. nuclear supply chain through Westinghouse’s “We Buy Where We Build™” policy; creating sustainable, skilled manufacturing jobs.
20
Westinghouse Non-Proprietary Class 3 © 2014 Westinghouse Electric Company LLC. All Rights Reserved.
Westinghouse AP1000 PWR Thank You
Photo © Sanmen Nuclear Power Company, Ltd. All rights reserved.