The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation

Transcript of The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

Page 1: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

The Virginia Capital Trail

Jimmy CarrAssistant Secretary of

Transportation

Page 2: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• 1957 Completion of Colonial Parkway to Jamestown

• 1975 Route 5 Scenic Byway Designation

• 1997-99 “Capital to Capital Bikeway” Feasibility Study

• 2003 Preliminary Engineering begins for Eastern Section phases of the Virginia Capital Trail

• 2004 Establishment of Virginia Capital Trail Foundation

• 2005 Construction of James City phases underway East Coast Greenway Corridor Designation

• 2006 Construction of Charles City phase underwayHenrico County Location Study

Project History

Page 3: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Tourism

• Recreation

• Sustainable Economic Development

• Historic Preservation

• Alternative Transportation • Private/Local Partnerships

Project Objectives

Page 4: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

From the Canal Walk in the heart of Richmond’s modern waterfront, to the Governor’s mansion in Colonial Williamsburg, the trail will traverse a unique landscape with unrivaled historic and cultural value.

Project Corridor

Page 5: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.
Page 6: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

The Project

Page 7: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

The Project

Page 8: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Phased Development

• Complex (most expensive) /pressured phases to receive priority

• Local, Private, Inter-Agency Partnerships

• Use of designated funding sources

• Context-Sensitive Design

• Use of Existing Right-of-Way (when possible)

Project Advancement

Page 9: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• 3-mile segment connecting Jamestown Island, Colonial Parkway and Route 5

• Trailhead at Jamestown High School

• 40-Acre Wildlife Preserve Acquisition

• $3M total cost – 30% private/local funds

• Under Construction

Greensprings Phase

Page 10: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• 5-mile/$5M phase • ROW acquisitions drive cost (~40%)• Trail over new Chickahominy bridge• Local funding for park acquisition and

construction, 10% trail construction • Under Construction

Chickahominy Riverfront Phase

Page 11: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• 8-mile / $4M phase • Use of existing ROW• Link to VCU Rice Center• Historic Clerk’s Office renovated for

Visitors Center with restroom facilities• Construction to begin summer 2006

Charles City Courthouse Phase

Page 12: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Trailhead and interpretive site at Henrico County Park

• Parking and restroom facilities• Locally-managed project• Under Construction

Four-Mile Creek Trailhead

Page 13: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

Richmond Riverfront Phase

Page 14: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Existing Canal Walk to serve as Richmond terminus of the Virginia Capital Trail

• Connection with James River amenities and growing residential area

Richmond Riverfront Phase

Page 15: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Not-for-profit foundation to work in partnership with public sector

• Independent Board of Directors / staff

• Community liaison

• Private fundraising / right-of-way donation

Virginia Capital Trail Foundation

Page 16: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Richmond Riverfront Phase public involvement process

• Henrico County stakeholder outreach

• Formalize partnership with VCTF

• Prioritize/advance additional phases

Next Steps

Page 17: The Virginia Capital Trail Jimmy Carr Assistant Secretary of Transportation.

• Jamestown 2007

• Rising expense

• Closing window of opportunity

Advancement Timeline