The University of Queensland Respondent€¦ · The University of Queensland Memorandum for...
Transcript of The University of Queensland Respondent€¦ · The University of Queensland Memorandum for...
The University of Queensland Memorandum for Respondent
i
UNIVERSITY OF QUEENSLAND A U S T R A L I A
Team 20
MEMORANDUM FOR RESPONDENT
CLAIMANT Cerulean Beans and Aromas Ltd
945 Moccasin Road Cerulean
v
RESPONDENT Dynamic Shipping LLC 23 Fuchsia Crescent Cerulean
COUNSEL ▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁
SANGEETHA BADYA | LAURA HEIT | JOSHUA MCKERSEY | PRIAM RANGIAH
19th Annual International Maritime Law Arbitration Moot ▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁▁
In the matter of an arbitration under the LMAA Arbitration Rules
The University of Queensland Memorandum for Respondent
i
TABLE OF CONTENTS LISTOFAUTHORITIES......................................................................................................................................................II
SUBMISSIONSONTHETRIBUNAL’SJURISDICTION..................................................................................................3
I. THEDISPUTESHOULDBEREFERREDTOEXPERTDETERMINATION...............................................................3
A. All‘technicalmatters’mustbereferredtoexpertdeterminationbeforearbitrationcanbecommenced
3
B. TheDisputeConcerns‘TechnicalMatters’...............................................................................................................................4
SUBMISSIONSONTHEINCORPORATIONOFTHEHAGUERULES.........................................................................5
I. CLAUSE28INCORPORATESTHE1924HAGUERULES.............................................................................................5
SUBMISSIONSONDELAYANDDEVIATION.................................................................................................................6
I. THERESPONDENTISEXCUSEDFROMLIABILITYFORLOSSCAUSEDBYITSBREACHOFCL1.................6
A. TheStormwasaneventofForceMajeure..............................................................................................................................6
B. TheStormwastheeffectivecauseofdelay.............................................................................................................................7
II. ALTERNATIVELYTHERESPONDENTISEXCUSEDFROMLIABILITYFORLOSSCAUSEDBYITS
DEVIATIONTOSPECTRE.....................................................................................................................................................8
A. TheRESPONDENT’sdeviationwasreasonable..........................................................................................................................8
B. Alternatively,theRESPONDENT’sdeviationwastosavelifeorpropertyatsea......................................................9
SUBMISSIONSONDAMAGETOCOFFEEBEANS........................................................................................................10
I. THERESPONDENTDELIVEREDTHECOFFEEBEANSINGOODCONDITION.................................................11
B. Alternatively,theRESPONDENTdeliveredtheCoffeeBeans‘ascustomary’...........................................................12
II. THERESPONDENTEXERCISEDDUEDILIGENCETOENSURETHEVESSELWASSEAWORTHYIN
ACCORDANCEWITHART3(1)OFTHEHAGUERULES..........................................................................................12
III. THERESPONDENTPROPERLYANDCAREFULLYCAREDFORANDDISCHARGEDTHECOFFEEBEANS
INACCORDANCEWITHART3(2)OFTHEHAGUERULES.....................................................................................13
The University of Queensland Memorandum for Respondent
ii
A. TheRESPONDENTdischargedtheCoffeeBeansproperlyandcarefully...................................................................13
B. Alternatively,theRESPONDENTisexemptedfromliabilityunderart4(2).............................................................14
IV. THERESPONDENTDIDNOTBREACHCL34OFTHECHARTERPARTY...........................................................15
SUBMISSIONSONDAMAGES.........................................................................................................................................15
I. THECLAIMANTCANNOTRECOVERTHECOSTSOFBOTHTHEDAMAGEDCOFFEEBEANSANDTHE
SETTLEMENTPAYMENT..................................................................................................................................................16
II. INANYEVENT,THERESPONDENT’SLIABILITYISLIMITEDUNDERART4(5)OFTHEHAGUERULES17
SUBMISSIONSONTHEMARITIMELIENCLAIM........................................................................................................18
I. THECLAIMANTISNOTENTITLEDTOAMARITIMELIENOVERTHEVESSEL..............................................18
A. Thepresentfactsdonotfallwithintherecognisedcategorieswhichgiverisetoamaritimelien........18
B. TheCLAIMANTisnotentitledtobesubrogatedtothecrew’slien..............................................................................18
SUBMISSIONSONTHECOUNTERCLAIM....................................................................................................................20
I. THECLAIMANTISLIABLETOPAYTHERESPONDENTUSD1,610,000OWINGUNDERTHECHARTERPARTY................20
A. TheCLAIMANTisliableforfreightintheamountofUSD500,000..............................................................................20
B. TheCLAIMANTisliabletotheRESPONDENTfordemurrageintheamountofUSD100,000.............................21
C. TheCLAIMANTisliableforrepairstotheVessel’shullintheamountofUSD875,000.....................................21
D. TheCLAIMANTisliableforagencyfeesandthecostofelectronicaccesssystemsatDillamondinthe
amountofUSD60,000..................................................................................................................................................................................23
E. TheCLAIMANTisliableforagencyfeesatSpectreintheamountofUSD75,000................................................23
PRAYERFORRELIEF.......................................................................................................................................................25
The University of Queensland Memorandum for Respondent
i
LIST OF ABBREVIATIONS
ABBREVIATION TERM
Access Authority Pass Electronic Access Authority Pass issued at the Port of
Dillamond
Australian Hague-Visby Rules Schedules 1 and 1A Carriage of Goods by Sea Act 1991 (Cth)
Charterparty The Voyage Charterparty
Coffee Beans 1000 x 70kg bags of Native Cerulean Coffee Beans
Claimant Cerulean Beans and Aromas Ltd
Dillamond The Port of Dillamond
Expert Report Statement of Expert Opinion of Simon Webster
Record International Maritime Law Arbitration Moot 2018 Moot
Scenario
Purchaser Coffees of the World
Respondent Dynamic Shipping LLC
Spectre The Port of Spectre
Storm Storm at Dillamond which commenced on 28 July 2017
Vessel The Ship ‘Madam Dragonfly’
The University of Queensland Memorandum for Respondent
ii
LIST OF AUTHORITIES
A. CASE
Albacora v Westcott & Laurance Line Ltd [1966] 2 Lloyd’s Rep 53
Athel Line Ltd v Liverpool & London War Risks Ins Assn Ltd [1994] KB 87
Australian Coastal Shipping Commission v Green [1971] 1 QB 456
Burns v MAN Automotive (Aust) Pty Ltd (1986) 161 CLR 653
Bunge AG v Fuga AG [1980] 2 Lloyd's Rep 513
Compania Naviera Azuero SA v British Oil & Cake Mills Ltd [1957] 1 Lloyd’s Rep 312
Constable v National SS Co (1894) 154 US 51
The Tasman Discoverer [2002] 2 Lloyd’s Rep 528
E L Oldendorff & Co GmbH v Tradax Export SA (The Johanna Oldendorff) [1973] 2 Lloyd’s
Rep 285
Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 527
Falcke v Scottish Imperial Insurance Co (1886) 34 Ch D 234
Gatliffe v Bourne 4 Bing NC 314
Goulandris Brothers v B Goldman & Sons [1957] 2 Lloyd’s Rep 207
Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998)
196 CLR 161
Hartono v Ministry for Primary Industries [2018] NZSC 17 (2 March 2018)
International Packers London Ltd v Ocean Steam Ship Co Ltd [1955] 2 Lloyd’s Rep 218
Keane v Australian Steamships Pty Ltd (1929) 41 CLR 484
The University of Queensland Memorandum for Respondent
iii
Kyokuyo Co Ltd v AP Møller-Maersk A/S [2017] 2 All ER (Comm) 922
Matsoukis v Priestman & Co [1915] 1 KB 681
Monarch Steamship Co Ltd v Karlshamns Oljefabriker (A/B) [1949] AC 196
Nea Agrex SA v Baltic Shipping Co Ltd (The Agios Lazaros) [1976] 2 Lloyd’s Rep 47
Nesbitt v Lushington (1792) 4 TR 783
Nickolay Malakhov Shipping v Seas Sapfor (1998) 44 NSWLR 371
Peterson v Freebody & Co [1895] 2 QB 294
Phelps, James v Hill [1891] 1 QB 605
Postlethwaite v Freeland (1880) 5 App Cas 599
Premier Telecom Communications Group Ltd v Webb [2014] EWCA Civ 994
Re Dalma No 1 Pty Ltd (in liq) (2013) 279 FLR 80
Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries & Food [1963] 1 Lloyd’s Rep 12
Reveille Independent LLC v Anotech International (UK) Ltd [2016] EWCA Civ 443
Seabridge Shipping AB v AC Orssleff’s Eftf’s A/S (The Fjellvang) [1999] 2 Lloyd’s Rep 685
Shell International Petroleum Co v Seabridge Shipping (The Metula) [1978] 2 Lloyd’s Rep 5
Shipping Corporation of India Ltd, v Gamlen Chemical Co A/Asia Pty Ltd (1980) 147 CLR
142
Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305
Société Nouvelle d’Armement v Spillers & Bakers Ltd [1917] 1 KB 865
Sotiros Shipping Inc v Sameiet Solholt (The Solholt) [1983] 1 Lloyd’s Rep 605
The University of Queensland Memorandum for Respondent
iv
Stag Line Ltd v Foscolo, Mango & Co Ltd [1932] AC 328
TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130
The Al Taha [1990] 2 Lloyd's Rep 117
The Janet Wilson (1857) Swab 261
The Petone [1917] P 198
The River Gurara [1998] 1 Lloyd’s Rep 225
The Rosa S [1988] 2 Lloyd’s Rep 574
The Ship ‘Hako Endeavour’ v Programmed Total Marine Services Pty Ltd (2013) 211 FCR
369
The St Lawrence (188) 5 PD 250
The Tagus [1903] P 44
The Wasp (1867) LR 1 A & E 367
The William F Safford (1860) Lush 69, 167 ER 37
Toepfer v Cremer [1975] 2 Lloyd's Rep 118
Trade Green Shipping Inc v Securitas Bremer Allgemeine Verischerungs AG (The Trade
Green) [2000] 2 Lloyd’s Rep 451
Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty Ltd (1998) 192 CLR 603
Vlassopoulos v British and Foreign Marine Insurance Co (The Makis) [1929] 1 KB 187
Wenham v Ella (1972) 127 CLR 454
Zeke Services Pty Ltd v Traffic Technologies Ltd [2005] 2 Qd R 563
The University of Queensland Memorandum for Respondent
v
B. ARTICLE/BOOK
D R Thomas, Maritime Liens (Stevens & Sons, 1980)
Sir Bernard Eder et al, Scrutton on Charterparties and Bills of Ladings (Sweet & Maxwell,
23rd ed, 2015)
Kate Lewins, ‘Are the 1998 Amendments to COGSA Holding Water?’ (2000) 28 Australian
Business Law Review 422
Julian Cooke et al, Voyage Charters (Informa Law, 4th ed, 2014)
Justice Steven Rares, ‘The Onus of Proof in a Cargo Claim - Articles III and IV of the Hague-
Visby Rules and the Uncitral Draft Convention’ (2008) 31 Australian Bar Review 159
Sarah C Derrington and James M Turner QC, The Law and Practice of Admiralty Matters
(Oxford University Press, 2nd ed, 2016)
Martin Davies and Anthony Dickey, Shipping Law (Thomson Reuters, 4th ed, 2016)
Yvonne Baatz ‘Clauses Paramount’ in Charterparties; Law, Practice and Emerging Legal
Issues eds Andrew Tettenborn and Baris Soyer (Taylor & Francis: 2017)
C. LEGISLATION
International Convention for the Unification of Certain Rules of Law Relating to Bills of
Lading, open for signature 25 August 1924
The University of Queensland Memorandum for Respondent
1
STATEMENT OF FACTS
1. On 22 July 2017, Dynamic Shipping LLC (RESPONDENT) entered into a voyage charterparty
(Charterparty) with Cerulean Beans and Aromas Ltd (CLAIMANT) for the shipment of native
Cerulean coffee beans (Coffee Beans) on the Madam Dragonfly (Vessel).1 The Charterparty
required delivery of the Coffee Beans from Cerulean to the Port of Dillamond (Dillamond) by 7pm
on 28 July, for use at a festival organised by the purchaser of the Coffee Beans, Coffees of the
World Ltd (Purchaser).2 The Vessel was expected to arrive at 5.00pm on 28 July.3
2. Prior to the execution of the Charterparty, the RESPONDENT requested that the CLAIMANT pay
USD100,000 into an account for crew’s wages.4 The RESPONDENT also amended the quantity of
goods in the Charterparty to read ‘4 containers of coffee’.5 The CLAIMANT did not object.
3. On 24 July, the Coffee Beans were inspected, and, consistent with industry standards placed into
sealed, waterproof shipping containers before the Vessel departed.6 During the voyage, solar flares
knocked out the Vessel’s communications and satellite systems, forcing the Vessel to deviate to
the Port of Spectre (Spectre).7 The solar flares were described as an ‘unprecedented international
emergency’, leaving outdoor travellers ‘fearing for their lives’.8
4. At approximately 4.28pm on 28 July, after the RESPONDENT had re-commenced the voyage, the
Vessel encountered a ‘freak storm’ (Storm).9 The crew dropped anchor in an attempt to avoid the
1 Record, 2: Letter from Claimant to Respondent of 22 July 2017. 2 Record, 2: Letter from Claimant to Respondent of 22 July 2017. 3 Record, 15: Letter from Respondent to Claimant of 24 July 2017. 4 Record, 1: Claimant’s Internal Memo of 19 July 2017. 5 Record, 14: Letter from Respondent to Claimant of 22 July 2017. 6 Procedural Order 2, [13]. 7 Record, 18: Email from Respondent to Claimant of 27 July 2017 at 7.17am. 8 Record, 35: ‘Solar Flares Knock out Global Communications’ Article in the Cerulean Mail of 25 July 2017. 9 Record, 22: Email from Respondent to Claimant of 28 July 2017 at 4.58pm.
The University of Queensland Memorandum for Respondent
2
Storm. When the crew lifted anchor, the Vessel’s hull was damaged.10 At 7.00am on 29 July the
Dillamond Port Authority instructed the Vessel to wait ~100nm from Dillamond due to congestion
following the Storm.11
5. At 4.28pm on 29 July, the RESPONDENT notified the CLAIMANT that the Vessel was due to berth.12
The RESPONDENT discharged the Coffee Beans at 8.42pm.13 After waiting until midnight for the
CLAIMANT to take delivery, the RESPONDENT issued an electronic barcode created by the Dillamond
Port Authority (Access Authority Pass) at 12.02am on 30 July. 14 The Access Authority Pass
allowed the CLAIMANT to access the Coffee Beans at any time.15 According to maritime engineer
Simon Webster's expert opinion (Expert Report), three containers of Coffee Beans were
subsequently damaged between 4.30am on 30 July and 4.30am on 31 July due to prolonged use of
the sealant and unprecedented rainfall.16 The CLAIMANT claims damages for the value of the Coffee
Beans (USD15,750,000).17
6. The CLAIMANT also seeks compensation for the cost of supplying the Purchaser with alternative
coffee beans (USD9,450,000).18 In addition, the CLAIMANT requests the RESPONDENT to indemnify
the CLAIMANT for its voluntary settlement payment to the Purchaser (USD5,000,000).19 The
RESPONDENT denies liability for these amounts.20 The RESPONDENT counterclaims for damages
10 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8.58am. 11 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8.58am. 12 Record, 22: Email from Respondent to Claimant of 28 July 2017 at 4.58pm. 13 Record, 24: Email from Respondent to Claimant of 29 July 2017 at 8.42pm. 14 Record, 23: Access Authority Pass. 15 Ibid. 16 Record, 43: Maritime Engineer Simon Webster’s Expert Report. 17 Record, 37: Claimant Points of Claim [13]; Record, 30: Email from Claimant to Respondent of 2 August 2017 at 10.59am. 18 Ibid. 19 Ibid. 20 Record, 40: Respondent Points of Defence and Counterclaim [9].
The University of Queensland Memorandum for Respondent
3
for freight, agency fees incurred at Spectre, hull repairs, demurrage and use of electronic access
systems at Dillamond (USD1,610,000).21 The CLAIMANT has referred these disputes to arbitration.
SUBMISSIONS ON THE TRIBUNAL’S JURISDICTION
I. THE DISPUTE SHOULD BE REFERRED TO EXPERT DETERMINATION
7. The Tribunal should refer the dispute to expert determination because: (A) all ‘technical matters’
must be referred to expert determination before arbitration can be commenced; and (B) the dispute
concerns ‘technical matters’.
A. All ‘technical matters’ must be referred to expert determination before arbitration can be
commenced
8. The Tribunal has prima facie jurisdiction to determine disputes ‘arising out of or in connection
with’ the Charterparty.22 However, this jurisdiction is limited by cl 27(d), which provides that ‘any
dispute as to technical matters... shall be referred to expert determination by an independent Master
Mariner.’23 Subclause (e) further provides that a party may not commence arbitration in respect of
disputes unless sub-cl (d) ‘has been complied with’.24 Clause 27, read as a whole, therefore requires
all ‘technical matters’ to be referred to expert determination prior to commencement of arbitration.
This interpretation accords with the commercial purpose of expert determination – to quickly and
inexpensively resolve matters involving the application of the expert’s special knowledge.25
9. Whether the Tribunal should stay the present proceedings therefore depends on whether the matters
pleaded by the CLAIMANT involve ‘technical matters.’
21 Ibid, 41[11]. 22 Record, 12: Charterparty, cl 27(a). 23 Ibid. 24 Ibid. 25 Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305, 315 [25] (French CJ, Crennan and Kiefel JJ); Zeke Services Pty Ltd v Traffic Technologies Ltd [2005] 2 Qd R 563, 570 [27] (Chesterman J); Premier Telecom Communications Group Ltd v Webb [2014] EWCA Civ 994, 9-13.
The University of Queensland Memorandum for Respondent
4
B. The Dispute Concerns ‘Technical Matters’
10. Technical matters are defined in cl 27(g) as ‘matters surrounding technical aspects of the
performance of the charterparty, such as the vessel’s route, loading and unloading of cargo, storage
conditions.’26 This list of ‘technical matters’ is non-exhaustive and the concluding phrase, ‘and
other matters which can reasonably be considered within the expert technical knowledge of a
Master Mariner’, creates a class to which any technical matters must belong.
11. The dispute between the parties turns on the determination of several technical issues which may
reasonably be considered within the expert technical knowledge of a Master Mariner. The
following are examples of ‘technical matters’ in this dispute:
a. Whether the Vessel would have avoided the Storm if it had not deviated to Spectre.
A Master Mariner would have the expert technical knowledge required to calculate the time
added by the deviation, the average speed of ships of the Vessel’s class, the time required to
dock and depart from Spectre and Dillamond, and the sea conditions that could be expected.
b. Whether the deviation to Spectre was reasonable. This is a dispute about the ‘vessel’s
route’,27 turning on whether a ‘prudent person controlling the voyage’ would have deviated in
the circumstances.28 A Master Mariner would have expert technical knowledge about what a
prudent Master in the circumstances would have done.
c. Whether the Vessel was fit to encounter the ordinary perils of the voyage and the Coffee
Beans were properly cared for and discharged. This involves fact-intensive inquiry,
particularly into ‘the nature of the particular goods and conditions of weather and sea likely to
26 Record, 12: Charterparty, cl 27(g). 27 Ibid. 28 Stag Line Ltd v Foscolo, Mango & Co Ltd [1932] AC 328, 343, 338, 346, 349.
The University of Queensland Memorandum for Respondent
5
be encountered on the voyage.’29 A Master Mariner would have expert technical knowledge
of the conditions that would ordinarily be encountered on a voyage of this type and whether it
would have usually been adequate to apply a short term sealant. Indeed evidence from experts
is often sought on this issue.30
12. Resolution of these technical matters is critical to the determination of whether the RESPONDENT
has breached its obligations under the Charterparty. Whether the RESPONDENT is liable for the
delay in the delivery turns on (a) and (b).31 Whether the RESPONDENT has complied with art 3(1)
and 3(2) Hague Rules depends on (c).32 It would therefore be futile and contrary to the parties’
agreement for the Tribunal to hear the disputes until these matters have been referred to expert
determination.
SUBMISSIONS ON THE INCORPORATION OF THE HAGUE RULES
I. CLAUSE 28 INCORPORATES THE 1924 HAGUE RULES
13. In determining which version of the Hague Rules is incorporated, the Tribunal should consider
what the clause would mean to ‘reasonable shipping men’.33 When used in a Charterparty, the
words ‘Clause Paramount’, without further qualification, have been understood as a reference to
the 1924 Hague Rules.34 This is so even where the countries of shipment, destination and
governing law have enacted the Hague-Visby Rules.35
29 Shipping Corporation of India Ltd, v. Gamlen Chemical Co. A/Asia Pty.ltd. (1980) 147 CLR 142, 150 (Stephen J); Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998) 196 CLR 161, 181 [49], 175 [34], 194 [86]. 30 Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998) 196 CLR 161, 203. 31 See below, [20]-[21], [23]-[25]. 32 See [37]-[38]. 33 Nea Agrex SA v Baltic Shipping Co Ltd (The Agios Lazaros) [1976] 2 Lloyd’s Rep 47, 50. 34 Ibid; Seabridge Shipping AB v AC Orssleff’s Eftf’s A/S (The Fjellvang) [1999] 2 Lloyd’s Rep 685, 689; Julian Cooke et al, Voyage Charters (Informa Law, 4th ed, 2014) 996. 35 Seabridge Shipping AB v AC Orssleff’s Eftf’s A/S (The Fjellvang) [1999] 2 Lloyd’s Rep 685, 689.
The University of Queensland Memorandum for Respondent
6
14. In the absence of ‘plain’ evidence to the contrary, it must be presumed that the parties intended to
wholly incorporate the Hague Rules.36 Here, there is no qualification on the words ‘Clause
Paramount’ and hence nothing to suggest that reasonable shipping men would understand cl 28 as
incorporating anything but the Hague Rules.37
SUBMISSIONS ON DELAY AND DEVIATION
15. The RESPONDENT concedes that it did not deliver the Coffee Beans by 7.00pm on 28 July. The
CLAIMANT contends that, as a result, it incurred costs of USD9,450,000 in sourcing alternative
coffee beans and USD5,000,000 to settle the Purchaser’s potential claims.
16. The RESPONDENT is not liable for these losses because: (I) the RESPONDENT is excused from
liability for loss caused by its breach of cl 1; or (II) alternatively, the RESPONDENT is excused from
liability for loss caused by its deviation to Spectre.
I. THE RESPONDENT IS EXCUSED FROM LIABILITY FOR LOSS CAUSED BY ITS
BREACH OF CL 1
17. Clause 17 of the Charterparty provides that ‘neither party shall be liable for any...delay in
performing its obligations under the Contract, where the party is being...delayed from doing so by
reasons of any Force Majeure Event’.38 The RESPONDENT is excused from any liability for loss
caused by its breach of cl 1 pursuant to cl 17 because: (A) the Storm was an event Force Majeure;
and (B) the Storm was the effective cause of delay.
A. The Storm was an event of Force Majeure
18. The Storm was a ‘Force Majeure Event’ within the meaning of cl 17(b) as it was not an ‘unforeseen
36 Nea Agrex SA v Baltic Shipping Co Ltd (The Agios Lazaros) [1976] 2 Lloyd’s Rep 47, 50; Dairy Containers Ltd v The Ship The ‘Tasman Discoverer’ [2002] 2 Lloyd’s Rep 528, [30]. 37 Yvonne Baatz ‘Clauses Paramount’ in Charterparties; Law, Practice and Emerging Legal Issues eds Andrew Tettenborn and Baris Soyer (Taylor & Francis: 2017), 249. 38 Record, 9: Charterparty, cl 17.
The University of Queensland Memorandum for Respondent
7
weather event’.39
19. The Storm was not picked up by radars until roughly 45 minutes before it hit and was described as
a ‘freak’ and ‘once in a lifetime’ event.40 It has been consistently held by the courts that abnormal
weather events, such as hurricanes and subsequent rain and flood events, can be instances of force
majeure.41 Unlike simple bad weather, which is a usual event of voyages,42 the effects of the Storm
on 28 July were felt for four days, and the Storm forced the evacuation of thousands of Dillamond
residents.43 Further, an event characterised as ‘freak’ and ‘once in a lifetime’ cannot also be
considered a usual event capable of foreseeability. Although, at the time of entering the
Charterparty, the RESPONDENT may have contemplated bad weather as part of the usual events of
a voyage,44 it could not have foreseen, or be expected to have foreseen, a storm of this magnitude.
B. The Storm was the effective cause of delay
20. The Tribunal should find that the Storm, which hit at 5.15pm on 28 July, caused the Coffee Beans
to be delivered after 7.00pm. At 4.28pm on 28 July, when the Storm was detected on radars, the
Vessel stopped to avoid its impact.45 It would have been futile for the Vessel to proceed, as the
Storm caused the closure of the Port of Dillamond for 12 hours,46 and resulted in significant
congestion. Due to this congestion, the Vessel was ordered to wait 100nm from Dillamond until at
least 8.58am on 29 July.47
39 Ibid. 40 Record, 21: ‘“Once in a Lifetime” Storm Closes Airport, Port, Rivers’ Article in the Dillamond Times of 29 July 2017. 41 See Toepfer v Cremer [1975] 2 Lloyd's Rep 118, 121; Bunge AG v Fuga AG [1980] 2 Lloyd's Rep 513, 513. 42 Matsoukis v Priestman & Co [1915] 1 K.B. 681, 687. 43 Record, 36: ‘Flooding After Storm’ Article in the Dillamond Times Article of 1 August 2017. 44 Matsoukis v Priestman & Co [1915] 1 KB 681, 687. 45 Record, 19: Email from Respondent to Claimant of 28 July 2017 at 5.48pm. 46 Record, 21: ‘“Once in a Lifetime” Storm Closes Airport, Port, Rivers’ Article in the Dillamond Times of 29 July 2017. 47 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8.58am.
The University of Queensland Memorandum for Respondent
8
21. The Tribunal should find that, on the balance of probabilities, the RESPONDENT would have
discharged the Coffee Beans by 7.00pm 28 July but for the Storm. The Storm was therefore the
cause of the CLAIMANT’s loss.
II. ALTERNATIVELY THE RESPONDENT IS EXCUSED FROM LIABILITY FOR LOSS
CAUSED BY ITS DEVIATION TO SPECTRE
22. On 25 July the RESPONDENT stopped at Spectre,48 deviating from the customary route.49 However,
even if this deviation, not the Storm, caused the delay, the RESPONDENT is excused from liability
for any resulting losses by art 4(4) of the Hague Rules because: (A) the RESPONDENT’s deviation
was reasonable; or (B) alternatively, the RESPONDENT’s deviation was to save life or property at
sea.
A. The RESPONDENT’s deviation was reasonable
1. A prudent person would have deviated in the circumstances
23. Article 4(4) of the Hague Rules provides that the carrier is not liable for damage caused by a
‘reasonable deviation’. A reasonable deviation is one that would have been made by a ‘prudent
person controlling the Vessel, in light of all the circumstances.50 A prudent master must have
regard to his or her duty to take care of the crew, ship and cargo, and, where an imminent peril
becomes apparent, to deviate to avoid the danger.51
24. For 17 hours from 9.30pm on 25 July, the Vessel had no access to communication or navigational
systems,52 and was thus unable to chart a safe, direct course to Dillamond. Not only was the Vessel
48 Record, 17: Email from Respondent to Claimant of 26 July 2017 at 2.32pm. 49 Record, 19: Email from Respondent to Claimant of 28 July 2017 at 4.58pm; Record, 39: Claimant Points of Claim, Annexure A. 50 Stag Line Ltd v Foscolo, Mango & Co Ltd [1932] AC 328, 343-4 (Lord Wright). 51 International Packers London Ltd v Ocean Steam Ship Co Ltd [1955] 2 Lloyd’s Rep 218, 235; Phelps, James v Hill [1891] 1 QB 605, 611; Sir Bernard Eder et al, Scrutton on Charterparties and Bills of Ladings (Sweet & Maxwell, 23rd ed, 2015) 291-2. 52 Record, 35: ‘Solar Flares Knock out Global Communications’ Article in the Cerulean Mail of 25 July 2017.
The University of Queensland Memorandum for Respondent
9
unable to navigate, but it was also unable to request assistance or ascertain how long satellite
systems may be down for. Further, without maps to Dillamond, it was futile for the RESPONDENT
to continue the planned voyage. In the premises, the only reasonable course of action available to
the RESPONDENT was to deviate to a port where it could seek to have its systems repaired.
2. The liberty to deviate is not displaced by the Vessel’s unseaworthiness
25. Shipowners have liberty to deviate even if necessitated by the vessel’s own unseaworthiness, unless
the shipowner actually knew of the unseaworthiness before loading.53 It is not enough that the
RESPONDENT should have had knowledge – the CLAIMANT must show that the RESPONDENT had
actual knowledge of the factors necessitating deviation; ‘mere imprudence… is not knowledge’.54
There is no indication that the RESPONDENT had actual knowledge of the Vessel’s unseaworthiness
owing to its lack of current hard copy maps.55
B. Alternatively, the RESPONDENT’s deviation was to save life or property at sea
1. The Respondent was entitled to deviate to save life or property under cl 17 of the
Charterparty and/or art 4(4) of the Hague Rules
26. Article 4(4) of the Hague Rules provides that the carrier is not liable for damage caused by a
‘deviation in saving or attempting to save life or property at sea’. This liberty is, in substance,
identical to the liberty set out in cl 17 of the Charterparty.
27. Once the solar flares disrupted the Vessel’s navigational equipment at approximately 9.30pm, the
Vessel could not safely navigate to Dillamond.56 Further, the Vessel’s communication systems
had failed, meaning she had no way to communicate her distress. The combination of these
53 Monarch Steamship Co Ltd v Karlshamns Oljefabriker (A/B) [1949] AC 196, 211 (Lord Porter); The Al Taha [1990] 2 Lloyd's Rep 117, 128. 54 A/B Karlshamns Oljefabriker and Another v Monarch Steamship Company Ltd (1948) 82 Lloyd’s Rep 137, 145. 55 The Al Taha [1990] 2 Lloyd's Rep 117, 127. 56 See above, [23]-[24].
The University of Queensland Memorandum for Respondent
10
circumstances was such that it would have caused the crew to fear for their safety.57 The
RESPONDENT’S paramount duty was to ensure the safety of the crew, ship and cargo,58 and, as such,
it would have been dangerous for the Vessel not to seek harbour at Spectre.
2. The liberty to deviate is not qualified by an obligation of due diligence
28. The qualification in cl 17 provides that ‘all the above exceptions are conditional on the exercise of
due diligence to make the ship seaworthy’.59 The liberty to deviate to save life or property
enunciated in art 4(4) and cl 17 is a right afforded to the shipowner, rather than an exception from
liability. The purpose of the liberty is to allow the shipowner to discontinue an unsafe voyage
without fear of liability. If this liberty was tempered by an obligation of due diligence, it would
have a chilling effect, discouraging shipowners from deviating where the vessel, crew and cargo
were in peril. Accordingly, the Tribunal should find that the liberty to deviate afforded by art 4(4)
and cl 17 is not conditional on the exercise of due diligence.
SUBMISSIONS ON DAMAGE TO COFFEE BEANS
29. The RESPONDENT is not liable to pay the CLAIMANT USD15,750,000 for the damaged Coffee Beans
because: (I) the RESPONDENT delivered the Coffee Beans in good condition; (II) the RESPONDENT
exercised due diligence to ensure the Vessel was seaworthy in accordance with art 3(1) of the
Hague Rules; (III) the RESPONDENT properly and carefully cared for and discharged the Coffee
Beans in accordance with art 3(2) of the Hague Rules; and (IV) the RESPONDENT did not breach cl
34 of the Charterparty.
57 The Al Taha [1990] 2 Lloyd's Rep 117, 127. 58 International Packers London Ltd v Ocean Steam Ship Co Ltd [1955] 2 Lloyd’s Rep 218, 235; Phelps, James v Hill [1891] 1 QB 605, 611; Eder, et al, Sir Bernard Eder et al, Scrutton on Charterparties and Bills of Ladings (Sweet & Maxwell, 23rd ed, 2015) 291-2. 59 Record, 9: Charterparty, cl 17.
The University of Queensland Memorandum for Respondent
11
I. THE RESPONDENT DELIVERED THE COFFEE BEANS IN GOOD CONDITION
30. If the goods were delivered in good condition, no prima facie case arises that the carrier has
breached its obligation under art 3(1) or 3(2).60 Delivery occurred at 12.02am on 30 July. This is
because: (A) the RESPONDENT waited a ‘reasonable time’ before leaving the Coffee Beans at
Dillamond; or (B) alternatively, the RESPONDENT delivered the Coffee Beans ‘as customary’.
31. According to the Expert Report, the Coffee Beans were damaged sometime between 4.30am on 30
July and 4.30am on 31 July.61 As such, the Coffee Beans were damaged prior to delivery, meaning
that there is no prima facie breach.
A. The RESPONDENT waited a ‘reasonable time’ before leaving the Coffee Beans at Dillamond
32. Delivery ordinarily requires the cooperation of both shipowner and charterer.62 However, where a
charterer fails to collect discharged goods after a ‘reasonable time’ has passed, the shipowner can
complete delivery by leaving the goods at the port of discharge.63
33. At 4.28pm on 29 July, the RESPONDENT notified the CLAIMANT that delivery was expected at
approximately 7.00pm and that the RESPONDENT would wait with the Coffee Beans until
midnight.64 At 8.42pm, the RESPONDENT once again notified the CLAIMANT of discharge.65
Despite the RESPONDENT giving the CLAIMANT approximately 8 hours’ notice, the CLAIMANT did
not make any attempt to communicate with the RESPONDENT or accept delivery, even in
circumstances where it considered delivery to be urgent and weather conditions posed a serious
60 Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998) 196 CLR 161, 197 [98] (McHugh J); Justice Steven Rares, ‘The Onus of Proof in a Cargo Claim - Articles III and IV of the Hague-Visby Rules and the Uncitral Draft Convention’ (2008) 31 Australian Bar Review 159[56]. 61 Record, 43: Maritime Engineer Simon Webster’s Expert Report. 62 Peterson v Freebody & Co [1895] 2 QB 294, 297. 63 Keane v Australian Steamships Pty Ltd (1929) 41 CLR 484, 491 ( Knox CJ, Gavan & Duffy JJ); Gatliffe v Bourne 4 Bing NC 314. 64 Record, 23: Access Authority Pass. 65 Record, 24: Email from Respondent to Claimant of 29 July 2017 at 8.42pm.
The University of Queensland Memorandum for Respondent
12
threat to the Coffee Beans.66 At 12.02am on 30 July, having waited for approximately 8 hours,
without any response from the CLAIMANT, the RESPONDENT had allowed a reasonable time to
elapse. The RESPONDENT was therefore entitled to leave the Coffee Beans at a secure facility at
Dillamond, accessible only with a barcode and delivered via the Access Authority Pass at 12.02am
B. Alternatively, the RESPONDENT delivered the Coffee Beans ‘as customary’
34. Delivery may occur in accordance with the ‘custom and usage of the Port’.67 Specifically, here the
RESPONDENT was entitled to deliver ‘as customary’ to the port of discharge.68 The Access
Authority Pass, created and maintained by the Dillamond Port Authority is a unique custom of
Dillamond.69 Consequently, the issuing of the Access Authority Pass from the RESPONDENT to the
CLAIMANT at 12.02am constituted delivery.
35. For these reasons, the RESPONDENT delivered the Coffee Beans at 12.02am on 30 July, well before
the damage occurred. Consequently, no prima facie case of breach arises under art 3(1).
II. THE RESPONDENT EXERCISED DUE DILIGENCE TO ENSURE THE VESSEL WAS
SEAWORTHY IN ACCORDANCE WITH ART 3(1) OF THE HAGUE RULES
36. The RESPONDENT complied with art 3(1) of the Australian Hague Visby Rules, which provides that
a carrier must, at the beginning of the voyage, exercise ‘due diligence’ to make the ship seaworthy.
The obligation of due diligence under art 3(1), requires carriers to ensure the vessel is fit to meet
the conditions it may encounter on the voyage in light of all the circumstances.70 Whether the
RESPONDENT has met this obligation must be assessed at the beginning of the voyage.71
66 Record, 2: Letter from Claimant to Respondent of 22 July 2017. 67 Constable v. National SS. Co (1894) 154 US 51, 63. 68 Record, 8: Charterparty, cl 14(a). 69 Procedural Order 2, [16]. 70 Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998) 196 CLR 161, 175; Martin Davies and Anthony Dickey, Shipping Law (Thomson Reuters, 4th ed, 2016) 450. 71 Ibid.
The University of Queensland Memorandum for Respondent
13
37. The voyage was anticipated to take 4 days and 8 hours, with delivery by 5.00pm on 28 July,72 and
the RESPONDENT applied a sealant with guaranteed waterproofing for 5 days - 16 hours beyond the
duration of the scheduled voyage.73 The RESPONDENT could not have anticipated that the voyage
would be delayed for more than 16 hours by the Storm, as it was unforeseen,74 and the sealant
would expire prior to delivery.75 In light of the circumstances known to the parties at the beginning
of the voyage, the RESPONDENT exercised due diligence to ensure the Vessel was seaworthy.
III. THE RESPONDENT PROPERLY AND CAREFULLY CARED FOR AND DISCHARGED
THE COFFEE BEANS IN ACCORDANCE WITH ART 3(2) OF THE HAGUE RULES
38. Article 3(2) of the Hague Rules obliges the carrier to ‘properly and carefully load, handle, stow,
carry, keep, care for, and discharge the goods carried.’ The RESPONDENT has satisfied this
obligation because: (A) the RESPONDENT discharged the Coffee Beans properly and carefully; or
(B) alternatively, the RESPONDENT is exempted from liability under art 4(2).
A. The RESPONDENT discharged the Coffee Beans properly and carefully
39. The obligations under art 3(2) end on discharge, when the cargo crosses the ship’s rail or is
delivered from the ship’s tackle.76 After discharge, the parties’ respective liability will depend on
the terms of the Charterparty.77 There is no indication that the RESPONDENT has contractually
undertaken to care for the Coffee Beans after discharge.
72 Procedural Order 2, [7]; Record, 15: Letter from Respondent to Claimant of 24 July 2017. 73 Record, 14: Letter from Respondent to Claimant of 22 July. 74 See above, [18] – [19]. 75 Record, 19: Email from Respondent to Claimant of 28 July 2017 at 4.58pm. 76 Nickolay Malakhov Shipping v Seas Sapfor (1998) 44 NSWLR 371, 408 (Close JA); for discussion in the context of Australilan Hague-Visby Rules see Kate Lewins, ‘Are the 1998 Amendments to COGSA Holding Water?’ (2000) 28 Australian Business Law Review 422. 77 Nickolay Malakhov Shipping v Seas Sapfor (1998) 44 NSWLR 371, 389.
The University of Queensland Memorandum for Respondent
14
40. The Coffee Beans were discharged safely at Dillamond at 8.42pm on 29 July78 – approximately
8hrs before the Coffee Beans were damaged.79 Consequently, the RESPONDENT has satisfied its
obligation to properly and carefully discharge.
B. Alternatively, the RESPONDENT is exempted from liability under art 4(2)
41. The obligations under art 3(2) are expressly subject to art 4.80 In this case, the RESPONDENT is
exempted from liability for the damage to the Coffee Beans because it was caused by either: (1)
the Storm, which was a peril of the sea;81 or (2) the deviation to Spectre, which was an attempt to
save life or property.82
1. The Damage was caused by the Storm, which was a Peril of the Sea
42. Article 4(2)(c) exempts parties from liability caused by ‘perils, dangers and accidents of the sea.’
The Storm, a peril of the sea, delayed the voyage, causing the sealant to expire prior to delivery.
43. Perils of the sea need not be ‘catastrophic’ or ‘unforeseeable’, but such expressions assist in
explaining why cargo which was otherwise properly cared for under art 3(2) was nonetheless
damaged.83 The Storm was unforeseeable, appearing on radars just 30 minutes before it hit.84 It
brought ‘rain, hail, and severe winds’, knocked down powerlines and trees, and forced the
evacuation of 40,000 Dillamond residents.85
44. The Storm, being of such a magnitude, caused significant delays. It was these delays which caused
the sealant, which would otherwise have been adequate for the voyage, to expire.
78 Record, 24: Email from Respondent to Claimant of 29 July 2017 at 8.42pm. 79 Record, 43: Maritime Engineer Simon Webster’s Expert Report. 80 International Convention for the Unification of Certain Rules of Law Relating to Bills of Lading, open for signature 25 August 1924, art 3(2) (‘Hague Rules’). 81 Hague Rules, art 4(2)(c). 82 Ibid, art 4(2)(l). 83 Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad (1998) 196 CLR 161, 179 [44]. 84 Record, 19: Email from Respondent to Claimant of 28 July 2017 at 4:58pm. 85 Record, 21;‘“Once in a Lifetime” Storm Closes Airport, Port, Rivers’ Article in the Dillamond Times of 29 July 2017; Record, 36: ‘Flooding After Storm’ Article in the Dillamond Times of 1 August 2017.
The University of Queensland Memorandum for Respondent
15
2. Alternatively, the damage was caused by the deviation to Spectre, which was an attempt
to save life or property
45. Alternatively, the RESPONDENT will be exempted from liability if the damage was caused by an
attempt to save life or property.86 The RESPONDENT’s deviation to Spectre was an attempt to save
life or property.87
IV. THE RESPONDENT DID NOT BREACH CL 34 OF THE CHARTERPARTY
46. Under cl 34 of the Charterparty, the RESPONDENT warranted that the Vessel would, ‘at presentation
for both loading and discharge, conform with the quality standards required to transport the
nominated coffee cargo for the duration of the scheduled voyage.’88
47. In this case, the duration of the scheduled voyage was 4 days and 8 hours.89 Consistent with normal
industry practice, the RESPONDENT shipped the Coffee Beans in fibre bags in waterproof
containers.90 It used a sealant with ‘guaranteed waterproofing’ for up to five days,91 ensuring that
the Coffee Beans would be waterproofed for at least 16 hours after the scheduled voyage. The
RESPONDENT did not breach cl 34 because it ensured that the Coffee Beans remained waterproof
for the duration of the scheduled voyage.
SUBMISSIONS ON DAMAGES
48. Even if the RESPONDENT breached the Charterparty, the CLAIMANT cannot recover the full
USD30,200,000 it claims in damages because: (I) the CLAIMANT cannot recover the costs of both
the damaged Coffee Beans and the settlement payment; and (II) in any event, the RESPONDENT’s
liability is limited under art 4(5) of the Hague Rules.
86 Hague Rules art 4(2)(l). 87 See above [27]-[28]. 88 Record, 13: Charterparty, cl 34. 89 Procedural Order 2, [7]. 90 Ibid, [12]. 91 Record, 14: Letter from Respondent to Claimant of 22 July 2017.
The University of Queensland Memorandum for Respondent
16
I. THE CLAIMANT CANNOT RECOVER THE COSTS OF BOTH THE DAMAGED
COFFEE BEANS AND THE SETTLEMENT PAYMENT
49. It is unclear whether the CLAIMANT received the purchase price of USD15,750,000 from the
Purchaser but: (A) if the CLAIMANT received the purchase price for the Coffee Beans, it cannot
recover the value of the damaged Coffee Beans as this would amount to double recovery; and (B)
if the CLAIMANT did not receive the purchase price of the Coffee Beans, it cannot recover the cost
of the settlement payment with the Purchaser.
A. If the CLAIMANT received the purchase price for the Coffee Beans, it cannot recover the value
of the damaged Coffee Beans
50. Had the Charterparty been performed, the CLAIMANT would have received USD15,750,000 for the
three damaged containers of Coffee Beans from the Purchaser. If the CLAIMANT received the
purchase price, it cannot claim USD15,750,000 from the RESPONDENT for the value of the damaged
Coffee Beans, as this would mean it would receive the purchase price for the Coffee beans twice
and would be placed in a better position than it would have been had the Charterparty been
performed.92
B. If the CLAIMANT did not receive the purchase price for the Coffee Beans, it cannot recover
the cost of the settlement payment with the Purchaser
51. If the CLAIMANT did not receive the purchase price, it cannot recover the cost of the settlement
payment with the Purchaser, as this costs was incurred unreasonably.93 The CLAIMANT will have
provided the Purchaser with USD9,450,000 worth of coffee beans free of charge and nonetheless
paid an additional USD5,000,000 as a settlement payment. This would only have been reasonable
92 Wenham v Ella (1972) 127 CLR 454, 471; Burns v MAN Automotive (Aust) Pty Ltd (1986) 161 CLR 653, 667. 93 Sotiros Shipping Inc v Sameiet Solholt (The Solholt) [1983] 1 Lloyd’s Rep 605, 608; Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty Ltd (1998) 192 CLR 603, 608-9[6]; TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130, 162.
The University of Queensland Memorandum for Respondent
17
if the loss incurred by the Purchaser was close to USD14,450,000. However, the festival was ‘very
successful’, meaning the CLAIMANT could not possibly have suffered such a large loss.94 In any
event, the settlement payment was paid less than 4 days after the alleged breach occurred,95 in
which time it would have been impossible for the CLAIMANT to assess its potential liability.96 For
these reasons, the CLAIMANT cannot recover the USD5,000,00 on the settlement payment.
II. IN ANY EVENT, THE RESPONDENT’S LIABILITY IS LIMITED UNDER ART 4(5) OF
THE HAGUE RULES
52. The RESPONDENT’s liability for loss is limited pursuant to art 4(5) of the Hague Rules. The
RESPONDENT’s limitation under art 4(5) should be calculated by reference to the three damaged
containers.97
53. Although generally a container will not constitute the relevant ‘package’ for the purpose of art
4(5),98 in this case the circumstances are distinguishable from the authorities because the parties
have contractually agreed to limitation by reference to the number of containers. In the River
Gurara,99 Phillips LJ found that statements in a bill of lading were not binding for the purposes of
art 4(5) because such statements ‘do not constitute an agreement between the parties as to the
identity of the cargo’. In contrast, here, the agreed form of the Charterparty stated the goods as ‘4
containers of Coffee Beans’.100
54. Although the final form of the Charterparty was not signed by the CLAIMANT, it was accepted by
the CLAIMANT’s conduct,101 and the parties proceeded with their contractual obligations on the
94 Record, 29: Letter from Purchaser to Claimant of 1 August 2017. 95 Ibid. 96 See Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty Ltd (1998) 192 CLR 603, 608-9[6] 97 Hague Rules art 4(5). 98 Kyokuyo Co Ltd v A.P. Møller – Maersk A/S (trading as “Maersk Line”) [2017] 2 All ER (Comm) 922, [67]. 99 [1998] 1 Lloyd’s Rep 225, 233 (Phillips LJ). 100 Record, 14: Letter from Respondent to Claimant of 22 July 2017. 101 Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 527; Reveille Independent LLC v Anotech International (UK) Ltd [2016] EWCA Civ 443, [45].
The University of Queensland Memorandum for Respondent
18
assumption that the lower limit of liability applied. This Tribunal should uphold the contractual
allocation of risk between the parties and find that the RESPONDENT’s liability is limited pursuant
to art 4(5) in the amount of USD29,812.41 per container,102 and USD89,437.23 in total.
SUBMISSIONS ON THE MARITIME LIEN CLAIM
I. THE CLAIMANT IS NOT ENTITLED TO A MARITIME LIEN OVER THE VESSEL
55. The CLAIMANT contends it holds a ‘maritime equitable lien’ over the Vessel.103 No such concept
is recognised in the laws of admiralty. The Tribunal should find that: (A) the present facts do not
fall within the recognised categories which give rise to a maritime lien. Further, if the RESPONDENT
is claiming subrogation as an equitable remedy (B) the CLAIMANT is not entitled to be subrogated
to the crew’s lien.
A. The present facts do not fall within the recognised categories which give rise to a maritime
lien
56. The categories in which a maritime lien can be recognised are closed, capable only of extension by
statute.104 While a lien for the unpaid wages of a crew is well established, the present facts do not
fall within any of the recognised categories of maritime lien.105
B. The CLAIMANT is not entitled to be subrogated to the crew’s lien
1. Subrogation, as a remedy, is not available where a third party pays a crew’s wages
57. It is firmly established that a person who purports to pay the crew’s wages is not, by that fact alone,
102 732.238g of fine gold as calculated in The Rosa S [1988] 2 Lloyd’s Rep 574, 577 × 40.7527 (value of gold per gram at date of delivery, 31 July 2017) = 29,812.4112 (3) = USD89,437.23 total. 103 Record, 38: Claimant’s Points of Claim, [13]. 104 Sarah C Derrington and James M Turner QC, The Law and Practice of Admiralty Matters (Oxford University Press, 2nd ed, 2016), 55. 105 The Ripon City [1897] P 226, 242 (Gorrell Barnes J); Derrington and Turner, above n 102, 57.
The University of Queensland Memorandum for Respondent
19
entitled to be subrogated to the crew’s lien.106 In the Petone, Hill J concluded that the weight of
authority was strongly against the doctrine ‘that the man who has paid off the privileged claimant
stands in the shoes of the privileged claimant and has his lien, whether it be regarded as a general
doctrine or applied to wages only’.107 While the Admiralty Court originally countenanced
subrogation in circumstances where a third party had paid a crew’s wages without prior court
sanction, this practice was abolished by Dr Lushington in the Janet Wilson, primarily because it
unfairly prejudiced other bona fide third party creditors.108 Justice Hill affirmed this in the
Petone.109 The Tribunal would be disregarding an unquestioned line of authority if it were to allow
the CLAIMANT to be subrogated to the crew’s position.
2. In the alternative, the CLAIMANT is not entitled to a remedy of subrogation on the present
facts
58. In any event, the circumstances of the case are such that the doctrine of subrogation is not engaged.
The CLAIMANT has not paid the crew’s wages.110 Thus, it has not actually discharged the
RESPONDENT’s obligation and it is still open for the Vessel’s crew to exercise a lien over the Vessel.
Indeed, the crew of the Vessel ‘have foreshadowed separate legal action against the company to
recover unpaid wages for a number of voyages’.111
59. Further, the CLAIMANT cannot prove that the payment was not made voluntarily. The CLAIMANT
was under no legal compulsion to advance the crew’s wages. The correspondence relating to the
106 The Petone [1917] P 198, 208–9 (Hill J); The Ship ‘Hako Endeavour’ v Programmed Total Marine Services Pty Ltd (2013) 211 FCR 369, 398 [102] (Rares J); Hartono v Ministry for Primary Industries [2018] NZSC 17 (2 March 2018) [28]; D R Thomas, Maritime Liens (Stevens & Sons, 1980) 267. 107 See the William F Safford (1860) Lush 69, 167 ER 37; The Wasp (1867) LR 1 A & E 367; The St Lawrence (188) 5 PD 250; The Tagus [1903] P 44. 108 The Janet Wilson (1857) Swab 261. 109 The Petone [1917] P 198, 200. 110 Record, 38: Claimant’s Statement of Claim [12]; Record, 41: Respondent’s Points of Defence and Counterclaim [10]. 111 Procedural Order 2, [20].
The University of Queensland Memorandum for Respondent
20
payment of the USD100,000 appears in an internal memo of the CLAIMANT.112 Although the
CLAIMANT expresses an intention to be repaid the sum advanced, it is not clear whether this was
communicated to the RESPONDENT.113 Parties who voluntarily discharge payments owed to the
crew cannot be subrogated to the crew’s lien for wages.114
60. In the premises, the Tribunal should find that the CLAIMANT is not entitled to a maritime lien over
the Vessel either by direct entitlement or by subrogation.
SUBMISSIONS ON THE COUNTERCLAIM
I. The CLAIMANT is liable to pay the RESPONDENT USD 1,610,000 owing under the Charterparty
61. This amount consists of: (A) freight; (B) demurrage; (C) repairs to the hull; (D) agency fees and
use of the electronic access systems at Dillamond; and (E) agency fees at Spectre.
A. The CLAIMANT is liable for freight in the amount of USD500,000
62. The RESPONDENT delivered the Coffee Beans to the CLAIMANT, undamaged and in a merchantable
condition, at 12.02am on 30 July.115 Freight was earned in full upon delivery.116 Thus, the
CLAIMANT is liable to the RESPONDENT for USD500,000 in respect of freight.117
63. In any event, under cl 22, freight was to be ‘calculated on Bill of Lading weight on completion of
load’.118 The amount of freight payable was therefore fixed as the amount ascertained at loading,119
being USD500,000. Upon delivery, this amount became payable by the CLAIMANT under the
Charterparty.
112 Record, 1: Claimant’s Internal Memo of 19 July 2017. 113 Ibid. 114 The Petone [1917]; Falcke v Scottish Imperial Insurance Co (1886) 34 Ch D 234 (CA), Bowen LJ at 248 (referred to in Re Dalma No 1 Pty Ltd (in liq) (2013) 279 FLR 80. 115 Paragraph [31]-[36]. 116 Record, 11: Charterparty, cl 22. 117 Record, 3: Charterparty, Box 11. 118 Record, 11: Charterparty, cl 22. 119 Shell International Petroleum Co v Seabridge Shipping (The Metula) [1978] 2 Lloyd’s Rep 5, 7 (Lord Denning MR), 8 (Roskill LJ).
The University of Queensland Memorandum for Respondent
21
B. The CLAIMANT is liable to the RESPONDENT for demurrage in the amount of USD100,000
64. Clause 8(c)(ii) provides for fixed laytime of half a weather working day in respect of discharge.120
The Tribunal should find that 29 July was a weather working day because the Vessel was, in fact,
unloaded.121
65. Laytime commences when the vessel ‘arrives at the discharge port’.122 A vessel is considered to
have arrived at the port of discharge when, in circumstances where it cannot proceed directly to a
berth, it is at a place where ships usually lie when waiting for a berth at that port.123 The Vessel
arrived at Dillamond at 7.00am on 29 July because, at this time, the Port Authority ordered that it
wait in position to berth with other vessels, and it was within the pilotage limits of the Port.124 In
the premises, laytime expired at 7.00pm on that day.
66. The discharging operation concluded at approximately 12.00am on 30 July, exceeding laytime by
approximately five hours.125 Consequently the CLAIMANT is liable to the RESPONDENT for
demurrage in the amount of USD100,000.
C. The CLAIMANT is liable for repairs to the Vessel’s hull in the amount of USD875,000
67. Clause 19 of the Charterparty incorporates the York Antwerp Rules. Article A of the Rules
provides that parties must contribute to payment of general average where: the parties are in a
‘common maritime adventure’, a party makes an ‘extraordinary sacrifice or expenditure’ for the
purpose of preserving property, and the sacrifice is ‘intentionally and reasonably made’.126 It is
120 Record, 6: Charterparty, cl 8(c)(ii). 121 Record, 24: Email from Respondent to Claimant 29 July 2017 at 8.42pm; Compania Naviera Azuero SA v British Oil & Cake Mills Ltd [1957] 1 Lloyd’s Rep 312, 329 (Pearson J); Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries & Food [1963] 1 Lloyd’s Rep 12, 41 (Lord Devlin). 122 Record, 6: Charterparty cl 8(c)(ii). 123 E L Oldendorff & Co GmbH v Tradax Export SA (The Johanna Oldendorff) [1973] 2 Lloyd’s Rep 285, 291 (Lord Reid), 302 (Viscount Dilhorne), 307 (Lord Diplock). 124 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8.58am. 125 Record, 22: Email from Respondent to Claimant of 28 July at 4.58pm; Record, 23: Access Authority Pass. 126 York-Antwerp Rules 2016, Rule A.
The University of Queensland Memorandum for Respondent
22
uncontentious that the parties are in a common maritime adventure.127
1. The RESPONDENT dropped anchor as ‘a sacrifice to preserve imperilled property’
68. A general average act must be done in response to a real peril faced by the common adventure.128
The Storm on 28 July was a peril to both the ship and the Coffee Beans. The Storm brought hail
and severe winds,129 each of which posed a distinct risk to the Vessel. Further, the Coffee Beans
were particularly sensitive to moisture.130 In summary, the Storm posed a substantial and real
peril.131 The RESPONDENT anchored the Vessel as they thought they would avoid the Storm’.132
This was a precautionary measure to avert the imminent threat the Storm posed.133
69. The RESPONDENT’s act of dropping anchor an ‘extraordinary sacrifice’. This type of loss is
encompassed by art II: ‘loss of or damage to the property involved in the common maritime
adventure by or in consequence of a sacrifice made for the common safety... shall be allowed as
general average.’
2. The RESPONDENT’s act was reasonable
70. The Rule Paramount of the York-Antwerp Rules provides that ‘in no case shall there be any
allowance for sacrifice or expenditure unless reasonably made or incurred’. The Master has
freedom to choose which action will best benefit the common adventure.134 Under Rule D, the
general average contribution is not affected even where one party was at fault.
71. Although the decision to drop anchor did not cause the crew to avoid the peril, it was still
127 Trade Green Shipping Inc v. Securitas Bremer Allgemeine Verischerungs AG (The Trade Green) [2000] 2 Lloyd’s Rep 451, [4]. 128 Nesbitt v Lushington (1792) 4 TR 783. 129 Record, 21: ‘“Once in a Lifetime” Storm Closes Airport, Port, Rivers’ Article in the Dillamond Times of 29 July 2017. 130 Record, 2: Letter from Respondent to Claimant of 22 July 2017. 131 Société Nouvelle d’Armement v Spillers & Bakers Ltd [1917] 1 KB 865, 871. 132 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8:58am. 133 Vlassopoulos v British and Foreign Marine Insurance Co (The Makis) [1929] 1 KB 187, 199. 134 Athel Line Ltd v Liverpool & London War Risks Ins Assn Ltd [1994] KB 87, 94.
The University of Queensland Memorandum for Respondent
23
reasonable. Reasonableness must be assessed in the context of a ‘time of danger’, and the Tribunal
should afford the RESPONDENT a margin of appreciation.135 The RESPONDENT’s decision was made
under extreme pressure, and ‘there wasn’t really any [other] option for the crew’.136
72. This decision caused the damage to the hull.137 The CLAIMANT is therefore liable for general
average for the loss incurred from the RESPONDENT dropping anchor to avoid the Storm.
D. The CLAIMANT is liable for agency fees and the cost of electronic access systems at Dillamond
in the amount of USD60,000
73. The CLAIMANT was under a duty to provide and make use of sufficient means for the discharge of
the Coffee Beans once the Vessel arrived at Dillamond.138 However, the CLAIMANT failed to
provide any means whereby the Coffee Beans could be consigned to their agents.
74. The CLAIMANT’s failure caused the RESPONDENT to incur additional costs in discharging the Coffee
Beans at Dillamond in the amount of USD50,000, and the cost of the use of the electronic access
system, which amounted to USD10,000.139 The RESPONDENT would not have incurred these costs
but for the CLAIMANT’s failure to provide and make use of sufficient means for the discharge of
the Coffee Beans.
75. In the premises, the CLAIMANT is liable to the RESPONDENT the agency fees at Dillamond, and the
use of the electronic access system at Dillamond, amounting to USD60,000.
E. The CLAIMANT is liable for agency fees at Spectre in the amount of USD75,000
76. The parties have incorporated the York-Antwerp Rules.140 The CLAIMANT is liable for general
average of the loss incurred by the RESPONDENT seeking refuge at Spectre on 26 July. As above,
135Australian Coastal Shipping Commission v Green [1971] 1 QB 456, 483. 136 Record, 20: Email from Respondent to Claimant of 29 July 2017 at 8.58am. 137 Goulandris Brothers v B Goldman & Sons [1957] 2 Lloyd’s Rep 207, 213. 138 Postlethwaite v Freeland (1880) 5 App Cas 599, 608 (Lord Selbourne LC); Sir Bernard Eder et al, Scrutton on Charterparties and Bills of Ladings (Sweet & Maxwell, 23rd ed, 2015), 259. 139 Record, 32: Email from Respondent to Claimant of 7 August 2017 at 3.40pm. 140 See above, [68].
The University of Queensland Memorandum for Respondent
24
the RESPONDENT and CLAIMANT were in a common maritime adventure, given that the
RESPONDENT transported the CLAIMANT’s Coffee Beans in return for freight.141
1. The RESPONDENT deviation to Spectre was ‘a sacrifice to preserve imperilled property’
77. The solar flare event on 25 July 2017 was a peril to the ship. The solar flare event meant that the
Vessel had no system of navigation and was required to deviate to ‘save life and property’.142 The
failure of the Vessel’s navigation systems meant that the Vessel could not continue on its voyage,
threatening the ‘common adventure’. Prima facie, an inability to navigate poses a substantial, and
not negligible peril.143 The harm posed was immediate,144 and the Master was required to act
quickly to minimise any harm caused to the ship or the voyage more generally.
78. The RESPONDENT’s deviation to Spectre and the incurring of agency fees, was an ‘extraordinary
sacrifice’ in accordance with Rule X(a)(i): ‘when a ship shall have entered a port or place of
refuge...in consequence of accident, sacrifice or other extraordinary circumstances which render
that necessary for the common safety, the expenses of entering such port or place shall be allowed
as general average’.
2. The RESPONDENT’s act was reasonable
79. The RESPONDENT’s decision to berth at Spectre was reasonable, as its deviation to Spectre was
reasonable. Under Rule D of the York-Antwerp Rules, the amount of general average contribution
is not affected even where the sacrifice is due to the fault of one of the parties. The CLAIMANT has
the burden of proving any interruptions to the causal chain.145
141 Trade Green Shipping Inc v. Securitas Bremer Allgemeine Verischerungs AG (The Trade Green) [2000] 2 Lloyd’s Rep 451, 453. 142 See above,[27]-[28]; Record, 8: Charterparty, cl 17 143 Société Nouvelle d’Armement v Spillers & Bakers Ltd [1917] 1 KB 865. 144 Cf Société Nouvelle d’Armement v Spillers & Bakers Ltd [1917] 1 KB 865 145 Goulandris Brothers v B Goldman & Sons [1957] 2 Lloyd’s Rep 207.
The University of Queensland Memorandum for Respondent
25
PRAYER FOR RELIEF
For the reasons set out above the RESPONDENT seeks the following orders and declarations:
a. An order that the CLAIMANT is liable to pay the RESPONDENT USD1,610,000 owing under
the Charterparty comprising:
i. Freight in the amount of USD500,000;
ii. Agency fees at Spectre in the amount of USD75,000;
iii. Damage to the Vessel’s hull in the amount of USD875,000;
iv. Agency fees at Dillamond in the amount of USD50,000;
v. Demurrage in the amount of USD100,000;
vi. Use of the Access Authority Pass at Dillamond in the amount of USD10,000;
b. A declaration that the CLAIMANT does not hold an equitable maritime lien over the Vessel;
c. An award for interest under s 49 of the Arbitration Act 1996 (UK); and
d. An order for costs.