The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr....

29
The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007

Transcript of The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr....

Page 1: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

The Towers at the City College of New York

Robin Scaramastro - Structural Option - Advisor: Dr. Memari

Senior Thesis Final Presentation – Spring 2007

Page 2: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Presentation Overview

IntroductionExisting Structural SystemProblem StatementProposed SolutionStructural Depth - Gravity System - Lateral System - FoundationsMechanical Breadth - LEED PointsConstruction Breadth - Cost Impact - Schedule ImpactConclusion

Page 3: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Introduction

Building Information:- 181,000 SF dormitory for CCNY students and faculty- 6, 8, and 10 stories- Located at 130th St. and St. Nicholas Terrace, New York- Project Cost : $59 million

Codes Used in Design:- The Building Code of the City of New York - ASCE7-05 - UBC 97

Page 4: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Existing Structural System

Structural Framing – Cast in place concrete

Page 5: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Existing Structural System

Structural Framing

8” Flat-Plate Concrete Slab

Gr 60 Reinforcement

f’c = 5,000 psi

Page 6: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Existing Structural System

Structural Framing

Rectangular reinforced concrete columns

12” – 14” diameter round concrete columns

f’c = 5000 psi

f’c = 5000 psi

Page 7: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Existing Structural System

Structural Framing

12” thick reinforced concrete shear walls

Poured monolithically (3 floors)

2 curtains of Gr 60 reinforcement

f’c = 4000 psi

Page 8: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Existing Structural System

Foundations

- Bearing pressure of

40,000 psf

- Typical spread footings

for columns and grade

beams

- Mat slabs used for shear

walls

Page 9: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Problem Statement

Large concrete columns in floor to ceiling corner windows

Page 10: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Problem Statement

Irregular grid

Significant impact on floorplan

Page 11: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Proposal

-Apply a steel structure - cantilever building corners to eliminate columns in windows - create a regular grid system

- reduce the number of columns

- create less impact on floor plan

Page 12: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Building redesigned in steel

Page 13: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Gravity System

Page 14: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Gravity System- 2” Composite metal deck with 2 ½” concrete slab- W10 and W12 composite infill beams with shear studs- W14 – W21 girders-W10 gravity columns

- Fireproofing provided by gypsum board

Page 15: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Typical Foundation- Spread footings like used in existing structure- less concrete needed for gravity column foundations

Page 16: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Lateral System

Page 17: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Lateral System- Braced frames implemented in stair cores

Page 18: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Lateral System- Braced frames implemented in stair cores- Moment frames with steel angle kickers used elsewhere- Placed to reduce eccentricity and torsional moment- Lateral columns W12 for added stiffness- Bracing provided by 2L6x6

Page 19: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Typical Connections

ShearConnection- Single Angle

Page 20: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Typical Connections

MomentConnection- Fully Restrained

Page 21: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Typical Connections

BracingConnection

Page 22: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Structural Depth

Impact on Foundations - Reduction of dead load from self weight - Up to 46% less concrete needed for some spread footings

Page 23: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Mechanical Breadth

- LEED Certification - 26 possible points can be earned

- sustainable site- water efficiency- material selection- indoor air quality

Investigated the existing building envelope - R-Value = 23.5 - Q = 2.42 BTU/hr (1sf wall area)

Page 24: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Mechanical Breadth

- Proposed building envelope - R-Value = 27.4 - Q = 2.09 BTU/hr (1sf wall area)

- Heat loss during winter months 14% less than the existing building envelope

Page 25: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Construction Breadth

Concrete Construction Cost and Schedule

- Duration = 140 days (28 weeks)

- Cost = $5.4 million

Source:ICE 2000RS Means

Page 26: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Construction Breadth

Steel Construction Cost and Schedule

- Duration = 95 days (19 weeks)

- Cost = $6.0 million

Source:ICE 2000RS MeansPrimavera

Page 27: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Conclusion

- Recommend steel for the structure - corner columns are eliminated in floor-to-ceiling windows - positive impact on floor plan - slightly higher construction cost - 9 weeks are saved in construction duration - steel construction is common in NYC - less concrete needed for foundations - potential for LEED certification

Page 28: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

THANKS!!!

Acknowledgements

Bruce McKee (Capstone

Development)Marc Bowen & Mike

Ergler (Greenman-Pedersen)Delia Nevola

(Goshow Architects)

Jackie Horowitz (Turner

Construction)

All AE Faculty

All My Friends and Family

Robert Chin(CCNY

Photographer)

Page 29: The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.

Conclusion

QUESTIONS??

Photos courtesy Robert Chin