1 (33) STRATEGY DOCUMENT
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TDOK number Document date Version
TDOK 2016:0199 03/06/2019 3.0
Adopted by Valid from Replaces
Manager CF Purchasing and Logistics 01/09/2019 [Replaces]
Created by
Andersson Claes, ILsy
Confidentiality level
Limited
The Swedish Transport Administration's business strategy for contracts and technical consultants
Introduction Since the Swedish Transport Administration was formed, the administration’s strategy as an employer has successively evolved and clarified. The overall approach was established in 2010 in the documents the Swedish Transport Administration's procurement policy (TDOK 2010:119) and the Swedish Transport Administration's procurer strategy (TDOK 2011:196). These documents have since been communicated and improved. Within this framework, control has been developed both within the respective VO/CF and business wide within e.g. the productivity group and in the Swedish Transport Administration's management team and in the Employer Council. The focus has previously been partly documented in the Swedish Transport Administration's main and support processes1 but many parts were previously only in the form of single decisions or approaches in presentations. At the same time, development projects are underway in several areas that are the basis for joint strategies for contracts and technical consultants.
This business strategy coordinates, documents, clarifies and develops, in some parts, the strategies for the procurement of contracts and technical consultants currently applied in the Swedish Transport Administration. The business strategy with appendices handles procurement where the Public Procurement Act (LOU) and the Procurement in the Supply Sector Act (LUF) apply within the category family contracts and the category family technical consultants in planning and design2. This business strategy is superordinate to category strategies.
1 Plan and implement measures on road and rail; Implement purchasing and procurement 2 Technical consultants refers only to those in planning and design throughout the document.
The Swedish Transport Administration's business strategy for contracts and technical consultants
Procedures
The Swedish Transport Administration’s procurement policy
The Transport Administration’s procurer strategy
Categories
Subcategories
Guidelines Requirements
Guidance Advice
u The policy expresses the Transport Administration’s principles and approach in all procurement and applies to all units of the Transport Administration.
u The strategy states overall goals and what attitudes we should have when we order.
u The strategy sets out the framework and strategies for the choice of business form for contracts and technical consultants.
u Category strategies specify detailed and defined strategies for framework agreements and object-specific agreements in the respective category area under subcontracting, consultancy material/indirect services (e.g. road surfacing, construction works, BEST etc.).
u Documents with governing requirements for compliance with established strategies e.g. choice of business form, development-promoting measures, collaboration, procurement guidelines according to LOU and LUF etc.
u Documents with non-governing advice, help and support for compliance with established strategies
2 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Joint
Purpose
The main aim is to facilitate and ensure a conscious choice of business form3 in accordance with the Swedish Transport Administration's agreed goals and approaches that build on organisational learning based on best practice in the Swedish Transport Administration and externally.
The implementation of the strategy also aims to achieve the following effects:
Total cost effectiveness in each purchase of contract and technical consultant because
the strategy that is deemed to provide the best outcomes for market development
towards increased productivity, competition and innovation is implemented
consistently throughout the Swedish Transport Administration.
Financial savings at suppliers because the Swedish Transport Administration behaves uniformly and consistently.
Time savings for every employee and manager involved in the process of producing
the choice of business form for projects by clarifying, concretising and gathering
together the Swedish Transport Administration's goals and approaches.
Enables and visualises conscious deviations from best practice so as to limit risk-
taking and conscious learning of new approaches.
Application
Before an internal order and any decision to draw up an action description, the administrator shall decide on the preliminary type of contract/type of assignment. The employer must apply this strategy together with the administrator and Purchasing and Logistics.4 If necessary, Legal Matters and Plan Review shall be consulted. Preliminary type of contract/assignment and choice of Basic or High Collaboration shall be documented in the project’s action description. The strategy shall cover both contract and technical consultant.
This strategy shall be applied on a continuous basis in the selection of business form for contracts and technical consultants in the planning of projects and implementation of projects as well as before advertising decisions. "Procedure for choice of business form" is used as a support. The business form and justification for this shall be documented in the "Justification appendix, choice of business form".
Application is set out in Appendix 1 Flowchart Choice of type of contract/assignment Collaboration High and Choice of business form.
The applicable governing documents are set out in Appendix 2 Overview of governing documents and document types that shall be applied in the choice of strategy.
Established category strategies shall be applied. Deviations shall be decided according to the relevant work instructions.
3 The term of choice of business form is defined in the guideline choice of business form. 4 The employer can be Market and Planning, Maintenance, system departments etc. The administrator can for example be Major Projects, Investments or Maintenance.
3 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Overall goals and strategic approach The Swedish Transport Administration shall, in the employer role, specifically work for market development that leads to the achievement of the goals: increased productivity, degree of innovation and competition in the construction industry. The goals shall be pursued on the basis of the conditions in the individual case.
The market will increasingly be given the opportunity to take greater responsibility for ensuring that the final product meets the requirements of the Swedish Transport Administration for function and quality.
The Swedish Transport Administration will increase the proportion of development-promoting procurements in order to contribute to the market having better conditions for achieving the Swedish Transport Administration’s goals.
For contracts, the most appropriate contract form shall be chosen based on the degree of
freedom, complexity, uncertainties and innovation needs or other benefits5. The proportion of design and construct contracts remains high and represents a significant part of both road and rail contracts.
For consultancy assignments, the most appropriate form of assignment shall be chosen based on complexity, uncertainties and innovation needs or other benefits. For consultancy assignments that are carried out with Collaboration Basic, the remuneration form fixed fee shall constitute a significant part of the remuneration.
Within the framework for its assignment, the Swedish Transport Administration shall set requirements that contribute to increased employment in society and ensure long-term skills provision in the industry.
The Swedish Transport Administration shall set social requirements in all procurement. The requirements shall create fair competition by ensuring that laws are respected and that no people are exploited or mistreated.
In procurement, the Swedish Transport Administration shall set requirements aimed at reducing the climate impact of infrastructure management.
When deciding on the individual contract, procurement legislation and long-term effects on the current and future business of the Swedish Transport Administration shall always be considered.
Sub-strategies and goals
Packaging and communication with the market Contracts and consultancy assignments respectively that are commercially suitable to implement together shall be packaged in the same procurement. Packaging should aim to promote innovation, industrial production and the life cycle costs of the objects. Combines procurement shall be considered in order to facilitate the submission of tenders by small and medium-sized suppliers.
For consultancy contracts relating to investments, the extent shall be as follows: road/rail plan + tender documents for the contract + site follow-up in the same assignment.
5 Degrees of freedom, complexity, uncertainty and innovation needs or other benefits are defined in Choice of business form, TDOK 2018:0007
4 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Where this can be justified and is appropriate with regard to calculations, e.g. due to an assignment time of more than 3 years or plan type with alternative locations, procurement may be carried out as follows: road/railway plan or localisation study is purchased in a separate assignment. Tender documents for contract and site follow-up are then procured in separate assignments.
Design, construct and maintain contracts, i.e. design and construct contracts with a long maintenance commitment (+ 10 years) shall be considered where the conditions for responsibility are clear (e.g. new road in a completely new route) during the contract period and the performance requirements are relevant and measurable.
Framework contracts for small construction works, BEST contracts and planning and/or design assignments are used up to the amount decided.
For the purchase schedule, procurements are introduced immediately after the purchase resource is allocated. Thereafter, 80% of the number of procurements calculated on a 12 month period shall be advertised within 3 months of being marked green.
In early dialogue with the market, the Transport Administration shall be involved with competence that ensures that a mutual discussion of the contract/assignment can be carried out.
Procurement and award criteria In the case of contracts/assignments above the threshold in LOU, the procurement procedure shall be open or negotiated, unless specific reasons for selective procurement or competitive dialogue exist. For procurement above the threshold according to LUF, the procurement procedure shall be negotiated.
Negotiations to adapt tenders shall be used more widely. In tenders where negotiation has been found to be possible and appropriate, the conditions for negotiation shall be formulated in the tender documents.
Qualification requirements shall be at company level.
Competency requirements for personnel shall be set as contractual requirements and not as qualification requirements in the procurement.
Qualification requirements relating to technical and professional capacity shall be easy to understand, unambiguous, proportionate and easy to assess. Requirements shall not be directed towards a particular supplier.
Most financially advantageous tender by price For award criteria, the most economically advantageous tender by price will generally be applied unless added value can be justified and can be monitored during the contract period.
For contracts TRV E1A and TRV E2 as well as contracts for BASIC Contract and contracts involving significant maintenance TRV UH1A and TRV UH2, only price shall be applied.
For consultancy assignments for TRV TK1 and TK2, only price shall be applied.
5 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
The most financially advantageous tender by the best relationship between price and quality (added value) Standard contracts TRV E1B and TRV UH1B can, if so justified, be procured with added value. The recommended level is up to 30%; if justified, the level can be increased to a maximum of 50%.
Complex and uncertain construction projects can, if justified, be procured with added value under the contract model Collaboration High.
Standard assignments TRV TK1B and TRV TK2B can, if so justified, be procured with added value. The recommended level is up to 30%; if justified, the level can be increased to a maximum of 50%.
Complex and uncertain assignments for technical consultants can, if justified, be procured with added value under the contract model Collaboration High.
Most financially advantageous tender by cost The award criterion of economically most advantageous tender by cost may only be chosen if the requirements set are possible to follow up in a life cycle perspective. When assessing the cost-effectiveness of tenders, the life cycle costs shall be included in the valuation.
Tendering periods For design and construct contracts over SEK 100 million for TRV E1A, TRV E1B and TRV E3, the tendering period shall be a minimum of 6 months. For TRV E4, TRV E5 and TRV E6, tendering period shall be according to "Contract model Collaboration High".
The tender calculation period for TRV E2 over SEK 100 million shall be minimum 2 months.
For contracts relating to BASIC Contract, the tendering period shall be a minimum of 3 months.
For consultancy assignments for TK1A, TK1B, TK2A and TK2B over SEK 20 million, the tendering period shall be a minimum of 4 months. For consultancy assignments TK 3, TK4 and TK 5, the tendering period shall be according to the contract model Collaboration High.
For the purpose of calculating the tendering period, account shall be taken of public holidays and holiday periods.
Collaboration and remuneration forms The Swedish Transport Administration’s Collaboration Basic shall be applied if Collaboration High has not been decided on at the latest when determining the action description. Collaboration High shall be considered in complex and uncertain projects. Decisions to cancel or proceed with Collaboration High shall be made at the latest before procurement of consultants for tender documents for the contract begins. Forms of remuneration shall be in accordance with Appendices 3, 4 and 5.
If bonus and/or added value for quality parameters are applied outside the contract model Collaboration High, they shall be formulated with project-adapted choices according to Routine Qualification, evaluation and remuneration form, bonus and penalties.
For procurement, maximum penalties shall always be calculated and the effect assessed at the supplier's risk level.
6 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
BIM The Swedish Transport Administration's lowest level BIM shall always be applied by VO Investments and VO Major Projects. BIM extended level shall be applied according to the established guideline.
Upplev Supplier follow-up shall take place 2 times per year in each contract and assignment that is longer than one year and once after the end of the contract with Upplev according to established levels for the contract’s size.
For BASIC Contract and other contracts with significant maintenance and that last more than one year, supplier follow-up shall be carried out at least once a year per contract and once after the end of the contract, with UPPLEV according to established levels for the contract’s size.
Business forms for types of contract commonly used in the Swedish Transport Administration
The following seven types of contract shall be used as a starting point for choice of business form with investment, regardless of VO.
If contracts are classified as standard, TRV E1A, TRV E1B or TRV E2 is chosen. If uncertainty regarding the complexity of the contract exists, the TMALL 0767 complexity assessment shall be used.
Collaboration Basic TRV E1A. Standard contracts with sufficient degrees of freedom and low uncertainty
TRV E1B. Standard contracts with sufficient degrees of freedom and an identified need for innovation or other benefit
TRV E2. Standard contracts with small degrees of freedom and low uncertainty
TRV E3. Complex contracts with a long maintenance commitment (= design, construct and maintain contract)
Collaboration High
TRV E4. Complex contracts with great degree of freedom and high uncertainty
TRV E5. Complex contracts with small degrees of freedom and high uncertainty
TRV E6. Complex contracts with very high uncertainty
The following five types of contract shall be used as a starting point for the choice of business form for contracts with BASIC Contract and other contracts with a significant and frequency-based maintenance component, regardless of VO.
If contracts are classified as standard, TRV UH1A, TRV UH1B or TRV UH2 is chosen. If uncertainty regarding the complexity of the contract exists, the TMALL 0767 complexity assessment shall be used.
7 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Collaboration Basic
TRV UH1A. Standard contracts with sufficient degrees of freedom and low uncertainty
TRV UH1B. Standard contracts with sufficient degrees of freedom and an identified need for innovation or other benefit
TRV UH2. Standard contracts with small degrees of freedom and low uncertainty
TRV UH3. Complex contracts with high uncertainty (BASIC Contract for district/contract area > 10 years together with a design and build contract with a performance commitment according to TRV E3)
Collaboration High
TRV UH4. Very complex contracts with high uncertainty – contract model under development
The forms of business for each type of contract are shown in Appendix 3 and Appendix 4.
Business forms for types of technical consultant assignments commonly used in the Swedish Transport Administration
Technical consultants perform strategic choice of measures studies, localisation studies investigations, planning assignments and design assignments including building site follow-up.
Choice of type of assignment for technical consultants shall be made irrespective of the choice of type of contract.
If uncertainty regarding the complexity of the assignment exists, the TMALL 0767 complexity assessment shall be used.
The following seven types of assignment shall be used as a starting point for choice of business form for technical consultants, regardless of VO.
Collaboration Basic TRV TK1A. Standard assignments with low uncertainty TRV TK1B. Standard assignments with low uncertainty and an identified need for innovation or other benefit
TRV TK2A. Standard assignments with high uncertainty TRV TK2B. Standard assignments with high uncertainty and an identified need for innovation or other benefit
Collaboration High TRV TK3. Complex assignments with high uncertainty
TRV TK4. Complex assignments with very high uncertainty
TRV TK5 Complex assignments with very high uncertainty regarding scope, project contests
Business forms are shown in Appendix 5 Business forms for the respective assignment types for technical consultants.
8 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Version log
Adopted
version
Document date Amendment Name
Version 1.0
TDOK
2016:0199
26/04/2016 First version.
GD decision TRV 2016/36508. GD confirms and delegates determination to cIL
Lars Malthe
Version 2.0 01/01/2018 VO Maintenance has been
included, new LOU 2016:1145
incorporated, experiences from
"Best Practice" included.
GD decision TRV 2017/107342. GD confirms and delegates determination to cIL
Claes
Andersson
Version 3.0 01/09/2019 Standard contracts/assignments
with the possibility of added
value for innovations have been
included as well as Collaboration
High consultant. Experiences
from best practice included.
GD decision TRV 2019/1417. GD confirms and delegates determination to cIL
Claes
Andersson
9 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Choice of preliminary type of contract/type of assignment TDOK 2016:0199 TDOK 2018:0007
Choice of business form contract TDOK 2018:0007, justification appendix improved and supplemented afterwards
Choice of business form consultant TDOK 2018:0007, justification appendix improved and supplemented afterwards
Application of business strategy, complexity assessment and choice of business form where necessary
Create action description Begin planning Begin implementation Collaboration High is decided no later than before tender documents for consultant
construction documents begin
Decision on advertisement
PS 1 PS 2
Action Description
(ÅB)
Simplified complexity assessment according to choice of business form is carried out before the
action description is established
Before action description (ÅB) Before planning
Before implementation Before advertisement
Before advertisement Appendix 1
Choice of business strategy, Collaboration high business form
Investment/Major Projects/Maintenance
– Decides to begin planning
Decision on project specification (PS) Justification appendix’s initial stage begins
Any revision of the choice of type of
contract/type of assignment is
documented in PS/justification appendix
Purchasing – Participates in dialogue
Investment/Major Projects/Maintenance – Decisions on preliminary type of contract/ type of assignment and any Collaboration High Purchasing – Participates in dialogue with administrator and Planning/Maintenance Planning/Maintenance Calls to meeting and documents preliminary type of contract/type of assignment in action description
Flow chart and Choice of
Investment/Major Projects/Maintenance – Decides to begin implementation Decision on possible revision of project specification (PS) The justification appendix is supplemented afterwards Any revision of the choice of type of contract/type of assignment is documented in PS/justification appendix Purchasing – Participates in dialogue
Investment/Major Projects/Maintenance – Decides on justification appendix Justification appendix is completed here at the latest Any revision of the type of contract/type of assignment is documented in PS/justification appendix Purchasing – Countersigns justification appendix and decides on advertising
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
10 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Appendix 2 Overview of governing documents and document types that are applied in the choice of strategy.
Document title Document ID Document type Contents Time horizon Target group
The Swedish Transport
Administration's
procurement policy
TDOK 2010:119 Policy document Approach 10 years All
The Transport
Administration’s
procurer strategy
TDOK 2011:196 Strategy document Focus 10 years All
The Swedish Transport
Administration's business
strategy for technical
consultants and contracts,
TDOK 2016:0199 Strategy document strategy and goals 5 years Managers,
purchasers,
project managers
Category strategies technical
consultants
Strategy document strategy, goals
and action plans
1-3 years Managers,
purchasers,
project managers
Category strategies contracts Strategy document strategy, goals
and action plans
1-3 years Managers,
purchasers,
project managers
Guidelines
(Supplier market plan
TDOK 2014:0086, Lowest
level BIM, Collaboration
Basic, Collaboration High,
Development-promoting
measures etc.)
Governing document Purchasers,
project
managers
Procedures (TDOK 2018:0007, TDOK 2018:0070, TDOK 2019:0177)
Governing document Purchasers,
project
managers
Guidance/Checklists Guidance document Purchasers,
administrat
ors
Construction market plan Comprehensive plan
for action to develop
critical markets
3 years Managers
The Swedish Transport
Administration's focus on
Research and innovation
Focus document
external web
Focus 1-3 years Managers
Research and
innovation personnel
internal and external
11 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Appendix 3 - Business forms for types of contract commonly used in the Swedish Transport Administration
The following seven types of contract shall be used as a starting point for choice of business form with investment, regardless of VO.
If contracts are classified as standard, TRV E1A, TRV E1B or TRV E2 is chosen. If uncertainty regarding the complexity of the contract exists,
the TMALL 0767 complexity assessment shall be used.
Collaboration Basic
TRV E1A. Standard contracts with sufficient degrees of freedom and low uncertainty
TRV E1B Standard contracts with sufficient degrees of freedom, low uncertainty and an identified need for innovation or other benefit
TRV E2. Standard contracts with small degrees of freedom and low uncertainty
TRV E3. Complex contracts with a long (> 10 year) maintenance commitment (= design, construct and maintain contract)
Collaboration High
TRV E4. Complex contracts with great degree of freedom and high uncertainty
TRV E5. Complex contracts with small degrees of freedom and high uncertainty
TRV E6. Complex contracts with very high uncertainty
12 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E1A Standard contracts with sufficient degrees of freedom and low uncertainty
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided
by the contractor (ABT).
Collaboration on design beyond ABT. Design and
construct contract. Design provided by contractor (ABT).
Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB).
Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment Cost plus principle (current account) with remuneration
form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee.
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
13 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E1B Standard contracts with sufficient degrees of freedom, low uncertainty and an identified need for innovation or other benefit
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided
by the contractor (ABT)
Collaboration on design beyond ABT. Design and
construct contract. Design provided by contractor (ABT).
Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB). Contractor
is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with remuneration
form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
14 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E2 Standard contracts with small degrees of freedom and low uncertainty
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided by the
contractor (ABT)
Collaboration on design beyond ABT. Design and
construct contract. Design provided by contractor (ABT).
Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB)
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB). Contractor
is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with remuneration
form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee.
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
15 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E3 Complex contracts with a long (> 10 year) maintenance commitment (= design, construct and maintain contract)
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided by the
contractor (ABT).
Collaboration on design beyond ABT. Design and
construct contract. Design provided by contractor (ABT).
Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB). Contractor
is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with remuneration
form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
16 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E4 Complex contracts with great degree of freedom and high uncertainty
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided by
the contractor (ABT)
Collaboration on design beyond ABT. Design and
construct contract. Design provided by contractor
(ABT). Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB).
Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
17 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E5 Complex contracts with small degrees of freedom and high uncertainty
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided by the
contractor (ABT).
Collaboration on design beyond ABT Design and construct
contract. Design provided by contractor (ABT). Transport
Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB). Contractor is
adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with remuneration
form incentive and guideline cost
Cost plus principle (current account) with possible fixed
contractor fee.
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
18 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV E6 Complex contracts with very high uncertainty
Competitive focus
Collaborative focus
Form of contract Design and construct contract. Design provided by the
contractor (ABT).
Collaboration on design beyond ABT Design and
construct contract. Design provided by contractor (ABT).
Transport Administration is adviser.
Deeper collaboration on the design through Early Contractor
Participation (TEM). Distribution of responsibilities through,
for example, early procurement on ABK or ABT.
Performance contract. Design provided by
employer (AB).
Collaboration on design beyond AB. Performance
contract. Design provided by employer (AB). Contractor
is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Cost plus principle (current account) with remuneration
form incentive and guideline cost.
Cost plus principle (current account) with possible fixed
contractor fee.
Bonus for quality and innovation aspects. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
19 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Appendix 4 - Business forms for types of contract with BASIC maintenance and other
contracts with a significant maintenance component commonly used in the Swedish
Transport Administration
The following five types of contract shall be used as a starting point for choice of business form for contracts with BASIC maintenance
and other contracts with a significant maintenance component, regardless of VO.
If contracts are classified as standard, TRV UH1A, UH1B or TRV UH2 is chosen. If uncertainty regarding the complexity of the contract
exists, the TMALL 0767 complexity assessment shall be used.
Collaboration Basic
TRV UH1A Standard contracts with sufficient degrees of freedom and low uncertainty
TRV UH1B Standard contracts with sufficient degrees of freedom and an identified need for innovation or other benefit
TRV UH2 Standard contracts with small degrees of freedom and low uncertainty
TRV UH3 Complex contracts with high uncertainty (BASIC maintenance contract for district/contract area > 10 years together with a design and build contract
with a performance commitment according to TRV E3)
Collaboration High
TRV UH4 Very complex contracts with high uncertainty – contract model under development
20 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV UH1A Standard contracts with sufficient degrees of freedom and low uncertainty
Competitive focus
Collaborative focus
Form of contract Contract with emphasis on functional requirements (ABT).
Measures, method and frequency are mainly
determined by the contractor based on degrees
of freedom.
Collaboration on choice of measure, method and
frequency beyond ABT. Design and construct
contract. Choice of measures, method and
frequency is performed by contractor. Transport
Administration is adviser.
Deeper collaboration on choice of measure, method and frequency through
Early Contractor Participation (TEM). Distribution of responsibilities
through, for example, early procurement on ABK or ABT.
Contract with emphasis on performance requirements (AB).
Measures, method and frequency are determined
by the employer based on degrees of freedom.
Collaboration on choice of measure, method and
frequency beyond AB. Performance contract.
Choice of measures, method and frequency is
performed by employer. Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Fixed price with or without quantity adjustment, as
well as cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account). Possibly with fixed contractor’s fee
and/or bonus for quality aspects.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated (selective) procurement.
Also simplified, below the threshold.) No limitation
of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
21 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV UH1B Standard contracts with sufficient degrees of freedom and an identified need for innovation or other benefit
Competitive focus
Collaborative focus
Form of contract Contract with emphasis on functional requirements (ABT).
Measures, method and frequency are mainly
determined by the contractor based on degrees
of freedom
Collaboration on choice of measure, method and
frequency beyond ABT. Design and construct
contract. Choice of measures, method and
frequency is performed by contractor. Transport
Administration is adviser.
Deeper collaboration on choice of measure, method and frequency
through Early Contractor Participation (TEM). Distribution of
responsibilities through, for example, early procurement on ABK or ABT.
Contract with emphasis on performance requirements (AB)
Measures, method and frequency are determined by
the employer based on degrees of freedom.
Collaboration on choice of measure, method and
frequency beyond AB. Performance contract. Choice
of measures, method and frequency is performed by
employer. Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Fixed price with or without quantity adjustment,
as well as cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account). Possibly with fixed contractor’s
fee and/or bonus for quality aspects.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated (selective) procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
22 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV UH2 Standard contracts with small degrees of freedom and low uncertainty
Competitive focus
Collaborative focus
Form of contract Contract with emphasis on functional requirements (ABT).
Measures, method and frequency are mainly
determined by the contractor based on degrees
of freedom.
Collaboration on choice of measure, method and
frequency beyond ABT. Design and construct contract.
Choice of measures, method and frequency is
performed by contractor. Transport Administration is
adviser.
Deeper collaboration on choice of measure, method and frequency
through Early Contractor Participation (TEM). Distribution of
responsibilities through, for example, early procurement on ABK or ABT.
Contract with emphasis on performance requirements (AB)
Measures, method and frequency are determined by
the employer based on degrees of freedom.
Collaboration on choice of measure, method and
frequency beyond AB. Performance contract. Choice
of measures, method and frequency is performed by
employer. Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Fixed price with or without quantity adjustment,
as well as cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account). Possibly with fixed contractor’s fee
and/or bonus for quality aspects.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated (selective) procurement.
Also simplified, below the threshold
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
23 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV UH3 Complex contracts with high uncertainty (BASIC maintenance contract for district/contract area > 10 years together with a design and build contract with a performance commitment according to TRV E3)
Competitive focus
Collaborative focus
Form of contract Contract with emphasis on functional requirements (ABT).
Measures, method and frequency are mainly
determined by the contractor based on degrees
of freedom.
Collaboration on choice of measure, method and
frequency beyond ABT. Design and construct
contract. Choice of measures, method and frequency
is performed by contractor. Transport
Administration is adviser.
Deeper collaboration on choice of measure, method and frequency
through Early Contractor Participation (TEM). Distribution of
responsibilities through, for example, early procurement on ABK or ABT.
Contract with emphasis on performance requirements (AB).
Measures, method and frequency are determined by
the employer based on degrees of freedom.
Collaboration on choice of measure, method and
frequency beyond AB. Performance contract. Choice
of measures, method and frequency is performed by
employer. Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Fixed price with or without quantity adjustment,
as well as cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account). Possibly with fixed contractor’s
fee and/or bonus for quality aspects.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated (selective) procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price. Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
24 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV UH4 Very complex contracts with high uncertainty – under development
Competitive focus
Collaborative focus
Form of contract Contract with emphasis on functional requirements (ABT).
Measures, method and frequency are mainly
determined by the contractor based on degrees
of freedom.
Collaboration on choice of measure, method and
frequency beyond ABT. Design and construct
contract. Choice of measures, method and
frequency is performed by contractor. Transport
Administration is adviser.
Deeper collaboration on choice of measure, method and frequency
through Early Contractor Participation (TEM). Distribution of
responsibilities through, for example, early procurement on ABK or ABT.
Contract with emphasis on performance requirements (AB).
Measures, method and frequency are determined
by the employer based on degrees of freedom.
Collaboration on choice of measure, method and
frequency beyond AB. Performance contract. Choice
of measures, method and frequency is performed by
employer. Contractor is adviser.
Form of remuneration Fixed price with or without quantity adjustment. Fixed price with or without quantity adjustment,
as well as cost plus principle (current account) with
remuneration form incentive and guideline cost.
Cost plus principle (current account). Possibly with fixed contractor’s fee
and/or bonus for quality aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Form of collaboration Collaboration according to TRV basic level. Collaboration according to TRV high level.
25 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
Appendix 5 - Business forms for types of technical consultant assignments commonly used in the Swedish Transport Administration
Technical consultants perform strategic choice of measures studies, localisation studies, planning assignments and design assignments including
building site follow-up.
Choice of type of assignment for technical consultants shall be made on the basis of the assignment conditions and irrespective of the choice of
type of contract.
The following seven types of assignment shall be used as a starting point for choice of business form for technical consultants, regardless of VO.
Collaboration Basic
TRV TK1A. Standard assignments with low uncertainty
TRV TK1B. Standard assignments with low uncertainty and an identified need for innovation or other benefit
TRV TK2A. Standard assignments with high uncertainty
TRV TK2B. Standard assignments with high uncertainty and an identified need for innovation or other benefit
Collaboration High
TRV TK3 Complex assignments with high uncertainty TRV TK4 Complex assignments with very high uncertainty
TRV TK5 Complex assignments with very high uncertainty regarding scope, project contests
26 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK1A. Standard assignments with low uncertainty
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration form
incentive and guideline cost. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement, project
contest, competitive dialogue. Also selection
under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
27 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK1B. Standard assignments with low uncertainty and an identified need for innovation or other benefit
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement,
project contest, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
28 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK2A. Standard assignments with high uncertainty
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement,
project contest, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
29 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK2B. Standard assignments with high uncertainty and an identified need for innovation or other benefit
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement,
project contest, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
30 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK3 Complex assignments with high uncertainty
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost. Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated procurement,
project contest, competitive dialogue.
Also selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
31 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK4 Complex assignments with high uncertainty
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement.
Also simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated
procurement, project contest,
competitive dialogue. Also
selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level
32 (33) STRATEGY DOCUMENT
TDOK number Version
TDOK 2016:0199 3.0
TM
ALL
015
5 S
trate
gy d
ocum
ent
4.0
TRV TK5 Complex assignments with very high uncertainty regarding scope, project contests
Competitive focus
Collaborative focus
Assignment form Assignments specified in tender documents Assignments specified in consultation
Form of remuneration Fixed fee Variable and fixed fee Variable fee with the remuneration
form incentive and guideline cost.
Bonus for quality and innovation aspects.
Procurement procedure Open and negotiated procurement. Also
simplified, below the threshold.
No limitation of the number of bidders.
Selective and negotiated procurement.
Also selection under threshold value.
Limitation to qualified bidders.
Selective, negotiated
procurement, project contest,
competitive dialogue. Also
selection under threshold value.
Limitation of the number of bidders.
Tender evaluation Greatest focus on price Focus on price and quality. Greatest focus on quality.
Collaboration Collaboration according to TRV basic level Collaboration according to TRV high level