The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala [email protected] National University of Laos International Young Scholar Workshop Kyoto University

Transcript of The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2...

Page 1: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

The Social & Economic Development Policy and Its Changes to the Livelihoods:

A Case of Nam Theun 2 Hydropower Project

3rd August 2011

Bounpheng Duangmala

[email protected]

National University of Laos

International Young Scholar WorkshopKyoto University

Page 2: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Country Overview

Lao People’s Democratic Republic (PDR) is a small, landlocked nation of less than six million people at the center of the dynamic Mekong region. The country is facing numerous development challenges but has been undertaking reforms that are helping to embark it on an increasingly sustainable development path. With strong economic performance and structural reforms in trade, private sector development, and public financial management - among others, Lao PDR is fighting poverty, addressing social inequities, and building stronger capacity to

manage its rich natural resources.

Page 3: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Introduction (cont);

The economic transition in Lao PDR

From 1986, the New Economic Mechanism (NEM) was introduced with opening up the country, focusing on market oriented economy, competitiveness, less government intervention; promoting all economic agents to participate in the economic development process of the country.

A foreign investment code was officially declared in 1988, The Foreign Investment Law 1994, Amended in 2004 and re-amended in 2010.

Poverty issues has been seen as a priority task for the government in development agenda.

Page 4: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Government policy & its driven-force

The World Bank and Asian Development Bank had been also active in pushing Lao PDR to the hydropower project

To ensure economic growth, hydropower is an income generating factor and important element in development strategy.

In Laos, the exploitable hydropower potential is estimated to be around 18,000 MW in total installed capacity of power plants.

To become the ‘battery of South-East Asia’.

Page 5: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Government policy & its driven-force (cont)

The development strategy from 2000-2020.- To sustain economic growth with security and stability

and maintain the GDP growth rate of about 8 % annually.

- To achieve the Millennium Development Goals by 2015.

- To leave Lao PDR from the least developed countries by 2020

- Ensure sustainability of development between the socio-economic development and natural resource preservation

Page 6: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Hydropower and GDP Growth

Resource contribution to GDP growth

1.6 2.8 3.7 3 3.55.7 4.2 4.1 4.8 4

7.2 7 7.8 7.7 7.5

0

5

10

15

20

2003-08 2009 2010 2011-2015 2016-2020

Electricity and mining Other sectors GDP growth (%)

Source: World Bank Staff estimates and projections

Page 7: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Hydropower and GDP Growth by sector (2009)

38.5%

31.7%

29.8%

Agriculthure

Industry

Services

Source: www.worldbank.org/lao/trade

Page 8: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Electricity demand in ASEAN countries

Page 9: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Project Cost: $1.45 B (= a half of Laos’ 2005 GDP)

Installed Capacity : 1,070 MW Reservoir size: 450km2 (= 2/3 of Singapore) Generating revenues to “reduce poverty” by

exporting electricity to Thailand * BOOT project (build-own-operate-transfer ) “A model of sustainable development”

The NT2 Hydroelectric Project

Page 10: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Source : International Rivers

Vietnam

Laos

Thailand

Mekong River

Nam Theun River

Xe Bang Fai River

Nam Theun 2 Dam

Page 11: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Power HouseSource : Mekong Watch

Page 12: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Foreign Direct Investment

Nam Theun 2 Power Company ($1.45 B)

Electricité d

e F

rance: 35%

(40%

)

Lao H

oldin

g S

tate En

terprise:

25% (25%

)

EG

CO

: 25%

(3

5%

)

Italia

n-T

hai:

15%

(0%

)

Contract

Lao Government (Concession Agreement)EGAT (PPA)Electricité de Lao ( PPA )

$350 Million (International Financers)・ World Bank・ ADB・ European Investment Bank・ COFACE (France) ・ Private Investors*

Page 13: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

History of the project

International arguments for more than 10 years

March - April 2005: World Bank and ADB decided to support the NT2

June 2005: Construction started April 2008: Village resettlement completed

/impoundment of the reservoir started March 2010: Full operation started

Page 14: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Major Social and Environmental Impacts of the NT2

About 6,200 indigenous peoples on Nakai Plateau have resettled to make way for a reservoir

More than 120,000 people downstream are affected (e.g., fisheries, flooded riverbank gardens, deteriorated water quality)

Wildlife habitats, including endangered species, were negatively affected.

Page 15: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Endangered species in the Nakai Plateau

Page 16: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Livelihoods AssetsLivelihoods Assets

Financial Capital

NaturalCapital

Social Capital

Physical Capital

Human Capital

The Poor

Sustainable Livelihoods Framework

Page 17: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Hydropower development in Laos after the NT2

70 projects in Laos’ Power Development Plan till 2020

Only 10* out of 70 projects implemented before NT2

The Lao government signed MOUs to implement/research the other projects

NT2 as a turning point for Laos’ power sector development

Page 18: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Questions about the long-term livelihood restoration in Nakai Plateu

Main livelihood has been changed from subsistence rice cultivation to cash crop cultivation. There are no stable markets for cash crops.

Upland rice cultivation on 0.66 ha of compensation land not enough space for fallow lands = unsustainable

Most resettlement villagers depend on reservoir fisheries It is possible that fish catch declines in several years

Grazing land for livestock and forests with rich NTFPs (e.g. Bamboo shoots, mushrooms and etc…) were flooded loss of safety net

Page 19: The Social & Economic Development Policy and Its Changes to the Livelihoods: A Case of Nam Theun 2 Hydropower Project 3 rd August 2011 Bounpheng Duangmala.

Conclusion

The history of hydropower development in Laos is general and the development of NT 2 in particular. It

looked at the major driving forces behind the development of the dam such as economic growth, the state policy to become the ‘Battery of Asia’ and also

respond to the energy demand of the neighboring countries, especially Thailand.

More work still needs to be done by the project to develop the asset base of the poor especially the human,

financial and physical capital in order to create a sustainable livelihood for the resettled communities

affected by the NT2 project.