The Seventh Dimension of Project Management
________
by Michael Singer Dobson, PMP
Risk and the Triple Constraints
![Page 2: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/2.jpg)
The Triple Constraints
How long do we have? (Time Constraint)
How much (of what) can we spend? (Cost Constraint)
What exactly does this puppy have to do, anyway? (Performance Criteria)
![Page 3: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/3.jpg)
The Six Dimensions
Time/Performance/Cost
Time/Cost/Performance
Performance/Time/Cost
Performance/Cost/Time
Cost/Performance/Time
Cost/Time/Performance
![Page 4: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/4.jpg)
Time
Specific Deadline
Event Triggered
Degree of Urgency
![Page 5: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/5.jpg)
Cost
Cash
Personnel
Equipment
Supplies
Overhead
Intangibles
![Page 6: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/6.jpg)
PerformanceFunctional/Technical Requirements
Purpose/Desired End-State
Evaluation Criteria
Establishment of the “Good Enough” Point
![Page 7: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/7.jpg)
Know Where “Good Enough” Lives
Continuous Improvement inside projects
“Exceeds customer expectations”
Quality and Time/Cost
Value
It ain’t dog food if the dogs don’t eat it.
![Page 8: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/8.jpg)
Six Possible Outcomes
Outstanding
Exceeds Expectations
Fully Satisfactory
Barely Adequate
Failure
Catastrophe
![Page 9: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/9.jpg)
Using Triple Constraints in Risk
ProcessesRisk Identification
Risk Analysis
Risk Response
Risk Monitoring and Control
![Page 10: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/10.jpg)
The Hierarchy of Constraints
Driver
Middle Constraint
Weak Constraint
![Page 11: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/11.jpg)
Risk #1—Getting the Hierarchy Wrong
• The most overlooked question in project management is
__________“WHY?”
![Page 12: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/12.jpg)
Classical Risk vs. Project Management
Risk
Limited use of the Law of Large Numbers
Evaluating impact on project objectives
![Page 13: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/13.jpg)
New Risk Response Categories
Leverage
Relax
Absorb
![Page 14: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/14.jpg)
Threat Risk and the Triple Constraints
Take More Time
Consume More Resources
Degrade Performance
THREATTHREAT
![Page 15: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/15.jpg)
Oppportunity Risk and the Triple ConstraintsSave Time
Lower Resource Consumption
Improve or Increase Performance
OPPORTUNITYOPPORTUNITY
![Page 16: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/16.jpg)
Known Knowns, Known Unknowns,
and Unknown Unknowns
Contingency/reserve
Dig deeper
Think backward
![Page 17: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/17.jpg)
The Fine Art of Bad Decision-Making
Butch Cassidy, the Sundance Kid, and Etta Place
![Page 18: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/18.jpg)
QuickTime™ and a decompressor
are needed to see this picture.
![Page 19: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/19.jpg)
Elements of Decision-Making
Frame the problem
Generate alternatives
Evaluate alternatives
Make a choice
Test and evaluate
![Page 20: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/20.jpg)
Decision Matrix
Fight Give Up
Go to JailStart a Rock
Slide
Go for Position and Shoot Us
Starve Us Out
Surrender to Us
![Page 21: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/21.jpg)
Bad is Better Than Worse
Fight Give Up
Go to JailDie Jump
Likely to Die “I Can’t Swim!”Possible
Survival and Escape
![Page 22: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/22.jpg)
UpgradUpgradee
BuildBuildWeak Weak
DemandDemand(35% Likely)(35% Likely)
Strong Strong DemandDemand
(65% Likely)(65% Likely)
Cost $120M
Cost $50M
Revenue $90MNet -$30M
Revenue $200MNet $80M
Weak Weak DemandDemand
(35% Likely)(35% Likely)
Strong Strong DemandDemand
(65% Likely)(65% Likely)
Revenue $60MNet $10M
Revenue $120MNet $70M
Value of the Decision(.65*$80M)+(.35*$30M)
=$41.5M
Value of the Decision(.65*$70M)+
(.35*$10M)=$49M
Build or Build or Upgrade?Upgrade?
Decision=UPGRADE$49M
Numbers Aren’t Decisions!
Adapted from PMBOK® Guide
![Page 23: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/23.jpg)
Decision Options
Correct Action
Correct Rejectionof Action
Failure to Act(Type I Error)
InappropriateChoice
(Type II Error)
![Page 24: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/24.jpg)
When Cost is WeakIs cash a flexible resource?
Do you have contingency funds?
Is there an acceptable degree of budget overrun?
Can you go back to the well?
Can someone else pay part of the bill?
Are there flexible resources available?
Can you borrow staff/equipment/consumables?
Can you borrow from other client deliverables?
Are there resources whose costs aren’t charged to your project?
Can you exploit intangible resources (call in favors, etc.)?
Do you have project sponsors or key stakeholders who can help?
![Page 25: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/25.jpg)
When Time is WeakCan you delay to acquire out-year budget authority?
Can you use delay to promote quality or solve problems?
Can you schedule delay to coincide with resource availability?
Could delay lead to lower resource consumption during critical time periods?
![Page 26: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/26.jpg)
When Performance is Weak
Can you change grade?
Can you cut, modify, or substitute features?
Can you cut, modify, or adjust scope?
Can you cut -ilities?
PS—Cutting quality is usually a bad idea
![Page 27: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/27.jpg)
Risk in 3D
Always a function of the Triple Constraints
Risks to the driver are always serious
Use the Weak Constraint as a resource
![Page 28: The Seventh Dimension of Project Management ________ by Michael Singer Dobson, PMP Risk and the Triple Constraints.](https://reader036.fdocuments.in/reader036/viewer/2022081515/56649e3a5503460f94b2bad7/html5/thumbnails/28.jpg)
Michael Dobson, PMP