The San Francisco Electricity Reliability Project
description
Transcript of The San Francisco Electricity Reliability Project
The San Francisco Electricity Reliability Project
Implementing a Clean Energy Plan that Shuts Down the Hunters Point Power Plant
and Reduces Emissions from Potrero Power Plant
Workshop Agenda
7:00 Introductions & Logistics – Maureen Barry, SF PUC
7:05 Welcoming Remarks –
Marti Paschal, Sup. Maxwell’s Office
7:10 Goals & Objectives
7:15 Presentation -
Theresa Mueller, SF City Attorney’s Office
Ed Smeloff, SF PUC
7:30 Questions & Answers -
Moderator, Sam Murray, SF PUC
8:10 Public Comment – 2 minutes per person
8:35 Wrap up & Summary
8:50 Upcoming Workshops
9:00 Adjourn
Meeting Logistics
Cell Phones & Pagers Sign in Hold All Questions Until After Presentation Workshop Segments Will Be Timed Respect Each Other - Only One Speaker at a
Time Hand Outs & Comment Cards Workshop Evaluation
Goals & Objectives
Educate the Public About the Electricity Reliability Project
Explain Approval Process for Power Plants
Solicit Community Input About Site Selection
Based on Information Gathered from Public
Issue Report on Site Selection
Prepare Application to Energy Commission
Background
1998 Agreement with PG&E on Hunters Point 2002 Agreements with
State Attorney General Department of Water Resources (DWR)
April 2003 California Independent System Operator (CAL-ISO) Letter
July 2003 SF Board of Supervisors
Resolution Opposing Potrero Unit 7
Project Objectives
Improve San Francisco’s Electricity Reliability
Facilitate Shutdown of Hunters Point Unit 4
Reduce Environmental Impacts of In-City
Electricity Generation
Improving Reliability
Improving Air Quality
Hunters Point Power Plant Unit 4
Potrero Power Plant Unit 7
Improving Air Quality
Comparison of NOx Emissions From In-City Power Plants
Comparison of Small Particulate Emissions From In-City Power Plants
Beneficial Trade-offs
Vs.
Clean Flexible PowerDirty Unreliable Power
Project Constraints
Zoning
Natural Gas Delivery
Existing Transmission System
Consequences of No Project
Existing Power Plants Continue to Run! Hunters Point Power Plant #4
Potrero Power Plant #3
Less Reliability for San Francisco Potential for Service Outages and Blackouts
San Francisco Loses $40-45 Million State Subsidy
Larger Power Plant May be Built by Private Developer
Site Selection – Multiple Power Plants
“Yes” indicates that the condition was satisfied, and that there was no difference in meeting the criteria by all listed sites. Differentiation in how the site met the conditions is indicated by a “5 to 1” rating system.
5 – Very Favorable4 – Favorable3 – Neutral2 – Unfavorable1 – Very Unfavorable
Criteria/SitesWestern Pacific
Potrero Power Plant
Pier 70Cesar
ChavezIllinois
Facilitates shutdown of Hunters Point Yes Yes Yes Yes Yes
Improves air quality Yes Yes Yes Yes Yes
Mitigation of Impacts Yes Yes Yes Yes Yes
Support siting of clean power technologies Yes Yes Yes Yes Yes
City zoning and planning Yes Yes Yes Yes Yes
Minimal noise and visual impacts 5 4 5 5 3
Impact on historical and cultural resources 5 4 2 5 3
DWR power purchase agreement requirements - Land Control
3 2 3 3 3
- Reasonable Capital Costs 4 5 2 4 4
Total 17 15 12 17 13
Site Selection – Single Power Plant
Criteria/Sites CALTRANS SFO SE Sewage Treatment
PG&EStation
I
NRG Thermal
Facilitates shutdown of the Hunters Point 5 1 5 5 5
Improves air quality 3 3 3 3 5
Mitigation of impacts Yes Yes Yes Yes Yes
Support siting of clean power technologies Yes Yes Yes Yes Yes
City zoning and planning Yes Yes Yes Yes Yes
Minimal noise and visual impacts 3 5 3 1 4
DWR power purchase agreement requirements- Land Control
3 5 5 4 5
- Reasonable Capital Costs 1 5 4 1 3
Total 15 19 19 14 22
5 – Very Favorable4 – Favorable3 – Neutral2 – Unfavorable1 – Very Unfavorable
“Yes” indicates that the condition was satisfied, and that there was no difference in meeting the criteria by all listed sites. Differentiation in how the site met the conditions is indicated by a “5 to 1” rating system.
Project Timeline
Community Workshops on Potential Sites Aug-Sept 2003
Select Primary and Alternate Site Oct 2003
Application Prepared for Energy Commission Oct-Nov 2003
Community Workshops – Mitigation of Environmental Impacts Oct-Dec 2003
Complete Final Application for Energy Commission Jan 31, 2004
CA Energy Commission Public Hearings Jan- Dec 2004
Construction of Power Plants Jan-Oct 2005
Shutdown of Hunters Point Power Plant Unit 4 Jan 2006
Community Response
Question & Answer Period – 40 minutes Participant’s Guide
One Speaker at a Time One Question Per Speaker Per Round Please State Your Name & Affiliation
Public Comment – 25 minutes 2 minutes per person
Summary – 10 minutes