The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in Cross Border Trade of...
description
Transcript of The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in Cross Border Trade of...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in Cross Border Trade of Electricity
Monowar Islam, ndc
Secretary, Power Division
Bangladesh
01 March 2013
Contents
• Introduction
• Bangladesh Power Scenario
• Current /On-going Initiatives
• Potential Proposals for Joint/Multilateral Cooperation
• Policy Issues
• Concluding Remarks/Way Forward
Introduction
• The SA region is currently experiencing a rapid growth in electricity demand due to the enhanced economic growth and industrialization.
• In spite of that, the average per capita electricity consumption (about 600 kWh) in the region is far below the world average of 3000 kWh.
Introduction- Continue
• Adequate electricity supply is, therefore, a major challenge the SA economies are facing
• It is important to ensure reliable and reasonably priced electricity to the customers of this region
• Therefore, mutual co-operation in developing energy resources and electricity trade to optimize demand - supply balance is the utmost priority.
Bangladesh Scenario
Vision 2021- • To be a Middle-Income Country
Vision for Power Sector: • To provide quality electricity to all people at a affordable
price by 2021
Mission • To increase generation, transmission and distribution
• To ensure energy efficiency
• To reduce system loss
• To build public – private partnership
• To develop cooperation with regional countries
Generation : 6000 – 6350 MW (Installed Generation Capacity- 8275 MW)
So far Achieved : 6350 MW ( Aug 4, 2012)
Peak Demand : 7500 MW (with DSM)
Load shedding up to 500 MW during peak demand (with DSM)
Shortage and unreliable power supply has retarded desired economic growth
Present Power Sector and Power Demand Supply Situation
Electricity Growth : 12 % (FY- 2012) (Av. 7 % since 1990)
Installed Generation Capacity: 8,275MW (Oct, 2012)
Per Capita Generation: 272 kWh (incl. Captive)
Access to Electricity: 60 % of People
Power Demand Supply Situation
Forecasting Of Power Demand Based
Financial Growth Rate Scenarios
For 6% GDP
For 7% GDP
For 8% GDP
Coal as Source for Power Generation
According to PSMP by
2030
• 50% Electricity will be
generated from Coal
• 22% from natural gas
• 28% from other source
• As a part of the Power System Master Plan (PSMP) BPDB has planned to construct
1320 MW coal based power plant at Khulna
1320 MW coal based power plant at Chittagong
8320 MW coal and LNG based power plant at Maheshkhali
9.04% 10.34%
22.87%
21.71%
29.07%
6.98%
Regional Grid 3500 MW
Nuclear 4000 MW
Gas/LNG 8850 MW
Imported Coal 8400 MW
Domestic Coal 11250 MW
Others 2700 MW
Total Generation Capacity in 2030: 38,700 MW
Priority Issues for PS in Bangladesh • Ensure primary fuel (gas, oil, coal, etc) supply sources for
power generation; • Financing arrangement for overall power sector , special
emphasis to arrange finance for coal based power plant; • Constructing transmission backbone line (400KV level); • Strengthen distribution network, upgrade and new line
construction for more coverage; • Ensure regional interconnectivity. Regional agreement for
power trade with Nepal, Myanmar, India and Bhutan; • Development of renewable energy and energy efficiency. • Operationalization of SREDA;
On-going Initiatives
• Bhutan perhaps exports about 1200 MW power to India mainly from its Chuka and Tala hydro power projects.
• Under a framework agreement between Bhutan and India, first 10 projects were selected for the development of 10,000 MW by 2020.
Regional Inter-connection in SAARC
• Bhutan has hydro power resources 30,000 MW
• Nepal has hydro power resources 83,000 MW
• India has hydro power resources 150,000 MW
• Pakistan hydro power potential 54, 000 MW
Potential Proposals for Joint/Multilateral Cooperation
Interconnection Voltage
Level
Remarks
Bheramara -
Baharampur
400 KV Power Import from Eastern
Region, India Comilla – Palatana,
Tripura
400 KV Power Import from
Fenchugonj –
Shilchar, Assam
400 KV Power Import from North-
Eastern Region including
Meghalaya
Barapukuria –
Purnia, Bhihar
765 kV Power Import from Nepal
Barapukuria –
Bongaigaon, Assam
765 kV Power Import from Arunachal
and Bhutan
Arunachal Pradesh:
• In term of Identified Capacity (as per reassessment study) total hydro potential in Arunachal Pradesh is estimated around 50328 MW.
• Among this huge potential around 405 MW is already developed and 2710 MW is under construction.
Hydro Potential In North Eastern India
Meghalaya: • At present, total installed capacity of Meghalaya
is around 370 MW. • Electricity demand in 2011-12 was about 319
MW. • In term of Identified Capacity (as per
reassessment study) total hydro potential in Maghalaya is estimated around 2394 MW.
• Among this huge potential around 240 MW is already developed and 82 MW is under construction.
Policy and Regulatory Issues:
• Frame-Work Agreement between India and Bangladesh at PM level
• Power Policy
• Special Power Act
• G to G Joint Venture ( Bangladesh-India)
Bangladesh India Friendship Power Company
Project site to Mongla Port
14km (S)
Project site to nearest Sundarbans boundary
14 km (S)
Project site to Khulna City 23 km (N)
Project site to Akram Point
67 km (S)
Project site to nearest World Heritage boundary
76 km (S)
Project site to Hiron Point 97 km (S)
All distances were measured from Plant location
Way Forward
• Track I diplomacy may be strengthened vis-à-vis Track II diplomacy
• Open mind dialogue from policy makers
• Win-Win situation for all regional countries to benefit the people of the SAARC region
• Time is running out
Way Forward
• Political will is the key for regional electricity interconnection and establishment of power market.
• This will certainly enhance the energy security in this region and land locked countries will have the opportunity to enhance their export earnings.
• Therefore, overall socio economic condition of this region will improve significantly.