The Red Line July 2015 - נת"ע · The red Line –Progress Launching Shafts Works complete TBM...
Transcript of The Red Line July 2015 - נת"ע · The red Line –Progress Launching Shafts Works complete TBM...
General Information
8Lines
215 KmTotal Length
415 milionNo. of Boarding
In 2030
1.4 milionNo. of Daily Boarding
In 2030
34.6 %Of Citizens Within
Walking Distance
180 ThousandNo. of Boarding During
Rush Hour
45.3 %Of Work Places Within
Walking Kistance
38%Of Boarding From
Public Transportation
Serves 6 cities: Petach Tiqva, Bnei Brak, Ramat Gan, Tel Aviv – Yafo, Bat Yam and Rishon LeZion
Crosses over 50 intersections
19 min. drive from PT (Beilinson) to TA (Allenby)28 min. drive from Bat-Yam (Balfour) to TA (Arlozorov) During rush hour
Line length: 25 km14 km & 27 stations on the ground level11 km & 10 stations on the underground level
The red line
Procurement
Contracts
•TBM & Boxes West - Six underground stations and 6 km tunnels
•TBM & Boxes East - Two underground stations and 4km tunnels
•Carlibach Station - Interchange station
•Station Fit out - finishes and electrical & mechanical works
•SDAG ( Systems, Depot Equipment and At Grade )
•Rolling Stock
•Turkish Alignment
•Depot and Depot Portal
•Em Hamoshaot
•Shenkar Portal
•Advanced shafts
Construction Tenders Package1. Construction of TBM launching shafts
Shenkar portal “box”
Turkish Alignment cut & cover
Depot portal “box” and Depot Civil works
Em Hamoshavot station “box” and crossover “box”
3. TBM tunnels construction West and 6 cut & cover structures for underground stations
4. TBM tunnels construction East ,2 underground stations and cut & cover chambers
5. Fit Out of 10 underground stations ( architecture , electrical & mechanical )
6. Construction of Carlibach Interchange Station
7. Design & construction of the railway system throughout the Red Line. Including trackwork and thecivil works of the At-Grade sections
8. Rolling Stock supply and Maintenance
9. Operation and Maintenance
3 contractors
1 contractor
1 contractor
1 contractor
1 contractor
1 contractor
1 contractor
1 company
1 contractor
1 contractor
1 contractor
1 company
2. Construction of 4 “Boxes”
Background OverviewMajor
ChangesAdditional Changes
Summary
Background – Construction method
To Last slide
Major Milestones 2014 - 2015
*Schedule is based on earliest possible dates without buffers
Q1, 2014 Q2, 2014 Q3, 2014 Q4, 2014 Q3, 2015
Start Box
construction
Em
Hamoshavot2nd quarter 2014
Start
Shenkar
construction3rd quarter 2014
Start of Depot
Portal and
Site
construction4th quarter 2014
Start
Carlibach
construction3rd quarter 2015
Start of
Underground West
Station Boxes
construction3rd quarter 2015
To construction
method slide
Background OverviewMajor
ChangesAdditional Changes
Summary
Major Milestones 2015 - 2021
*Schedule is based on earliest possible dates without unforeseen
To construction
method slide
2015 2016 2017 2018 2019 2020 2021
Start of East
Station boxes
construction1st quarter 2016
Start
mobilization
at-grade
south
section 2nd quarter
2015
Start launch
of TBM’s
1st quarter 2017
First LRV’s
delivered to
Depot2nd quarter 2018
Start testing the
AG South
section Phase 14th quarter 2019
Start trial
operation on
AG South
section2nd quarter 2020
Systems
contractor
starts in
tunnels3rd quarter 2019
Line
operation4th quarter
2021
Background OverviewMajor
ChangesAdditional Changes
Summary
Red Line Top Ten Risks
1. Delay in permits by Petach-Tikva, Bnei-Brak and Bat-Yam
Municipalities
2. 24/7 work permits
3. Delay in Police approval for traffic arraignments
4. Delays by utility owners
5. Tunnel collapse
6. Damage to buildings
7. Framework agreements with Municipalities
8. Objections & claims by residents
9. Permitting interface with Shlavim road project
10. Shortage in skilled workers, work permits for foreign
workers
Health & Safety Structure
• Senior Management has issued a Health & Safety Policy to NTA and its project partners.
• NTA is committed to zero fatalities and set a demanding accident frequency rate of <0.1.
• A Construction Health & Safety Management Manual, in many aspects, exceeding Israeli H&S legal requirements, is mandatory in contracts.
• Construction Health & Safety Management will be overseen by an international experienced foreign expert – this will ensure lessons learnt (internationally) are adopted.
Construction Methodology
Typical Reference Cross-passage Section
Lining
Shotcrete
Lining
Shotcrete
Segmental LiningLiningShotcrete
LiningShotcreteSegmental Lining
Running TunnelRunning Tunnel
Running TunnelRunning Tunnel
Fire doors
cross passages to meet to Israel Standard requirements
Jet Grout
Systems Depot At-Grade
Scope of SDAG
•Design and Build
•Railway Systems along the entire line
•Depot
– Workshop Equipment
– Track, Rail Systems, Control Centers
•At Grade (AG South, AG East, Ext to Kiryat Aryeh)
– Civils including P-way, TTRs, Stops, landscaping, roads and junctions
– Temporary Depot at Bat Yam
– Turnback at Koifman
•Underground 2nd stage concrete, M&E in tunnels
•Maintenance of critical systems for 10 years
Vehicle Basics
• Articulated, with vehicle length 32 – 37.5 m
• Standard track gauge 1435 mm
• Nominal voltage 1,500 V DC
• Max. speed 80 km/h
• Bi-directional and capable of operating as single units or trainsets (2 vehicles coupled)
• Low floor
• Expected life 30 years
• High performance Air Conditioning Requirements
• Capable of LOSD and ATO/ATP operation
25
Current Status
The red Line – Progress
Launching Shafts Works complete
TBM and Boxes- West Contract awarded. NTP issued
TBM and Boxes- East Out to tender – return on 30 July
Shenkar Portal Diaphragm walls in progress
Station Fit-out Tender to be issued mid 2016
Carlibach Contract awarded. NTP issued
SDAG Tender issue in Sept 2015
Depot & Depot Portal Diaphragm walls for the portal and piling for depot buildings completed.
Rolling Stock Tender under evaluation