The Real Estate development Process - Daniel...
Transcript of The Real Estate development Process - Daniel...
DRAFT FOR DISCUSSION AND COMMENT
Page 1 of 20
The Real Estate Development Process:
Is This A Value Creation Chain?
The Potomac Yard Example
Presented at,
2007 American Real Estate Society Annual Meeting
San Francisco, California
Presented by,
Daniel B. Kohlhepp, Ph.D.
President, Commercial Division
Crescent Resources, LLC
April 12, 2007
DRAFT FOR DISCUSSION AND COMMENT
Page 2 of 20
The Real Estate Development Process:
Is This A Value Creation Chain?
The Potomac Yard Example
I. PERSONAL INTODUCTION
In 1973, Ohio State University Professor Ronald L. Racster invited University of
Wisconsin Professor James A. Grasskamp to Columbus, Ohio to address a group of real
estate practitioners about land development. Dr. Racster assigned me, his eager graduate
student, to be Dr. Graaskamp’s personal assistant for the day. I was unprepared for Dr
Graaskamp’s physical condition and totally unprepared for his presentation on land
development. His explanation of the land development process was a watershed day for
me, and his critical thinking about the stages of the process, the tasks involved, and the
skills required in each stage became an integral part of my real estate self-identity.
Through several panel discussions like this one, I became friends with Jim, and, in the
process, I became even more respectful of his critical thinking and its influence on my
future career. I have lost my notes from his lecture, but I think of him every day as I
thrash through the stages of land development and deal with the risks and returns on a
real-time basis. The real estate development process described in this paper is based on
Dr. Graaskamp’s lecture 33 years ago, but I have never been able to find an adequate
citation for his work in this area. Perhaps, my friends at ARES can help me with an
appropriate citation and recognition.
This paper addresses the questions: 1. Is the real estate development process a value
creation chain? And 2. If so, can the value creation be measured and observed in the
marketplace? This paper will focus on the Land Packaging, Land Development,
Building Development, and Building Operations stages of the development process. The
Potomac Yard Development, a mixed-use, urban-infill development in Northern Virginia
that Crescent Resources, LLC just completed, is used as an example to demonstrate the
real estate development process and the value created by it.
DRAFT FOR DISCUSSION AND COMMENT
Page 3 of 20
II. THE REAL ESTATE DEVELOPMENT PROCESS (a la Grasskamp)
Real estate development is a seven-stage process. Each stage has specific tasks which
require specific skills, and each stage has specific risks that must be accepted,
conditioned, reduced, or eliminated. Finally, each stage has profit opportunities that can
be captured. Participants and investors in the real estate development must be cognizant
of the characteristics of the stage or stages of development in which they participate.1
Failure to understand this process can lead to “getting in too early” or “getting out too
late” which, of course, leads to financial frustration and sometimes ruin
The seven stages in the real estate development process are listed below and presented
schematically in Figure 1.
DRAFT FOR DISCUSSION AND COMMENT
Page 4 of 20
Land Banking Stage
Sell? Stop YES
NO
Operating Stage
Sell? Stop YES
NO
Land Packaging Stage
Sell? Stop YES
NO
Building Development
Stage
Sell? Stop YES
NO
Land Development Stage
Sell? Stop YES
NO
Renovation Stage
Sell? Stop YES
NO
Redevelopment Stage
Sell? Stop YES
NO
DRAFT FOR DISCUSSION AND COMMENT
Page 5 of 20
1. Land Banking Stage: The “Land Banker” waits for general market forces to increase
the value of the land. This is a relatively passive investment position. The land banker
then sells the land to a “land packager.”
2. Land Packaging Stage: The “Land Packager” buys the raw land from the passive land
banker and then improves the value of the land through conceptual land planning, zoning
changes, financing schemes, or other “paper enhancements” like title insurance, accurate
surveys, or environmental studies. The packaged land is then sold to the “land
developer.”
3. Land Development Stage: The “Land Developer” buys the land with the paper
enhancements from the land packager and then improves the land so it can be sold as
finished building pads to the building developer. This usually involves the construction
of horizontal infrastructure such as roads and utilities as well as common improvements
such as water detention and recreational facilities.
4. Building Development Stage: The “Building Developer” buys the finished pad from
the land development and then does the vertical development by constructing the building
improvement. During construction, the building developer may also attempt to lease the
building so the finished building can be sold to the building operator.
5. Operating Stage: The “Building Operator” leases up the property, manages the
property, and develops a building operating history so it can be sold to other building
operators during its economic life or sold to a building renovator at the end of its
economic life.
6. Renovation Stage: The “Building Renovator” buys the property with substantial
economic and physical depreciation and creates value by curing these deficiencies and
continues to operate the building until the property is ready for redevelopment.
7. Redevelopment Stage: The “Building Re-developer” buys the property with such
serious physical or physical deficiencies that the building must be torn down or re-
developed for another use. This essentially begins the real estate development process all
over again.
The next sections of the paper will focus on the Land Packaging, Land Development,
Building Development, and Building Operations stages and will address the questions:
(1.) what is a value creation chain and
(2.) when or how does the real estate development process become a value
creation chain.
DRAFT FOR DISCUSSION AND COMMENT
Page 6 of 20
III. REAL ESTATE VALUE CHAIN (a la Roulac)
“The chain of property distribution traces those functions, tasks, and activities involved in
the conversion of land through planning and design processes, the manufacture via
building of physical forms and legal processes of property interests, through the
marketing and merchandising of physical forms and property interests. The producers
and providers of property goods and services elect business models which achieve
varying levels of prices in the resource markets and investment returns in the capital
markets.”2
“Value-added is the result of such unique contributions as:
1. perceiving an opportunity that others do not,
2. changing the use of a property, so that the new use has a value greater than costs
incurred in making the change,
3. doing what others say cannot be done,
4. doing what others are unwilling to do, and
5. taking on financial risks to make or guarantee payments in case others do not
perform and/or the project is unsuccessful.”3
“Real estate development services that can be put into five categories:
1. Creativity/ingenuity,
2. Reward for risk,
3. Provided service/resources,
4. Manage process, and
5. Advantageous purchase/negotiation.”4
DRAFT FOR DISCUSSION AND COMMENT
Page 7 of 20
IV. IS THE VALUE CREATION CHAIN OBSERVABLE AND MEASURABLE?
The value creation chain will focus on the Land Packaging, Land Development, Building
Development, and Building Operations stages of development. In each stage, the
developer buys the raw material and changes the input into a different product by adding
capital improvements so that the developer is selling a new product at the end the stage to
a participant in the next stage of development. In this process, I suggest the following
measurable and observable propositions:
Each successive stage of development has less risk and uncertainty that the earlier
stage of development e.g.,
o Land packaging has more risk than land development,
o Land development has more risk than building development, and
o Building development has more risk than building operations.
Each successive stage has a lower cost of capital than the earlier stage e.g.
o Land Packaging required rate of return – 25% and up,
o Land development required rate of return – 20%,
o Building development required rate of return – 15%, and
o Building operations required rate of return – 10%
Each successive stage requires more additional capital that the earlier stage e.g.
o Land Packaging – mostly fees to professionals,
o Land Development – fees, excavation costs and infrastructure materials,
o Building Development – fees, construction costs, and building materials,
and
o Building Operations -- building management and systems, (oops this one
doesn’t work).
The bad news is that more capital is required at each stage, and the good news is
that the cost of capital is lower at each stage.
Each successive stage creates value (or profit) by creating or manufacturing a new
product.
o Land Packaging produces “land with a plan”,
o Land Development produces “building pads”,
o Building Development produces “completed building”, and
o Building Operations produces “leased building with an operating history
and a cash flow” (an institutional investment).
With each successive stage of development, the developer attempts to create
additional value by incurring additional risks and increasing its capital exposure.
DRAFT FOR DISCUSSION AND COMMENT
Page 8 of 20
Most developers have neither the requisite skill set nor the appropriate capital
structure to complete all stages in the development process.
How should value creation be measured?
The quotient of Sales Price divided by the Total Development Costs) minus 1
equals the value added
[Sales/Total Cost] - 1
How should he cost of capital be treated?
The cost of capital should be treated as part of the costs of the venture so that
the value created truly reflects the profit or “value added” in the development
process, so that
Total Development Costs = Sales Costs + Infrastructure Costs + Land Costs +
Capital Costs
DRAFT FOR DISCUSSION AND COMMENT
Page 9 of 20
V. POTOMAC YARD: AN EXAMPLE OF THE REAL ESTATE PROCESS
AND THE VALUE CREATION CHAIN
A. The Set up
Who : Crescent Resources, LLC
What : Acquired 300 Acres of RFP Former Rail Yard
Where : Adjacent to Ronald Reagan National Airport
o Adjacent to DOD’s Pentagon
o Adjacent to CSX Rail Corridor
o Adjacent to NPS’s George Washington Parkway
o Adjacent o WMATA (METRO) line
o Partially in Arlington, VA
o Partially in Alexandria, VA
Why: To capture profits in Land Packaging and Land
Development stages, and to capture profits in the building
development stage on an opportunistic basis
Target Yield: IRR on Total capital = 15%
B. What Happened
Land Banking Stage/Redevelopment Stage
o RFP used site as a rail yard since 1848
o US Army Corp of Engineers Flood Control Project late
1980’s
o Rail yard decommissioned in early 1990’s
o Interim Land Uses include parking lots, warehoused,
auto service garage
DRAFT FOR DISCUSSION AND COMMENT
Page 10 of 20
Land Packaging Stage (Paper Infrastructure)
o Approved Conceptual Plans
Alexandria, CCD
Arlington, PDSP
o Alta Survey
o First Chicago Title Insurance
o Environmental Studies and Tests
o Environmental Remediation Plan
o Environmental Liability Insurance ($100,000,000)
o NEPA law suit resolved
o North Tract title issues resolved
o North Tract transfer to Arlington which included
environmental remediation plan and financial
guarantees
o Preliminary Phasing Plan in Alexandria – Infrastructure
Plan
o Preliminary Infrastructure Plan in Arlington
o Approved Soil Management Plan
o Community Outreach Program which resulted in
Neighborhood Approval of Off-site
Infrastructure
Monroe Avenue Bridge design and approval
o Development and approval of Arlington’s Public Art
Policy
o Arlington Park Approvals
Land Development Stage
o Off-Site Infrastructure
Alexandria --
Trunk Sewer construction
Outfall Construction and Enhancement
on Potomac River
Two water lines under CSX and
WAMTA rail lines
Sewer Lines under CSX and WMATA
rail lines
Play fields
US Route 1 Improvements
Haul road construction
DRAFT FOR DISCUSSION AND COMMENT
Page 11 of 20
Arlington
Pump Station
Outfall on Army Corps Flood Control
project
Water line under CSX to Regan National
Airport
Trunk Sewer line under US Route 1
US Route 1 Improvements
Crystal Drive Improvements
Glebe Road – US Route 1 Intersection
33rd
Street, Crystal Drive, and US
Route 1 Intersection
o On-Site Infrastructure
Alexandria
Rough Grade Potomac Avenue
Potomac Avenue Water Line (partial)
Potomac Avenue Sanitary Sewer (partial)
Potomac Avenue Storm Sewer (partial)
School Park Play Field
Soil Management Plan Execution (480
cu yds of land import and lay-down)
Dog Park Resolution
Pedestrian Bridge Resolution
Future WAMTA Station design and
reservation
DRAFT FOR DISCUSSION AND COMMENT
Page 12 of 20
Arlington
Potomac Avenue Construction
Glebe Road Extension Construction
33rd
Street Construction
35th
Street Partial Construction
Ball Street Construction
Storm Sewer Construction
Sanitary Sewer Construction
Water Line Construction
Communication and Power Duct Banks
Construction
Installed Traffic Signals with
communications and interconnection at
five intersections
Planted Potomac Avenue and Crystal
Drive Landscaping
Rough graded and Engineered transit
way
Managed excavation of soils in Land
bays F, E-East, and Land Bay A
Removed 40 tons of contaminated soils
and cinder ballast
DRAFT FOR DISCUSSION AND COMMENT
Page 13 of 20
o Building Development Stage
Municipal Site Plan Approvals
Arlington Land Bay F
Arlington land Bay E-East
Arlington Land Bay A
Alexandria Land Bay A
Alexandria Land Bay C
Building Permit
Arlington Land bay A
Arlington Land Bay E-East
Constructed land Bay A (1.1 million square
feet)
654,000 FAR SF in two, 12-story
Towers
Six stories of parking (3 above,3 below
grade)
Leased 420,000 SF to US Env.
Protection Agency
IAQ Implementation and Testing
Commissioned All Building Systems
Achieved USGBC’s Gold LEED Rating
Installed Public Art
Certificate of Occupancy permits
Federal protection Services level IV
Security
Build out EPA Tenant Improvements
Moved EPA into Space
Building monitoring systems for DOE’s
Energy Star Rating
DRAFT FOR DISCUSSION AND COMMENT
Page 14 of 20
C. Total Development Costs in millions:
Land: $118.86
Infrastructure: $48.39
Building Costs: $123.89
Selling Costs: $2.43
Capital Costs@ 15%: $77.33
Total Development Costs: $370.90
D. Total Benefits (aka Sales) in millions:
Alexandria Land Bays A & C: $28.37
Arlington Land Bay F: $21.15
Arlington Land Bay E-East: $16.43
Alexandria Land Bays G, H, I, J, L: $105.00
Arlington Land Bays B,C, D, E-West: $80.00
Arlington Land Bay A: $213.50
Total Sales: $464.45
E. Total Value Created:
Total Sales: $464.45
Divided by
Total Costs: $370.90
Minus 1
25 %
F. Value Created by Sale (in chronological order):
Land Bay Value Increase
No Capital Costs
Value Increase
with Capital
Costs
Alexandria Land Bays A & C 30% 1%
Alexandria Existing Buildings 39% 3%
Arlington Land Bay F 39% 3%
Arlington Land Bay E-East 75% 24%
Alexandria Land Bays G, H, I, J, L 74% 23%
Arlington Land Bays B,C, D, E-
West
47% 5%
Arlington Land Bay A 61% 25%
DRAFT FOR DISCUSSION AND COMMENT
Page 15 of 20
G. How Value was Created (in chronological order):
Alexandria Land Bays A & C
Letter of Intent: October 31, 2001
Contract Execution: April 1, 2002
Sales Date: September 25, 2003
Conditions of Sale:
o Off-site Infrastructure (Trunk sewer)
o On-site Infrastructure ( Utilities to property line)
o Site Plan Approval (Special Use Permit)
o Executed Development Agreement
Value Created
o Sales Price: 28.37
o Total Costs:
Land: 16.235
Infrastructure: 5.44
Selling Expenses: .08
Capital Cost: 6.22
o Value Created: 1%
Arlington Land Bay F
Letter of Intent: April 2003
Contract Execution: June 2003
Sales Date: December 15, 2003
Conditions of Sale:
o Off-site Infrastructure (Pump station, Road
Improvements)
o On-site Infrastructure ( Utilities to property line)
o Soil Disposal
o Site Plan Approval (Regulation 4.1 approval)
o Executed Development Agreement
Value Created
o Sales Price: 21.15
o Total Costs:
Land: 11.356
Infrastructure: 3.8
Selling Expenses: .02
Capital Cost: 5.38
o Value Created: 3%
DRAFT FOR DISCUSSION AND COMMENT
Page 16 of 20
Arlington Land Bay E-East
Letter of Intent: May 2003
Contract Execution: August 2003
Sales Date: June 11, 2004
Conditions of Sale:
o Off-site Infrastructure (Pump station, Road
Improvements)
o On-site Infrastructure ( Utilities to property line)
o Soil Disposal
o Site Plan Approval (Regulation 4.1 approval)
o Building Permit.
o Executed Development Agreement
Value Created
o Sales Price: 16.43
o Total Costs:
Land: 6.897
Infrastructure: 2.31
Selling Expenses: .17
Capital Cost: 3.88
o Value Created: 24%
Alexandria Land Bays G, H, I, J, L
Letter of Intent: December 2003
Contract Execution: January 2004
Sales Date: June 30, 2004
Conditions of Sale:
o Off-site Infrastructure (Trunk sewer)
o On-site Infrastructure ( Utilities to property line)
o Executed Development Agreement
Value Created
o Sales Price: 105.
o Total Costs:
Land: 44.688
Infrastructure: 14.96
Selling Expenses: .66
Capital Cost: 25.15
o Value Created: 23%
DRAFT FOR DISCUSSION AND COMMENT
Page 17 of 20
Arlington Land Bays B, C, D, E-West
Letter of Intent: June 2004
Contract Execution: September 2004
Sales Date: October 28, 2004
Conditions of Sale:
o Off-site Infrastructure (Trunk sewer)
o On-site Infrastructure ( Utilities to property line)
o Executed Development Agreement
Value Created
o Sales Price: 80.
o Total Costs:
Land: 34.059
Infrastructure: 19.99
Selling Expenses: .28
Capital Cost: 21.29
o Value Created: 6%
Arlington Land Bay A
Letter of Intent: June 2005
Contract Execution: October 2005
Sales Date: November 15, 2005
Conditions of Sale:
o Off-site Infrastructure (Pump station, Road
Improvements)
o On-site Infrastructure ( Utilities to property line)
o Soil Disposal
o Site Plan Approval (Regulation 4.1 approval)
o Building Permit.
o Executed Development Agreement
o Constructed Buildings
o 66% Leased
o Occupancy Permits
o LEED Gold Rating
Value Created
o Sales Price: 213.5
o Total Costs:
Land: 5.6610
Infrastructure: 1.89
Selling Expenses: 1.23
Building Improvements: 123.89
Capital Cost: 15.42
o Value Created: 44%
DRAFT FOR DISCUSSION AND COMMENT
Page 18 of 20
H. Serendipity Value Creation
Existing Building Re-Sale
Purchase Option Sale
Falling Capitalization Rates
DRAFT FOR DISCUSSION AND COMMENT
Page 19 of 20
Land and Infrastructure Cost Allocations and Summary of Cash Flows
in millions
Date of Sale Sept. 25, 2003 Dec. 15, 2003 June 11, 2004 June 30, 2004 Oct 28, 2004 Nov 15, 2005
Municipality Alexandria Arlington Arlington Alexandria Arlington Arlington Total
Land Bay A & C F E-East G, H, I, J, L B, C, D, E-West A
Sales Price 28.37 21.15 16.43 105.00 80.00 213.50 464.45
Less: Selling Expenses 0.08 0.02 0.17 0.66 0.28 1.23 2.43 Less: Land Cost (Mar 22, 2001) 16.23 11.35 6.89 44.68 34.05 5.66 118.86
Less: Infrastructure Allocation 5.44 3.80 2.31 14.96 19.99 1.89 48.39 Less: Building Improvement Cost 123.89 123.89 Net Proceeds Before Capital Costs 6.63 5.98 7.07 44.70 25.68 80.83 170.88
less: Capital Costs @ 15% 6.22 5.38 3.88 25.15 21.29 15.42 77.33 Net Proceeds After Capital Costs 0.41 0.59 3.19 19.55 4.39 65.42 93.55
Value Increases [(sales/cost)-1]
No capital costs 30% 39% 75% 74% 47% 61% 58%
high capital costs @15% 1% 3% 24% 23% 6% 44% 25% Conditions to Purchase Off Site
infrastructure Off Site
infrastructure Off Site
infrastructure Off Site
infrastructure Off Site
infrastructure Off Site
infrastructure
On Site
Infrastructure On Site
Infrastructure On Site
Infrastructure On Site
Infrastructure On Site
Infrastructure On Site
Infrastructure
Site Plan Approval
Site Plan Approval
Site Plan Approval
No Site Plan Approval
No Site Plan Approval Site Plan Approval
Building Permit Building Permit
Bldg Construction
67% Lease-up
Occupancy Permit
DRAFT FOR DISCUSSION AND COMMENT
Page 20 of 20
END NOTES
1 James A. Graaskamp, Lecture Notes, 1973
2 Stephen Roulac, “Competitiveness of Business Models and the Chain of Property Distribution,” p
389. 3 Roulac, Adair, Allen, Berry, and McGreal, “Beyond Valuation Measurement to Value Creation,”
4 Ibid
5 FASB Statement 67 Real Estate: Accounting for Costs and Initial Rentals Operations of Real Estate
Projects Paragraph 11a. “Land cost and all other common costs (prior to construction) shall be
allocated to each land parcel benefited. Allocation shall be based on the fair value before
construction.” 6 Ibid
7 Ibid
8 Ibid
9 Ibid
10 Ibid