The Project Management Formulas
Name Formula Knowledge Area PMI Process
PERT estimate/ three-point estimate PERT = (P + 4M + O)/6 Time (and cost) Estimate activity duration
SD (standard deviation) SD = (P - 0)/6 Time (and cost) Estimate activity duration
Float (slack) Late finish - early finish or late start - early start
Time Control schedule
Free float (ES of successor - EF of predecessor) - 1 Time Control schedule
Duration (Early finish - early start) + 1 or (Late finish - late start) + 1
Time Control schedule
BAC (budget at completion) No formula—just the estimated budget amount (used with formulas below)
Cost Control costs
AC (actual cost) No formula; the amount of money actually spent so far on the project (used with formulas below)
Cost Control costs
PV (planned value) PV = Planned percent complete * BAC Cost Control costs
EV (earned value) EV = Actual percent complete * BAC Cost Control costs
SPI (schedule performance index) SPI = EV/PV Cost Control costs
CPI (cost performance index) CPI = EV/AC Cost Control costs
Cumulative CPI CPIc = EVc/ACc Cost Control costs
SV (schedule variance) SV = EV - PV Cost Control costs
CV (cost variance) CV = EV - AC Cost Control costs
EAC (estimate at completion) EAC = BAC/CPI or EAC = BAC/CPIc Cost Control costs
ETC (estimate to complete) ETC = EAC - AC Cost Control costs
VAC (variance at completion) VAC = BAC - EAC Cost Control costs
TCPI (to-completeperformance index) TCPI = (BAC - EV)/ funds remaining Cost Control costs
COQ (cost of quality) COQ = Prevention costs + appraisal costs + failure costs
Quality Plan quality, quality assurance, quality control
Communication channels Communication channels = (N(N - 1))/2 Communications Plan communications
PI (probability and impact) PI = P * I Risk Perform qualitative risk analysis
EMV (expected monetary value) EMV = P (as a percentage) * I (as a dollar amount)
Risk Perform quantitative risk analysis
PTA (point of total assumption) PTA = Target cost + (ceiling price - target price)/buyer's % share of cost overrun
Procurement Plan procurements
Name Formula Knowledge Area PMI Process
PERT estimate/ three-point estimate
PERT = (P + 4M + O)/6 Time (and cost) Estimate activity duration
SD (standard deviation) SD = (P - O)/6 Time (and cost) Estimate activity duration
Float (slack) Late finish - early finish or late start - early start
Time Control schedule
Free float (ES of successor - EF of predecessor) - 1
Time Control schedule
Duration (Early finish - early start) + 1 or (Late finish - late start) + 1
Time Control schedule
BAC (budget at completion) No formula—just the estimated budget amount (used with formulas below)
Cost Control costs
AC (actual cost) No formula; the amount of money actually spent so far on the project (used with formulas below)
Cost Control costs
PV (planned value) PV = Planned percent complete * BAC
Cost Control costs
EV (earned value) EV = Actual percent complete * BAC
Cost Control costs
SPI (schedule performance index)
SPI = EV/PV Cost Control costs
CPI (cost performance index) CPI = EV/AC Cost Control costs
Cumulative CPI CPIc = EVc/ACc Cost Control costs
SV (schedule variance) SV = EV - PV Cost Control costs
CV (cost variance) CV = EV - AC Cost Control costs
EAC (estimate at completion) EAC = BAC/CPI or EAC = BAC/CPIc
Cost Control costs
ETC (estimate to complete) ETC = EAC - AC Cost Control costs
VAC (variance at completion) VAC = BAC - EAC Cost Control costs
TCPI (to-completeperformance index)
TCPI = (BAC - EV)/ funds remaining
Cost Control costs
COQ (cost of quality) COQ = Prevention costs + appraisal costs + failure costs
Quality Plan quality, quality assurance, quality control
Communication channels Communication channels = (N(N - 1))/2
Communications Plan communications
PI (probability and impact) PI = P * I Risk Perform qualitative risk analysis
EMV (expected monetary value)
EMV = P (as a percentage) * I (as a dollar amount)
Risk Perform quantitative risk analysis
PTA (point of total assumption) PTA = Target cost + (ceiling price - target price)/buyer's % share of cost overrun
Procurement Plan procurements