The PREMIER Bolted Industrial Storage Tank For DRY BULK · 704-846-3737 The PREMIER Bolted...
Transcript of The PREMIER Bolted Industrial Storage Tank For DRY BULK · 704-846-3737 The PREMIER Bolted...
704-846-3737www.CMTNC.com
The PREMIER BoltedIndustrial Storage Tank
For DRY BULK
FLAT PANEL BOLTED TANKTHE PRODUCT OF CHOICE
Precision designed superior modular flatpanel
Smooth Wall Interior, NO interior ledges Leak Free Tank In-house professional engineering, special design
per customer specifications Industrial hopper design Premier Powder Coat line in bolted tank
fabrication QA - Quality System certified fabrication On-time deliveries Field construction services Install and put into operation quickly Complete "customer satisfaction" customer
service BOSS Tank’s strengths are our people and our
commitment to our customers. Combined,BOSS Tank has hundreds of years experience instorage tank design, manufacturing, and quality.
SPECIALIZING in hopperbottom tanks for plastics,mineral, chemical andfood storage.
Crossover to the future inindustrial storage …
Master Distributor:CMT Inc.704-846-3737
Website: www.cmtnc.com
HOW A BOLTED FLAT PANEL TANK IS BUILT!
1. Erection begins with the “starter” or anchor ring that is anchored to the foundation. Next, the tank jacks are put into position and secured in place. 2. Note the jacks being anchored to the slab as well as the “starter” ring attached to the anchor bolts.
Master Distributor:CMT Inc.704-846-3737 Website: www.cmtnc.com
3. The tank erection begins with the upper most top ring and then the roof is assembled in place at ground level. 4. Sidewall sheets are added from the ground level until the ring is complete. Then the ring is raised with the jacks and the next ring down is added and so on.
Master Distributor:CMT Inc.704-846-3737 Website: www.cmtnc.com
5. Sidewall sheets are added in a counter-clockwise direction one panel at a time, sealed and bolted. 6. Once the ring is complete, the tank is lifted to allow the installation of the next ring.
Master Distributor:CMT Inc.704-846-3737 Website: www.cmtnc.com
7. At any time the tank can be lowered and attached to the “starter” ring to allow anchorage for leaving the tank overnight, over the weekend or in the event of sudden increase of wind or a storm. 8. Getting another panel moved into position to finish the last ring of the towering BOSS Storage Tank.
Master Distributor:CMT Inc.704-846-3737 Website: www.cmtnc.com
9. Look at that!!! The nearly finished tank. The tank is
26’ Dia. X 96’ Ht, 55 deg hopper storing Cement.