The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions...

100
The National Energy Guarantee Consultation Regulation Impact Statement 29 June 2018 ENERGY SECURITY BOARD The Energy Security Board has five members: Dr Kerry Schott AO Independent Chair Clare Savage Independent Deputy Chair Paula Conboy Chair of the Australian Energy Regulator John Pierce AO Chair of the Australian Energy Market Commission Audrey Zibelman CEO of the Australian Energy Market Operator

Transcript of The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions...

Page 1: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

The National Energy Guarantee

Consultation Regulation Impact Statement 29 June 2018

ENERGY SECURITY BOARD

The Energy Security Board has five members:

Dr Kerry Schott AO Independent Chair

Clare Savage Independent Deputy Chair

Paula Conboy Chair of the Australian Energy Regulator

John Pierce AO Chair of the Australian Energy Market Commission

Audrey Zibelman CEO of the Australian Energy Market Operator

Page 2: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

2

Page 3: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

3

Contents

1 Introduction ............................................................................................................8

1.1 The electricity supply chain ........................................................................................................... 8

1.2 The National Electricity Market ..................................................................................................10

1.3 The NEM’s spot market and financial markets .....................................................................12

1.4 NEM governance ............................................................................................................................13

1.5 Reliability in the NEM ....................................................................................................................15

1.5.1 The NEM’s reliability standard and reliability settings ........................................................16

1.5.2 Generation reliability ......................................................................................................................17

1.6 The Renewable Energy Target (RET) and the growth of renewable generation .....18

1.7 The Australian Government’s Paris Commitment ...............................................................20

1.8 The National Greenhouse and Energy Reporting (NGER) scheme .............................20

1.9 Emissions from electricity generation ......................................................................................21

2 Problem .................................................................................................................24

2.1 Overview ............................................................................................................................................24

2.2 Increased electricity prices ..........................................................................................................24

2.3 Increasing risk of unreliability......................................................................................................26

Reducing emissions....................................................................................................................................29

2.4 Generator financial incentives decoupled from system needs ........................................29

2.5 Summary ............................................................................................................................................30

3 Objectives .............................................................................................................31

4 Options ..................................................................................................................32

4.1 Business as usual ...........................................................................................................................32

4.2 National Energy Guarantee .........................................................................................................32

4.2.1 Emissions reduction requirement ..............................................................................................33

4.2.1.1 Overview................................................................................................................................33

4.2.1.2 Electricity emissions targets ...........................................................................................34

4.2.1.3 Applying the emissions reduction requirement ........................................................35

4.2.1.4 Flexible compliance options ............................................................................................40

4.2.1.5 Reporting and compliance ...............................................................................................43

4.2.1.6 Other considerations .........................................................................................................47

4.2.2 Reliability requirement ...................................................................................................................48

4.2.2.1 Overview................................................................................................................................48

4.2.2.2 Step 1: Forecasting the reliability requirement .........................................................49

4.2.2.3 Step 2: Updating the reliability requirement ..............................................................50

4.2.2.4 Step 3: Triggering the reliability obligation .................................................................50

4.2.2.5 Step 4: Liable entities ........................................................................................................52

Page 4: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

4

4.2.2.6 Step 5: Qualifying contracts ............................................................................................53

4.2.2.7 Step 6: Procurer of Last Resort .....................................................................................57

4.2.2.8 Step 7: Compliance ............................................................................................................58

4.2.2.9 Step 8: Penalties .................................................................................................................59

4.3 Physically Backed Contracts .......................................................................................................59

5 Impact Analysis ....................................................................................................65

5.1 Business as usual ...........................................................................................................................65

5.2 National Energy Guarantee .........................................................................................................68

5.2.1 Price impacts ....................................................................................................................................69

5.2.1.1 Wholesale price impacts ..................................................................................................69

5.2.1.2 Retail bill impacts................................................................................................................71

5.2.1.3 Ability to achieve emissions reduction target ............................................................72

5.2.1.4 Investment and retirements ............................................................................................73

5.2.1.5 Generation output ...............................................................................................................75

5.2.2 Qualitative assessment of the Guarantee ..............................................................................76

5.2.2.1 Certainty of achieving policy objectives ......................................................................77

5.2.2.2 Technological and geographic neutrality ....................................................................78

5.2.2.3 Appropriateness of risk allocation .................................................................................78

5.2.2.4 Impact on contract market liquidity ...............................................................................78

5.2.2.5 Implementation flexibility ..................................................................................................79

5.2.2.6 Adaptability and sustainability ........................................................................................79

5.2.3 Distributional impacts ....................................................................................................................79

5.2.3.1 Impacts on prices ...............................................................................................................79

5.2.3.2 Impacts on market customers ........................................................................................80

5.3 Physically Backed Contracts .......................................................................................................90

5.3.1 Price impacts ....................................................................................................................................90

5.3.2 Financial market impacts .............................................................................................................90

5.3.3 Competition impacts ......................................................................................................................91

5.3.4 Emissions impacts ..........................................................................................................................91

5.3.5 Regulatory burden ..........................................................................................................................91

5.4 Summary ............................................................................................................................................92

6 Consultation .........................................................................................................93

6.1 Consultation for the detailed design papers and consultation Regulation Impact Statement ..........................................................................................................................................94

7 Conclusion ............................................................................................................95

8 Implementation/Review .......................................................................................96

8.1 Implementation and governance ...............................................................................................96

8.1.1 Implementation through NEM governance arrangements ................................................96

8.1.2 Relevant Commonwealth legislation ........................................................................................97

Page 5: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

5

8.1.3 Advice on including Western Australia in the emissions reduction requirement ......97

8.1.5 Summary of key steps and issues ............................................................................................98

8.2 Reviews ..............................................................................................................................................99

Abbreviations and defined terms ..............................................................................100

Page 6: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

6

EXECUTIVE SUMMARY

The Energy Security Board (ESB) is consulting on a mechanism designed to integrate

energy and emissions policy in a way that encourages new investment in clean and low

emissions technologies while allowing the electricity system to continue to operate

reliably. Providing long-term policy confidence is critical to lowering investment risk in

the National Electricity Market (NEM) and ultimately bringing down electricity prices.

This Consultation Regulation Impact Statement (RIS) explains the problem being

addressed, sets out policy options and invites comments from interested parties. It is a

COAG requirement that if regulatory options that impose mandatory requirements upon

business and the community have a more than minor or machinery impact then

Ministerial Councils must subject these options to a regulatory impact assessment

process through the preparation of a Consultation RIS and Decision RIS.

The past decade has been characterised by changes in emissions reduction policies,

and the absence of a clear long-term policy. Electricity prices have been rising, partly

as a result of this uncertainty affecting investment decisions.

Without a policy commitment to achieve emissions reductions in the NEM, emissions

may exceed the electricity sector’s share of Australia’s international commitments

under the Paris Agreement.

At the same time, the proportion of available dispatchable generation capacity in the

NEM is declining. Australia’s ageing generators are becoming less reliable and in

recent years the retirement of old plant (mainly coal) has been replaced mainly by

variable renewable alternatives. From a reliability standpoint, variable renewable

generation is not a direct replacement for coal-fired generation. The reduction in

dispatchable generation presents risks to the reliability of electricity supply in the NEM.

The ESB’s proposed National Energy Guarantee (the Guarantee) is a mechanism

designed to integrate energy and emissions policy in a way that encourages new

investment in clean and low emissions technologies while allowing the electricity

system to continue to operate reliably. Providing long-term policy confidence is critical

to lowering investment risk in the NEM and ultimately bringing down electricity prices.

The Guarantee has two requirements:

The emissions reduction requirement is an annual obligation on retailers and large

customers who directly purchase electricity in the wholesale market (market

customers) in the NEM to ensure the average emissions intensity of their load is

at or below the prescribed electricity emissions per MWh target for that

compliance period.

The reliability requirement builds on existing spot and financial market

arrangements in the electricity market to facilitate investment in dispatchable

capacity. If a reliability obligation is triggered, liable entities may be expected to

demonstrate future compliance by entering into qualifying contracts for

dispatchable capacity to cover their share of system peak demand at the time of

the gap.

Page 7: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

7

The ESB has designed the Guarantee to have a mechanism to reduce emissions and

provide sufficient dispatchable generation to ensure reliability. A business-as-usual

approach will not be sufficient to ensure those objectives are met. The alternative to the

Guarantee considered in this Consultation RIS is a variation of the Guarantee as

proposed in the ESB's February 2018 consultation paper. The alternative requires

contracts used to meet the emissions requirement and the reliability requirement to be

physically backed by a generator (physically backed contracts). Compared to the

alternative, the Guarantee is expected to achieve its objectives at a lower cost, and

with a larger net benefit.

The ESB’s final position will be reflected in a Decision RIS, after it has considered

stakeholder submissions and refined its impact analysis. The Decision RIS will be

published following consideration by the COAG Energy Council in August.

Page 8: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

8

1 Introduction

1.1 The electricity supply chain

The electricity supply chain is the infrastructure and organisations that deliver electricity

from generators to our homes and businesses. The existing electricity market design,

and the regulatory framework that governs it, has historically been based on a linear

supply chain: from generator to transmission network to distribution network to

consumer. However, changing consumer preferences and technology developments

are enabling electricity customers to make decisions that serve their own interests as a

user, or producer, of electricity. This is leading to distribution networks experiencing

two-ways flows, as shown in Figure 1.1.

Figure 1.1: The electricity supply chain

Source: Australian Energy Market Commission1

1 Australian Energy Market Commission, https://www.aemc.gov.au/energy-system/electricity/electricity-

system/electricity-supply-chain access 29 June 2018

Page 9: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

9

Figure 1.2 shows the contribution of various fuel sources to Australia's electricity

generation.

Figure 1.2: Australian electricity generation by fuel type, 2016-172

Source: Clean Energy Regulator, Australian PV Institute3

Transmission and distribution networks

Transmission networks are high voltage lines that transport electricity from generators

to major demand centres. Distribution networks transport electricity at lower voltages to

end-user consumers, such as homes and businesses.

Electricity networks are natural monopolies and in the NEM they’re regulated by the

Australian Energy Regulator (the AER).

Retailers

Energy retail markets provide the interface between retailers and their customers. They

allow energy retailers to sell electricity, gas and energy services to residential and

business customers.

2 Percentages are based on electricity generated (MWh) for the whole of Australia including in the

NEM, other networks and large freestanding generators, such as on remote mining sites. 3 Clean Energy Regulator, Electricity Sector Emissions and Generation Data 2016-17, Australian PV

Institute, Monthly PV Output by State, http://pv-map.apvi.org.au/analyses accessed 22 June 2018

Page 10: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

10

Competitive retail markets with appropriate consumer protections provide a basis for

innovation, product choice and competitive pricing.

Retailers seek to recover the costs that they pay (e.g. purchasing energy from the

wholesale market, as well as network charges) from their consumers as well as

recovering a margin for the task of providing a retail service. The AEMC publishes an

annual report that provides an understanding of the cost components of the electricity

supply chain that contribute to the overall price paid by residential consumers; and the

expected trends in these components.

1.2 The National Electricity Market

The National Electricity Market (NEM) is an electricity system covering around

40,000 km of transmission lines. It comprises five interconnected regions in eastern

and south eastern Australia and supplies around 80 per cent of Australia’s electricity

consumption.4 The regions are:

Queensland

New South Wales (which includes the Australian Capital Territory)

Victoria

Tasmania

South Australia

Figure 1.3 shows the extent of the NEM.

Western Australia and the Northern Territory are not connected to the NEM. They have

their own electricity systems and separate regulatory arrangements5.

4 Australian Energy Market Commission, https://www.aemc.gov.au/energy-system/electricity/electricity-

system/national-electricity-market accessed 8 June 2018 5 The Northern Territory applies some parts of the NEM’s National Electricity Rules, discussed below .

Page 11: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

11

Figure 1.3: The National Electricity Market

Source: Australian Energy Market Commission

Page 12: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

12

1.3 The NEM’s spot market and financial markets

In electricity systems the amount of electricity generated needs to continuously match

the amount of electricity consumed. The NEM has a formal spot market, operated by

the Australian Energy Market Operator (AEMO), to ensure supply meets demand plus

an appropriate amount of reserves.

Almost all electricity generated in the NEM must be settled through the spot market.

The spot market matches bids from market generators to demand from market

customers (retailers and some large industrial user) every 5 minutes.

Prices are calculated at each regional reference node. This process determines a spot

price for each region. The spot price is settled (averaged) over a 30 minute period

(trading interval) and this is the price generators are paid for the electricity they

produce and retailers pay for the electricity their customers consume6.

Buyers and sellers manage the risk of price volatility through financial hedge contracts,

such as swaps and caps settled against the spot price, to reduce the exposure of both

parties to high prices. These contracts can be exchange traded or over-the-counter (i.e.

bilaterally rather than through an exchange).

The financial derivatives market has been an integral part of the operation of the NEM

since its inception. A generator's revenues and a retailer’s costs are determined by

their net exposure to the spot market and the financial derivatives market. Hedging

against spot market risk can significantly reduce market participants' (and ultimately

consumers') exposure to high price events.

6 The AEMC has recently made a final determination to move to five-minute settlement from mid-2021.

Page 13: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

13

Figure 1.4: Hedge contracts in the NEM

Source: Australian Energy Market Operator7

1.4 NEM governance

Electricity legislation is the jurisdiction of each state and territory. The NEM is governed

by the National Electricity Law (NEL) and the National Electricity Rules (NER). The

NEL was enacted in the South Australian Parliament through the National Electricity

(South Australia) Act 1996. The NEL is applied in every other state and territory

participating in the NEM by application statutes.8

The Council of Australian Governments (COAG) Energy Council is a Ministerial forum

for the Commonwealth, states and territories. It has overarching responsibility and

policy leadership for Australia's electricity markets and developing Australia’s energy

and mineral resources. The COAG Energy Council’s governing principles are:9

Promoting the interests of electricity consumers by overseeing the development

and maintenance of competitive electricity and gas markets and effective

regulation of network monopoly infrastructure.

Greater productivity, energy efficiency and sustainability.

Industry and other stakeholder participation in policy development and

implementation.

7 Australian Energy Market Operator, http://www.abc.net.au/mediawatch/transcripts/1234_aemo2.pdf,

accessed 13 June 2018

8 Australian Energy Market Commission, https://www.aemc.gov.au/regulation/legislation, accessed

12 June 2018

9 COAG Energy Council, http://www.coagenergycouncil.gov.au/about-us/our-role, accessed

12 June 2018

Page 14: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

14

Regulation and governance reform to streamline processes and decision-making

and deliver outcomes more efficiently and consistently.

The operation, regulation and development of the NEM is the responsibility of three

market bodies.

The Australian Energy Market Operator (AEMO) operates the NEM and Western

Australia's Wholesale Electricity Market. AEMO is responsible for maintaining the

security (ensuring parameters like frequency and voltage are within defined technical

limits) and reliability (ensuring supply meets demand) of the NEM in operational

timescales, subject to parameters set out in the NER. It also has network planning and

forecasting roles. AEMO is funded by market participants through market fees.

The Australian Energy Market Commission (AEMC) is the rule maker for Australian

electricity and gas markets. It makes and amends the National Electricity Rules,

National Gas Rules and National Energy Retail Rules. It also provides market

development advice to governments. The AEMC is funded by state and territory

governments.

The Australian Energy Regulator (AER) regulates electricity networks in all jurisdictions

except Western Australia, and sets the amount of revenue network businesses can

recover from customers for using these networks. The AER enforces the laws for the

NEM's spot market and monitors and reports on the conduct of market participants and

the effectiveness of competition. The AER also enforces the National Energy Retail

Law in New South Wales, South Australia, Tasmania, the ACT and Queensland, which

protects household and small business consumers. The AER is funded by the

Commonwealth Government and shares staff, resources and accommodation with the

Australian Competition and Consumer Commission.10

In addition to the three energy market bodies is the Energy Security Board (ESB),

created by the COAG Energy Council in 2017 at the recommendation of the

Independent Review into the Future Security of the National Electricity Market, led by

Australia's Chief Scientist, Dr Alan Finkel AO. The ESB's role is to coordinate the

implementation of the Review's reform blueprint. The ESB also provides whole of

system oversight for energy security and reliability to drive better outcomes for

consumers. The ESB comprises an Independent Chair, Independent Deputy Chair and

the heads of the AEMC, AEMO and AER. The ESB reports to the COAG Energy

Council. Each year the ESB delivers a Health of the National Electricity Market report

to the COAG Energy Council that tracks the performance of the system, the risks it

faces, and the opportunities for improvement. Figure 1.5 shows the NEM’s institutional

governance framework.

10 Australian Energy Regulator, https://www.aer.gov.au/about-us , accessed 12 June 2018

Page 15: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

15

Figure 1.5: NEM governance framework

Source: COAG Energy Council

1.5 Reliability in the NEM

In the NEM, reliability means having enough generation, demand response and

network capacity to supply customers with the energy they demand, with a very high

degree of confidence. This has several elements including: efficient investment;

adequate capacity to meet demand plus a sufficient level of reserves; a reliable

transmission network; a reliable distribution network, and maintaining the system in a

secure operating state (see Box1.1).

This involves longer-term considerations such as having the right amount of

investment, as well as shorter-term considerations such as making appropriate

operational decisions.

Page 16: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

16

Box 1.1: Reliability vs security in the NEM

Security: A secure system is one that operates within defined technical limits, such as for

voltage and frequency, even when there is a loss of a major transmission line or large

generator. Security events are mostly caused by sudden equipment failure, often associated

with extreme weather or bushfires.

Reliability: A reliable system is one with enough energy (generation and demand side

participation) and network capacity to supply consumers. A reliable supply needs reserves that

allow demand and supply to balance when there are unexpected demand changes.

1.5.1 The NEM’s reliability standard and reliability settings11

The reliability standard is the level of reliability sought from the NEM’s generation and

transmission assets. The standard currently requires sufficient generation and

transmission interconnection so 99.998 per cent of annual demand for electricity is

supplied.

The reliability settings promote investment to achieve the reliability standard. The

settings protect the long term integrity of the market by limiting the extent to which

wholesale prices can rise and fall. They are set at a level so as not to interfere with the

price signals needed for efficient investment and operation. The settings comprise the:

Market price cap: this imposes a maximum price that a generator may bid.

The cumulative price threshold: this limits participants’ financial exposure to

prolonged high prices by capping the total market price that can occur over seven

consecutive days.

The administered price cap: this is the ‘default’ price cap that applies when the

cumulative price threshold is exceeded.

The market floor price: this is the minimum price that a generator may bid during a

dispatch interval.

The reliability standard and reliability settings are set in the National Electricity Rules

(NER).12 Under the NER, they are required to be reviewed by the AEMC’s Reliability

Panel every four years13.

11 Australian Energy Market Commission, https://www.aemc.gov.au/energy-

system/electricity/electricity-system/reliability, accessed 12 June 2018

12 Australian Energy Market Commission, https://www.aemc.gov.au/regulation/energy-

rules/national-electricity-rules, accessed 12 June 2018

13 The AEMC may instruct the Panel to conduct an interim review before the next scheduled review.

Page 17: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

17

1.5.2 Generation reliability14

AEMO must continuously monitor levels of generation in the short term, as generator

availability changes for things like maintenance, and the medium and long term, as

generators retire from the market and new generators take their place.

In the short and medium term, AEMO assesses supply adequacy through its Projected

Assessments of System Adequacy (PASA) process. This involves collecting

information and analysing if the electricity supply can meet the reliability standard in the

short term (a one week outlook) and medium term (a two year outlook).

In the long term, AEMO’s Electricity Statement of Opportunities (ESOO)15 assesses

supply adequacy across the NEM ten years ahead, taking into account any significant

developments, such as expected power station closures and committed new build.

AEMO has mechanisms it can use if it believes electricity supply and demand will not

meet the reliability standard. The mechanisms it uses will depend on the immediacy

and size of the expected supply short-fall. These mechanisms include:

Invite generators to bid any spare supply into the market, or bid load reduction to

reduce their consumption in the market

Activate the Reliability and Emergency Reserve Trader (RERT) mechanism (see

below)

Direct a generator to increase its output, if possible and can be done safely

Direct a large energy user, such as an aluminium smelter, to temporarily

disconnect its load or reduce demand.

Direct network businesses to shed load following schedules provided by the

relevant state government.

Box 1.2: The RERT16

The RERT is a function conferred on AEMO to maintain power system reliability and system

security using reserve contracts. It allows AEMO to contract for electricity reserves ahead of a

period where it projects a shortage of reserves or, where practicable, for power system

security. AEMO can call for tenders to provide these reserves where it has 9 months’ notice of

a projected shortfall. Alternatively, AEMO may maintain a panel of RERT providers that can

provide short notice (between three hours and seven days) and medium notice (between 10

weeks and 7 days) reserve if required. The panel allows AEMO to run an expedited tender

process. Reserves can include customer load that can be curtailed and generation that is not

available to the market.

14 Australian Energy Market Commission, https://www.aemc.gov.au/energy-system/electricity/electricity-

system/reliability, accessed 12 June 2018

15 Australian Energy Market Operator, https://www.aemo.com.au/Electricity/National-Electricity-Market-

NEM/Planning-and-forecasting/NEM-Electricity-Statement-of-Opportunities, accessed 8 June 2018

16 Australian Energy Market Operator, https://aemo.com.au/Electricity/National-Electricity-Market-

NEM/Emergency- Management/RERT-panel-expressions-of-interest, accessed 15 June 2017

Page 18: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

18

1.6 The Renewable Energy Target (RET) and the growth of renewable generation17

The RET is an Australian Government scheme designed to reduce greenhouse gas

emissions in the electricity sector and encourage additional electricity generation from

sustainable and renewable sources.

The RET has been modified several times since its inception in 2001. In its initial form

fixed targets were set to achieve 9.5 TWh of additional renewable energy generated

per annum by 2010 or approximately 2% of demand. In August 2009 this target was

increased to 41 TWh or approximately 20% of demand. In June 2010 further

modifications to the RET were legislated due to the unforeseen rapid uptake in small

scale solar, and subsequently the RET was split into the Large-scale Renewable

Energy target (LRET), which applies to large power stations, and the Small-scale

Renewable Energy Scheme (SRES), which applies to solar PV systems and solar hot

water heaters installed by households and small businesses.

The LRET and SRES create large-scale generation certificates (LGCs) and small-scale

technology certificates (STCs), respectively, for each MWh they generated from

accredited renewable sources. Electricity retailers are required to purchase certificates

proportional to the amount of wholesale electricity they purchase and submit them to

the Clean Energy Regulator (CER). This creates a market which provides financial

incentives to both large-scale renewable energy power stations and the owners of

small-scale renewable energy systems.

Between 2009–10 and 2013–14 demand in the NEM fell 1.8% per annum on

average18. This decline combined with a fixed LRET increased the expected share that

the 41 TWh target would have from 20% to 28% of demand. Subsequently in 2015 the

2020 LRET was revised down to 33 TWh.

The 2017 Independent Review into the Future Security of the National Electricity

Market found that “the existing Large-scale Renewable Energy Target scheme should

remain unchanged to the end of its design life, but not be extended in its current

form”19.

The current LRET is an annual target that increases each year to the ultimate target of

33 TWh by 2020. The target then remains at this level until 2030, when the scheme

ends. The SRES target depends on the number of small PV and solar hot water

installations and is set each year by the CER so STC demand matches STC creation.

17 Clean Energy Regulator, http://www.cleanenergyregulator.gov.au/RET, accessed 18 June 2018

18 Australian Energy Market Operator,

https://www.aemo.com.au/media/Files/Other/MediaReleases/AEMO_NEFR2014_NEM.pdf

accessed 20 June 2018

19 Commonwealth of Australia, Independent Review into the Future Security of the National

Electricity Market (Finkel Review), June 2017

https://www.energy.gov.au/publications/independent-review-future-security-national-electricity-

market-blueprint-future

Page 19: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

19

STCs are created up front following the installation of an eligible system, and are

calculated based on the amount of electricity a system produces or replaces (that is,

electricity from non-renewable sources) over set a period of time. Generally,

householders who purchase these systems assign the right to create their certificates

to an agent in return for a lower system price.

The RET's cost is passed through to consumers20. The electricity purchased by

emissions-intensive trade-exposed (EITE) industries is exempt from a retailer's liable

electricity.

Since 2010, the increase in large-scale renewable generation in the NEM from the

LRET and the growth in rooftop solar PV (due in part to the SRES) has coincided with

declining NEM demand. Further, many renewable generators are paid through

contracts with retailers to supply LGCs and are not reliant on spot market revenues,

undermining spot market fundamentals. This resulted in a period where wholesale

electricity prices declined to levels that contributed to the departure of dispatchable

capacity.

Over the last decade around 5,200 MW of thermal (coal and gas) generation was

withdrawn from the NEM21.Of the 2,600 MW of generation capacity added over the six

years to March 2018, 90 per cent was intermittent renewables built primarily for the

RET22. An intermittent generator is a generator whose output is dependent on factors

beyond the control of its operator, such as wind speed or solar radiation. The last

dispatchable generator built in the NEM was in Victoria more than five years ago. A

dispatchable generator can generate electricity and adjust its output up or down at the

request of the market operator, given adequate notice and supply of fuel.

After a record year for renewable energy investment in 2017, which included 4,900 MW

of announced and fully financed new capacity, and 6,553 MW of capacity built or under

construction since January 2016, the CER said the RET is on track to achieve its target

of 33 TWh of generation from additional renewable sources in 202023 24. It should be

noted there is no proposal to change the operation of the RET under any of the options

examined in this RIS.

In addition to large scale generation, solar photovoltaic (PV) generation on the roofs of

houses and businesses has grown rapidly. At March 2018, Australia’s total rooftop

20 The RET made up 3.6% of the national average cost of electricity in 2016-17. AEMC, Residential

Electricity Price Trends Report 2017, December 2017

21 Australian Energy Market Operator, Advice to Australian Government on Dispatchable Capacity,

September 2017

22 Australian Energy Regulator, State of the Energy Market 2017 – updated with AEMO Generation

Information

23 Clean Energy Regulator, Record year of investment means Australia’s 2020 Renewable Energy

Target will be met, media release, January 2018

http://www.cleanenergyregulator.gov.au/RET/Pages/News%20and%20updates/NewsItem.aspx?L

istId=19b4efbb%2D6f5d%2D4637%2D94c4%2D121c1f96fcfe&ItemId=468

24 Clean Energy Regulator, http://www.cleanenergyregulator.gov.au/RET/About-the-Renewable-

Energy-Target/Large-scale-Renewable-Energy-Target-market-data/large-scale-generation-

certificate-market-update/large-scale-generation-certificate-market-update-may-2018 accessed

22 June 2018

Page 20: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

20

capacity was approximately 7.8 GW25. Figure 1.6 shows the change in the NEM’s

renewable generation capacity.

Figure 1.6: Renewable generation contribution to NEM electricity supply26

Source: AER, State of the Energy Market 2017

1.7 The Australian Government’s Paris Commitment27

In August 2015 the Australian Government committed to reducing Australia's

greenhouse gas emissions to 26–28 per cent below 2005 levels by 2030, as part of the

Paris Agreement.

The Paris Agreement is under the United Nations Framework Convention on Climate

Change. The agreement is a framework for all countries to take climate action from

2020, building on existing international efforts in the period up to 2020.

The Paris Agreement came into force 4 November 2016 when the threshold was met of

55 countries ratifying the agreement and covering 55 per cent of global emissions.

1.8 The National Greenhouse and Energy Reporting (NGER) scheme28

NGER is the national framework for reporting and disseminating company information

about greenhouse gas emissions, energy production, energy consumption and other

information. It is administered by the CER.

NGER considers the emissions of corporations and facilities and classifies emissions

as scope 1 or scope 2. Scope 1 emissions are greenhouse gases released into the

atmosphere as a direct result of an activity. For example, emissions from burning coal

to generate electricity at a facility are scope 1 emissions. Scope 1 emissions will be

used to calculate the emissions per MWh of a generator for the Guarantee.

25 Australian PV Institute, http://pv-map.apvi.org.au/analyses, accessed 12 June 2018. 26 Note: Rooftop solar PV generation is not traded in the NEM’s spot market but acts to reduce spot

market demand. 27 Department of the Environment and Energy, http://www.environment.gov.au/climate-

change/government/international/paris-agreement, accessed 13 June 2018. 28 Clean Energy Regulator, http://www.cleanenergyregulator.gov.au/NGER/Reporting-cycle/Assess-

your-obligations/Understand-your-corporate-group, accessed 15 June 2018.

Page 21: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

21

Scope 2 emissions are greenhouse gases released into the atmosphere as a direct

result of one or more activities that generate electricity, heating, cooling or steam that is

consumed by a facility but do not take place at the facility. For example, the emissions

from the electricity a facility consumes from an electricity network are scope 2

emissions. A facility's scope 2 emissions are counted as scope 1 emissions at another

facility. Scope 2 emissions are not considered in the Guarantee.

NGER applies to a controlling corporation, which is usually the corporation at the top of

a corporate hierarchy, but can also be another corporation. A controlling corporation

must register for NGER reporting if it meets the facility or corporate group annual

thresholds:

Facility threshold:

o 25,000 tonnes or more of scope 1 and scope 2 emissions

o Production of 100 TJ (27.8 GWh) or more of energy

o Consumption of 100 TJ or more of energy

Corporate group threshold:

o 50,000 tonnes or more of scope 1 and scope 2 emissions

o Production of 200 TJ (55.6 GWh) or more of energy

o Consumption of 200 TJ or more of energy

Corporations submit their NGER reports at the end of each financial year.

1.9 Emissions from electricity generation

Figure 1.7 shows electricity generation is the largest source of emissions in Australia’s

National Greenhouse Gas Inventory. It accounted for 35 per cent of Australia’s

greenhouse gas emissions in the year to December 2017. Approximately 80 per cent of

generation emissions are from the NEM.29

29 Department of the Environment and Energy, Quarterly Update of Australia’s National Greenhouse Gas

Inventory: December 2017.

Page 22: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

22

Figure 1.7: Australia’s emissions contribution by sector, year to December 201730

Source: Department of the Environment and Energy , Quarterly Update of Australia’s National Greenhouse Gas Inventory: December 2017

Australia’s electricity sector emissions have declined 12.9 per cent in the year to

December 2017 from the sector’s emissions peak in the year to December 2008.

Figure 1.8 shows carbon dioxide emissions in the NEM have declined 12.5 per cent (or

5 Mt) over the past decade.

Reasons for these declines include, on the generation side, increased wind and solar

capacity and the closure of coal-fired generators in South Australia and Victoria. On the

demand side, NEM demand has gradually declined for a number of reasons including

the loss of some industrial load and the growth of rooftop PV, which displaces NEM

demand.

30 LULUCF means Land Use, Land Use Change and Forestry.

Page 23: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

23

Figure 1.8: Quarterly NEM electricity emissions

Source: Department of the Environment and Energy , Quarterly Update of Australia’s National Greenhouse Gas

Inventory: December 2017

Page 24: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

24

2 Problem

2.1 Overview

Fifteen years of climate policy uncertainty has complicated long-term investment

decisions in the NEM, contributing to compromised system security and reliability. This

has left our energy system vulnerable to escalating prices while placing pressure on

the ability for the system to remain reliable and secure. Accordingly, this has shifted

security and reliability needs across the NEM, impacting the system’s operation.

2.2 Increased electricity prices

In real terms, electricity prices for households increased by 80 to 90 per cent between

2007-08 and 2015-16.31 As shown in Figure 2.1 below, these price increases have

exceeded those in other parts of the economy, and have not been matched by wage

growth, causing significant affordability challenges, particularly for low income

households.32

Figure 2.1: Electricity, All CPI Groups and Wage Price Index - Australia (December quarters)

Source: Australian Bureau of Statistics, Catalogue Number 6401.0, 6345.0

Business has also experienced large increases in prices, particularly in the past 18

months, following the renegotiation of expiring contracts. The significant increase in

31 Australian Competition and Consumer Commission, Retail Electricity Pricing Inquiry, Preliminary

Report, September 2017, p.12.

32 See for example, submissions to the National Energy Guarantee Draft Design Consultation Paper

by the Australian Council of Social Services, March 2018, p.9 and Queensland Council of Social

Service March 2018, p.1.

Page 25: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

25

business input costs undermines the international competitiveness of Australian

businesses and the economy. In 2004, Australia had the fourth cheapest electricity

prices in the OECD (and below the OECD average), but by 2016 had slipped to ninth

cheapest, behind Norway, Canada, United States, Mexico, Israel, Switzerland, Korea

and Finland (and above the OECD average).33

In December 2017, the report Small to Medium Enterprise Retail Energy Tariff Tracker,

prepared by Alviss Consulting (with Energy Consumers Australia) reported that on

average, annual electricity bills for small to medium enterprises consuming 20,000 kWh

per annum increased by 19 per cent between April 2016 and October 2017. South

Australian SMEs typically experienced increases of 36 per cent, per annum during this

period, while businesses in Tasmania and the Northern Territory experienced

increases well below the national average.34

The ACCC found extensive evidence that higher prices were impacting businesses

across the economy. As reported in its Retail Electricity Pricing Inquiry, Preliminary

Report, September 2017, the doubling of wholesale prices between 2016 and 2017

across the NEM has seen significant increases in the prices offered to commercial and

industrial users. Submissions to the report from businesses confirmed cases of

electricity prices doubling or tripling, against their most recent electricity offer.

According to the Australian Industry Group this may be because businesses were

coming off long running (3 to 5 year) contracts when wholesale prices were suppressed

by higher levels of supply, decreasing demand, and the removal of the carbon price.35

Submissions to the ESB’s National Energy Guarantee Draft Design Consultation Paper

and presentations at the public consultation on 26 February 2018 reiterated the

challenges high electricity prices are posing for the community and businesses. The

Queensland Farmers Federation described the challenge its members were facing in

its submission:

“In response to price increases, farming businesses, including irrigators, have

been installing energy efficiency measures and renewable energy and, in many

cases, simply reducing demand. Much of these gains however, have been

diminished by the increasing electricity costs; whilst simply reducing demand

has also come at a cost either through reduced productivity or farmers simply

choosing not to plant a crop.”36

33 Australian Competition and Consumer Commission, Retail Electricity Pricing Inquiry, Preliminary

Report, September 2017, p.25 34 Alviss Consulting (with Energy Consumers Australia), Small to Medium Enterprise Retail Energy

Tariff Tracker, December 2017, http://energyconsumersaustralia.com.au/wp-content/uploads/SME-

Retail-Tariff-Tracker-Final-Report-December-2017.pdf, accessed 8 June 2018. 35 Australian Competition and Consumer Commission, Retail Electricity Pricing Inquiry, Preliminary

Report, September 2017, p.18 36 Queensland Farmers Federation submission to the National Energy Guarantee Draft Design

Consultation Paper, March 2018, p.3.

Page 26: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

26

2.3 Increasing risk of unreliability

The reduction in dispatchable coal and gas generation and the greater penetration of

intermittent technologies such as solar and wind generation present risks to the

reliability of our electricity supply.

Historically, most of the installed generation capacity has been “dispatchable” (that is,

able to generate as required) provided by coal, gas and hydro-electric plants. Provided

these generating units have sufficient fuel (that is, coal, gas, stored water) and their

operational positions allow it – and assuming no unexpected outages or transmission

constraints – they can be called upon by AEMO to increase or decrease their output at

any time in a predictable manner, given enough notice.

However, Australia’s ageing generators are becoming less reliable and in recent years

the retirement of old plant (mainly coal) has been replaced by cheaper variable

renewable alternatives or gas-fired power stations. Since 2000, over 10,000 MW of

variable renewable generation has been built or is expected to be built; and about

5,500 MW of generation fleet has retired.37 From a reliability standpoint, variable

renewable generation is not a direct replacement for coal-fired generation, due to

having a lower capacity factor.

Figure 2.2 shows the change in electricity production by fuel source in the NEM for

comparison.

Figure 2.2: Annual NEM electricity generation by fuel, year to March

Source: Department of the Environment and Energy, Quarterly Update of Australia’s National Greenhouse Gas Inventory: December 2017

There will continue to be increasing penetration of intermittent renewable generation in

the form of large-scale wind and solar plant driven by the Renewable Energy Target

37 Clean Energy Regulator and Australian Energy Market Operator data.

Page 27: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

27

(RET), state-based renewables schemes, and the rapidly declining costs of these

technologies.

As a result of these factors, the proportion of available dispatchable generation

capacity in the NEM is declining. While some new wind and solar investments in

Australia are seeking to make themselves “dispatchable” by co-locating with a battery

or storage such as pumped hydro, this is not currently true for the majority of these

resources.

It is a fundamental physical requirement in any electricity system that the volume of

electricity generated (supply), must be balanced with the volume of electricity

consumed (demand) on a second-by-second basis at all and every location on the

system.

For the supply of electricity to be reliable, the power system must have sufficient

capacity beyond expected consumer demand, known as reserves, to allow for both

supply and demand fluctuations over time. For this reason AEMO monitors the NEM’s

reserve generation capacity and issues notices to the market when reserves drop

below certain levels.

It is worth noting that in 2016/17, AEMO issued 22 lack of reserve notices (see Figure

2.3 below). This was the highest number of lack of reserve notices since 2008/09. In

the summer of 2017/18 AEMO declared 31 lack of reserve conditions (not shown in

Figure 2.3)38. In one sense, this is an early warning of reliability concerns that could

arise in the future. Despite this, the current reliability standard is not forecast to be

breached.

38 Australian Energy Market Operator, https://www.aemo.com.au/-

/media/Files/Media_Centre/2018/Summer-2017-18-operations-review.pdf, p.19. Note new

arrangements for determining lack of reserve conditions were implemented on 15 February 2018 so

2017/18 may not comparable to previous years.

Page 28: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

28

Figure 2.3: NEM Lack of Reserve (LOR) notices, 2008-09 to 2016-17

Note: This f igure uses the history of Market Notices of LORs being issued, w hich is similar to how the AEMC has

counted LORs in reporting market performance. The count does not exactly match the number of times LOR conditions

have existed, but it show s the same trend and also enables us to go as far back as 2008-09.

Source: AEMO 39

Legend for Figure 2.3 – Lack of Reserves (LOR) levels

LOR 1 - An indication to the market to encourage more generation. No impact to

power system reliability is expected.

LOR 2 - No impact to power system reliability is expected, however AEMO will

bring in available additional resources if required.

LOR 3 - Signals a deficit in the supply/demand balance. With no market response,

controlled load shedding by AEMO may be required.

Source: AEMO https://www.aemo.com.au/Media-Centre/AEMO-market-notifications-

explained)

39 Australian Energy Market Operator, Summer Operations 2017-18, November 2017

https://www.aemo.com.au/-/media/Files/Media_Centre/2017/AEMO_Summer-operations-2017-18-

report_FINAL.pdf page 11, accessed 12 June 2018

Page 29: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

29

Reducing emissions

Under the Paris Agreement, Australia has committed to reducing its emissions by

26 to 28 per cent on 2005 levels by 2030.40 The electricity generation sector accounts

for around one-third of Australia’s emissions.

The past decade has been characterised by changes in emissions reduction policies.

The absence of a clear long-term policy has seen a range of different instruments,

subsidies and renewable energy targets employed at state and federal levels to

attempt to deliver emissions reductions. Prices have been rising partly as a result of

this uncertainty affecting investment decisions. Without a specific policy commitment to

reduce emissions from electricity use, Australia may exceed its 2030 emissions

reduction target.41

The principal national mechanism to reduce emissions in the wholesale electricity

generation sector currently is the RET. The RET is a policy mechanism designed to

encourage investment in large-scale renewable energy technologies. The RET policy

sits outside the energy market framework and the design of the RET is not focused on

working with the risk allocation and incentive mechanisms built into the NEM that align

the financial incentives of market participants with the physical needs of the power

system.

2.4 Generator financial incentives decoupled from system needs

Many renewable generators receive the majority of their revenue as a result of the

LRET. A common example is a generator that enters into a contract for difference to

supply a retailer with large-scale generation certificates based on an agreed NEM spot

price. The generator receives a certificate for each MWh they dispatch to the NEM.

When the spot price is above the agreed price, the generator pays the retailer the

difference for the certificates it supplies the retailer. When it is below, the retailer pays

the generator. This gives both parties price certainty.

As a result, the generator is insulated from the spot price and does not have a strong

financial incentive to be available when the physical system needs it.

This contrasts with hedge contracts (e.g. swaps or caps) used by many generators that

are not part of LRET. For example, a swap creates a link between the needs of the

system for capacity and the financial rewards that accrue to generators from being

available and dispatched, and the losses or penalties they incur if they are not. The

various types of hedge contracts and the payments and receipts flowing from them

have this effect because they are linked to the NEM spot prices reflecting the demand-

supply balance at a particular point in time.

New generation financed under the RET adds to the physical capacity of the system

but does not directly result in a corresponding increase of hedge contracts.42 This is

because typically, renewable generation is intermittent and so cannot easily enter into

40 Australian Government, http://www.environment.gov.au/system/files/resources/c42c11a8-4df7-

4d4f-bf92-4f14735c9baa/files/factsheet-australias-2030-climate-change-target.pdf.

41 Energy Security Board, The Health of the National Electricity Market, 2017 Annual Report, p.23.

42 In this report, ‘contract’, ‘firm -capacity hedge contract’ and ‘firm contract’ are terms used

interchangeably unless noted otherwise.

Page 30: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

30

these contracts without undertaking other investments e.g. having a hybrid site with

both wind and solar or installing a battery.

2.5 Summary

As the section has described, business as usual does not have the incentives to deliver

the emissions reductions required to help meet Australia's international commitments.

There are also concerns that the increasing penetration of renewables and the

retirement of dispatchable generation may be a risk to the NEM's reliability.

At the same time there is a need to reduce electricity prices, which are causing

significant affordability challenges, particularly for households with low incomes or

vulnerabilities, and leading to a loss of international competitiveness for many

businesses.

Page 31: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

31

3 Objectives

The COAG Energy Council's objectives are to:

Maintain the NEM's reliability

Achieve the emissions reductions required to help meet Australia's international

commitments

Achieve these objectives at the lowest overall cost.

Page 32: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

32

4 Options

This section describes business as usual and the options being considered.

4.1 Business as usual

One option for the COAG Energy Council is to leave the NEM as it is: business as

usual. The NEM's operation and policy settings have been described in the Introduction

and Problem sections and are summarised as follows.

The RET continues as the main emissions reduction mechanism for the generation

sector. The RET's Large-scale Renewable Energy Target (LRET) reaches 33 TWh of

generation around 2020 and stays at this level until 2030, when the scheme ends.

Similarly, the RET's Small-scale Renewable Energy Scheme (SRES), which requires

market customers to purchase in each year the small-scale technology certificates

created by solar PV, solar hot water and heat pump hot water installations, continues to

its 2030 end date.

The NEM's reliability continues to be managed by the market and AEMO under the

current reliability framework. AEMO's market projections – the ESOO and the short and

medium term PASAs – and the NEM's reliability settings are used to encourage the

market to meet any projected supply shortfalls. In the event there isn't a timely

response from the market, AEMO has various mechanisms, such as the Reliability and

Emergency Reserve Trader (RERT) mechanism, to meet the shortfall.

The COAG Energy Council, through the NEM's energy market bodies, continues to

implement the recommendations of the Independent Review into the Future Security of

the National Electricity Market (the Finkel Review), with the exception of a clean energy

target. These recommendations cover security, reliability, system planning, governance

and consumers.

4.2 National Energy Guarantee

The National Energy Guarantee (the Guarantee) is a mechanism designed to integrate

energy and emissions policy in a way that encourages new investment in clean and low

emissions technologies while allowing the electricity system to continue to operate

reliably. Providing long-term policy confidence is critical to lowering investment risk in

the NEM and ultimately bringing down electricity prices.

The emissions reduction and reliability requirements work together to ensure the

market has a fair opportunity to deliver adequate reliability whilst lowering emissions.

The Guarantee will provide a clear investment signal, so the cleanest, cheapest and

most reliable generation (or demand response) gets built in the right place at the right

time.

Market participants are expected to contract in a variety of ways to meet both of these

requirements. Increased contracting in deeper and more liquid contract markets would

be expected to reduce the level and volatility of spot prices. Cognisant of the risks to

liquidity and transparency in the contract market, the ESB has sought to ensure that

the contracting approach to meet compliance remains flexible.

Page 33: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

33

The Guarantee has been specifically designed to ensure it does not undermine but

rather enhances the liquidity, transparency and the level of competition in the retail and

wholesale electricity markets.

The Guarantee will require liable entities to contract with generation, storage or

demand response so that:

there is a minimum amount of dispatchable energy available to meet consumer

and system needs (reliability requirement), and

the average emissions level of the electricity they sell to consumers supports

Australia’s international emissions reduction commitments, as set by the

Commonwealth Government (emissions reduction requirement).

The emissions reduction and reliability requirements of the Guarantee will require

retailers to support a range of different generation and demand-side technologies

through their contracting. This will result in increased contracting levels, which in turn

will create deeper and more liquid contract markets. This is expected to reduce the

level and volatility of spot prices.

The Guarantee will be implemented through the NEM’s existing governance

arrangements. Using an established framework, with clear accountabilities and change

processes, will give businesses and investors the confidence and certainty they need

to invest in the long-term and deliver cheaper, cleaner and reliable electricity for

Australian consumers.

4.2.1 Emissions reduction requirement

4.2.1.1 Overview

The emissions reduction requirement will be an annual obligation on market customers

to ensure the average emissions per MWh of generation allocated against their load is

at or below the prescribed electricity emissions target for a given compliance period.

It will be established by the COAG Energy Council under the existing national electricity

governance framework (see Chapter 8). The Commonwealth Government will set the

trajectory of annual electricity emissions targets, expressed as annual average

emissions per MWh.

Many State and Territory Governments in Australia have also established schemes to

encourage renewable energy and to reduce electricity sector emissions. All State and

Territory renewable energy schemes can operate with the Guarantee and contribute

towards achieving the emissions reduction trajectory for the Guarantee.

Compliance with the Guarantee’s emissions reduction requirement will be assessed

and reported annually, based on a financial year compliance period. The first

compliance year is proposed to be the 2020-21 year. The AER will be the agency

responsible for monitoring and enforcing compliance.

Page 34: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

34

An emissions registry (the registry) will be used to support the allocation of generation

and associated emissions to a market customer’s load. This approach will ensure the

Guarantee works in a way that is integrated with existing electricity market operations

without compromising financial market liquidity. Importantly, it will draw on existing

reporting obligations with which participants already comply.

The registry provides the necessary infrastructure to facilitate efficient compliance with

the emissions reduction requirement. It allows market customers to be allocated a

share of a generator’s output and associated emissions, for which they have obtained

the rights. This can be based on any contractual arrangement held with a counterparty

outside the registry, as long as both parties verify the agreement in the registry. Market

customers can choose to enter into contracts to allocate generation in the registry with

the same generators that they enter into hedging contracts with, but there is no

requirement for these parties to be the same.

To provide flexibility in how market customers meet the emissions reduction

requirement while reducing the costs of compliance, market customers will be allowed

to carry forward a limited amount of a previous year’s over-achievement for use in the

next compliance year, and will be allowed limited deferral of compliance to future

compliance years.

At the end of the compliance period, and following a four month reporting and revision

window, the AER will assess the compliance of each market customer based on final

information in the registry. There will be a robust framework for the AER to monitor and

enforce compliance.

4.2.1.2 Electricity emissions targets

Annual average emissions per MWh targets for the electricity sector are proposed to be

legislated by the Commonwealth Government.

The Commonwealth Government will set these in Commonwealth legislation as a table

of annual emissions per megawatt hour (MWh) targets (known as electricity emissions

targets) for the financial years ending 2021 to 2030.

The National Electricity Law (NEL) would adopt the target set in Commonwealth

legislation for the purpose of the Guarantee.43

The Commonwealth Government is undertaking a separate consultation process in

respect of its proposed design of the Commonwealth elements of the emissions

reduction requirement, including its approach to setting electricity emissions targets.

See http://www.coagenergycouncil.gov.au/publications/national-energy-guarantee-

draft-detailed-design-commonwealth-elements for further information on the

Commonwealth elements.

43 The NEL is a schedule to a South Australian Act – the National Electricity (South Australia) Act

1996. It is applied in the states and territories that participate in the National Electricity Market by

the various application Acts of those jurisdictions.

Page 35: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

35

4.2.1.3 Applying the emissions reduction requirement

Entities covered by the emissions reduction requirement

Entities subject to the emissions reduction requirement will be each entity registered by

AEMO as a market customer under the Rules (mostly retailers, but also other parties

that purchase electricity directly from the NEM).

The market customer’s performance against the electricity emissions target will be

determined as the average emissions associated with its generator allocations from the

registry, per MWh of its load.

The allocation of generation against a market customer’s load, and the calculation of

that load is discussed below.

Generation and emissions allocation approach

Allocation rules

Market customers will be responsible for meeting the electricity emissions target.

At the start of the compliance period, all generation and associated emissions will be

unallocated.

Unallocated generation and associated emissions in the registry will have a ‘residual’

emissions per MWh. This will be a floating value, which varies over the compliance

period as allocations are recorded. Market customers that do not have generation

allocated for some or all of their load by the end of the compliance and reporting period

will be assigned the residual emissions per MWh for that load.

To record the allocation of generation in the registry, it must be requested by one party,

and approved by the counterparty.44 The parties can record allocations at any time

during the compliance period. They will also have four months after the end of the

compliance period to continue to adjust their portfolios by recording reallocations. This

includes three months before all data is taken as final at 30 September, plus one

further month.

An additional measure to support retail market competition will be included such that

the first 50,000 MWh of any market customer’s load will be exempt from the emissions

reduction requirement, and instead spread over other market customer load (this is

similar to the approach used for exempt emissions-intensive trade-exposed (EITE)

load). As a market customer’s load increases above 50,000 MWh, its exempt

proportion decreases. This measure will help smaller market customers meet the

emissions reduction requirement, while not having a material impact on overall

coverage.

Shifting the small market customer exemption to non-exempt load, excludes around

half of all small market customers, but only adds around 1 per cent additional load to

the non-exempt load amount. Shifting the EITE exempt load adds around 15 to 20 per

cent of load to non-exempt load. In both cases it does not result in any market

44 It is not intended that output could be directly allocated between generators.

Page 36: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

36

customer having to meet an unreachable target. This is because the emissions per

MWh target of the load is unchanged. The exempt load is shared across retailers.

The ESB is considering the merits of introducing an anti-avoidance regime which could

address matters like the risk of a market customer splitting into multiple market

customers to gain the benefit of this exemption and avoid responsibility for meeting the

electricity emissions target (see section 4.2.1.5 under Reporting and administrative

requirements).

To ensure the registry operates efficiently, generators will have some administrative

requirements under the emissions reduction requirement. They will be required to enter

or confirm allocations in a timely manner to allow AEMO to provide regular updates of

the contents of the unallocated pool and its emissions intensity. They will have an

administrative requirement to allocate all generation and associated emissions by the

reporting and compliance date.

To ensure that a competitive market is fostered, there will be a legal requirement that

market customers and generators do not unreasonably withhold any allocations for

anti-competitive purposes. These requirements are detailed further in the Technical

Working Paper on Compliance and Penalties for the Emissions Reduction

Requirement.45 The AER may take enforcement action for breaches of these

requirements.

Over-allocations

It is reasonable for a market customer to initially contract more generation than their

expected load to allow for load uncertainty. However, since total generation must equal

total load in the registry for each compliance period, over-allocation of generation at the

end of this period by a market customer would mean at least one market customer

couldn't be allocated generation, either through contracts or from the residual

unallocated generation pool, to cover their load.46 Further, a market customer could

seek over allocation at the end of the compliance year for competition reasons, for

example, to force others into non-compliance and face the resulting penalties.

To deter over allocation, a market customer would be assigned a deemed emissions

per MWh for allocated generation above its load after the compliance year reporting

deadline of 31 October. The deemed emissions intensity will be set at the level of the

highest emissions intensity generator in the NEM. In addition, the market customer

would face a civil penalty (as discussed in section 4.2.1.5 under Enforcement tools for

emissions reduction requirement). These measures are expected to incentivise market

customers to reallocate generation in advance of the reporting deadline to avoid being

over-allocated.

45 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

46 Over-allocation refers to an instance in which a market customer allocates more generation than it

has load. This is distinct from over-achievement where the generation matches the market

customer load but the emissions intensity is less than the electricity emissions target.

Page 37: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

37

This approach will also incorporate adjustments for exempt EITE load and to exclude

voluntary GreenPower load.

These elements are outlined below and are detailed further in the Technical Working

Paper on Market Customer Load (the adjustment for exempt EITE load is detailed

separately, in the Technical Working Paper on Exempt Load).47

Pool generation and wholesale pool purchases

All pool generation and wholesale pool purchases will be defined ‘at the node’:

Pool generation data will be measured at the transmission node identifier, with

generator imports netted against exports, and then adjusted by the marginal loss

factor.

Wholesale pool purchases will be measured by applying transmission and distribution

loss factors to the metered volumes.

This approach ensures that pool generation and wholesale pool purchases will require

minimal scaling to match (estimated to be within around 1 per cent).

For grid-connected batteries that are registered in the NEM as both a scheduled load

and scheduled generator, their generation will be netted against their load, such that

only their net wholesale pool purchases are included in their market customer load.

Stakeholders have raised concerns that pre-1997 renewable generation that is

currently not included in the Renewable Energy Target would be included in the

emissions reduction requirement. While the Guarantee is substantially different, the

treatment of this generation will be further considered by the ESB.

Non-market embedded generation and solar PV

To ensure that the emissions reduction requirement remains technology neutral, some

load supplied by non-market embedded generators and behind the meter resources

will be added to a market customer’s load in the registry. In order for total generation to

match total load, corresponding generation will be automatically allocated to that same

market customer in the registry.

Non-market embedded generation will be captured by adding its exports to the relevant

market customer’s load48. Similar to the wholesale pool purchases, transmission and

distribution loss factors will be applied to the embedded generation exports. The

embedded generation exports (and associated emissions) will be automatically

allocated to that market customer in the registry.

Rooftop and other small-scale solar PV will be captured by adding the net exports from

PV installations to the relevant market customer’s load, and will also be automatically

allocated to that market customer in the registry as zero emissions generation.

47 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

48 To avoid capturing back-up plant that rarely runs.

Page 38: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

38

Exempt EITE load

The Commonwealth Government intends to exempt EITE load from the emissions

reduction requirement.

All EITE activities exempt under the Renewable Energy Target (RET) will be eligible for

exemption under the emissions component of the Guarantee.

EITE entities will apply to the Clean Energy Regulator (CER) for an exemption, as they

do under the RET. The application process and audit requirements will be streamlined

to minimise duplication.

The CER will be responsible for determining the electricity eligible for exemption under

the Guarantee. This will be based on a method established in Commonwealth

legislation consistent with the ‘electricity use method’ under the RET.

To ensure the required emissions target is achieved, the total exempt MWhs will be

shared across all non-EITE load as an adjustment to the annual load used for

compliance.

The ESB’s proposed approach to give effect to this is that each market customer’s load

for the purposes of the emissions reduction requirement will be reduced by any EITE

load it supplies in a compliance year. Across all market customers, each MWh of non-

EITE load will then be scaled-up by a factor such that it equals the total system load for

the purposes of the emissions reduction requirement.

The scaling factor will be calculated three months after the end of the compliance

period, based on the proportion of total system load to non-EITE load for that

compliance period. To provide market customers with greater certainty, the scaling

factor will be capped at a maximum based on the prior year’s proportion of system load

to non-EITE load (or based on a best estimate of future EITE load).

GreenPower load

Some businesses and household consumers undertake voluntary action to reduce

emissions associated with their electricity use. A prominent example is the

GreenPower program.49

The ESB proposes to facilitate the treatment of GreenPower in the emissions reduction

requirement to allow consumers to make an additional contribution to emissions

reduction beyond that required by the target.

Conceptually, this would be achieved by deducting a market customer’s GreenPower

load and associated renewable generation occurring in the compliance year from its

49 The GreenPower Program is a government managed scheme that enables Australian households

and businesses to displace their electricity usage with certified renewable energy, which is added to

the grid on their behalf. By purchasing GreenPower, households and businesses commit their

GreenPower Providers to purchasing the equivalent amount of electricity from accredited

renewable energy generators, which generate electricity from sources like wind, solar, water and

bioenergy. See https://greenpower.gov.au/About-Us/What-Is-GreenPower/ for more information.

Page 39: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

39

total load and allocated generation. Similar to the wholesale pool purchases,

transmission and distribution loss factors will be applied to GreenPower loads.

However, the GreenPower arrangements were designed around ensuring additionality

to the RET, and do not contemplate the emissions reduction requirement.

Complications will arise to the extent that surrendered large-scale generation

certificates (LGCs) under GreenPower cannot be matched to an allocation of

generation in the registry. Subtracting GreenPower load from a market customer’s load

without subtracting any generation from the registry would leave it unbalanced.

The ESB intends to work with the National GreenPower Steering Group to find a way to

achieve the policy goal of additionality within the framework of the Guarantee.

Registry operations

The registry provides the necessary infrastructure to facilitate efficient compliance with

the emissions reduction requirement. It allows market customers to be allocated a

share of a generator’s output and associated emissions, and to present this for the

purposes of compliance in respect of their load. The proposed approach to registry

operations is outlined below and is detailed further in the Technical Working Paper on

the Emissions Registry.50

It is proposed that the registry will be administered by AEMO, as an enhancement to its

existing systems. AEMO already holds most of the data relevant for the Guarantee’s

operation – in particular, pool generation and wholesale pool purchases. It also has

some existing data exchange protocols in place with the Clean Energy Regulator

(CER). As the registry administrator, AEMO’s responsibilities will include developing

detailed procedures for interacting with the registry and managing IT requirements. The

AER will have complete access to the registry to facilitate its role in monitoring and

enforcing compliance.

The registry will record the emissions per MWh for each generator to apply to a given

compliance year. This will occur before the start of the compliance year.

Emissions data used to calculate the emissions intensity will primarily be sourced

from NGER, for the financial year two years prior to the compliance year.

Any gaps in the NGER emissions data will be addressed in appropriate

legislation, regulations or Rules. For instance, provisions will be made for

estimating the emissions per MWh of new or refurbished generators.

From the start of the compliance period, pool generation and wholesale pool

purchases data will be provided into the registry. This data is settled by AEMO in

weekly batches, and each week’s data first becomes available four weeks in

arrears. The wholesale pool purchases data is subject to 20 and 30 week

revisions, but will be taken as final for the purpose of compliance as at 30

September following the compliance year.

50 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

Page 40: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

40

Figure 4.1: Example of information recorded in the registry

The registry will also record other information, including output from embedded

generation and rooftop solar PV and exempt EITE loads. Depending on the source

availability, this data may be recorded during or after the compliance period, but no

later than 30 September following the compliance year, at which point all data is taken

as final for the purpose of compliance. The registry will also record the use of flexible

compliance options.

Throughout the compliance period and prior to the reporting deadline, the registry will

match emissions to each market customer based on the allocated generation volumes

as recorded at the point in time. Market customers will be able to use this information to

monitor their compliance position. Following the reporting deadline, the information

recorded in the registry will be used by the AER to assess compliance.

Only market customers and generators will have accounts in the registry. Some

information will be made public at given intervals. For instance, for each generator, its

unallocated generation will be published by AEMO on a regular basis (e.g. weekly or

monthly), alongside its pre-assigned emissions intensity.

4.2.1.4 Flexible compliance options

Providing flexibility in how market customers meet the emissions reduction requirement

will minimise instances of non-compliance and reduce the costs of the mechanism to

market customers, and in turn, electricity consumers. This flexibility will allow market

customers to manage variables such as unexpected generator outages and potential

delays to the entry of new generators. Importantly, providing this flexibility will not

change the emissions outcome for the NEM. The required emissions outcome for the

NEM will still be achieved over the medium-term despite year to year fluctuations.

Page 41: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

41

The proposed approach to implementing the flexible compliance options is outlined

below and is detailed further in the Technical Working Paper on the Emissions

Registry.51

Carrying forward over-achievement

Market customers will be permitted to carry forward a limited amount of a previous

compliance year’s over-achievement, for use in a later compliance year. This is

expected to incentivise investment when the market needs it and should enable market

customers to achieve compliance at a lower cost.

Each year, a market customer will be able to carry forward an amount (in tCO2-e) of up

to:

5 per cent of the electricity emissions target for the first year of the emissions

reduction requirement for each MWh of load, plus

a fixed amount of 60,000 tCO2-e.

No market customer will be allowed to carry forward an amount more than 100 per cent

of the first year’s target as applied to its load.

Example of carrying forward over-achievement52

Hypothetically, the electricity emissions target for the first year of the emissions reduction

requirement is set at 0.8 tCO2-e/MWh.

Market Customer A has 10,000,000 MWh of load.

They can carry forward a total amount of up to 460,000 tCO2-e, calculated as: 400,000 tCO2-e [= 5% × 0.8 × 10,000,000], plus

the fixed amount of 60,000 tCO2-e

This carry forward amount is equivalent to 5.75% of their load. Market Customer B has 50,000 MWh of load.

They cannot carry forward the full amount of 62,000 tCO2-e, calculated as:

2,000 tCO2-e [= 5% × 0.8 × 50,000], plus

the fixed amount of 60,000 tCO2-e This is because this full carry forward amount is equivalent to more than 100% of their

load at

0.8 tCO2-e/MWh [= 62,000 / (0.8 × 50,000) = 155%]

Instead, they can only carry forward 40,000 tCO2-e.

51 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

52 This example assumes the 50,000 MWh exemption as discussed in section 3.3.2 is already

accounted for.

Page 42: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

42

This approach ensures that the largest market customers will face an effective carry

forward limit of around 5 per cent of the first year’s target as applied to their load,

whereas smaller market customers will have a higher effective limit.

There would be no need to apply a carry forward limit if all market customers have

access to enough low emissions generation to meet the electricity emissions target in a

given compliance period. However, this can only be assessed once the compliance

position of each market customer is known. Accordingly, the limit would be lifted in any

year where all market customers were found to be compliant with the electricity

emissions target.

To remain appropriate to market conditions, the limit will be able to be updated through

rule-change processes in the future.

Deferring compliance

To provide adequate flexibility for market customers while ensuring the emissions

reduction trajectory is met, market customers will be able to defer 10 per cent of the

electricity emissions target per MWh of load.

The limit will be cumulative over two years, with the market customer required to make

good in the third year on the first year’s deferral amount. This will provide sufficient lead

time for market customers to make investments in generation to meet the electricity

emissions target, as needed. It will also assist market customers to manage annual

variability in demand, variable renewable generation and hydro production.

Beyond this limit, any additional increase in the market customer’s emissions intensity

above the electricity emissions target will mean the entity is non-compliant.

To remain appropriate to market conditions, the limit will be able to be updated through

rule-change processes in the future.

This approach balances the need for flexibility without undermining the objective of

providing long-term policy confidence through delivery of the requirements of the

Guarantee.

Use of offsets

The Commonwealth Government is continuing to consider whether market customers

should be able to use external offsets as a flexible compliance option to meet the

emissions reduction requirement, and if included, whether to apply conditions, such as

an overall cap on the number of offsets that could be used.

If offsets are permitted, the NEL and Rules would provide details regarding their use.

This would include a mechanism for linking offsets surrendered in the Australian

National Registry of Emissions Units (ANREU) for the purpose of the emissions

reduction requirement, to compliance calculations for market customers.

In addition, if the Commonwealth Government set an overall cap on the number of

offsets that could be used across the electricity sector, the NEL and Rules would

Page 43: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

43

address how to establish individual allowances of offsets across market customers in

the NEM.

Further information on the treatment of external offsets can be found in the Department

of the Environment and Energy's Draft Detailed Design for Consultation –

Commonwealth Elements document.53

4.2.1.5 Reporting and compliance

For the Guarantee to achieve its policy objectives, it is important to have a robust

framework for monitoring and enforcing compliance with the emissions reduction

requirement and its associated reporting requirements.

A market customer will be deemed ‘compliant’ with the emissions reduction

requirement for a given compliance year when the emissions intensity of its allocated

generation is below the electricity emissions target for that year or when it exceeds the

electricity emissions target by a margin less than or equal to the deferral limit (see

section 4.2.1.6 under Deferring compliance). A market customer which exceeds its

electricity emissions target by more than the deferral limit will be deemed ‘non-

compliant’.

The primary aim of enforcement is to ensure policy objectives are met. Effective

enforcement requires the enforcement agency to have resources to determine when an

entity has not complied with its obligations, and to impose an appropriate penalty – one

that is proportionate to the offence, acts as a deterrent, and provides greater certainty

that the policy objectives are to be met.

Some key elements of reporting and compliance – including defining compliance, the

approach to reporting on compliance, the timeframe for assessing compliance,

reporting and administrative requirements, and enforcement options – are detailed

further in the Technical Working Paper on Compliance and Penalties for the Emissions

Reduction Requirement.54

The AER as the enforcement agency for the Guarantee

The AER was established in 2005 and enforces the laws for the NEM, and monitors

and reports on the conduct of market participants and the effectiveness of competition.

The AER is also the economic regulator of the electricity networks. This role currently

extends to electricity networks in all jurisdictions except Western Australia. The AER

operates under the Competition and Consumer Act 2010 (Cth) and shares staff,

resources and accommodation with the ACCC.

In light of the need to integrate the dual requirements of the Guarantee with the

functioning of the energy markets, and the fact that the enforcement agency for the

Guarantee will need to enforce requirements set out in the NEL and Rules (see

53 National Energy Guarantee Draft Detailed Design for Consultation – Commonwealth Elements

http://www.coagenergycouncil.gov.au/publications/national-energy-guarantee-draft-detailed-design-

commonwealth-elements

54 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

Page 44: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

44

Chapter 8), the AER is considered best placed to monitor and enforce compliance with

both requirements of the Guarantee. In doing so, it will use information provided by

agencies such as AEMO and the CER.

In carrying out its role, the AER will draw on a range of enforcement tools that already

exist under the NEL. These are discussed under Enforcement tools for emissions

reduction requirement below.

The AER will report annually on high-level compliance outcomes for each compliance

year, by 31 December following the compliance year. The information published will

identify by name all market customers and their emissions intensities for the given

compliance year. The information published will also include other relevant parameters,

such as:

the final emissions intensity of unallocated generation in the registry

any over-allocation by market customers

the extent of the use of flexible compliance options

the extent of EITE exemptions provided, and

the amount of load allocated to GreenPower.

This publication approach will help to promote and maintain a culture of compliance

and provide transparency to electricity consumers.

The compliance period

The compliance period for the emissions reduction requirement will be on a financial

year basis.

There will be a specified reporting and revision window after the end of each

compliance period, with a deadline of 31 October. This will allow for relevant data to be

finalised by 30 September and any allocation imbalances in the registry to be resolved

in the following month. The AER will commence assessing compliance for the period

from 1 November onwards.

Figure 4.2 shows a timeline for the compliance period, including the timing for

availability of key data inputs – in particular, exempt EITE load and NGER emissions

data (to be sourced from the CER), and transmission and distribution loss factors (to be

sourced from AEMO). These data inputs and their timing were outlined in section

4.2.1.5).

Page 45: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

45

Figure 4.2: Simplified timeline of the compliance period for the emissions reduction requirement

Reporting and administrative requirements

The proposed compliance framework for the emissions reduction requirement has

been designed to minimise the reporting burden on market customers and generators.

Where possible, the reporting required to assess compliance will build on existing data

sources (for which the existing frameworks for monitoring and enforcing reporting

requirements will continue to apply). Where new information is required to assess

compliance, such as emissions data for generation not currently captured in NGER,

additional reporting requirements will be introduced. In doing so, the ESB will be

cognisant to minimise duplication of existing reporting requirements and to draw on

existing systems and associated compliance arrangements wherever possible.

The ESB is considering the merits of introducing an anti-avoidance regime in the NEL

that relates to the Guarantee. This is intended to prohibit an entity which has a potential

obligation under the Guarantee from restructuring or taking other action for the purpose

of avoiding or minimising that liability. Anti-avoidance regimes are often included in

taxation and revenue laws to prevent tax structuring for the purposes of avoidance. The

anti-avoidance regime would be general in its scope, as distinct from specific

avoidance or anti-gaming measures which might be included in respect of specific

obligations. Such a provision could help to reduce the complexity of the regulatory

framework giving effect to the Guarantee.

Enforcement tools for emissions reduction requirement

If, despite the flexible compliance options described in section 4.2.1.4, market

customers fail to meet the emissions reduction requirement, the AER needs to be able

to enforce compliance in a way that minimises costs for consumers. The AER already

has access to a range of compliance tools and discretion in deciding whether to take

enforcement action and the nature of that action. Each case is assessed on its merits.

In determining an appropriate enforcement response, the AER considers all relevant

factors and circumstances.

The AER will publish guidance on the enforcement options within its power and the

circumstances in which they are likely to be applied in the context of the Guarantee and

the emissions reduction requirement.

Page 46: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

46

Culture of compliance

The primary approach will be to build a culture of compliance. Minimising non-

compliance through informing, educating and engaging stakeholders is better than

enforcement action after a breach has occurred. The AER will actively educate and

engage with the market to ensure participants understand their obligations and

encourage compliance under the Guarantee. Annual reporting of compliance will also

encourage a culture of compliance.

Civil proceedings

The AER can initiate civil proceedings in the courts for alleged breaches of civil penalty

provisions of the NEL:

A court may order an injunction requiring a person to do something or desist from

doing something.

A court may order that an entity pay a financial penalty (a ‘civil penalty’) as a

result of breaching its obligations.

The existing definition of civil penalty in the NEL should be amended in order to provide

for more meaningful penalty levels to apply under the Guarantee.55 A civil penalty with

a new upper limit of $100 million will apply in the following circumstances:

Non-compliance by market customers with the emissions reduction requirement,

in exceedance of the deferral limit.

Any non-compliance by market customers with the requirement to not over-

allocate generation to their load in the registry (as discussed under Generation

and emissions allocation approach in section 4.2.1.3).

It is likely a court would take into account the circumstances and reasons surrounding

the non-compliance and other relevant factors in awarding a penalty within the upper

limit. The guidance published by the AER will outline the factors which are likely to be

taken into account when determining a civil penalty level.

Additional enforcement options

The AER, at its discretion, may seek to undertake other enforcement options in place

of or in addition to civil penalties:

Administrative undertakings are a more informal and less intrusive enforcement

option which the AER would use to resolve certain matters. The AER may be

more likely to act administratively where the effect of an actual or potential

contravention is limited, and an entity has taken (or agreed to take) appropriate

steps to end the conduct and to remedy any harm done.

55 It is likely this will need to occur irrespective of proposed changes to civil penalties currentl y being

considered by the COAG Energy Council as part of its AER Powers and Civil Penalty Regime

review.

Page 47: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

47

Infringement notices give a recipient an option of paying a penalty in full (without

there being an admission of breach) or electing to have the matter heard in court.

The existing infringement penalty for a breach of a relevant civil penalty provision

is up to $20,000. It is proposed that infringement notices of additional value are

created to provide more meaningful penalty options to apply under the Guarantee.

These could be applied to breaches of reporting requirements or other breaches

of a similar nature.

Court enforceable undertakings are written statements from an entity that it will

take specified actions (for example, entering into contracts in order to resolve a

breach), and will be used in addition or as an alternative to infringement notices.

Compliance can be enforced by the courts. The AER may use enforceable

undertakings to manage situations where market customers have clearly shown

efforts to enter into contracts or arrangements but they have not delivered as

expected. The AER may also use enforceable undertakings to require a market

customer to make up in future years for a previous failure to meet its electricity

emissions target, to help ensure that the NEM as a whole does not fall short of the

emissions reduction trajectory set by the Commonwealth Government.

4.2.1.6 Other considerations

Interaction with the Large-scale Renewable Energy Target

The Large-scale Renewable Energy Target (LRET) is designed to deliver 33,000 GWh

of large-scale renewable generation per annum by 2020, the target does not increase

beyond this. The current target operates in isolation of broader energy policy and

consequently investment has been driven without regard to the security and reliability

of the NEM. The Finkel Review found that “the Large-scale Renewable Energy Target

scheme should remain unchanged to the end of its design life, but not be extended in

its current form”.

The Guarantee brings together climate and energy policy for the first time,

consequently future investment in low emissions technology will be rewarded through

the emissions reduction requirement of the Guarantee. However, the existence of the

LRET and any participation in this scheme does not preclude this generation from also

being included in the Guarantee and contributing to achieving the emissions reduction

trajectory for the sector. Some stakeholders have argued that the LRET should be

locked to new entrants once the target is met. This would artificially inflate the price of

large-scale generation certificates and unnecessarily increase costs to customers.

The ESB supports the Finkel Review conclusion that no changes should be made to

the LRET, which is legislated to continue through to 2030. Following the

implementation of the Guarantee, the LRET should continue as legislated without

closure to new entrants as suggested by some stakeholders. All renewable generators

will contribute to achieving the emissions reduction trajectory established for the

electricity sector under the Guarantee.

Page 48: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

48

Interaction with State and Territory renewable energy targets

Some States and Territories in the NEM have renewable energy targets that imply

greater ambition out to 2030 than the proposed emissions reduction trajectory for the

Guarantee. All State and Territory renewable energy schemes can operate with the

Guarantee and contribute towards achieving the emissions reduction trajectory for the

Guarantee.

4.2.2 Reliability requirement

4.2.2.1 Overview

The reliability requirement of the Guarantee is designed to incentivise retailers and

large customers (liable entities) to support the reliability of the power system, through

their contracting and investment in resources.

If the reliability obligation is triggered, liable entities may be expected to demonstrate

future compliance by entering into qualifying contracts for ‘dispatchable’ capacity

(including demand response) to cover their share of system peak demand at the time

of the gap.

The eight high-level steps to the reliability requirement are:

1. Forecasting the reliability requirement

2. Updating the reliability requirement

3. Triggering the reliability obligation

4. Liable entities

5. Qualifying contracts

6. Procurer of last resort

7. Compliance

8. Penalties

These steps are outlined in sections 4.2.2.2 to 4.2.2.9 below, and are detailed further in

the Technical Working Papers.

Figure 4.3 below presents an overview of the timelines of the various components of

the reliability obligation. If the requirements are met, the reliability obligation will be

triggered three years out from the forecast reliability gap. Once the reliability obligation

is triggered, liable entities are put on notice that they may be required to demonstrate

future compliance.

At one year from the forecast reliability gap (T-1), if a sufficient gap persists, AEMO will

seek approval from the AER to use its safety-net procurer of last resort to access the

RERT framework to procure the required resources to close the remaining gap, and

liable entities will have to disclose their contract positions to the AER. If actual system

demand (at T) exceeds that which would be expected to occur one in every two years,

Page 49: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

49

then the AER will assess the compliance of liable entities.

Figure 4.3: Simplified timeline for various components of the reliability obligation

4.2.2.2 Step 1: Forecasting the reliability requirement

Using the Electricity Statement of Opportunities (ESOO), AEMO will forecast whether

the reliability standard is likely to be met (or not) in each NEM region over a 10-year

outlook period. If the forecast is that the reliability standard will not be met, AEMO will

identify the size of any ‘gap’ in supply/demand response.

The Guarantee is based on using unserved energy (USE) forecasts reported in the

ESOO to assess reliability in each region for the next ten years. To support liable

entities to make informed decisions, additional descriptive information will be required

to provide further context to support these USE forecasts including:

an indication of the additional capacity required to ‘close’ the gap by reducing

USE to an acceptable level

the pipeline of potential generation projects over the forecast period, along with

progress of their development

likely time of occurrence of the shortfall, such as season and time of day

duration of the expected shortfall, and

indicative examples of conditions under which USE is occurring.

Since AEMO’s ESOO forecast could form the basis of a regulatory obligation, they will

be subject to a robust and transparent process along with an annual performance

review.

Sufficient information will be made available so that the ESOO forecast is reproducible

(or close to) by an independent forecaster or reviewer.

Page 50: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

50

To provide confidence to market participants in the quality of the ESOO forecast,

AEMO will be required to assess its forecasting process against AER best practice

guidelines.

AEMO will be required to consult on its forecasting process with stakeholders

through a more formal consultation process (set out in published guidelines).

AEMO will consult with stakeholders on defining performance metrics and

consider back-casting as part of the performance monitoring. Forecast

performance will be reported and published at least on an annual basis.

AEMO will be required to publish and consult on a proposed improvement

program, and then report on it as part of the next ESOO.

AEMO will continue to work with the Reliability Panel on the appropriateness of the

current Reliability Standard in the face of an increasingly ‘peaky’ supply-demand

balance. The intention of the Guarantee is to remain aligned to the Reliability Standard

while ensuring there are adequate resources available to meet peak (as opposed to

average) demand.

4.2.2.3 Step 2: Updating the reliability requirement

The ESOO publishes expected USE forecasts to assess reliability in each region over

a 10-year outlook. As expected USE is consistent with the framing of the reliability

standard, it is proposed that this expected USE by region and year continue to form the

backbone of reliability assessment under the Guarantee.

Annual updates to the ESOO will continue unless there is a need to update forecasts

more frequently due to a material change to the supply/demand outlook. AEMO may be

required to undertake a six monthly ESOO update following a decision to trigger the

obligation, with little advance 'notice', at year T-3; that is, where there is a significant

change in ESOO outcomes from year to year.

4.2.2.4 Step 3: Triggering the reliability obligation

Calculating the materiality of the ‘gap’

The identification of a reliability gap will signal to the market the additional generation

output or demand response required over the period in question.

If AEMO has identified a reliability gap in its ESOO forecast three years out from the

period in which the gap is forecast, it will need to form a view on whether the gap is

sufficiently ‘material’ to trigger the reliability obligation of the Guarantee. If it is, AEMO

will be required to submit a request to an independent entity to trigger the reliability

obligation on retailers and large customers.

The basis for the assessment of materiality must be clearly defined and transparently

communicated to support liable entities to predict their potential liability and to close the

gap as efficiently as possible. Determining whether a reliability gap is ‘material’ requires

a balance between certainty and predictability together with flexibility to accommodate

changing market conditions. This can be achieved by the use of more objective criteria

Page 51: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

51

such as a percentage of maximum demand in a region persisting for a given period of

time.

The Rules will set out a transparent framework to allow AEMO (and the independent

entity) to determine the materiality of a reliability gap. This could be similar to that

which applies to reviews of the market reliability settings by the AEMC’s Reliability

Panel. The framework will specify:

The timing of the materiality assessment.

Prescriptive requirements which must be adhered to as part of the materiality

assessment.

A requirement that AEMO must publish a guideline, as part of the annual ESOO

development consultation process, outlining how it will determine materiality.

How a material gap, and decision to trigger the reliability obligation, is

communicated to market participants.

The reliability obligation is intended to incentivise liable entities through contracting and

investment in resources to support the reliability of the power system. If a reliability gap

is identified through the ESOO forecast, then liable entities are placed on notice that

until the gap closes they may be required to demonstrate future compliance.

The role of the independent entity

The objective of the independent entity’s assessment is to provide confidence to

stakeholders that the information and processes informing any decision to trigger the

reliability obligation is robust given concerns about relying on forecasts to determine

the required level of capacity in the market.

The role of the independent entity is to provide a check on a request by AEMO to

trigger the reliability obligation. If approval is given, the reliability obligation is triggered.

The independent entity will require technical capability to check AEMO’s assessment

as to whether there is a material reliability gap, must be impartial and not affected by

the outcome of the decision, and have clear and express powers to trigger the reliability

obligation.

The AER will be assigned the role as the independent entity, as expected functions of

this role align with the AER’s existing energy market regulation remit. The AER will

need to develop technical capabilities to fulfil this function and will be tasked with

determining whether to accept a recommendation from AEMO to trigger the reliability

obligation.

The AER as the independent entity should follow a transparent and efficient process,

set out in a guideline, to give stakeholders confidence that the decision to trigger the

reliability obligation is justified.

To implement the preferred ‘light touch’ approach, the AER may develop appropriate

procedural check points with AEMO. This may include annual checks on AEMO’s

adherence to Consultation Procedures, regular forecast performance monitoring and

Page 52: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

52

reporting on definitions and measures used, assumptions, modelling and analytical

approaches to estimating reliability gaps.

4.2.2.5 Step 4: Liable entities

The reliability requirement is designed to provide sufficient incentives for liable entities

to support the reliability of the system to prevent gaps in reliability emerging.

Retailers, in aggregate, should be willing to help manage the long-term reliability of the

power system on behalf of their residential and small-to-medium enterprise customers

because they are confident in their future demand for electricity.

The high-level design also noted the benefit of including large customers along with

retailers as liable entities. As acknowledged by some stakeholders, there is a range of

very large customers in the NEM whose future demand for electricity is unknown and is

unknowable to retailers. Without a long-term contract from these customers, retailers

(in aggregate) may be unwilling to help support the long-term reliability of the power

system on behalf of these customers without charging a significant risk premium.

Further, if the reliability obligation is placed only on retailers (on behalf of all their

customers) then the majority of the obligation to purchase contracts will be with a

concentrated number of market participants making it more difficult for smaller retailers

to compete, negatively impacting the affordability of electricity.

Giving large customers the choice to contribute to the reliability of the power system

directly, or to contract with a retailer, should ensure that the reliability requirement is

managed at least cost.

All retailers (large and small) will then be able to compete to manage the reliability

requirement on behalf of large customers. This should have significant benefits for

competition in the electricity market.

However, some large customers have suggested that this additional optionality would

negatively – rather than positively – impact upon them. Further consideration will be

given to the treatment of large customers under the reliability obligation prior to

completing the final detailed design of the Guarantee.

It is currently proposed that the Guarantee will set a threshold size of 5 MW peak

demand at a single site for large customers to be deemed liable entities under the

reliability requirement. This threshold includes an estimated 100 sites with total load of

36 TWh or 20 per cent of annual consumption in the NEM.

A large customer’s peak demand will be determined by historical load

performance, covering a period of at least 12 months to ensure the liability is

based on an accurate reflection of their operational demand profile. The entity

that has entered into the supply contract will be deemed liable.

New entrants – for example, entities commencing operations during the

compliance year – will be required to take steps to secure contracts or enter an

agreement with a retailer to manage their obligation for load over the forecast

gap period. Compliance with this requirement would be demonstrated by the

new entrant through it reporting relevant actions to the AER.

Page 53: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

53

The ESB considers that the administrative burden involved in identifying relevant sites

and associated customers will not be excessive.

If the reliability obligation is triggered, then all liable entities that have not transferred

their obligation to a retailer will need to assess their likely share of system peak

demand and secure sufficient qualifying contracts to cover this. The existing contracts

of liable entities that are large customers, will be considered qualifying contracts (up to

the load covered by the contracts in place).

Liable entities will need to cover their share of the level of system peak demand which

would be expected to occur one in every two years. This requirement should provide a

safe harbour within the reliability obligation which helps prevent excessive costs being

incurred by over-contracting.

Customers falling below the 5 MW threshold will be provided the flexibility to ‘opt-in’ to

manage their own reliability obligation if they believe they can do so better, and at a

lower cost, than a retailer. For example, a corporate entity with a large load spread

over a number of sites may consider self-management of their load to support a more

cost-efficient outcome.

As a further safe harbour to promote competition and avoid disincentives to take on

additional commercial and industrial customers below the 5 MW threshold, under

specific circumstances, liable entities will be able to adjust their contract position within

the compliance year. This will allow liable entities to account for a specified material

change in circumstances; such as where a retailer has taken on additional large

commercial and industrial customers that are below the 5 MW threshold. However, to

ensure the objectives of the reliability requirement to promote efficient contracting are

maintained, retailers will not be able to adjust their T-1 contract position where they

take on new customer sites above the 5 MW threshold.

4.2.2.6 Step 5: Qualifying contracts

If the reliability obligation is triggered, liable entities will be required to enter into

sufficient qualifying contracts to cover their share of system peak demand at the time of

the reliability ‘gap’ to meet possible future compliance.

Qualification framework

Two approaches were considered in defining qualifying contracts: prescriptive; and

high level framework. Given that the key factor was to provide a financial incentive to

make available sufficient resources to close any gap, it is considered that any

wholesale contract with direct links to the electricity market which a liable entity uses to

reduce exposure to high spot prices should qualify, rather than being prescriptive about

the specific types of contracts that can be used.

In other words, the qualification framework with the reliability obligation will be based

on the principle that physical capacity follows the financial instruments used to hedge

Page 54: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

54

physical market risk.56 Further, rather than require liable entities to provide all their

contracts to the AER at T-1, if a sufficient gap persists:

Liable entities will be required to aggregate all qualifying contracts which have

been bought and sold in the relevant region over the period of the gap and

submit their net contract position to the AER.

Liable entities will be required to ensure that the net position submitted has

been appropriately adjusted for the ‘firmness’ of contracts used for compliance

i.e. they will need to ensure that each contract is assigned an appropriate

‘firmness factor’, similar to the ‘delta’ used for risk measurement in financial

markets.

This firmness will be approximated by a ‘firmness factor’ which will consider

contract characteristics such as strike price, likelihood of cover over the period

of the gap, and volatility.

To provide assurance to the AER that liable entities have adopted a reasonable and

widely accepted approach to measuring the firmness of different instruments, they will

be required to submit an independent auditor’s report confirming the appropriateness of

the methodology adopted.

To help manage significant stakeholder concerns about the liquidity and transparency

of contract markets and the level of concentration in the electricity market, the ESB

considered five options as follows:

1. Centrally cleared contracts only would qualify.

2. Contracts recorded in trade repositories would qualify, with appropriate

reporting developed to facilitate transparency.

3. Large, vertically integrated retailers are covered by a ‘Market Liquidity

Obligation’ when the gap is triggered.57

4. A combination of options 1 and 2.

5. A combination of options 2 and 3.

Centrally Cleared Contracts

Centrally cleared contracts are contracts that are traded and centrally cleared on an

exchange (e.g. ASX Trade24 for derivatives including wholesale electricity contracts).

To promote liquidity these contracts are standardised in their design. For example, the

ASX currently lists $300 caps in each region in the NEM (other than Tasmania) but not

caps for other strike prices. To mitigate default risk these markets are managed

through a central counterparty, backed by a diverse range of financial institutions and

underpinned by a prudential and margining framework that is a party to all trades (i.e.

56 Submissions to the Department of the Treasury’s “Implementation of a framework for Australia’s

G20 over-the-counter derivatives commitments” highlighted the largely physical nature of electricity

contract markets that are primarily used to hedge physical market risk rather than for speculation.

57 All contracts and physical generation would qualify subject to the firmness test except when

combined with option 2 where contracts must be reported in a trade repository.

Page 55: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

55

they become the buyer to every seller and the seller to every buyer.)

A centrally cleared only approach would be likely to enhance transparency and liquidity

as all positions would need to be traded through the market. However, the risks to this

approach are:

Limiting flexibility through use of only standardised contracts;

Reducing innovation as new product development is hindered;

Increased prudential, margining and transaction costs that could

disproportionately harm smaller participants;

Creating an illusion of liquidity while volumes can continue to be traded through

off-market trading mechanisms (Block Trades and ‘Exchange for Physical’).

Trade Repositories

Trade repositories are entities that centrally collect records of Over the Counter (OTC)

derivatives in a number of sectors. Under current ASIC requirements, the choice of

trade repository is up to the participant in the relevant market, with data stored

accessible only by ASIC for the purposes of monitoring the risks of financial contagion.

To enhance transparency in the event that the reliability requirement is triggered, a

regulator would need to access the repository data and then publish this in some form.

This would need to reflect privacy and competition concerns, which may involve the

cleansing and aggregation of data before publishing.

The use of trade repositories in the NEM has been limited as electricity derivative

reporting requirements are currently exempt. An intermittent trade repository

requirement that was aligned to the triggering of the reliability obligation would be

challenging due to lead times and set up costs for integrating systems and processes

with a repository. A key benefit of allowing trade repositories over a centrally cleared

only approach is the ability to support flexible, innovative and bespoke contracting.

While a trade repository and reporting approach could increase the transparency of

internal transfers at vertically integrated entities, the flexibility that trade repositories

provide and the opportunity this creates for bespoke contracting may undermine these

potential benefits.

Beyond the benefit of capturing internal transfers of vertically integrated entities, a

further opportunity for increased transparency can be delivered through the capturing

of relatively opaque ‘OTC’ contract markets. In 2014-15, the Australian Financial

Markets Report (AFMR)58 produced by the Australian Financial Markets Association

identified that approximately 16 per cent of surveyed electricity derivative volumes were

traded ‘OTC’, with the balance traded on centralised exchanges. While the AFMR

ceased surveying the electricity market in 2014-15, anecdotally the percentage of

‘OTC’ volumes traded has not increased.

58 Australian Financial Markets Association, https://afma.com.au/data/AFMR

Page 56: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

56

Market Liquidity Obligation

A key concern raised by stakeholders is that trade repositories on their own may not

support liquidity. An important element in ensuring that the Guarantee does not

negatively affect liable large customers and small retailers is through a safety net

mechanism that provides liable entities with the confidence of being able to access

contracts when they need them. Given the challenges identified with a centrally cleared

only approach, the ESB is considering the benefits of an alternative mechanism called

a Market Liquidity Obligation.

The Market Liquidity Obligation would require large vertically integrated retailers to

make contracts available, for the period of the gap, on a centrally cleared platform.59

This would manage stakeholder concerns about access to contracts in the event that

the reliability obligation had been triggered. Obligated participants would be determined

based on a size threshold (ownership of a percentage share of generation) in a given

region and would need to involve more than one party in each region. Obligated

participants would be required to post bid and offer spreads for the quarterly flat and

peak swap products in the region over the quarter corresponding to the gap period.

Maximum bid-offer spreads would apply to both products, however pricing beyond this

would be at the discretion of the obligated parties.

Energy Security Board recommended approach

The ESB’s draft preferred approach is to adopt option 5 that combines the Market

Liquidity Obligation with a trade repository and reporting requirement. Qualifying

contracts would need to be either centrally cleared or reported in a trade repository;

including where vertically integrated retailers wanted to use their own generation.

Option 5 is preferred because this approach is most likely to ensure that if the reliability

requirement were triggered that it would not be detrimental to liquidity, transparency

and competition.

A key question for the ESB in finalising the detailed design of the Guarantee is whether

the benefits of implementing the trade repository requirement would warrant the costs

incurred by industry.

Voluntary ‘book-build’

In the high-level design the ESB agreed to further develop a voluntary book-build

approach to facilitate competitive market outcomes and provide liable entities with

additional optionality to traditional contracting processes in meeting their obligations

under the reliability obligation. Given the preferred approach is to implement a Market

Liquidity Obligation further consideration by the ESB will be made finalising the detailed

design on whether the voluntary book-build is required. The ESB invites feedback from

industry on the benefits and costs of a voluntary book-build.

If implemented in the final design, the primary benefit of the mechanism will be to

provide an opportunity for liable entities to secure contracts which are underpinned by

the prospect of physical resources. It will additionally provide contracting options to

assist liable entities – in particular, small retailers and large customers – to lock in

59 Further consideration is needed on how this requirement would apply to the Tasmanian region.

Page 57: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

57

qualifying contracts in the event that the market is not sufficiently liquid. Contracts

delivered through the book-build will qualify for compliance under the reliability

obligation.

If the reliability obligation is triggered, AEMO will invite interested parties to lodge an

expression of interest to participate in the ‘book-build’. The ‘book-build’ will be

conducted by inviting sellers to make offers to sell new contracts for the duration of the

gap and for buyers to make offers to buy new contracts. AEMO will aim to match

buyers and sellers in a way that delivers the maximum closure of the gap. AEMO will

not take on any financial exposure or credit risk, with all risks to be borne by the

participants.

The book-build process will be run by AEMO three years out from a forecast gap if the

reliability obligation has been triggered. If a reliability gap continues to persist then

AEMO will have the option to re-run the book-build again two years before the reliability

gap is forecast to occur.

If implemented, AEMO would be required to consult with industry and other

stakeholders to develop a set of guidelines and procedures outlining how it will conduct

the book-build process.

Demand response contracts

The development of demand response products that qualify under the reliability

obligation will be central to ensuring the reliability requirement of the Guarantee is met

at least-cost. Products will qualify provided they meet the same criteria as other

financial instruments, that is, it must have a direct link to the electricity market which a

liable entity used to manage exposure to high spot prices. The demand response will

have to be ‘in-market’, meaning it is not eligible to be contracted by AEMO through the

Procurer of Last Resort, and allocated to a liable entity and a supply region.

In addition, to provide AEMO visibility of demand response in its forecasting processes

and support compliance, demand response contracts will need to be registered with

AEMO via its Demand Side Participation Portal. To avoid under or over-counting, rules

will apply to the treatment of relevant load as part of the reliability obligation’s

compliance and penalties regime (see steps 7 and 8 below).

4.2.2.7 Step 6: Procurer of Last Resort

The Procurer of Last Resort is the ‘safety net’ for the reliability obligation. If the

reliability obligation has been triggered and a sufficient reliability gap persists one year

out the AER will activate the requirement for retailers to provide details of qualifying

contracts.

Concurrently, AEMO will be able to commence procurement of resources through the

RERT framework to address the remaining gap.

Any resources procured via the RERT framework will be for supply ‘outside of the

market’ to avoid distorting the operation of the electricity market.

AEMO will work with relevant state governments and other market bodies on an

ongoing basis to ensure the nature of any reliability ‘gap’ is well understood along with

Page 58: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

58

the pipeline of potential projects to resolve the reliability ‘gap’. If, at any time, AEMO

and/or a relevant state government feel that the specific circumstances in a particular

jurisdiction dictate that prudent action is required to ensure the ongoing reliability of the

electricity system, then either AEMO or the relevant state government can make a rule

change request that would be processed via a six week, expedited process. The rule

change could enable AEMO to commence its Procurer of Last Resort function earlier

than one year before the forecast reliability gap given the extenuating circumstances in

that jurisdiction at that time. It is not the intention of the Guarantee for AEMO to

become the default procurer of capacity for the NEM.

4.2.2.8 Step 7: Compliance

If AEMO identifies a ‘material’ gap in capacity three years in the future through the

publication of the ESOO, it will make a request to the AER to trigger the reliability

obligation. As the independent entity, the AER reviews AEMO’s request to trigger the

reliability obligation, and if consistent with an assessment framework, the request is

approved.

If the gap persists in one or more NEM regions one year out, retailers and liable entities

in the affected regions will be required to submit their contract position to the AER to

demonstrate they have sufficient enduring qualifying contracts over the gap period.

Following the compliance period, if AEMO has procured additional resources and peak

demand actually exceeds the one in two year forecast threshold, the AER will assess

the contract positions submitted by liable entities and confirm if the level of contract

coverage was adequate to meet their obligation.

The AER will use data for each trading interval in a region in which demand exceeded

the one in two year forecast to determine each liable entity’s share of demand in that

interval. It will then compare liable entities’ contract positions with their share of

demand in that interval, scaled back to the one in two year forecast consistent with the

‘safe harbour’ provision that contracts should only be required to meet the one in two

year forecast. The calculation of each liable entity’s actual demand will be determined

by the AER based on metering data provided by AEMO.

The ‘compliance period’ will be a set of trading intervals – whether multiple trading

intervals in a day or intervals over multiple days – across the reliability gap period in a

region in which regional demand exceeded the one in two year forecast. The AER will

assess all intervals where demand exceeds the forecast threshold.

Where liable entities are under-contracted in one or more trading intervals, the AER will

calculate the shortfall across the relevant compliance period. This shortfall will be used

to determine and assign penalties for non-compliance (see below).

Liable entities will be able to adjust their contract position within the compliance year to

account for a specified material change in circumstances; such as where a retailer has

taken on additional large commercial and industrial customers that are below the 5 MW

threshold.

Page 59: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

59

The details of the compliance framework will be further developed in consultation with

stakeholders and will provide guidance on the types of information that will need to be

reported to the regulator and the form in which that information is to be reported.

4.2.2.9 Step 8: Penalties

Penalties will be assigned to retailers that are assessed to have fallen short of their

reliability obligation. These penalties will include at least some of the cost of procuring

necessary resources via the procurer of last resort function.

A two-stage approach to compliance and assignment of penalties will be undertaken:

The first stage of the penalty framework for the reliability obligation will allocate

costs to liable entities which have failed to meet their contractual obligations. A

liable entity found to be non-compliant will be charged a predetermined

proportionate cost per MW of non-compliance to refund a proportionate cost of

the Procurer of Last Resort costs to consumers.

In the second stage, the AER will retain its ability to apply its usual suite of

enforcement options in addition to the assignment of RERT costs in stage one.

These enforcement options would likely only be used for more significant or

repeated failures to comply with the reliability obligation. They comprise

administrative undertakings, enforceable undertakings and civil proceedings,

including issue of financial penalties.

The definition of civil penalty in the NEL will be amended to provide a

meaningful upper limit on the financial penalties which can be assigned for non-

compliance under the reliability obligation. Similar to rebidding civil penalty

provisions, the ESB considers up to $1 million would be an appropriate upper

limit on first offences, with up to $10 million the upper limit on repeat offences.

The contracted load of liable entities may undergo a material change that was

reasonably beyond their control, following submission of their contract position to the

AER one year ahead of a forecast gap (e.g. taking on additional large customers that

fall below the 5 MW threshold). To accommodate such circumstances, liable entities

will be able to apply to the AER for an amendment to their contract position.

4.3 Physically Backed Contracts

The National Energy Guarantee Draft Design Consultation Paper released in February

2018 envisaged the potential for ‘physical backing’ of certain types of contracts. This

approach would involve linking contracts to the physical plant or portfolio of plants that

generate the MWh under the contract.

In relation to the reliability obligation, the link between contracts and physical backing

(to be confident that reliability would be achieved) was stressed. The Draft Design

Consultation Paper stated:

“The degree to which a contract is physically backed will provide assurance that the

reliability requirement will promote investment and provide incentives for the

Page 60: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

60

continued operation of physical assets. There are four ways that can be

considered:

Certain types of financial contracts will be considered to be eligible contracts

Financial contracts that are ‘certified’ as being reconciled back to a physical

source

Contracts will need to demonstrate that the generation or demand response,

the subject of the contract itself, was sourced from a dispatchable generator or

user

Physical ownership of generation assets as part of an integrated retail and

generation portfolio.

..[In relation to determining the extent of physical backing] there could be a

certification of financial contracts. This would have the benefit that for compliance

purposes, the contract can uniquely be identified with a particular physical

generator i.e. there is a stronger link between the financial contract and the physical

asset … which will reduce the risk of double counting. For example, OTC contracts

specify a buyer and a seller so can be used to identify the source, but because they

are financially settled can be sold multiple times against the same physical

generator. For example, a 500 MW generator could sell 500 MW of caps to one

retailer, buy 500 MW of caps from a generator, and then sell 500 MW of caps to a

second retailer. The reliability requirement needs to avoid double counting so there

needs to be a mechanism to tie the retailer contract to the physical capacity

available.

This could be achieved through allowing financial contracts to be certified against

installed physical capacity. In this example, only 500 MW can be certified so the

two retailer contracts would need to be either scaled to match the total, or the

contracts varied so that only one retailer could certify its contract. Under this

approach, only OTC swaps, caps and PPAs would be eligible to be certified, and

may lead different classes of contract under each category. Contracts which do not

specify sources such as futures or that are contingent on exercise such as options

would not qualify for certification unless a mechanism could be established to link

futures volumes to the physical backing. This could, however, have the impact of

limiting liquidity in the financial markets which would be counter to the objectives of

the Guarantee60.”

In relation to the emissions reduction requirement, contracts would be assigned an

emissions value based on their source. This approach would effectively tie the

contracts transacted to meet the reliability requirement to the emissions obligation.

Each contract would be assigned a value based on actual intensity, or a calculated

approach, that would result in liable entities ’ emissions intensity representing the

combination of contracts in their portfolio. The Draft Consultation Paper stated:

60 Energy Security Board, National Energy Guarantee Draft Design Consultation Paper,

February 2018, pages 37 - 38

Page 61: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

61

“Retailers would report contracts of their choosing to demonstrate compliance with

the emissions requirement. These contracts could, but need not, specify the

generation source or emissions per MWh. Broadly speaking, the following three

types of contracts could be used by retailers to achieve compliance with the

emissions requirement.

1. Contracts that specify a generation source, which allows the emissions per

MWh to be directly determined. An example of such a contract is a power-

purchase agreement sold by a wind farm (with zero emissions).

2. Contracts that specify the emissions per MWh but do not specify a generation

source. While such contracts do not currently exist, the design of the emissions

requirement needs to allow for possible innovation in contract markets. An

example of such a contract in future could be an existing exchange-traded

contract with an emissions per MWh specification.

3. Contracts that do not specify either the emissions per MWh or a generation

source. Examples include existing exchange-traded and OTC swaps and

caps61.”

In relation to contracts that specify emissions per MWh but not a generation source, the

Draft Consultation Document suggested that contracts could be developed that specify

the emissions level for each MWh of electricity but are not linked to one specific

generation source. Examples of such contracts could include those that pool together

several generators with similar emissions within a region. They could also take the form

of a ‘stapled security’, where a specified amount of emissions per MWh is ‘stapled’ to

those types of contracts currently in existence (such as OTC or Australian Securities

Exchange-traded swaps).

In relation to contracts that specify neither an emissions intensity nor a generation

source, the Draft Consultation Paper suggested that a deemed emissions level could

be assigned to particular types of contract (such as ASX-listed swaps) sold in a region.

This could be based on the average emissions intensity of generators that sold that

type of contract, or, alternatively, all types of contracts sold in a particular region could

be deemed to have the same emissions level.

From a reliability perspective the benefit of a physically-backed approach is that it

would provide more assurance that the required investment needed to cover the gap is

actually occurring. However, this approach would potentially necessitate a fundamental

change not only to the contract market, but potentially to other aspects of the current

reliability framework, imposing significant costs on participants, reducing liquidity and

the fungibility of contracts. For example, the Australian Financial Markets Association

stated:

“… [T]he consultation paper appears to suggest that the electricity derivative

financial market should move to a more physical-backed version, rather than a

primarily financial one. AFMA believes that any shift in contracting markets from

financial to physically-backed would be detrimental to financial market

61 Energy Security Board, National Energy Guarantee Draft Design Consultation Paper,

February 2018, pages 16

Page 62: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

62

efficiency, liquidity and price transparency, as contracts would be less

homogenous, and priced on a case-by-case basis.”

A physically backed contract market also has the potential to exacerbate existing

market structure issues, and considerable concerns about the competitiveness of retail

markets.

Some stakeholders pointed out that purely financial contracts already created strong

incentives for physical output, and so should be eligible contracts in their own right. For

example, AGL argued:

“… [W]e consider that investments in capacity should be made through the

existing financial incentives that participants have in the energy market to avoid

exposure to high prices at times of tight demand. We therefore strongly support

an approach that allows purely financial caps and swaps to be considered

qualifying instruments, as well as any new contractual forms that may emerge

which can be may be physically defended or backed, as well as physical

ownership of assets and specific physically backed contracts.”

From the emissions perspective, stakeholder feedback overwhelmingly suggested that

there were serious risks to the liquidity of existing contract markets if retailers were

required to tie their financial contracts to the physical supply of electricity and the

emissions associated with that supply. For example, the Australian Financial Markets

Association suggested that:

“AFMA believes that this suggestion [of a contract that specifies the emissions

per MWh but does not specify a generation source] may be problematic, as it

may detract from liquidity in the current market. This type of contract could

introduce a bespoke condition (emission) into the contract, and would mean

that the product would be non-homogenous and illiquid. It could also be

detrimental to the overall liquidity and depth of the electricity financial markets,

to the extent that it may take away liquidity from the standard contract markets,

both exchange traded and over the counter. In addition, depending on design,

there may be difficulties in determining an appropriate reference rate for

valuation and settlement, and difficulties in contractual arrangements under

standard ISDA (International Swaps and Derivatives Association)

documentation.”

Other stakeholders questioned the ‘fit’ between financial contracts and emissions

accounting. For example, Origin argued:

“It is not appropriate to seek to ascribe some level of emissions intensity to financial contracts. These contracts were never intended to be used in this manner and it is impractical to do so.”

A further challenge in implementing ‘physical backing’ of contracts relates to the

significant layer of administration for the liable entities and the AER in tagging and

validating the linkage on all contracts that were put forward as qualifying to meet the

reliability requirement.

Page 63: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

63

Table 4.1: Differences between the Guarantee and physically backed contracts

THE GUARANTEE PHYSICALLY BACKED CONTRACTS

Emissions

contract

requirements

A liable entity can demonstrate its right

for generation to be assigned to it

based on any contractual arrangement

they have with a counter party.

The two parties must agree to the

generation assignment in the

emissions registry.

A liable entity must have a contract

with a generator, such as a power

purchase agreement or exchange

traded/over the counter swaps and

caps. Swaps and caps used for

compliance in the emissions reduction

requirement must link to physical

output and emissions.

The two parties must agree to the

generation assignment in the

emissions registry.

Reliability

contract

requirement

If the reliability requirement is

triggered, a liable entity may be

required to demonstrate future

compliance by having sufficient

qualifying contracts to cover their share

of system peak demand at the time of

the reliability gap.

Qualifying contacts (including demand

response) are contracts, such as cap

and swap contracts, with direct links to

the electricity market that expose

contract sellers to high prices . These

do not have to be linked to a specific

generator, preserving liquidity and

competitive outcomes.

If the reliability requirement is

triggered, a liable entity must enter into

sufficient contracts that are physically

linked to dispatchable generators to

cover their share of system peak

demand at the time of the reliability

gap.

Existing standardised contract

products (such as ASX futures and

$300/MWh caps) would need to be

modified to specify the generator the

contract is linked

Registry alternatives

The ESB has considered options for the Guarantee's various components.

Fundamental to a scheme such as the Guarantee is tracking how generator emissions

are allocated to market customers. In the ESB's view a registry is the only practical way

to do this. A registry simplifies functions like reallocating between parties and

distributing any unallocated generation to uncontracted load. It also makes it easy to

enforce scheme rules like market customer load must equal generation and generation

load can't be over allocated.

An alternative is a risk-based approach to compliance, as used by the CER to

administer the Commonwealth Government’s Emissions Reduction Fund. This

approach would rely on market customers stating their emissions intensity and

providing a summary of their contract positions at the time of reporting. A risk

assessment framework would be used to identify market customers most at risk of non-

compliance and these customers would be a priority for auditing. An audit (by the AER

Page 64: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

64

or an auditor contracted by the AER) would include reviewing a market customer’s

contracts to confirm their contractual position supports their stated emissions intensity.

Only a proportion of market customers would be audited in any one year but over a

number of years all would be audited.

This approach has the potential to reduce the administrative burden for market

participants, though it would likely increase the burden for the AER. For example, a

market customer would not have to verify every reallocation they’re involved with in the

registry. However, such an approach is impractical when it is central to the scheme's

integrity that every MWh dispatched in the NEM is accounted for. Further, large market

customers may have hundreds of contracts, making an audit time consuming and

expensive and limiting the number of audits a regulator could undertake.

The ESB considers there are no viable alternatives to a registry, and so the two options

in this RIS differ only in their contract requirements.

Page 65: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

65

5 Impact Analysis

This section considers the costs and benefits of the two options being considered.

The ESB is seeking feedback on whether interested parties agree with the impacts

described in the following impact analysis.

The estimates of BAU trends and impacts of the Guarantee are drawn from modelling

by Frontier Economics used by the ESB in its November 2017 advice to the

Commonwealth Government. This modelling is not a forecast of the future but rather an

indication of what outcomes could be expected using reasonable assumptions. It is

important to note the model's sensitivity to assumptions such as technology costs, fuel

prices and generator retirements, discussed later in this section.

5.1 Business as usual

As outlined in the problem section, a continuation of the business as usual will not

achieve the COAG Energy Council's dual objective of meeting the Commonwealth

Government's emission reduction target while maintaining the reliability of the electricity

market.

Reliability

As shown in Table 5.1, renewable generation as a proportion of total generation under

business as usual was estimated to increase from 26 per cent in 2020 to 31 per cent in

2030. Intermittent renewable generation is estimated to increase from 18 per cent of

total generation in 2020 to 24 per cent in 2030. At the same time the proportion of

dispatchable renewable energy generation is estimated to remain constant.

Table 5.1: BAU Renewable generation output (% of total): 2020, 2025 and 2030

Type of renewable generation 2020 2025 2030

All 26% 29% 31%

Intermittent renewable 18% 21% 24% Dispatchable renewable 8% 8% 8%

Source: Frontier Economics

Table 5.2: BAU Output mix (% of total generation): 2020 and 2030

Year Dispatchable generation Intermittent generation

2020 81%* 18%* 2030 77%* 24%*

* Note: Does not add to 100 per cent due to rounding. Source: Frontier Economics

Emissions target

Under the BAU, renewable generation is estimated to increase from 26 per cent of total

generation to 31 per cent between 2020 and 2030.

As shown in Figure 5.1, by the end of 2030, CO2-e emissions will be 7.6 per cent above

the assumed Paris target if there were no change to current policy settings.

Page 66: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

66

Figure 5.1: Annual Emissions under Business as Usual compared to assumed Paris Target

Source: Frontier Economics

NEM-wide wholesale prices are currently higher than historical levels, reflecting the

absence of new investment in dispatchable generation, and the withdrawals of

Northern and Hazelwood. Wholesale prices were estimated to fall from 2018 to 2022

due to the committed entry of almost 6,000 MW of renewable capacity across the NEM.

Wholesale prices are estimated to increase in 2022 as the assumed retirement of

Liddell power station reduces supply (see Figure 5.2).

As demand rises over time and there is a greater need for new investment, the impact

of a risk premium due to policy uncertainty also contributes to higher prices under BAU.

Page 67: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

67

Figure 5.2: Historic NEM weighted prices in comparison to BAU case

Source: Frontier Economics

Business as usual regulatory burden

The electricity sector is highly regulated and has a number of compliance requirements

that intersect with the emissions requirement and the reliability requirement. These

include:

NEM spot market participants – Market customers and generators generally

trade in the spot market 24/7. They must meet AEMO's prudential and system

requirements and manage AEMO's market settlement process.

Generator regulation – Apart from trading in the spot market, generators must

comply with various technical and reporting requirements and follow electricity

dispatch instructions from AEMO.

Retailer regulation - Apart from trading in the spot market, retailers have a

range of regulatory and reporting obligations to consumers and the AER.

NGER reporting – Each year generators/facilities must determine their

emissions according to NGER requirements and report their emissions to the

CER.

RET compliance – Retailers must meet their annual LRET and SRES

compliance targets.

These requirements would be unaffected if the Guarantee were implemented.

Page 68: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

68

5.2 National Energy Guarantee

The Guarantee is designed to incentivise retailers and large market customers, through

contracting and investment:

to support the power system's reliability

to ensure the average emissions intensity of the electricity they sell to

consumers supports Australia's international emissions reduction commitments

The impacts of the Guarantee were initially modelled by the ESB and published in

November 201762. As some elements of the Guarantee have changed slightly since

the November paper was published, the analysis might not completely represent the

Guarantee’s full impacts. However, it is presented to give stakeholders an indication of

the relative magnitude of the likely impacts and the relative performance of the

Guarantee compared with BAU. It is these relativities, rather than actual modelled

outcomes, that provide the most valuable insights.

The November modelling of the wholesale electricity market provides an indication of

how wholesale prices, retail bills, emissions levels, and generator investment,

retirement and output may change with the implementation of the Guarantee, relative

to business-as-usual (BAU).

Modelling assumptions

For the purposes of modelling, the NEM's emissions budget is assumed to be

consistent with the Commonwealth Government’s stated 2030 emissions reduction

target. The emissions budget is the maximum aggregate emissions that could come

from the NEM and meet the NEM's share of Australia's emissions reduction target. This

has been translated to 1,352Mt CO2-e of emissions for the period 2021 to 2030, as

determined by the Commonwealth Department of Environment and Energy.

In the model, the emissions requirement increases financial contracting with low-

emissions generators, providing both certainty for low-emissions generation investment

and their cash flows to make that investment viable.

The Guarantee also requires market customers to contract for a certain level of

dispatchable generation in the NEM. This can include either thermal generation, or

dispatchable renewable generation such as solar thermal with storage or hydro.

Generators typically do not commit all of their capacity under a firm contract, to account

for the physical constraints of their plant. These constraints include the potential for

outages at higher plant operating levels and fuel constraints. In addition, market

customers’ demand for contracts also influences the extent to which a generator’s

capacity is contracted.

62 Energy Security Board Advice – The National Energy Guarantee 20 November 2017 -

http://www.coagenergycouncil.gov.au/sites/prod.energycouncil/files/publications/documents/Report

%20on%20the%20National%20Energy%20Guarantee.pdf.

Page 69: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

69

If the Guarantee’s reliability requirement is triggered, market customers are required to

contract a pre-determined proportion of their forecast load, and some market

customers may consequently need to increase the extent of their contracting. To the

extent that this higher demand for contracts is met from existing capacity, this will

increase the proportion of generation capacity contracted (and reduce the proportion

uncontracted). This is likely to lead to more competitive bidding in the spot market as

generators will bid lower to increase their chances of being dispatched in order to cover

their contracted capacity. This is likely to result in lower spot prices.

Lower spot prices may be partly offset by higher contract prices due to increased

contract demand, but this may, in turn, be offset by the lower risk faced by generators

from being able to contract more of their capacity.63

If the higher demand for contracts was not able to be met by existing resources due to

their physical constraints, the demand would be met from new entrants, which

improves system reliability and reduces the likelihood of extreme spot price events (i.e.

lowers volatility).

5.2.1 Price impacts

5.2.1.1 Wholesale price impacts

The Guarantee’s impact on prices is evaluated for both wholesale and retail prices.

Wholesale prices provide an investment signal for new generation or for retirement of

existing generation, while consumer impacts are best understood through analysis of

retail bills.

Figure 5.3 reveals NEM-wide wholesale prices are currently higher than historical

levels. This reflects a policy uncertainty-induced freeze in new entrant plant, outside of

subsidised renewable generation, withdrawals of Northern and Hazelwood and

increases in coal and gas prices. The steep decline in wholesale prices under both

BAU and Guarantee from 2018 to 2022 is due to the committed entry of almost 6,000

MW of renewable capacity across the NEM.64

This generation is already planned and so is not specifically incentivised by the

Guarantee. This price decline is also reflected in the price of baseload futures

contracts.65

Initially, the introduction of the reliability requirement leads to more competitive bidding

from coal and gas, which reduces prices in the Guarantee somewhat compared with

BAU. This difference in bidding has a minimal impact on price differences in 2021-22

as the market becomes oversupplied. In an oversupplied market, higher contracting

63 Contracting reduces the volatility of generators’ revenues, which lowers generators’ financing costs

and improves their ability to obtain adequate fuel supply contracts at a lower price compared to

remaining uncontracted.

64 The amount of committed generation is based on market data and Frontier Economics own

analysis, and includes projects under construction, financially closed, or and already committed

under the Snowy Hydro expansion, RET, VRET (650MW) and QRET (400MW). Only 460MW of the

7,700MW of committed generation is not being built under one of those three schemes.

65 Price of ASX-traded calendar-year baseload futures contracts, from https://www.asxenergy.com.au

Page 70: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

70

levels and more competitive bidding has less impact on prices as an oversupplied

market is already more competitive than a market with a tight demand/supply balance.

Figure 5.3: NEM weighted-average wholesale prices (incl. RET certificate costs)

Source: Frontier Economics

Beyond 2022, the assumed retirement of Liddell power station reduces supply once

again. This results in a sharper increase in prices in the BAU case than the Guarantee,

as bidding from existing dispatchable plant is more competitive under the Guarantee.

This price jump is similar to recent price increases following the withdrawal of Northern

and Hazelwood (see Figure 5.4), which leads to a much tighter supply/demand

balance. This is less severe in the modelling which assumes perfect foresight and

immediate replacement of retiring capacity with new entrant; this result may be more

severe in reality for the BAU case if new investment involves a lag.

Page 71: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

71

Figure 5.4: Historic NEM prices in comparison to BAU and Guarantee case

Source: Frontier Economics

As demand rises over time and there is a greater need for new investment, the impact

of a risk premium due to policy uncertainty also contributes to higher prices under BAU

compared to prices under the Guarantee.

Furthermore, to the extent the demand for contracts is met by supply of contracts from

new entrants, rather than from contracting existing uncontracted capacity, this provides

an additional constraint on a generator’s ability to set higher market prices.

5.2.1.2 Retail bill impacts

Retail bill estimates under both the Guarantee and BAU were developed from the

AEMC's Residential Electricity Price Trends 2017, which estimates bills for residential

consumers from financial year 2016 to financial year 2019.

Figure 5.5 shows the modelled range of average NEM-wide residential consumers’

annual bills under the BAU and Guarantee in 2020 and 2030. This is compared to the

annual expected bill in 2017. A retail customer’s bill is comprised of network, retail and

wholesale costs and the cost of other environmental schemes. Only the wholesale

component is modelled and network charges are estimated based on the information

available at the time of modelling. The average bill saving from implementing the

Guarantee policy, compared to the do-nothing scenario, is around $120 a year (in 2017

dollars) for the 2020 to 2030 period.

Page 72: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

72

Figure 5.5: Breakdown of retail bills in 2020 and 2030, NEM

Sources: AEMC; Frontier Economics

Furthermore, annual bills are consistently lower under the Guarantee than current bills,

over the 2020 to 2030 period. For example, average bills under the Guarantee over the

2020 to 2030 period are around $400 (in 2017 dollars) a year lower than the estimated

bill for 2017.

5.2.1.3 Ability to achieve emissions reduction target

The model imposed a cumulative target for 2021 to 2030 of 1,352 Mt consistent with

the Commonwealth government’s Paris commitments and determined the trajectory

that is the least-cost way of achieving the 2030 target over the decade. This resulted in

a mostly linear trajectory (see Figure 5.6). Annual emissions produced under BAU and

the Guarantee are also shown in Figure 5.6.

Emissions in both cases are projected to fall to 2023, reflecting:

falling demand forecasts,

the entry of a large amount of committed renewable energy capacity, and

the announced closure of Liddell (i.e. exits of committed generation capacity).

The decline in emissions stalls from the early 2020s under BAU once these schemes

are met and all committed investments are deployed; the target is not met in this case.

Page 73: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

73

Figure 5.6: Emissions under the Guarantee and BAU

Source: Frontier Economics

Emissions continue to fall under the Guarantee due to the emissions requirement. The

emissions trajectory modelled for the Guarantee is the least-cost way of achieving the

emissions target under the model’s assumptions relative to BAU.

5.2.1.4 Investment and retirements

The Guarantee is expected to drive differences in the type of new generation

investment, compared to BAU. The emissions requirement is expected to incentivise a

shift towards lower emissions technologies, while the reliability requirement is expected

to incentivise a shift towards dispatchable technologies. Those generators that have

both attributes are expected to be highly valued and likely recipients of increased

investment focus.

Figure 5.7 shows the amount of committed and uncommitted generation capacity that

enters and exits the NEM under the Guarantee vs. BAU. The majority of investment

throughout the entire period, and particularly earlier in the period, is committed (almost

6,000 MW). As per the definition of ‘committed’ capacity, the amount of capacity that

enters and exits is identical under the Guarantee and BAU. In contrast, the amount of

‘uncommitted’ or additional investment that occurs and plant that exits differs between

BAU and the Guarantee, and is therefore more informative about the Guarantee’s

impact on generation investment.66

66 Committed capacity reflects entry and exit that are not an outcome of the model. Uncommitted

investment reflects outputs from the modelling.

Page 74: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

74

There is more new capacity installed under the Guarantee than under BAU. For

example, around 4,400 MW of new uncommitted capacity enters by 2030 under the

Guarantee, compared to 861 MW under BAU (bottom panel of Figure 5.7).67 Overall,

the Guarantee results in extra capacity in the system which both boosts system

reliability and lowers wholesale prices under the Guarantee vs. BAU (see Table 5.3).

The Guarantee’s dual requirements results in greater entry of those technologies that

are both low-emissions and dispatchable, compared to BAU. The least-cost mix of new

investment under the Guarantee is comprised mostly of wind, followed by large-scale

solar PV, batteries and mid-merit gas.

Figure 5.7: Entry and exit of cumulative generation capacity by technology type

and year68

Source: Frontier Economics

Table 5.3 highlights that over the 2020 to 2030 period, the Guarantee encourages

1,086 MW more dispatchable generation capacity into the system, with this extra

capacity used to ‘firm up’ intermittent renewables. This is additional to the 2,543 MW of

committed investment in dispatchable generation capacity to 2030 under both BAU and

the Guarantee, comprising 2,000 MW through Snowy 2.0, a further 338 MW of pumped

storage hydro, 198 MW in solar thermal with storage and 7 MW in gas peaking plant.

67 Figure 5.7 only includes generation investment in the wholesale market, and therefore excludes

investment in rooftop solar PV. Investment is represented as positive, exit as negative.

68 The exit of uncommitted capacity under the Guarantee relates to the mothballing of those units of

Gladstone coal power station in operation under BAU (773 MW).

Page 75: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

75

No additional dispatchable renewable capacity enters under BAU beyond the

committed generation.

Table 5.3: Investment in uncommitted plant (MW)

Coal Gas Dispatchable renewable (incl. batteries)

Intermittent renewable

BAU 0 263 0 597 Guarantee 0 251 835 3,271

Source: Frontier Economics

5.2.1.5 Generation output

In addition to showing the path of new investment in generation technologies in the

NEM, the modelling can also provide insights into what proportion of generation output

comes from different generation technologies.

Table 5.4 shows the output of different generation technologies as a percentage of total

output in 2020 and 2030. Under the Guarantee, 36 per cent of generation output in

2030 will come from renewable generation, with four-fifths of this (i.e. 28 per cent of all

output) from intermittent renewables. In contrast, under BAU, 31 per cent of output will

come from renewable generation (23 per cent from intermittent renewables) in 2030.

Table 5.4: Output mix (% of total generation) by technology: 2020 and 2030

Mechanism

Year Black Coal

Brown Coal

Hydro Gas Solar Thermal

with storage

Solar PV (incl.

rooftop)

Wind

BAU 2020 55% 16% 8% 2% 0% 7% 11% 2030 48% 16% 8% 5% 0% 12% 11%

Guarantee 2020 57% 16% 8% 2% 0% 7% 11% 2030 45% 15% 8% 4% 0% 13% 15%

Note: Some years do not add to 100 per cent due to rounding. Source: Frontier Economics

Under both BAU and the Guarantee, the penetration of renewables increases from

2020 to 2030, with this increase largely due to higher penetration of intermittent

renewables. As expected, the increase in renewables is greater under the Guarantee

due to the emissions requirement. The proportion of total generation figures include

rooftop solar generation.

If the reliability obligation is triggered under the Guarantee, liable entities will be

required to enter into sufficient qualifying contracts to cover their share of system peak

demand. This provides an incentive for liable entities to support the reliability of the

system through their contracting and investment in resources, as qualifying contracts

are typically only offered by dispatchable capacity (or demand response) that is

available to be dispatched when the system needs it.

Page 76: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

76

5.2.2 Qualitative assessment of the Guarantee

Following on from the quantitative assessment of the Guarantee in the preceding

section, this section provides a qualitative assessment of the Guarantee. Such an

assessment should be made with reference to an assessment framework, which is

provided below.

When contemplating the integration of energy and environmental policy, it is important

to design a mechanism to achieve a reliability objective and an emissions reduction

objective that are consistent with the design of the energy market. In particular, The

National Electricity Objective (NEO), as stated in the National Electricity Law, is to

promote efficient investment in, and efficient operation and use of, electricity services

for the long term interests of consumers with respect to price, quality, safety and the

reliability and security of supply. The following principles are important to consider

when designing such a mechanism:

Certainty of achieving policy objectives – for mechanisms to be sustainable

and effective, they need to be able to meet their objectives in the face of a

changing and uncertain future. Without this ability to adapt when the future does

not turn out as expected, investors may begin to expect that a mechanism may

be changed in light of the actual outcomes, for example if demand is lower than

anticipated at the outset of the policy. This can lead to investors not having the

confidence to invest in new capacity. A credible and durable compliance

framework would also provide greater certainty that both requirements can be,

and are being, met.

Technology-neutral – a mechanism that allows the greatest variety of

technology options to assist in achieving its policy objectives will help minimise

the long term costs to consumers.

Geographically-neutral – a mechanism that is indifferent to where generation

technology options are to be located, and allows the locations selected to be an

outcome of the trade-off between economic costs and benefits, is likely to

minimise costs for consumers.

Appropriateness of risk allocation – a mechanism should allocate risks to

those parties best-placed to identify and respond to risks in an efficient manner.

Contract market liquidity – a mechanism that, through its effect on the

generation mix, preserves or enhances liquidity in the market for ‘firm’

contracts, will assist participants to manage risks efficiently for the long-term

benefit of consumers. Firm contracts are backed by generators that generate

when needed by customers and so are more valuable to customers than the

‘non-firm’ contracts offered by generators with intermittent output.

Implementation flexibility – the extent to which a mechanism can be

implemented in a manner that automatically adjusts or ‘self-corrects’ in the face

of changing demand, cost or other system conditions.

Cost estimates and impacts on consumers – consumer impacts are

assessed through wholesale prices, generator investment, retirement and

Page 77: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

77

output changes. As these cost estimates and impacts are sensitive to key input

assumptions, such as demand, fuel prices and generator retirements, it is

important to compare the relative differences in outcomes between different

sets of assumptions.

Adaptability and sustainability of mechanism design – investors need a

level of confidence that policy objectives can be met and that the mechanism

for achieving these objectives is sufficiently robust to deal with changes in

energy market conditions or policy objectives without succumbing to calls for

the mechanism or the policy objectives to be altered or replaced. This requires

that the acceptability of outcomes generated by the mechanism should not be

predicated on a single view of the future, whether that is a specific demand

forecast, relative technology or fuel costs, or the policy objective itself. Rather,

investors will need to be satisfied that the mechanism can yield predictable

outcomes given different market conditions and policy objectives. Without

confidence in the resilience of the mechanism, investment will not be

forthcoming and it is likely that neither the emissions reduction nor energy

policy objectives will be met.

Minimising regulatory burden – a mechanism’s regulatory burden should be

minimised by focusing compliance on only the key information needed to

assess and demonstrate compliance with the mechanism, leveraging existing

systems and processes for reporting and data collection as far as possible. That

is, a mechanism should be designed in a way that minimises the costs of

complying with the mechanism whilst achieving the mechanism’s desired policy

objectives.

Failing to consider Australia’s energy policy objectives when designing this reliability

and emissions mechanism is likely to result in higher prices for consumers in the long-

run and a less reliable and secure power system than would otherwise be achievable.

Conversely, designing the emissions reduction mechanism in a manner that is

consistent with governments’ energy policy objectives will contribute to the resilience

and longevity of both the emissions reduction policy and its associated mechanism.

5.2.2.1 Certainty of achieving policy objectives

Both the emissions and reliability requirements embed the policy objectives of

emissions reductions and a reliable power system, respectively, into the wholesale

electricity price. This provides certainty that the policy objectives will be achieved.

The Guarantee’s reliability objective is that system reliability is consistent with the

reliability standard. A greater level of contracting will encourage generators to invest in

their plant and offer their capacity into the spot market at their marginal costs to ensure

they are dispatched to fund their contractual requirements. Furthermore, the reliability

requirement would only bind when it is expected supply won't meet demand. This

makes it cheaper than other reliability mechanisms that could be used such as a

capacity market.

The design of the Guarantee therefore enables it to meet its policy objectives at lowest

possible cost, and it has the inherent ability to adapt to changes in the target without

Page 78: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

78

having to modify the scheme. On the reliability side, market participants are able to

adjust their contract positions to account for changes in their demand forecasts, so the

cost of the reliability requirement remains reflective of the value to the system of having

that additional reliability.

While these goals may change, the mechanism to achieve them will not. This would in

turn, promote greater investor confidence to invest in new generation capacity,

facilitating the achievement of the policy objectives.

5.2.2.2 Technological and geographic neutrality

Technology neutrality is one of the principles crucial to designing effective policy

mechanisms that are integrated with the energy market. Technology neutrality means

that the widest range of technologies is available to achieve the stated policy

objectives. Policies should not favour or subsidise certain technologies over others.

The emissions requirement is technologically-neutral. This means it supports the

lowest-cost ways of meeting the emissions requirement, whether that is improving the

efficiency of coal generators, fuel switching from coal to gas and/or building renewable

energy capacity, even under different assumptions about the future (for example,

assumptions about future gas prices or technology costs). The emissions requirement

is also geographically-neutral, as the choice of locations for the new generation

capacity in the NEM is selected solely on the basis of a cost-benefit trade-off.

The reliability requirement is technology-neutral. The obligation is regionally-based

reflecting the physical needs and constraints of the system, which limits the extent of its

geographic neutrality.

5.2.2.3 Appropriateness of risk allocation

The NEM is designed so that generators make investment and retirement decisions

based on price signals in the spot and contract markets, and face the outcomes of their

decisions. If electricity demand, fuel costs, or other variables are higher or lower than

expected, the primary implications for plant profitability are borne by generators, rather

than consumers or taxpayers. This is appropriate because generation businesses have

the expertise, information and commercial incentives to manage such risks efficiently.

In this way, the risk of changes in different variables is appropriately allocated to

generators, rather than customers, which helps promote the National Electricity

Objective.

The Guarantee maintains the existing pricing and risk management mechanisms in the

NEM for signalling whether new investment is required and whether generators should

exit. It does this by maintaining the balance of incentives and risks that ordinarily

prevail in the wholesale market. Investors will continue to be responsible for managing

risks associated with demand, fuel costs and plant fixed costs diverging from forecast

levels.

5.2.2.4 Impact on contract market liquidity

Market customers manage wholesale price and volume risks as a natural part of their

business. Generators have an incentive to contract to provide more revenue certainty.

Page 79: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

79

Retailers and generators are natural counterparties in such contracts and retailers are

the more appropriate counterparty to generators than governments. Risk-sharing

amongst market participants is common practice in the NEM, through the use of

forward contracts such as swaps and caps.

Therefore, the Guarantee is likely to promote contract market liquidity by requiring

retailers to contract with generators in order to meet their emissions and reliability

requirements. As a result, the Guarantee is likely to increase the demand for contracts.

These comments are consistent with the quantitative assessment of the Guarantee’s

impacts on the generation mix.

5.2.2.5 Implementation flexibility

The Guarantee’s design allows retailers and, through their contracts, generators to

determine the least-cost generation mix to meet the reliability and emissions

requirements. Competition incentivises retailers to meet their dual requirements at the

lowest possible cost to consumers, and a credible and durable compliance framework

would ensure both requirements are met. Similarly, generator competition would

ensure the lowest cost generation mix.

5.2.2.6 Adaptability and sustainability

The inherent flexibility of the Guarantee means it is likely to meet its policy objectives if

the emissions reduction target were to change. As discussed in the Implementation

and Review section (Chapter 8), the preferred implementation option is the design

elements of the emissions reduction and reliability requirements be in the National

Electricity Law and Rules. This would mean that the mechanism need not change even

if emissions reduction policy objectives change. This would make it more sustainable

and stable, promoting investor confidence whilst allowing for changes to the

mechanism to be considered via the open, transparent and consultative process of a

rule change request.

The Guarantee can also be designed in a manner that gives it flexibility to adapt to

changing market conditions, such as lower than expected demand or lower than

expected costs for new dispatchable renewables.

5.2.3 Distributional impacts

5.2.3.1 Impacts on prices

The Guarantee provides four key ways to lower prices:

1. By providing an integrated energy and emissions reduction policy and certainty

in the mechanism to deliver the policy, the Guarantee lowers the risks on

investment in new renewable and non-renewable generation capacity.

2. The Guarantee is likely to result in an increase in the proportion of generation

capacity contracted (and therefore reduce the proportion that is uncontracted).

Page 80: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

80

This will increase supply by incentivising generators to be available at times the

system most values the generation output (i.e. when spot prices are high). This

is likely to reduce both the level and volatility of spot prices due to a

combination of more competitive spot market bidding and the risk reduction

from having more capacity contracted.

3. The Guarantee will incentivise investment in low cost dispatchable resources,

which may include intermittent renewables ‘firming up’ their capacity, for

example by investing in storage. This will enable renewable generators to

supply firm-capacity contracts such as swaps and caps and compete with

existing dispatchable capacity, increasing contract supply and liquidity and

lowering contract prices.

4. The technology-neutral nature of the Guarantee’s reliability requirement means

both demand and supply-side resources can be used. By allowing demand-side

resources to compete with the generation sector, the Guarantee ensures that

supply-demand balance is achieved efficiently.

5.2.3.2 Impacts on market customers

Market customers will be responsible for meeting the electricity emissions target.

To record the allocation of generation in the registry, it must be requested by one party,

and approved by the counterparty.69 In practice, it is likely that generators or market

customers will be able to enter an allocation by completing a form on an online registry

platform and this form will then be electronically submitted to the counterparty to

approve. The form will be designed to minimise the administrative burden of submitting

allocations to the registry. Evidence of contractual or other arrangements underpinning

the allocation will not be required due to the counterparty endorsement requirement.

Once approved by the counterparty, the allocation will be recorded in the registry.

The parties can record allocations at any time during the compliance period. They will

also have four months after the end of the compliance period to continue to adjust their

portfolios by recording reallocations. This includes three months before all data is taken

as final at 30 September, plus one further month.

The process of recording and approving allocations in the registry is likely to introduce

minimal additional administrative costs for most market customers, above business as

usual management of operations. Additional capital expenditure to do this is likely to be

limited to one-off IT system, process and education expenses. Ongoing operational

costs of inputting data to the registry should be minimal as the registry design is likely

to be kept simple.

Managing contractual or other arrangements that underpin the allocations in order to

comply with the emissions reduction requirement may introduce some additional

operational costs for market customers, such as expenses associated with legal,

financial and regulatory expertise.

69 It is not intended that output could be directly allocated between generators.

Page 81: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

81

Providing flexibility in how market customers meet the emissions reduction requirement

will minimise instances of non-compliance and reduce the costs of the mechanism to

market customers, and in turn, electricity consumers. This flexibility will allow market

customers to manage variables such as unexpected generator outages and potential

delays to the entry of new generators. Importantly, providing this flexibility will not

change the emissions outcome for the NEM. The required emissions outcome for the

NEM will still be achieved over the medium-term despite year to year fluctuations.

The high-level design set out the flexible compliance options that will be in place for the

emissions reduction requirement, including that market customers will be allowed to

carry forward a limited amount of a previous year’s over-achievement for use in a later

compliance year, and will be allowed limited deferral of compliance to future

compliance years. The proposed approach to implementing the flexible compliance

options is outlined further in the Technical Working Paper on the Emissions Registry.70

Deferred and carried-forward emissions reductions will be recorded in the registry and

it is not expected that market customers would be required to input this information.

These requirements are estimated to be a modest impost in the context of the business

as usual management of a market customer’s operations.

5.2.4.3 Impacts on Generators

To ensure the registry operates efficiently, generators will have some ongoing

administrative requirements under the emissions reduction requirement. They will be

expected to enter or confirm allocations in a timely manner to allow AEMO to provide

regular updates of the contents of the unallocated pool and its emissions intensity.

They will have an administrative requirement to allocate all generation and associated

emissions by the reporting and compliance date.

These administrative requirements of entering or confirming allocations in the registry

are estimated to be a modest impost in the context of the business as usual

management of a generator’s operations. The registry design will aim to keep the

processes simple and ensure the administrative burden is minimised for participants.

The process of entering and confirming allocations for generators is expected to be the

same as that for market customers, as outlined in Section 5.2.4.2.

Additional operational costs may be incurred by generators in order to meet the

administrative requirement to allocate all generation and associated emissions in each

compliance period. This requirement may require generators to input greater time and

resources into contracting arrangements than they would under business as usual,

however this is not expected to be a substantial impost above existing contracting

processes.

Most generators are already required to report emissions data to the NGER system

annually and, as this data will be used for the Guarantee, additional emissions

reporting is not expected to be required.

70 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports-papers.

Page 82: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

82

5.2.4.4 Impacts on large and EITE customers (sourcing electricity direct from NEM)

The Commonwealth Government intends to exempt EITE load from the emissions

reduction requirement. This means that the emissions obligation under the Guarantee

will have little effect on EITE customers.

The ESB’s proposed approach to give effect to this is that each market customer’s load

for the purposes of the emissions reduction requirement will be reduced by any EITE

load it supplies in a compliance year. Across all market customers, each MWh of non-

EITE load will then be scaled-up by a factor such that it equals the total system load for

the purposes of the emissions reduction requirement.

The scaling factor will be calculated three months after the end of the compliance

period, based on the proportion of total system load to non-EITE load for that

compliance period. To provide market customers with greater certainty, the scaling

factor will be capped at a maximum based on the prior year’s proportion of system load

to non-EITE load (or based on a best estimate of future EITE load). AEMO will

regularly publish how the scaling factor is tracking based on the year-to-date proportion

of total system load to non-EITE load.

5.2.4.5 Impacts on Residential and business customers

As outlined above, the Guarantee is estimated to deliver savings to average annual

household electricity bills in the order of $120 between 2020-2030, compared to BAU.

Likewise, business customers are expected to benefit from lower electricity costs under

the Guarantee. The extent of savings depends on the size of the business and its

electricity usage. Larger businesses can typically negotiate lower electricity rates than

average household rates. As a consequence it is difficult to estimate the average

saving to businesses, however it is reasonable to assume that percentage reductions

in electricity rates would be similar to those estimated for households between 2020-

2030.

Businesses that will benefit the most from the Guarantee are those with high electricity

inputs relative to other business inputs. To the extent that these businesses either

export goods or services, and/or compete with imported goods and services, they are

expected to experience an increase in international competitiveness.

Residential and business customers not subject to the reliability requirement will not

experience any compliance costs as a result of the introduction of the Guarantee.

The guarantee proposes the reliability requirement apply to large energy users with

peak demand above 5 MW. Without this threshold, it would make it difficult for a small

retailer to compete for reliability contracts, as the obligation would be concentrated with

a few of the largest retailers. This could manifest in increased contracts prices for

smaller retailers, with the flow costs potentially making it more difficult for them to

compete, affecting competition in the market.

5.2.4.6 Impacts on Environment

One of the main objectives of the Guarantee is to reduce emissions arising from

electricity generation by 26 per cent on 2005 levels by 2030.

Page 83: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

83

If this emissions reduction target is met by 2030, Frontier Economics estimated that a

cumulative amount of 1,352 Mt of CO2 equivalent will have been abated.

5.2.4.7 Competition Impacts

This section describes current NEM competition concerns and how competition issues

have been considered in the Guarantee’s design.

NEM competition issues

In 2017, the Finkel Review highlighted concerns about wholesale market competition

and increased retail and wholesale market concentration, and the implications for price

and service outcomes.71 The ACCC is considering these issues of market

concentration as part of its Retail Electricity Pricing Inquiry.

The majority of stakeholder submissions to the ESB's discussion paper mention

various competition issues. In particular, the design must not undermine competition,

for example by inadvertently creating barriers to entry for new retailers or entrenching

the market power of vertically integrated retailers. Some submissions said the

Guarantee should be used to improve retail and wholesale market competition through

increased liquidity and transparency.72

Market share is one indicator, amongst many, of the potential existence of market

power. This section presents some standard market share-based indicators, for

generation and retail sectors and draws on the evidence presented in the ESB’s

November 2017 advice.73

Competition in the generation sector

Figure 5.8 shows market shares by generation capacity installed.74 In each NEM

region the combined market shares of the two or three most significant generators

exceeds 70 per cent on both capacity and dispatched energy measures. Tasmania-

excluded,75 South Australia’s generation sector has the highest degree of

71 Commonwealth of Australia, Independent Review into the Future Security of the National Electricity

Market (Finkel Review), June 2017, p.138 https://www.energy.gov.au/publications/independent-

review-future-security-national-electricity-market-blueprint-future.

72 Various stakeholder submissions, Energy Security Board National Energy Guarantee - Consultation

Paper, http://coagenergycouncil.gov.au/publications/energy-security-board-national-energy-

guarantee-consultation-paper.

73 See Chapter 6 of Energy Security Board, The National Energy Guarantee, Advice to the

Commonwealth Government, 20 November 2017.

74 Figure is based on capacity rather than output, it is likely to overstate the market share of

businesses that have mostly peaking generators (such as Origin in Queensland and Victoria), or

fuel-constrained hydro plants (such as Snowy Hydro), who may have a lot of generation capacity

but typically only run it for short bursts at peak times.

75 In Tasmania, Hydro Tasmania is effectively the only generator, but Tasmania has access to

mainland generation through the Basslink interconnector.

Page 84: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

84

concentration, with the largest generation business (AGL Energy) having a larger

market share (42 per cent) than the largest generator in any other NEM region.

Figure 5.8: Market shares in generation capacity, 201776

Source: AER, State of the energy market 2017, May 2017

As noted by the ACCC, generation sector concentration has increased over time.77 For

example, in 2011–12 Queensland consolidated some of its state-owned generation and

in 2012 AGL acquired full ownership of Loy Yang A in Victoria. More recently,

concentration has been exacerbated by the closure of a number of key facilities. In

particular, in 2015-16 Alinta exited SA when it retired its coal-fired power stations and

Engie’s share of the Victorian market was significantly reduced in 2016-17 when it

closed its Hazelwood power station.

In some NEM regions, a single generation business accounted for more than 30 or 40

per cent of dispatched energy in 2016-17. AGL, in particular, accounted for over 40 per

cent in each of NSW and SA, and over 30 per cent in Victoria. In Queensland, the

76 Note: Capacity is based on summer availability for January 2017, except wind, which is adjusted for

an average contribution factor. Interconnector capacity is based on observed flows when the price

differential between regions exceeds $10 per MWh in favour of the importing region; the data

excludes trading intervals in which counter flows were observed (that is, when electricity was

imported from a high priced region into a lower priced region). Capacity that is subject to power

purchase agreements is attributed to the party with control over output.

77 See Chapter 3 of Australian Competition and Consumer Commission, Retail Electricity Pricing

Inquiry, Preliminary report, 22 September 201

Page 85: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

85

state-owned CS Energy and Stanwell Corporation facilities each account for over 30

per cent of electricity generated.

Guarantee competition considerations

In general, the greater the extent of competition amongst market participants, the lower

the likely costs to consumers of achieving the Guarantee’s policy objectives.

Competition in the generation sector influences contract prices and therefore affects

the cost to retailers of meeting their requirements under the Guarantee. The greater the

effectiveness of this competition, the lower the cost to retailers. In addition, competition

in the retail sector influences the cost of the Guarantee to end-consumers. Retail sector

competition influences the extent to which the savings to retailers, from competition in

generation sector, are passed through to consumers.

The design of the emissions reduction and reliability requirements will support the

liquidity, transparency and competitiveness of the NEM in the following key ways:

Compliance with the emissions reduction requirement will be facilitated by the

allocation of generator output via an emissions registry. This will address the

key concern of many stakeholders that the emissions reduction requirement

would require the physical linking of contracts to their emissions source, making

contracts more bespoke and reducing contract market liquidity.

Market customers will continue to enter into financial contracts to hedge their

position in the spot market as per their usual business practices, and to manage

any obligations they may have under the reliability requirement of the

Guarantee. They will then be able to use their existing contracts, or enter into

new ones, to obtain the right to assign physical generation and emissions for

the purpose of the emissions reduction requirement. This can be done in any

way the market customer deems appropriate, based on its current contract

arrangements.

Limits will be applied to the carry forward of over-achievement under the

emissions reduction requirement to ensure that there is sufficient opportunity for

all market customers to secure adequate contracts to meet the electricity

emissions targets for their load. Unlimited carry forward of over-achievement

could present a significant risk to effective competition. The limit imposed will

ensure that market customers do not unreasonably withhold over-achievement

from the market.

A limited allowance for under-achievement in a particular year under the

emissions reduction requirement will also help ensure that market customers

are not forced into non-compliance by a temporary shortage.

As an additional measure to support retail market competition, the first 50,000

MWh of any market customer’s load will be exempt from the emissions

reduction requirement, and instead spread over other market customer load.

This level has been set such that small market customers will be exempt for

some or all of their load. As a market customer’s load increases above

Page 86: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

86

50,000 MWh, their exempt proportion decreases. This measure will help smaller

market customers meet the emissions reduction requirement, while not having

a material impact on overall coverage.

If the reliability obligation is triggered, transparency, liquidity and competition

issues would be addressed through a Market Liquidity Obligation and a trade

repository and reporting approach. The Market Liquidity Obligation could be

imposed on vertically integrated retailers with generation shares in gap regions

over a certain threshold. These participants will be required to post bid and offer

spreads for swaps in the region to cover the period of the forecast gap. These

bids and offers will be provided through a centrally cleared platform and provide

access to qualifying contracts. This will enhance competition through access to

tradeable contracts. A trade repository and reporting approach would seek to

capture additional transparency in areas of wholesale contracting that are

currently opaque.

A voluntary AEMO book-build could enhance wholesale market competition by

allowing smaller retailers to band together and bring new resources to market to

back qualifying contracts such as swaps and caps.

Liable entities under the reliability requirement will be retailers and large

customers. Retailers are well positioned to support the reliability of the power

system through their contracting as they are already incentivised to contract to

cover their mass market loads. However, it is difficult for retailers to accurately

forecast the potential demand from large customers as their contracts expire.

Large customers often change retailers frequently. Retailers would need to

impose additional costs on customers to manage the obligation without knowing

whether they were ultimately responsible for the load associated with a large

customer. Therefore, large customers will have the choice to either contribute

directly to the reliability of the power system, or alternatively, enter into a

commercial arrangement to have a retailer manage its obligation on their

behalf. This should see the reliability requirement managed at least cost while

providing retailers (large and small) the opportunity to compete to manage the

reliability requirement on behalf of large customers.

5.2.4.8 Regulatory Burden

Emissions Requirement

The emissions reduction requirement is an annual obligation on market customers to

ensure the average emissions intensity of generation allocated against their load is at

or below the prescribed electricity emissions target for a given compliance period.

The registry provides the necessary infrastructure to facilitate efficient compliance with

the emissions reduction requirement. It allows market customers to be allocated a

share of a generator’s output and associated emissions, for which they have obtained

the rights. This can be based on any contractual arrangement held with a counterparty

outside the registry, as long as both parties verify the agreement in the registry. Market

customers can choose to enter into contracts to allocate generation in the registry with

Page 87: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

87

the same generators that they enter into hedging contracts with, but there is no

requirement for these parties to be the same.

Fundamental to the operation of the emissions registry is the capacity to ‘allocate’

generation from a generator to a market customer (and subsequently reallocate

between market customers).

When a market customer allocates generation to their load in the registry, the allocation

must be underpinned by evidence that the counterparty has approved it. This

requirement will reduce the risk of generation being inaccurately allocated or the same

generation being allocated to multiple market customers. Non-compliance with this

requirement will be automatically identified in the Registry and non-compliant entities

may be subject to enforcement action.78

Market customers can use information recorded in the registry over a compliance year

to monitor their compliance position. At the end of the compliance period, and following

a four month reporting and revision window, the AER will assess the compliance of

each market customer based on final information in the registry. There will be a robust

framework for the AER to monitor and enforce compliance.

Generators will be required to enter or confirm allocations in a timely manner to allow

AEMO to provide regular updates of the contents of the unallocated pool and its

emissions intensity. They will also have an administrative requirement to allocate all

generation and associated emissions by the reporting and compliance date.

There are approximately 75 market customers and 150 registered participant

generators that will need to be involved in all allocations.

The proposed compliance framework has been designed to minimise the reporting

burden on generators and market customers. Where possible, the reporting required to

assess compliance with the emissions reduction requirement will build on existing

information sources. For the data being sourced from existing information sources, the

existing frameworks for monitoring and enforcing reporting requirements will continue

to apply.

Existing data sources that will be drawn on to assess compliance are likely to include:

Emissions intensity data: Emissions for each generator will be primarily sourced

from NGER reporting. Monitoring and enforcing compliance with data reporting

requirements and record keeping requirements will continue to be the

responsibility of the Clean Energy Regulator. These requirements fall under the

National Greenhouse and Energy Reporting Act 2007. For the purposes of

calculating a generator’s emissions intensity, emissions data will be combined

with generation data that matches the year of the emissions data and scaled

according to the marginal loss factors applying in the compliance year (both

generation and market customer purchases will be calculated at the node). For

further details, see the Technical Working Paper on Market Customer Load.79

79 Energy Security Board, Technical Working Paper, see

http://www.coagenergycouncil.gov.au/reports -papers.

Page 88: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

88

Generation data: Output data for each market generator will be sourced from

AEMO’s settlement systems. This data will show actual volume of generation

from each generator in the NEM over the compliance period. The compliance

with data reporting requirements will continue to be the responsibility of the

AEMO.

Pool purchases: Pool purchases for each market customer will be sourced from

AEMO’s settlement systems. This data is settled in weekly batches, and each

week’s data first becomes available four weeks in arrears. The compliance with

data reporting requirements will continue to be the responsibility of the AEMO.

Where existing data sources are used to assess compliance, there is no additional

burden on market customers, compared to business as usual. The existing frameworks

for monitoring and enforcing reporting requirements will continue to apply.

Where new information is required to assess compliance with the emissions reduction

requirement, such as emissions data for generation not currently captured in NGER

reporting, additional reporting requirements will be introduced (largely under NGER

legislation).

For most generators and market customers, the significant additional reporting

requirements above business as usual are likely to be the requirements to report on

and confirm allocations of generation to load in the emissions registry. As outlined in

Section 5.2.4.2 and Section 5.2.4.3, undertaking this additional reporting (inputting and

approving allocations in the online registry platform) will incur costs. Capital costs are

likely to be incurred in order to establish IT systems, processes and education to

enable participation in the allocation process in the registry. These costs are likely to be

minimal for smaller entities and increasing with size and complexity of the entity.

Ongoing operational cost may include human resources and potentially the

procurement of legal, regulatory and financial expertise to manage contractual or other

arrangements that underpin the allocations in the registry. The ongoing operational

costs are expected to be higher than the capital expenditure and will similarly be

smaller for smaller and less complex entities. The expense is likely to be very

dependent on each entity’s existing resourcing and capacity.

The costs of securing contractual or other arrangements to underpin allocations of

generation and associated emissions in the registry will be subject to the electricity

emissions target and the shape of the trajectory to reach that target.

Page 89: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

89

Reliability requirement

If the reliability obligation is triggered (at T-3), then the liable entities will have 2 years

to ensure that they have qualifying contracts in place to cover their electricity demand

for the 1 in 2 year regional peak demand forecast for the compliance year (T).

A liable large customer will be able to meet their obligation by contracting with an

electricity retailer, arranging their own qualifying contracts for supply, use of their own

demand response capability, or through a mix of these approaches.

The reliability obligation provides a safe harbour that scales down actual measured

demand when it is above the 1 in 2 year peak demand forecast to a share of the 1 in 2

year forecast. A liable large customer can be confident that if they contract for their

expected peak load they will meet or exceed their reliability obligation.

New entrants – for example, entities above the demand threshold commencing

operations during the compliance year – will be required to take steps to secure

contracts or enter an agreement with a retailer to manage their obligation for contracts

over the forecast gap period. New entrants would demonstrate their compliance with

the reliability requirement in the same way as all liable entities. The difference is that

the new entrant would only need to demonstrate they met the contracting requirement

at the time they entered the market, rather than at the commencement of the

compliance year (T-1).

The existing contracts of liable entities that are large customers, will be considered

qualifying contracts (up to the load covered by the contracts in place). This is a

transitional concession that deems existing contracts to be eligible contracts to reduce

regulatory burden and avoid impacting pre-existing contracts entered in good faith

before the Guarantee design was released.

If the reliability obligation is triggered (at T-3), then all liable entities, excluding those

that have transferred their obligation to a retailer, will need to assess their likely share

of regional peak demand and secure sufficient qualifying contracts to cover this.

If the gap persists in one or more NEM regions one year out, liable entities in the

affected regions will be required to submit their net contract position to the AER to

demonstrate they have sufficient enduring qualifying contracts over the gap period.

A liable entity’s reported contract position at T-1 will be the primary information source

for the AER to assess compliance should a compliance assessment arise. The

information contained in the report must therefore be sufficiently detailed to enable the

AER to make this assessment.

A liable entity will need to have appropriate systems and processes in place to record

the contracts they have procured at T-1. These contracts will also then need to be

accessible for an external auditor to assess the ‘firmness’ of the contracts for time T. A

record of the eligible contracts will also need to be retained by the liable entity in the

event that the AER needs to make further compliance enquiries or information

requests.

An external audit of the contract position at time T-1 for time T will have varying

resource costs depending on the nature of the contracts under assessment and the

Page 90: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

90

AER’s reporting requirements. In circumstances in which the eligible contracts are firm

(such as exchange traded caps and swaps) the audit cost should be minimal. A liable

entity with more complex risk management arrangements, will likely already have a

similar internal (or external) auditing process to monitor risk. In this case, the cost of

auditing the contract position may be more resource intensive but would likely utilize

existing processes of assessing the effectiveness of contract positions for risk

management.

5.3 Physically Backed Contracts

Physically backed contracts (described in section 4.3) were a key element of one of the

ESB's original options. This approach requires contracts used to meet the emissions

requirement and the reliability requirement to be linked to a specific generator. This

option was developed from the ESB's observation that the NEM's spot market, together

with the contracts between generators and retailers to manage price volatility, promote

competition and support the power system. Therefore any mechanism to maintain

reliability and reduce emissions must be able to operate with these contracts.

All other components of physically backed contracts are the same as the Guarantee

including the emissions and reliability requirements, the market customers and liable

entities to whom these requirements apply, the treatment of EITEs exemptions and

offsets.

5.3.1 Price impacts

The ESB's modelling projects the Guarantee will reduce wholesale prices by 30 per

cent by 2030 compared to BAU, while retail bills will be an average of around $120 per

year lower over the 2020 to 2030 period. The ESB considers the wholesale modelling

could be considered applicable to the Guarantee and physically backed contracts, as

the two options are similar. However, linking contracts in the wholesale market to

generation will likely decrease liquidity and competition driving up wholesale prices as

a result. This would also likely reduce a retailer's ability to manage price risk, which

could lead to higher prices for consumers, compared to the guarantee, and it would

have high regulation costs (discussed below).

As previously discussed, the modelling doesn't include the exemption of EITE load for

the emissions requirement. However, changing this assumption would not have had a

material impact on the model's results because the key drivers of electricity price

reductions under the Guarantee are not affected by whether EITEs receive an

exemption.

5.3.2 Financial market impacts

Stakeholder submissions to the ESB's Draft Design Consultation Paper were almost

universal in warning of the risk to the financial derivatives/contracts market if contracts

were required to be physically backed by generators.

It should be noted these contracts do affect the physical market. For example, as

discussed previously, when a retailer and a generator enter into a swap the generator

pays the retailer when the spot price is above the strike price and vice versa when it is

Page 91: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

91

below the strike price. In this contract the generator has the incentive to generate when

prices are high to help lower prices with more supply and reduce its liability to the

retailer.

Physically backed contracts could provide greater certainty for the reliability

requirement being met. At a time of peak demand and limited generation reserves, a

contract with a specific generator would be more likely to result in the necessary

generation than a financial contract, though for the reasons above, the financial

contract could be expected to have a fair degree of certainty of providing generation at

the required time.

However, use of physically backed contracts would significantly increase costs, partly

as a result of the impact on liquidity and competition, but also in relation to the

complexity and costs that would be associated with transitioning the existing financial

derivatives market to physical products.

Stakeholder concerns with physically backed contracts included that existing financial

contracts would have to be revised to be used for the emissions and/or reliability

requirement, increasing complexity and costs. Physically backed contracts would result

in a move away from standard exchange traded and over the counter contracts to less

fungible bespoke contracts. This would fragment the financial derivatives/contracts

market and reduce the market's liquidity and transparency. Another concern was

physically backed contracts would limit the ability of market participants to innovate and

develop flexible new products to support the introduction of new technology, thus

increasing the financial risks associated with investment.

5.3.3 Competition impacts

Requiring a link to generation in contracts would increase the market power of vertically

integrated retailers.

Liable entities would be required to source physical contracts, limiting their ability to

manage financial risks ordinarily dealt with through existing financial products in both

the ASX and OTC products.

This could lead to increased premiums for investment in new sources of dispatchable

generation.

5.3.4 Emissions impacts

The ESB considers the outcomes of its modelling are applicable to both the Guarantee

and physically backed contracts. The model's assumptions are common to both options

with the exception of the exemption of EITE customer load from the emissions

requirement. The ESB considers the impact of the EITE customer exemption not to be

material to the model's projections.

5.3.5 Regulatory burden

Physically backed contracts will have a greater regulatory burden than the Guarantee.

The compliance and regulatory processes for physically backed contracts are expected

to cover all those for the Guarantee, and with the same amount of burden. However,

Page 92: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

92

physically backed contracts would have additional costs from its additional compliance

and administration requirements.

Emissions requirement

In addition to the Guarantee's regulatory requirements, under this option, physically

backed contracts would require a market customer to confirm their contracts are

physically backed. This may be as simple as the market customer ticking a box in the

registry.

The approach for checking compliance would be for the AER to decide. The following

is one possible approach for the purposes of this RIS.

The AER could take a risk and audit based approach to check compliance. It would

develop a risk assessment framework against which each market customer would be

tested for their risk of non-compliance.

Audits would be conducted by AER staff and/or contractors. The AER would audit a

certain number of market customers each year, some selected from the AER's risk

assessment, some chosen at random. All market customers would eventually be

audited.

The AER would develop an audit framework for its auditors and market customers,

describing the roles and requirements of both. The audit may look at all of a market

customer's contracts or a portion of them, depending on the number. An audit could

take a day or more, depending on the number of contracts being audited and their

complexity. Audits would be conducted through the year and could be for any year for

which the market customer has participated in the Guarantee.

Reliability requirement

If the reliability requirement were triggered, the AER would check a liable entity's

contracts are physically backed as part of its review of contracts to confirm the entity

met its obligation. As a result, physically backed contracts are expected to have

minimal additional regulatory burden for the reliability requirement compared to the

Guarantee.

5.4 Summary

Requiring physically backed contracts in the wholesale market will likely decrease

liquidity and competition driving up wholesale prices as a result. This would also likely

reduce a retailer's ability to manage price risk, which could lead to higher prices for

consumers, compared to the guarantee, and it would have high regulation costs. As a

result, the net benefit to the community of the Guarantee compared to BAU will be

higher than the net benefit of physically backed contracts.

Page 93: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

93

6 Consultation

The following is the timeline for ESB's consultation so far.

October 2017 – The ESB advised the COAG Energy Council on proposed

changes to the National Electricity Market and associated legislation to implement

the Guarantee. The Commonwealth Government asked the ESB to provide a

report and modelling on the operation of the Guarantee and its impacts on the

NEM.

10 November – The ESB held a public webinar on the Guarantee and posted

answers to questions that weren't answered in the webinar.

24 November – The ESB released its report and modelling on the Guarantee's

operation and impacts on the NEM. The COAG Energy Council agreed the ESB

should provide further advice.

15 February 2018 – The ESB's first consultation paper was released.

Submissions closed 8 March and over 150 were received.

26 February – The ESB held a stakeholder forum and webinar in Sydney.

20 April – The ESB released its high level design paper. The Commonwealth

Government released a paper for its design elements: the emissions trajectory,

emissions-intensive trade-exposed (EITE) industry exemptions and the use of

offsets. The COAG Energy Council agreed the ESB develop the Guarantee's

detailed design.

22 May – The ESB released 14 issues papers for discussion with jurisdictions and

technical working groups.

21 – 25 May and 4 – 8 June – Technical working group meetings were held. The

groups had government, industry and energy market body representatives.

15 June – The ESB and the Commonwealth released their high level design

documents. Submissions on the Commonwealth consultation close Friday 6 July.

Submissions on the ESB consultation close Friday 13 July.

22 June – The ESB released technical working papers. Submissions close Friday

13 July.

29 June – The ESB released the Consultation RIS. Submissions close Friday

20 July.

Page 94: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

94

6.1 Consultation for the detailed design papers and consultation Regulation Impact Statement

Submissions to the COAG Consultation RIS

The ESB is seeking input from interested parties on the proposed Guarantee and

physically backed contracts for addressing the policy problem as described in this

Consultation RIS by 20 July 2018. All submissions will be published on the COAG

Energy Council’s website, subject to any claims of confidentiality. All submissions

should be sent to [email protected].

This RIS should be read in conjunction with the ESB Draft Detailed Design

Consultation Document (and its Technical Working Papers)80 and the Commonwealth

Government's Draft Detailed Design for Consultation - Commonwealth Elements

paper81, both released on 15 June 2018. Submissions on the Commonwealth elements

paper are due 6 July 2018. Submissions on the Draft Detailed Design for Consultation

are due 13 July 2018.

The ESB intends to consult broadly in finalising the design of the Guarantee.

Stakeholders have a range of opportunities to be involved, as detailed below.

Public forum and webinar

A public forum and live webcast will be held Monday 2 July 2018. Further information

about how to participate is published on the COAG Energy Council website.

Next steps

Following the consultation process, the detailed design of the Guarantee will be

finalised and a COAG Decision RIS will be prepared. The detailed design and Decision

RIS will be presented to the COAG Energy Council for decision at its August 2018

meeting.

If the COAG Energy Council approves the final design of the Guarantee at its August

2018 meeting, it is expected that the draft legislation will be finalised for introduction to

the South Australian and Federal parliaments by the end of 2018.

80 Energy Security Board, Draft Detailed Design Consultation Paper,

http://www.coagenergycouncil.gov.au/publications/energy-security-board-%E2%80%93-draft-

detailed-design-national-energy-guarantee-consultation, accessed 18 June 2018 81 Department of the Environment and Energy, Draft Detailed Design for Consultation Commonwealth

Elements, http://www.coagenergycouncil.gov.au/publications/national-energy-guarantee-draft-

detailed-design-commonwealth-elements, accessed 18 June 2018

Page 95: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

95

7 Conclusion

The ESB's preliminary view is the Guarantee is the preferred option. The Guarantee

will achieve the COAG Energy Council's objectives to maintain the NEM's reliability and

meet the electricity sector’s share of the Commonwealth Government's international

emissions reduction commitment. It will do this at the lowest cost and with a larger net

benefit to the community than physically backed contracts.

The ESB's modelling shows the Guarantee and physically backed contracts can both

reduce the electricity sector's emissions to 26 per cent below 2005 levels by 2030 and

provide more dispatchable generation to ensure reliability. BAU will not meet either of

these objectives.

The ESB's modelling projects the Guarantee will reduce wholesale prices by 30 per

cent by 2030 compared to BAU, while retail bills will be an average of around $120 per

year lower over the 2020 to 2030 period. The modelling doesn't include the exemption

of EITE load for the emissions requirement, but the ESB considers this would not

materially impact prices. The impact analysis suggests the physically backed option

would have higher compliance costs.

Physically backed contracts would see the market use more bespoke contracts and

limit options to meet the emissions and reliability requirements. This in turn would

increase compliance and transaction costs, fragment the financial derivatives/contracts

market and reduce the market's liquidity.

The ESB will publish its final position in a Decision RIS, after it has considered

stakeholder submissions and refined its impact analysis. The Decision RIS is expected

to be published following the COAG Energy Council's meeting in early August 2018.

Page 96: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

96

8 Implementation/Review

8.1 Implementation and governance

Based on the preliminary analysis in this Consultation RIS, the Guarantee is the

preferred option for addressing the emissions and reliability objectives. The following

outlines the implementation and governance arrangements for the Guarantee.

Stable and effective implementation of the Guarantee will provide certainty for market

participants about the market's operation and allow for long-term investment decisions

to be made in the electricity sector.

The ESB’s preferred option is for COAG Energy Council agreement with

implementation through existing governance arrangements for the NEM. The majority

of the Guarantee would be implemented through amendments to the Australian Energy

Market Agreement (AEMA), the NEL and the Rules.

Embedding the Guarantee into the broader energy governance framework would allow

the mechanism to be fully integrated with the broader energy Rules. This would

maximise consistency between the reliability and emissions reduction requirements,

reducing complexity and compliance costs for market participants.

8.1.1 Implementation through NEM governance arrangements

Amendments to the NEL, after being agreed by the COAG Energy Council in

accordance with the AEMA, would be implemented by South Australia and

automatically applied in each of the other jurisdictions.

The necessary changes to the Rules would be made by the South Australian Energy

Minister.

The NEL and Rules would be amended to:

translate the emissions target and reliability requirement into retailer obligations,

and

establish the compliance and enforcement framework.

After the initial package of changes to the Rules are made, the AEMC would be the

rule-maker in accordance with its current functions. It would be able to accept and

assess rule change requests from any entity relating to the portion of the Guarantee

mechanism that is contained in the Rules, following the well-understood rule making

processes set out in the NEL. This will give participants clarity in relation to how and

when revisions to the mechanisms will occur, recognising that the design of the

Guarantee is already flexible to changing market dynamics. Certainty that the policy will

last, along with a mechanistic and known approach to any updates, would increase the

investor confidence and certainty needed in the electricity sector where the assets are

long-lived, and the planning horizons are lengthy.

Page 97: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

97

8.1.2 Relevant Commonwealth legislation

As discussed above, the Guarantee would be implemented primarily through

amendments to the NEL after agreement by the COAG Energy Council.

The Commonwealth Government would set the electricity emissions target as

discussed in Chapter 4. Some amendments to existing Commonwealth legislation may

also be required. These changes would relate primarily to the setting the emissions

targets, provisions relating to EITE businesses, possibly the use of offsets, and

emissions reporting and information gathering powers.

8.1.3 Advice on including Western Australia in the emissions reduction requirement

At the last COAG Energy Council meeting in April 2018, Western Australia requested

that the ESB provide advice on how Western Australia might be able to participate in

the emissions reduction requirement of the Guarantee. Preliminary advice on this

matter will be provided to the COAG Energy Council at its August 2018 meeting.

Page 98: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

98

8.1.5 Summary of key steps and issues

An outline of the key steps and considerations involved in implementing this approach

is provided below.

Page 99: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

99

8.2 Reviews

The National Energy Guarantee may evolve over time through the existing AEMC rule

making processes under the National Electricity Law. Stakeholders can shape the

design and regulation of the Guarantee through participation in the rule change

process, including by submitting rule change requests.

An important aspect of the National Electricity Rules is that any party, except the

AEMC, can propose a change to the rules. Rule changes that are recommended as

part of an AEMC review can also be requested by any party.

Engagement with stakeholders is conducted during the rule making process through a

number of mediums such as seeking written submissions and participation in meetings,

workshops and forums.

Page 100: The National Energy Guarantee Consultation Regulation ... · contracts used to meet the emissions requirement and the reliability requirement to be physically backed by a generator

100

Abbreviations and defined terms

ACCC Australian Competition and Consumer Commission

ACT Australian Capital Territory

AEMA Australian Energy Market Agreement

AEMC or Commission Australian Energy Market Commission

AEMO Australian Energy Market Operator

AER Australian Energy Regulator

ANREU Australian National Registry of Emiss ions Units

ARENA Australian Renewable Energy Agency

ASX Australian Stock Exchange

CER Clean Energy Regulator

COAG Council of Australian Governments

ESOO Electricity Statement of Opportunities

EITE Emissions-intensive trade-exposed

ESB Energy Security Board

Guarantee National Energy Guarantee

LRET

MW

Large-scale Renewable Energy Target

Megawatt

MWh Megawatt-hour

NEL National Electricity Law

NEM National Electricity Market

NEO

NER

National Electricity Objective

National Electricity Rules

NGER National Greenhouse and Energy Reporting scheme

OTC Over the counter

PPA Power purchasing agreement

RERT Reliability and Emergency Reserve Trader

RET Renewable Energy Target

Rules

SRES

National Electricity Rules

Small-scale Renewable Energy Scheme

tCO2-e Metric tonnes of carbon dioxide equivalent

USE Unserved energy