The n- 3 He Project
description
Transcript of The n- 3 He Project
The n-3He Project
Christopher CrawfordUniversity of Kentucky
for the n-3He Collaboration
n-3He Technical Review
ORNL, TN 2013-01-08
Outline
Experiment design• Reaction and observable• Experimental setup
Execution• Commissioning plan
– 2 configurations• Run time• Resources
Collaboration• Organization• Manpower
WBS subpackages• Beam line• Solenoid• Spin rotator• Target / detector• Preamplifiers• Data acquisition• Online analysis• Integration• Commissioning
23-04-21 2
10 Gausssolenoid
RF spinrotator
3He target /ion chamber
supermirrorbender polarizer
(transverse)
FnPB coldneutron guide
3He BeamMonitor
FNPB n-3He
Experimental setup
Measure PV spin asymmetry A ~ 1x10-7 sn kp (Viviani) 15% relative error
longitudinal holding field – suppressed PC nuclear asymmetry A=1.7x10-6 (Hale) sn kn x kp suppressed by two small angles
RF spin flipper – negligible spin-dependence of neutron velocity
3He ion chamber – both target and detector
23-04-21 3
Experimental Layout – from NPDGamma …
23-04-21 4
Experimental Layout – … to n3He
23-04-21 5
Experimental Layout – … to n3He
23-04-21 6
Even though NPDG and n3He are
very similar,
we still require two separate IRR’s
for n3He
Unistructure support – preliminary CAD model
TOP VIEW
23-04-21 7
Unistructure support – preliminary CAD model
SIDE VIEW
23-04-21 8
n-3He collaboration
Spokespersons D. Bowman, M. Gericke, C. Crawford
Local Project Manager S. Penttila
Project Engineer Jack Thomison
Work Subpackage Leaders G. Greene Neutronics
L. Barrón Solenoid
C. Crawford Spin rotator
M. Gericke Target / detector
D. Bowman Preamplifiers
C. Crawford Data acquisition
N. Fomin Online analysis
J. Hamblen Integration
D. Bowman Commissioning
23-04-21 9
Neutronics for the experiment
23-04-21 10
Neutronics for the experiment
Scope• FnPB guide, polarizer, beam monitors – stays UNCHANGED• PPS remains UNCHANGED• Beam profile scanners, polarimetry
Status• All equipment is being used for NPDG experiment
except the beam profile scanners• XY-scanners in hand and tested
Remaining work• Design shielding and mounts for xy-scanner – April• Design mount for 3He analyzer (polarimetry) – April• Modify beamline shielding – April
23-04-21 11
Chris Hayes,Kabir LatifulJosh HamblenGeoff Greene
Magnetic field
23-04-21 12
Magnetic field
Scope • Magnetic field simulations to verify adiabatic spin rotation and uniformity• Unistructure frame for Magnetic coils, Spin rotator, and Target/detector
mounts directly onto existing NPDG stands on the beamline• Design, construction, and testing of longitudinal solenoid
10 Gauss holding field, just like NDPG
Status • Conceptual design, preliminary calculations indicate adiabaticity
15 coils, 15 cm apart, 35 cm radius, 150 A turns• Materials for frame and coil supports are in hand
Remaining work• Machining of coil supports: January – March• Assembly of coils and stand: April• Test coils and mapping of field at UNAM: May
23-04-21 13
Andrés Ramirez,Libertad Barrón
Spin rotator
23-04-21 14
Spin rotator
Scope• Design of RF double cos-theta coil• Machining forms for inner/outer coils,
aluminum enclosure, mounts• RF driver electronics• Field mapping and testing
Status• Design complete• Machining of coil forms
near completion• RF driver electronics exist
and are being used for NPDG
Remaining work• Winding of coils: January• Construction of enclosure: Jan (in parallel)• Testing and field mapping: Jan–Feb (in parallel)
23-04-21 15
Chris Hayes,Geoff GreeneChris Crawford
Inner Cylinder
Design: Complete
Construction: In progress at UT Physics machine shop. Scheduled completion date: January 2014.
23-04-21 16
Outer Coils
Design: Complete
Construction: Outer coils fabricated using 3D print Technology. Delivered 2014-01-03
23-04-21 17
Aluminum Shell
Design: Some design issues are still in progress including a moveable stand for precision alignment with neutron beam.
Construction: Aluminum shell will be built by UT physics machine shop end of January
23-04-21 18
Target / detector
23-04-21 19
Target /detector
Scope • Vacuum enclosure with 1 atm 3He
• 144 channels of sense wires
Status • Vacuum enclosure in hand• Wires soldered to frames
Remaining work• Assemble wire plane stack, readout plane: Feb – March• Vacuum test and fill with 3He: March• Electronics noise testing April
23-04-21 20
Mark McCreaMichael GerickeSeppo Penttila
Target /detector: vacuum housing
12” Conflat end flanges
1 mm Al windows
Fill gas: 1 atm 3He
Feedthroughs: 4x signal, 2x high voltage, 2x vacuum
23-04-21 21
Target / detector: ion chamber wire planes
17 HV planes
16 signal planes• 144 signal wires
All wires soldered to frames
Mounting hardware and fittings all constructed
PCB readout boards willarrive late January
Assembly in February
Testing starting in March
23-04-21 22
Preamplifiers
Scope• 4 boxes of 36 channels: one per vacuum feedthrough• Circuit board designed locally at ORNL• Connector to ion chamber vacuum port and cabling to DAQ module
Status• Circuit boards constructed and initial testing complete• Achieved theoretical limit on some channels, testing in progress
Remaining work• Design forced air cooling• Build cables to preamp• Test all channels• Test instrumental
asymmetries withspin rotator, target
23-04-21 23
Kabir LatifulIrakli GarishviliDavid Bowman
Data acquisition
Scope • 144 channels of 24 bit, 128 KS/s ADC• Standalone system: NO support from DAQ group
Progress• PO to be issued for data acquisition electronics next week
– delivery of hardware end of March, firmware upgrade end of May• Basic control software written; used to take and analyze data• Preliminary measurements of electronic noise – within specification
Remaining work• Build cabling from preamps to DAQ: Jan• Test complete system: Feb – April
23-04-21 24
Kabir LatifulIrakli GarishviliNadia FominChris Crawford
Online Analysis
Scope:• Data transfer and analysis computers• 36 TB RAID storage• Online analysis software• STAND-ALONE system
– no support required from DAQ group
Status: • NPDG infrastructure• Existing software
Schedule forward: • Build complete
network – March• Production-grade
software – April
23-04-21 25
Kabir LatifulIrakli GarishviliCarlos OlguinIvan NovikovNadia FominMichael GerickeChris Crawford
Integration / preassembly
Scope: • Design of unistructure support frame• Design, construction of mounting
and alignment hardware• Maintain 3d solid model of experiment
Status: • Preliminary solid model exists• Conceptual design for mounts and alignment
Remaining work:• Final design of stand and mounting / alignment: Feb• Construction of mounting, alignment hardware: Apr• Assembly of complete system: May-June• Dry run of commissioning process: June
23-04-21 26
Caleb WickershamMark McCreaJack ThomisonGeoff GreeneJosh Hamblen
Alignment
Mounting / alignment components• Aperture / crosshairs for beam scan• Support stand and xy-adjustment for theodolite• Alignment V-block for trimming B-field• Optical system and adjustable mount for target• 10 mrad tolerance – no need for S/A crew
23-04-21 27
Commissioning
Scope: • Testing for instrumental asymmetries• Dry run of commissioning during assembly• Polarimetry and beam scans• Alignment of beam / magnetic field / chamber• Measurement of parity-conserving asymmetry with transverse field
Status: • Preliminary commissioning plan well-thought out
Remaining work:• Installation in FnPB: July• Beam alignment scans: Aug-Sept PHASE 1 IRR• Measure transverse asymmetry: Oct–Dec PHASE 2 IRR
23-04-21 28
everyone…David Bowman
Installation – see Jack’s talk for more details
Commissioning / run planIRR #1IRR #2
Timeline – see Seppo’s talk for more details
Construction of subsystems in parallel• Will stage experiment in EDM building and perform
dry run of field map, beam map, and alignment procedures• Expect to be ready for beam at beginning of cycle Aug 2014
Milestones• 2014-05-01 Begin integration on common stand• 2014-08-01 Begin installation in FnPB cave• 2014-10-06 IRR – begin commissioning phase• 2014-02-15 Begin physics data taking
Runtime• 66 days commissioning (all equipment pre-assembled)• 15 days PC transverse asymmetry 1.7 x 10-6 ± 0.6 x 10-7
• 208 days PV longitudinal asymmetry 1.2 x 10-7 ± 1.7 x 10-8
* based on theoretical calculations
23-04-21 31
Resources – see Jack’s talk for more details
Minimal utilization of SNS crafts• Most equipment mounted on single support structure,
staged in the EDM building, craned onto NPDG det. Support• Machining will be done at university shops• only SNS engineer is Jack Thomison, on n3He funds
– 3D solid model will be drafted within the collaboration,reviewed by Jack, and incorporated into SNS model
• Minimal radiological group support– MCNP model created by Nadia Fomin, Paul Mueller, validated by radiation group
• No survey & alignment resources required – alignment is relative to beam scan
• No support required from DAQ group – standalone system
23-04-21 32