The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex...

4
Printed on recycled paper Contact the Northern Link Team: Northern Link Consultation Team Brisbane City Council LLI Reply Paid 1434 Brisbane QLD 4000 Phone: 1800 692 333 (freecall) Email: [email protected] www.brisbane.qld.gov.au/northernlink www.northernlinkeis.com.au F2010-00406 © Brisbane City Council 2010 TRANSAPEX RINGROAD The Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will combine to form an inner city ringroad. It will increase the number of vital river crossings, fill critical missing links in the motorway network and allow traffic to bypass the CBD. A RINGROAD SYSTEM Northern Link is a key part of TransApex, designed to relieve congestion on Brisbane’s arterial roads and improve cross city connectivity in Greater Brisbane. TransApex is a system of roads – primarily tunnels – that will form an inner city ringroad. It is part of the Lord Mayor Cambell Newman’s balanced approach to tackling traffic congestion on Brisbane’s road network and will help reduce the cost of congestion, which could rise to $3 billion per annum by 2020 if traffic issues are not addressed. Two of these TransApex projects have already been completed with the opening of the Clem Jones Tunnel (CLEM7) and Go Between Bridge earlier this year, with the third of the projects, Airport Link, due to open in 2012. Northern Link is the fourth TransApex project and Council remains fully committed to delivering Northern Link ahead of the scheduled completion date of 2016. BENEFITS FOR MOTORISTS Northern Link will complete the missing link of motorway standard road between the Western Freeway and the ICB, allowing motorists to avoid seven sets of traffic lights. By providing an alternative route, Northern Link will reduce congestion on surface roads such as Milton Road and Coronation Drive, and reduce through-traffic on some local streets. Northern Link will deliver travel time savings of up to 45% in 2014. For example, it will reduce the peak period travel time from the Centenary Bridge to the ICB: in the morning peak from 20 minutes to 11 minutes – a saving of 9 minutes in the afternoon peak from 20 minutes to 12 minutes – a saving of 8 minutes. CBD BRISBANE MOUNT COOT-THA Vulture Street Turbot Street Jubilee Terrace Old Cleveland Wynnum Ro d Kingsford Smith Drive Nudgee Road Port o Stafford Road G y m pie R o ad e S and g at d Roa Moggill Road Coronation Drive Road y a Annerley Road Gold Coast Sunshine Coast Waterworks Road LUTWYCHE GORDON PARK KEDRON CHERMSIDE KELVIN GROVE CLAYFIELD NEW FARM WEST END GREENSLOPES NUNDAH BOWEN HILLS EAST BRISBANE MORNINGSIDE DUTTON PARK ST LUCIA YERONGA INDOOROOPILLY ASHGROVE FERNY GROVE MILTON TOOWONG INNER CITY BYPA S S W E S T E R N F R E E W A Y P A C I FI C M O T ORW A Y Clem Jones Tunnel Motorway standard Go Between Bridge Airport Link Tunnel Northern Link Tunnel East-West Link Tunnel 1 3 4 5 2

Transcript of The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex...

Page 1: The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will ... – Transcity

Printed on recycled paperContact the Northern Link Team:Northern Link Consultation Team

Brisbane City Council LLIReply Paid 1434

Brisbane QLD 4000

Phone: 1800 692 333 (freecall)Email: [email protected]/northernlink www.northernlinkeis.com.au

F2010-00406© Brisbane City Council 2010

TRANSAPEX RINGROADThe Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will

combine to form an inner city ringroad. It will increase the number of vital river crossings,

fill critical missing links in the motorway network and allow traffic to bypass the CBD.

A RINGROAD SYSTEM

Northern Link is a key part of TransApex, designed to relieve congestion on Brisbane’s arterial roads and improve cross city connectivity in Greater Brisbane. TransApex is a system of roads – primarily tunnels – that will form an inner city ringroad. It is part of the Lord Mayor Cambell Newman’s balanced approach to tackling traffic congestion on Brisbane’s road network and will help reduce the cost of congestion, which could rise to $3 billion per annum by 2020 if traffic issues are not addressed.

Two of these TransApex projects have already been completed with the opening of the Clem Jones Tunnel (CLEM7) and Go Between Bridge earlier this year, with the third of the projects, Airport Link, due to open in 2012. Northern Link is the fourth TransApex project and Council remains fully committed to delivering Northern Link ahead of the scheduled completion date of 2016.

Benefits for motorists

Northern Link will complete the missing link of motorway standard road between the Western Freeway and the ICB, allowing motorists to avoid seven sets of traffic lights. By providing an alternative route, Northern Link will reduce congestion on surface roads such as Milton Road and Coronation Drive, and reduce through-traffic on some local streets.

Northern Link will deliver travel time savings of up to 45% in 2014. For example, it will reduce the peak period travel time from the Centenary Bridge to the ICB:

• in the morning peak from 20 minutes to 11 minutes – a saving of 9 minutes

• in the afternoon peak from 20 minutes to 12 minutes – a saving of 8 minutes.

AIRPORT

CBD BRISBANE

MOUNT COOT-THA

Vulture Street

Turb

ot Stre

et

Jub

ilee

Terr

ace

Old Cleveland Road

Kessels Road

Cre

ek R

oad

Wynnum Road

Cre

ek R

oad

Kingsford Smith Drive

Nud

gee

Ro

ad

Gat

eway

Mo

torw

ay

Port of Brisb

ane

Motorway

Stafford Road

G

ympi

eRo

ad

eSa

ndg a

t d

Roa

Moggill Road

Coron

ation

Driv

e

Ipsw

ich R

oad

yawhgiH yranetneC

Gat

eway

Mot

orw

ay

Annerley Road

Gold Coast

Sunshine Coast

Waterworks Road

LUTWYCHE

GORDON PARK

KEDRON

CHERMSIDE

KELVIN GROVE

CLAYFIELD

NEW FARM

WEST END

GREENSLOPES

CARINA

MT GRAVATT

NATHAN

NUNDAH

BOWEN HILLS

EAST BRISBANE

MORNINGSIDE

DUTTON PARK ST LUCIA

YERONGA

OXLEY

INDOOROOPILLY

ASHGROVE

FERNY GROVE

MILTON

TOOWONG

INNER C

ITY B

YPA

SS

WE

STE

RN

FR

EE

W

AY

PA

CIF

IC M

O

TORWAY

GA

TEWA

Y MO

TORW

AY

Clem Jones Tunnel

Motorway standard

Go Between Bridge

Airport Link Tunnel

Northern Link Tunnel

East-West Link Tunnel

1

3

4

5

2

Page 2: The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will ... – Transcity

NORTHERN LINKCommunity Newsletter

August 2010It’s al l part of Counci l ’s plan

Construction on the 5km Northern Link is due to start later this year, a major step in completing the missing motorway link between the Western Freeway and the Inner City Bypass (ICB).

The tender process is progressing well with two bidders – Transcity and Northern Direct – remaining in contention to design, build and operate Northern Link. Council will continue evaluation on the bids before a decision is made on a preferred contractor in the coming weeks.

Detailed plans of the project, including drawings and urban design features, and 3D models will be available following this decision. Council will provide further information once an announcement is made.

Northern Link is on track to open in 2014, delivering much needed traffic relief for the inner west and reducing travel times between Toowong and Kelvin Grove.

COORDINATOR-GENERAL AppROvES NORTHERN LINK pROjECT

The Queensland Government’s Coordinator-General has released the final report on Northern Link, granting approval for the project to proceed.

The report details conditions for the construction of Northern Link and sets out environmental requirements for the project. These conditions provide guidance on managing issues such as noise and vibration and traffic management, and are some of the most stringent guidelines for a major project undertaken in Queensland.

To view the Coordinator-General’s report on Northern Link, go to http://www.dip.qld.gov.au/coordinator-general/index.php and follow the links.

CONSTRUCTION DUE TO START LATE 2010

ABoUt northern Link

Northern Link is the 5km underground toll road which will link the Western Freeway at Toowong with the Inner City Bypass (ICB) at Kelvin Grove. Northern Link will include:

• two lanes for traffic in each direction

• a speed limit of 80km/h

• a ventilation system to manage air quality

• safety systems including emergency exits

• fire protection and monitoring systems

• a free flow electronic tolling system.

Page 3: The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will ... – Transcity

Market Sounding

Council representatives met with more than 30 organisations in eight countries, gaining valuable feedback on the project and attracting strong interest from the local and international market.

Announcement of Federal funding

The Federal Government committed $500m to build Northern Link.

Local road connections removed from project

In response to community feedback and technical and financial considerations, Council removed local road connections at Toowong and Kelvin Grove from the Project Reference Design, significantly reducing the surface impact of Northern Link.

EIS Supplementary Report submitted

Council prepared a Supplementary Report to the EIS in response to questions from the Coordinator-General.

New tender process launched

Council launched a new tender process using feedback from governments and the private sector from both Australia and abroad. Council received expressions of interest from seven consortia, including five internationally-led submissions.

DECEMBER 2008

ApRIL 2009

jUNE 2009

FEBRUARY 2009

SEpTEMBER-DECEMBER 2008

SEpTEMBER- OCTOBER 2009

Preliminary Concepts Council undertook initial environmental investigations and developed a preliminary design.

MARCH-ApRIL 2008

Environmental Impact Statement

A Project Reference Design was developed to assess the project’s potential benefits and impacts on issues such as traffic, noise and vibration. The design was released for comment.

MAY-OCTOBER 2008

Environmental Impact Statement (EIS) submitted

Council submitted an EIS on the proposed Northern Link tunnel for review by the Queensland Coordinator-General. Council undertook extensive consultation on the EIS and the Coordinator-General received more than 200 responses from community members and state agencies.

2008 2009 NORTHERN LINK TIMELINE

Page 4: The Lord Mayor’s TransApex project is a system of bypasses ... · The Lord Mayor’s TransApex project is a system of bypasses – primarily tunnels – which will ... – Transcity

Bids shortlisted

Council shortlisted three consortia from the seven expressions of interest and issued each with Request for Proposal documents. The shortlisted bidders were:

• Northern Direct (Bouygues Travaux Publics SA, Laing O’Rourke and Transfield Services)

• Transcity (Acciona, BMD and Ghella)

• LBRJV (a joint venture comprising Leighton, Baulderstone and Razel).

Coordinator-General approves project

The Coordinator-General released a final report on Northern Link, detailing conditions for construction and granting approval for the project to proceed.

Close of bids

The three shortlisted consortia submitted their bids to design, build and operate Northern Link after five months and more than 500,000 work hours invested.

Construction

The Contractor is due to commence construction before Christmas this year. Surface works will likely ramp-up over several months. Construction is expected to take four years.

Change Report

The Coordinator-General will assess any changes in community impacts between the Reference Design and the final design and determine whether a Change Report is needed.

Shortlist reduced to two

Northern Direct and Transcity were selected to proceed to final evaluation.

Preferred Contractor announced

Council will complete its evaluation and announce a preferred contractor.

DECEMBER 2009 jULY 2010 SEpTEMBER 2010

ApRIL 2010

MAY 2010

SEpTEMBER- DECEMBER 2010 DECEMBER

2010-2014

Purchase of equipment/ worksite established

During the detailed design phase, the Contractor will begin purchasing construction equipment and potentially establish worksites at both the Western Freeway and Inner City Bypass. At the same time as early works commence, Council may be completing a Change Report.

NOvEMBER-DECEMBER 2010

2010 2011