Page 1: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The local partnership approach to the siting of a LILW repository in Belgium

Erik Laes, Gaston MeskensSCK•CEN, Belgium

CIP, NSG meeting, Slovenia10 January 2008

Page 2: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

Overview presentation

History of LILW radioactive waste management policy in Belgium;

The Belgian ‘partnership approach’-brief description;-SWOT analysis;

General reflections;

Conclusions.

Page 3: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

History of LILW radioactive waste management policy in Belgium

1960start of sea dumping;1970sea dumping under supervision of NEA/OECD;1983joining the international moratorium on sea dumping (Convention of London, 1983);1985-1987first selection of 5 sites by NIRAS, based on criteria of the IAEA, NEA and US NRC (geological);1990NIRAS report stating that surface disposal is best option (alternative techniques : old coalmines (unpredictable groundwater behavior) and deep disposal in clay layers (more R&D needed));1994government agrees with definitive ban on sea dumping (established internationally in 1993);1994NIRAS report presenting 98 selected sites (in 47 communities), unanimously rejected by communities;

Page 4: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

History of LILW radioactive waste management policy in Belgium

1995government orders new study on alternatives ; three solutions were considered: temporary surface storage, definite surface storage, deep disposal;1996government orders new study considering 25 old military sites. NIRAS selects 16 sites and drops ‘temporary’ alternatives based on ethical considerations;1998community of Beauraing is candidate (has old military site); proposal turned down by 95% of own population;1999establishment of MONA and STOLA partnerships;1999green party enters government;2003law on nuclear phase-out;2004establishment of Paloff partnership (Fleurus-Farciennes municipalities);

Page 5: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

History of LILW radioactive waste management policy in Belgium

STOLA

Sept 2004Final report approved by the general assembly of the partnership;Nov 2004Final report presented to Dessel municipality council;Jan 2005Final report approved by municipality council;April 2005dissolution of STOLA; creation of STORA, with the extension of the mandate to all kinds of waste;May 2005STOLA Dossier forwarded to the competent Minister of the Belgian Government;

Page 6: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

History of LILW radioactive waste management policy in Belgium

MONA

Jan 2005Final report approved by the general assembly of the partnership and presented to Mol municipality council;April 2005Final report approved by municipality council;July 2005MONA Dossier forwarded to the competent Minister of the Belgian Government;

PaLoFF Dec 2005Final report approved by the general assembly of the partnership;Feb 2006Final report rejected by the executive council of the municipality of Fleurus;

Page 7: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

History of LILW radioactive waste management policy in Belgium

May 2006ONDRAF/NIRAS presented a definitive report that should allow the government to make a properly informed decision concerning the follow-up program for the disposal of low and medium active short-lived waste;

June 2006Based on the recommendation of ONDRAF/NIRAS, the council of ministers decided to opt for a surface disposal site for the disposal of low and medium level short-lived waste in the municipality of Dessel.

Page 8: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

Future of LILW radioactive waste management policy in Belgium

Nov 2007Signing of declaration of intent of cooperation between NIRAS, STORA and MONA

-two-level cooperation:→operational level: preparatory discussions, studies and actions through the different working groups of the partnerships; → managerial level: integrated decision making and project managementthrough a joint steering committee NIRAS-STORA-MONA with an advisory role for the majors of the two communities.

Page 9: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

Future of LILW radioactive waste management policy in Belgium

Master plan:

projects- the siting concept- employment, maintenance of nuclear know-how- communication centre- local development fund- related environmental & town planning- future ensuring of involvement and participation- finances of the integrated project

planningdesign phase: 2007 – 20112008 milestone: detailed report to federal authorityconstruction phase: 2012 – 2016operation phase: 2016 –

Page 10: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBrief description

Page 11: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBrief description – basics

-structure: constitution of stakeholders based on ‘social map’ of the community (governing actors, societal actors, economical actors);

-spirit: to give potential host communities the opportunity (1) to be involved in the development of both the technical and the socio-economic part of the repository project and (2) to determine for themselves the conditions for accepting the site;

-format: developed for ONDRAF/NIRAS by the University of Antwerp and the Fondation Universitaire Luxembourgeoise.

Page 12: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBrief description - modalities

-The constitution reflects the community it represents in a balanced way;-The partnership functions in a democratic and autonomous way and had the (Belgian) structure of a non-profit organisation;-The partnership makes internal decisions in an autonomous way, including the decision to eventually end its activities in the run of the process;-The registered office of the partnership is situated in the community it represents;-The partnership received a local working budget of 250 K€/y and two times a 75 K€ study budget. It could manage these budgets in an autonomous way.

Page 13: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

submission withmunicipality council

project approvalby partnership

integrated project

contribution others(social-econom, ecological)

contribution NIRAS(technical, concept)

evaluation bymunicipality council

submission withfederal authority

closedossier

closedossier

closedossier

feasible? feasible?

feasible?

yes yes

yesno

no no

political, societal and economical actors

establishment partnershipstartphase

studyphase

designphase

decisionphase

Page 14: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBrief description - structure

generalassembly

executive committee

siting &design

safetyenvironment

& healthlocal

development

projectcoordinators

Page 15: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis

disclaimerSWOT analysis:

-SWOT technique: limited critical-analytic capacity; not possible to grasp full complexity and nuance -from out of the ‘ideal inclusive governance’ perspective; not from out of the perspective of the national waste agency, the politicians or the stakeholders;-twofold analysis:1of the partnership model ‘as such’;2of the inclusive governance process in Belgium (1999 – now); (3 independent partnerships working in parallel within one process)

Page 16: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - strengths

1partnership model

-mobilising ‘civic duty’: defending well-being of entire community & opportunity for long-term financing for local development (LLW management as an integrated project);-empowerment of stakeholders (veto right);-Dessel, as small community, saw an important part of the population involved in an intense participative process.

Page 17: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - strengths

2Belgian process

(given the fact that the Belgian process first had to go through expensive lessons to come to a more inclusive character)

-voluntary involvement of three communities(all three nuclear, implying a certain familiarity with the issue);-waste was not a ‘hot’ political issue in the beginning;-problem ownership: waste ‘already there’ (pragmatic fact that ‘enabled’ nuclear communities to become involved and to be finally accepted as legitimate partners in the political negotiation process).

Page 18: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - weaknesses

1partnership model

-problem of representativity remains (how ‘representative’ can an involvement process be?); referenda to validate partnership work could have affirmed conclusions but were not organised;-creation of another independent body alongside the (democratically elected) municipality council: representation of the municipality council in the partnership needed;-after the local partnership process, the report of the candidate community comes in the hands of the traditional (national) politics (no multi-level inclusive governance).

Page 19: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - weaknesses

2Belgian process

-phenomenon of competition between communities;-NIRAS ‘long term fund’ up till now only foresees to cover technical costs; amount of and recourses for socio-economic costs still unknown, even so who will be responsible to collect the finances;-only small waste producers paid their share of the ‘long term fund’ up till now; accountability of Electrabel becomes a possible issue due to the change of ownership (Suez); -local process was not backed by societal debate on national level.

Page 20: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - opportunities

1partnership model

-character of robustness for future follow-up (‘symbolic’, structural, administrative).

Page 21: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - opportunities

2Belgian process

-experience and existing dynamics to support and feed into future governance of high level waste.

Page 22: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - threats

1partnership model

-creation of another independent body alongside the (democratically elected) municipality council; →possible authority conflicts;

→could start living ‘an own life’ (risk of decoupling from grassroots level);-issue of authority with regard to the future management of local development fund.

Page 23: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

The Belgian partnership approachBasic SWOT analysis - threats

2Belgian process

-loss of motivation from the start, especially within the community of Mol (against previous promises, NIRAS expressed preference for one of the communities (Dessel) towards the national authorities);-long continuous working period: risk of stakeholder fatigue;-strict NIRAS timing to be compatible with time-intensive participatory process;-loss of political support before or during project phase through varying future local and national legislations;-loss of ‘evidence’ of connection of compensation with site; conflict on future reassessment of compensation.

Page 24: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

General reflectionsVoluntarism, inclusiveness, accountability

-Voluntary engagement: apparently only of communities that have nuclear activity already?.

-Local participatory decision making is not backed by participatory decision making on national level→RW governance debate kept local;→RW governance debate kept separate from (national) energy policy debate.

-Nuclear community and political decision makers (Belgium, international) remain to evade the real debate on the issue of retrievability.

Page 25: The local partnership approach to the siting of a LILW repository in Belgium Erik Laes, Gaston Meskens SCKCEN, Belgium CIP, NSG meeting, Slovenia 10 January.

Conclusions

-Process generated concrete results (dialogue, reports, concept, decision);-Innovative character (as well international as in the Belgian context): an integrated solution supported by local citizens and politics;-Key weakness: no integration in national participative decision making process;-Near future steps and evolutions will be of key importance for success: → cooperation STORA – MONA – NIRAS;→organisation and coordination of long term fund; → organisation of official EIA process; → continuing local and national political support.