State Office for Water Management Munich The Isar -Plan Project in Munich Great (Un) expectations. European River Restoration Conference Session 5- Enhancement of Multi-Use Landscapes 11-13 September 2013

Transcript of The Isar -Plan Project in Munich Great (Un) expectations. ·  · 2013-09-16The Isar -Plan Project...

State Office for Water ManagementMunich

The Isar -Plan Project in Munich Great (Un) expectations.

European River Restoration Conference

Session 5- Enhancement of Multi-Use Landscapes

11-13 September 2013

State Office for Water ManagementMunich

N. Mahida27.06.2012

2

The Isar-Plan Project: Basic Facts

Approximate length of the project= 8 km Planning start 1995 Construction start 2000 Project completed 2011 Successful cooperation between the Free State of Bavaria and the

City of Munich Approximate costs= 35 Mio. € High public acceptance and (ab)use

Présentateur
Commentaires de présentation
Here I will highlight the downside that we currently face with ‚over-use‘ of the restored Isar Floodplains for recreation. Waste production, glass pieces, flattened vegetation, noise, campers, bbq, facilities such as toilets and parking

State Office for Water ManagementMunich

N. Mahida27.06.2012

3

Content of this Presentation

Highlights of the Isar-Plan Project Diversity of land use Multiple uses of the Isar through the Isar-Plan Unexpected issues encountered during the project

Présentateur
Commentaires de présentation
Hochwasserschutz herabgesetzte Deichsicherheit (geringes Freibord, Gehölzbewuchs, Befahrbarkeit) Gewässerökologie geringe Längs- und Quervernetzung, begradigt, keine Eigenentwicklung, monotone Gewässerbettstruktur, geringe Lebensraumvielfalt, Artenrückgang, Verlust an Pionierstandorten, geringer Restabfluss, keine Durchgängigkeit Landschaftsbild kanalartiges Erscheinungsbild, keine Blickachsen zum Fluss, fehlende optische Abschirmung unattraktiver Bauwerke Freizeit- und Erholung schlechte Gewässerzugänglichkeit, mangelhafte Badegewässerqualität, fehlende Anbindung an das städtische Umfeld

State Office for Water ManagementMunich

N. Mahida27.06.2012

4

The River Isar in Munich

The project area= 8km.

Total area of the river in the city=

14Km

State Office for Water ManagementMunich

N. Mahida27.06.2012

5

Catchment area 9000 km²

Length 270 km

Medium Low Discharge 40 m³/s

Medium discharge 90 m³/s

Medium high discharge 420 m³/s

High discharge (100 a)       1.100 m³/s

Isar River Sections

1  Upper Isar (alpine Character)

2 Isar in Munich (urban character)

3  Middle Isar (alluvial forest)

4  Lower Isar

5  Danube

Présentateur
Commentaires de présentation
Typical flow of an alpine river- variation between the discharge

State Office for Water ManagementMunich

N. Mahida27.06.2012

6

Highlights of the Project

Improving dyke security without affecting tree stands Modelling of a river section in a 1:20 model scale Landscape architecture competition UV treatment of water from sewage treatment plants Special method (hydrosaat) for planting saplings Removal of barriers for fish (weir replacement) Follow-up monitoring of ecological revitalistion Stakeholder Involvement and consultation Information system for the public

Présentateur
Commentaires de présentation
Here I will explain how these measures were taken. Ecological monitoring- minimal monitoring report.

State Office for Water ManagementMunich

N. Mahida27.06.2012

7

Multiple uses of the Isar through the Isar- Plan

Ecological protection zones & monitoring

Recreation & tourist attraction Hydropower Cooling of power plant Improvement of micro-climate Stormwater drainage Canalisation Flood retention Social impacts

State Office for Water ManagementMunich

N. Mahida27.06.2012

8

Issues with diversity of land-use

Adaptation of land-use to land demand (for example for recreation, ecological value, public needs)

Historical and cultural value preservation

Urban use versus ecological protection

Management of different interest groups

State Office for Water ManagementMunich

N. Mahida27.06.2012

9

Unexpected Issues with the Isar-Plan Project

Conflicting objectives of various stakeholders Contractual deals Timing of public participation Liability issues in case of standing surf wave and potential accidents Land and water ownership Free and public goods are not valued Rule enforcement Awareness is lacking (eg. waste management) Cultural and commercial activities are becoming more popular which

potentially affect biodiversity

Présentateur
Commentaires de présentation
The anglers, the architects, the Ngos, the Canoeists, all parties want to use the Isar and their goals are conflicting. Among the recreation seekers- residents want it quiet- partygoers not. The River and bank management is carried out by city officials and the river belongs to the city in city limits. Out of city limits, the river belongs to the free state of Bavaria. This contractual deals runs for 100 years and is a reason for less influence of State over the maintenance of the project. Enforcement of rules does not work 100 %- BBQ areas need to be aptrolled, driftwood used for campfires, paddleboats not allowed everywhere. The public is pressing for more cultural and commercial activities at the river- which is problematic owing to the status of the flood plains as a protacted area. The greatest issue is the lack of awareness/recognition that the project is actually a free service for the public and should be cherished. However this ‚free‘ service is often misused and assumed to

State Office for Water ManagementMunich

N. Mahida27.06.2012

10

Thank you for your attention !

Website: http://www.wwa-m.bayern.de/index.htm

State Office for Water ManagementMunich

N. Mahida27.06.2012

11

Extra Slides- if needed

State Office for Water ManagementMunich

N. Mahida27.06.2012

12

Historical Floods in Munich

HQ 1940 = 1.440 m³/s

HQ 1999 = 854 m³/s

HQ 2005 = 1050 m³/s

Historical Events

(above) - Destruction of the Ludwigsbrücke in 1813

(right)- Floods of August 2005

Présentateur
Commentaires de présentation
Destruction of the Ludwigsbrücke in September 1813- The floods of 2005 at the Wittelsbacher bridge

State Office for Water ManagementMunich

N. Mahida27.06.2012

13

The Isar in Munich in 1905- an Artists Impression

State Office for Water ManagementMunich

N. Mahida27.06.2012

14

The Isar at the same location in 1930

State Office for Water ManagementMunich

N. Mahida27.06.2012

15

The Isar in November 2001

State Office for Water ManagementMunich

N. Mahida27.06.2012

16

A Balancing Act of the 3 Main Project Goals

Flood protection Near-natural ecological

restoration Recreation & leisure

The baseline reference

situation at the Flaucher

Présentateur
Commentaires de présentation
These goals had a different weightage,

State Office for Water ManagementMunich

N. Mahida27.06.2012

17

The Isar-Plan Project

The baseline situation (Flaucher)

Accessible banks

New island

Gravel banks

Species-rich flowering meadows

Stone-blocks for seating

Rock ramps replace sill beams

Dyke reinforcement

Start- Großhesselohe Bridge

End- Cornelius Bridge

Widened river bank

State Office for Water ManagementMunich

N. Mahida27.06.2012

18

Two spatial zones of the Isar-Plan: Urban and Semi-urbanThe Semi-Urban River Character

•Focus on biodiversity and rare species

•Flood protection

•Wide bed and gravel banks

•Optimising land-use

Présentateur
Commentaires de présentation
optimising land-use: focus on biodiversity and rare species

State Office for Water ManagementMunich

N. Mahida27.06.2012

19

Two spatial zones of the Isar-Plan: Urban and Semi-urban

The Urban River Character•Optimising land-use for recreation purposes

•Flood protection for densely urbanised areas

•Improving attractiveness for visitors

Présentateur
Commentaires de présentation
optimising land-use: focus on biodiversity and rare species

State Office for Water ManagementMunich

N. Mahida27.06.2012

20

Dyke Reinforcement

State Office for Water ManagementMunich

N. Mahida27.06.2012

21

Flood Protection Measures

1) Widening the river bed from 50m- 90m2) Increase in dyke height (freeboard)3) Silt deposition removed to the flood meadows4) Near natural design of the banks

State Office for Water ManagementMunich

N. Mahida27.06.2012

22

Model Simulation at the TU

State Office for Water ManagementMunich

N. Mahida27.06.2012

23

Stakeholder Involvement

Prior to 1990 Isar restoration planning was largely isolated;

Interesting cooperation between government and city/municipal planners and NGO‘s and public groups;

Mediation process to assist identification of the optimal solution for the last 1.5 km of the urban Isar

Présentateur
Commentaires de présentation
Free State of Bayern- the State water office and the deparment for construction at the City municipality cooperated on the project. There were large scale protests to the winner of the landscaping competition that threatened the continuation of the project. The City authorities were not convinced of the initial plan and nor were the Ngos . At the end, the state office for water management drew out plans from the 1st and 2nd winners- a combination of a largely natural plan and a very built-up plan. This was accepted finally and a mediation firm was invited to carry out the process of acceptance.

State Office for Water ManagementMunich

N. Mahida27.06.2012

24

AfterBefore

Sill beams on the river bed pose a barrier for fish

Présentateur
Commentaires de présentation
linienhaftes Sperrbauwerk keine biologische Durchgängigkeit eintönige Fließstruktur The sohl rampen – ground sills prevented the river bed from deepening further and were located 200meters apart. 17 of these were remodeled to create continuity for fish

State Office for Water ManagementMunich

N. Mahida27.06.2012

25

Before

After

Sloping concrete river banks

Flattened stony river banks

State Office for Water ManagementMunich

N. Mahida27.06.2012

26

Before: Monotonous River Landscape

State Office for Water ManagementMunich

N. Mahida27.06.2012

27

After : Diversified Bank Structures

State Office for Water ManagementMunich

N. Mahida27.06.2012

28

Before- A concrete

channelized water course

State Office for Water ManagementMunich

N. Mahida27.06.2012

29

After- more structural

variety and diversity

State Office for Water ManagementMunich

N. Mahida27.06.2012

30

Recreation and Leisure at the Isar River