The Inata Gold Mine · Inata 2010 –A very successful year! 4 •91,524 oz poured in initial 9...
Transcript of The Inata Gold Mine · Inata 2010 –A very successful year! 4 •91,524 oz poured in initial 9...
The Inata Gold Mine
1
Inata management team
2
General Manager Inata
Gold Mine
Colin Belshaw
Deputy GM and Projects
Manager
Bob Voisey
Mining Manager
Michel Labbe
Maintenance Manager
Frans Gonsalves
Environment and
Community Manager
Nick Shirley
Safety and Training Manager
Terry Wilhelm
Security Manager
Daniel Gagnon
General Services Manager
Sharon Kell
Finance Manager
Guy Riopel
Technical Services
Kell Monro
Geology Manager
Alex Hagan
Chronology of Inata Project
2009 – present Avocet Mining PLC Step-out drilling commenced
April 2009 announced takeover of Wega in all-share deal
June 2009 acquisition completedFirst gold pour in December 2009 and commercial completion by March 2010
2007-2009 Wega Mining ASA No drilling at Inata
Acquired Goldbelt Resources in 2007 for C$130 million in cashEntered US$65 million project finance facility agreement with
MBL
2004 – 2007 Goldbelt Resources Ltd 69,000m
TSX-V listedAcquired properties in January 2004 for cash and shares worth US$6.5 million
Outlined reserves and resources of 0.944 Moz and 1.7 Moz respectively
1998 – 2004 BHP - Resolute Ltd Joint Venture Metres drilled: 49,000m
Joint venture with BHP (1998-2001) Resolute sole operator until 2004 Resolute outlined 750,000 oz resource
3
Inata 2010 – A very successful year!
4
• 91,524 oz poured in initial 9 monthso First gold produced December ’09 – 152oz
o Production (poured) of 40,461oz Q3 ‘10
o Gold now sold at hedge and spot prices
• Ramp up to name plate thru’put (285tph)
achieved Sept 2010 (and showing
potential for greater capacity)o Plant recoveries currently >93%
o Commercial production planned for by Q3
2010. Actually achieved from 1st April 2010
• Set to produce over 120,000 oz in 2010
1 NI 43-101-compliant Reserves as of 31 August 20102 NI 43-101-compliant Resources as of 30 June 2010
AVM Ownership 90%
LocationBurkina
Faso
Reserves (oz) 1 1,081,500
Resources (oz) 2 1,310,700
Production (oz pa)2010 c. 120,000
LoM c. 165,000
Cash costs ($/oz) LoM 525-575
Plant feed grade (g/t) LoM 2.12
Estimated Mine Life (years) 7+
Inata – progress and YTD performance
• Extensive rectification work by
Avocet post June ‘09 acquisition of
Wega Mining – ore to mills 28th
November 2009
• De-bottlenecking completed
October 2010
• Recoveries as planned at 93%+
• YTD feed grade of 2.65gpt
• Mined tonnages reconciling well
with BFS resource model
5
2010 – Other achievements and milestones
• Successful Inauguration by the Prime Minister, His Excellency
Mr Tertius Zongo
• Increased Resources and Reserves
• Set up Geology and Exploration facilities on site – teams
working closely with each other
• Improved Chart of Accounts and management accounting
• Completed numerous infrastructure projects incl. Gendarmerie
6
Inata North Pit
7
Geological Settings and Prospectivity
• Deposit hosted in Birimian
greenstone belt of volcano-
sedimentary series
• Folded metasediments and
ovoid granites intrusives
• Gold mineralisation commonly
associated with quartz–sulphide
veining along sheared zones
and contacts of volcanic
intrusives
8
Avocet Mining
INATA
1.8 Moz Au
VTEM Map Of Inata Prospect
Ore Deposit – Mineralization Style
9
• Generally NE trending fold axial plane
structures
• Extensive weathering and lateritisation of
the mineralisation and surrounding host
rocks, resulting in oxide mineralisation up
to 100 m depth
• Mineralization associated and\or in close
proximity to the graphitic shales, quartz
veins and sulphides
• Simple structural domain at deposit scale
N
s
Reserve Potential
• Mineralization open both
along strike and at depth
• Grade improves with
depth
• Good correlation
between Resource
Model and Grade
Control Model
• Revision of Grade
Control Processes
OngoingINATA NORTH _SECTION 1588475N
0.3 – 0.7 g/t Au
0.7 – 2.0 g/t Au
> 2.0 g/t Au
Grade Control Processes
A section along 1588392N showing the GC model with
the GC RC drill holes
A plan view of 285mRL showing mining
outlines from the GC model
• Robust, wide and continuous ore body being delineated from the Grade Control modelling.
• Mining outlines wide and well defined
Reconciliation - GC and Resource Model
INATA NORTHGRADE CONTROL RESOURCE MODEL-NEW
RL Tonnes Grade Ounces Tonnes Grade Ounces
TOTAL INSITU ORE
285-282,5 63,049 3.35 6,786 63,074 2.88 5,841
282,5-280 63,693 3.17 6,502 63,514 2.85 5,830
280-277,5 63,693 3.06 6,269 62,124 2.96 5,917
277,5-275 63,322 3.01 6,121 61,967 2.95 5,885
275-272,5 59,117 3.01 5,722 56,472 3.03 5,510
272,5-270 57,902 2.87 5,348 56,429 3.03 5,502
GRAND TOTAL 370,776 3.08 36,748 363,580 2.95 34,485
ORE GRADE PROPORTIONS
MARGINAL ORE 11% 16% 2% 5% 19% 1%
LOW GRADE ORE 32% 43% 14% 29% 44% 13%
HIGH GRADE ORE 58% 147% 85% 66% 131% 86%
VARIANCE 2% 4% 7%
• Revision of
Grade Control
Processes
Ongoing
• Good
reconciliation
between GC
Model Mined and
Resource Model
• Positive
reconciliation
being observed
Reconciliation Resource, Mine Production vs Processing
• Good reconciliation
between Mined and
Resource Model
• Good reconciliation
between Mining and
Processing head
grade and Ounces
13
2011 – Inata Processing Plant
14
Inata - increasing production capacity
15
• Forecast gold production for Inata life of mine
increased to 165,000 ounces p.a. from
120,000 ounces p.a.:
• Capital required: US$25 milliono Mining equipment: US$15 million
o 1 x PC2000 excavator
o 5 x 777F dump trucks
o 1x 988H wheel loader
o 1 x D9R dozer
o 1 x L8 blast hole rig
o Plant upgrade: US$10 million
o 2nd elution circuit and electro-winning cells
o Upgrade CIL inter-tank screens and piping
o Upgrade lime supply system
o Expand gold room
o Extra raw water and process water pumps
o Dust collection systems – crusher and reclaim
o CIL tanks oxygen supply system
The 3rd Mine Fleet
16
A Third Mine Fleet of value US$15M is required for the following reasons, both of
which represent opportunities created by successful resource development and
plant expansion:
• Exploit the new Inata Resource Model completed August 2010
−235,000 oz additional Ore Reserve announced September
−Evaluation of economic pits completed, new designed pits
−Ore Reserve increased as a result, 25% increase to 1.08M oz
−LOM waste to ore strip ratio increased from 7:1 to 9:1 as a result of deeper pits
• Enable the expansion of existing Inata plant
−Increase from 285t/hr to 340t/hr
−Reduce % of annual production that is hedged from ~70% to 55%
−Increase spot price exposure at time of increased gold prices
Expanding the plant
•Planning for expansion of processing
capacity has been progressing since
July
•Processing plant reached nameplate
capacity of 285 tph in August as
planned and has run steadily since
•Expanding capacity by fully utilising
installed milling capacity and further
debottlenecking to reach target of 340
tph by July 2011
17
Increasing mining capacity
18
Mining equipment
• Existing mining fleet:
− Excavator: 1 x PC2000
2 x PC1250
− Production Loader: 1 x WA 800H
− ROM Loader: 1 x 988H
− Dump Trucks: 6x 777F
6 x HD785-7
− Track Dozer: 1 x D9R
1 x 375A
− Wheel Dozer: 1 x 834H
− Grader: 1 x 16M
1 x GD825A
− Water Truck: 2 x HD475-7
− Blast Hole Drill Rig: Atlas Copco L8
− RC Drill Rig: Atlas Copco L8
• Ordered 3rd mining fleet:
− Excavator: 1 x PC2000
− Dump Trucks: 5 x 777F
− ROM Loader: 1 x 988H
− Dozer: 1 x D9R
− Blast hole drill rig: Atlas Copco L8
19
Life of mine plan
• Current life of mine plan outlines the following:
o 7 year initial mine life, subject to ore body
extensions and/or additional greenfields
discoveries
oOverall strip ratio of 9.4 (rising from 6.5 in 2010
to 12.7 in 2011/2012, declining thereafter)
oExpanded plant capacity of 2.7 Mt p.a.
o LoM plant feed grade of 2.12 g/t
oBudgeted recoveries of 90-95%; currently
>93%
20
Mining schedule
• Optimisation of pit designs and LOM schedule
• Schedule focuses initially on higher grade
Inata North pit
• Mining fleet performing as budgeted
• Mining in 2.5 m flitches to reduce dilution
• Currently achieving 920k BCM per month
• Production to increase to 1.3M BCM per
month with arrival of 3rd fleet Q3 2011
• Large stockpile of ore maintained on ROMo Stockpile of 500,000 tonnes at +2.05 g/t (as
of 30 November ‘10)
• Mining from Inata North and Central Starter
Pits
21
Inata North
Sayouba
Inata Central
Inata South
Mining challenges and opportunities
• Operator trainingo Mining is new to Burkina Faso
o Lack of skilled operators
• Optimise drill and blast operations
• Minimising dilution and ore loss
• Resource model performing well
• Diesel consumption per tonne and
tyre wear lower than expected
22
Plant key components
• 7 x 1.8 MW (de-rated) Generators
• 1 x 110 kW Primary Crusher
• 1 x SAG Mill
• 2 x Ball Mills
• 1 x Cyclo-Pac (20 cyclones)
• 6 x 1980 m3 CIL Tanks
• 1 x Falcon Concentrator
o Installation progressing
23
Process flow chart
24
Gomde barrage
• Capacity of 120 Mm3
• Current monthly usage of 0.3 Mm3
o Evaporation in dry season accounts for 5.2 Mm3 per month
25
Inata Cost Structure and Cost Drivers
• Diesel - price set by government in FCFA (current equivalent – US$0.81/litre); sourced from Benin
• Reagents – principally cyanide, lime and grinding media; synergies in supply with S.E. Asian operations
• Labour – high initial requirement for expats, declining in subsequent yearso Presently employing 501 nationals (105 local area) and 49 expats
• . LoM cash costs of US$525-575/oz (incl. government royalties)
26
Diesel22%
Reagents12%
Maintenance Consumables
- Plant10%
Maintenance Consumables
- Mine18%
Contractors & Consultants
6%
Labour -Expatriate
11%
Labour -National
8%
Others13%
Adimistration 30%
Mine32%
Process 38%
Key Operating Cost Drivers
• Fuel usage and cost
• Cyanide usage and cost
• Labour
• Strip ratio
• Planned maintenance schedules
• Grade
• Royalties
• Scale of operations
27
Focus on incremental operational cost savings
• Change to Junior staff accommodation policy
• Change to bulk explosives
• Change to SAG mill lifter design
• Reengineering of high wear areas of plant
• Move to in house services for environmental assays, grade control drilling
etc
• Reduction of 3rd party rental equipment such as craneage, backhoes etc
• Negotiation of consignment stock agreements
28
An Excellent Safety Record
• Occupational Health, Safety & Environment Committees
• First meeting held in May with the Committees being comprised of representatives from all departments and management
• Committees meet once per month to review health and safety issues
• Emergency Response Team
• In May, 2009 SMB developed an Emergency Response Team. The team is comprised of representatives from every department. They train four hours per week in all aspects of rescue; first aid, fire extinguishment, spill response, confined space rescue and embankment rescue.
• Achievements• In December 2009 SMB worked 1 Million man hours without a Loss Time
Injury (LTI)
• In June, 2010 SMB worked 2 Million man hours consecutively without a LTI
• On September 30th SMB worked 3 Million man hours consecutively without a LTI
Environment Programmes
30
• Implementation of Environment Management Systems for SMB
• Development of:• Operational and system procedures
• Impact and Aspects Register for all mining activities
• National and International Environmental Legal Register
• Conducting regulatory reporting regarding environmental
management and control
• Establishment of on-site waste management program, and
local recycling projects in the community
• Establishment of formal monitoring and control programs for
water, air and soil discharges
• On going reforestation and restoration programmes
• On going environmental training for employees
• Launch of the „Foundation Avocet Pour Le
Burkina‟ “FAB”
• Investment in projects that have directly benefited
the local communities including:o Road systems
o Improvement of medical centres
o Village water supply
o Improvements in mobile communication
• Emphasis with regards to local recruitment by SMB
and contractors
• Developing local business opportunities in the
impacted region
• SMB holds regular Local and Regional Committee
Meetings to maintain close links with the mine and
the communities
Community Relations – Projects
31
In Conclusion
32
2010 Goals and Achievements
Skilled management team with diverse worldwide mining experiences
Safety culture
Completed construction
De-bottlenecking and commissioning
Mining on schedule
Implemented AccPac financial software
Motivated national team
Effective community relations
Gomde barrage water storage
Potential to outperform resource model and extend mine life via resource
development
Potential to expand plant capacity
PP
P
PP
PPP
P
33
P
P
2011 Goals
• Maintain safety record
• Successfully implement expansion plans and achieve production targets
• Continue incremental cost saving initiatives
• Successfully complete current drilling program with resultant resource
increase
• Redesign mine plan based on new resource model to increase reserves
whilst also providing greater operational flexibility and smoothed waste
mining profile
• Build on AVM’s capacity in West Africa by development of Regional Office in
Ouagadougou utilising synergies between SMB and the exploration entities
34
Inata – upside potential
• Only main zone modelled
• Significant mineralisation outside of modelo At depth
o Parallel zones (in pit)
o Along strike
35
And final thoughts
• Inata successfully operating
above nameplate capacity
• Skilled management team with
diverse worldwide mining
experiences
• Production and exploration upside
substantially greater than
expected – already being
exploited
36
www.avocet.co.uk
Cautionary note
DISCLAIMER
• The information contained in this confidential document ("Presentation") has been prepared by Avocet Mining PLC (the "Company").This Presentation has not been approved by an authorised person in accordance with Section 21 of the Financial Services and Markets Act 2000 and therefore it is being delivered for information purposes only to a very limited number of persons and companies who are persons who have professional experience in matters relating to investments and who fall within the category of person set out in Article 19 of the Financial Services and Markets Act 2000 (Financial Promotion) Order 2005 (the "Order") or are high net worth companieswithin the meaning set out in Article 49 of the Order or are otherwise permitted to receive it. Any other person who receives this Presentation should not rely or act upon it. By accepting this Presentation, the recipient represents and warrants that they are a person who falls within the above description of persons entitled to receive the Presentation.
• While the information contained herein has been prepared in good faith, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers give, have given or have authority to give, any representations or warranties (express or implied) as to, or in relation to, the accuracy, reliability or completeness of the information in this Presentation, or any revision thereof, or of any other written or oral information made or to be made available to any interested party or its advisers (all such information being referred to as "Information") and liability therefore is expressly disclaimed. Accordingly, neither the Company nor any of its shareholders, directors, officers, agents, employees or advisers take any responsibility for, or will accept any liability whether direct or indirect, express or implied, contractual, tortious, statutory or otherwise, in respect of, the accuracy or completeness of the Information or for any of the opinions contained herein or for any errors, omissions or misstatements or for any loss, howsoever arising, from the use of this Presentation.
• Neither the issue of this Presentation nor any part of its contents is to be taken as any form of commitment on the part of the Company to proceed with any transaction and the right is reserved to terminate any discussions or negotiations with any prospective investors. In no circumstances will the Company be responsible for any costs, losses or expenses incurred in connection with any appraisal or investigation of the Company. In furnishing this Presentation, the Company does not undertake or agree to any obligation to provide the recipient with access to any additional information or to update this Presentation or to correct any inaccuracies in, or omissions from, this Presentation which may become apparent.
37