The Implications of Political Transaction Costs for Benefit Cost Analysis Kerry Krutilla Associate...
-
Upload
jeffrey-fitzgerald -
Category
Documents
-
view
233 -
download
10
Transcript of The Implications of Political Transaction Costs for Benefit Cost Analysis Kerry Krutilla Associate...
The Implications of Political Transaction Costs for Benefit Cost Analysis
Kerry Krutilla
Associate Professor
School of Public and Environmental Affairs
Indiana University
Bloomington Indiana 47405
Presented at the Department of Public Administration and Policy
National Taipei University
March 23, 2010
Acknowledgment and Disclaimer
The model in this paper is an extension of one jointly developed with Chulho Jung and W. Kip Viscusi to assess rent-seeking behavior towards environmental policy proposals. I am indebted to them for the insight and original collaboration. All errors and omissions in this extension are the author’s exclusive responsibility.
Overview• Conventional standard for economic efficiency
NB= B-C > 0, or B/C > 1
(absolute comparison)
• Issue: benefits and costs fall on stakeholders• Informed stakeholders have an economic incentive
to seek or avoid these benefits and costs, if they have “standing” in the political process
• Political behavior of stakeholders itself imposes economic costs
Relevant Question For Ex Post Evaluation
Could the economic cost of the political activity over a project proposal exceed the net value of a project whose conventionally-measured net-benefits are positive (B-C > 0, or B/C >1)?
Let C1* = the economic costs incurred by the beneficiaries to politically support the project
Let C2* = the economic costs incurred by the “losers” to politically oppose the project
Is NB = B-C > (C1*+C2*)?
Example for Ex Post Evaluation Context
B-C > (C1*+C2*) => B > C + (C1*+C2*), OR
B/C > 1+ [(C1*+C2*)/C]
Suppose (C1*+C2*)/C =.5
In this case, society would be worse off for approving any project with a B/C ratio less than 1.5
• Will a project’s conventionally-measured expected net-benefits cover its projected political costs?
• Since political decision-making is uncertain, a potentially beneficial project might or might not be approved.
• If a project is not approved, the political cost of the project decision-making ends up as unrecovered economic cost.
Relevant Question For Ex Ante Evaluation
Modified Decision Criterion for Ex Ante Evaluation
Assuming “risk neutrality”:
π(B-C) > C1*+ C2*
π=probability of a project proposal passing in a political contest, 0 < π < 1
Or: B/C > 1 + (1/π) [(C1*+C2*)/C]
Example for Ex Ante Evaluation Context
Suppose Π=.5 and (C1*+C2*)/C =.5
For B/C > 1 + (1/π) [(C1*+C2*)]/C]
B/C must be greater than 2 for the expected value
of the project proposal to be positive
Research Question and Objective
Question: Are C1* and C2* likely to be large enough to affect conclusions about the project’s overall economic effects?
Objective: Develop a model explaining C1* and C2*, and compute an adjusted project decision criterion reflecting C1* and C2*
1. Develop a model of strategic interaction giving:
C1= f1[Πν(C1,C2)B,X] => C1=f3(C2,B,X)
C2=f2[Πν(C1,C2)C,X] => C2=f4(C1,C,X)
2. Solve for C1*=f5(B/C,X); C2*=f6(B/C,X)
3. Substitute solutions for C1* and C2* into:
B/C > 1+ [(C1*+C2*)/C] => B/C > 1 + f7(B/C,X) (ex post) B/C > 1+ (1/Π)[(C1*+C2*)/C] => B/C > 1+ f8(B/C,X) (ex ante)
4. Solve out for modified B/C ratios from right-hand side of (3)
Research Strategy
Qualification
• Above assumes a political contest, rather than a negotiated “political settlement”
• Assumption maintained in this paper
Public Choice Literature
• Rent-seeking literature on the economic cost of public decision-making
– Tullock, Gordon. (1993). Rent seeking. Brookfield: Edgar Elgar.
• Development economics literature
– Krueger, Anne O. (1990). Government failures in development. The Journal of Economics Perspectives, 4(3), 9-23.
– Varian, Hal R. (1989). Measuring the deadweight costs of dup and rent seeking activities. Economics and Politics, 1, 81-95.
– Stevens, Paul. (2003). Resource impact-Curse or blessing? A literature survey. Journal of Energy Literature, 9(1), 1-42.
Project Evaluation Literature• Political Feasibility Assessment
Kelvin, Alex. (2000). How stakeholders with various preferences converge on acceptable investment programs. Evaluation and Program Planning, 23, 105-113.
• Cost Minimizing Project Design
Fleming, E. (1998). Rent-seeking in rural development projects: Its potential causes and measures to reduce its costs. Journal of International Development 10: 277-299.
Thompson, Dale B. (1999). Beyond benefit-cost analysis: Institutional transaction costs and regulation of water quality. Natural resources Journal, 39, 517-541.
Influential Paper for Modeling Strategy
• Becker, Gary S. (1983). A theory of competition among pressure groups for political influence. Quarterly Journal of Economics, 98, 371-400.
Background for Model Set-Up
Financial transfers attenuate the incidence of project benefits/costs, altering the project’s net impact on various stakeholders
In particular, project financing affects the incidence of benefits and costs
Assumption 1: B-T > 0 Assumption 2: T+TP-C=0, or T+TP=C, or T-C= -TP Assumption 3: 0 < T < C, or -C < T-C = -TP < 0
Stakeholder Impacts
Beneficiary Input Suppliers
Tax Payers
Net
Benefit B BFinancial Transfer 1 (User Fee )
-T T 0
Financial Transfer 2(Tax Payer Finance)
TP -TP 0
Cost -C -CNet B -T > 0 T+TP-C=0 -TP B-C
Model
Model Solution
Model Solution – Cont’d
Aggregate Lobbying Costs
Aggregate Lobbing Costs as a Fraction of Total Project Costs
Figure 1Lobbying Cost as a Fraction of Project Cost
for Different B/C Ratios and Compensation Levels
1-d=0
1-d=.25
1-d=.5
1-d=.75
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 1 2 3 4 5 6 7 8 9
B/C Ratio
Rat
io o
f L
ob
byi
ng
Co
st t
o P
roje
ct C
ost
Figure 2Lobbying Cost as a Fraction of Project Cost for Varying Political Power and B/C Ratios
B/C=1
B/C=2
B/C=3
B/C=4
B/C=5
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 5 10 15 20 25 30
Relative Political Power
Rat
io o
f L
ob
byi
ng
Co
st t
o P
roje
ct C
ost
Implications for Project Evaluation
Ex Post Decision Criterion Continued
Figure 3Break-Even B/C Ratios for Different
Compensation Levels and Relative Political Power
a=.25
a=.5
a=.75
a=1
a=2
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 0.2 0.4 0.6 0.8 1 1.2
Fraction of Project Cost Compensated throgh Transfer Payments(1-d=T/C)
Bre
ak-E
ven
Rat
ios
Figure 4Break-Even B/C Ratios as a Function of Relative
Political Power (No-Compensation Case)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 2 4 6 8 10 12
Relative Political Power
Bre
ak-E
ven
B/C
Rat
ios
Modeling Qualifications
Modeling attributes biasing the modified B/C decision criteria upwards
• Complete information/zero organizing costs
The two most approximate contexts: – large federal regulatory programs in health, safety,
environment– local issues with highly impacted and informed
stakeholders
• Some influence activities financial transfers• Consensual policy design possible • Assumption of risk neutrality
Modeling attributes biasing the modified B/C decision criteria downwards
• Loss aversion/feelings of entitlement increase resource costs of political activity
• Costs of political activity also falls on government “stakeholders”
• Project financing costs. Suppose “excess financing burden” is: C3/C
then B/C > 1+ [C1*+C2*]/C + C3/C (ex post)
Conceptual Issue
• If Stakeholders are uncompensated, always some political transaction costs
• Default CBA practice is to ignore them
• Standard CBA metric, Kaldor-Hicks criterion is justified by “the potential compensation test”
• Potential compensation test fails when modified B/C thresholds not met.
Figure 5Socially Optimal Level of Public Investment using Modified B/C
$ of public investment
SC
Y
Q2
MC
Q1
XMC
MB
Q31
MB
TC
Conclusions
Political costs of project proposals can be a significant fraction of a project’s total costs
These costs should be estimated and incorporated into ex ante and ex post project appraisal standards
“Rule of Thumb” for ex ante evaluation of controversial projects featuring mobilized and informed stakeholders:
=> only consider projects with B/C ratios of 2 or greater, or
=> include transfer schemes in the project design to compensate negatively-impacted stakeholders
More research needed to clarify the magnitude of political decision-making costs in different contexts
.
Next Research Steps
• More complete specification of the Ex Ante Evaluation Context
• Two Stage Game to examine incentives for political negotiation, and their implications for modified B/C ratios