The Festival Walk - City University of Hong...
Transcript of The Festival Walk - City University of Hong...
![Page 1: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/1.jpg)
Raymond Wong 1
Construction of a Semi-Buried Building –A Super-sized Shopping Mall :
The Festival Walk
Presented by
Raymond Wong Wai Man,Division of Building Science & Technology,
City University of Hong Kong
![Page 2: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/2.jpg)
Raymond Wong 2
General InformationSite area – 21000 sq m (overall measure 290m x 80m)geological features- Tat Chee Avenue (+35m) on one longitudinal
sides and the Kowloon Canton Railway (+20m) on the other, a level diff. of about 15m exist.
- rockhead range between +25m to -35m. - Mass Transit Railway tunnels cutting across
site at +8m - deepest basement down to -3m (36m below
Tat Chee Av.)
![Page 3: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/3.jpg)
Raymond Wong 3
Block Plan
Site
25m roadway
Railway track
N
(Tat Chee Avenue)
![Page 4: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/4.jpg)
Raymond Wong 4
Building Section along Tat Chee Road
![Page 5: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/5.jpg)
Raymond Wong 5
Diaphragm Wall
![Page 6: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/6.jpg)
Raymond Wong 6
Typical Section cutting through MTR tunnels
![Page 7: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/7.jpg)
Raymond Wong 7
Site Formation andDiaphragm Wall Construction
Sub-divided into 7 stages from level +35m down to +20m.
Diaphragm wall and bored pile foundation construction work at the same time.
Two rows of temporary ground anchor were installed at Diap. Wall along Tat Chee Avenue Av as lateral support to cut during site formation excavation.
![Page 8: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/8.jpg)
Raymond Wong 8
Diaphragm Wall
Boring MachineTemporary Ramp
Preliminary Site Formation
![Page 9: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/9.jpg)
Raymond Wong 9
Tat Chee Av
Row of anchor as lateral retrain to diaphragm wall
![Page 10: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/10.jpg)
Raymond Wong 10
KCR Rail track Tat Chee Av. Hand-dug caisson in progress (bored pile)
Site at the up-hill portion had been formed down to +20m (level to the KCR Rail track level)
![Page 11: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/11.jpg)
Raymond Wong 11
Site formation close to its completion
![Page 12: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/12.jpg)
Raymond Wong 12
Site Formation andDiaphragm (cont.)
2m thick Diap. Wall constructed using traditional grab/chisel and reverse circulation trench cutting (hydrofraise) methods, both using bentonite slurry as a stabilizing agent.Removal of soil maintained at 2 exit-points arrangement as far as possibleLater stage of site formation merged with the main contract.
![Page 13: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/13.jpg)
Raymond Wong 13
Using a trench cutting machine (hydrofraise) to form the diaphragm wall panel
![Page 14: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/14.jpg)
Raymond Wong 14
Detail of the cutting drums of the hydrofraise(trench cutting machine)
![Page 15: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/15.jpg)
Raymond Wong 15
Forming the diaphragm wall panel using grabs (clamshell)
![Page 16: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/16.jpg)
Raymond Wong 16
Bored Pile Foundation
Total about 165 piles ranging from 1.8, 2.65 and 3.25m dia.3.25m dia piles were done by hand-dug method.Excavation done by steel grab/chisel and reverse circulation drilling method, both using steel casing as excavation support.With steel stanchion anchored into the pile as support to basement structure constructed in top-down arrangement.
![Page 17: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/17.jpg)
Raymond Wong 17
MTR Kwun Tong Line Tunnels
Bored Piles Layout
![Page 18: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/18.jpg)
Raymond Wong 18
Forming the bored pile using grab
Protective steel casing
![Page 19: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/19.jpg)
Raymond Wong 19
Forming the bored pile using Reversed Circulation Drill
![Page 20: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/20.jpg)
Raymond Wong 20
Stages of construction
![Page 21: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/21.jpg)
Raymond Wong 21
Stages of construction – from site formation to completion of superstructure
Diaphragm wall MTR TunnelsExcavation start at this point
Ground anchor to serve as lateral support during excavation
2.5m dia bored pile
Site formation stages
![Page 22: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/22.jpg)
Raymond Wong 22
Commencement of Top-down Basement ConstructionBasement excavation
below the ground slab
Upper floor slab and basement excavation and construction work at the same time
Excavation to form the vehicular ramp
![Page 23: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/23.jpg)
Raymond Wong 23
Work Flow direction
Completed vehicular ramp in advance to facilitate the removal of excavated spoil
Basement excavation and construction
Superstructure
![Page 24: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/24.jpg)
Raymond Wong 24
Atrium space
![Page 25: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/25.jpg)
Raymond Wong 25
Topping out of the entire structure
![Page 26: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/26.jpg)
Raymond Wong 26
Construction of Basement4-level full basement and 3-level semi-basement.Full basement constructed in top-down method.Construction generally arranged in a 6-phased manner, each with appropriate sub-sectioning depending to local layout. Spoil removal:1st stage, maintain a exit point to road level on the down-slope side of site; 2nd stage, use the newly constructed vehicle ramp (permanent structure) at the up-slope side.
![Page 27: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/27.jpg)
Raymond Wong 27
Steel stanchions to be inserted into bores piles as temporary support during the top-down construction of the basement structure (encased to become column later)
Steel stanchions
![Page 28: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/28.jpg)
Raymond Wong 28
Anchor plate at head of stanchion
Floor slab formwork for basement at +22m
Connecting the stanchion to the basement slab
![Page 29: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/29.jpg)
Raymond Wong 29
Exit point
Provision of temporary ramp to exit point at down-slopel location
![Page 30: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/30.jpg)
Raymond Wong 30
Basement underneath to be formed by top-down method
Vehicular ramp leading to basement carpark used as temporary access for removal of spoil during site formation and basement excavation
![Page 31: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/31.jpg)
Raymond Wong 31
Forming an entrance into he basement for carrying
out of excavation
![Page 32: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/32.jpg)
Raymond Wong 32
Progressing stage of superstructure & basement construction (1)
![Page 33: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/33.jpg)
Raymond Wong 33
Progressing stage of superstructure & basement construction (2)
![Page 34: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/34.jpg)
Raymond Wong 34
Progressing stage of superstructure & basement construction (3)
![Page 35: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/35.jpg)
Raymond Wong 35Progressing stage of superstructure & basement construction (4)
![Page 36: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/36.jpg)
Raymond Wong 36
Progressing stage of superstructure & basement construction (5)
![Page 37: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/37.jpg)
Raymond Wong 37
Principle of top-down method: Construct the ground slab first (in this case slab between full and semi-basement at +20m). Provide an entrance to the basement to facilitate downward excavation (between portion 2 & 3 at the first start). Excavate downward until the proceeding slab being cast. Repeat the excavation and basement slab casting horizontally and vertically until the entire basement finished. Cast/encase other vertical elements (staircase, ramps or columns) at time appropriate.
![Page 38: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/38.jpg)
Raymond Wong 38
Forming the first basement slab at +20m
![Page 39: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/39.jpg)
Raymond Wong 39
Steel columns erected in the bored pile helps to support the ground slab at the beginning of the top-down basement construction
![Page 40: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/40.jpg)
Raymond Wong 40
Formwork for the lower basement slab being erected
Excavation in progress
Upper basement slab already cast
Excavation and casting the basement slab in a top-down manner
![Page 41: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/41.jpg)
Raymond Wong 41
Steel columns support the ground slab at the beginning stage
![Page 42: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/42.jpg)
Raymond Wong 42
Excavation along Tat CheeAvenue where rockheadlocated close to ground
![Page 43: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/43.jpg)
Raymond Wong 43
Rock cutting carried out under the steel shore
![Page 44: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/44.jpg)
Raymond Wong 44
The Main Structure
Traditional timber panel formwork was used.Majority of structure in span ranging from 8.5m to 16m, some post-tensioned beams up to 35m and 48m.Strength of concrete in 40 (in-situ) and 45 (post-tensioned).Phasing and sectioning arrangement somewhat similar to basement construction, but more complicated due to the layout of the shopping mall.
![Page 45: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/45.jpg)
Raymond Wong 45
Portion 1
Portion 2
Portion 3
Portion 4
Portion 5
Portion 6
Construction of the superstructure in complicated phases
![Page 46: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/46.jpg)
Raymond Wong 46
Superstructure constructed using traditional manual timber formwork
![Page 47: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/47.jpg)
Raymond Wong 47
Construction of the superstructure at its final stage (observe the complicated sectioning arrangement of formwork)
![Page 48: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/48.jpg)
Raymond Wong 48
series
![Page 49: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/49.jpg)
Raymond Wong 49
Steel fixing for the superstructure structure
![Page 50: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/50.jpg)
Raymond Wong 50
Elevation along Tat Chee Avenue
Office block48m span post-tensioned girder beams
Skating rink below
![Page 51: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/51.jpg)
Raymond Wong 51
Main Structure : Other features
- existence of large volume atrium spaces (120m x 35m high, 80m x 40)
- ice skating ring measures 46m (span) x 70m x 30m high)
- fully glazed sky light (180m x 22m for mall, 30m x 35m for office)
- Glass wall total 3500 sq m.
![Page 52: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/52.jpg)
Raymond Wong 52
Isolated “Island” sub-divided by the “River” & “canyon”
The “River”
The “canyon”
Complicated spacing arrangement within the superstructure
![Page 53: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/53.jpg)
Raymond Wong 53
![Page 54: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/54.jpg)
Raymond Wong 54
The “River”taking shape
Escalator spanning below two levels of the shopping mall
![Page 55: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/55.jpg)
Raymond Wong 55
Steel frame that formed the skeleton of the skylight of “River”and “Canyon”
Intermediate frames
Main frame
![Page 56: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/56.jpg)
Raymond Wong 56
Installing the glazing panels for the skylignt
![Page 57: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/57.jpg)
Raymond Wong 57
Office block
Roof plan showing layout of “River” & “Canyon”
![Page 58: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/58.jpg)
Raymond Wong 58
Isometric view of the Festival Walk superstructure
![Page 59: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/59.jpg)
Raymond Wong 59Glass wall that form the “Canyon”
![Page 60: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/60.jpg)
Raymond Wong 60
Forming the glass wall at end-side of Canyon
![Page 61: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/61.jpg)
Raymond Wong 61
Cladding the glass wall of the “Canyon”
![Page 62: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/62.jpg)
Raymond Wong 62
GI grille (A/C compressors behind
Powder coated metal panels
Marble slab
![Page 63: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/63.jpg)
Raymond Wong 63
Difficulties encountered in the project
Very large scale of works – site formation, volume of excavation, large layout, huge amount of formwork and concrete, interior space that fitting out works required etc.
Very deep excavation and the required support.Works in close proximity with MTR facilities and tunnels.
Difficult phasing and sectioning arrangement.Relatively tight schedule.Very high headroom and difficult accessible interior spaces sub-divided by the atrium.
![Page 64: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/64.jpg)
Raymond Wong 64
Complicated teething arrangement between interface of phased sections (1)
Steel stanchion to support basement slab
1.2m thick slab (MTR tunnel tubes below)
![Page 65: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/65.jpg)
Raymond Wong 65
Complicated teething arrangement between interface of phased sections (2)
![Page 66: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/66.jpg)
Raymond Wong 66
Bored-piles as protection to pedestrian shaft
Working close to the MTR pedestrian facilities – in-situ bored piles were constructed to protect during excavation
![Page 67: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/67.jpg)
Raymond Wong 67
Protecting the MTR pedestrian facilities
Steel strut supporting pedestrian shaft to partially completed basement structure
![Page 68: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/68.jpg)
Raymond Wong 68
MTR pedestrian and ventilation shaft
Structural steel strut frame to stabilize the shaft
Squeezing difficultly into the ground to form the basement structure when working close to the MTR facilities
![Page 69: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/69.jpg)
Raymond Wong 69
Cut into rockhead to extend diap. wall further downward
Diap. wall being concreted
Underpinning to extend diaphragm wall panels further down into the rockhead
![Page 70: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/70.jpg)
Raymond Wong 70
Vast volume within the atrium add difficulty in the carrying out of superstructure and interior works
![Page 71: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/71.jpg)
Raymond Wong 71
Finishing the atrium formed within the “River”
![Page 72: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/72.jpg)
Raymond Wong 72
The “River” and the skylight
![Page 73: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/73.jpg)
Raymond Wong 73
The 48m-span interior space at the skating rink and food-stall area
![Page 74: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/74.jpg)
Raymond Wong 74
Finishing the skating rink
![Page 75: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/75.jpg)
Raymond Wong 75
Finishing the 20m-high, 48m-span Skating Ring
![Page 76: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/76.jpg)
Raymond Wong 76
Construction of a series of linking bridge in structural steel within the atrium space of the Skating Rink
![Page 77: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/77.jpg)
Raymond Wong 77
The vast interior space within the long-span atrium area (skating rink)
![Page 78: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,](https://reader034.fdocuments.in/reader034/viewer/2022042806/5f68c05469d71c333d7c5680/html5/thumbnails/78.jpg)
Raymond Wong 78
End of presentation